Professional Documents
Culture Documents
Sugano Et Al. Innovative Manufacturing Activities PDF
Sugano Et Al. Innovative Manufacturing Activities PDF
Group Plants
activities
To switch over from a conventional produc-
tion system to the TPS, efforts were made to deliveries)
eliminate waste activities, shorten processes and Then, the activities were promoted under the
not create delays as well as to create a continuous scenario of switching over to the kanban opera-
workflow (repetition of work) without depending tion referred to by TPS.
on a system or spending money. Specifically, the As examples of improving the production line,
following initiatives were taken for the line: workers stand up to work instead of sitting down
1) Work standing up, tightening up of work and processes have been changed to a worker
intervals,note 2) and sharing of multiple pro- handling only a single process to multiple process-
cesses (reduction of space) es. Moreover, improving the equipment and jigs
2) Changing offline to inline (shortening of pro- has enabled a reduction in persons on the produc-
cesses and reduction of goods in process) tion line. (Figure 1)
3) Using mizusumashi (fixed-course pick-up)note 3) Further improvements include initiation of
(creation of Takt time) outside arrangement and one-touch operation to
4) Reduction of arrangement time (reduction of reduce the time needed to change arrangements
goods in process) of the mounting equipment, presses, molding
In addition, the following initiatives were devices and others. As a result, the high target of
taken at each plant and company-wide: reducing the time by more than half has been
1) Integration of plants, handling of outside or- achieved. Initiations have also been undertaken
ders, reduction of warehouses, and storingnote 4) to increase the number of arrangements to
2) Arrangement of distribution (procurement promote the creation of smaller lotsnote 5) and
and finished products) network (route One-Piece-At-a-Time production.note 6)
note 2) Reduction of the interval between processes. note 5) Reduction of the number of components of
note 3) Workers who supply the parts between work lots.
processes. note 6) Passing of each finished product to the next
note 4) Location for placing items assorted by type. process.
As shown in Figure 2, the results of promot- wastefulness. In addition, reforms have been con-
ing plant integration, handling of outside orders, tinued in FCL overall by starting quality
reduction of warehouses, and storing as improve- innovation activities, design innovation activities,
ments for the production system have reduced the and new product development promotion sessions.
percentage of outside orders by 40%. Tightening
up of work intervals to reduce the space has also 3. FJIT innovative manufacturing
had a great effect in creating room within the activities
plants (53% reduction), reducing the outside FJIT is a manufacturing company that was
warehouses that originally numbered 10, and in established in April 2002 through the integration
terms of costs. of the manufacturing departments of Fujitsu’s
The effect of these improvement activities has Numazu Plant (large-scale server manufacturer),
also been beneficial in improving the morale of Nagano Plant (storage system manufacturer),
the workers. The goals and progress of individu- Kumagaya Plant (printed circuit board [PCB] unit
als have been posted and training activities such manufacturer), and PFU Limited (small-scale
as walking to experience the speed have been server and peripheral device manufacturer). FJIT
undertaken to encourage all of the employees in a handles a wide variety of products from core
plant to be more committed to manufacturing. devices such as large-scale and small-scale
As a start to creating a continuous flow at a servers to peripheral devices such as scanners and
production site, One-Piece-At-a-Time production printers. FJIT handles continual manufacturing
has been thoroughly emphasized and a mecha- of items ranging from PCB units to devices.
nism prepared so that workers can differentiate Because FJIT manufactures various types of
between what is acceptable and what is not devices that require much time and processes to
(enabling workers to check visually). Innovative complete, FJIT has taken on the problems of
manufacturing activities have then been initiat- reducing the number of inventories and work in
ed with the aim of thoroughly eliminating process.
Warehouse 1 2 9 10
Cooperating plants
Subsidiary A
Figure 2
Arrangement of warehouse at factory at FCL.
This section describes the promotion of the eliminated in the fourth quarter of 2004. As of
innovation manufacturing activities for solving September 2006, there is now only one outside
these problems and the actual innovations taken. warehouse.
manufactured while the orders had not been realizes the pull system in the entire plant. As
guaranteed. Currently, therefore, initiatives have shown in the top half of Figure 3, conventionally
been taken to reduce the manufacturing lead time there is a load of work in process between each
from assembly to testing, realize BTO consistent process and intermediate warehouse. However,
manufacturing from the beginning without activities are currently being undertaken to abol-
carrying half-finished products (basics), and ish intermediate warehouses and work in process
realize a system where the materials can be by creating production lines, which matches the
supplied to the production line in a timely format aimed at in the bottom half of Figure 3 to
manner. meet the initial plan.
Conversion to the pull system is scheduled
for future implementation. However, from June 4. Nasu Plant innovative
2005, progress has been made in converting to this manufacturing activities
system for some of the device types and activities The Nasu Plant is involved in the manufac-
are currently being undertaken to increase the ture of wireless terrestrial station equipment,
number of device types. network controllers, signal processors, and so on.
3) Manufacturing of PCB units For the Nasu Plant, the problem is flexible
Efforts are being made to realize mixed handling of the required changes.
One-Piece-At-a-Time productionnote 8) in the man- This section outlines the progress of the
ufacturing of PCB units. For ROM write at innovative manufacturing activities for solving
preprocessing, the components are being set on this problem and describes their contents.
the production line synchronized with the produc-
tion sequence units. For surface mount technology 4.1 Outline of plant improvement and
(SMT) manufacturing, small-lot flownote 9) is being innovative manufacturing activities
implemented using single arrangement.note 10) For Figure 4 shows the schedule of the plant
the insert mount technology (IMT) process, the improvement and innovative manufacturing
process course and work time for each process are activities for the Nasu Plant.
being reorganized. In particular, activities are Even before now, separate activities have
being undertaken to construct a rectified produc- been continuously undertaken for improving the
tion line and achieve mixed One-Piece-At-a-Time Nasu Plant. From construction innovations after
production by reducing the time and number of the collapse of the telecommunications bubble,
patterns when changing the arrangement of the implementation of a cell production system and
solder flow equipment that is a restraining factor steady improvement activities such as the
in terms of equipment. promotion of multi-skill development have been
From the rectification and One-Piece-At-a-Time promoted to strengthen the production capability
production within a process, we have currently to enable the flexible handling of the required
entered the phase of constructing a system that changes. Moreover, in December 2003, innova-
rectifies the lines connecting all processes and tive manufacturing activities (PI2004 activities)
note 8) To circulate various products of different were started with the aim of doubling productivity
processes on a single production line to within two years.
achieve One-Piece-At-a-Time production.
note 9) To flow the parts in lots as small as possible
so as to be able to meet the needs of the 4.2 Details of innovative manufacturing
customers. activities (PI2004 activities)
note 10) To complete arrangement within 10 minutes
This section describes the PI2004 activities
at the time when much time is needed to
change the arrangement. in regards to the innovative manufacturing
PTU manufacture
Acceptance inspection
Small-scale
Assembly Testing
Parts vendor
server BTO
Intermediate warehouse
Large-scale Large-scale
server server Large-scale
Parts warehouse
assembly block testing server BTO
Packaging
Small-scale RAID basic part Shipping
production line
Small-scale
Assembly Testing
RAID BTO
Process
vendor Large-scale Large-scale
RAID Large-scale
RAID
testing RAID BTO
assembly
Work
Ideal flow (device manufacturing)
(Inspection capability
warehouse manufacture
Acceptance inspection
PTU
Parts shelf
Packaging
note) Large-scale server production line (BTO production)
Parts shelf Shipping
Shared parts
note) In-plant outside order RAID: Redundant Array of Inexpensive Disk (storage system)
PTU: Printed Circuit Board Unit BTO:Build To Order (received order production system)
Figure 3
Conventional and ideal production lines at FJIT.
April 2003 to March 2004 April 2004 to March 2005 April 2005 to March 2006
★Phase III (to end of fiscal 2005) Education and training, creation of
• Education and training system for training personnel
• TPS furtherance
• Expansion of applicable Upgrading Just-In-Time system
processes
Packaging and shipping, test line,
NPI activities
BTO, parts procurement flow
• Expansion of applicable device
Application of new device types
types
Figure 4
Innovation activity schedule at Nasu Plant.
activities for the production line of the Nasu Plant. amounts because the production lead time of 14
days was longer than the customer’s supply lead
4.2.1 Improvements of production line time of 13 days to be improved as shown in
The production line of the Nasu Plant Figure 6. The supply lead time to the customer
consists of various processes. These processes could also be reduced significantly by three days.
include assembling PCB units referred to as plug- Excellent results in regards to space, number of
in units (PIUs) into SMT units, testing the units retention days, and cost reductions were also
and then installing them into shelves, installing obtained as listed in Table 1. Moreover, the tar-
the shelves on shelf racks, testing the devices, get of doubling the quality, cost, and delivery
packaging, and finally shipping. (QCD) within two years was achieved within one
Under the guidance of the TPS consultant, year.
the production flow has been rectified and a In addition, to accelerate the understanding
Takt-time concept where the products can be con- of TPS and for education and training, improve-
structed even as fast as they can be sold ment review meetings are being held every other
introduced. For the Nasu Plant members also, week separate from the guidance meetings held
the activities have been expanded with the fol- by the consultant. At the improvement review
lowing concepts emphasized: meetings, confirmation and investigations are
1) Work honestly adhering to the TPS concept. made in regards to such items as the aim and
2) Think of ways to improve without giving any effectiveness of the execution method of the
reason why it cannot be done. improvements. The leader of the production line
Before the improvements, each process had also starts under his or her own initiative a
a buffer where components could be added to any mini-guidance meeting to promote the awareness
production line utilizing this buffer. Moreover, a of problems among all of the operators and the
flexible production system had been constructed understanding of TPS.
by arranging intermediate warehouses to prevent
any loss of balance. However, there was a lot of 4.3 Development of future innovations
branching and merging and congestion between Currently, upgrading the improvement level
the processes [Figure 5 (a)]. Introduction of the within the Nasu Plant involves reviewing the
innovative manufacturing activities enabled the appropriate work in process within the plant to
promotion of rectification by device type and the reveal and remedy any problems as well as initi-
construction of a mixed flow production line. ating automation such as stopping at specific
After flow rectification, the production flow was points on individual production lines and utiliza-
changed to the pull system for all production lines tion of andon indicators.note 11) In addition, the
and processes for SMTs, PIUs, device assembly, existing production lines by device types are be-
device testing, and packaging [Figure 5 (b)]. ing reformed into a mixed-device type production
line and special-purpose test equipment that has
4.2.2 Result of production line improvements been a source of problems is being changed to
As described above, a single-flow production general-purpose equipment. Activities are also
line without any branching and merging between being investigated and expanded to meet the
the processes has been created, the test types have introduction of the pull system from within the
been integrated, and mixed flow of different plant, between the plants, and with the suppliers.
device types has been created. This has initially
note 11) Electric light board indicating whether a
enabled a production format where products could equipment or process is currently active or
be manufactured taking into account estimated inactive.
Process table
SMT line group Common cell group PIU cell group
Cell #1
Pd Common BF Pd
Pd SMT line #A BF cell #A
Assembly ~ Function test
Intermediate warehouse
Cell #2
Common Pd Assembly ~ Function test
Pd BF
cell #B
Pd SMT line #B BF Cell #3
Pd Assembly ~ Function test
Pd Common BF
cell #C Cell #4
Pd Assembly ~ Function test
Pd Common BF
cell #D Cell #5
Pd Assembly ~ Function test
Information flow Work
Parts flow Cell #6
Pd Assembly ~ Function test
BWB cell group Shelf cell group Device cell group Device test
line group
BWB warehouse
PIU mounting
Pd
Assembly/ BF Pd
Assembly BF
Pd
Rack BF Device test #A BF
test assembly
BF Packaging
Cell #2 Cell #2 Cell #2 Test line and
Device test #B BF shipping
BF Assembly BF BF
Pd Pd Pd
Assembly/ Rack
test assembly
Test line
Device test #C BF
A consistent line
Sa SMT line #A Sa Assembly ~
Function test
Supplement
SMD warehouse
Sa SMT line #B
B mixed flow line
Sa Assembly ~
Function test
St C consistent line
Sa Assembly ~
Sa SMT line #D Function test
Figure 5
Production line improvement at Nasu Plant.
Demand confirmation
[March 2004]
Customer’s lead time : 13.0 days
Shipping
preparation
Intermediate
Mounting
Start of warehouse Shipping
production SMT Set, single (PIU surface Device test
including preparation)
estimated
amounts Production lead time (14.0 days)
Mounting
Store Shipping
pull system)
Set, Device test
SMT single
Figure 6
Improvement of lead time at Nasu Plant.
Table 1
Result of Nasu Plant activities. en so far (Figure 7).
Productivity 2.1 times
Lead time 14.0 days → 7.4 days (▲47%)
5.1 Outline of promotion of plant
Retention days 18.7 days → 9.6 days (▲49%)
improvement activities and innovative
Parts boxes 5000 boxes → 1200 boxes (▲76%)
manufacturing activities
Space 6287 m2 → 4163 m2 (▲34%)
In 1999, SFJ started cost reduction activi-
Amount of 1.18 billion yen (3.8 times compared to
cost reduction fiscal 2003) ties as the plant improvement activities. SFJ has
undertaken activities to reduce the lead times and
manufacturing costs company-wide.
5. SFJ innovative manufacturing The result of these activities is the establish-
activities ment of a cell line production system (system that
SFJ is a domestic manufacturing plant that successfully combines the flexibility of cells that
produces two million laptop computers a year. SFJ enable the workers’ skills to be fully utilized with
is fully involved with domestic manufacturing an automated production line that increases
from the manufacture of PCB units to device equipment efficiency) and the construction of a
assembly. SFJ has constructed a consistent pro- single-flow production line that encompasses all
duction system that even extends to testing. To facets of production from assembly, running, and
maintain QCD that is second to none, SFJ is testing, to packaging.
actively involved in innovative manufacturing
activities. This section describes the innovative 5.2 Initiation of shape-up activities
manufacturing activities that SFJ has undertak- As described in the previous section, the cost
Shape-Up activities
Figure 7
Innovation activity schedule at SFJ.
reduction activities of the plant improvement 2005, initiatives have again been undertaken to
activities started in 1999 have resulted in reduc- rectify the production line, change to small lots,
ing the manufacturing costs by 15% and the synchronize with the subassembly processes, and
manufacturing lead time by 23% as listed in upgrade the Just-In-Time method of parts supply.
Table 2. To further promote the improvements, The analysis and investigations carried out
company-wide activities given the name of based on this guidance have resulted in the
Shape-Up activities, with on-site guidance, have elimination of branching and merging of the
been initiated as innovative manufacturing activ- production flow, switching to a new production sys-
ities starting from November 2003. tem (NPS) that adheres to a single-flow production
The weekly improvement activities and line, and further reduction in lead time and costs.
improvement study meetings that are held regu-
larly each week have aimed at completing 2Ss, 5.3 Future innovations
tightening the work intervals, and creating a Because orders received fluctuate greatly for
material supply flow. These activities have personal products, how to promote level produc-
reduced the production lead time by 25%, created tion and improve the supply method of materials
space and free areas within the plant, and enabled in cooperation with the suppliers are signification
the elimination of outside warehouses in problems.
December 2004. In parallel with the innovations within the
The parts supply and work efficiency on the plant, innovations in propagating and making
device assembly lines has been improved by equal information including marketing divisions
changing the parts supply method from side sup- and innovations in the supply chain management
ply [Figure 8 (a)] to front supply [Figure 8 (b)]. (SCM) for the procurement of supplies including
The plan has always been to construct a the flow of parts from overseas are being
single-flow production line. However, with the undertaken.
introduction of the TPS consultant starting from
Table 2
Results of activities at SFJ.
2002 2003
Target
Second half First half Start of activities November Second half
Manufacturing costs 100% 94% 93% 85%
Manufacturing lead time 100% 100% 93% 77%
(a) Supplying parts from the side (before improvement) (b) Supplying parts from the front (after improvement)
Figure 8
Assembly line improvement at SFJ.