Sample X: Determination 427

Sample X: Determination
Engineer to Parties: Determination
This document is suitable for use with the FIDIC Yellow
and Red Book

Claim [insert number] related to project [insert project name]

Dear Sirs,

I hereby give notice of my determination as to claim no. [insert number]. With


regard to all relevant facts and circumstances I determine that the Contractor is
entitled to [. . .] days of extension of Time for Completion.
I have given my approval/disapproval with comments on [. . .].
I have consulted with the Parties who have submitted the following statements:
[insert details of statements]
The Contractor has submitted
l particulars
l supported by evidence,
l including contemporary records,
l which I have monitored.
The Contractor has given notice of [. . .] on [insert date]:
l This was in time because he became aware of the relevant facts on [. . .].
l This was not in time because became aware of the relevant facts on
[. . .].
In accordance with Sub-Clause [. . .] the Contractor is entitled to extension of Time
for Completion. In accordance with Sub-Clause 8.4 the relevant event must have an
impact on an activity which lies on the critical path. Both requirements are met:
[Insert reasons]

Yours faithfully

(Engineer)