Monthly Report: A Report Presented To The Project Team Department of Wilmar Africa Limited BY
Monthly Report: A Report Presented To The Project Team Department of Wilmar Africa Limited BY
MONTHLY REPORT
1.0 INTRODUCTION………………………………………………………………………………………………………3
2
1.0 INTRODUCTION
This report highlights on the activities that was carried out by the third party contractors which is been
supervised by the project team of wilmar Africa limited from 4 th of may 2020 to 5th of june 2020.
Currently we have four third party contractors on site that is Buckdes contractors, Amara contractors,
Asterion contractors and BZL contractors. The project team and safety team made sure the third party
contractors worked according to the standards of wilmar Africa limited . All neccessary permits that is
height permit, hot work permit and risk assessment permit was provided to the contractors before they
start working. All kinds of personal protective equipment that is personal overall , helmets, safety
3
1.1 ONGOING PROJECT AT REFINERY
I Supervised a third party team known as ‘buckdes’ who has been given a contract to restructure the
outer walls of the refinery plant . Pictures of ongoing project is shown below for your consideration.
• Sand blasting
• Placement of purlings
• Painting
4
5
6
7
1.2 ONGOING PROJECT AT MARGARINE PLANT
Civil works is still ongoing by the third party contractors at the new margarine plant . We have three
contractors currently working on site that is contractors from Buckdes, Asterion and BZL. All the three
contractors have different projects they are assigned to. Asterion contractors are working on the
changing room and canteen for the new margarine plant. Buckdes contractors are working on the
production floor for the new margarine plant . BZL construction is working on the leveling of floor and
building of production room for the new margarine plant. Pictures of work done so far will be shown
8
Asterion contractors working on the changing room and canteen for new margarine plant
Use of scaffold and helmet must be ensured to prevent fallen and also objects dropping from the top to
9
BZL construction is working on the leveling of floor and building of production room for the new
margarine plant.
All pits dugged must be barricade and also put a warning sign around it.
10
Buckdes contractors working on the production floor for the new margarine plant .
Proper house keeping needs to be done with the safety manager also enforcing the use of hand gloves
to prevent injuries.
11
1.3 FIXING OF LEAKAGE ISSUE AT DETERGENT PLANT
I also supervised Amara contractors to fix leakage issue at detergent plant. The pictures below explains
12
13
1.4 BACK OFFICE EXTENSION
Civil works for the back office extension has been completed by the shelter matrix contractors. Their
14
Area needs to be barricade to prevent workers from using the bridge and also road sings needs to be
15
Use of hand gloves and a helmet must be enforced to help the workers from hand injuries and falling
objects.
I recommend that workers should take their safety measures serious and also put
16