Q: Please Advise when WIKA started building the project, their current completion

progresss (%)

A: Current Progress as per November 2019 is 41.14 %, according to the ODS,


construction work starts in 15th November 2018.

Q: The Contract between WIKA and Niger, please advise if there is any amandments
made to the contract. If yes, please submit the amandments.

A: There is not yet contract amandment to be made.

Q: What is the status/progress of the fund disbursement(s) and repayment schedules. I


understands that Exim has released the downpayment about a couple of months
ago ? would you mind sharing the disbursement and repayment schedules ? has any
repayment been made by WIKA (if any)?

A: 1st Invoice : 10 % (paid)

2nd Invoice : 16.05 % (approved, on payment process)

3rd Invoice : 3.48 % (approval process at the Nigerien ministry of finance)

4th Invoice : 11.42 % (approval process at the Nigerien ministry public works)

Total Invoice in the process : 31.14 %

Total paid Invoice : 10 %