Method Statement
Purpose
To provide work sequence of the activities for the tapping of Primary supply of HP compressor
equipment and ensuring to comply the HSE requirements of URC Calamba
Work Sequence
1. Preparation of High voltage XLPE Cable
Cutting, installation of terminal lugs and Termination Kit
2. Conduct Testing
3. Preparation of supports
4. Shut down works
Request shutdown schedule 2 weeks ahead
Ensure no connected load to open the Load break switch
Apply LOTOTO in main Load Break Switch
Check voltage using high voltage detector tester
Install grounding cluster
Install H frame /scaffolding
Disconnect existing cable
Installation of support of Fuse cut out and insulators
Install fuse cut out and insulators
Termination of cables in LBS and Fuse cut out including dismantled wires
Energization –
List of Manpower