Professional Documents
Culture Documents
73-1 of 73-91
SECTION 73
BLDG19/S73.DOCX(1)
Sal(150319)
(DPG)
BSS S73
73-2 of 73-91
For the avoidance of doubt, in addition to paying the rates specified above,
all other costs and expenses for such tests shall also be borne by the
Contractor.
Any material test that fails shall be considered not to have fulfilled the
requirements under the Schedule of Material Tests. In that event, the SO
Rep may, without prejudice to his other rights under the Contract, order
such further test as he deems necessary, all at the cost and expense of
the Contractor. The Contractor shall bear the cost and expense for all
failed tests.
The SO Rep may also order additional material tests over and above
those specified in the Schedule of Material Tests. The cost and expense
for carrying out such additional material tests shall be borne by the
Employer, provided that such tests pass the requirements stipulated under
the Contract. The Contractor shall bear the cost and expense of any
additional test that fails.
In the event any test listed in the Schedule of Material Tests is not carried
out, there shall be no cost recovery from the Contractor.
BLDG19/S73.DOCX(2)
Sal(150319)
(DPG)
BSS S73
73-3 of 73-91
The Contractor shall submit all test reports to the SO Rep expeditiously. In
the event that the Contractor fails to provide the requisite test reports to
the SO Rep, the SO Rep shall be empowered to obtain the said test
reports from the laboratories direct. In such event, all costs and expenses
incurred shall be deducted from any monies due or becoming due to the
Contractor or be recovered from the Contractor as a debt due by the
Contractor to the Employer.
BLDG19/S73.DOCX(3)
Sal(150319)
(DPG)
BSS S73
73-4 of 73-91
5 Metal props of frames Load test to SS 280 1 test per type. 1 sample per
test.
BLDG19/S73.DOCX(4)
Sal(150319)
(DPG)
BSS S73
73-5 of 73-91
8 100 mm cube mould Dimensional tolerance 1 test per source. 1 sample per
test.
BLDG19/S73.DOCX(5)
Sal(150319)
(DPG)
BSS S73
73-6 of 73-91
10 Steel reinforcement of a) Steel reinforcement bar: ) 3 tests per source. ) 3 pieces per
diameter 8 mm & i) Tensile test ) ) size per test.
above ii) Bend test ) )
iii) Re-bend test
11 Load bearing grout Compression 3 tests per grade per 1 concrete cube
and load bearing casting day. per test.
mortar
12 Prestressing steel Yield & Tensile 1 test per source. 3 samples per
size per test.
13 For household
shelters, the following
shall be tested:
BLDG19/S73.DOCX(6)
Sal(150319)
(DPG)
BSS S73
73-7 of 73-91
15 Precast lightweight
concrete partition
panel
17 Flexible Loop Shear Test 2 tests per contract 4 joints per test
Connector (Façade) (HDB in-house test
method)
18 Grout for spiral Compression 1 test per casting day 3 cubes per test
connector / Grout for per building block
splice sleeve
20 Showerhead Nickel and chromium 2 tests per contract 1 piece per test
(handset) and sliding plating
bar
BLDG19/S73.DOCX(7)
Sal(150319)
(DPG)
BSS S73
73-8 of 73-91
BLDG19/S73.DOCX(8)
Sal(150319)
(DPG)
BSS S73
73-9 of 73-91
b) Tensile Adhesion ) )
strength tests ) 1 test. ) 1 sample.
) )
c) Average Shrinkage ) )
b) Tensile Adhesion ) )
strength tests ) 1 test. ) 1 sample.
) )
c) Average Shrinkage ) )
BLDG19/S73.DOCX(9)
Sal(150319)
(DPG)
BSS S73
73-10 of 73-91
BLDG19/S73.DOCX(10)
Sal(150319)
(DPG)
BSS S73
73-11 of 73-91
BLDG19/S73.DOCX(11)
Sal(150319)
(DPG)
BSS S73
73-12 of 73-91
BLDG19/S73.DOCX(12)
Sal(150319)
(DPG)
BSS S73
73-13 of 73-91
BLDG19/S73.DOCX(13)
Sal(150319)
(DPG)
BSS S73
73-14 of 73-91
54 Cement
(Contractor source)
55 Coarse Aggregate
(D/d > 2 and D > 11.2
mm); where D=20 and
d=4) In accordance with HDB Standard Specification For Building Works And
Other Installations
(Contractor source)
56 Fine Aggregate
(D≤4mm and d=0;
where D=4)
(Contractor source)
BLDG19/S73.DOCX(14)
Sal(150319)
(DPG)
BSS S73
73-15 of 73-91
62 Wall tiling work Tensile pull-out test Up to 20 storeys: 3 tests 5 samples per
(Within flats) per building block test
Up to 30 storeys: 4 tests
per building block
Up to 40 storeys: 5 tests
per building block
Above 40 storeys: 6
tests per building block
Up to 20 storeys: 3 tests
64 per building block
Up to 30 storeys: 4 tests
per building block
Floor tiling work Up to 40 storeys: 5 tests
Tensile pull-out test 5 samples per
(Within Flats) per building block
test
Above 40 storeys: 6
tests
per building block
BLDG19/S73.DOCX(15)
Sal(150319)
(DPG)
BSS S73
73-16 of 73-91
66 Anchor Bolts Ultimate Tensile & Shear 1 tensile test and 1 5 samples per
Test shear test per contract test
3
67 Grout Mix for Micro Compression 1 test for every 3 m of 4 cubes per test
Piles grout (7-days & 28-
days strength)
68 Basin Mixer and a) Coating thickness 2 tests per contract 1 piece per test
Shower Mixer b) Mechanical Endurance
70 Approved Soil Mixture a) Analysis for pH, EC, N, a) 1 per 500 m² subject a) 1 bag of 500g
(ASM) P, K, Ca, Mg, Na, Cu, to a minimum of 3 of composite
Fe, Mn, Zn, Organic samples soil mixture
Carbon/Total comprising 5
Carbon/Organic Matter, sub-samples
CEC, C:N Ratio and from the root
Moisture Content by zone at depth
AVA’s Plant Health of about 15 to
Laboratory Service, or 20 cm.
equivalent lab subject
to SO Rep’s approval
BLDG19/S73.DOCX(16)
Sal(150319)
(DPG)
BSS S73
73-17 of 73-91
71 Organic Mulch / Analysis for pH, EC, N, P, ) 1 for every 100 trees ) 1 bag of 500g
Compost K, Ca, Mg, Na, Cu, Fe, ) with mulching and ) in a sealed
Mn, Zn, Organic ) repeat for each new ) polythene bag.
Carbon/Organic Matter, ) batch and each type
CEC, C:N Ratio and ) of mulch
Moisture Content by AVA’s
Plant Health Laboratory
Service, or equivalent lab
subject to SO Rep’s
approval
)
73 Aluminium Bi-Fold a) Durometer Hardness
)
Door b) Vicat Softening
)
temperature
) 1 test
c) Density/Specify Gravity
)
d) Water absorption
)
(After 2 hours and after
)
24 hours)
)
e) Endurance of lockset
)
74 Paint on staircase Adhesion (ASTM D3359) 1 test per block 2 locations per
nosing test and 3 points
per location
BLDG19/S73.DOCX(17)
Sal(150319)
(DPG)
BSS S73
73-18 of 73-91
TYPE OF NO. OF
TYPE OF TEST TO BE FREQUENCY OF TEST
S/N MATERIAL SAMPLES
CARRIED OUT FOR EACH TYPE OF TEST
TO BE TESTED PER TEST
2
79 Interlocking a) Compressive strength a) 1 test for each 550 m of 16
concrete paving interlocking concrete
blocks pavement.
BLDG19/S73.DOCX(18)
Sal(150319)
(DPG)
BSS S73
73-19 of 73-91
TYPE OF NO. OF
TYPE OF TEST TO BE FREQUENCY OF TEST
S/N MATERIAL SAMPLES
CARRIED OUT FOR EACH TYPE OF TEST
TO BE TESTED PER TEST
2
81 Clay pavers for a) Mean Transverse a) 1 test for each 200 m of 10
flexible pavement Breaking Load Test clay pavers pavement.
(Type PB)
2
b) Mean Wet Skid b) 1 test for each 200 m of 5
Resistance clay pavers pavement.
84 Final testing of Water absorption test 1 test for every 120 m length
kerbs. subject to a minimum of
2 tests.
2
85 Final testing of Grading analysis, 1 test for every 550 m of
premix. thickness and bitumen carpark and 1 test for every 450
2
content m of service road/driveway
subject to a minimum of 2 tests.
2
86 Final testing of Water absorption test 1 sample for every 350 m
precast footpath subject to a minimum of 2 tests.
slabs.
2
b) In Situ Field Density b) 1 test for every 300m of
Test surface of each compacted
layer.
BLDG19/S73.DOCX(19)
Sal(150319)
(DPG)
BSS S73
73-20 of 73-91
Clause
and/or
Works/Materials To Be Warranted Format
Subclause
No.
3.16.12 Pre-Treatment Of Soil For Protection
Appendix A1 and/or
Of Buildings Against Subterranean
Appendix A1(TC)
Termites
23.2.2(e) External Painting Works Appendix A5 and/or
Appendix A5(TC)
* Cast-In-Situ EPDM Rubber Flooring Appendix A6 and/or
25.8.6
For Children's Playground Appendix A6(TC)
Appendix A7 and/or
38.22.2 * Rainwater Harvesting System
Appendix A7(TC)
Light Emitting Diodes (Led) Appendix A8 and/or
54.15.7
Luminaires Appendix A8(TC)
* Power Consumption and Fault Appendix A9 and/or
50.11.2
Detection Monitoring System Appendix A9(TC)
Appendix B2 and/or
**74.1.14 * Tensile Fabric Structures
Appendix B2(TC)
Complete Waterproofing Membrane
Appendix B3 and/or
74.2.7 System for MSCP Roof Decks & Other
Appendix B3(TC)
Specified Areas
* Prefabricated Extensive Green (PEG) Appendix B4 and/or
**74.3.13
Roof System Appendix B4(TC)
Appendix A2 and/or
73.14 Ceiling Leak and External Seepage
Appendix A2(TC)
74.
75.
75.
BLDG19/S73.DOCX(20)
Sal(150319)
(DPG)
BSS S73
73-21 of 73-91
In the event that the country of origin deviates from the approved
original, equivalent or alternative tile, the SO’s rep shall reserve the
right to instruct Contractor to remove and replace the tiles.
BLDG19/S73.DOCX(21)
Sal(150319)
(DPG)
BSS S73
73-22 of 73-91
The polished porcelain tile shall be rectified with the edges trimmed to
achieve precise dimension for its length and width. The polished porcelain
tiles shall not be made of red clay. Dimensional and surface quality
requirements and physical and chemical properties shall be in accordance
with the latest ISO 13006 (Annex G) unless otherwise specified:
(a) Dimensions
The dimensions shall be as follows :
Nominal Length : 600 mm
Nominal Width : 600 mm
Nominal Thickness : 10 mm
BLDG19/S73.DOCX(22)
Sal(150319)
(DPG)
BSS S73
73-23 of 73-91
(a) Dimensions
BLDG19/S73.DOCX(23)
Sal(150319)
(DPG)
BSS S73
73-24 of 73-91
BLDG19/S73.DOCX(24)
Sal(150319)
(DPG)
BSS S73
73-25 of 73-91
The laying of floor tiles shall be in accordance with clause 19.7 “Laying of
Ceramic Floor Tiles” including all sub-clauses under it.
BLDG19/S73.DOCX(25)
Sal(150319)
(DPG)
BSS S73
73-26 of 73-91
HDB shall produce, store and supply these components directly from its
Woodlands plant or from its appointed Precast Term Contractors’ plant to
the worksite. For the interpretation of this Clause on “Supply Of Precast
Components By HDB”, reference to HDB may also include HDB’s
appointed Precast Term Contractors.
BLDG19/S73.DOCX(26)
Sal(150319)
(DPG)
BSS S73
73-27 of 73-91
The Contractor shall be deemed to have included in the tender price the
cost of supply, delivery, labour, etc., for the following items to HDB:
(a) Tiles where required (excluding the ceramic tiles for the ring water
tank and prefabricated toilet) shall be supplied by the Contractor;
(d) All proprietary lifting anchors for handling and installation of precast
elements;
(f) All cast-in fixtures or accessories for site safety provisions or for
securing of formwork;
(h) For loose cast-in items supplied for precast production, the
Contractor shall ensure that they are pre-assembled and fastened
adequately to prevent loosening, falling apart or movement during
precasting. A template shall be provided to prevent movement during
precasting. The cost of assembling, securing the loose cast-in items
and the template are deemed to have been included in the tender
sum.
BLDG19/S73.DOCX(27)
Sal(150319)
(DPG)
BSS S73
73-28 of 73-91
(j) All accessories which are not cast-in with the precast component and
are necessary for the completion of the works in accordance to the
Standard Specifications For Building Works, such as, Rockwool /
woodwool insulation used in the construction of the Lift Machine
Room, steel angle plates required for connections of precast partition
wall, etc.
73.5.5.2 The rates listed in Clause “Supply Of Precast Components By HDB” are
without GST. GST shall be added to the rates. Payment shall be made by
deduction from the contractor's monthly progress payment.
BLDG19/S73.DOCX(28)
Sal(150319)
(DPG)
BSS S73
73-29 of 73-91
For the purpose of calculation of projected area, the full height of the
precast component including the kerbs shall be used. Deduction of
projected area due to partial kerb shall be made only if the kerb length is
less than 1.0m.
The rate of supply for precast wall is inclusive of the cast-in reinforcement.
All other reinforcement that are to be placed on site or for connection at
joints are not included and to be supplied by the Contractor.
In the event that a different thickness other than those specified in the
clause “Precast Components To Be Supplied By HDB” and “Precast
Components To Be Supplied By HDB or Source on their own from HDB’s
Materials List”, are required, the price of the precast component shall be
determined by linear interpolation/ extrapolation from the median thickness
(if applicable) specified in the above clauses.
The measurement guide for precast component listed in drawing no. HB-
BI-B&P-PLANK-01 provided in Appendix B1 shall be read in conjunction
with the clause on “Method Of Measurement”.
BLDG19/S73.DOCX(29)
Sal(150319)
(DPG)
BSS S73
73-30 of 73-91
73.5.7.1 The contractor shall submit the followings to HDB for approval not later
than 4 weeks after the date of the Letter of Acceptance of the contract:
(b) Site installation plan showing the accesses and trailer parking
positions for each block;
(e) The contractor shall also submit its planned site activities schedule
for each construction cycle, which would show the timing for the
requirement of each type of precast components.
BLDG19/S73.DOCX(30)
Sal(150319)
(DPG)
BSS S73
73-31 of 73-91
The Contractor shall email the order form to HDB at least 3 days in
advance to confirm the actual requirement of precast components.
When the delivery schedule has to be amended, HDB will inform
Contractor 2 days in advance of the required changes.
The Contractor shall inform HDB and HDB’s appointed Precast Term
Contractors at least 24 hours before the scheduled delivery for any
cancellation of delivery order or any change to delivery dates for
precast components. Otherwise, the delivery order is deemed to have
been confirmed.
73.5.7.3 Where there is a need for Contractor to supply cast-in items, HDB will
provide the materials delivery schedule to the Contractor. The Contractor
shall check and ensure the accuracy of all the quantity and types of cast-in
items before delivery. Contractor shall provide feedback to HDB if any
adjustment to the ordering schedule is required. Otherwise, the ordering
schedule is deemed to have been confirmed and all the cast-in items shall
be delivered to HDB or its appointed precast term contractor plant
accordingly. The Contractor shall be liable for all costs of delay arising
from the late delivery of the cast-in items. All cost of materials, labour etc
necessary for the supply and delivery of all items to be supplied by the
Contractor are deemed to be included in the tender sum.
BLDG19/S73.DOCX(31)
Sal(150319)
(DPG)
BSS S73
73-32 of 73-91
The Contractor shall submit the site schedule to HDB and allow a
minimum of 10 weeks, upon approval of workshop drawings, for the
delivery of the first precast component.
The Contractor shall ensure the site is fully accessible at all times for
trailers to deliver precast components and hard standing access shall be
provided.
The Contractor shall provide washing facilities at the site to ensure that
vehicles leaving the site do not dirty the public roads. Any charges for road
littering as a result of the Contractor's failure to do so shall be borne by the
Contractor.
The Contractor shall ensure that the prime mover or the trucks are not
held up at the site for more than 2 hours and the trailer is unloaded within
24 hours.
In the event that the precast components are produced and delivered from
overseas:
(a) The Contractor shall ensure that all such precast components on
trailers or trucks are unloaded within the same day if deliveries arrive
at the site before 3:00 pm. If deliveries arrive at the site after 3:00 pm,
the Contractor shall ensure that all precast component are unloaded
by 12:00 noon on the following day.
(b) The Contractor shall verify the times of deliveries arrive at the site
and upon completion of the unloading, sign and endorse on delivery
order.
If the Contractor fails to carry out his obligation as aforesaid, the SO Rep
may exercise his right under Clause 1.6 "Nuisance and Irregularities' to
impose a charge against the contractor.
BLDG19/S73.DOCX(32)
Sal(150319)
(DPG)
BSS S73
73-33 of 73-91
73.5.9.1 The Contractor shall designate and allocate storage space of at least 100
square metres per block. The designated storage space shall be on hard
standing ground. The Contractor shall provide storage racks for the
storage of precast components delivered to site. This storage area shall be
indicated and submitted together with the site office location plan. The
Contractor is deemed to have included in the tender sum the cost of
storage racks, ground improvement etc necessary for safe and orderly
storage of precast component on site.
73.5.9.2 The Contractor shall ensure that there are sufficient precast components
stored on site to ensure smooth construction progress. The contractor will
have to bear all cost arising out of construction delays due to insufficient
precast components storage on site.
The Contractor shall check the precast components for any major defects
before unloading the precast components from the trailer. Defects
feedback must be made to HDB within 7 days from the time the
components reaching the worksite or before installation of the precast
components, whichever earlier. Thereafter, the Contractor shall be
responsible for any necessary rectifications at his own cost and time.
Contractor shall install components with alignment taken on the external.
Components with serious dimension error that cause external
misalignment shall not be installed and must feedback to HDB
immediately.
The Contractor shall address precast quality issues early in the project for
components obtained from HDB’s appointed precast term contractors, to
establish a reasonable and achievable level of quality. If some of the
precast components at early stage have defects or quality issues, the
Contractor can highlight at delivery and get the term contractors to repair
later on site. If the defects or quality issues are a wide ranging and
consistent problem, the Contractor shall resolve the problem with the term
contractors. The Contractor shall not take the “receive-and-install”
approach without assessing the quality of the precast components and
expect the term contractors to do wide ranging repair at a later stage. This
is to avoid duplication of works and the delay of building hand-over.
BLDG19/S73.DOCX(33)
Sal(150319)
(DPG)
BSS S73
73-34 of 73-91
The Contractor shall also check the accuracy of the position and routing of
the services or cast-in accessories and provide feedback to HDB for
incorporation into the drawings. Recesses shall be provided in the precast
components, for site installation of electrical socket boxes by the
Contractor.
BLDG19/S73.DOCX(34)
Sal(150319)
(DPG)
BSS S73
73-35 of 73-91
The Contractor shall be allowed to claim for material off-site at HDB or its
designated storage yard. The quantity of precast components, which the
Contractor is allowed to claim, shall be based on the quantities given in the
stock list from HDB, which is provided in the monthly invoices for supply of
precast components: “BILLING TO CONTRACTOR FOR PRECAST
COMPONENTS DELIVERED TO SITE”.
The Contractor shall make use of the billing from the preceding month to
claim for material off-site in the current month.
To illustrate:
For Material Off-Site at HDB claim for progress payment for month ending
31 May 2008, the Contractor shall submit a copy of the billing received for
the “Billing of delivery up to 20 Apr 2008”.
BLDG19/S73.DOCX(35)
Sal(150319)
(DPG)
BSS S73
73-36 of 73-91
HDB reserves the right to lower the required MYE due to the higher
prefabrication plant productivity.
BLDG19/S73.DOCX(36)
Sal(150319)
(DPG)
BSS S73
73-37 of 73-91
(a) Connection details and for all water, sanitary and electrical piping,
fixtures and fittings, within and between modules.
(b) Installation for wash basin with tap mixer, bath/shower mixer with
shower set, future provision for water heaters (instant and storage
heater within toilet, gas heater outside toilet), toiletries cabinet/holder,
etc.
(d) Installation of built-in kitchen cabinets with induction hob, cooker hood,
kitchen sink and dish drying rack in the kitchen (2-room Flexi flats on
short leases) (where applicable).
(e) Installation of built-in Wardrobe and Window Grilles for (2-room Flexi
flats on short leases) (where applicable).
The Contractor shall supply all items such as loops, joints bars/connectors,
accessories, pipe conduits, M&E accessories, sealants, etc, that are to be
cast in or place on site that are necessary for the completion and functioning
of the PPVC as a complete system to be integrated with other modules and
rest of the building works.
The Contractor shall propose a staging area for the storage of PPVC modules and
to ensure that there are close and proper monitoring, progress reporting and
documentation, delivery, installation, safe storage and erection of the PPVC
modules. The Contractor shall study the site access(es) and ensure there will be no
obstruction to his other works / trades on site.
BLDG19/S73.DOCX(37)
Sal(150319)
(DPG)
BSS S73
73-38 of 73-91
(b) The Contractor shall fabricate, test, deliver and install all
construction system necessary for execution of the PPVC
system to all the dwelling units of this project. The PPVC system
shall be complete in all aspect, including all measures that may be
required to that end, notwithstanding any omissions or
inadequacies of Drawings and/or Specifications.
BLDG19/S73.DOCX(38)
Sal(150319)
(DPG)
BSS S73
73-39 of 73-91
73.9.2.4 Materials
Where the Contract requires the Contractor to obtain materials from the
HDB Material List or where it is specified that materials provided are
subject to the approval of the SO Rep, such requirements shall not in
any way affect, vary or relieve the Contractor’s obligations under the
Contract.
(b) Are of satisfactory quality and fit for their intended purpose.
BLDG19/S73.DOCX(39)
Sal(150319)
(DPG)
BSS S73
73-40 of 73-91
This clause shall be added as clause 53.10 “Switch Socket Outlets With
Universal Serial Bus (USB) Port” of the Standard Specifications For Building
Works and Other Installations.
The switched socket outlet with USB port shall be of similar construction by
the same manufacturer and product range to match the standard switched
socket outlets.
The switched socket outlet with USB port shall comprise a combined switch,
3-pin shuttered type outlet and USB port intended for charging portable
devices. The switched socket outlet with USB port shall comply with the
requirements of SS 145. USB circuits incorporated in the switch socket
outlet shall comply with the requirements of SS145-2 Annex I. The USB
port shall be suitable for charging most portable devices connected via a
USB 2.0 and 3.0 type A plug. The rated charging current of the USB port
shall be at least 2 amp.
In addition to SS 145, switched socket-outlets with USB port shall pass the
positive break test according to Clauses 13.111.2, 13.11.3 and 13.11.4 of
BS1363-2 or approved equivalent.
BLDG19/S73.DOCX(40)
Sal(150319)
(DPG)
BSS S73
73-41 of 73-91
For flush mounting installation, the front plate of the switch socket outlet with
USB port shall be decorative model and the fixing screws shall be
concealed.
All switched socket outlets with USB port shall be registered with Enterprise
Singapore and bear the Safety Mark.
Switched socket outlets with USB port installed in the dwelling units shall be
certified under a safety and quality assurance scheme by SAC-SINGLAS
accredited laboratories. They shall have the SAC-SINGLAS accredited
laboratories Test Mark.
BLDG19/S73.DOCX(41)
Sal(150319)
(DPG)
BSS S73
73-42 of 73-91
Characteristics &
Testing Method Specifications
Properties
Tensile Strength ASTM D412 > 35N/mm2
Elongation ASTM D412 1000%
Tensile Shear at Joint SS374:1994 >760N
Resistance to Hydrostatic
DIN 16726 >20 Bar
Pressure
Resistance to Leakage at
- No Leakage
Joints
Puncture Resistance ASTM E154 >1000N
Adhesion to Concrete ASTM D903 >5740N
UV Accelerated
500 Hours ASTM G154 Passed
Weathering
No water leakage at
Lateral Water Migration ASTM D5385
pressure of 100psi
Overlap all roll ends and cut edges by minimum 75mm and ensure the area
is clean and free from contamination. Waterproofing tape can be applied to
ensure continuous bond between the 2 adjoining membranes.
BLDG19/S73.DOCX(42)
Sal(150319)
(DPG)
BSS S73
73-43 of 73-91
This clause shall supersede clause 4.35 “Installation of Fibre Optic Sensor
For Columns” of the Standard Specifications For Building Works and Other
Installations.
The Contractor shall provide and install encased fibre optic sensors at
different 1st storey columns of each building above 10 storeys as shown in
the table below:
Number of residential
Number of columns for sensors
units in each typical
installation
storey
6 or less 8 (minimum)
More than 6 10
Where the columns are precast, the Contractor shall provide such sensors
for the precaster to install in the precast columns. The locations of the
sensors shall be approved by the SO Rep and as-built drawings indicating
actual position of sensors must be submitted upon successful installation.
The sensors shall have connecting cables terminating with a socket at the
column face to enable the SO Rep to take readings. The Contractor shall
submit 3 sets of readings per block during the construction stage, and 1 set
of reading per block during DLP to HDB to verify that the sensors are in
working condition.
73.13 WARRANTY
The Contractor shall warrant for a period of Five (5) years against ceiling
leak and external seepage.
The Contractor shall warrant the Works on the terms and conditions as
stipulated in the Deed of Warranty for Ceiling Leak and External Seepage as
produced in Appendix A2. In this respect, the Contractor shall submit such
Deed of Warranty to the Employer or to such other party or such Town
Council(s) as the SO Rep may at its sole discretion decide.
BLDG19/S73.DOCX(43)
Sal(150319)
(DPG)
BSS S73
73-44 of 73-91
In the event the Deed of Warranty for part of the Works or for the whole
Works is to be submitted to such Town Council(s), the Contractor shall
submit such Deed of Warranty as produced in Appendix A2(TC) to such
Town Council(s). The duly executed Warranty shall be submitted
immediately upon request by the SO Rep, and if no such request is made,
then at such time when the SO Rep considers the Works have been
substantially completed in accordance with the Contract. In the event the
Contractor shall fail to execute and submit the Deed of Warranty within the
time specified, the SO Rep shall be allowed to withhold 15% of the payment
of any sums due to the Contractor in relation to the execution of such
Works, subject to the minimum sum of S$5,000 per Deed of Warranty.
However, such sums withheld shall be released to the Contractor upon
submission by him of the duly executed Deed of Warranty.
BLDG19/S73.DOCX(44)
Sal(150319)
(DPG)
BSS S73
73-45 of 73-91
APPENDIX A2
……………………………………………………………………
……………………………………………………………………
……………………………………………………………………
WHEREAS :
(1) ………………………………………………………………………………………………………………………………
(Name and Address of Contractor)
………………………………………………………………………………………………
(hereinafter called the "Contractor") is the contractor of the Housing & Development Board (hereinafter called the
"Employer") in respect of the above contract works (hereinafter called the "Contract").
In consideration of the premises and of the Employer giving the consent aforesaid at the request of
the Contractor, the Contractor agrees with the Employer as follows:
1 The Contractor warrants for a period of Five (5) years (hereinafter called the "Warranty Period") that
the Works shall remain watertight, leakproof and waterproof and/or remain free from defects including but not
limited to water seepage through external walls and toilet walls, ceiling leak, and failure of all components of the
precast structure joints and waterproofing details.
The Warranty Period in respect of the Works shall commence from the Date(s) of Substantial Completion of the
Contract as certified by the Superintending Officer of the Contract.
BLDG19/S73.DOCX(45)
Sal(150319)
(DPG)
BSS S73
73-46 of 73-91
APPENDIX A2
Page 2
(a) they have exercised all proper skill and care in the selection of materials and goods for the
Works;
(b) they have exercised all proper skill and care in the design and execution of the Works;
(c) their workmanship is of a standard that may be expected from a contractor with specialised
experience and expertise in his particular trade; and
(d) the Works are fit and suitable for the purpose designed and required in the Contract.
3 It is an express term of the Warranty that the Works when completed and the goods or materials used
shall meet the Performance Requirement of the Contract in respect of the Works. ln the event the Works when
completed and/or the goods and materials used should fail to meet such Performance Requirement, the
Contractor shall be precluded from disclaiming liability under the Warranty on the ground that the Works as
completed and/or the goods and materials used accord or comply with the Contract, and in this connection, the
Contractor is deemed to have waived this defence in the event a claim is made by the Employer against them in
respect of their breach of the Warranty.
4 Subject to Clauses 5 and 9 below, if any damage or defects should occur in relation to the Works
within the Warranty Period due to whatever cause, the Contractor undertake to remove and/or rectify and make
good such damage or defects including ancillary works within a reasonable period or duration specified by the
Employer's notice in writing. If such damage or defects are attributable to the Contractor's breach of warranty
under Clause 2 above, then the cost of such removal rectification and/or making good work shall be borne by the
Contractor. If the Contractor shall fail to comply within the period or duration specified, it shall be lawful for the
Employer to order such damage or defects as are referred to in such notice to be removed, rectified and/or made
good by any other person and recover from the Contractor such cost and expense incurred for which they may
be liable. PROVIDED ALWAYS that such instructions shall be issued without prejudice to the Employer's right to
recover damages against the Contractor by reason of their failure to comply with this Clause.
5 In the event such damage or defects are caused wholly or in part by the Employer or a third party, and
the Contractor is required under Clause 4 above to remove, rectify and/or make good such damage or defects
including ancillary works within the period or duration specified by the Employer's notice in writing, then upon
completion of such work, the Employer shall pay the Contractor for the work or that part of the work which the
Employer's Chief Executive Officer or at the discretion of the Chief Executive Officer, a person nominated by him
in writing may determine as occasioned by damage or defects caused by the Employer or third party, and the
valuation of such work or such part of the work shall be ascertained in accordance with one or a combination of
the methods mentioned below in descending order of priority :
(b) if the above method is not applicable, then the valuation shall be based on the actual cost of
necessary materials or goods, labour, Construction Equipment and equipment (other than
ordinary plant) plus 15% which percentage shall include the use of all ordinary plant, tools and
supervision, overheads and profits.
6 The approval by the Employer of any works required under Clauses 4 or 5 above does not absolve
the Contractor from their responsibility to rectify future occurrence of defects in respect of such works.
BLDG19/S73.DOCX(46)
Sal(150319)
(DPG)
BSS S73
73-47 of 73-91
APPENDIX A2
Page 3
7 It is a term of this Warranty that the Contractor shall indemnify the Employer against all loss damage
cost and expense suffered or incurred by the Employer in relation to any damage to property or injury to person
caused or occasioned by the acts or omissions of the Contractor's employees, representatives or workmen in the
course of the works undertaken under the terms of this Warranty. The Contractor shall at their own cost and
expense effect and maintain a Public Liability Insurance Policy for the execution of such works.
8 The Contractor shall indemnify the Employer against any compensation payable by the Employer
under the Workmen's Compensation Act Cap 354 (1985 Edition) in connection with any accident arising out of
rectification works undertaken by the Contractor pursuant to the provisions of this Warranty. The Contractor shall
at their own cost and expense effect and maintain a Workmen's Compensation Policy for the execution of such
works.
9 This Warranty shall not be invalidated in the event another person is instructed to execute the
rectification work on account of the Contractor's failure to discharge their obligations under Clauses 4 and 5
above, nor shall this Warranty be invalidated in the event a third party is engaged without the consent of the
Contractor to carry out regular maintenance and cleaning of the Works, provided that in the latter event, any
rectification work or part thereof undertaken by the Contractor that is occasioned by the negligence of such third
party shall be valued in the manner described in Clause 5 above and paid by the Employer.
10 All differences and/or disputes arising under this Warranty (including questions relating to
interpretation) shall be determined by the Employer's Chief Executive Officer or at the discretion of the Chief
Executive Officer, by a person nominated in writing by him. Any decision by the Chief Executive Officer or his
nominee under this Clause shall be final and binding on and conclusive against the Contractor in any
proceedings that may arise under this Warranty unless otherwise determined by the Court in respect of
proceedings arising under this Warranty.
11 This Warranty shall remain valid and shall not be affected by any extensions, variations or
compositions granted or entered into with respect to the terms of or obligations under the Contract.
12 This Warranty shall be read together with the Contract but in case of any conflict between the two
documents the provisions of this Warranty shall prevail.
13 The validity, construction and interpretation of this Warranty and all rights, obligations and liabilities
arising hereunder shall be governed by, and interpreted in accordance with, the laws of Singapore.
14 The Employer shall have the absolute discretion to assign the benefit of this Warranty to any third
parties without the consent of the Contractor.
IN WITNESS WHEREOF we have hereunto set our hands and seals the day of
20 .
BLDG19/S73.DOCX(47)
Sal(150319)
(DPG)
BSS S73
73-48 of 73-91
To: ……………………………
……………………………
Republic of Singapore
STAMP
If stamp duties required
……………………………………………………………………
……………………………………………………………………
……………………………………………………………………
WHEREAS :
(1) ………………………………………………………………………………………………………………..………………
(Name and Address of Contractor)
………………………………………………………………………………………………
(hereinafter called the "Contractor") is the contractor of the Housing & Development Board (hereinafter called the
"Employer") in respect of the above contract works (hereinafter called the "Contract").
In consideration of the premises and of the Employer giving the consent aforesaid at the request of
the Contractor, the Contractor agrees with the Employer as follows :
1 The Contractor warrants for a period of Five (5) years (hereinafter called the "Warranty Period") that
the Works shall remain watertight, leakproof and waterproof and/or remain free from defects including but not
limited to water seepage through external walls and toilet walls, ceiling leak, and failure of all components of the
precast structure joints and waterproofing details.
The Warranty Period in respect of the Works shall commence from the Date(s) of Substantial Completion of the
Contract as certified by the Superintending Officer of the Contract.
BLDG19/S73.DOCX(48)
Sal(150319)
(DPG)
BSS S73
73-49 of 73-91
APPENDIX A2 (TC)
Page 2
(a) they have exercised all proper skill and care in the selection of materials and goods for the
Works;
(b) they have exercised all proper skill and care in the design and execution of the Works;
(c) their workmanship is of a standard that may be expected from a contractor with specialised
experience and expertise in his particular trade; and
(d) the Works are fit and suitable for the purpose designed and required in the Contract.
3 It is an express term of the Warranty that the Works when completed and the goods or materials used
shall meet the Performance Requirement of the Contract in respect of the Works. ln the event the Works when
completed and/or the goods and materials used should fail to meet such Performance Requirement, the
Contractor shall be precluded from disclaiming liability under the Warranty on the ground that the Works as
completed and/or the goods and materials used accord or comply with the Contract, and in this connection, the
Contractor is deemed to have waived this defence in the event a claim is made by the Employer against them in
respect of their breach of the Warranty.
4 Subject to Clauses 5 and 9 below, if any damage or defects should occur in relation to the Works
within the Warranty Period due to whatever cause, the Contractor undertake to remove and/or rectify and make
good such damage or defects including ancillary works within a reasonable period or duration specified by the
Employer's notice in writing. If such damage or defects are attributable to the Contractor's breach of warranty
under Clause 2 above, then the cost of such removal rectification and/or making good work shall be borne by the
Contractor. If the Contractor shall fail to comply within the period or duration specified, it shall be lawful for the
Employer to order such damage or defects as are referred to in such notice to be removed, rectified and/or made
good by any other person and recover from the Contractor such cost and expense incurred for which they may
be liable. PROVIDED ALWAYS that such instructions shall be issued without prejudice to the Employer's right to
recover damages against the Contractor by reason of their failure to comply with this Clause.
5 In the event such damage or defects are caused wholly or in part by the Employer or a third party, and
the Contractor is required under Clause 4 above to remove, rectify and/or make good such damage or defects
including ancillary works within the period or duration specified by the Employer's notice in writing, then upon
completion of such work, the Employer shall pay the Contractor for the work or that part of the work which the
Employer's Chief Executive Officer or at the discretion of the Chief Executive Officer, a person nominated by him
in writing may determine as occasioned by damage or defects caused by the Employer or third party, and the
valuation of such work or such part of the work shall be ascertained in accordance with one or a combination of
the methods mentioned below in descending order of priority :
(b) if the above method is not applicable, then the valuation shall be based on the actual cost of
necessary materials or goods, labour, Construction Equipment and equipment (other than
ordinary plant) plus 15% which percentage shall include the use of all ordinary plant, tools and
supervision, overheads and profits.
6 The approval by the Employer of any works required under Clauses 4 or 5 above does not absolve
the Contractor from their responsibility to rectify future occurrence of defects in respect of such works.
BLDG19/S73.DOCX(49)
Sal(150319)
(DPG)
BSS S73
73-50 of 73-91
APPENDIX A2 (TC)
Page 3
7 It is a term of this Warranty that the Contractor shall indemnify the Employer against all loss damage
cost and expense suffered or incurred by the Employer in relation to any damage to property or injury to person
caused or occasioned by the acts or omissions of the Contractor's employees, representatives or workmen in the
course of the works undertaken under the terms of this Warranty. The Contractor shall at their own cost and
expense effect and maintain a Public Liability Insurance Policy for the execution of such works.
8 The Contractor shall indemnify the Employer against any compensation payable by the Employer
under the Workmen's Compensation Act Cap 354 (1985 Edition) in connection with any accident arising out of
rectification works undertaken by the Contractor pursuant to the provisions of this Warranty. The Contractor shall
at their own cost and expense effect and maintain a Workmen's Compensation Policy for the execution of such
works.
9 This Warranty shall not be invalidated in the event another person is instructed to execute the
rectification work on account of the Contractor's failure to discharge their obligations under Clauses 4 and 5
above, nor shall this Warranty be invalidated in the event a third party is engaged without the consent of the
Contractor to carry out regular maintenance and cleaning of the Works, provided that in the latter event, any
rectification work or part thereof undertaken by the Contractor that is occasioned by the negligence of such third
party shall be valued in the manner described in Clause 5 above and paid by the Employer.
10 All differences and/or disputes arising under this Warranty (including questions relating to
interpretation) shall be determined by the Employer's Chief Executive Officer or at the discretion of the Chief
Executive Officer, by a person nominated in writing by him. Any decision by the Chief Executive Officer or his
nominee under this Clause shall be final and binding on and conclusive against the Contractor in any
proceedings that may arise under this Warranty unless otherwise determined by the Court in respect of
proceedings arising under this Warranty.
11 This Warranty shall remain valid and shall not be affected by any extensions, variations or
compositions granted or entered into with respect to the terms of or obligations under the Contract.
12 This Warranty shall be read together with the Contract but in case of any conflict between the two
documents the provisions of this Warranty shall prevail.
13 The validity, construction and interpretation of this Warranty and all rights, obligations and liabilities
arising hereunder shall be governed by, and interpreted in accordance with, the laws of Singapore.
14 The Employer shall have the absolute discretion to assign the benefit of this Warranty to any third
parties without the consent of the Contractor.
IN WITNESS WHEREOF we have hereunto set our hands and seals the day of
20 .
BLDG19/S73.DOCX(50)
Sal(150319)
(DPG)
BSS S73
73-51 of 73-91
This clause shall supersede clause 21.3 “Cable Tray For Broadband Coaxial
Cable Telecommunication Systems” of the Standard Specifications For
Building Works and Other Installations.
The number and size of metal cable tray to be used shall be in accordance
to the latest Code of Practice for Info-Communications Development
Facilities (COPIF) in Building issued by Info-Communications Media
Development Authority (IMDA) or as shown in the drawing. Any discrepancy
in the drawings with COPIF shall be brought up to the SO Rep for decision.
However, metal trunkings are to be installed instead of cable trays in each
telecommunication risers. The metal trunkings are to be installed in a
straight run with a minimum number of bends and the dimensions of the
metal trunkings shall be as follows:
For
Telecommunication 300mm x 100mm 400mm x 100mm
(≤ 25 storeys)
For
Telecommunication
400mm x 100mm 500mm x 100mm
(between 26 and 50
storeys)
This clause shall supersede clause 21.5 “Earth Bars In MDF And TER
Rooms” of the Standard Specifications For Building Works and Other
Installations.
BLDG19/S73.DOCX(51)
Sal(150319)
(DPG)
BSS S73
73-52 of 73-91
The title of clause 24.2 of the Standard Specifications For Building Works
and Other Installations shall supercede and read as “Telecommunication
Pipe System”.
All trenches excavated for the provision of underground pipe system for
telecommunication cables shall be backfilled as follows:
(i) For trenches that are located within the road, backfill shall be from the
completed pipe level to the subgrade of the road with granular
materials such as sand/granite fines or quarry dust. The backfilling shall be
properly compacted.
(ii) For trenches which are not located within the road, backfill to the level
required under the Contract with good dry earth approved by the SO
Rep.
73.21 GENERAL
This clause shall supersede clause 61.2 “The System” of the Standard
Specifications For Building Works and Other Installations.
(b) All components installed shall be adequately protected from theft. The
Contractor shall be responsible for the safety of the equipment before
any official handover.
This clause shall supersede clause 61.4 “The Installation” of the Standard
Specifications For Building Works and Other Installations.
(a) The subscriber's outlet and TV inlet shall normally be mounted next to
the 13-Amp socket outlets in the flat unit.
(d) All TV outlets in the unit including the household and storey shelters
shall come with TV ports only.
BLDG19/S73.DOCX(53)
Sal(150319)
(DPG)
BSS S73
73-54 of 73-91
(e) Metal base boxes shall be provided for TV outlets installed in the
household and Storey shelters. The boxes shall be sufficiently strong
to resist mechanical damages and the service conditions specified. The
boxes shall be constructed in such a way that they cannot be readily
deformed. The Contractor shall submit samples to the SO Rep for
approval:
- Provision shall be made for holes in the base of the boxes for
securing it to a mounting surface.
(f) All the conduits and PVC trunkings shall be painted with the approved
paint. The colour of the paint shall be similar to the surroundings.
(g) The single cable TV ‘F’ type connector socket, TV inlet shall be made
of white polycarbonate, urea or other material approved by the SO Rep
and match the colour of the electrical/telecoms outlets and having the same
brand / finishes. The polycarbonate, urea or other approved material
shall be UV stabilised and shall not discolour within the Defects Liability
Period even if the outlet is exposed to sunlight.
Clause 61.5 – “Cable Tray And Tee Box” of the Standard Specifications For
Building Works and Other Installations shall be deleted.
BLDG19/S73.DOCX(54)
Sal(150319)
(DPG)
BSS S73
73-55 of 73-91
73.27.1 The maintenance period shall commence from the certified completion of
the block and the Contractor shall respond to any maintenance service calls
from the SO Rep as if from the Employer.
The maintenance service shall include all the items specified hereunder
during the Maintenance Period.
(b) The Contractor shall be responsible for informing the above informant/s
within one hour after a case has been referred to him, to report on:
(c) The Contractor shall attend to and rectify all the faults promptly.
73.27.2 The Contractor shall liaise with the SO Rep for carrying out any modification
work to the TV system and emergency repairs.
73.27.3 If the contractor fails to attend an urgent call within the same day or fails to
attend other faults within 24 hours or fails to rectify the faults successfully
after three (3) attempts, the Employer or the SO Rep reserves the right to
engage another contractor to carry out the works. The costs of the repairs
and replacement plus the administration charges shall be borne by the
Contractor and will be deducted from any payment due to the Contractor.
73.27.4 The Contractor shall provide standby equipment to keep the system
functioning when the faulty equipment are taken back to the workshop for
repairs.
BLDG19/S73.DOCX(55)
Sal(150319)
(DPG)
BSS S73
73-56 of 73-91
This clause shall supersede clause 62.1 “Scope Of Work” of the Standard
Specifications For Building Works and Other Installations.
(iv) The requirements for the 2-way air-blown microducts and tube
patch panel shall comply with COPIF 2018 and COPIF 2018
addendum.
BLDG19/S73.DOCX(56)
Sal(150319)
(DPG)
BSS S73
73-57 of 73-91
73.29 GENERAL
The Contractor shall provide all necessary labour, tools and materials
required for the telecommunication cabling works. All materials for the
telecommunication cabling works shall be as approved by IMDA. It shall
match the electrical wiring accessories and of the same construction.
This clause shall supersede clause 62.3 “Installation Of Optical Fibre Cable
From Telecommunication Riser To Each Residential Unit” of the Standard
Specifications For Building Works and Other Installations.
(b) A Fibre Termination Point which is located in the residential unit service
Closet.
BLDG19/S73.DOCX(57)
Sal(150319)
(DPG)
BSS S73
73-58 of 73-91
The number and type of optical fibre cables, fibre termination point,
unshielded twisted pair cable(s) and accessories provided in the residential
units such as RJ45 patch panel and RJ45 outlets shall comply with the
requirements of COPIF:2018, COPIF 2018 addendum and approved
relevant standards.
This clause shall supersede clause 62.5 “Fibre Interface Point” of the
Standard Specifications For Building Works and Other Installations.
The fibre termination point shall be securely mounted at the width of the
telecommunication riser, i.e. wall that is facing the door. The fibre
termination point shall have 4 SC/APC connectors.
This clause shall supersede clause 62.6 “Fibre Termination Point” of the
Standard Specifications For Building Works and Other Installations.
(a) be securely mounted adjacent to the RJ45 patch panel (located in the
service closet and 13A switch socket outlet; and
(b) have a clear space of 50mm from the SC/APC connectors to allow the
connection of patch cords.
For storey shelter, the Fibre Termination Point shall be of recessed mounted
type.
This clause shall supersede clause 62.9 “Testing Criteria For The Optical
Fibre Cable” of the Standard Specifications For Building Works and Other
Installations.
To ensure that the optical fibre cable to the unit is in good working condition
upon completion of installation works, both of the following methods of
testing must be carried out:
BLDG19/S73.DOCX(58)
Sal(150319)
(DPG)
BSS S73
73-59 of 73-91
(a) Continuity Testing – This involves checking that the optical fibre cable
is not physically broken at any point, and that the optical fibre cable does
indeed go from one location to the correct destination using a powerful
visible red laser; and
(b) Scanning at the fibre interface/ termination point with an Optical Time
Domain Reflectometer (OTDR) – An OTDR is capable of measuring
the fibre lengths, losses, connector losses, splice losses and fibre
defects, and works by sending a pulse of light into the fibre and
measuring how much light is reflected back and detected at the OTDR.
It will produce a line or graph on a screen and by measuring how much
light is reflected, the OTDR can determine the loss associated with
each of these anomalies. The optical fibre cable will be treated as
being in good working condition if the losses measured between
the fibre termination point at the telecommunication riser and the fibre
termination point at the residential unit and lift motor room/TMS closet
using the OTDR are less than 0.6dB.
(c) Test report by licensed telecom wiring installer/ tester and accepted by
licensed telecom services operator shall be submitted to SO Rep for
record.
There should not be any significant wiring changes after the optical fibre
cable and its associated fibre termination points have been certified “fibre-
ready”.
BLDG19/S73.DOCX(59)
Sal(150319)
(DPG)
BSS S73
73-60 of 73-91
This clause shall supersede clause 62.12 “Installation Of Optical Fibre Cable
And Fibre Termination Point In Lift Motor Room / TMS Closet & MSCP” of
the Standard Specifications For Building Works and Other Installations.
The Contractor shall install, test and commission optical fibre cable from
Telecommunication Riser to the lift motor room/TMS closet of residential
blocks and multi-storey car parks. A minimum of one number of 2-Core
optical fibre cable shall be installed in the conduit.
(b) A Fibre Termination Point which is located in the lift motor room / TMS
closet.
For lifts with Machine Room, the Fibre Termination Point shall be located at
Telecommunication Riser at top storey. For lifts with Machine room-less, it
shall be located at the same storey with the TMS closet. An additional 13
ampere switch-socket outlet shall also be installed in the lift motor
room/TMS closet. If there are more than one lift motor room/TMS closet in a
residential block or multi-storey car park, only one number of fibre
termination point and an additional 13 ampere switch-socket outlet are
required to be provided in one of the lift motor rooms/TMS closet.
BLDG19/S73.DOCX(60)
Sal(150319)
(DPG)
BSS S73
73-61 of 73-91
Fibre termination point (FTP) with 1 number of 4 core optical fibre cable from
telecom duct shall be provided for the social communal facility (SCF) and
commercial units. The 1 number 4-core optical fibre cable shall be provided
in the 2-way-air blown microducts (5/3.5) mm. The fibre cable shall be
terminated into a fibre termination point which is located in the
SCF/commercial units and into the rack mount fibre patch panel via the tube
patch panel located in the telecommunication riser at the other end. The
fibre termination point shall have 4 SC/APC connectors and there shall be a
13A switch socket outlet beside the FTP.
Location of the FTP is preferably near the consumer unit. Patch panel shall
also be provided beside for configuring RJ45 outlets for office room.
Detailed provision such as the number of RJ45 outlets shall follow the
drawing.
The contractor shall supply and install cable tray from Telecom Duct to the
commercial premises and SCF. Adequate space shall be provided for both
copper and fibre cables on the cable tray for each shop and SCF.
The 2-way air-blown fibre microducts used shall meet or exceed the
minimum requirements stated below:
BLDG19/S73.DOCX(61)
Sal(150319)
(DPG)
BSS S73
73-62 of 73-91
73.38 TUBE PATCH PANEL FOR 2-WAY AIR BLOWN FIBRE MICRODUCTS
This clause shall be added as clause 62.17 “Tube Patch Panel For 2-Way
Air Blown Fibre Microducts” of the Standard Specifications For Building
Works and Other Installations.
A tube patch panel with bulk head connectors (5 mm) shall be installed in
the telecommunication riser for the termination of 2-way air-blown fibre
microducts. The tube patch panel shall be located at a height of 1.5m (from
floor finish) and placed on the width of the telecommunication riser. The tube
patch panel shall come with a supporting bracket to allow a turning radius of
100mm or 20times the diameter of the 2-way air-blown fibre microducts.
73.39 DIMENSIONS
This clause shall supersede clause 19.5.4 (a) “Dimensions” of the Standard
Specifications For Building Works and Other Installations.
Rental Unit,
Bathroom,
Kitchen Floor Service Yards
Balcony Floor Tiles
Tiles and Household
Shelter Floor
Tiles
Nominal
600mm* 600mm 600mm 600mm
Length
Nominal
600mm 300mm 150mm 300mm
Width
Nominal
10.0mm 9.0mm 9.0mm 9.0mm
Thickness
Ceiling material located at 1st Storey lift lobby, Letterbox area, Community
Living Room and any other area as specified shall be of perforated
aluminium suspended ceiling. The details shall follow the suspended ceiling
supplier’s recommendation. Shop drawings shall be submitted for SO rep
approval.
For those ceiling that has been approved by SO rep that used calcium
silicate board / gypsum board, it shall be of 1200mm x 2400mm x 12mm
thick non-combustible gypsum board. Boards shall be fixed to ceiling joists
and noggings with 38mm galvanised steel clout nails at maximum 150mm
centre at all edges and intermediate fixing (along the centre of the board) of
galvanised steel clout nails shall be of maximum 300mm centres. Joints
between boards shall be covered with 38mm x 15mm nominal, moulded
wood fillets at edge of wall and open joint at intermediate joint. Sufficient
number of access panels (minimum two) shall be provided for maintenance
purpose.
This clause shall supersede subclause 50.11.3 (d) (viii) “Touch Screen
Panel HMI” of the Standard Specifications For Building Works and Other
Installations.
The HMI shall be provided with passwords for user security / permission to
prevent unauthorised usage. Only the security level that is equal or higher
than the current setting can use the element.
This clause shall supersede subclause 50.11.3 (b) “Areas of Monitoring &
Measurements” of the Standard Specifications For Building Works and
Other Installations.
Current(A),
Incoming Voltage(V),
Supplies 2 incoming supplies MCCB, EFR, OCR Power (W),
from SPPG Energy (kWh),
Max. Demand Reading
Current(A)
2 SPPG metered supplies MCCB, EFR Power (W)
Energy (kWh)
Current(A)
All risers to lift motors MCCB, ELR Power(W)
control panels
Energy (kWh)
Current(A),
Public Lightings - Power(W)
(Outdoor, Indoor)
Energy (kWh)
Abbreviations:
BLDG19/S73.DOCX(64)
Sal(150319)
(DPG)
BSS S73
73-65 of 73-91
The Contractor executing the works have to ensure that the works, goods or
materials used shall be suitable and reasonably fit for the purposes for
which they are required (hereinafter referred as "Performance
Requirement”.
73.44.2 Materials
The APCC with sealer coat system consists of 2 components: a 3mm acrylic
polymer-modified cementitious screed and a water-borne polyurethane (PU)
or acrylic polymer cementitious topcoat. The topcoat / sealer coat shall be
compatible with the acrylic polymer-modified cementitious screed in
accordance to the manufacturer’s specification.
The APCC with sealer coat shall be applied to all external corridor space,
not limited to 1st storey and typical storey common corridors and any other
area as shown in the Drawings.
(a) Substrate
The APCC with top coat system shall be laid on top of screed floors. The
screed used shall comply with the performance requirements specified in
the Standard Specifications sub-clause on “Pre-packed Mortar Screed”.
(b) Topcoat
BLDG19/S73.DOCX(65)
Sal(150319)
(DPG)
BSS S73
73-66 of 73-91
Prior to any w orks, the Contractor shall submit test reports for the
follow ing tests:
The slip resistance and resistance to stains shall be carried out af ter
the application of the sealer topcoat.
The test results of FTIR shall match the chemical thumbprint of the
topcoat established during the application for listing under the HDB
Materials List
The Contractor shall carry out in-situ testing for slip resistance,
resistance to stains and tensile adhesion bond strength tests at locations
decided by the SO Rep.
BLDG19/S73.DOCX(66)
Sal(150319)
(DPG)
BSS S73
73-67 of 73-91
Absorption ≤ 10%
Water Absorption After ASTM C (max) (after 30
5
Thermal Aging (%) 413:2001 minutes water
immersion)
BLDG19/S73.DOCX(67)
Sal(150319)
(DPG)
BSS S73
73-68 of 73-91
The APCC and sealer top coat full system shall comply with the following
technical requirements:
ISO 10545-14
(staining
agents: olive oil,
Class 4 or Class 5
5 Resistance to Stains coffee with milk,
cleanability
used engine oil
and black
rubber hose)
BLDG19/S73.DOCX(68)
Sal(150319)
(DPG)
BSS S73
73-69 of 73-91
73.44.4 Application
Place, spread and finish APCC with appropriate laying tools to the specified
thickness.
The surface after preparation shall be clean, dry and free of dust, dirt, oil,
grease, and any other material prior to application of the APCC coating.
The APCC coating shall be sufficiently cured, clean and free of loose
deleterious matters before application of the topcoat. The Contractor
shall apply the topcoat in accordance to the manufacturer’s methods
statement.
The title of section 21 of the Standard Specifications For Building Works and
Other Installations shall supercede and read as “Electrical And
Telecommunication Systems Installations”.
BLDG19/S73.DOCX(69)
Sal(150319)
(DPG)
BSS S73
73-70 of 73-91
The title of section 24 of the Standard Specifications For Building Works and
Other Installations shall supercede and read as “Underground Pipe System
For Low Tension Reticulation And Telecommunication Cables”.
BLDG19/S73.DOCX(70)
Sal(150319)
(DPG)
BSS S73
73-71 of 73-91
Perimeter joints shall be provided for living room, dining room and
bedroom floor tiles. The joints shall extend through the tiling and its
beddings and shall be a minimum of 8mm wide. The joint shall be provided
where the tiling abuts restraining surfaces such as perimeter walls,
columns, kerbs etc.
BLDG19/S73.DOCX(71)
Sal(150319)
(DPG)
BSS S73
73-72 of 73-91
Submit shop drawings and a sample to the SO Rep for approval prior to
their installations. Provide and fix all electrical cables, ballast, lamp
holders, fluorescent tubes and other necessary lighting accessories
including connection with wiring from the nearest connection box.
BLDG19/S73.DOCX(72)
Sal(150319)
(DPG)
BSS S73
73-73 of 73-91
The Contractor and his Specialist executing the Works as required in this
clause including all subclauses under it have to ensure that the Works,
goods or materials used shall be suitable and reasonably fit for the
purposes for which they are required (hereinafter referred as "Performance
Requirement"). In the event the Works, goods or materials to be used as
specified in this clause including all subclauses under it are upgraded in
order to meet the Performance Requirement, the Contractor and his
Specialist shall do all necessary upgrading at no extra cost to the
Employer.
73.gg.2 General
BLDG19/S73.DOCX(73)
Sal(150319)
(DPG)
BSS S73
73-74 of 73-91
73.gg.3 Performance
When directed by the SO Rep, the Contractor shall send sample(s) of the
aluminium windows for performance tests as required in SS 212 : 2007 to
be carried out by PSB or a testing laboratory accredited under SINGLAS.
The details shown in the Drawings shall serve as a guide only. The
Contractor shall submit shop drawings to ensure compliance with SS 212 :
2007.
73.gg.4 Material
(B) Accessories
All screws, nuts, bolts, washers, fasteners and all other accessories
to be used in the fabrication of the windows shall be stainless steel
type 304 minimum complying with BS EN 10088. All screws (except
screws used to fix stainless steel hinges), bolts and other accessories
which are exposed shall be in approved matching colour. All screws
used to fix stainless steel friction hinges shall be approved stainless
steel screws precoated with epoxy coating as shown in the Drawings.
All joints shall be sealed with synthetic butyl rubber and all inner
frames shall have insertion of gaskets or other air gaskets or other
air-tightening materials complying with SS 212:2007. Gaskets shall
be neoprene or ethylene propylene diene monomer (EPDM).
BLDG19/S73.DOCX(74)
Sal(150319)
(DPG)
BSS S73
73-75 of 73-91
Safety devices shall be incorporated into all the glazed sliding window
panels to prevent them from jumping track and shall be in black or
other approved matching colour.
(G) Hardware
BLDG19/S73.DOCX(75)
Sal(150319)
(DPG)
BSS S73
73-76 of 73-91
The stainless steel friction stays shall comply with the following
requirements :
Test Requirements
Resistance to 300N for 5 second Passed
obstructed stay Arm bent at 40 kg (392N)
track Destruction Test
minimum
Strength of 200N for 5 second Passed
maximum Stay track permanent deformed at
Destruction Test
opening stop 65 kg (638N) minimum
1000N for 1 min. passed
Resistance to Stay track bent at 130kg (1275N)
accidental minimum
Destruction Test
loading Sash remains intact 150kg
(1472N) minimum
Passed (no adjustment throughout
50,000 cycles
Endurance of the test)
Fastener Passed (no adjustment throughout
100,000 cycles
the test)
(i) Surfaces
(ii) Thickness
Using the falling sand test method ASTM D 968, the Abrasion
Coefficient Value of the coating shall be 20 minimum.
BLDG19/S73.DOCX(78)
Sal(150319)
(DPG)
BSS S73
73-79 of 73-91
BLDG19/S73.DOCX(79)
Sal(150319)
(DPG)
BSS S73
73-80 of 73-91
(L) Weathering
The coating shall maintain its film integrity and as a minimum meet
the colour retention, chalk resistance, gloss retention and erosion
resistance properties specified hereunder. The SO Rep shall request
data relative to the long term durability of the colour/colours selected.
Less than 10 percent film loss after the exposure test expressed
as a percent loss of total film.
BLDG19/S73.DOCX(80)
Sal(150319)
(DPG)
BSS S73
73-81 of 73-91
80 - 100 %
73.gg.6 Appearance
The powder coating on the significant surface shall not have any scratches
through to the base metal. It shall be of even colour and gloss with good
coverage. It shall not have Defect such as excessive roughness, flow
lines, bubbles, inclusions, craters, blisters, dull spots, pin holes, scratches
or any other unacceptable flaws.
73.gg.7 Colour
BLDG19/S73.DOCX(81)
Sal(150319)
(DPG)
BSS S73
73-82 of 73-91
73.gg.10 Installation
The design and profile of all the powder coated aluminium sliding
windows, casement windows and top hung shall be as shown in the
Drawings.
(B) Detailing
All windows and other aluminium items shall be fixed strictly to the
manufacturer's instructions.
Any clearance spaces between the window work size and the work
surrounding the window shall be sealed with an approved sealant
when fixing is completed.
BLDG19/S73.DOCX(82)
Sal(150319)
(DPG)
BSS S73
73-83 of 73-91
(D) Glazing
(a) Glass
Unless otherwise stated, all tinted glass for sliding door shall be
6mm ±0.2mm green gray/gray tinted float glass with a shading
coefficient of 0.75.
1 Height +/- 2 mm
2 Width +/- 2 mm
3 Straightness of edge +/- 1 mm
(c) Protection
BLDG19/S73.DOCX(83)
Sal(150319)
(DPG)
BSS S73
73-84 of 73-91
(d) Replacements
(e) Fixing
Set all glass in a true plane, tight and straight, with proper and
adequate clearance, firmly anchored to prevent rattling and
looseness, with all edges cleanly cut, do not nip or seam the
edges.
(f) Cleaning Up
BLDG19/S73.DOCX(84)
Sal(150319)
(DPG)
BSS S73
73-85 of 73-91
All safety glazing to the fixed panels below the cill height, described under
this clause including all subclauses under it, shall be of 12.76 mm
laminated glass comprising of 6 mm thick tinted float glass and 6 mm thick
clear float glass cemented together with 0.76 mm thick clear polyvinyl
butyral (PVB) interlayer with glazing gaskets and a shading co-efficient of
0.69, where shown in the Drawings. The tint of the glazing shall be the
same as those of the remaining glass panels when viewed from the
external and inner surfaces of the glass. The PVB interlayer shall be
Saflex RA41 or Saflex RB41 or Butacite B52 or other approved.
The laminated glass shall be of Grade A and shall comply with the relevant
requirements in SS 341:2001 as specified hereunder :
BLDG19/S73.DOCX(85)
Sal(150319)
(DPG)
BSS S73
73-86 of 73-91
The thickness limit shall comply with Table 1.1 “Thickness limits for
standard nominal thickness of glass” of SS 341:2001
The logo of the supplier which carry out the lamination of the glass panels
shall be imprinted on each and every panel of laminated glass supplied.
BLDG19/S73.DOCX(86)
Sal(150319)
(DPG)
BSS S73
73-87 of 73-91
The laminated safety glass panels shall comply with the Building
Regulations requirements - "Fourth Schedule for Parapets And
Balustrades, Table 4". The laminated safety glass panels shall be
designed to resist the loads stipulated in the said Fourth Schedule for
Parapets And Balustrades, Table 4.
The Contractor shall submit complete workshop drawings for all glazing
and aluminium Works with PE calculations and endorsement for the
approval of the SO Rep prior to its fabrication and installation. Complete
samples shall be installed at the Site for approval by the SO Rep.
73.hh.6 Replacement
BLDG19/S73.DOCX(87)
Sal(150319)
(DPG)
BSS S73
73-88 of 73-91
73.jj.1 Glazing
BLDG19/S73.DOCX(88)
Sal(150319)
(DPG)
BSS S73
73-89 of 73-91
1 Height +/- 2 mm
2 Width +/- 2 mm
3 Straightness of edge +/- 1 mm
73.jj.2 Testing
All safety glazing to the fixed panels below the cill height, described under
this clause including all subclauses under it, shall be of 13.52mm
laminated glass comprising of 6mm ±0.2mm thick clear glass and 6mm
±0.2mm thick tinted glass cemented together with 1 layer of 1.52mm thick
clear polyvinyl butyral (PVB) interlayer with glazing gaskets and a shading
co-efficient of 0.69, where shown in the Drawings. The tint of the glazing
shall be the same as those of the remaining glass panels when viewed
from the external and inner surfaces of the glass. The PVB interlayer shall
be Saflex RA71 or Saflex RB71 or Dupont (Butacite B54) or other
approved.
BLDG19/S73.DOCX(89)
Sal(150319)
(DPG)
BSS S73
73-90 of 73-91
The laminated glass shall be of Grade A and shall comply with the relevant
requirements in SS 341:2001 as specified hereunder :
BLDG19/S73.DOCX(90)
Sal(150319)
(DPG)
BSS S73
73-91 of 73-91
The thickness limit shall comply with Table 1.1 “Thickness limits for
standard nominal thickness of glass” of SS 341:2001
BLDG19/S73.DOCX(91)
Sal(150319)
(DPG)