RADIO FREQUNECY SERVICES (M) SDN BHD
DOC. NO: RFSSB-EHS-P-004
HAZARD IDENTIFICATION , RISK ASSESMENT EFF. DATE: 4 Jan 2019
AND RISK CONTROL (HIRARC) PROCEDURES PAGE: 2 OF 4
This procedures is made under the C&C Universal Engineering SDN BHD Safety and
Health Policy
2.0 PURPOSE
The purpose of this procedure is to ensure that hazards, environment impact and aspect are
continually identified, potential risks are assessed and necessary control measures are
effectively implemented
3.0 SCOPE
This procedure shall apply to all C&C Universal Engineering SDN BHD employees and other
interested parties at all C&C Universal Engineering SDN BHD premises and associated work
areas
4.0 REFERENCE
NO. 12, JALAN BK 1/15, BANDAR KINRARA INDUSTRIAL PARK, 47180 PUCHONG, SELANGOR, MALAYSIA.
TEL: 03 - 8071 1733 FAX: 03 – 8071 1663
REV: 0
RADIO FREQUNECY SERVICES (M) SDN BHD
DOC. NO: RFSSB-EHS-P-004
HAZARD IDENTIFICATION , RISK ASSESMENT EFF. DATE: 4 Jan 2019
AND RISK CONTROL (HIRARC) PROCEDURES PAGE: 3 OF 4
5.4 Follow Up
• The OSH Coordinator shall assist Head of Department to establish follow-up
action plan to monitor progress of measure taken in reducing the identified risks.
NO. 12, JALAN BK 1/15, BANDAR KINRARA INDUSTRIAL PARK, 47180 PUCHONG, SELANGOR, MALAYSIA.
TEL: 03 - 8071 1733 FAX: 03 – 8071 1663
REV: 0
RADIO FREQUNECY SERVICES (M) SDN BHD
DOC. NO: RFSSB-EHS-P-004
HAZARD IDENTIFICATION , RISK ASSESMENT EFF. DATE: 4 Jan 2019
AND RISK CONTROL (HIRARC) PROCEDURES PAGE: 4 OF 4
5.0 APPENDIX
NO. 12, JALAN BK 1/15, BANDAR KINRARA INDUSTRIAL PARK, 47180 PUCHONG, SELANGOR, MALAYSIA.
TEL: 03 - 8071 1733 FAX: 03 – 8071 1663