You are on page 1of 7

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/299516367

WINDFARM GROUNDING

Conference Paper · March 2016

CITATIONS READS

0 66

1 author:

Paulo Edmundo Fonseca Freire


PAIOL Engenharia
28 PUBLICATIONS   15 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Belo Monte HVDC transmission system View project

Brazilian Grounding Standards View project

All content following this page was uploaded by Paulo Edmundo Fonseca Freire on 31 March 2016.

The user has requested enhancement of the downloaded file.


2016 CIGRE C4 International Colloquium on EMC, Lightning and Power Quality
Considerations for Renewable Energy Systems

WINDFARM GROUNDING

Paulo Edmundo da F. Freire


PAIOL Engenharia
Unicamp
Paulínia, Brazil
paulofreire@paiolengenharia.com.br

Abstract— This paper presents a review of the typical design  the typical grounding of each wind turbine comprises two
and the commissioning methodology of wind farm grounding rings of 70 mm² bare copper cables, interconnected to the
system. This kind of large area generating plant is often built steel reinforcement of the tower foundation, and these
on high resistivity grounds. The wind turbines are structures rings may be complemented by steel-copper rods and by
highly exposed to lightning, due to its height and geometric radial grounding conductors;
aspect, besides being located in treeless and lightly undulated  the foundations of neighboring towers are eventually
plains. High ground resistivity results in high grounding joined by buried bare copper cable or by the shield wires
resistances for the towers individually, and for this reason, the of the 34.5 kV lines.
design of a windfarm grounding system needs to be conducted Windfarms and their medium voltage transmission lines, can
in an integrated manner, considering at least the contribution be classified as facilities with extreme exposure to the effects
of the foundations reinforcement steel and the interconnection of lightning, usually due to a combination of several critical
of the towers’ bases within a wind turbines cluster. conditions, such as:
The design of grounding systems of large facilities, such as  unsheltered areas, sometimes very exposed to the direct
industrial complexes, petrochemical, power plants etc., with incidence of lightning;
dimensions of the order of hundreds of meters, are usually  very tall towers, which favor the formation of ground-to-
developed with the same methodology applied to conventional cloud lighting;
substations, which typically have dimensions on the order of  high resistivity ground, which makes it difficult to obtain a
tens of meters. good grounding;
This work presents the limitations of the typical methods used  very frequently the interconnections are done by overhead
for the design of wind farms grounding systems, and suggests medium voltage lines, also very exposed to the effects of
a more compatible approach, considering the following direct and indirect lighting.
aspects: The grounding of a wind turbine tower can be analyzed from
 resistivity measurements and geoelectric modeling of the the point of view of two parameters:
ground;  impulsive impedance - ground response to a current
 simulation of large groundings, considering the non- impulse, the case of the front wave of a lightning, which is
equipotentiality of this kind of system; and the ground impedance viewed by the lightning at t = 0+,
 the need to reduce the transient impedance of the wind immediately after its incidence; and
turbines groundings, considering its lightning performance.  leakage resistance - valid for low frequencies, as is the
case of a short-circuit to ground in the medium voltage
Keywords — windfarm; grounding; lightning protection. network, which can be seen as the resistance to the impulse
tail that appears after the transient associated with the
I. CHARACTERISTICS OF THE WINDFARMS lightning front wave.
The typical wind farm has the following structure:
 wind turbines separated from each other for about 400 m,
II. DESIGNING AND COMMISSIONING CONSIDERATIONS
generating energy at low voltage (400 V to 600 V);
 a transformer located in a cubicle at the base of each A. Restrictions to the Typical Design Methodology
turbine raises the voltage to 34.5 kV, feeding an overhead
The grounding design of windfarms very often is limited to a
or underground energy collecting network;
typical drawing of the tower base grounding, and when
 the turbines are grouped within one or more windfarms,
resistance calculations are done, uniform ground model is
which are interconnected by medium-voltage lines to an
used. Ground models are obtained based on a few resistivity
interface substation, which makes the interconnection with
measurements, usually made by the Wenner technique with
the transmission system;
spacing, at most, ranging up to 32 m.

1
 the non-equipotentiality of the grounding system, which
due to its dimensions, certainly will result on potential
B. Restrictions to the Typical Commissioning Practice
differences, even for power short-circuits (60 Hz), and
The grounding resistance and step/touch potentials  the ground model – which shall be representative of the
measurements, usually performed when commissioning the specific windfarm subsystem that is being studied, what
facilities, are very frequently unreliable. Typically, the may be a tower cluster or the interface substation.
resistance is measured with low power equipment and using The windfarm grounding design should start with a field
small distances for the remote current probe, incompatible campaign for the measuring of ground resistivity, including
with the size of the base of the wind turbines and the the following set of electroresistivity soundings:
resistivity of the local ground. The usual practice is to apply  by the Wenner arrangement, with up to 64 m spacing at the
the potential drop method, with the measurement of only three construction site of each tower and also at the substation;
points on the ground, at a distance about 62% from the total
 by Schlumberger arrangement, with higher spacing (if
tower to current probe spacing (between 50 to 100 m), without
possible up to 1000 m between current probes) at selected
the construction of the complete resistance curve, and taking
alignments, preferably coincident with the towers rows.
the average of the three resistances as the grounding resistance
These soundings should be complemented by the geotechnical
of the tower.
survey of the area, with the evaluation of the local lithology
As the ground where the windfarms are constructed present,
and geological structure.
usually, high resistivity, and considering that the remote
Based on this data it is possible to build ground models that
electrode current is not located at a sufficient distance to
are effectively representative of the ground volumes involved
ensure uncoupling with the base of the tower, the measured
in the dissipation processes of electrical currents into the earth,
resistance is actually only a fraction of the real value, allowing
upon the occurrence of lightning or short circuits to ground.
to the wrong conclusion that the resistance is low and
From the electrical and civil drawings, it can be evaluated the
acceptable.
options of grounding system for the windfarm. At this stage of
It should be noted that the higher the ground resistivity, the
the work is necessary the availability of a short-circuit study,
farthest the remote current probe shall be positioned, for the
considering faults phase-to-ground at the substation buses and
correct measurement. For the typical windfarm, the proper
at the medium voltage cubicles at each tower. This short-
distance between the remote current probe and the tower base
circuit study should determine the phase-to-ground short
is usually much higher than three times the base diameter.
circuit currents, including the contributions of the lines that
Another typical situation in the field is the resistance
feed each faulting point. The study of the windfarm grounding
measurement without verifying if the base of the tower is
system shall include two types of simulations:
connected to the neighboring towers, either through bare
 phase-to-ground faults in the medium and high-voltage
copper buried cable or by the shield wires of the medium
systems (60 Hz); and
voltage transmission line.
In the case of step and touch potentials measurement, the  injection of high frequency current (25 kHz) on the towers
difficulty is the same, as the reference source used to simulate bases, in order to simulate lightning.
the short-circuit needs to be enough spaced from the base of This set of simulations allow for the evaluation of the selected
the tower, under the risk of measuring only fractions of true grounding topology for the windfarm, resulting on the
step and touch potential. Here also, it is important to take into following information:
account the existence of ground interconnections with other  design values of the resistances of the substation grounding
towers and substation, and also the measuring alignment with grid and of the windfarm towers, at 60 Hz and 25 kHz;
respect to buried cables.  step and touch potential mapping in the substation and on
It can be concluded that the commissioning tests of the the bases of the towers;
grounding system of a wind farm is dependent not only from  transferred potential between different parts of the
the local ground characteristics, but also on the topology of the windfarm, in the event of faults to ground.
grounding system and on the construction stage of the Among the results of the grounding studies, it shall be defined
windfarm. The complexity of this process requires a field team if the substation grounding grid has to be interconnected the
that knows very well the work to be done, familiarized to the towers groundings.
grounding design of the wind farm and with the
commissioning procedures.
IV. GROUNDING PERFORMANCE AT HIGH-FREQUENCIES
The application of sinusoidal high-frequency currents for the
III. WINDFARM GROUNDING DESIGN evaluation of a grounding grid, either as a field measurement
Among the various aspects that shall be considered in this type or by a computer simulation, is a useful method for the
of project, it is worth to mention: evaluation of the ground response to the wave front of a
 the grounding of the windfarm as a whole, including the lightning discharge.
tower bases, buried interconnections, medium voltage
shield lines and the interface substation;

2
The IEEE Guide 81/1983 - "IEEE GUIDE FOR V. SIMULATION OF TOWER GROUNDINGS
MEASURING EARTH RESISTIVITY, GROUND It was simulated a few different configurations of wind turbine
IMPEDANCE", in item 12.6 "High-Frequency Earth groundings, considering two uniform soil resistivity values:
Resistance Meter", presents the technique for the measurement 550 Ωm (medium resistivity) and 1000 Ωm (high resistivity).
of grounding resistance of transmission line towers with an Figure 3 shows the simulated groundings, constituted by the
equipment that operates at 25 kHz. steel foundation reinforcements of a 16 m tower base
For the evaluation of the response of wind turbine towers to diameter, 13 m long vertical anchor bolts and a 70 mm² bare
direct lightning, the technical literature recommends the use of copper wire ring, 19m in diameter, on the outer perimeter of
the 10/350 wave, which is characteristic of positive polarity the tower base.
lightings generated at the top of high and thin structures
(which are only 1% of the lightning). These structures are
considered "triggers" of ground-to-cloud lightning, which VI. EVALUATION OF THE SIMULATIONS
have return strokes with higher peak values (dependent on the In the following evaluations, to facilitate the understanding of
wave front) and energy (associated with long wave tail). The the text, the 60 Hz calculated values are treated as grounding
10/350 wave simulates also the effect of the superimposition resistances, while the 25 kHz calculated values are treated as
to the lightning surge current, of the traveling wave resulting ground impedances.
from the reflection/refraction process of the lightning return It shall be noted that the grounds constituted by lumped
wave at the top and the base of the tower. elements (foundation reinforcement, anchor bolts, copper
The sine wave at 25 kHz has the period (T = 1/freq.) of 40 μs cable rings or relatively short radial conductors) present quite
and is situated around the middle of the range from 1 to 40 similar resistance and impedance values, but when the long
kHz, where the 10/350 standard impulse wave presents the wires are applied (which are the only solution for effective
largest energy content. Also, both the 25 kHz sine wave and reduction of ground resistance), the resistance values are
the 10/350 μs impulse take the same 10 s to reach the peak reduced more than the impedance values. It is evident that the
value. It can be considered, therefore, that the grounding performances of the grounding for short-circuits and lightning
response at the frequency of 25 kHz is a good approximation are quite different.
of the 10/350 standard impulse wave. For separated towers, where the grounding is provided only by
the steel reinforcements of its foundation and by the 70 mm²
Fig. 1. Superposition of a 25 kHz senoidal wave on the 10 x 350 s standard bare copper cable rings, the ground resistivity of 550 Ωm
impulse wave.
results on almost equal values for the resistance and
impedance, around the 10 Ω threshold design value typically
specified by the wind turbines manufacturers. For 1000 Ωm
ground resistivity, the simulations show that the local
grounding alone is not able to comply with the 10 Ω criterion.
The complementation of the foundation ground with four rods
9 m deep results in a less than 10% reduction of the grounding
resistance and impedance values. The connection of two
relatively short radial conductors (50 m in length) promotes a
reduction of about 25% of the resistance and impedance
values, not enough to attend the desired limit of 10 Ω at high-
resistivity grounds. In these grounds, only the use of long
counterpoises enables the resistance and impedance reduction
to values below 10 Ω.
In Tables 1 and 2, the simulations are sorted in descending
order of grounding resistance, and it can be seen that longer
groundings present lower resistances. The analysis of the
impedance values shows a not so systematic variation, which
depends on the extension and also on the number of radial
conductors.

3
TABLE I. CALCULATED RESISTANCES/IMPEDANCES FOR UNIFORM RESISTIVITY GROUND MODEL

ρ = 550 Ωm ρ = 1000 Ωm

Grounding Configuration R (60 Hz) Z (25 kHz) R (60 Hz) Z (25 kHz)

1 Single AG (fig. 4a) 9,59 Ω 9,63 Ω 17,43 Ω 17,47 Ω


2 AG + 4 x 9 m rods (fig. 4b) 8,65 Ω 8,72 Ω 15,72 Ω 15,78 Ω
3 Single AG with 2 x 50 m radial counterpoises (fig. 5a) 7,07 Ω 7,50 Ω 12,85 Ω 13,17 Ω
4 Single AG with 4 x 50 m radial counterpoises (fig. 5b) 5,39 Ω 5,88 Ω 12,25 Ω 12,39 Ω
5 Single AG with 2 x 100 m radial counterpoises 4,93 Ω 7,12 Ω 8,96 Ω 10,83 Ω
6 Single AG with one 250 m radial counterpoise (fig. 6a) 4,19 Ω 9,09 Ω 7,60 Ω 15,07 Ω
7 Two AG interconected by a 250m counterpoise (fig. 6b) 3,21 Ω 4,68 Ω 5,84 Ω 7,83 Ω

Fig. 2. Geometry and dimensions of the grounding and tower foundation of the simulated AG base.

Fig. 3. Basic grounding and tower foundation and improvement with 4 x 9 m rods.

4
Fig. 4. Application of two and four 50 m radial counterpoises.

Fig. 5. Single and two AG interconected by 250 m counterpoise.

5
VII. CONCLUSIONS
The impedance grounding "viewed" from the point of
application of the disturbance is be different, depending on the
disturbance nature - a short-circuit (low frequency) or a
lightning (high-frequency). This fact is extremely important
for the analysis of grounding systems that are spread over
wide areas, with several square kilometers, as is the case of
windfarms.
For the medium or low-resistivity grounds (below 500 Ωm),
the foundations steel reinforcement is enough for obtaining
resistance and impedance below than 10 Ω (depending on the
dimensions of the tower base). For the high-resistivity grounds
(above 1000 Ωm), the complementation of the local grounding
with counterpoises is important to reduce the resistance and
impedance values to the required 10 Ω.
For a given condition of geoelectric structure, only by carrying
out simulations of different grounding combinations it can be
possible to optimize the performance of the grounding system
for both short-circuits and lightning discharges.
Finally, it is worth remembering that, in general, the
measurement of grounding resistance of wind turbine towers
with conventional earth meters, which work with low
frequency, will not result in reliable values, mainly for
grounds with high resistivity or in the case long
complementary grounding conductors. In these cases, it is
important to measure the impedance grounding by means of a
high-frequency ground meter (25 kHz).
This statement it is not new at all, since the IEEE Guide
81/1983 - "IEEE GUIDE FOR MEASURING EARTH
RESISTIVITY, GROUND IMPEDANCE", in item 12.6
"High-Frequency Earth Resistance Meter", proposes and
recommends the measuring of ground resistance of
transmission line towers, by means of an earth meter which
operates at a frequency of 25 kHz.

VIII. REFERENCES
[1] IEC-TR61400-24 - Wind Turbine Generator Systems - Part 24:
Lightning Protection
[2] Paulo Edmundo da F. Freire e Edgard Pane, Sistemas de Aterramento de
Parques Eólicos, Brazil WindPower 2012, Rio de Janeiro, agosto/2012
[3] Paulo Edmundo da F. Freire, Ariel Costanzo, Marcos Villarreal, Edgard
Pane, Parque Eólico Água Doce – Medições de Resistividade do solo e
de Resistências de Aterramento, Brazil WindPower 2013, Rio de
Janeiro, agosto/2013
[4] Paulo Edmundo da F. Freire, Medição de Aterramentos com o
Terrômetro de Alta-frequência – Aplicação a Parques Eólicos, ENIE
2014, São Paulo, agosto/2014
[5] Heidler F., Zischank W., Flisowsky Z., Bouquegneau Ch., Mazzetti C,
Parameters of Lightning Current Given in IEC-62305 – Background,
Experience and Outlook, 29th International Conference on Lightning
Protection, Uppsala/Sweden, jun/2008

View publication stats

You might also like