Quantity and Rate Calcautions for Pile and Well Foundations

S.No Description of Item No Length Width Depth Qty Total Qty

1 1000m Dia Piles


Abutment A1 33 23 759
Pier P1 -1 12 23 276
Pier P1 -2 12 23 276
Pier P2 -1 12 23 276
Pier P2 -2 12 23 276
Abutment A2 33 23 759 2622

2 1000m Dia Piles Concrete


M35 Concrete 2622 0.785398 2059.314

3 Steel
Steel 2059.314 140 kG/m3 288.304 MT

4 Pile Cap
Abutment A1 1 31.5 8.44 1.5 398.79
Pier P1 -1 1 10.5 8.44 1.5 132.93
Pier P1 -2 1 10.5 8.44 1.5 132.93
Pier P2 -1 1 10.5 8.44 1.5 132.93
Pier P2 -2 1 10.5 8.44 1.5 132.93
Abutment A2 1 31.5 8.44 1.5 398.79 1329.3

4 Pile Cap Steel


Steel 1329.3 180 kG/m3 239.274 MT

Quantity Calculation of Well

S.No Description of Item No Length Width Depth Qty Total Qty


Abutment Well Dim
Outer Dia 12 m Assuming Cantiliver of 5.4m
Inner Dia 8.4 m Abt Width 14
Length 23 m Skew 52 Deg
Abt Length in Skew 22.74
Outer Dia 11.94 m
Pier Well Dim
Outer Dia 8m Assuming Cantiliver of 2m
Inner Dia 5m Pier Width 12 in Skew
Length 23 m
Outer Dia 8m

1 Well Stening Qty M35


Abutment A1 2 23 57.67964 2653.263
Pier P1 -1 1 23 30.63053 704.5022
Pier P1 -2 1 23 30.63053 704.5022
Pier P2 -1 1 23 30.63053 704.5022
Pier P2 -2 1 23 30.63053 704.5022
Abutment A2 2 23 57.67964 2653.263 8124.536
3 Steel
Steel 8124.536 45 kG/m3 365.6041 MT

4 Well Cap Qty M35


Abutment A1 2 22.74 7 2 636.72
Pier P1 -1 1 12.99 5.25 1.5 102.2963
Pier P1 -2 1 12.99 5.25 1.5 102.2963
Pier P2 -1 1 12.99 5.25 1.5 102.2963
Pier P2 -2 1 12.99 5.25 1.5 102.2963
Abutment A2 2 22.74 7 2 636.72 1682.625

5 Well Cap Steel


Steel 1682.625 140 kG/m3 235.5675 MT

6 Intermediate Plug
Abutment A1 2 55.41769 0.4 44.33
Pier P1 -1 1 19.63495 0.4 7.85
Pier P1 -2 1 19.63495 0.4 7.85
Pier P2 -1 1 19.63495 0.4 7.85
Pier P2 -2 1 19.63495 0.4 7.85
Abutment A2 2 55.41769 0.4 44.33 120.06

7 Intermediate Plug
Steel 120.06 50 kG/m3 6.003 MT

8 Bottom Plug - M15


Abutment A1 2 55.41769 3.5 387.92
Pier P1 -1 1 19.63495 3.5 68.72
Pier P1 -2 1 19.63495 3.5 68.72
Pier P2 -1 1 19.63495 3.5 68.72
Pier P2 -2 1 19.63495 3.5 68.72
Abutment A2 2 55.41769 3.5 387.92 1050.72

9 Well Excavation
Abutment A1 2 113.0973 23 5202.48
Pier P1 -1 1 50.26548 23 1156.11
Pier P1 -2 1 50.26548 23 1156.11
Pier P2 -1 1 50.26548 23 1156.11
Pier P2 -2 1 50.26548 23 1156.11
Abutment A2 2 113.0973 23 5202.48 15029.4

S.No Description of Item Unit Quantity Rate Amount


1 Pile Boaring Rm 2622 8000 20976000
2 Pile Concrete Cum 2059.314 0 0
Cement for Piling MT 906.0982 6000 5436588.9
3 Steel for Pile MT 288.304 65000 18739757
4 Pile Cap Cum 1329.3 2500 3323250
Cement for Pile Cap MT 584.892 6000 3509352
5 Pile Cap Steel MT 239.274 65000 15552810
Total Amount 67537758 6.75

S.No Description of Item Unit Quantity Rate Amount


1 Well Sinking Cum 15029.4 415 6237201
2 Well Stening Cum 8124.5 2800 22748700
Cement MT 3574.8 6000 21448774
3 Well Steel MT 365.6 65000 23764267
4 Well Cap Cum 1682.6 2800 4711350
Cement MT 740.4 6000 4442130
5 Well Cap Steel MT 235.6 65000 15311888
6 Intermediate Plug Cum 120.1 2800 336168
Cement MT 52.8 6000 316958.4
7 Intermediate Plug Steel MT 6.0 65000 390195
8 Bottom Plug Cum 1050.7 2800 2942016
Cement MT 315.2 6000 1891296

104540942 10.45
22.73977
11.93977

11.36988
7.369885

57.67964
136
20
0.147059 385.5882

3 180 540
7 283 1981
5 394 1970
5 541 2705
3 777 2331
23 9527
Avg Rate 414.2174