You are on page 1of 11

Comprehensive Disaster Management Programme

CDMP-II

Union :
Upazila :
District :

Project ID :

MEASUREMENT BOOK
Name of the project:

Date of First Entry:


Notes
Classes of work.
5. The measurement books, must be looked upon as important- records.
6. Whenever a PIO/National Cossultant-Site Engineer is required to submit his measur
book with his accounts. The submitted MB must be signed by the countered signature.

7. It will be found convenient so far as possible to keep the measurement relating to one
together and to effect this the number of pages likely to be wanted for a work or sub
should be estimated and set apart for the purpose or recording the measure
consecutively.

8. Before detailing the measurements relating to work the following information s


invariably be given at the top of the first page of such measurements:-
(1) Name of work
(2) Situation of work
(3) Agency by which work is executed
(4) Date of written order to commence work or supplies
(5) Date of actual completion of work or supplies covered by the contract
(6) Date of Measurement
Name of work

Situation of work

Agency by which work is executed

Date of written aggrement to commence work

Date of Actual completion of work

Date of Measurement

(These heading should be repeated at the commencement of the measurement relating to each
work.)

Serial Description No Length Breadth Depth/Height Contents


INDEX-Contd. Page
Measurement Books
Serial Description No Length Breadth Depth/Height Contents

Earth works
Earthwork in excavationin
1
@
Extra Lift:
2
@
Extra Lead:
3
@
Compaction works
4
@
Levelling, Dressing and
5 Cambering
@

Turfing works:
6
@

7 Water removing 1329.00 @ 14.76 19616.04


Earth work for pond and
canal
1st Step(upper) Avarage 1 49.25 42.25 2.50 5202.03

2nd Step(Lower) Avarage 1 40.175 33.175 1.55 2065.85

Total Volume in CUM. 7267.88


8
Pre volume in CUM - 3137.00

Net Volume in CUM 4130.88

Acceptable Volume 3988.00

Total Amount in Tk. 3988.00 @ 86.88 346477.44

9 Extra lift for pond and canal 2 3988.00 @ 13.90 110866.40

10 Extra lead for pond and canal 2 3988.00 @ 17.36 138463.36

Extra item: Hard, Clay and sandy


11 1 1990 @ 6.95 13830.50
soil.

Total Amount in Tk. 629253.74

12 Supervision fees (1%) 1% @ 629253.74 6292.54

13 Sarder(1%) 1% @ 629253.74 6292.54


Total Scheme cost in Tk. 641839.00