The Human Resource Management Plan guarantees that the project has sufficient
human resources with the right skills and experience to ensure successful project
completion.
The Bike Route project requires forty-seven skillful individuals with thirteen
different roles. that They are categorized into three mainmain categoriesgroups: Project
Management (2 people), Code Developers (40 people), Functional Team (4 people),
and External Resources (1 person). The Project Manager has strictly defined the roles
and responsibilities as well as the skills that individuals should possess in order to
perform their work in the project.
The total human resources budget amounts to $6,636,800. 10% of it is spent in Initiation
and Planning phases, 10% in Control and Closeout, and 80% in the Execution.
The human resources budget amounts to $6,636,800, 10% of which goes into
Initiation & Planning, and another 10% into Control & Closeout. The remaining 80% is
allocated to the Execution phase.
The Resource Management Plan also contains the RACI Chart that shows the
relationship between the project's key main deliverables and the team members. . The
project total of 101 deliverables, out of which 37 are key. It assigns responsibilities and
ensures that tasks get done. The Project Mmanager and Project Sponsor will beare
accountable and responsible for the most of thevast majority of the project deliverables.
The Project Organization Chart illustrates the project team reporting relationships.
The Project Organization Chart is analogous to a functional hierarchical organization
structure.The role links provided here were used as an additional source to develop role
descriptions for project team members. The Project Sponsor is on the top of the
hierarchy, followed by the Project Manager. Others are split among the 11 departments
according to their functions.
The role links provided here were used as an additional source to develop role
descriptions for project team members. The Project Sponsor is responsible for overall
project success.
As anIn addition to the Resource Management Plan, the staffing Staffing plan Plan
provides a brief guidance on the f how resources will be acquihiring, red, utilizationed,
and trainedtraining of the employees, as well as and performance review tips how for
the Project Manager will review their performance.
1.1 Introduction
The Human Resources Management Plan provides an HR framework for the Bike
Route project. It contains the processes to identify, acquire, and manage the resources
needed for the successful closeout of the project. The HR management plan includes:
The Project Manager has clearly defined roles and responsibilities for the Bike
Route Project. Team members are required to know their R&R to prior to taking
perform their part in the project. The PM has determined, and Project Sponsor has
accepted approved the following roles and & responsibilities, and key deliverables for
the project team:
Table 1.1
The flowing chart is a graphical display of project team members and their reporting relationships.
Table 1.2
Project
Sponsor
Steering
Committee
Project
Manager
Subject
Matter Expert
Developers
Team #3
1.3 RACI Chart
The following RACI chart shows the relationship between the project's main deliverables and team members. Any
proposed changes to project duties must be reviewed and approved by the Project Sponsor. As changes are made, all
project records will be updated by the Project Manager.
Table 1.3
Risk Management
App Development
Staff Recruitment
User Agreement
Feasibility Study
Project Charter
Business Case
Marketing Plan
Map Collection
Staff Training
Archive Files
Update Files
App Testing
Project Sponsor A A A C C C A A A A A A A A A C I C I C A A I I I A A A A A A A A
Leadership
Advisory Commettee C C C C C I I C C C C C
Steering Committee C C C I I C C C C
Project Manager R R R R R R R R R R R R R R R A A A A A A A A A R R A A A R R R R R R R R
HoSD I C I R C I C C I I I C I
Project Team Members
Software Developers I C I R C I C C I I I C I
Head of QA I I R I C I I C I
Software Testers I I R I C I I C I
Graphic Designers I R R C I C I I C I
Database Administrator C R C I C I I C I
System Architects C R C I C I I C I
System Integrators I C R C I I I C I
Research Analyst I I R C
Functional Team
HR Specialist C R R R I C I C R R R I C I
Finance Officer C C C C C I I I I C I
Marketing Specialist R C I C I I C I
Legal Assistant C C C C C C I R I C R I I I C I
Subject Matter Expert E. C C C C C C C C C I C I I I
1.4 Staffing Plan
The purpose of the staffing plan is to make sure the project has sufficient staff with the right skills to ensure a
successful project closeout. It establishes a common understanding of how human resources will be acquired, utilized,
trained, and how the Project Manager will review their performance. The number of staff will remain the same during the
whole project, but the PM will shuffle their tasks according to their skills.
It The following table displays ais a detailedfull breakdown list of the project roles required to successfully complete
the projectfor successful project .completion.
Table 1.4
Role
Skills Required
Experience
Project Phase
# of Staff
Rate
Start Date
Total Working Hours
Total Wage
Project Manager
Project management skills, leadership skills, interpersonal skills, presentation skills.
5 years
All
1
$80
Apr-20
3,840
$307,200
Software Developers
Programming languages skills, software testing skills, release management skills.
2 years
Execution
25
$50
Jul-20
76,000
$4,180,000
Software Testers
Software testing skills, quality assurance skills.
3 years
Execution
3
$40
Jul-20
9,120
$364,800
Graphic Designers
Image editing, master of photoshoot, Illustrator & InDesign. beginner HTML skills, and UX design.
4 years
Execution
2
$40
Jul-20
6,080
$243,200
Role
Skills Required
Experience
Project Phase
# of Staff
Rate
Start Date
Total Working Hours
Total Wage
Database Administrator
The ability to prioritize tasks, keeping databases up to date, helping with database design, good organizational skills,
Problem-solving skills Familiar with computer operating systems and database technology
5 years
Execution
1
$55
Jul-20
3,040
$167,200
System Architects
Software engineering technical skills, software design skills
5 years
Execution
1
$70
Jul-20
3,040
$212,800
System Integrators
Performed training needs assessment for final preparation/system integration test. Conduct computer network operations,
installation, and reconfiguration of computer hardware and software phase and created documentation/presentation.
5 years
Execution
2
$60
Jul-20
6,080
$364,800
Role
Skills Required
Experience
Project Phase
# of Staff
Rate
Start Date
Total Working Hours
Total Wage
System Integrators
Performed training needs assessment for final preparation/system integration test. Conduct computer network operations,
installation, and reconfiguration of computer hardware and software phase and created documentation/presentation.
5 years
Execution
2
$60
Jul-20
6,080
$364,800
Research Analyst
Analytical skills, software documentation skills, negotiation skills, business processes understanding
1 year
Execution
6
$35
Jul-20
18,240
$638,400
HR Specialist
Excellent decision-making skills.
Critical thinking skills.
Strong computer skills.
Excellent written and verbal communication skills.
3 years
All
1
$35
Jun-20
480
$ 16,800
Role
Skills Required
Experience
Project Phase
# of Staff
Rate
Start Date
Total Working Hours
Total Wage
Finance Officer
A formal accounting qualification, interpersonal skills, ability to communicate, financial reporting, analytical ability,
knowledge of IT software.
5 years
All
1
$45
May-20
480
$21,600
Marketing Specialist
Good teamwork skills,
communication skills and networking ability
adaptability, strong attention to detail, good organization and planning skills,
creativity and writing skills,
commercial awareness,
IT skills.
3 years
All
1
$35
Jun-20
640
$22,400
Legal Assistant
Strong communication skills, people Skills, time management skills, research skills, detail oriented
5 years
All
1
$55
Apr-20
320
$17,600
Subject Matter Expert
Teamwork, communication, time management, problem-solving.
10 years
Planning, Execution
1
$250
Apr-20
320
$80,000
$ 6,636,800
1.4.2 Employment Rate
The following chart displays the project’s human resources employment rate by by
segment segment.
Table 1.5
120%
100%
80%
60%
40%
20%
0%
For the Bike Route Project, most ofall of the staff consists entirely of internal
resources, except for the Subject Matter Expert. There is no outsourcing/contracting
conducted within the scope of the project. The Project Manager works with the internal
HR specialist to hire and train new and existing project team members. The Project
Sponsor approves the staff roles and responsibilities before they resource may begin
any project work.
1.4.4 Workplace
The project team is located in the UnitedHealth Group’s headquarters. For each
team member the Project Sponsor has devotesd special workplace and equipment that
will be available as the project progresses.
1.4.5 Training
Every member of the team is skilled in the tools and programming languages that
that the Project Sponsor chose selected to for the develop the appapp development.
There is currently no training scheduled besides for the code developers. The code
developers will be trained in the first week of the project execution. They will become
accustomed to the UnitedHealth Group’s IT System Architecture. The training will last 4
days.
The project manager reviews the project team members’’s work activities at an
early stage of the project. He then evaluates each team member once a month. The
team members receive a final review from the Project Sponsor quarterly. The Project
Manager has budgeted $120,000 as bonus pay of the project employees.
Works Cited: