Professional Documents
Culture Documents
Please note:
InfoMine USA’s subscription fees are charged
on a per user basis. Unauthorized redistribution
of InfoMine USA information, including the
forwarding of email publications to third parties
and the copying of printed publications, is
prohibited without prior written authorization
of InfoMine USA, Inc.
If you wish to add users to your subscription please contact us.
After your company has purchased its first subscription to Coal
Cost Guide, second and third users at the same location receive
their subscriptions at a 50% discount. Four or more subscribers
receive a 75% discount, and 10 or more added subscribers are
eligible for special bulk rates. For information on discounts for
other company locations, please contact us.
Tel: 509-328-8023
Fax: 509-328-2028
Email: jleinart@infomine.com
DEVELOPMENT SERIES
Number 6 October 2010
Slope Angle Reduction top of the stockpile at the surface expression of the
Re-contouring, as it pertains to mining projects, most desired (post re-contoured) crest. It then angles
often refers to one of a number of variations of the task toward the existing crest, dozing a load of material
of reducing the slope of a stockpile of waste, with it. The machine continues to the existing crest
overburden, or tailings. These materials are most often and casts the material down the face of the slope. It
placed in a way that leaves their side-slopes at an repeats this process until all of the material from the
associated angle of repose. initial cut has been excavated, transported, and cast.
The preferred way to reduce the side-slope angle of Next, the expression of the final slope on the bench is
these stockpiles has a bulldozer excavating horizontal surveyed in and staked, and the machine begins again
cuts into the material and then casting it down the face with the next cut thereby eventually providing the
(figure 1). Specifically, the bulldozer begins on the desired final slope in the new face of the stockpile.
DS6
Copyright © 2010 InfoMine USA, Inc. COAL COST GUIDE 1
As is evident, after a point roughly half-way down the re-handling. Of these methods, the one presented here
vertical extent of the stockpile, all of the material and used to estimate the following costs is the method
moved will consist of that previously excavated from that minimizes both the total amount of material
above and so re-handling of previously cast material moved and the average distance that the bulldozer
quickly becomes part of the re-contouring process must transport it, which maximizes the efficiency of
(figure 2). There are other ways to re-slope the face of the bulldozer.
a stockpile, however each requires varying amounts of
In general terms, the volume of material re-handled is have been excavated and the final slope angle is
roughly equivalent to the volume of material originally obtained, the bulldozer travels up and down the slope
excavated. In other words, because some of the cast to smooth the re-contoured face, to compact the newly
material must be re-excavated and re-cast (in some placed material, and to cleat the surface to impede
cases multiple times), the volume of material that must erosion and to prepare the slope for planting.
be moved to re-contour a slope is generally about In the following sets of tables, the costs of re-
twice the amount excavated in the first place. sloping the face of a stockpile (of either waste, topsoil,
However, a straight-forward 2:1 relationship does not or tailings) from an assumed angle of repose (42°) to
suffice because the angle of the underlying slope also a variety of face angles are presented. These final face
impacts the calculations, as do the factors of swell and slopes include angles of (33°) (1.5:1 - horizontal:
compaction for the excavated material. These all play vertical), (30°) (1.75:1), (26°) (2:1), and (19°) (3:1).
into the amount of material that must be moved to The process of estimating the following costs begins
arrive at the desired face slope of the stockpile and with calculating the amount of material that must be
must be considered when estimating the costs of re- excavated and determining where (how far in from
contouring. face) that excavation must begin. After that
Near the lower extremities of the slope, the bench information has been derived, the work of estimating
widths may become too narrow to allow for effective costs consists of a series of cycle-time calculations and
use of the bulldozer. At that point, the bulldozer may then the assignment of the associated wages and
work directly down the face to re-contour the final prices.
base of the slope. Typically, after all of the benches
DS6
2 COAL COST GUIDE Copyright © 2010 InfoMine USA, Inc.
In the first four tables, a 310 horsepower bulldozer from the following tables must be multiplied by 8 to
is used to re-contour the slope. Costs presented are for arrive at the overall cost. The slopes of the underlying
each 100 feet (30 meters) of length along the slope surface, that is the slopes of the surface upon which
face at a point roughly half-way down the vertical the stockpile was placed, are listed in the column
extent of the stockpile . In other words, if the crest farthest to the left.
length of the stockpile is 800 feet, the applicable value
DS6
Copyright © 2010 InfoMine USA, Inc. COAL COST GUIDE 3
Table 4. 19 degree final slope
Stockpile Height (feet)
Underlying
Slope 80 120 160 200 240 280 320 360 400
(degrees) (24 meters) (37 meters) (49 meters) (61 meters) (73 meters) (86 meters) (98 meters) (110 meters) (122 meters)
In the next four tables, the costs associated with re-contouring are listed for a series of scenarios in which a 580
horsepower bulldozer tractor is used to re-slope the stockpile. Costs presented are for each 100 feet (30 meters) of
length along the slope face at a point roughly half-way down the vertical extent of the stockpile.
DS6
4 COAL COST GUIDE Copyright © 2010 InfoMine USA, Inc.
Table 7. 26 degree final slope
Stockpile Height (feet)
Underlying
Slope 80 120 160 200 240 280 320 360 400
(degrees) (24 meters) (37 meters) (49 meters) (61 meters) (73 meters) (86 meters) (98 meters) (110 meters) (122 meters)
In the final four tables, the costs associated with re-contouring are listed for a series of scenarios in which an 850
horespower bulldozer tractor is used for the work. Costs presented are for each 100 feet (30 meters) of length along
the slope face at a point roughly half-way down the vertical extent of the stockpile.
DS6
Copyright © 2010 InfoMine USA, Inc. COAL COST GUIDE 5
Table 10. 30 degree final slope
Stockpile Height (feet)
Underlying
Slope 80 120 160 200 240 280 320 360 400
(degrees) (24 meters) (37 meters) (49 meters) (61 meters) (73 meters) (86 meters) (98 meters) (110 meters) (122 meters)
The above costs include those associated with owning, with the project parameters (volumes moved over
maintaining, repairing, and operating the bulldozer as specific distances and gradients, blade and traction
well as the wages of the dozer operator. Also included efficiencies, etc.) to calculate machine cycle times
are those costs associated with surveying and staking which are used, in turn, to determine equipment and
the slope during the process of re-contouring, and for labor needs. These are then combined with price and
onsite supervision. Not included are costs for wage data from Mining Cost Service to provide the
mobilization, project management, contractor profit, or estimated costs. Itemized costs for the labor and
engineering. supplies used in the models are as follows:
All costs were derived through the use of in-house,
spreadsheet-based cost models. These models work
DS6
6 COAL COST GUIDE Copyright © 2010 InfoMine USA, Inc.
Unit Costs * Maintenance and repair parts, ground engaging
Labor components, and ownership costs are specific to
Foreman $ 27.54/hour each machine and based upon manufacturer
Surveyor $ 26.60/hour recommendations.
Equipment Operator $ 23.33/hour
Mechanic $ 22.66/hour Almost all of the costs of re-contouring are attributable
Laborer $ 20.60/hour to either labor or to the expenses of owning and
Burden Rate 36.1% of wages operating the equipment. Few supplies are consumed
except those associated with staking the slope as it is
Equipment Operation surveyed, and with the equipment-based consumables.
Diesel Fuel $ 2.645/gallon $ 0.699/liter Average cost distributions are listed in the following
Lubricants $ 8.09/gallon $ 2.137/liter tables:
Repair & Overhaul Parts*
Ground Engaging Components*
Equipment Ownership*
Average Equipment Operating and Ownership Cost Distribution (percent of total cost)
Final Slope
Bulldozer 19° 26° 30° 33°
310 horsepower 51.9% to 27.9% 47.9% to 20.4% 36.0% to 14.3% 11.4% to 4.4%
580 horsepower 53.3% to 27.5% 51.5% to 19.7% 38.4% to 14.1% 11.8% to 4.3%
850 horsepower 64.7% to 32.0% 58.2% to 23.1% 44.7% to 7.1% 14.5% to 5.4%
DS6
Copyright © 2010 InfoMine USA, Inc. COAL COST GUIDE 7
In the three preceding tables, the numbers to the of the stockpile and the steepness of the final slope,
left of each range are typical of the 400-foot-high costs are heavily influenced by the efficiency of the
stockpile, and the numbers to the right are those for the dozer’s blade (which in this case is a function of the
80-foot-high stockpile. thickness of the cut and the width of the bench) and by
Volumes excavated of course vary from one the dozer’s ability to gain and maintain traction (which
model to the next and are based upon the size and is a function of the nature of the stockpiled material
configuration of the stockpile, the slope angle of the and the weight of the machine). Some of the
underlying surface as well as the cut and repose parameter values used in the models include:
angles, and the density, swell, and compaction
characteristics of the material. In addition to the size
Acknowledgment
The author wishes to thank Jeff Gabardi, Mining Engineer for the USDA Forest Service, Region 4, for his insights
into the tasks associated with re-contouring.
References
Campbell, D.B., Resloping Waste Rock Dumps, in International Mine Waste Management News, Volume 2, Number
2, April 1992.
Leinart, J.B. (Ed.), 2009, “Mining Cost Service,” InfoMine USA. Inc.
DS6
8 COAL COST GUIDE Copyright © 2010 InfoMine USA, Inc.