You are on page 1of 13

Ain Shams Engineering Journal 10 (2019) 731–743

Contents lists available at ScienceDirect

Ain Shams Engineering Journal


journal homepage: www.sciencedirect.com

Electrical Engineering

Harmonic resonance overvoltage due to main transformer energization


in large wind farms, Zafarana, Egypt
Ahmed Fouad a, Mostafa Elshahed b,⇑, Mahmoud Sayed b, Mahmoud Gilany b
a
Egyptian Electricity Transmission Company, Ministry of Electricity, Egypt
b
Electric Power Dept., Faculty of Engineering, Cairo University, Egypt

a r t i c l e i n f o a b s t r a c t

Article history: When a large power transformer is energized, a high magnitude inrush current may result in harmonic
Received 24 March 2018 resonance overvoltage (HRO), if the system has resonance phenomenon. Such overvoltages may cause
Revised 27 February 2019 large stresses on the system. This paper investigates the energization of two winding 220/22 kV main
Accepted 3 April 2019
power transformer in a weak system of a grid-connected wind farm. To achieve this aim, the produced
Available online 15 May 2019
HRO during the energization of the main power transformers and the affecting factors are investigated.
In addition, the effect of the sympathetic inrush phenomena is studied. Finally, the sequential energiza-
Keywords:
tion of the three-phase transformer and the pre-insertion resistor method are discussed as mitigation
Grid-connected wind farms
Harmonic resonance overvoltage
methods. The investigated scenarios and results will contribute in developing the power system restora-
Pre-insertion resistor tion procedures for existent wind farm, its extension, and future-planned wind farms.
Sequential energization of transformers Ó 2019 The Authors. Published by Elsevier B.V. on behalf of Faculty of Engineering, Ain Shams University.
This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-
nd/4.0/).

1. Introduction the arrangement of system elements. If one of the frequencies pro-


duced by the inrush current is equal to or close to one of the sys-
Wind farms have been widely used recently, Zafarana wind tems low resonant frequencies, harmonic resonance overvoltage
farm is one of the largest wind farms in Egypt. The Medium Voltage (HRO) occurs [4,5].
(MV) cables and the wind turbine transformers (WTT) in Zafarana Overvoltage is considered a more serious problem in wind
always suffer from repeated insulation breakdown. Such problems farms than in conventional power stations for the following
are general and well-known in grid-connected wind farms [1,2] reasons:
and are not limited to Zafarana. This ensures that there are unde-
sired overvoltages produced especially during the main transform-  Wind farms are characterized by repeated switching of different
ers energization. There is shortage of studies and information types of equipment due to frequent change in wind speed, in
related to such problems [2]. Therefore, it is important to investi- addition to the need for periodic different equipment mainte-
gate these behaviors to introduce a suitable mitigation for over- nance. The repeated energization of the main transformers
voltage due to transformers energization. may lead to high magnitudes of inrush currents which are
The energization of the main transformer may lead to high enriched with harmonics of different orders.
magnitudes of inrush current which are enriched with harmonics.  Wind farms have a large number of cables used to connect
The attendant frequencies due to transformer energization phe- between different types of equipment. These cables increase
nomenon always vary from the fundamental power frequency up the system capacitance leading to an increased probability of
to about 1 kHz [3]. Low resonance frequencies may exist due to resonance phenomenon occurrence.
 Wind farms are always designed far from the grid and the over-
⇑ Corresponding author. head transmission lines (OHTLs), connecting between wind
E-mail address: m.elshahed@eng.cu.edu.eg (M. Elshahed). farms and the grid, are usually long. This may lead to consider-
Peer review under responsibility of Ain Shams University. ing wind farms as weak systems with low MVA fault levels
[6–8].

Production and hosting by Elsevier

https://doi.org/10.1016/j.asej.2019.04.002
2090-4479/Ó 2019 The Authors. Published by Elsevier B.V. on behalf of Faculty of Engineering, Ain Shams University.
This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/).
732 A. Fouad et al. / Ain Shams Engineering Journal 10 (2019) 731–743

The produced HROs are temporary overvoltages lasting for during energization of main power transformers in wind farms is
some cycles and taking the form of undamped or slightly damped investigated.
oscillations at a definite frequency [9–11]. Different factors affecting HRO are investigated including num-
Some affecting factors exist on HROs are overviewed in [12]. ber and lengths of MV feeders connected on secondary of any par-
These factors are the transformer to be energized rating, the source allel on-line transformer. Moreover, the sympathetic inrush
fault level, the circuit length, the loads, the system voltage profile, phenomena effect is also studied. Finally, the most common-used
and the transformer flux density. methods of overvoltages mitigation including sequential energiza-
It can be said that, factors affecting inrush current affect also tion of the three-phase transformer and pre-insertion resistor
HROs. In addition, the type of resonance, which may be series res- method are assessed in damping worst scenarios that may occur.
onance [1,12] or parallel resonance [5,14], affects HRO. The system
natural frequency (fn) also affects HRO. Finally, the wind farm site
2. System description and modeling
with respect to the grid determines the degree of overvoltages
damping [6–8].
The system under study, shown in Fig. 1, consists of two 75
Overvoltages may lead to protection disturbances, equipment
MVA, 220/22 kV, main transformers (TR1 and TR2) connected from
problems, and consumer problems. The protection disturbances
primary sides to the same bus bar (substation 1) which is con-
are represented in mal-operations of protection system, especially
nected to the 220 kV grid by two, 220 kV, OHTLs. The secondary
the unnecessary tripping of overvoltage over-fluxing relays. Over-
side of the first transformer (energized transformer), TR1, is always
voltages may result in large stresses in equipment involved and
open. The secondary side of the second transformer, TR2, may be
overheating causing damage and destruction of different system
connected to one, two, three, four, or five, 22 kV, feeders.
equipment as insulators, cables [1], circuit breakers, and protection
The MV Feeders are symmetrical, each one is 22 kV, 500 mm2,
elements. The repairs or replacements of these elements are costly.
CU cable connected to 12 WTT rated at 1.1 MVA and 22/0.69 kV;
As for transformers, the overvoltages may cause deterioration
the WTTs are tied to each other from the primary side by 22 kV,
and collapse of weak spots; in both insulators and mechanical sup-
AL cables. Each WTT is responsible for transmitting the generated
port structures of the transformer windings which lead to trans-
power from 0.85 MW, 0.69 kV wind turbine generators to the
former breakdown [2]. There were recorded accidents in different
22 kV side.
wind farms [1,2] may classify wind farms as hazardous systems.
The study addresses mainly on no-load energization of the first
Power quality problems may also be a nuisance to consumers
transformer, TR1, in two main case studies. In the first case study,
and result in complaints to network operators due to oscillations
the first transformer (TR1) is energized whereas the second trans-
and flickering of network user lights. This may cause continuity
former (TR2) is off-line, so this case takes into consideration only
disturbance of power delivery leading to a generating system low
the outer power grid and OHTLs effects. In the second study, the
reliability.
first transformer (TR1) is energized while the second one (TR2) is
There are several kinds of literature available about HRO excita-
on-line. This case takes into consideration the effect of wind farm
tion due to inrush currents [4–17]. The HRO in different portions of
elements in addition to the outer power grid and OHTLs effects.
power system is discussed as follows:
In both cases, the secondary of the energized transformer is always
open.
i. The resonance overvoltages due to cable energization [12].
Transient events have a short duration and need special treat-
ii. The resonance overvoltages in HVDC systems due to ener-
ment in modeling to consider the wide range of frequencies. The
gization of converter transformers [16,17].
range of frequencies, attendant to transformer energization, varies
iii. The resonance overvoltages in industrial applications; due to
from fundamental power frequency up to about 1 kHz, therefore
energization of furnace power transformers [14].
the frequency dependent modeling of different system equipment
iv. The resonance overvoltages due to system restoration
such as main transformers and cables should be conducted. The
[5,9,10].
studies used PowerFactory DIGSILENT program. The whole sys-
tem consists of the external grid, transformers, transmission lines,
Although there are many studies about HRO excitation from
and cables. The following subsections describe different system
inrush currents as reported in [4,5,9], and [15] but there are still
elements modeling.
other system components that affect the HRO. The researchers
have concentrated on consequences of single transformer ener-
gization connected to a long OHTL or cable, known as ‘‘system 2.1. Source (External Grid)
restoration case”. In such cases, the factors influencing HRO are
the OHTL and transformer parameters. Investigation of other ele- The Egyptian transmission grid at substation 2, shown in Fig. 1,
ments effects such as connected to the secondary side on-line has max S.C current of 16.6 kA, and X/R ratio is 8.8. It is modeled
transformer feeders in wind farms are is necessary. according to PowerFactory DIGSILENT manual [18].
The relation between HROs and natural system frequency
reported in [5,16] are not fully studied. There is still lack of infor- 2.2. Main transformers
mation about the dynamic behaviors of wind farms and uncom-
pleted explanation of HRO phenomenon. There are two main transformers in under-study system shown
The objective of this paper is to study HRO problems in wind in Fig. 1. The basic parameters of these transformers are shown in
farms and their relation with system natural frequency. This paper Table 1. The transformer model is based on type/time simulation.
assesses the simulation model to study resonance overvoltage fol- The time for needed simulation here is short, and currents would
lowing the energization of a 75 MVA 220/22 kV main transformer flow such as displacement currents in the capacitive of windings.
in a weak system. Although Zafarana is an existing wind farm with Thus, capacitances between windings and winding to ground
existing equipment, the investigated scenarios and results will should be included in the transformer model [3]. Fig. 2 shows val-
contribute in developing the power system restoration procedures ues of different capacitances in the main transformers taken from
for existent wind farms, its extension, and future-planned wind onsite tests after transformer installation. The values of stray
farms taking into consideration the plans to extend wind farm pro- capacitance are taken from the transformers datasheet in the
jects to contribute to the energy mix. To achieve this aim, the HRO Zafarana WF.
A. Fouad et al. / Ain Shams Engineering Journal 10 (2019) 731–743 733

Fig. 1. System under study.

Table 1
Basic parameters of the main transformer.

Rated power (MVA) Voltage (kV) Vector group No load loss (kW) Impedance voltage (%) Short circuit loss (kW)
75 220 / 22 Yn D 11 43 11.78 215

The nonlinear magnetizing curve is shown in Fig. 3a. When the


transformer is de-energized, the magnetizing current goes to zero
directly and magnetizing field strength is removed while the flux
follows the hysteresis loop of the core as shown in Fig. 3b. As a
result, the Ferromagnetic material of the transformer core retains
some remnant flux [8]. The magnitude and direction of remnant
flux are based on instant of de-energization and transformer core
material. This remnant flux will be stored in the magnetic core till
another energization. It is modeled in DIGSILENT as psimd event
(residual flux) which is assumed to be 0.9p.u as a worst value
[18]. The magnetizing characteristics depend mainly on data given
in Table 2 in addition to basic data given in Table 1.

2.3. Transmission lines and cables

Fig. 2. Stray capacitances of the 220/22 kV transformer. The distributed parameters models are used for modeling
OHTLs in PowerFactory DIGSILENT. The parameters of OHTLs are
shown in Table 3.
In order to simulate nonlinear electromagnetic transients such There are high numbers of medium/low voltage cables in wind
as transformer inrush currents, the core saturation (magnetizing farms. The cable model should take into consideration frequencies
characteristics) must be included in the transformer model [19]. attendant to transformer energization which ranges from funda-
734 A. Fouad et al. / Ain Shams Engineering Journal 10 (2019) 731–743

Fig. 3. Main transformer characteristics; (a) nonlinear magnetizing curve, (b) hysteresis loop curve.

Table 2 are modeled using the frequency dependent distributed parameter


The magnetizing curve data for main transformers. model in DIGSILENT program, according to J Marti model [21]. The
Knee voltage (p.u) Magnetizing current (%) Saturated reactance (p.u) parameters of cables are taken from manufacturer catalog [22].
1.19 0.07 0.09

3. Methodology

mental power frequency to 1 kHz [20] due to the changing of con- As discussed before, the energization of main power trans-
ductor impedance with applied power frequency. Therefore, cables former may cause harmonic resonance overvoltage (HRO), if the

Table 3
The parameters of overhead transmission lines.

Positive sequence parameters Zero sequence parameters


Resistance R (O/km) Reactance X (O/km) Susceptance B (lS/km) Resistance Ro (O/km) Reactance Xo (O/km) Susceptance Bo (lS/km)
0.06 0.306 3.25 0.13 0.83 2.3
A. Fouad et al. / Ain Shams Engineering Journal 10 (2019) 731–743 735

 pffiffiffiffiffiffi
system has low resonance frequency and if one of the harmonics f n ¼ 1= 2p LC ð1Þ
produced due to transformer energization inrush current coincides
with this resonance frequency. In the following parts, the HRO fol- Since the natural frequency is inversely proportional to the
lowing the transformer energization is investigated in the system square root of system capacitance, it can be deduced that with
shown in Fig. 1 using the PowerFactory DIGSILENT program, with increasing the OHTLs length, the system natural frequency will
the aid of transient model, discussed before. The first transformer decrease as clearly shown in Fig. 5. In addition, Fig. 5 shows that
(TR1) is energized (by closing S1) from 220 kV side while the sec- there is one system natural frequency corresponding to each OHTL
ondary side is open (S2 in Fig. 1 is always open). The energization is length. The relation between HRO and OHTLs lengths does not
examined in two cases as follows: have a regular trend and cannot be expected as shown in Fig. 5.
This is because the variation of the HRO with OHTLs lengths is
i. Absence of on-line transformers
based on two factors; the system resonance frequency (which is
In this case, TR1 is energized while no other transformers are affected by OHTLs length as discussed before) and the related har-
connected. The influencing elements on produced overvoltage are monic inrush current contents (which may randomly have high or
the external grid and OHTLs. In this case, lengths of OHTLs (L1 low values affected by the nonlinear magnetization or energized
shown in Fig. 1) are equally changed from 70 to 120 km with transformer saturation).
5 km step. The produced HRO is examined in each step. The over-
voltage peak at PCC (Point of Common Coupling) is recorded and
examined to investigate the effect of OHTLs lengths on resultant 5. MV cables lengths effect
overvoltage.
In the previous case study, the energization of a single trans-
ii. System with one on-line transformer former is done while the second one is off-line. The overvoltage
In this case, TR1 is energized (by closing S1) from 220 kV side at peak of a 1.22p.u occurred at a 551 Hz natural frequency as shown
no load (S2 is open) with existence of one on-line transformer TR2 in Fig. 5. In the next case study, the transformer is energized in
(S3 and S4 were previously closed). This case has five subcases of existence of another on-line transformer connected to MV feeders
energization; the subcases are different in number of feeders con- on its secondary side. The effects of the number/lengths of the MV
nected to secondary TR2 side. In each subcase, the lengths of MV feeders on the produced overvoltages are evaluated. HRO in this
Copper cables (L2, L3, L4, L5, and L6 shown in Fig. 1) are equally case study is examined at the 95 km length of the OHTLs.
changed from 1 to 20 km with 1 km step and in each step, TR1 is i. Changing overvoltage peak values with lengths of main
energized. cables
The overvoltage peaks at PCC are recorded to investigate the
effect of on-line transformer as well as the effect of the MV feeders Fig. 6 shows the effect of the number and lengths of MV feeders,
(quantity and the lengths) on resultant overvoltage. The voltage connected to the secondary on-line transformer (TR2) on HRO
source and the instant of circuit breaker closing are constant in peaks. It is shown that overvoltage peak values start with small
all simulations. The general form of the instantaneous voltage values when using small MV cables lengths. Increasing lengths will
wave at PCC after transformer energization is shown in Fig. 4. increase overvoltage peak values reaching severest values at
The harmonic overvoltage peak at PCC, shown in Fig. 4, is recorded lengths equal or closer to 10 km. Increasing cable lengths beyond
in all simulations. certain limit will decrease overvoltage peak values. This sequence
occurs when using one, two, three, four, or five feeders.

ii. Changing of the overvoltage peak values with system nat-


4. OHTLs lengths effect
ural frequencies (resonance frequencies)

In this case study, the main transformers are energized in The system natural frequencies are changed due MV cables’
absence of on-line transformers during the energization. The length changing. Fig. 7 shows that the overvoltage peaks at PCC
drawn inrush current by the energized transformer flows from varies with the variation of the system natural frequencies which
the external grid passing through both OHTLs, and as a result; varied with the number of MV feeders connected to the secondary
the OHTLs’ parameters have a dominant effect on produced of the already-connected transformer TR2. Fig. 7 shows that ener-
HRO. In such case, the system generation units cause low damp- gization of main transformer in existence of an on-line transformer
ing for voltage fluctuations as discussed above. There are two connected to one, two, three, four, or five feeders on its secondary
OHTLs in the system under study as shown in Fig. 1. The effect side will nearly produce a natural frequency range from 495 Hz to
of their lengths on HRO peak value produced from transformer 560 Hz.
energization is investigated in this section during system The 560 Hz frequency occurs with small lengths of MV cables
restoration. (near 1 km). The 495 Hz frequency occurs with relatively long
The produced inrush current has a very high magnitude that lengths of cables (near 20 km). That is because increasing MV
exceeds 2100A in its first half cycle of phase (A) and hence, the cables lengths will increase system capacitance which in turn
remnant flux in phase (A) has been chosen at maximal. This value decreases the system natural frequency, as discussed earlier. Exis-
has a slight change in the different simulations. Fig. 5 shows the tence of on-line transformer connected to MV cables in its sec-
effect of OHTLs lengths on overvoltage peak produced during ener- ondary side with a low length of their main cables results in an
gization of a single transformer, TR1, while TR2 is off-line. addition of relatively inductive impedance parallel to the system.
Transformer energization leads to high magnitude of inrush This causes an overall decrease in system inductance which in turn
currents rich in harmonics. The transformer under such conditions increases the natural frequency from 551 Hz as shown in Fig. 5 to
is considered as a current source injecting harmonics current nearly 560 Hz as shown in Fig. 7.
including a frequency component equal to the resonance fre- The feeders consist of WTTs and wind turbine generators that
quency [16,14]. The AC grid produces fundamental frequency com- have nearly inductive impedances. Adding a new feeder will cause
ponent only. Increasing the OHTLs length will increase system a decrease in overall system impedance due to addition of new
overall parallel capacitance. The system natural frequency is given parallel impedance. Decreasing system impedance provides more
in Eq. (1). damping due to the decrease in parallel resonance impedance
736 A. Fouad et al. / Ain Shams Engineering Journal 10 (2019) 731–743

Fig. 4. Instantaneous voltage at PCC after transformer energization in p.u; (a) Instantaneous voltage waveform, (b) Magnification of the period which contains the overvoltage
peak.

Fig. 5. Variation of overvoltage peaks in p.u and corresponding system natural frequencies in Hz at PCC with the lengths of the OHTLs.

[5]. This damping is observed in Figs. 6 and 7 which show that the equal to 10 km as shown in Fig. 6. The system natural fre-
severest overvoltage peak for a system including only one feeder is quency, in this case, is 541.2 Hz as shown in Figs. 7 and 8. Ener-
1.55p.u while the severest overvoltage for a system including five gization of transformer TR1 in this system produced 1.534p.u
feeders is 1.49p.u. overvoltage peak at PCC as shown in Fig. 9. The results of apply-
ing Fast Fourier Transform (FFT) on the waveforms shown in
iii. Severest overvoltage values
Fig. 9 are presented in Fig. 10. As expected, the voltage wave-
To explain the severest overvoltage production, two-feeder form contains a high content frequency of 541.5 Hz. Therefore,
system is taken into consideration as an example. The system it can be deduced that the severest overvoltage value is
includes two feeders connected to the on-line transformer sec- expected to appear when the voltage waveform during energiza-
ondary side. The severest overvoltage peak in the two-feeder tion contains harmonic equal or very close to the system natural
system is produced when the length of both cables (L2, L3) is frequency.
A. Fouad et al. / Ain Shams Engineering Journal 10 (2019) 731–743 737

Fig. 6. Variation of the overvoltage peaks at PCC with the lengths of the MV cables using one, two, three, four, and five feeder systems while OHTLs’ length is 95 km.

Fig. 7. Variation of the overvoltage peaks at PCC with the system natural frequencies using one, two, three, four, and five feeder systems while OHTLs’ length is 95 km.

Fig. 8. Impedance frequency characteristics when using two-feeder system.

iv. MV cables critical lengths increased from 1.22p.u to nearly 1.55p.u with the existence of
MV cables with critical lengths close to 10 km. Any wind farm with
From Figs. 4 and 9, it is clear that the peak value of the produced definite OHTLs length will have its own critical range of cables’
harmonic overvoltage in a wind farm with 95 km OHTL may be lengths that will produce severest overvoltage peak values. Fig. 7
738 A. Fouad et al. / Ain Shams Engineering Journal 10 (2019) 731–743

Fig. 9. Instantaneous voltage waveform at PCC when using two-feeder system.

Fig. 10. FFT of the produced overvoltage at PCC in p.u when using two-feeder system.

shows that the operating frequency range with one feeder system u to 1.433p.u. It is observed that, overvoltage value has been dou-
extends from 535 Hz to 548 Hz (narrow bandwidth). This range is bled due to existence of on-line transformer. There is lower decay
increased gradually when increasing the number of connected MV- in duration of inrush current. The sympathetic inrush current is
feeders in the secondary of the on-line already connected trans- one of the problems related to inrush current phenomenon. It usu-
former. The range extends from 495 Hz to 560 Hz (wide band- ally makes the inrush current behavior worse as it reduces damp-
width) with the five feeder system. The increased operating ing of inrush current causing an increase in its decay time. This
frequency range or bandwidth will enable having a wide range of increased duration of inrush current can lead to lower damping
cable lengths far from the severest overvoltage peak values and in inrush current related problems such as HRO. The on-line trans-
hence providing a more stable system. former, TR2, causes new sympathetic inrush current in its primary
side as shown in Fig. 14 during the energization of TR1. This sym-
6. Sympathetic inrush phenomenon pathetic inrush caused longer decay of both inrush current drawn
by TR1 and HRO at PCC.
In this section, the effect of the existence of another on-line un-
loaded transformer in parallel with the transformer to be energized
is investigated. The un-loaded (S4 was previously open) to show 7. Mitigation of harmonic resonance overvoltages
only the effect of the sympathetic inrush current on HRO. The
length of OHTLs is kept constant at 95 km. The results for energiz- The followings are the most common used mitigation methods
ing TR1 are compared when TR2 is off-line (S3 was previously of inrush current/HRO. The sequential energization of three phases
open) and when TR2 is on-line (S3 was previously closed). Ener- of transformer (controlled switching of the three phases) and the
gization is achieved by closing S1 in the system shown in Fig. 1 pre-insertion resistor are used to damp the worst operational sce-
for both cases. Fig. 11 shows impedance-frequency characteristic narios in Zafarana wind farm.
seen at system PCC. The natural frequency of such system is
i. Sequential energization of transformer (controlled switch-
544.1 Hz. The instantaneous voltage waveform at PCC is shown
ing of the three phases)
in Fig. 12. The produced inrush currents in all three phases due
to energization of TR1 are shown in Fig. 13; (a) when S3 was pre- One of the widely-used methods to eliminate/decrease inrush
viously open and (b) when S3 was previously closed. current, drawn when transformer energization is the controlled
The existence of the second transformer caused system natural switching method of the main CB. A sequential energization of
frequency to decrease from 550.7 Hz to 544.1 Hz due to existence transformer three phases is made so that each phase a, b, and c will
of TR2. This decrease in frequency is produced due to consideration be energized at 90-deg switching angle [23]. By this method, the
of transformer capacitances. The transformer capacitances raise inrush current is reduced and hence, the HROs are eliminated. This
overall system capacitance; resulting in system natural frequency method is not very effective to eliminate inrush current and HRO
decrease. Such decrease increased HRO peak values from 1.221p. unless the remnant flux is controlled. The remnant flux mainly
A. Fouad et al. / Ain Shams Engineering Journal 10 (2019) 731–743 739

Fig. 11. Impedance-frequency characteristics at PCC; (a) when S3 was previously open, (b) when S3 was previously closed.

Fig. 12. Instantaneous voltage waveform at PCC; (a) when S3 was previously open, (b) when S3 was previously closed.

depends on separation instant of circuit breaker poles, so it is ii. Pre-insertion resistor


decreased to minimum value by controlling opening time of the
circuit breaker [24–26]. The pre-insertion resistor declines the harmonic overvoltage by
If the opening/closing times of the circuit breaker poles are con- decreasing the inrush current. The closing resistors are inserted in
trolled so that the switching angle is 90-deg and remnant flux is series with high voltage circuit breakers, and it is short circuited
zero, then inrush current has a very good damping. In this case, after 20 ms as optimum insertion time should be more than
severest HRO value does not exceed 1.08p.u as shown in Fig. 15. 14 ms [27].
740 A. Fouad et al. / Ain Shams Engineering Journal 10 (2019) 731–743

Fig. 13. Instantaneous inrush current waveforms in kA; (a) when S3 was previously open, (b) when S3 was previously closed.

Fig. 14. Instantaneous sympathetic inrush current waveforms, generated in the primary side of TR2 when TR2 is on-line case.

The minimum value of overvoltage peak is achieved in the rich in harmonics decays slowly in case of controlled switching
above-described system using a 400-ohm resistor. Choosing a method. This may increase the probability of HROs production.
400-ohm pre-insertion resistor will maintain overvoltage peak to On the contrary, with pre-insertion resistor method, the inrush
less than 1.08p.u as shown in Fig. 16. The produced voltage current instantly decays (within less than one cycle only). This will
waveform with this method is smoother and free of ripples and damp all possible harmonic frequency components contained in
overvoltages, as shown in Fig. 17. the inrush current and reserve the system away from HROs. There-
fore pre-insertion resistor method is preferred to damp the inrush
iii. Comparison between pre-insertion resistor method and
currents and HROs.
controlled switching method

The instantaneous inrush current waveforms produced during


worst energization scenario described early with using sequential 8. Conclusion
energization in case of maximum residual flux and in case of zero
residual flux and with adding the pre-insertion resistor are shown This paper presents a simulation model to study resonance
in Fig. 18. overvoltage following energization of a 75 MVA 220/22 kV main
The controlled switching method is not very effective in elimi- transformer in a weak wind farm system, far from the grid, and
nating the inrush current or reducing the HRO unless the residual investigates the effect of OHTL and MV cable lengths on the pro-
flux is controlled. Moreover, the produced inrush current which is duced harmonic overvoltage. The results show that the main MV
A. Fouad et al. / Ain Shams Engineering Journal 10 (2019) 731–743 741

Fig. 15. Instantaneous voltage at PCC after sequential energization of the transformer three phases without remnant flux when using one feeder system in p.u; (a)
Instantaneous voltage waveform, (b) Magnification of the sequential energization period.

Fig. 16. Overvoltage Peak variation with pre-insertion resistor values while line length is 95 km when using one feeder system (1*13 km main cable lengths).

Fig. 17. Instantaneous voltage at PCC after transformer energization in p.u when using 400-ohm pre-insertion resistor.
742 A. Fouad et al. / Ain Shams Engineering Journal 10 (2019) 731–743

Fig. 18. Instantaneous inrush current waveforms in kA; (a) Using sequential phase energization at 90-deg with 0.9p.u residual flux, (b) Using sequential phase energization at
90-deg with 0p.u residual flux, (c) Adding a 400-ohm pre-insertion resistor.

cables may cause higher levels of harmonic overvoltage compared the transformer is de-energized. The pre-insertion resistor method
to those produced in absence of these cables. Any wind farm with gives very good results and eliminates inrush current to low
definite OHTL length will have its own critical range of cables’ acceptable values. In addition, the harmonic resonance overvolt-
lengths which will produce severest overvoltage peak values. The ages are well damped using pre-insertion resistor. Finally, this
more the number of feeders is the more the operating frequency work addresses designers of wind farms in order to be careful
range and system stability. Although Zafarana is an existing wind when choosing arrangement of the MV feeders and when develop-
farm with existing equipment, the investigated scenarios and ing the procedures of power system restoration.
results will contribute in developing power system restoration
procedures for the current wind farm, its extension, and new
planned wind farms in Egypt. References
Decreasing the overvoltage peak to a minimum value using the
controlled switching method cannot be done apart from control- [1] Zhang Tao, Sun Liuxue, Zhang Yin. Study on switching overvoltage in off-shore
wind farms. IEEE Trans Appl Supercond October 2014;24(5).
ling the remnant flux as it has a high effect on inrush current. Con- [2] Villar FS, Reza M, Srivastava K, da Silva LCP. High frequency transients
trolling of remnant flux is done by controlling the instant at which propagation and the multiple reflections effect in collection grids for offshore
A. Fouad et al. / Ain Shams Engineering Journal 10 (2019) 731–743 743

wind parks. In: Proc. Power Energy Soc. Gen. Meet., San Diego, CA, USA, Jul. 24– [27] Hu Jingxuan, Maki Bruno Bisewski Dudley, Marz Michael B. Mitigation of
29; 2011. p. 1–7. voltage drop using pre-insertion resistor during large transformer energization
[3] Allan Greenwood. Electrical transients in power systems. Wiley-Interscience; in a weak system: simulation and field verification. In: International
1991. conference on power systems transients (IPST2011) in Delft, the Netherlands
[4] Povh D, Schultz W. Analysis of overvoltages caused by transformer June 14–17; 2011.
magnetizing inrush current. IEEE Trans Power App Syst 1978;PAS-97(4).
July/Aug.
[5] Ketabi A, Mohammad A, Feuillet R. Analysis and control of temporary
overvoltages for automated restoration planning. IEEE Trans Power Delivery Ahmed Fouad received the B.Sc. degree from Zagazig
October 2002;17(4). University, Egypt, in 2009, and the M.Sc. degree from
[6] Bandyopadhyay P, Begum A. Impact of energization of large power transformer Cairo University, Egypt, in 2017. He is currently at the
from weak source through ICT. In: Nirma university international conference Egyptian Electricity Transmission Co since 2010.
on engineering (NUICONE); 2013.
[7] Bindner H. Power control for wind turbines in weak grids: concepts
development. Roskilde: Riso National Laboratory; March 1999.
[8] Vaddeboina V, Taylor G, Proudfoot Ch. Switching large transformers on weak
transmission networks - a real time case study. In: 47th international
university power engineering conference, December 2012.
[9] Sadeghkhani I, Ketabi A. Estimation of temporary overvoltages during power
system restoration using artificial neural network. In: 15th international
conference on intelligent system application to power systems (ISAP); 2009.
[10] Adibi MM, Alexander RW, Avramovic B. Overvoltage control during
restoration. IEEE Trans Power Syst Nov. 1992;7:1464–70.
[11] Rowora RG. Switching surge: Part iv control and reduction on AC transmission
lines. IEEE Trans Power App Syst 1982;PAS-101(8):2694–702. 8 August. Mostafa Elshahed received the Ph.D. degrees in electric
[12] Cheng CP, Chen Shihe. Simulation of resonance over-voltage during power engineering from Cairo University in 2013. Since
energization of high voltage power network. Electr Power Syst Res January 2014, he is an assistant professor with Cairo
2006;76:650–4. University. He is also a part-time consultant with
[13] Ametani Akihiro, TeruoOhno, Nagaoka Naoto. Cable system transients: theory, KAYAN power systems Ltd, Bristol, UK. Through last two
modeling, and simulation; 2015. years, he was a postdoctoral fellow at the University of
[14] Witte JF, DeCesaro FP, Mendis SR. Damaging long-term overvoltages on Porto, Portugal and at University of Manchester, UK. His
industrial capacitor banks due to transformer energization inrush currents. interests include power quality, power systems stabil-
IEEE Trans Ind Appl 1994;30(4). July / August.
ity, power systems operations, stochastic optimization
[15] Sybille G, Gavrilovic MM, Belanger J, Do VQ. Transformer saturation effects on
and integration of renewable energy sources.
EHV system overvoltages. IEEE Trans Power App Syst 1985;PAS-104
(3):671–80. March.
[16] Yacamini R, Abu-Nasser A. Transformer inrush currents and their associated
overvoltages in HVDC schemes. IEE Proc C-Generation Transmission
Distribution 1986;133. Pt. C, no. 6, September.
[17] Bowles JB. Overvoltages in HVDC transmission systems caused by transformer
magnetizing inrush currents. IEEE Trans Power App Syst 1974;PAS-93:487–93. Mahmoud Sayed Mahmoud Sayed was born in Cairo,
Jan. Egypt, in 1982. He received the B.S. in 2005 , M.S. in
[18] PowerFactory. Power Factory DIGSILENT 14.1 User’s manual; 2015. 2008 and Ph.D in 2013 in Electrical engineering from
[19] Chiesa N, Mork BA, Høidalen HK. Transformer model for inrush current Cairo University, Egypt. He is currently an Assistant
calculations: simulations, measurements and sensitivity analysis. IEEE Trans professor at faculty of engineering, Cairo University.
Power Delivery 2011;25(4):2599–608.
[20] Zgainski F, Caillault B, Renouard V. Validation of power plant transformers re-
energization schemes in case of black-out by comparison between studies and
field tests measurements. In: Proc. international conference on power systems
transients; 2007.
[21] Marti J. Accurate modeling of frequency dependent transmission lines in
electromagnetic transient simulation. IEEE Trans Power App Syst 1982;PAS-
101:147–57.
[22] ElSewedy Co. EL Sewedy Cables -EGYTECH CATALOG; 2015.
[23] Xu W, Abdulsalam SG, Chen S, Liu X. A sequential phase energization method
for transformer inrush current reduction, Part II: theoretical analysis and
design guide. IEEE Trans Power Delivery April 2005;20:950–7. Mahmoud Gilany (M’05) was born in Helwan, Egypt, in
[24] Goldsworthy D, Roseburg T. Controlled switching of HVAC circuit breakers: 1964. He received the B.Sc. and M.Sc. degrees from Cairo
application examples and benefits. In: 34th annual western protective relay University, Cairo, Egypt, in 1987 and 1989, respectively,
conference, October 2007.
and the Ph.D. degree from Calgary University, Calgary,
[25] Prikler L, Bánfai G, Bán G, Becker P. Reducing the magnetizing inrush current
AB, Canada, in 1993. He was a Professor with the College
by means of controlled energization and de-energization of large power
of Technological Studies, Shuwaikh, Kuwait. Currently,
transformers. In: International conference on power system transients (IPST),
in New Orleans, USA; 2003. he is a Professor with Cairo University. His research
[26] Chandrasena W, Jacobson D, Wang P. Controlled switching of a 1200 MVA interests include power system protection, power
transformer in Manitoba. IEEE Trans Power Delivery Oct. 2016;31 quality, and integration of renewable energy sources.
(5):2390–400.

You might also like