TELANGANA STATE POWER GENERATION CORPORATION LIMITED
KOTHAGUDEM THERMAL POWER STATION - V & VI STAGES, PALONCHA
Ojo. The Chief Engineer,
Operation & Maintenance,
KTPS V& VI Stages, Paloncha.
Cir. Memo No. CE/O&M/KTPS V&VI/ DE/E&P/V&VI/F.No.cir. /D. No 44/20, Dt.2-9.09.2020
Sul
KTPS V&VI Stages ~ Fulfilment of X2 Criteria for opening ESVs during absolute cold
start-ups - OEM recommended procedure for pre warming control valves - Certain
instructions ~ Issued - Regarding.
It is noted by the undersigned that unwarranted delay is being caused for fulfilment
of X2-Criteria for opening ESVs (Curve between Main steam saturation temperature and
HP control valve midwall temperature) during absolute cold startups i., HP casing
temperatures ~ 50°C
In this regard, certain recommendations proposed for fulfilment of X2 criteria during cold
startups by Original Equipment Manufacturer (OEM) ie., M/s.BHEL elaborating the
procedure to be adopted for pre warming control values vide No.
HIA/STE/SM/8300/Technical Circular No.X-133 dated 09.09.2013 is enclosed for ready
reference.
The Superintending Engineer/O&M/KTPS V_ Stage and The Superintending
Engineer/O&MKTPS/VI Stage are directed to issue necessary instructions to the
concerned Maintenance and Shift Engineers in this matter of concern so as to minimize
startup time and oil consumption during cold start-ups.
These instructions shall be followed scrupulously.
Encl: No, HW/STE/SM/8300/Technical Circular No.X-133 [2 8-2
CHIEF ENGINEER
O&M/KTPS V & VI STAGES
To
The Superintending Engineer/O&M/KTPS-V Stage.
The Superintending Engineer/O&M/KTPS- VI Stage
Copy communicated to Chief Engineer/Generation/TSGENCO/Vidyut Soudha/Hyderabad,
Copy to DE/Technical to the Director/Thermal/TSGENCO/Vidyut Soudha/Hyderabad.