EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION

PART 1: PRELIMINARY & GENERAL SABS 1200 A

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO

SABS SECTION A: PRELIMINARY AND GENERAL


1200 A
8.3 A1. SCHEDULE FIXED CHARGE AND VALUE RELATED
ITEMS
8.3.1 A1.1 Contractual Requirements Sum 1 20,000.00 20,000.00

8.3.2 A1.2 Provision of Facilities on Site


PSA 8.2.1
8.3.2.1/ A1.2.1 (a) Facilities required for the Engineer:
PSA 8.2.1
A1.2.1.1 (i) Construction Signboards Sum 1 8,000.00 8,000.00

A1.2.2 (a) Facilities required by Contractor

A1.2.2.1 (i) Site Offices and storage area Sum 1 8,000.00 8,000.00

A1.2.2.2 (ii) Workshops Sum Rate Only

A1.2.2.3 (iii) Laboratory Sum Rate Only

A1.2.2.4 (iv) Ablution and latrine facilities Sum 1 8,298.20 8,298.20

A1.2.2.5 (v) Tools and equipment Sum 1 15,000.00 15,000.00

A.1.2.2.6 (vi) Water supplies, electrical power and communications Sum 1 6,000.00 6,000.00

8.3.3 A1.3 General Responsibilities and Other Fixed Charge Sum 1 2,500.00 2,500.00
Obligations

8.3.4 A1.4 Removal of Site Establishment Sum 1 5,000.00 5,000.00

8.4 A2. SCHEDULED TIME-RELATED ITEMS:

8.4.1 A2.1 Contractual Requirements Sum 1 12,000.00 12,000.00

8.4.2 A2.2 Operation and Maintenance of Facilities on Site

A2.2.1 (a) Facilities required for the Engineer:

A2.2.1.1 (i) Construction Signboards Sum 1 -

Carried Forward 84,798.20

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2 /77

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION

PART 1: PRELIMINARY & GENERAL SABS 1200 A

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO

Brought Forward 84,798.20

A2.2.2 (a) Facilities required by Contractor

A2.2.2.1 (i) Offices and storage sheds Sum 1 7,000.00 7,000.00

A2.2.2.2 (ii) Workshops Sum Rate Only

A2.2.2.3 (iii) Laboratory Sum Rate Only

8.4.2 A2.2.2.4 (iv) Ablution facilities Sum 1 3,000.00 3,000.00

8.4.2 A2.2.2.5 (v) Tools and equipment Sum 1 3,000.00 3,000.00

A2.2.2.6 (vi) Water supplies, electrical power and communications Sum 1 3,000.00 3,000.00

8.4.3 A2.3 Supervision for Duration of Construction Sum 1 3,000.00 3,000.00

8.4.4 A2.4 Company and Head Office Overhead Costs Sum 1 3,000.00 3,000.00

8.4.5 A2.5 General Responsibilities and Other Time Sum 1 3,000.00 3,000.00
Related Obligations

8.6 A3. PRIME COST SUMS

A3.1 (i) Additional tests required by the Engineer PC Sum 25,000.00

A3.2 (ii) Charge required on item (i) above: % 25,000.00 10.0% 2,500.00

8.8.2 A4. ACCOMODATION OF TRAFFIC Sum

8.8.4 A5. LOCATION AND PROTECTING OF EXISTING


SERVICES

A5.1 (a) Provision of detecting services for:

A5.1.1 (i) Water and sewer pipes Prov. Sum 7,500.00

A5.1.2 (ii) Electrical and other cables Prov. Sum 7,500.00

A5.2 (b) Hand excavation necessary for locating


and exposing existing services in all material:
A5.2.1 (i) In Roadways m3 Rate Only

A5.2.1 (ii) In all other areas m3 Rate Only

Carried Forward 152,298.20

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2 /78

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION

PART 1: PRELIMINARY & GENERAL SABS 1200 A

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO

Brought Forward 152,298.20

8.9 A6. Employer's share of DAB fees services Prov. Sum 25,000.00

8.10 A7. PROVISIONAL SUM FOR AUXILIARY WORK Prov. Sum 10,000.00
(Required to private properties as instructed by the
Engineer)

TOTAL SECTION (A) SABS1200 CARRIED TO SUMMARY 187,298.20

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2/79

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION

PART 2: WATER RETICULATION INFRASTRUCTURE SABS 1200 DM

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO

SABS SECTION A: SITE CLEARANCE


1200 C
8.2.1 A1. CLEAR AND GRUB SITE (incl. removal of vegetation):

A1.3 (c) Clear and grub areas of 3,0m wide Strips:

A1.3.1 (ii) Water reticulation infrastructure route m 2,080 12 24,960.00

8.2.3 A2. REMOVE AND GRUB ALL TREES AND TREES


STUMPS REGARDLESS OF GRITH:
Rate shall cover all operations cost No 20 7 140.00

8.2.4 A3. RECLEAR SURFACES


(as per Engineer's Instruction):
A3.1 (a) Re-clear surfaces m 2500 8 20,000.00

8.2.9 A3. REMOVAL OF REDUNDANT MATERIALS

A2.3 (a) Transport all redundant materials to approved t.km 50 120 6,000.00
municipal dumpsite

TOTAL SECTION (A) SABS1200 C CARRIED TO SUMMARY 51,100.00

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2/80

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION
SCHEDULE A4
PART 2: WATER RETICULATION INFRASTRUCTURE SABS 1200 DM

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO

SABS SECTION A: EARTHWORKS (PIPE TRENCHES)


1200 DB
8.3.2 A1. EARTHWORKS (PIPE TRENCHES)
(a) Excavate in all materials for trenches, backfill,
compact, and dispose of surplus material for:

A1.1 Water distribution pipeline up to 300mm dia


for trench:
A1.1.1 (a) Not exceeding 1,5 m depth, as indicated on m 2065 32.00 66,080.00
relevant drawings

A1.1.2 (b) Extra-over item (a) above for :


(i) Hand excavation in soft material to make m³ 100 120.00 12,000.00
connections to existing pipelines

A1.2 Extra-over item (b) above for :


A1.2.1 (a) Intermediate excavation m³ 100 120.00 12,000.00

A1.2.2 (b) Hard rock excavation m³ 50 450.00 22,500.00

PSDB 8.3.3 A2. EXCAVATION ANCILLARIES


Make up deficiency in backfill material (Provisional)
PSDB A.2.1 (a) from other necessary excavations on site m³ Rate Only
8.3.3.1
A.2.2 (b) by importation from designated borrow pit m³ Rate Only

A.2.3 (c) by importation from commercial or off site sources m³ Rate Only
selected by the Contractor

8.3.6 A3. FINISHING


Reinstate road surfaces complete with all courses
PSDB
8.3.3.3 A.3.1. (a) Gravel wearing course roads m³ 50 320.00 16,000.00

TOTAL SECTION (A) SABS1200 DB CARRIED TO SUMMARY 128,580.00

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2/81

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION
SCHEDULE A4
PART 2: WATER RETICULATION INFRASTRUCTURE SABS 1200 LB

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO

SANS SCHEDULE B: BEDDING (WATER PIPES)


1200 LB
PSLB 8.2.1 B1 Provision of bedding from trench excavation

B1.1 (a) Selected granular material (bedding cradle) m³ 450 85.00 38,250.00

B1.2 (b) Selected fill material (selected fill blanket) m³ 180 85.00 15,300.00

B2 Supply only of bedding by importation

PSLB B2.1 From other necessary excavations


8.2.2.1
B2.1.1 (a) Selected granular material m³ 450 85.00 38,250.00

B2.1.2 (b) Selected fill material m³ 180 85.00 15,300.00

PSLB 8.2.2.2B2.2 From borrow pits

B2.2.1 (a) Selected granular material m³ 180.00 Rate Only

B2.2.2 (b) Selected fill material m³ 180.00 Rate Only

PSLB 8.2.2.3B2.3 From commercial sources

B2.3.1 (a) Selected granular material m³ 140 300.00 42,000.00

B2.3.2 (b) Selected fill material m³ 60 300.00 18,000.00

PSLB 8.2.5 B2.4 Overhaul of Material for bedding cradle and km.m³ Rate Only
selected fill blanket

PSDB 3.5 B2.5 Soilcrete Backfilling (5% cement) (Provisional) m³ 20 340.00 6,800.00

TOTAL SECTION (B) SABS1200 LB CARRIED TO SUMMARY 173,900.00

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2/82

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION
PART 2: WATER RETICULATION INFRASTRUCTURE SABS 1200 L

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO

SABS SECTION C: MEDIUM PRESSURE PIPELINES


1200 L
C1. Expose & connect to existing services:

C1.1 (a) 110mm diameter uPVC pipelines No. Rate Only

C1.2 (b) 160mm diameter uPVC pipelines No. 5 650.00 3,250.00

8.2.1 C2. Supply, lay, joint, and disinfect uPVC class 9 pipes (SABS
966) socketed for mechanical jointing complete with rubber
ring sealers:

C2.1 (a) 63mm diameter m Rate Only

C2.2 (b) 90mm diameter m 1000 65.00 65,000.00

C2.3 (c) 110mm diameter m 1080 75.00 81,000.00

C2.4 (d) 160mm diameter m Rate Only

8.2.1 C3. Supply, lay, joint, and disinfect HDPE class 10 pipes (SABS
966) socketed for mechanical jointing complete with
couplings and test:

C3.1 (a) 32mm diameter m 275 25.00 6,875.00

C3.2 (b) 25mm diameter m Rate Only

8.2.5 C4. Supply, lay, joint, and disinfect uPVC class 16 bends
socketed for mechanical jointing complete with with rubber
ring sealers:

C4.1 (a) 11.25°, 110mm diameter No. 2 110.00 220.00

C4.2 (b) 11.25°, 90mm diameter No. 3 110.00 330.00

C4.3 (c) 11.25°, 63mm diameter No. Rate Only

C4.4 (d) 22.5°, 110mm diameter No. Rate Only

C4.5 (e) 22.5°, 90mm diameter No. Rate Only

Carried Forward 156,675.00

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2/83

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION
#REF!
PART 2: WATER RETICULATION INFRASTRUCTURE SABS 1200 L

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO
Brought Forward 156,675.00

C4.6 (f) 22.5°, 63mm diameter No. Rate Only

C4.7 (h) 45°, 110mm diameter No. Rate Only

C4.8 (i) 45°, 90mm diameter No. Rate Only

C4.9 (j) 45°, 63mm diameter No. Rate Only

C4.10 (k) 90°, 110mm diameter No. Rate Only

C4.11 (l) 90°, 90mm diameter No. 1 110.00 110.00

C4.12 (m) 90°, 63mm diameter No. Rate Only

8.2.5 C5. SGI Reducers socketed for mechanical jointing complete


with rubber ring sealers:

C5.1 (a)110 x 90 mm diameter No. Rate Only

C5.2 (b) 110 x 63mm diameter No. Rate Only

C5.3 (b) 90 x 63mm diameter No. Rate Only

C5.4 (b) 90 x 63mm diameter No. Rate Only

8.2.5 C6. SGI Equal Tee socketed for mechanical jointing complete
with rubber ring sealers:

C6.1 (a) 63mm diameter No Rate Only

C6.2 (b) 90mm diameter No 1 110.00 110.00

C6.3 (c) 110mm diameter No 2 110.00 220.00

C6.4 (d) 160mm diameter No Rate Only

Carried Forward 157,115.00

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2/84

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION
PART 2: WATER RETICULATION INFRASTRUCTURE SABS 1200 L

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO
Brought Forward 157,115.00

8.2.5 C7. SGI Reducing Tee socketed for mechanical jointing


complete with rubber ring sealers:

C7.1 (a) 110 x 63mm diameter No Rate Only

C7.2 (b) 110 x 90mm diameter No 4 110.00 440.00

C7.3 (c) 90 x 63mm diameter No Rate Only

C7.4 (d) 160 x 90mm diameter No 2 110.00 220.00

C7.5 (e) 160 x 110mm diameter No 3 110.00 330.00

8.2.5 C8. Supply & Install Resilient Seal Gate Valve spigot with
complete valvebox as per the typical drawing, (AVK or
similar approved), inclusive of all nuts, bolts & gasket
seals:
C8.1 (a) 50mm Nominal Bore PN10 No Rate Only

C8.2 (b) 80mm Nominal Bore PN10 No 6 1,600.00 9,600.00

C8.3 (c) 100mm Nominal Bore PN10 No 6 2,100.00 12,600.00

C8.4 (d) 150mm Nominal Bore PN10 No Rate Only

C8.5 (e) 200mm Nominal Bore PN10 No Rate Only

8.2.5 C9. Supply & Install Full-Bore Ball Valve, both ends BSP
Female Threaded, (Cobra ITAP or similar approved),
inclusive of all nuts, bolts & gasket seals:

C9.1 (a) 32mm Nominal Bore No Rate Only

C9.2 (b) 50mm Nominal Bore No Rate Only

Carried Forward 180,305.00

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2/85

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION
#REF!
PART 2: WATER RETICULATION INFRASTRUCTURE SABS 1200 L

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO
Brought Forward 180,305.00

8.2.5 C10. Supply & Install Free Shaft Swing Check Valve, (AVK or
similar approved), inclusive of all nuts, bolts & gasket
seals:

C10.1 (a) 100mm Nominal Bore PN10 No Rate Only

C10.2 (b) 150mm Nominal Bore PN10 No Rate Only

8.2.5 C11. Supply & Install Double - Orifice Air Valve, inclusive of all
nuts, bolts & gasket seals:

C11.1 (a) 100mm Nominal Bore PN25 No Rate Only

C11.2 (b) 150mm Nominal Bore PN25 No Rate Only

8.2.5 C12. SGI End Caps socketed for mechanical jointing complete
with rubber ring sealers:

C12.1 (a) 63mm diameter No Rate Only

C12.2 (b) 90mm diameter No Rate Only

C12.3 (c) 110mm diameter No Rate Only

Carried Forward 180,305.00

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2/86

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION
#REF!
PART 2: WATER RETICULATION INFRASTRUCTURE SABS 1200 L

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO
Brought Forward 180,305.00

8.2.5 C14. SGI Flange Adaptors socketed for mechanical jointing


complete with rubber ring sealers:

C14.1 (a) 160mm diameter No Rate Only

8.2.11 C15. Grade 15/19 Concrete for Thrustblocks, to be cast into open
trench and against undisturbed soil, inclusive of formwork
as required:

C15.1 (a) For 11.25° bends m³ 5 850.00 4,250.00

C15.2 (b) For 22.5° bends m³ 5 850.00 4,250.00

C15.3 (c) For 45° bends m³ Rate Only

C15.4 (d) For 90° bends m³ 1 850.00 850.00

C15.5 (e) For T-pieces and End Caps, Other sizes as may be specified in writing
m³ 5 850.00 4,250.00

8.2.14 C16. Construct new Fire Hydrant complete as specified in No. 6 2,500.00 15,000.00
drawings, inclusive of excavation, concrete, brickwork,
valves and pipework as indicated in drawings:

TOTAL SECTION (C) SABS1200 L CARRIED TO SUMMARY 208,905.00

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2/87

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION
PART 2: WATER RETICULATION INFRASTRUCTURE SABS 1200 LF

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO

SABS SECTION D: ERF CONNECTION (WATER)


1200 LF
8.2.1 D1. Provide erf connections complete, including all fittings,
specials as indicated in the drawings, excavating,
backfilling etc

D1.1 (a) Single erf connection No 6 1,100.00 6,600.00

D1.2 (b) Double erf connection (approximately 6m) No 30 1,500.00 45,000.00

D1.3 (c) Double erf connection (approximately 15m) No 6 1,900.00 11,400.00

D1.4 (d) Double erf connection (approximately 19m) No 17 2,500.00 42,500.00

D1.5 (e) Double erf connection (approximately 32m) No 20 4,500.00 90,000.00

D1.6 (f) Multiple unit erf connection No Rate Only

D2. Cleaning & Finishing of entire pipeline route m 2080 15.00 31,200.00

TOTAL SECTION (D) SABS1200 LF CARRIED TO SUMMARY 105,500.00

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2 /88

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION

PART 3: RISING MAIN INFRASTRUCTURE SABS 1200 C

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO

SABS SECTION A: SITE CLEARANCE


1200 C
8.2 A1. CLEAR AND GRUB SITE (incl. removal of vegetation):

8.2.1 A1.1 (a) Clear and grub Rising Main Route m 3,200 12.00 38,400.00

A1.2 (b) Clear and grub area as per Engineers indication ha Rate Only

8.2.3 A2. REMOVE AND GRUB ALL TREES AND TREES STUMPS
REGARDLESS OF GRITH:
Rate shall cover all operations No 15 750.00 11,250.00

8.2.4 A3. RECLEAR SURFACES


(as per Engineer's Instruction):
A3.1 (a) Re-clear surfaces m 1800 8.00 14,400.00

8.2.9 A3. REMOVAL OF REDUNDANT MATERIALS

A3.1 (a) Transport all redundant materials to approved t.km Rate Only
municipal dumpsite

A3.2 (b) Remove redundant pipe material and building material t.km Rate Only
that remain on site from construction activities to a
municipal activities to a municipal dumpsite of the
contractor's choice, approved by the Engineer

TOTAL SECTION (A) SABS1200 C CARRIED TO SUMMARY 64,050.00

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2 /89

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION

PART 3: RISING MAIN INFRASTRUCTURE SABS 1200 DB

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO

SABS SECTION B: EARTHWORKS (PIPE TRENCHES)


1200 DB
8.3.2 A1. EARTHWORKS (PIPE TRENCHES)
(a) Excavate in all materials for trenches, backfill,
compact, and dispose of surplus material for:

A1.1 Water distribution pipeline up to 300mm dia


for trench:
A1.1.1 (a) Not exceeding 1,5 m depth, as indicated on m 3200 32.00 102,400.00
relevant drawings

A1.1.2 (b) Extra-over item (a) above for :


(i) Hand excavation in soft material to make m³ 5 120.00 600.00
connections to existing pipelines

A1.2 Extra-over item (b) above for :


A1.2.1 (a) Intermediate excavation m³ 100 120.00 12,000.00

A1.2.2 (b) Hard rock excavation m³ 256 450.00 115,200.00

A1.2.3 (c) Extra-over items (a) and (b) above for disposal of m³ Rate Only
materials off-site, unlimited distance

8.3.2 A1.2.4 (d) Extra-over items (a) above for the hand excavation and m³ Rate Only
back fill where ordered by the Engineer

8.3.3 B2. EXCAVATION ANCILLARIES

Make up deficiencies in backfill material (provisional)

PSDB 8.3.2 B2.1 (a) from other necessary excavations on site m³ 200 80.00 16,000.00

B.2.2 (b) by importation from designated borrow pit m³ Rate Only

B.2.3 (c) by importation from commercial or off site sources m³ Rate Only
selected by the Contractor

8.3.6 B3. FINISHING

Reinstate road surfaces complete will all course

(a) Gravel wearing course roads m³ 100 320.00 32,000.00

TOTAL SECTION (B) SABS1200 DB CARRIED TO SUMMARY 278,200.00

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2 /90

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION

PART 3: RISING MAIN INFRASTRUCTURE SABS 1200 DB

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO

SANS SCHEDULE B: BEDDING (WATER PIPES)


1200 LB
PSLB 8.2.1 B1 Provision of bedding from trench excavation

B1.1 (a) Selected granular material (bedding cradle) m³ 930 85.00 79,050.00

B1.2 (b) Selected fill material (selected fill blanket) m³ 520 85.00 44,200.00

B2 Supply only of bedding by importation

PSLB B2.1 From other necessary excavations


8.2.2.1
B2.1.1 (a) Selected granular material m³ 930 85.00 79,050.00

B2.1.2 (b) Selected fill material m³ 520 85.00 44,200.00

PSLB 8.2.2.2B2.2 From borrow pits

B2.2.1 (a) Selected granular material m³ Rate Only

B2.2.2 (b) Selected fill material m³

PSLB 8.2.2.3B2.3 From commercial sources

B2.3.1 (a) Selected granular material m³ 280 120.00 33,600.00

B2.3.2 (b) Selected fill material m³ 160 120.00 19,200.00

PSLB 8.2.5 B2.4 Overhaul of Material for bedding cradle and km.m³ Rate Only
selected fill blanket

PSDB 3.5 B2.5 Soilcrete Backfilling (5% cement) (Provisional) m³ 20 320.00 6,400.00

TOTAL SECTION (C) SABS1200 LB CARRIED TO SUMMARY 305,700.00

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2 /91

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION

PART 3: RISING MAIN INFRASTRUCTURE SABS 1200 L

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO

SABS SECTION D: SEWER MAIN PIPELINE


1200 L
D1. Expose & connect to existing services:

D1.1 (a) 110mm diameter uPVC pipelines No. Rate Only

D1.2 (b) 160mm diameter uPVC pipelines No. 1 850.00 850.00

8.2.1 D2. Supply, lay, joint, and disinfect uPVC class 12 pipes
(SABS 966) socketed for mechanical jointing complete
with rubber ring sealers:

D2.1 (a) 110mm diameter m Rate Only

D2.2 (b) 160mm diameter m Rate Only

D2.3 (b) 200mm diameter m 3,200 95.00 304,000.00

8.2.5 D3. Supply, lay, joint, and disinfect uPVC class 16 pipes
(SABS966) bends socketed for mechanical jointing
complete with with rubber ring sealers:

D3.1 (a)11.25°, 200mm diameter No. Rate Only

D3.2 (b) 22.5°, 200mm diameter No. 1 110.00 110.00

D3.3 (c) 45°, 200mm diameter No. Rate Only

D3.4 (e) 90°, 200mm diameter No. 2 110.00 220.00

Carried Forward 305,180.00

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2 /92

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION

PART 3: RISING MAIN INFRASTRUCTURE SABS 1200 L

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO

Brought Forward 305,180.00

8.2.11 C15. Grade 15/19 Concrete for Thrustblocks, to be cast into


open trench and against undisturbed soil, inclusive of
formwork as required:

C15.1 (a) For 11.25° bends m³ Rate Only

C15.2 (b) For 22.5° bends m³ 2 850.00 1,700.00

C15.3 (c) For 45° bends m³ Rate Only

C15.4 (d) For 90° bends m³ 2 850.00 1,700.00

TOTAL SECTION (D) SABS1200 L CARRIED TO SUMMARY 308,580.00

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2 /93

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION

PART 3: RISING MAIN INFRASTRUCTURE SABS 1200 L

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO

SABS SECTION E: NON-RETURN VALVE BOX


1200 L
E1. Expose & connect to existing services:

E1.1 Supply and install Non-Return Valve (AVK or approved No. 1 4,500.00 4,500.00
similar) inclusive of all specials, pipework, nuts, bolts,
gasket seals& manhole complete as indicated on the
drawing

D6.1 (a) 200mm Nominal Bore No 2,500.00 Rate Only

TOTAL SECTION (D) SABS1200 L CARRIED TO SUMMARY 4,500.00

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2/94

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION

PART 4: OXIDATION PONDS SABS 1200 DE

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO

SABS SECTION A: SMALL EARTH DAMS


1200 DE
8.3.1 A1. SITE CLEARANCE

8.3.1.1 A1.2 Clear and strip site and conserve topsoil of quantity ha 0.5 750.00 375.00
specified in item no.A8.1

8.3.1.2 A2. Remove and grub large trees


or stumps only, as scheduled, of girth

A2.1 (a) over 0 m and up to and including 1 m No 10 1,200.00 12,000.00

A2.2 (b) over 1 m and up to and including 2 m No 10 1,700.00 17,000.00

A2.3 (c) over 2 m and up to and including 3 m No 10 2,500.00 25,000.00

8.3.3 A4 EXCAVATION

A4.1 (a) Material unsuitable for embarkment.


The rate shall cover the cost of excavating, removal to 0.00
designated spoil dumps, spreading and trimming. m³ 200 35.00 7,000.00

A4.2 Extra-over for item (A4.1) above for:

(1) Intermediate material m³ 40 220.00 8,800.00

(2) Hardrock m³ 50 450.00 22,500.00

A4.3 b) Material suitable, use for fill and compact


to density of 90% MOD AASHTO m³ 300 0.00

8.3.4 A5 PREPARATION OF EXPOSED SURFACES

A5.1 (a) Rip and Recompact insitu material to a density of 95% m³ 400 250.00 100,000.00
Mod. AASHTO density

Carried Forward 192,675.00

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2/95

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL SABS 1200 DE

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO

Brought Forward 192,675.00

8.3.5 A7 FORMING EMBANKMENT

A7.1 G7 selected material for embankment wall, imported m³ 2300 55.00 126,500.00
material and compacted to 95% MOD AASHTO Density

A7.2 G6 material for embankment wall, imported material and m³ 450 55.00 24,750.00
compacted to 95% MOD AASHTO Density

8.3.9 A8 TOPSOILING

A8.1 (a) Topsoiling m² 430 55.00 23,650.00

TOTAL SECTION (A) SABS1200 DE CARRIED TO SUMMARY 367,575.00

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2/96

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION

PART 4: OXIDATION PONDS SABS 1200 G

PAY ITEM
REFERS ITEM NO DESCRIPTION UNIT QUANTITY RATE (N$) AMOUNT (N$)
TO

SABS SECTION B: CONCRETE STRUCTURAL


1200 G
8.4.3 B1. Strength concrete, 30 MPa mm in:
B1.1 Spillway m³ 4 1,800.00 7,200.00

8.4.4 B1.1 Unformed surface finishes


B1.1.1 Steel Float Finish m² 35 67.50 2,362.50

SABS B2 SEWER INSTALLATION


1200LD

8.2.1 B2.1 110mm diameter uPVC pipelines m 20 110.00 2,200.00

8.2.7 B2.2 Encasing of Pipes in 15 MPa concrete m³ 2 1,200.00 2,400.00

B3 MISCELANEOUS ITEMS

B3.1 Supply & install razor fence wire as detailed on drawings m 280 30.76 8,612.80

B3.2 Supply, install & commission Index Testudo waterproofing m² 3,000 30.76 92,280.00
membrane as detailed on drawings (Installation by Specialist)

B3.3 Construction of inlet box with concrete manhole in accordance Sum 1 3,700.00 3,700.00
with the issued construction drawings, complete with inlet
screen, drio tray (stainless steel)-200 bar spacing

TOTAL SECTION (B) SABS 1200 G CARRIED FORWARD 118,755.30

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD


PART 2 /97

EMPLOYER: KAVANGO WEST REGIONAL COUNCIL PROCUREMENT REFERENCE NO.:


W/ONB/KWRC-07/2020
PROJECT: THE CONSTRUCTION OF MUNICIPAL
INFRASTRUCTURE (OXIDATION POND, SEWER
RISING MAIN, WATER RETICULATION) AT
KATWITWI EXTENSION 1, KAVANGO WEST REGION SUMMARY OF SCHEDULES

PART SABS REFERENCE DESCRIPTION AMOUNT (N$)

PART 1: PRELIMINARY & GENERAL OBLIGATIONS

PART 1 - SECTION (A) SABS 1200 A PRELIMINARY & GENERAL 187,298.20

TOTAL FROM THE SCHEDULE OF QUANTITIES (PART 1)

PART 2: WATER RETICULATION INFRASTRUCTURE

PART 2 - SECTION (A) SABS 1200 C SITE CLEARANCE 51,100.00


PART 2 - SECTION (B) SABS 1200 DB EARTHWORKS (RISING MAIN PIPE TRENCHES) 128,580.00
PART 2 - SECTION (C) SABS 1200 LB BEDDING (RISING MAIN PIPE TRENCHES) 173,900.00
PART 2 - SECTION (D) SABS 1200 LD MEDIUM PRESSURE PIPELINES 208,905.00
PART 2 - SECTION (E) SABS 1200 LF ERF CONNECTIONS (WATER) 105,500.00

TOTAL FROM THE SCHEDULE OF QUANTITIES (PART 2)

PART 3: SEWER RISING MAIN INFRASTRUCTURE

PART 3 - SECTION (A) SABS 1200 C SITE CLEARANCE 64,050.00


PART 3 - SECTION (B) SABS 1200 DB EARTHWORKS (RISING MAIN PIPE TRENCHES) 278,200.00
PART 3 - SECTION (C) SABS 1200 LB BEDDING (RISING MAIN PIPE TRENCHES) 305,700.00
PART 3 - SECTION (D) SABS 1200 L SEWER MAIN PIPELINE 308,580.00
PART 3 - SECTION (E) SABS 1200 GB CONCRETE WORKS - BUILDING MANHOLE 4,500.00

TOTAL FROM THE SCHEDULE OF QUANTITIES (PART 3)

PART 4: OXIDATION PONDS

PART 4 - SECTION (A) SABS 1200 DE SMALL EARTH DAMS 367,575.00


PART 4 - SECTION (B) SABS 1200 G CONCRETE STRUCTURAL 118,755.30

TOTAL FROM THE SCHEDULE OF QUANTITIES (PART 4)

SUMMARY OF SCHEDULES

PART 1: PRELIMINARY & GENERAL = A1 187,298.20

PART 2: WATER RETICULATION INFRASTRUCTURE = A2 667,985.00

PART 3: SEWER RISING MAIN INFRASTRUCTURE = A3 961,030.00

PART 4: OXIDATION PONDS = A4 486,330.30

TOTAL OF SCHEDULES (A1 + A2 + A3 + A4) = B 2,302,643.50

CONTINGENCIES (C = 10% of B)
230,264.35
The sum provided here is under the sole control of the Engineer and may be deducted in whole or in part (10%)

SUB-TOTAL (D = B + C) 2,532,907.85

(15% of D), VALUE ADDED TAX (VAT) 379,936.18

BID SUM CARRIED FORWARD TO BID OFFER, APPENDIX TO TENDER AND COVER PAGE 2,912,844.03

PREPARED BY DENCHI CONSULTING ENGINEERS (PTY) LTD