The survey report summarizes the as-built column plumbness measurements for piers on the Abusag Bridge construction project in Baggao, Cagayan from February to August 2020. Fifteen piers were measured, with down and up readings in centimeters and any deviations from plumbness in millimeters noted. The survey was prepared by Manuel Mangaoang and checked by Junbert Oquindo.
The survey report summarizes the as-built column plumbness measurements for piers on the Abusag Bridge construction project in Baggao, Cagayan from February to August 2020. Fifteen piers were measured, with down and up readings in centimeters and any deviations from plumbness in millimeters noted. The survey was prepared by Manuel Mangaoang and checked by Junbert Oquindo.
The survey report summarizes the as-built column plumbness measurements for piers on the Abusag Bridge construction project in Baggao, Cagayan from February to August 2020. Fifteen piers were measured, with down and up readings in centimeters and any deviations from plumbness in millimeters noted. The survey was prepared by Manuel Mangaoang and checked by Junbert Oquindo.