You are on page 1of 8

- - - - - -- - - - - - -- - - - -- -- - - - -- - - --

ENGINEERS FILE NOTE NO .7 . CISfB' I


I (21.9) I FG2
I
I
7

• Published by the Brick Development Association


January 1988

A REINFORCED
BRICKWORK FREESTANDING
BOUNDARY WALL
By G.D. Johnson B Eng(Tech) phD MICeram MIStruetE C. Eng.

• Consulting Engineer, Hertford.

This File Note describes the design and in perhaps too many instances, are not
construction of a "simple " garden wall designed by structural engineers.
- a project which cost less than £4,000. Secondly the File Note describes how
Nonethelesss, it is interesting for at least tight cost constraints were fulfilled by
two reasons. Firstly freestanding walls, adopting a reinforced solution.


Fig. 1.

A
""/--
1....
--.. -..... __
-- -- -.l'-_
B

-- -- - --c:
- - -... -... l. -...-.....

INTRODUCTION
Brick boundary walls are a common
feature of the built environment in Britain.
They not only enhance a property but
often provide an element of both security
and privacy. While much time will
undoubtedly be spent on the planning,
design and detailing of the dwelling,
freestanding walls are seldom subjected to
an engineering appraisal but are left to the
bricklayers to build.
However, attitudes are changing and
many more walls are now being designed
on sound engineering prindples. The BDA

Design Guide No 12 "The Design of
Freestanding Walls" is a useful publication
in this regard.
As with any structure, economy of
design is of importance and this File Note
describes the design and construction of
one particular boundary wall, where
economics, aesthetics and engineering
considerations led to the adoption of a
fully reinforced brickwork solution.

BRIEF
The brief was to design and construct a
boundary wall between a public footpath
and a private garden to enhance the
property and to ensure privacy. Awall
height of at least 2m above footpath level
was therefore required. Cost was an
important consideration since the wall
was to be 25m long. The side of the wall
adjacent to the footpath had to present a
smooth, uninterrupted face free from piers
and obstructions. In addition, since part of
the garden was higher than the path, the
wall was required to act as a retaining wall
in places. Afurther consideration was that
disruption to the footpath should be
minimal during the construction process
as should any damage to the footpath 's
surface if consequent expensive
reinstatement was to be avoided. Finally,
as a planning consideration, the brick to
be used for the wall was to blend and
complement the existing brickwork of the
property.
STRUCTURAL DESIGN CONSIDERATIONS


Thebrick chosen to complementthe grouted cavitysection was used. Typical
existing brickwork was in the upper halfof sections are shown in Fig.2.
the pricespectrum. It was obviously Somelight bed jointreinforcement was
important to keep costs to a minimumand to be includedin the panels to enhance
it was dedded to construct the wall, as far the integrity ofthe wall under acddental
as possible. as a singleleafwall,supported loads.
at intervals by piers.The piers required to Theconcrete base was designed to
be on the garden elevation so as to leave a resist the applied moments from the piers
smooth side adjacent to the footpath. and to provide stability to the wall as a
Further economy ofmaterialscould be whole.
made by adopting a reinforced brickwork Becausethere was to be no significant
section for the piers. Thusfor the intrusion into the footpath - thus requiring
freestanding wall allbrickwork couldbe minimal reinstatment afterwards - the
constructed as a singleskin ofstretcher foundations to the reinforced brick piers
bond with intermediate 327.5mmsquare were extended to the rear ofthe wall to
hollow piers. At sections where the wall is provide the necessary stability.
calledupon to retain soil, a reinforced


CONCRETECAPI'lNG_ ,r -- ..,

• STAINLESS STEEL ' --1:0.1..1


MESH IN BED JOINTS -L..-4-
TOP. BOTTOM AND
MIDDlE OF Wo\ll

CONCRETE BASE

A142 MESH


Ag. 2. A142MESH IN BASE 2112IN WALL FOOTING

AA BB
MATERIAL CONSIDERATIONS
The brick chosenwas a Waingroves mortarwithin unprotected brickwork
Muirfield Mixture Rustic - a dense
engineering brick suppliedby Butterley Brick.
Limited.Thenature ofthis brick is such
that both sides ofthe wall could be
constructedto a fair-face finish.Thebrick
duringwet conditions) the mortar
purposely contained no lime. Aproper
coping placedon a OPC was considered to
be essentialat the head ofthe wall to
protect the brickwork from water

strength and water absorptionconformed percolating downwards ifa longmainten-
to the BS 3921 requirement fora Class A ance-free serviceable life is to be achieved.
Engineering Brick. The bed jointreinforcement was
Consequently no OPC was necessaryat spedfied as stainlesssteel sincethe
the base ofthe wall sincea Class Aor B author was not convinced that galvanized
brick provides a suitableOPC forfree - mild steelwould remain free ofcorrosion
standing walls. Structurally this is in a situationwherethe coveris only
important With the momentfixity 12mm. Furthermore, it is normal practice
available from a brickwork OPC the base of to find that the reinforcement is laiddry
the wall panel can be regardedas a on top ofa courseand then mortar placed
continuousedge. This reducesthe design on top ofit - irrespective ofwhat the
momentin the centre ofthe wall, hence spedfication calls for. This leads to the


leadingto economy. steel not beingtotallysurrounded and
Themortar used was designation (i) - embedded in the mortar and this leaves it
a 1:3 cement: sand mix. Thedensest and moreproneto corrosion. The use of
most durableofthe normal building stainlesssteel in this situation is now
mortars,it isappropriateforthis form of required to conform with the requirements
construction wherea thin, halfbrick wall ofBS 5628 Part 2 and Part 3.The major
is exposedto the rainfrom both sides and reinforcement containedin the pierswas
hence may be subjectto frostwhile considered well protectedand ordinary
saturated. To lessen the possibility oflime highyield steel reinforcement was
staining(the leeching offree lime from the spedfied here.

Ag. 3.

T
~

t
§
t---------'

J I--- - - - - - - ------i
MOVEMENT JOINT DESIGN
Normally, in walling, movement joints are worksomewhat, it was nonetheless

• positioned at 10 to 12m centres. Since the


brickwork is exposedon both sides and
the wall thicknessis one halfbrick
(102.Smm) it was felt that the thermal
changesmay be particularly significant.
decided to position the movementjoints
at approximately 8m centres whichalso
suited the plan ofthe wall as influenced by
structural considerations. The maximum
movement which wouldreasonably be
Although the use ofbed joint reinforcement expectedto occurat the jointwouldbe of
is consideredto restrain the expansive the order ofS/6mm, thus a 12mm joint
longterm moisture movement ofbrick- widthwas spedfied.


STRUCTURAL DESIGN reinforcement would be avoidedand a
slightreduction in the size ofexcavations
Design Data: be effected, such savings would not
Brick:

Mortar:
Crushing Strength 80 N/mm 2
WaterAbs. 2-5%
1:3 sand:cement mix
Concrete: Grade 25 to CP110
Windload: Basic windspeed 40m/sec.
outweigh the extra cost oflabour and
materials. Using the Small Works Section
ofthe Building PriceBook, comparative
"base" pricesforthe reinforced - and a
suitable unreinforced - solution show the

former to be 27% cheaper than the latter.
Thelight bed jointreinforcement was Of course, both cost figures generated by
'Bricktor' high tensilestainless steel, - the Price Book, exceedthe final cost ofthe
75mmwide. wall as constructed but it is believed that
the cost savingratio wouldhave been
similar. Thereinforced solution, therefore,
CONSTRUCTION can be seen to be both technically sound
and economically viableforthe design
No particular difficulties werefound with briefgiven.
the construction. However, a few minor
points are worthy ofnote.
(i) Stainless steel bedjointreinforcement, CONCLUSIONS


although available, is not widely enough
used to be a stock item at many Builders' When spedal situations prevail, the use of
Merchants. Arrangements to supply this reinforced brickwork in boundary walls
were made well in advance. can effect worthwhile economies. Half
(ii) Forthis wall a spedal copingwas made brick thickwalls can be made to span
whichfitted overthe thickness ofthe wall considerable distances ifsupported on 3
to ensure stabilitywith a correct overhang edges;the horizontal distance between
and drip. Itwas placedovera dpc. vertical supporting piersor buttresses
Thebricklaying was done by a normal may be increasedfurther by the use ofbed
3 man gang. Although the use of joint reinforcement. (See BS 5628 Parts 1
reinforcement in brickwork in this way and 2 forthe design ofsuch panels).
was new to them they were able to As in this case some nominal bed joint
construct the wall without difficulty reinforcement is thought desirable in walls
including handlingand fixing steel and over about 1.2m high to enhance the
groutingthe steel in position. Since free- overall integrityofconstructionand to
standing walls relyon good mortar bond copewith 'accidental events'.
to achieve structural stabilityit was However as with all design it is
consideredessential to ensure that no important to ensure that the material
unapproved additiveswere allowed in the
mortar and that all bed jointsand perpend
joints werefully filled.
spedfication and details are also carefully
considered. While the strength
requirementswere an area ofobvious
importancein the design, the nature ofthe
projectwas such that other material

COSTINGS properties- Le, frost resistance ofthe brick
and the mortar - were ofequal importance
Thebreakdown ofcosts applicable to the if a sound longterm solutionto the brief
boundary wall was as follows: were to be achieved.
Finally, it is the author's view that
Labour £1588.00 unreinforced masonry freestanding walls
Bricks £1223.00 will continue to be used as a popular,
OtherMaterial £704.00 straight-forward solutionto the majority of
Equipment Hire £211.00 screen walls.Thef1exiblity ofmasonry
£3726.00(Ex VAT) bonding, however, and its abilityto
accomodatereinforcement can be used to
An unreinforced wall to achievethe same great advantage to provide a sound


performance would be expected to use economicsolutionwhen particular
about twicethe quantity ofbricks used in constraints are present in the brief.
this design. Even though the cost of
CALCULATIONS

• 1, Deslgn Load.

p. - 0.5 kN/m' x 2 x 1.2 x 1.2


- 1.4 kN/m
A - (2 x 2) + 0.33 x 2 - 4.66m'
@ 0.5 kN/m'
Therefore:
Therefore: LOAD - 2.33 kN

M d - (2.33 x (2 x 2/3 + 0.6) x 1.2)


- 5.4 kN.m/m
Po = 1/ 2 x O.33 x 20 x 11' x 1.6
- 6.4kN/m SecTiO N

SecTiON THRO' IlETAlNING WALL 330


Say lever arm - 0.9 x 2 - 149mm
<t. SECTION THRO'
M _ 5.~~ 10' _ 36.3 kN COlUMN THUS:
z ,----...,."

Therefore: 36 3 10' 115


A,REQD= . x
460
x .

t1!t1
I. I I_ ,I


x 330/2 330/2
x
Use 1NO 112 - 113m m'

3. Wind Panel.

M u = p. (2/2 + 1.1) + Po H/3


- 5.2 kN.m/m

Say lever arm = 0.95 x 150 FOR GROUTED

...
= 143mm CAVITY WAll THUS:

~l~
AS TYPE D: BS 5623 ParI 1.
m "I, - 1.2 ; "Im - 3.5
W. - 0.5 kN/m'
:h~ef~e~ 36 x 10' x 1.15
l00mm ~150-.l ~ - 0.35
'" eq 460 h/L _ 0.50 Therefore : IX = 0.032

- 9Omm2/m M - ex YrWk .l 2
- 0.032 x 1.2 x 0.5 x 4'
Use A98 MESH (A, - 98mm' /m.) - 0.31 kN.m/m

• 2.~_

SHADED AREA = LOADTO REINFORCED BRICKWORK


Z
M
z
- 1/61000 x 103'

0.31 x 1()6
1.77 x 1()6
= 1.77 x 1()6 (mm' /m)

- 0.17 N/mm'

COlUMN. • f.. 41EQD = 0.17 x 3.5 - 0.61 N/mm'

FOR BRICK OF WATER ABS < 7'1>


and In 1:1/4:3 MORTAR

i I.. - 2.0 N/mm' > 0,6 N/mm'


I Therefore: OK

.i Include so me bed Joint reinforcement to assist


I Integrity. (Accldenlal Damage and ResistThermal!
+----
I
Moisture Expansion).
Concrete bases to suit ground condirlons and
I for no tension under moment condlrlons .


• It will be noled from Table 3 of BS 5628 Part 1
that ANY brick would have been sarlsfactory. The
I I high strength In this case Is coincidental following
330mm the aestherlc choice of the brick.

The Association would be interested to hear. from Engineers or Architects. of projects which they
consider worthy of inclusion in The BDA Engineers' File Note Series . All initial submissions should
contain reference to the particular area of the design which, it is considered. would be of interest to
the design profession as a whole . All enquiries should be addressed to The Technical Editor.

JMorton B5cPhD CEng MICE MICeramMlnstM.
The views expressed in this FileNote are those of the Authors. Readers are expressly advised that they
do not necessarily reflect the views of the Association.
To demonstrate the initia l engineering decisions ta ken. scheme calculations have been included in the
Note. They are NOT intended to be full and detailed calculations and they should NOT be read as such.

THE ENGINEERS FILE NOTES SERIES BINDER


A specially designed binder has been produced to hold the File Note series and is available from the
Promotional Manager, the Brick Development Association,
woodside House, Winkfield, Windsor, Berkshire SL4 2DX.


Please enclose £2.50 remittance per binder to cover post and packing.

Readersare e xpr~sly adVised that, whilst the contentsof Hilspubbcauon art' beheved to besccurete. COI"red and complete. noreliance should be placed upon its
conte-nls as bei"8appbcable to any pIIrticularcirc\oImstanus Anyadvn, opinion Of llIformauoncont.tmed 15 publishedonfyon the footi"i that thl!' Brick
~Iopment Association, its servanlsor agents and all contl1butorsto this pubiKalion shan beundft nobability whatSOl!'Yer In respectof itScontents

D6tgned and ProducedforIhI!'Brick DewIopmml Association


W:Jodside House, Winkfield. Windsor. ~kshlre 51..4 2DX ~: w ltIkMId Row103441885651 by Frank Wllter Dnign Umitrd
C The BriCk DNelopiltill Assodll bon

You might also like