You are on page 1of 9

Pressure Monitoring using Hydraulic Cells 119

Suggested Methods for Pressure Monitoring


using Hydraulic Cells
SCOPE (b) Cells are typically either circular or rectangular in
plan with dimensions from 6-40 cm. The largest size
1. (a) The hydraulic pressure cell consists of a flatjack
compatible with the size and configuration of the
(fluid filled pressure pad) connected to a hydraulic or
measuring location should be selected to avoid errors
pneumatic diaphragm transducer which in turn is con-
due to edge effects1.. The flatjack may be fitted with
nected by flexible tubing to a read-out unit. Pressure
wires to assist in fixing it in position.
transferred from the surrounding soil, rock or concrete
(c) The stiffness (flexibility) of the flatjack should be
to the flatjack is measured by balancing the fluid pres-
similar to that of the material in which it is embedded,
sure in the cell by a pressure applied to the reverse side
of the transducer diaphragm. to ensure that stress is transferred to the jack without
arching effects, so that the measured pressure is closely
(b) The cell is intended as a means of measuring total
similar to that in the surrounding material. Thus, cells
pressure changes in soil, earth or rockfill, concrete, or
for installation in soil should be more flexible than
at the interface between any of these materials. It may
those for use in rock or concrete. For satisfactory per-
also be used to measure pressure changes in rock when
formance the gap between plates, controlling the
installed in a machined slot. Typical applications are in
earth or fill embankments, dams and dam foundations, volume of fluid and therefore the stiffness of the cell,
retaining walls, and behind or within tunnel linings. should not exceed 1 mm; also, the ratio of cell diameter
(c) Total pressure at a given location is defined as the (side length) to cell thickness should be greater than
20:1.
sum of effective soil or rock pressure and groundwater
or air pressure. If effective earth or rock pressure is to (d) The materials of the flatjack, transducer and all
be distinguished from water pressure, a piezometer ancillary components should be selected to resist cor-
should be installed alongside the pressure cell. Pressure rosion from the surrounding materials and ground-
change is defined as the difference between total pres- water, also these materials should be compatible with
sure at any given time and the total pressure value at the cell fluid and measuring fluid 2.
the time of cell installation. Measurements of absolute (e) The fluid filling the cell ('the cell fluid') should, to
pressure, the ground pressure before cell installation, ensure a suitable stiffness, be mercury if the cell is to be
can not be made using this cell. Such measurements installed in rock or concrete, but should be a less dense
require, for example, use of one of the ISRM Suggested fluid such as oil if the cell is to be installed in soil. The
Methods for Stress Determination. cell, connecting and compensating tubes and trans-
(d) The hydraulic transducer that forms a component ducer, should be completely filled with fluid, free from
of the total pressure cell may be used in other appli- air bubbles. The cell is usually filled under controlled
cations, for example to measure groundwater pressures factory conditions by the manufacturer.
or settlements. These alternative applications fall out- (f) The connecting tube from the flatjack to the trans-
side the scope of this Suggested Method. ducer may be either welded to the face of the cell or
welded to its flange. Connections to the cell and trans-
ducer must be strong enough to avoid damage resulting
APPARATUS in pinching or leakage during installation and oper-
ation. The connecting tube, typically of length 20-60
2. The hydraulic pressure cell (for example Fig. 1), mm, should be bent as required in the factory to ensure
should meet the following requirements:. no damage or kinking.
(a) The pressure sensor consists of a flatjack which is (g) The hydraulic or pneumatic transducer (for
fluid filled and connected by a steel tube to the pressure example Fig. 2) is a hydraulic valve consisting of a
measuring transducer and compensating tube if fitted. flexible steel, plastic or rubber diaphragm incorporated
The flatjack is typically manufactured from two flat in a metal housing. The diaphragm must completely
sheets of steel, welding around the periphery to form a separate the cell fluid from the measuring fluid under
leak-free container for the cell fluid. In some cell all operating conditions. One side of the diaphragm is
designs, a groove with a depth of about 1/3 of the plate connected to the cell fluid and the other to the measur-
thickness is cut along the edges of the flatjack to mini- ing fluid delivery and return tubes. The transducer
mize the edge effects during and after welding. design should be such that pressure in the cell fluid is
slightly greater than that in the measuring fluid in order
to prevent return flow of the measuring fluid. When
* Superscript numbers refer to Notes at the end of the text. the applied measuring pressure exceeds the cell fluid
120 International Society for Rock Mechanics

Cor~crele stress cell

Eorfh pressure celt

Fig. 1, Examples of alternative hydraulic pressure cell designs (Photos: Gloetzl, W. Germany).

pressure by more than an amount corresponding to throughout the working life of the cell. Corrosion or
diaphragm inertia the diaphragm will displace allowing components, changes in shape or flexibility of the dia-
flow along the measuring fluid return line. phragm during use will adversely affect the operating
(h) The design and materials of the transducer should characteristics of the transducer. The diaphragm inertia
be such as to ensure minimum diaphragm inertia so being the difference between the cell fluid pressure and
that the pressure in the measuring fluid corresponds the maximum measuring pressure required to open the
closely with that in the cell fluid at the time of measure- diaphragm, should not exceed 3", of the minimum
ment. This low inertia value should be maintained pressure that the cell is required to measure.
Pressure Monitoring using Hydraulic Cells 121

CONNECTION TO FLATJACK
use, and that the rate of flow and pressure drop along
¥ PRESSURE PAD
the tubing are such that measurements can be made
within the required accuracy limits. Lengths of tubing
may typically be from 10 to 500 m. The required inside
J TUBE
COMPENSATING
diameter of the tube is typically 2-5 mm depending on
CELLFLUID ,,,,, the viscosity of the fluid that is used. Manufacturers
advice should be sought in selecting appropriate tubing,
Y and if in doubt, trials should be carried out. The burst
I pressure of the tubing and fittings should usually be at
I
FLEXIBLE
t j DIAPHRAGM least 100~ above the maximum to be applied in use.
I
I (d) When several cells are to be installed these may
I • conveniently be connected to a valve-manifold terminal
I
unit fixed to the structure or in an instrument house.
I The terminal should be designed to ensure positive leak
I
free connection of the readout pump to each cell in

MEASURING FLUID
DELIVERY FROM
y- L RETURNTO
turn, and to prevent entry of air into the measuring
fuid delivery line. Quick connect couplings may be
used.
READOUT PUMP
READOUT PUMP 4. Installation equipment to facilitate placing, labelling
and filling of the ceils, tubing and terminals, including:
Fig. 2. Schematic drawing: hydraulic (pneumatic) diaphragm
transducer. (a) Equipment for preparing the cell location, embed-
ding the cell and fixing the cell as described under
(i) The transducer is generally embedded along with 'installation' Paras 9-12.
the flatjack in the surrounding soil or concrete and (b) Equipment for connecting and securing the
should be protected from malfunction due to pressure measuring fluid tubes and terminal units and for label-
transmitted from these materials, either by robust ling each tube with the cell designation.
design or by an applied coating of rubber or similar (c) Equipment to fill the delivery tubes with measur-
protective material. The transducer should be pos- ing fluid and to check for leaks in the hydraulic circuits.
itioned with respect to the flatjack at a location that In some cases the readout equipment may be used for
will not result in an unrepresentative or non-uniform this purpose 3.
transfer of pressure to the flatjack from the surrounding
material. 5. Readout equipment including a fluid reservoir; a
(j) When the cell is to be installed in or adjacent to pump with pressure gauge to measure the applied pres-
concrete where shrinkage may create a gap between the sure; and a detector to indicate the fluid return from
flatjack and the surroundings, it should be fitted with a the cell. The equipment is usually contained in a port-
'compensating tube' or similar means of augmenting able unit and may deliver air, nitrogen or oil pressure.
the cell fluid volume. The compensating tube may, for The readout equipment should meet the following re-
quirements:
example, consist of a metal tube filled with cell fluid
and connected to either the flatjack or transducer. This (a) The choice between cell fluids should be made to
tube may be crimped to inject further fluid into the cell suit project requirements. Gas pressure is convenient
as described in Para. 13(e). and clean but is generally only used at pressures below
3. Hydraulic connecting tubes, valves, couplings, 3 MPa. Liquid (generally a low viscosity liquid such as
terminal panels etc. to connect the readout pump unit a mixture of 90~o kerosene and 10% non-detergent oil)
to one or more cells, (for example Fig. 3). This equip- is usually employed for higher pressures and also for
ment should meet the following requirements: long delivery lines in order to avoid time lags due to
compressibility. Gas pressure is delivered from a com-
(a) One tube is required per cell for delivery of the pressed gas bottle with regulator valve. Liquid pressure
measuring fluid directly from the pump. There may be is delivered by either manual or electric pump.
one fluid return tube or the return tubes from several (b) The pump or gas pressure system should be cap-
cells may be coupled and connected by not less than 2 able of applying a pressure at least 20~o in excess of the
tubes to the readout location. maximum to be measured. It should be able to gradu-
(b) The tubes should be flexible to allow them to ally increase or decrease the applied pressure through-
travel along a convenient route to the readout. They out the measuring range and to hold this pressure
may, for example, be manufactured from plastic, steel steady for periods of at least several minutes.
or copper provided that they meet requirements listed (c) The retrun flow indicator system, whether visual
elsewhere in this Suggested Method. (liquid system) or mechanical (gas system) should be
(c) The length, inside and outside diameters and capable of detecting a return flow of less than 10~,,, of
material of the tubing should be selected to ensure that the maximum flow possible through the cell transducer
no blockages or leaks develop during installation or and tubing.
122 International Society for Rock Mechanics

Pressure cells
for contact and
circumferential stress

Shotcrete lining

nil

j Terminal panel

able hydraulic

INSTALLATION IN A TUNNEL LINING

I II I

/ /
Excavation 8m x 3m x lm deep ..=~/ " JSoil
/-- or rock fill

Pockets for pressure cells

INSTALLATION IN FILL

Fig. 3. Examplesof terminal connectionsfor hydraulicpressure ceils.

(d) The pressure gauge should have a range of (c) Before installation, the complete assembly should
110-150~o of the maximum to be measured, and a be checked to determine diaphragm inertia and the
measuring accuracy better than +27o of the measured effects of delay between pumping and fluid return.
pressure throughout this range. (d) The readout pressure gauge should be calibrated
at least before and after the project, for example using a
6. Calibration equipment should be available to ensure deadweight pressure tester.
that accuracy requirements are maintained throughout
the project, for example: 7. The overall accuracy requirements are to be speci-
(a) The flatjack design should be checked, for fied in accordance with requirements for the project.
example in a compression testing machine, to Generally, the overall accuracy of measurement should
determine edge effects and to evaluate the appropriate be better than _+5% of the pressure to be measured,
correction factor 1. this specification including the combined effects of inac-
(b) Calibration may be required to allow compensa- curacies due to lag, temperatures, tube pressure losses
tion for temparature effects at the cell location 4. and gauge calibration errors 5.
Pressure Monitoring using Hydraulic Cells 123

PROCEDURE Where tubes must necessarily cross each other they


should be separated by a minimum of 150mm of
8. Selection of locations granular material. The trench alignment and backfill
will, in the case of water retaining structures, require
(a) Cells are generally installed in pairs or clusters to
designing to prevent leakage and internal erosion.
measure pressure in different directions at the same
(f) The cluster excavation is then backfilled and
location. Adjacent cells should be separated by a dis-
compacted with natural embankment material having
tance of at least 1 cell diameter in such a way as to
removed rocks larger than the cell dimensions. Three
prevent the presence of a cell affecting readings on adja-
lifts of 10-20 cm each should first be placed and com-
cent cells. Typical layouts are shown in Fig. 3.
pacted by hand operated equipment before completing
(b) The location for the cell or cell cluster is
the backfill with light mechanical equipment. No heavy
determined depending on the specific objectives of the
vibratory rollers should be used until at least 2 m of fill
measurements, however each cell should be located in
has been so placed.
ground that is undisturbed (for example by blasting)
and that is typical of the surrounding materials. 10. Installation at the interface between soil and concrete
(c) The cell must be in uniform and complete contact or rock
with the surrounding material. Soil or rock adjacent to
(a) When placing cells adjacent to piers, piles, retain-
the cell should be free from protrusions or unrepresen-
ing walls, culverts and other structures, the cells may
tative material that would result in stress irregularities
either be attached to the formwork and placed in the
on the flatjack.
structure or fastened to the structure prior to backfill-
(d) Cells should preferably not be located where they
ing, or embedded in the backfill a short distance away
will be exposed to appreciable temperature changes, for
from the structure. The contact between the cell and the
example by the action of direct sunlight or cold winds
backfill material should be effected by means of a layer
on exposed surfaces. Insulation may be required in such
of fine grained material as previously described.
cases.
(b) The interface between the cell and the structure
should consist of a cement mortar or epoxy resin pad,
9. Installation in soils installed as described in Para. ll(c). The cell should be
(a) When installing cells in a natural soil or fill fixed securely to the structure ensuring that there are
embankment, an excavation is made to accommodate a no air spaces or hard particles or protrusions in contact
cell cluster, then individual pockets for each cell are with the cell.
hand dug at the correct locations with flat faces at the
required inclinations. The excavation as a whole should 11. Installation at the interface between concrete (or
be stable with side slopes as necessary, and of dimen- shotcrete) and rock
sions not less than 4 x 4 x 2 metres deep. The cell (a) The area of rock or concrete over which the cell is
pockets should be excavated with extreme care to avoid to be placed should be prepared fiat +_ 10 mm. Loose
disturbance to the soil, each being of size approxi- material should be removed. The area should be pre-
mately twice that of the cell. coated with a 15 mm thick layer of cement mortar. The
(b) Rock fragments of size greater than 1/10 the cell cell should be cleaned of grease and any aluminium
diameter, except in cases where the embankment is of paint and dipped in cement mortar 6.
rock fill, should be removed and replaced by fine grained (b) The positions of the transducer and compensating
material, generally hand compacted into the voids. A tube should be checked ensuring that the compensating
bed of fine grained material is placed and compacted to tube, which is essential when installing in or adjacent to
separate the cell from any irregularities in the pocket concrete, is accessible after placing of the shotcrete or
walls. The cell is then fixed in position taking care that concrete.
it is fully in contact with the underlying material, and (c) A pad of cement mortar (for example 1:2
checking to make sure it is functioning correctly. cement:sand, 4 second flow cone reading) is trowelled
(c) Each pocket is then backfilled with fine grained onto the rock or concrete surface and the cell is placed
material, hand compacted to a density similar to that of against the pad squeezing out mortar until a layer no
the surrounding soil. more than 5-10 mm thick remains beneath the flatjack.
(d) When the embankment is of coarse grained Entrapment of air bubbles must be avoided. The cell is
material such as rock fill, the pockets should be larger secured in position either by tying to pins in the rock or
and the pocket backfill should be graded with coarse concrete, or by securing it to nearby reinforcement. The
material adjacent to the embankment and finer mater- fixings must be such that the cell remains in place dur-
ial adjacent to the cell. ing concreting or shotcreting operations.
(e) The measuring fluid tubing is carefully identified (d) The tubing is led along the wall of the structure or
and labelled, and carried to the readout location in a excavation to the terminal unit, is labelled, and is fixed
trench. The tubing should be snaked along the trench securely to the reinforcement or to pins in the rock or
to allow for embankment movements and should be concrete. If the tubing is to be embedded in concrete or
protected above and below with fine grained material shotcrete it must be secured at intervals not exceeding
in order to prevent damage by compaction equipment. 3 m along its length. Kinks and constrictions in the
124 International Society for Rock Mechanics

tubing must be avoided. Tubing that is not to be readings. This pressure should not exceed 5°,; of the
protected by embedment in concrete must be protected maximum anticipated at the location of measurement.
by other means, for example by metal conduit.
(e) The correct functioning of each cell is to be 14. Procedure for taking readings
checked and any leaks repaired before concrete or shot- (a) The readout equipment should be calibrated at
crete is placed. least before and after the project and should be checked
before and after each set of readings. Any malfunctions
12. Installation in concrete should be corrected at once.
(b) The readout unit is connected to the cell delivery
(a) The cell is fixed to the reinforcement or the struc-
and return tubes, taking care to avoid entrapment of air
ture. Its positioning should be such as to ensure an all
in the delivery tube.
round cover of concrete, Entrapment of air must be
avoided. (c) The supply pressure is increased gradually until a
return flow is recorded. The return flow should be
(b) Cell alignment should be within _+ 10° of that
maintained for a period of at least 4min to ensure
specified by the client. Cells must be fixed securely to
removal of air bubbles (liquid system) and to establish
ensure that alignment is maintained during pouring of
steady conditions. An approximate reading of the deli-
concrete.
very pressure is then noted.
(c) For measurement in concrete containing large size
(d) The pressure is released and again increased at a
aggregate (for example > 30 mm) it is advisable where
very slow and constant rate (usually 3 4 cm3/min) until
possible to surround the cell in a special concrete mix
return flow is observed. The 'bypass pressure' is noted,
from which the coarser aggregate particles have been
being the minimum pressure at which, under conditions
removed.
of minimum flow, a steady return flow is achieved.
(d) All other aspects of installation should follow the
There is usually a characteristic peak in the pressure-
specifications in Para. 11 above 6.
flow curve, due to inertia of the diaphragm valve. This
should be ignored, and the steady pressure taken as the
13. Connecting,.filling and checking the cells reading (Fig. 4).
(a) The terminal equipment is fixed securely in place, (e) Further readings are taken and recorded until a
either near to the cells for example as a wall fixture, or consistent reading Pr is established. At any one measur-
remote from them for example in an instrument house. ing time there should be a minimum of three readings.
Terminal panels should be prechecked to ensure that (f) Special procedures may be used to obtain an ap-
the valves function correctly and that the system is free proximate reading when leakage or partial blockage
from leakage. The cell designations should be clearly develops in the tubing 7. The requirement for such pro-
and permanently labelled. cedures should be noted in the report.
(b) The labelled tubing is connected to the appro- (g) Delivery line pressures should preferably be main-
priate terminals and is secured in place. A test should tained between readings, at a level that will avoid entry
be made on each cell while still accessible for repair and of air, yet well below the long term burst pressure of the
replacement, to ensure that the completed hydraulic tubing.
circuit is functioning correctly. (h) The reading procedure is then repeated for all
(c) The cells, where liquid is to be used as a measur- other cells at which readings are required.
ing fluid, may be filled by the readout unit pump but (i) The frequency of readings should be specified
usually it is more convenient to arrange for gravity depending on requirements for the project, and
feeding from a fluid reservoir. The method of filling should preferably be adjusted from time to time
should be such as to ensure that the delivery tubes are depending for example on the recorded rate of pressure
completely filled. Bleed points should be provided at change.
positions where air entrapment is likely. (j) The field results should be recorded on a data
(d) A check should be made along the complete tube sheet similar to that shown in Fig. 5, designed to facili-
length for leaks, and to ensure that all tubing and cells tate comparison of one set of readings with preceeding
are adequately supported, free from damage, and pro- sets.
tected, Each tube should be temporarily disconnected
from the cell and the complete system tested to a pres- CALCULATIONS
sure of at least 120~o the maximum anticipated in use.
(e) After completion of the installation and backfill- 15. (a) The cell pressure P is obtained from the reading
ing, the pressure in the cells should again be measured Pr by making corrections as follows:
and recorded. Cells in concrete are then backpressured, P=(Pr- Pi- Ph- Pf) x E
after a period usually of two to three days to allow for
concrete shrinkage and dissipation of initial heat of set- where
ting, to ensure that a small positive reading is obtained. Pr is the pressure reading
This may be achieved for example, by crimping the Pi is the initial cell pressure applied during manu-
tube or by an injection pump. The pressure after com- facture and (in concrete) subsequently adjusted by
pensation is taken as a reference level for all subsequent compensation for shrinkage.
Pressure Monitoring using Hydraulic Cells 125
II
Return
Flow
L
3i 4 cm3/min

'__ P:el:minjeFYOIP,r/~b~lre:arian Second pressurizationto take readings

Pressure

t oro
°0 4 mm
Time
Fig. 4. Pumping sequence for readings (See Para. 14).

FIELD DATA: HYDRAULIC PRESSURE CELLS

SITE LOCATION VILLESTE MARIE TUNNEL STATION # 14

DATE INSTALLED 28 Dec 1977 STATION LOCATION 6+42

DATE TIME TEMP :ell # READINGS CkPa) REMARKS


1978 °C 1 2 3 4 5 6 7 8 9
3Jan 2210 12 0 0 0 0 0 0 0 0 0 Pressure compensation
10 Jan 1750 13 6 35 75 84 I l l 84 1 2 2
5 Jan 1730 9 II 72 198 136 191 293 9 3
l Feb 0835 15 15 91 253 193 235 354 16 4
5 Feb 0915 17 17 los 316 215 zsz 402 21 5 4
l Mar 2350 19 20 128 335 235 273 460 28 5 6 Supplementary bolts
15 Mar 2100 19 23 151 342 240 281 481 35 8
3 Apr 1230 21 25 164 353 246 289 502 45 II lO
l May 2100 19 27 175 362 251 294 520 53 15 I15 Inner l i n e r placed
0 Jun 1835 23 29 184 368 255 298 541 58 18 19
30 Jul 2200 21 30 190 370 260 300 560 60 20 20
Pressure
(kPo)
6OO I I I 1 I ,, I

Cell ~ 6
500
o / ~ o ~ ' ~ •

400

/ Cell #: 5
300
/ .j._ . . . . . . . --e

200- #~,/~....~,~o-- Cell#= 4

I00-

i • , |

Jan Feb Mar Apr May Jun Jul


1978
Fig. 5. Example, presentation of pressure cell results.
126 International Society for Rock Mechanics

Ph is the static head correction for the pressure should be investigated at the start of the project and
due to difference in elevation between the cell and reported, whether or not they are found to be signifi-
readout (liquid only; for gas, Ph = 0). cant.
Pf is a correction for friction losses in the fluid (h) The corrected values of cell pressure P should be
delivery line tabulated and plotted graphically to show fluctuations
E is a multiplicatiOn factor (less than 1.0) to com- of pressure as a function of time after installation.
pensate for cell edge effects.
(b) In most applications only changes in pressure are REPORTING OF RESULTS
of interest. In these cases an initial reading Pi is taken
after completion of installation and includes the effects 16. Results should, unless otherwise specified, be pre-
Ph and Pf which remain constant throughout the pro- sented in two forms of report: an Installation Report
ject. In these cases: giving basic data on the instrumentation system at the
time of installation; followed by Monitoring Reports
P=(Pr-Pi) x E presenting periodically the results of routine obser-
It should be noted however, that the minimum pressure vations. The Monitoring Reports will generally be
change that can be recorded using this cell is required at frequent intervals to minimise delay
(Pi + Ph + Pf), so that if small pressure values are to between the detection of adverse behaviour and the
be measured a gas is preferred as the measuring fluid. implementation of any remedial measures that may be
necessary.
(c) The elevation correction Ph may be calculated as
follows: 17. The Installation Report should include the follow-
ing:
Ph = 7(hl - hz)
where (a) A description and diagrams of the monitoring
= unit weight of measuring fluid, g/cm z (for gas equipment used including detailed performance specifi-
cations and manufacturers literature.
this unit weight is zero)
(b) Details of methods used for installation, calibra-
h i - h2 = difference in elevation (cm) between
ting and monitoring; reference may be made to this
readout and cell (positive when the cell is below
the readout) ISRM Suggested Method stating only the departures
from the recommended procedures.
Ph is then obtained in g/cm 2 and should be con-
(c) A location plan showing details of the pressure
verted to kPa by multiplying by 0.0981.
cell locations with respect to the structural configur-
(d) The tube friction correction Pf should be ation and the surrounding soil, rock or concrete condi-
measured during installation, before connecting the cell, tions.
being the pressure required to maintain a steady flow (d) For each cell, a report giving the initial installa-
through the tubing at a flow rate similar to that tion pressure and, if applicable, the pressure after com-
obtained during measurement. Under normal condi- pensation for shrinkage. Details of calibrations and
tions, with unobstructed and correctly selected tubing, determinations of correction factors should be included,
this correction should be small. along with any pertinent comments on the peculiarities
(e) The edge effect correction E should be established or problems encountered during installation of each
by the manufacturer on the basis of control tests in a cell.
compression machine. For this purpose, a representa-
18. The Monitoring Reports should include the follow-
tive cell should be cast in a concrete block of at least 3
ing:
times the cell dimensions. The correction is usually only
significant for cells of small size. (a) An updated field data sheet and results graphs
(f) In addition, a temperature correction may be similar to those shown in Fig. 5.
required in some specialized applications such as for (b) A brief commentary drawing attention to signifi-
cells in mass concrete 4. The correction Pt to be sub- cant pressure changes and to all instrument malfunc-
tracted from the reading may be expressed as: tions occurring since the preceding report.
(c) The results of any calibrations or instrument
Pt = Kt(tr - ti)
checks carried out since the preceding report.
where
(tr-ti) is the temperature increase (°C) from the NOTES
time of the initial reading Pi; and Kt is a coeffi-
1. Edge effects occur due to the presence of the weld
cient expressing the response of the system (cell,
around the circumference of the flatjack. They are
fluid and surrounding material) to temperature.
greatest when the jack is small and rigidly constructed.
Experimentally, Kt has been found to lie in the range The thickness of flange around the cell circumference is
2(~50 kPa/< C for cells installed in concrete. The actual also critical, since this flange may partially prevent
value will depend on the size of cell. transfer of stresses to the cell from the surrounding
(g) The magnitude and importance of the above cor- material. Edge effects are difficult to determine but may
rections, which in many cases will prove negligible, be estimated experimentally by embedding the cell in a
Pressure Monitoring using Hydraulic Cells 127

large concrete block which is then subjected to uniaxial can continue to be taken provided that these problems
compressive stress under controlled laboratory condi- are not too serious, by careful control of the applied
tions. flow rate and provided that the results are carefully
2. Mercury that is used to fill cells for use in rock or examined and interpreted. If such problems develop,
in concrete can corrode metals. Cells containing mer- the pump unit itself should first be checked. The possi-
cury are general)y constructed from stainless steel, bility of blockage or leakage is the principal reason why
whereas oil-filled cells may be constructed from mild this specification calls for individual delivery lines to
steel, copper or similar materials. each cell, so that if one tube is affected others are not.
3. The cells may be filled by hand pump when the
length of delivery tube and the volume of the cell are
comparatively small. Otherwise, it is more convenient REFERENCES
to fill the cell by gravity feed using a reservoir and
Agarwal S. L. and Venkatesan S. An instrument to measure skin
manifold system designed for the purpose. friction and normal earth pressure on deep foundations. Am. Soc.
4. Probably the most reliable method for temperature Test. Mats., STP392, (1965).
correction is to incorporate in the structure to be moni- Arthur J. R. F. and Roscoe K. H. An earth pressure cell for the
measurement of normal and shear stresses. Cir. Engng pub. Wks
tored a special additional cell that is subjected to the Rev. No. 659 (1961).
ambient temperatures at that location but not to the Brown S. F. The performance of earth pressure cells for use in road
pressure. An apparent pressure increase in this control research. Cir. Engng publ. Wks Rev. 66, 160-165 (1971).
Escario V. and Sagaseta C. Lateral forces on an experimental section
cell, due to temperature increase, may then be sub- of the Madrid subway. Proc. 5th European Conf. Soil Mech.
tracted from the pressure reading in adjacent cells that Found. Engng. Vol. 1, Madrid (1972).
have been installed so as to be subjected to pressure Franz G. Umnittelbare Spannungsmessung in Beton und Baugrund,
Der Bauingenieur, Heft 5 (1958).
from the surrounding structure. This precaution will Habib P. and Marchand R. Mesures des pressions de terrains par
rarely be necessary since in most circumstances the l'essai de verin plat. Ann, I.T.B.T.P., No. 58, Paris (1952).
temperature correction may be shown as insignificant. Hamilton J. J. Earth pressure cells, design, calibration and perform-
ance. NRC., Div. of Bldg. Res. Tech. P. No. 109, Ottawa (1960).
5. Various additional and largely unknown sources of Kallstenius T. and Bergau W. Investigations of soil pressure measur-
error may exist, for example due to inadequate match- ing by means of cells. Royal Swedish Geotechnical Inst., Proc.
ing of the cell and surrounding material stiffnesses; due No. 12, Stockholm (1956).
Kruse G. H. Measurement of embankment stresses on a hundred-
to placing of the cell at an unrepresentative location in foot-high retaining wall. Instruments and apparatus for soil and
the structure; or due to use of an inappropriate size of rock mechanics. A.S.T.M. Stand. 392, 131-142 (1965).
flatjack for the application. These sources of error can Levillain J. P. Mesure des pressions derribre et sous un tour de soute-
nement, Rapport de recherche No. 22, Lab. Cent. Ponts et
only by avoided by careful planning of the instrumenta- Chaussees, Paris (1973).
tion program before the start of the project. Massarsch R. New method for measurement of lateral earth pressure
6. Aluminium reacts with portland cement to form a in cohesive soils. Can. Geotech. J. 12, (1975).
Panek L. A. Measurement of rock pressure with an hydraulic cell.
gas, so that pressure cells to be installed in concrete Proc. A.I.M.E. Meeting St. Louis, TP61 (1961).
should not include aluminium components. In some Peattie. K. R. and Sparrow R. W. The fundamental action of earth
cases, the cells supplied by the manufacturer are pro- pressure cells, Conj. on Earth Pressure Problems (1958).
Sauer G. and Jonuscheit P. Kdifteumlagerungen in der Zwischen-
tected against corrosion by aluminium paint which
wand eines DoppelrShrentunnels im Zuge eines Synchronovor-
should be removed before installation in concrete to triebes. Rock Mech. H.7/3 (1975).
avoid accumulation of gas in the vicinity of the cell Sauer G. and Sharma B. A system for stress measurement in con-
structions in rock. Field Measurements--Rock Mechanics; Proc.
which could seriously affect the pressure measurements. Int. Syrup. 1, 317 329.
7. Pressure cell fluid delivery tubes may develop leak- Schober W. Large scale application of Gl6tzl type hydraulic stress
age or partial blockage in the course of the project, due cells at the Gepatsch rockfill dam Austria. Baumess Technick,
Bericht 1, (1965).
to excessive ground movements. A leakage will be de-
Thomas H. S. H. and Ward W. H. The design, construction and
tectable at the readout unit, generally as a failure to performance of a vibrating wire earth pressure cell. Geotechnique
maintain a steady pressure after opening of the dia- 19, 39-51 (1969).
phragm valve. A blockage will be detected at the pump Trollope D. H. and Currie D. T. Small embedded earth pressure
cells--their design and calibration. Third Australia-New Zealand
as a decrease in return flow rate. Generally, readings Conference on Soil Mechanics and Foundation Engineerin 9 (1959).

You might also like