Professional Documents
Culture Documents
Foreword
When producing Volume 1 of this guidance document the authors decided to initially focus on
the design aspects of fibre reinforced concrete segmental tunnel linings, recognising that both
segment design and production constitute equally important aspects for the success of tunnels
lined with precast fibre reinforced concrete segments. Volume 2 therefore concentrates on the
production of segments and the associated quality control.
The advantages of using Fibre Reinforced Concrete for segments are particularly eminent in the
production phase, as the absence or reduction of bar reinforcement typically results in program
and cost savings, and in the reduction of risk associated with the manufacture and installation of
reinforcement cages.
As in Volume 1, the aim of this document is to present the common understanding of designers,
manufacturers and users of fibre reinforced concrete segments of what constitutes good
practice in this field of engineering. The document should be read in combination with Volume 1,
which contains useful information on elementary properties of fibre reinforced concrete.
ITAtech and the sub activity group welcomes all feedback on this document and will incorporate
the user experience with the document in the course of future new editions.
>> Table of contents
FOREWORD.............................................................................................................................................3
AUTHORS.................................................................................................................................................6
NOTATION................................................................................................................................................7
1. PRODUCTION......................................................................................................................................8
1.1 FACTORY AND PRODUCTION SYSTEM......................................................................................8
1.1.2 Carousels...........................................................................................................................10
2.2.2. Aggregates........................................................................................................................16
2.2.3. Admixtures........................................................................................................................16
2.2.4. Water................................................................................................................................16
2.2.5. Fibres...............................................................................................................................16
2.3 CURING...............................................................................................................................17
2.4.2. Storage.............................................................................................................................18
2.4.5. Tolerances.........................................................................................................................19
4 Guideline For Good Practice Of Fibre Reinforced Precast Segment – VOLUME 2 : production ASPECTS
>> Table of contents
3.4.5. Fibres...............................................................................................................................22
ANNEXE 1...............................................................................................................................................26
PRECISION 3D MEASUREMENT OF MOULDS AND SEGMENTS........................................................26
Performance specification..................................................................................................26
Tolerances............................................................................................................................26
ANNEXE 2...............................................................................................................................................32
CE MARKING.............................................................................................................................32
Peer Reviewers
Rolando JUSTA CAMARA Acciona
Luis PINILLOS LORENZANA Mott MacDonald
Paolo ROMUALDI Salini Impregilo
6 Guideline For Good Practice Of Fibre Reinforced Precast Segment – VOLUME 2 : production ASPECTS
>> Notation
Figure 1b : Overhead bucket concrete delivery for static Figure 1c : Static moulds covered with thermal blankets.
mould system.
8 Guideline For Good Practice Of Fibre Reinforced Precast Segment – VOLUME 2 : production ASPECTS
1 >> Production
1.1.2. Carousels
3 >> Preparing the mould for concreting. 3 >> Preparing the mould for concreting.
a. Placement of inserts, application of debonding agent, and greasing of the mould. b. Placement of reinforcement cages, if required (not shown) and closing of the mould.
10 Guideline For Good Practice Of Fibre Reinforced Precast Segment – VOLUME 2 : production ASPECTS
1 >> Production
5 >> Trowelling of the segment extrados surface to remove entrapped air, if required, and closing of the mould lids before the
mould is transferred into the heated curing tunnel.
6 >> C
leaning the outside of the mould of residual concrete. 7 >> Preparing the mould for the curing tunnel.
Depending on the required production and The benefit of utilising fibre only reinforced
project program, a carousel may be set concrete in the design and manufacture
up inside a factory shed and three shifts of tunnel lining segments is the fact that
worked. Each segment mould is cast in the fabrication of reinforcement cages and
line with the planned cycle time, typically their insertion into the moulds prior to the
in the range of 12 to 15 minutes, with the placement of concrete is entirely eliminated.
cycle time based on the required curing This can give very significant cost savings
time considering the number of moulds. The to the project, saving not only materials and
number of working shifts can be reduced labour but also reducing QA/QC processes
once a sufficient stockpile supporting the and requirements, as well as eliminating the
TBM drive has been produced. risk associated with producing and handling
reinforcement cages.
It should be noted that when using a carousel
system to produce fibre reinforced concrete 1.2. Moulds and vibration
segments, it is very common for the placed
concrete to “slough” and settle within the Moulds for tunnel lining are manufactured from
moulds as they are moved along the carousel steel sections and plates. Segment moulds
curing chamber if the lids are kept slightly are precision engineered items that may be
open. This can lead to a reduced thickness subjected to in excess of 1,000 castings
at the centre of the segment. It is therefore during a project. A consequence of this is that
recommended that the mould lids are Figure 4 : Additional central extrados lid. they need to be extremely robust and durable.
completely closed prior to entering the curing
chamber and, dependent upon the rheology 1.1.3. Production - summary
of the concrete mix, it may be necessary to
also install an additional central section of lid There are no hard and fast rules as to which
onto the extrados when the lids are closed production system is best or most economical
after trowelling of the concrete. This ensures for a particular project. Just as each tunnelling
that the segment is then fully closed with no project is unique, then so is the segment
concrete surface visible. manufacturing requirements and factors (such
as land availability, transportation, programme
The project programme will dictate the and availability of labour, etc.) that influence any
production requirements for the number decision making.
of ring sets of segments that need to be If static moulds are considered, each segment
produced each day. If there is a long period mould is cast once per shift. If the production
between the commencement of segment required according to project program can be
production and the commencement of achieved with one working shift per day, static
tunnelling operations, then a static production moulds are the preferred solution. It may be
line operated with a single shift, the static seen that the major difference between the two
production line could well be adequate for methods of production is that with static moulds
the project requirements. If, however, the the workforce moves and the moulds remain
project has several TBMs working on different in place and in a carousel system the moulds
tunnel drives at the same time, a number of move and the workforce remains in place.
carousels may be required in the factory and
a two or three shift system worked on a 24/7 Carousel systems provide a factory production
basis. Generally speaking, most projects line process and will normally require a lesser
will require a stock of approximately three number of segment moulds than a static
months’ anticipated tunnel production prior to system and may also require a smaller factory Figure 5 : High precision moulds.
commencement of the tunnel drive(s). footprint.
12 Guideline For Good Practice Of Fibre Reinforced Precast Segment – VOLUME 2 : production ASPECTS
1 >> Production
Alternatively, the moulds can be placed Figure 6 : Mould design with 3D modelling.
on a vibrating table at the casting location.
Vibrators can be either pneumatic or electric
type. Electric vibrators are more expensive
than pneumatic but they have the advantage
of being able to have their frequency and
amplitude adjusted so that the vibration during
the casting cycle may be “tweaked” to suit the
concrete characteristics, thereby optimising
vibration times. Similarly, pneumatic vibrators
must be operated so that progressive vibration
is obtained. In any case, the vibration power
must be adjusted to the poured concrete mass
in the mould.
14 Guideline For Good Practice Of Fibre Reinforced Precast Segment – VOLUME 2 : production ASPECTS
1 >> Production
2.1. introduction to alkali-aggregate reactivity will generally to concrete. More recent developments
have to be used. The maximum aggregate have also included admixtures containing
The design of a concrete mix that is suitable size used is normally between 20 mm calcium-silicate-hydrates (C-S-H) in aquatic
for the production of fibre reinforced concrete and 28 mm, depending on local supply. suspensions that will accelerate the setting
(FRC) precast segments for tunnel linings is Aggregates with a rough surface texture, time of the concrete and instigate early
paramount to a successful manufacturing such as crushed limestone or granite hydration of the cement particles.
process. Many factors need to be taken into rock aggregates are typically considered
consideration. The primary consideration is best for use in the manufacture of precast 2.2.4. Water
the availability and type of local materials – concrete segments. Once the concrete
cementitious materials, aggregates, admixtures has been placed, vibrated and compacted, Water for the production of FRC mixes
and ancillaries such as mould release agents, angular aggregates will tend to interlock and for segment production should comply
etc. significantly reduce the tendency for the with the relevant local regulations, codes
concrete to shift and settle in the mould after and standards for concrete. In cold
The development of the FRC mix not only has trowelling of the extrados surface and during conditions (less than 5 degrees Celsius) it is
to meet the technical requirements of the project the early stages of its journey through the recommended to use heated water in the
specification (compressive, flexural tensile (LOP), curing tunnel. concrete mix to aid early hydration of the
residual flexural tensile, indirect tensile strengths cement particles. Similarly, the pre-heating of
and possibly other durability parameters such The larger surface area of angular aggregate aggregates may also be required in very low
as chemical resistance, permeability and can result in higher bond strengths than temperatures.
diffusivity) but also has to take into consideration would be obtained with a smooth aggregate.
the requirements of manufacturing and early For similar reasons the inclusion of crushed It should be noted that the precise
age demoulding and handling. rock fine aggregate (0-4 mm) in the concrete calculation of water content in the
mix, either as a whole or partial replacement aggregates is a key factor. It is
There may be additional requirements for for sand, will increase the flexural strength recommended to use an automatic device to
anti-spalling resistance of the segmental lining (Limit of Proportionality or LOP) of the measure the water content in sands which is
in the event of fire in a tunnel that will dictate concrete, however the workability of the mix connected to the batching plant.
the inclusion of monofilament polypropylene can be improved by using washed river sand
micro fibres in the concrete mix. as corrector sand. 2.2.5. Fibres
A key outcome of the design is to achieve It should be noted that an angular Fibres shall be steel or structural synthetic.
a homogeneous concrete mix, leading to aggregate will require more water for a given There may also be an additional requirement
consistent concrete and segment quality. workability than a smooth aggregate, this for monofilament polypropylene fibres (micro
should be considered during mix design, fibres, for spalling reduction) in the mix. In
2.2. Constituent materials particularly when selecting the admixtures. each case, fibres should be dispensed into
All aggregates must be washed to limit and the concrete mix by means of specialist
2.2.1. Cementitious Materials control dust content. calibrated dispensing units. This unit should
be tested for compatibility with the selected
The cementitious materials to be used in the 2.2.3. Admixtures fibres and regularly monitored during the
FRC mix may comprise Ordinary Portland casting process to ensure fibres are properly
Cement only, or combinations of Ordinary The incorporation of a superplasticising distributed throughout the mix and don’t
Portland Cement with PFA and/or GGBS. Other admixture within the FRC mix is essential. form ‘clumps’.
additions, such as microsilica, colloidal silica and This is required in order to provide the
ultrafine limestone powder may also be used. necessary water reduction within the mix A key aspect in fibre reinforced concrete
that is required for durability and very early production is to ensure that homogeneous
2.2.2. Aggregates age strength. In recent years, very powerful fibre distribution in the concrete is achieved.
polycarboxylate ether (PCE) superplasticisers It is recommended to consider the fibre
Aggregates that are locally available for have been developed that will impart manufacturer’s recommendations to ensure
use in concrete and are inert with respect normal or even accelerated setting times the best possible homogeneity is achieved.
16 Guideline For Good Practice Of Fibre Reinforced Precast Segment – VOLUME 2 : production ASPECTS
2 >> Concrete mix design
2.3. Curing
The use of accelerating admixtures can enable 2.4. Coordination of structural Extreme cases for segment end support and
a slight reduction in the level of heat required design and mix design central support are presented below. Please
for curing but this is usually not cost effective. note that handling and transportation checks
Recent developments in admixtures containing The method and sequence of construction, should mirror the actual support conditions,
C-S-H hydration initiators have proven to from pre-casting to installation, needs to be such as a more distributed support for use of
be viable in reducing heat curing of precast coordinated between the segment designer vacuum pads. The resulting maximum shear
concrete segments. Where heat reduction and the supply chain and the contractor force and bending moment in both support
through admixtures is required, the approach installing the segments on site, as segments cases are checked against the time dependent
is to be selected by the mix designer in context have to be designed for all design situations capacity of the fibre reinforced concrete.
with overall constraints. within their lifecycle, including temporary cases
such as demoulding, stacking and erection of
Another way of reducing the amount of heat segments.
required for curing is to use a concrete maturity
monitoring system in the curing tunnel of a For temporary design situations stresses
carousel. By knowing the temperature profile are generally calculated by elastic methods
and history within a segment and inputting to ensure that the flexural strength of the
this temperature and time data into the known unreinforced concrete is not exceeded
Case 1 : Lateral supports.
maturity characteristics of the mix, the actual and thus the segments remain uncracked.
real-time compressive strength of the segment Otherwise, steel reinforcement should be
can be determined and the temperature within included into segments to withstand the
the curing tunnel can be adjusted down so as anticipated bending due to handling.
to impart only the minimum amount of energy
required to achieve demoulding strength. 2.4.1. Handling and Transportation
18 Guideline For Good Practice Of Fibre Reinforced Precast Segment – VOLUME 2 : production ASPECTS
2 >> Concrete mix design
considered: a value of 50mm is recommended tensile resistance of a segment in bending, as Similarly, segment moulds will also require
as a minimum value, and should be agreed opposed to resistance in direct tension. While to have dimensional tolerances specified
with the construction team. both parameters have a strong correlation they by the lining designer. Several international
should be specified and tested separately. documents contain suggested tolerances for
The maximum reaction forces and bending precast tunnel lining segments, such as
moments for the bottom segment of a Tests of flexural tensile strength are typically •T he British Tunnelling Society Specification
stockpile shall be considered in the segment beam tests, as specified by the designer, e.g. for Tunnelling, 3rd Edition 2010
design. Where the segments have insufficient the beam test specified in EN 14651, or ASTM •D AUB (German Tunnelling Committee)
capacity, the stacking height for “young” based tests. It should be noted that the type Recommendations for the design,
segments is typically reduced. of test must be specified by the designer and production and installation of segmental rings
cannot be changed without the designer’s (TTB 2014)
2.4.3. Compressive Strength confirmation.
However, any tolerances should always be
The characteristic 28 days compressive Flexural tensile strength is typically tested at selected recognising the actual demands
strength of the FRC will be specified by the 3 and 28 days as a minimum. The early age of the project. For further information on
designer of the segmental lining. This is tests are required to confirm the capacity of tolerances please refer to Annex A.
generally in the range 40 to 60 MPa. Typically, the segments for design situations associated In addition to specifying the dimensional
the early strength requirement for demoulding with early ages, such as stacking and handling. tolerances for moulds and cast segments at
(usually around 12 to 18 MPa) dictates that the Tests typically capture the flexural tensile a reference temperature, the designer should
concrete should have a water/cementitious strength at first cracking, and the post crack also specify the methods and techniques to
(W/C) ratio of below 0.38. Durability residual strength at various strain levels. be used for measurement. The most accurate
requirements may well dictate that the W/C method is a 3D laser tracker system.
ratio is below 0.35. In these cases, the ultimate The post crack strength is delivered by the
characteristic strength of the concrete will be structural fibres incorporated into the concrete.
> 70 MPa, depending upon the cementitious The correlation between post crack strength,
blend used and the concrete curing fibre type and fibre content is not well defined,
temperatures reached. The compressive and contains a number of unknowns. Post
strength of FRC in segmental linings can be in crack flexural strength values specified by
excess of 100 MPa after 90 days or longer. the designer will therefore typically require
substantiation by an appropriate testing
The development of the mix design for FRC programme to generate a sufficient statistical
segmental linings needs to be conducted well data base.
in advance of segment production as there
are many variables to be taken into account. 2.4.5. Tolerances
For projects in remote areas or locations with
little or no track record in high performance Precast concrete tunnel lining segments,
concretes, it is worthwhile for contractors as any precast concrete product, need to
to evaluate the local concrete and materials be manufactured to specified dimensional
supply chain during the tender stage of the tolerances. The tolerances should be
project. specified by the lining designer at a reference
temperature in order to eliminate the effects
2.4.4. Tensile and Flexural Tensile of thermal expansion/ contraction when
Strengths measurements are taking place and ensure
that accurate comparisons can be made.
Similar to the compressive strength, the tensile Alternatively, the actual temperature during the
and flexural tensile strength will be specified by measurements needs to be converted to the
the designer of the segmental lining. reference temperature.
The flexural tensile strength represents the
3.1. Introduction repair procedures for defective segments. supply of constituent products, and in the
These criteria should be agreed with the manufacture of segments.
The requirements for the segments are client before segment production starts.
the basis for the planning and execution of Segments are typically stockpiled and
quality control. The specified requirements 3.2. Initial Testing stored for a considerable time before
resulting from design and design standards being used on site, as a just in time
will define the methods and frequency The aim of initial testing of the fibre production process for segments would
of investigations, alongside with specific reinforced concrete is to confirm the typically be considered unacceptably risky.
requirements from the client. overall concept of design and have an It is therefore possible to approve the
initial indication of the controlling test use of segment batches based on tests
General requirements resulting from the parameters. A key factor is to ensure a undertaken in the course of production
project’s segmental lining design are : homogeneous mix can be achieved. control, and to identify and quarantine
• Resistance to design stresses batches where the required performance
(compression, tension, flexure) Depending on the duration of testing, has not been reached.
• Ductility initial tests often have to be conducted
• Durability well in advance of full production. This The frequency of production control should
is especially the case when durability therefore be selected considering the
The quality control programme needs to requirements, such as water permeability, production process, and ensure that only a
establish reasonable confidence in the biogenic attack, sulphate attack or similar, limited amount of the segment production
performance of the concrete mix and are specified. is at risk of being compromised if a test
its constituents to deliver the required fails.
performance throughout the design life of The initial testing should also include
the structure. Any quality control program investigation of the mixes with the 3.4. Quality Control Plan
should be developed in a manner so to link maximum allowed deviations of the
into the locally available design and testing proposed mix design. This will define the The quality control plan summarises
standards (ACI, Eurocode) as well as the tolerances for the production process. For production procedures and parameters
locally available tests. the production of fibre reinforced concrete where they have the potential of influencing
segments, the batching weight tolerances the quality of the concrete, as well as
Quality control is commonly differentiated are usually taken as those within the initial and production control testing.
into : respective National Standard, such as EN The tests are specified in terms of type
• Initial testing 206. of testing, frequency of testing, and the
• Continuous production control associated acceptance criteria. In addition
In the phase of the initial testing load- to the pass/fail criteria for the tests it
Initial, pre production testing will be carried tests of whole elements (full scale testing) would be expected to contain procedures
out to ensure the proposed mix and the or fire resistance testing (if required) may implemented if the required values are not
proposed manufacturing process are be conducted to verify the design. It is achieved. Further, the quality control plan
capable of delivering a product complying normally impractical to undertake any non- shall capture how records of the testing will
with the project specific requirements. standardised testing for production control. be kept and distributed.
Quality control during production is
required to demonstrate the segments 3.3. Production control It is recommended to base the quality
achieve the expected performance during control plan on appropriate standards,
production. Production control is required to establish such as EN 206. The following section is
assurance of the quality of the finished based on EN 206, however it is expected
Quality control should establish the product (the segment), as used on site. that the principles can be adopted to other
acceptance criteria for segments, and Its key role is to flag up irregularities in the national standards or guidelines.
20 Guideline For Good Practice Of Fibre Reinforced Precast Segment – VOLUME 2 : production ASPECTS
3 >> Quality control for precast segments
3.4.1 Conformity testing As the performance requirements for the 3.4.4. Conformity of concrete
concrete and the aggregate are often
The various tests undertaken for the governed by local conditions in terms The testing requirements should be
segment concrete are designated as of exposure and availability it is highly established on the basis of standards
conformity testing, which is generally recommended to develop a bespoke generally applicable to the works. Testing
grouped into control of the following testing plan geared to the local situation. should generally be representative for the
aspects: expected placement conditions, and the
1. Control of the constituent materials 3.4.3. Control of equipment preparation and transport of the concrete
2. Control of equipment mix employed in testing should represent
3. Control of production procedures and of Similar to the constituent materials, the actual production conditions as far as
concrete properties the equipment used in the production practicable.
of segments requires control during It is recommended to undertake all
Conformity testing is undertaken for the production. The requirements of EN concrete testing on the basis of testing
initial testing as well as for the continuous 206 Table 23 represent a similar staged triplets, i.e. one test constituting of the
production testing. approach to inspection as the production testing of three individual specimen, in
control of the constituents outlined order to facilitate interpretation of the
3.4.2. Control of the constituent above : results and to identify outliers.
materials •D aily visual inspection of the plant. This In addition to testing of the concrete itself,
should be preferably carried out before the constituents of the concrete such as
Minimum requirements for the production the first use of the production day. aggregates, admixtures, cement and water,
control of the constituent materials are •T he temperature in the casting area need to be quality tested. Appropriate tests
presented in EN 206 Table 22. The should be monitored and recorded, are often available from the suppliers who
production control is undertaken with the with a plan in place as to what to do if undertake testing in the course of their
following staged approach: the temperature falls outside the range respective quality management plan.
• Inspection of delivery ticket prior to required by the mix design. Key pre production tests for fibre
discharge/use. This is mandatory for •S pecific metered installations such as reinforced concrete are presented below.
each delivery. It is recommended to take the water meter should be inspected The suggested tests must be validated
and store samples. on installation, and periodically against project specifications and code
• Visual inspection of aggregate and test afterwards. The inspection interval requirements, and the previous experience
of density for additions in suspension. should be established with the supplier of the supply chain with segment
Likewise, this test is mandatory for each of the equipment, as it depends on the production. In particular, the possible
delivery. conditions of its use. exposure of concrete to aggressive
• Testing of specific parameters, e.g. sieve environmental conditions needs to be
analysis for aggregate. These tests are It is advisable to include references to assessed, and a specific testing regime
mandatory as initial test, and whenever the testing and maintenance schedule of be developed. These tests would be
a supplier is changed. Depending on the equipment in the quality control plan. undertaken in addition to the tests
the reliability of the local supplier it is Further it is recommended to include suggested below.
recommended to undertake these tests workflows for the testing of specific Please note that a pre production test
periodically. equipment (such as the admixtures typically consists of a minimum of 3
dispensers, and for monitoring water samples of not less than 2m3 of concrete.
The quality control plan should contain content in aggregates, in particular sands), The total number of individual tests (e.g.
procedures and tests if there is doubt to be executed if there is doubt about the compressive strength) is (number of
about the properties of the constituent performance of specific elements of the samples) x (number of tests) x (number of
materials. plant. specimen per test).
22 Guideline For Good Practice Of Fibre Reinforced Precast Segment – VOLUME 2 : production ASPECTS
3 >> Quality control for precast segments
with beam tests to establish flexural strength The characteristic value is defined as : If data is available from large production of a
(e.g. with 3 point tests on the EFNARC beam, similar concrete mix, the coefficient of variation
EN 14651), and with tensile splitting tests can be considered known. In this case the
(e.g. EN 12390-6). coefficient kn is equal to :
The following text is based on a classification The value of kn is defined according to ISO
of the material according to Model Code 12491, with the use of a Student’s distribution :
2010, and testing undertaken to associated
standards. The variables used in the
assessment represent the characteristic
residual flexural strength at the following test with u0.05 fractile of the standardized normal
situations : with t0.05 fractile of the t- distribution for the distribution for the probability 0.05. Values of kn
fL,k At limit of proportionality/LOP (first crack) probability 0.05. The value of kn for different for different number of specimen are reported
fR1,k At a crack mouth opening displacement number of specimen is reported in Table 1. in Table 2.
of 0.5mm (representative for SLS)
fR3,k At a crack mouth opening displacement
n Kn n Kn
of 2.5mm (representative for SLS)
3 3.37 3 1.89
The method to establish compliance can 4 2.63 4 1.83
be adopted to other test and other suites of 5 2.34 5 1.80
standards.
6 2.18 6 1.77
8 2.01 8 1.74
When undertaking concrete tests in the
pre-production phase, the test results can be 9 1.96 9 1.73
Further tests
24 Guideline For Good Practice Of Fibre Reinforced Precast Segment – VOLUME 2 : production ASPECTS
3 >> Quality control for precast segments
The procedure for the quality control during The contractor and designers should define
segment production should be specified on and agree a procedure for the use of the
the basis of requirements produced by the segments that fail quality control. Ideally this
designer. This shall take into account the should be in place before the start of segment
forecast production rate (number of segments production.
per day), and the potential variation of the
production test results through time. Typical solutions would be using the segments
in parts of the tunnel where imposed loads are
It is recommended to perform flexural tests lower than the worst design case (lower cover,
on the fibre reinforced concrete in addition to different ground, etc), using the segments
compressive tests. For this purpose, beam in ‘sacrificial’ areas (inside shafts / station
test according to EN 14651 can be performed boxes /similar) or using the segments as bulk
to control the residual strengths during the fill / ballast (for instance placed inside large
production. It is suggested to test a sample of mass concrete pours in shaft base slabs,
at least 3 beams for every test. replacing an equivalent volume of poured
mass concrete). Disposal or dumping of the
The conformity control can be made adopting segments should be considered the last resort.
the same approach of EN 206 for concrete in
compression. If more than 15 data points are The procedure should include a process for
considered, the mean values should respect identifying why the concrete failed quality
the conditions : control and what measures have been put in
place to prevent future failures.
Precision 3D measurement of On some projects there is only a passing 2) D imensional Measurement control of all
Moulds and Segments reference to the tolerance and quality control segments after the 20th casting from
requirements which enable the contractor or each mould.
Performance specification precast company to bypass the checking that is 3) D imensional Measurement control of all
implied in the standards / guidelines. The simple segments after the 30th casting from
Tapered rings enable the tunnel lining to addition of a few clarifying clauses in the tender each mould.
accommodate alignments that contain curves documents are called for to significantly improve Or
or to compensate for misalignment of the this. The inclusion of all of these requirements 4) A fter the start of production, the 50th
tunnel due to site-specific problems. The use in a table or diagrammatically on a single ring produced from every formwork
of Fibre Reinforced Segments necessitates composite diagram will dramatically improve the mould should be re-measured. The next
more precise segments and greater care in understanding of the requirements and assist in measurements should be performed after
their installation is needed. their implementation. (See figures 1-4) every 100 castings, unless otherwise
The reasoning for specifying the very tight provided for in the construction contract.
tolerances in these standards are : The total quality control should be clearly 5) If manufacturing tolerances are exceeded
1. Geometric sensitivity to inaccuracies and defined as the responsibility of the contractor in any measurement, all segments
distortions of individual segments who should supervise the segments supplied produced after the last measurement
2. High load effects from earth, water and by the precast company. (with compliant tolerances) must be
grouting pressure on the tunnel lining re-measured working backwards from
3. Jacking forces during mining Key points to add include : the most recent. All segments within
4. The load transfer takes place only in limited 1. T
he reference temperature that the the tolerances should be accepted, all
areas (partial surface load) segments should achieve the specified segments exceeding the tolerances must
5. Damage cannot always be detected (for tolerances. be considered separately.
example, on the outer side of the ring) 2. T
he time after de-moulding when precision 4. Tolerances on “closed” (built) ring must NOT
6. Repairing of damaged segments are costly measurement of the segment is acceptable. be the sum of all individual tolerances.
and time-consuming 3. A
clear measurement regime should be 5. Individual tolerances should be
specified such as: compensated with the mathematical sign.
Tolerances a. D imensional Measurement control of 6. Every controlled segment must be proved
all moulds at manufacturers’ factory by a record sheet (physical or digital). A full
Most projects include a requirement in the including segment detail such as bolt hole segment documentation system should enable
tender documents that specifies compliance size and position, gasket grooves etc. full traceability of the segment production; this
with the tolerances indicated in one of b. C heck Dimensional Measurement control should include all the constituent components
the several international standards, most of all moulds on the precast production of the segment, the production methods and
of which were issued prior to the use of line (either static or carousel before mass durations, personnel responsible, tolerance
fibre reinforcement or the availability of the production), this should include a check measurements right through to the precise
current measurement technologies. Many on any torsion. place the segment is installed in the finished
of these international standards already call c. T he measurement location (e.g. roofed tunnel.
for sub millimetre accuracy on several key hall with temperatures between 15
dimensions. Ring designers will frequently and 20°C) should be specified in the
modify these values according to project construction contract.
specific requirements. All of these standards d. T hree Dimensional Measurement control
are however incomplete with respect of all segments after first pouring
to the requirements of current precision e. T hen after a given number of castings,
measurement techniques and fail to include the exact frequency can be varied
full traceability of the segment, its constituent according to the designer’s project
components, manufacturing process, specific requirements such as:
dimensional accuracy and installed location as 1) Dimensional Measurement control of
part of an ongoing Quality Assurance / Quality all segments after the 10th casting
Control process. from each mould.
26 Guideline For Good Practice Of Fibre Reinforced Precast Segment – VOLUME 2 : production ASPECTS
>> Annex 1
Segment Lining
Code Segment Tolerances
Tolerances of fabrication
External Segment Arch Length type A1, A2, A3, A4, A5 An, B, C. AE ±1mm 2.3 ±0.6mm ±0.7mm
Internal Diameter of Ring (Master Ring) ID ±0.2% ID or 6mm Maximum 5.2 ±10.0mm ±15.0mm
Position of Bolt hole and plastic dowels 1mm 6.2 ±1.0mm ±1.0mm
Pitch angle Segment Type A1, A2, A3, ..An B, C. αp ±0.02° ±0.02°
Smoothness of faces other than joints ±1.5mm(smooth float) ±1mm (formed face)
Gap between longitudinal segment Joints (Master Ring) LI 1.0mm feeler gauge not passing
1
2.0mm feeler gauge not passing beneath a 1 m long straight edge
2
From the theoretical plane, with a rate of deviation not exceeding 0.6mm/m
Notes :
1. It is not allowed that the Maximum tolerances add to one another, hence tolerances of the whole ring are smaller than the sum of the single tolerances.
2. Two test rings shall be erected on a flat and level base with the top ring rotated one bolt pitch from the bottom ring with the bolts inserted. The base ring shall be retained as
the master-ring. Checks shall be made against the master-ring at intervals not exceeding 0.5% of the segment production.
3. All given tolerances refer to a reference temperature of 20°C.
4. In the case of inconsistencies of two dependent tolerances then the more stringent shall be relevant.
5. Tolerances for Gasket groove (TG, WG) shall be in accordance with the requirements of the gasket supplier. itatech ACTIVITY GROUP - SUPPORT 27
>> Annex 1
28 Guideline For Good Practice Of Fibre Reinforced Precast Segment – VOLUME 2 : production ASPECTS
>> Annex 1
Annex 1 Figure 4
Due to the often complex design of tapered rings there are frequently designs that have no parallel surfaces from which to measure the dimensional
accuracy of either the moulds used to produce the segments or the segments themselves. To correctly check the individual dimensional accuracies
would require a very time consuming measurement procedure using hand-held tools with highly skilled personnel or the use of a “dynamic full surface
3D measurement system”.
Annex 1 Figure 5
Annex 1 Figure 6
30 Guideline For Good Practice Of Fibre Reinforced Precast Segment – VOLUME 2 : production ASPECTS
>> Annex 1
Such a system typically comprises a LaserTracker to carry out a measurement of all the contact surfaces, the radii, both the outer and the inner
diameters as well as any detail such as gasket grooves and bolt-hole positions etc,. These measurements are analysed and processed via a
traceable 3D metrology software platform and comparison is then made between the measured object and the nominal design. Any report that
is made from the measurement of the tolerances should be as succinct as possible but as comprehensive as necessary to impart the necessary
information. (see example below Figures 5-8)
Annex 1 Figure 7
Annex 1 Figure 8
CE marking
System 1 System 3
The basic information given in the CE marking
is the following : Field of use
• Type of fibres: steel/polymer; Structural use A) Non structural use
• CE Certification; Quality control
• Type and dimension;
• Initial Type Testing by a Notified Laboratory
• Tensile strength; • Initial type Testing (ITT) under the responsibility of the
Notified certification Body
• Young’s modulus; •F
actory Production Control (FPC) under responsibility
of the manufacturer
• Length; • Initial and Annually Factory Production Control (FPC)
assessment by Notified Body
• Cross sectional form; •T
he manufacturer creates and signs a “Declaration
of conformity”
• Diameter or dimensions of cross section; • Certification institute → “Certificate of Conformity”
• Surface finish and anchorage (eg. hooked at
A)
Structural use of fibres is where the addition of fibres is designed to contribute to the load bearing capacity of a
the end or embossed); concrete element
• Tolerances on the length, the diameter (and
the aspect ratio for steel fibres); Difference between attestation under System 1 and System 3.
• Safety aspects.
In addition the declaration of performance System 3 is applicable when fibres are used In practice, therefore, when the post-crack
under standard tests is reported. for other reasons, i.e. for some non-structural strength of fibre concrete is taken into account
For CE-marking of fibres, two levels of function - for instance to reduce the risk of in the structural design, the fibres must be
attestation of conformity are defined: System 1 plastic shrinkage, or to improve the behaviour certified under System 1, and the CE label on
and System 3. of concrete in fire. This system allows the the packaging must indicate that the fibres are
System 1 is applicable when the fibres have manufacturer alone to declare that the quality certified for structural use (System 1).
a structural function, i.e. when the fibres are is in accordance with the requirements of the
designed to contribute to the load-bearing standard: no confirmation by a third party is
capacity. The system requires a continuous necessary.
surveillance of the production process of the
fibres by an independent Certifying Body,
which delivers a certificate of conformity
(CE- mark).
32 Guideline For Good Practice Of Fibre Reinforced Precast Segment – VOLUME 2 : production ASPECTS
>> Annex 2
ITA Secretariat - c/o MIE2 – Chemin de Balexert 9 - CH-1219 Châtelaine (GE) - Switzerland
Tel. : + 41 21 693 23 10 - Fax : + 41 21 693 41 53 - Email : secretariat@ita-aites.org - Web : www.ita-aites.org