Principal : PT. AKR Corporindo, Tbk Vessel : SPOB. AKRA 70 Place/Port : Jetty PT. PKN, Site SMO Kind of cargo : Biosolar (B30) Case : DISCHARGING SUPERVISION
EVENTS DATE HOURS
Vessel's arrived at PT. PKN, Site KMO March 27, 2020 3:00 NOR Tendered - - NOR Accepted - - Free Pratique Granted - - Dropped anchor March 27, 2020 2:15 Anchor Up March 30, 2020 10:20 Pilot on board for berthing - - First line to shore / connected March 30, 2020 10:38 All fast at Jetty PT. PKN, Site SMO March 30, 2020 10:45 Surveyor on Board March 30, 2020 11:15 Key meeting held March 30, 2020 11:20 Initial survey completed (observation - sounding and calculation) March 30, 2020 12:00 - 13:00 Hose / Loading arm connected ( 1 x 3") March 30, 2020 11:30 Commenced discharge / taking ballast - - Completed discharge / taking ballast - - Commenced loading / discharge / bunker (BBC - 03) March 30, 2020 15:40 Initial sampling / one foot completed - - Completed loading / discharge / bunker (BBC - 03) March 31, 2020 0:00 Final sampling completed - - Final survey completed (observation - sounding and calculation) March 31, 2020 00:05 - 01:00 Hose / Loading arm disconneted March 31, 2020 0:30 Figure/Calculation ascertained March 31, 2020 1:30 Document completed March 16, 2020 2:00 Pilot on board for unberthing - - Vessel's unberthed Vessel's departed o o DESCRIPTION K/LITTERS OBS K/LITERS @ 15 C US BBLS @ 60 F METRIC TON LONG TON B/L Figure (T.54B) 400.000 394.344 - - - SFAL Figure (T.54B) 395.650 390.055 - - - Difference -4.350 -4.289 - - - Percentage (R1) -1.09 -1.09 - - -