You are on page 1of 130

less 4 Sundays in a month 31-(4) = 27

12 months in 1 year
31 days in a month ALL IN LABOUR RATES PER DAY (2003)
Day W'man/ Driver 'A'/ Artisans
General Labour Head Labourer Time Keeper Store Keeper Driver 'L' Night W'man [Grade 1] Foreman
Consolidated Basic Rate/Day (A) 16,201.00 16,715.00 17,761.00 17,761.00 18,835.00 19,904.00 20,904.00 22,034.00
Cost/Year 'A'x27x12 5,249,124.00 5,415,660.00 5,754,564.00 5,754,564.00 6,102,540.00 6,448,896.00 6,772,896.00 7,139,016.00

Add; On cost on Basic


Social Security - 12.50%
Gang Leadership - 2.00%
Workmen Compesation - 2.50%
Funeral Grant - 1.00%
18.00% 944,842.32 974,818.80 1,035,821.52 1,035,821.52 1,098,457.20 1,160,801.28 1,219,121.28 1,285,022.88
Leave allowance ['A'x23 days] 372,623.00 384,445.00 408,503.00 408,503.00 433,205.00 457,792.00 480,792.00 506,782.00
Tools allowance [384x27x12] - - - - - - - -
Height allowance [768x27x12] 248,832.00 248,832.00 - 248,832.00 - - 248,832.00 248,832.00
Medical facilities 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00
Medical facilitators for family 192,000.00 192,000.00 192,000.00 192,000.00 192,000.00 192,000.00 192,000.00 192,000.00
Redundancy award [Av. 6 wks pay] 486,030.00 501,450.00 532,830.00 532,830.00 565,050.00 597,120.00 627,120.00 661,020.00
Severance Award(two month) 874,854.00 902,610.00 959,094.00 959,094.00 1,017,090.00 1,074,816.00 1,128,816.00 1,189,836.00
Long Service(two month) 874,854.00 902,610.00 959,094.00 959,094.00 1,017,090.00 1,074,816.00 1,128,816.00 1,189,836.00
Ex-Gratia Award [8 wks(5x8) pay] 648,040.00 668,600.00 710,440.00 710,440.00 753,400.00 796,160.00 836,160.00 881,360.00

Total cost per year[T] 9,991,199.32 10,291,025.80 10,652,346.52 10,901,178.52 11,278,832.20 11,902,401.28 12,734,553.28 13,393,704.88

T/Effective working days 219 219 219 219 219 219 219 219

ALL-IN DAILY RATE 45,621.91 46,990.99 48,640.85 49,777.07 51,501.52 54,348.86 58,148.65 61,158.47
RATE PER HOUR: - 8 5,702.74 5,873.87 6,080.11 6,222.13 6,437.69 6,793.61 7,268.58 7,644.81
less 4 Sundays in a month 31-(4) = 27
12 months in 1 year
31 days in a month ALL IN LABOUR RATES PER DAY (2004)
Day W'man/ Driver 'A'/ Artisans
General Labour Head Labourer Time Keeper Store Keeper Driver 'L' Night W'man [Grade 1] Foreman
Consolidated Basic Rate/Day (A) 20,575.00 21,228.00 22,556.00 22,556.00 23,920.00 25,275.00 26,624.00 27,983.00
Cost/Year 'A'x27x12 6,666,300.00 6,877,872.00 7,308,144.00 7,308,144.00 7,750,080.00 8,189,100.00 8,626,176.00 9,066,492.00

Add; On cost on Basic


Social Security - 12.50%
Gang Leadership - 2.00%
Workmen Compesation - 2.50%
Funeral Grant - 1.00%
18.00% 1,199,934.00 1,238,016.96 1,315,465.92 1,315,465.92 1,395,014.40 1,474,038.00 1,552,711.68 1,631,968.56
Leave allowance ['A'x23 days] 473,225.00 488,244.00 518,788.00 518,788.00 550,160.00 581,325.00 612,352.00 643,609.00
Tools allowance [384x27x12] - - - - - - - -
Height allowance [768x27x12] 248,832.00 248,832.00 - 248,832.00 - - 248,832.00 248,832.00
Medical facilities 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00
Medical facilitators for family 192,000.00 192,000.00 192,000.00 192,000.00 192,000.00 192,000.00 192,000.00 192,000.00
Redundancy award [Av. 6 wks pay] 617,250.00 636,840.00 676,680.00 676,680.00 717,600.00 758,250.00 798,720.00 839,490.00
Severance Award(two month) 1,111,050.00 1,146,312.00 1,218,024.00 1,218,024.00 1,291,680.00 1,364,850.00 1,437,696.00 1,511,082.00
Long Service(two month) 1,111,050.00 1,146,312.00 1,218,024.00 1,218,024.00 1,291,680.00 1,364,850.00 1,437,696.00 1,511,082.00
Ex-Gratia Award [8 wks(5x8) pay] 823,000.00 849,120.00 902,240.00 902,240.00 956,800.00 1,011,000.00 1,064,960.00 1,119,320.00

Total cost per year[T] 12,542,641.00 12,923,548.96 13,449,365.92 13,698,197.92 14,245,014.40 15,035,413.00 16,071,143.68 16,863,875.56

T/Effective working days 219 219 219 219 219 219 219 219

ALL-IN DAILY RATE 57,272.33 59,011.64 61,412.63 62,548.85 65,045.73 68,654.85 73,384.22 77,004.00
RATE PER HOUR: - 8 7,159.04 7,376.45 7,676.58 7,818.61 8,130.72 8,581.86 9,173.03 9,625.50
less 4 Sundays in a month 31-(4) = 27
12 months in 1 year
31 days in a month ALL IN LABOUR RATES PER DAY (2005)
Day W'man/ Driver 'A'/ Artisans
General Labour Head Labourer Time Keeper Store Keeper Driver 'L' Night W'man [Grade 1] Foreman
Consolidated Basic Rate/Day (A) 24,700.29 25,484.21 27,078.48 27,078.48 28,715.96 30,342.64 31,962.11 33,593.59
Cost/Year 'A'x27x12 8,002,893.15 8,256,885.34 8,773,426.87 8,773,426.87 9,303,971.04 9,831,014.55 10,355,724.29 10,884,323.65

Add; On cost on Basic


Social Security - 12.50%
Gang Leadership - 2.00%
Workmen Compesation - 2.50%
Funeral Grant - 1.00%
18.00% 1,440,520.77 1,486,239.36 1,579,216.84 1,579,216.84 1,674,714.79 1,769,582.62 1,864,030.37 1,959,178.26
Leave allowance ['A'x23 days] 568,106.61 586,136.92 622,804.99 622,804.99 660,467.08 697,880.66 735,128.58 772,652.60
Tools allowance [384x27x12] - - - - - - - -
Height allowance [768x27x12] 248,832.00 248,832.00 - 248,832.00 - - 248,832.00 248,832.00
Medical facilities 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00
Medical facilitators for family 192,000.00 192,000.00 192,000.00 192,000.00 192,000.00 192,000.00 192,000.00 192,000.00
Redundancy award [Av. 6 wks pay] 741,008.63 764,526.42 812,354.34 812,354.34 861,478.80 910,279.13 958,863.36 1,007,807.75
Severance Award(two month) 1,333,815.53 1,376,147.56 1,462,237.81 1,462,237.81 1,550,661.84 1,638,502.43 1,725,954.05 1,814,053.94
Long Service(two month) 1,333,815.53 1,376,147.56 1,462,237.81 1,462,237.81 1,550,661.84 1,638,502.43 1,725,954.05 1,814,053.94
Ex-Gratia Award [8 wks(5x8) pay] 988,011.50 1,019,368.56 1,083,139.12 1,083,139.12 1,148,638.40 1,213,705.50 1,278,484.48 1,343,743.66

Total cost per year[T] 14,949,003.70 15,406,283.71 16,087,417.79 16,336,249.79 17,042,593.79 17,991,467.31 19,184,971.17 20,136,645.79

T/Effective working days 219 219 219 219 219 219 219 219

ALL-IN DAILY RATE 68,260.29 70,348.33 73,458.53 74,594.75 77,820.06 82,152.82 87,602.61 91,948.15
RATE PER HOUR: - 8 8,532.54 8,793.54 9,182.32 9,324.34 9,727.51 10,269.10 10,950.33 11,493.52
less 4 Sundays in a month 31-(4) = 27
12 months in 1 year
31 days in a month ALL IN LABOUR RATES PER DAY (2006)
Day W'man/ Driver 'A'/ Artisans
General Labour Head Labourer Time Keeper Store Keeper Driver 'L' Night W'man [Grade 1] Foreman
Consolidated Basic Rate/Day (A) 31,892.00 32,903.00 33,938.00 34,962.00 37,076.00 39,182.00 41,267.00 43,374.00
Cost/Year 'A'x27x12 10,333,008.00 10,660,572.00 10,995,912.00 11,327,688.00 12,012,624.00 12,694,968.00 13,370,508.00 14,053,176.00

Add; On cost on Basic


Social Security - 12.50%
Gang Leadership - 2.00%
Workmen Compesation - 2.50%
Funeral Grant - 1.00%
18.00% 1,859,941.44 1,918,902.96 1,979,264.16 2,038,983.84 2,162,272.32 2,285,094.24 2,406,691.44 2,529,571.68
Leave allowance ['A'x23 days] 733,516.00 756,769.00 780,574.00 804,126.00 852,748.00 901,186.00 949,141.00 997,602.00
Tools allowance [384x27x12] - - - - - - - -
Height allowance [768x27x12] 248,832.00 248,832.00 - 248,832.00 - - 248,832.00 248,832.00
Medical facilities 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00
Medical facilitators for family 192,000.00 192,000.00 192,000.00 192,000.00 192,000.00 192,000.00 192,000.00 192,000.00
Redundancy award [Av. 6 wks pay] 956,760.00 987,090.00 1,018,140.00 1,048,860.00 1,112,280.00 1,175,460.00 1,238,010.00 1,301,220.00
Severance Award(two month) 1,722,168.00 1,776,762.00 1,832,652.00 1,887,948.00 2,002,104.00 2,115,828.00 2,228,418.00 2,342,196.00
Long Service(two month) 1,722,168.00 1,776,762.00 1,832,652.00 1,887,948.00 2,002,104.00 2,115,828.00 2,228,418.00 2,342,196.00
Ex-Gratia Award [8 wks(5x8) pay] 1,275,680.00 1,316,120.00 1,357,520.00 1,398,480.00 1,483,040.00 1,567,280.00 1,650,680.00 1,734,960.00

Total cost per year[T] 19,144,073.44 19,733,809.96 20,088,714.16 20,934,865.84 21,919,172.32 23,147,644.24 24,612,698.44 25,841,753.68

T/Effective working days 219 219 219 219 219 219 219 219

ALL-IN DAILY RATE 87,415.86 90,108.72 91,729.29 95,592.99 100,087.54 105,697.01 112,386.75 117,998.88
RATE PER HOUR: - 8 10,926.98 11,263.59 11,466.16 11,949.12 12,510.94 13,212.13 14,048.34 14,749.86
less 4 Sundays in a month 31-(4) = 27
12 months in 1 year
31 days in a month ALL IN LABOUR RATES PER DAY (2006)REVISED
Day W'man/ Driver 'A'/ Artisans
General Labour Head Labourer Time Keeper Store Keeper Driver 'L' Night W'man [Grade 1] Foreman
Consolidated Basic Rate/Day (A) 31,892.00 32,903.00 33,938.00 34,962.00 37,076.00 39,182.00 41,267.00 43,374.00
Cost/Year 'A'x27x12 10,333,008.00 10,660,572.00 10,995,912.00 11,327,688.00 12,012,624.00 12,694,968.00 13,370,508.00 14,053,176.00

Add; On cost on Basic


Social Security + NHIL - 15.00%
Gang Leadership - 2.00%
Workmen Compesation - 2.50%
Funeral Grant - 1.00%
20.50% 2,118,266.64 2,185,417.26 2,254,161.96 2,322,176.04 2,462,587.92 2,602,468.44 2,740,954.14 2,880,901.08
Leave allowance ['A'x23 days] 733,516.00 756,769.00 780,574.00 804,126.00 852,748.00 901,186.00 949,141.00 997,602.00
Tools allowance [384x27x12] - - - - - - - -
Height allowance [768x27x12] 248,832.00 248,832.00 - 248,832.00 - - 248,832.00 248,832.00
Medical facilities 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00
Medical facilitators for family 192,000.00 192,000.00 192,000.00 192,000.00 192,000.00 192,000.00 192,000.00 192,000.00
Redundancy award [Av. 6 wks pay] 956,760.00 987,090.00 1,018,140.00 1,048,860.00 1,112,280.00 1,175,460.00 1,238,010.00 1,301,220.00
Severance Award(two month) 1,722,168.00 1,776,762.00 1,832,652.00 1,887,948.00 2,002,104.00 2,115,828.00 2,228,418.00 2,342,196.00
Long Service(two month) 1,722,168.00 1,776,762.00 1,832,652.00 1,887,948.00 2,002,104.00 2,115,828.00 2,228,418.00 2,342,196.00
Ex-Gratia Award [8 wks(5x8) pay] 1,275,680.00 1,316,120.00 1,357,520.00 1,398,480.00 1,483,040.00 1,567,280.00 1,650,680.00 1,734,960.00

Total cost per year[T] 19,402,398.64 20,000,324.26 20,363,611.96 21,218,058.04 22,219,487.92 23,465,018.44 24,946,961.14 26,193,083.08

T/Effective working days 219 219 219 219 219 219 219 219

ALL-IN DAILY RATE 88,595.43 91,325.68 92,984.53 96,886.11 101,458.85 107,146.20 113,913.06 119,603.12
RATE PER HOUR: - 8 11,074.43 11,415.71 11,623.07 12,110.76 12,682.36 13,393.28 14,239.13 14,950.39
less 4 Sundays in a month 31-(4) = 27
12 months in 1 year
31 days in a month ALL IN LABOUR RATES PER DAY (2007)
Day W'man/ Driver 'A'/ Artisans
General Labour Head Labourer Time Keeper Store Keeper Driver 'L' Night W'man [Grade 1] Foreman
Consolidated Basic Rate/Day (A) 37,953.00 39,155.00 40,386.00 41,605.00 44,120.00 46,627.00 49,108.00 51,615.00
Cost/Year 'A'x27x12 12,296,772.00 12,686,220.00 13,085,064.00 13,480,020.00 14,294,880.00 15,107,148.00 15,910,992.00 16,723,260.00

Add; On cost on Basic


Social Security 12.50%
Gang Leadership - 2.00%
Workmen Compesation - 2.50%
Funeral Grant - 2.50%
19.50% 2,397,870.54 2,473,812.90 2,551,587.48 2,628,603.90 2,787,501.60 2,945,893.86 3,102,643.44 3,261,035.70
Leave allowance ['A'x21 days] 797,013.00 822,255.00 848,106.00 873,705.00 926,520.00 979,167.00 1,031,268.00 1,083,915.00
Tools allowance [1000x27x12] - - - - - - 324,000.00 -
Height allowance [800x27x12] 259,200.00 259,200.00 - - - 259,200.00 248,832.00
Medical Subsidy 2.50% 307,419.30 317,155.50 327,126.60 337,000.50 357,372.00 377,678.70 397,774.80 418,081.50

Redundancy award [Av. 6 wks pay] 1,138,590.00 1,174,650.00 1,211,580.00 1,248,150.00 1,323,600.00 1,398,810.00 1,473,240.00 1,548,450.00
Severance Award(two month) 2,049,462.00 2,114,370.00 2,180,844.00 2,246,670.00 2,382,480.00 2,517,858.00 2,651,832.00 2,787,210.00
Long Service(two month) 2,049,462.00 2,114,370.00 2,180,844.00 2,246,670.00 2,382,480.00 2,517,858.00 2,651,832.00 2,787,210.00
Ex-Gratia Award [8 wks(5x8) pay] 1,518,120.00 1,566,200.00 1,615,440.00 1,664,200.00 1,764,800.00 1,865,080.00 1,964,320.00 2,064,600.00

Total cost per year[T] 22,813,908.84 23,528,233.40 24,000,592.08 24,725,019.40 26,219,633.60 27,709,493.56 29,767,102.24 30,922,594.20

T/Effective working days 216 216 216 216 216 216 216 216

ALL-IN DAILY RATE 105,619.95 108,927.01 111,113.85 114,467.68 121,387.19 128,284.69 137,810.66 143,160.16
RATE PER HOUR: - 8 13,202.49 13,615.88 13,889.23 14,308.46 15,173.40 16,035.59 17,226.33 17,895.02
GRACE GROUP QSCE3 KNUST/IDL

No. Name Student Ref. Student Positions in Contact No. Email


Number Index No. Company

1 Managing Director
2 General Manager
3 Technical Director
4 Project Manager
5 Project Accountant
Chief Quantity
6
Surveyor
7 Chief Estimator

Quality Control &


8 Assurance Manager

9 Estimator
10 Project Engineer
11 Services Engineer
12 Procurement Officer

NOTE;

The Company Positions are provisional and subject to any reasonable changes.

Anybody can contribute to it.

Also I have lost the list with the index numbers so you may put in your numbers and forward it back to me or just call and inform me
less 4 Sundays in a month 31-(4) = 27
12 months in 1 year
31 days in a month ALL IN LABOUR RATES PER DAY (2013-Projected)
Lab.Grouping(As per TUC rating) Group 1 Group 2 Group 3 Group 4 Group 5
Typical Designation Gen. Lab. Head Lab. Time Keeper St. Keeper Driver 'L'
Consolidated Basic Rate/Day (A) 8.10 8.16 8.40 8.64 9.24
Cost/Year 'A'x27x12 2,624.40 2,643.84 2,721.60 2,799.36 2,993.76

Add; On cost on Basic


Social Security 12.50%
Gang Leadership - 2.00%
Workmen Compesation - 2.50%

Funeral Grant - 2.50%

19.50% 511.76 515.55 530.71 545.88 583.78


Leave allowance ['A'x21 days] 170.10 171.36 176.40 181.44 194.04
Tools allowance [0.15x27x12] - - - - -
Height allowance [0.12x27x12] 38.88 38.88 - -
Medical Subsidy 2.50% 65.61 66.10 68.04 69.98 74.84

Redundancy award [Av. 6 wks pay] 243.00 244.80 252.00 259.20 277.20
Severance Award(two month) 437.40 440.64 453.60 466.56 498.96
Long Service(two month) 437.40 440.64 453.60 466.56 498.96
Ex-Gratia Award [8 wks(5x8) pay] 324.00 326.40 336.00 345.60 369.60

Total cost per year[T] 4,852.55 4,888.20 4,991.95 5,134.58 5,491.15

T/Effective working days 216 216 216 216 216

ALL-IN DAILY RATE 22.47 22.63 23.11 23.77 25.42

RATE PER HOUR: - 8 2.81 2.83 2.89 2.97 3.18

ALL-IN DAILY RATE 22.47 22.63 23.11 23.77 25.42

25%added for night rate 28.08 28.29 28.89 29.71 31.78


EFFECTVE WORKING DAYS IN A YEAR
PER DAY (2013-Projected)
Group 6 Group 7 Group 8 No of days in a year 365
Driver 'A'/ [Grade 1] Foreman
9.72 10.20 10.80 LESS
3,149.28 3,304.80 3,499.20 Week-Ends(2 x 52 weeks in a year) 104
National Holidays 12
Annual Leave 21
Casual or Sick Leave 7
Bad weather days 5
149

Hence Effective working days/year 216

614.11 644.44 682.34


204.12 214.20 226.80
- 48.60 48.60 National Holidays
- 38.88 38.88
78.73 82.62 87.48 New year's day 1
Indece day 1
291.60 306.00 324.00 Good Friday 1
524.88 550.80 583.20 Easter Monday 1
524.88 550.80 583.20 May day 1
388.80 408.00 432.00 AU day 1
Republic Day 1
5,776.40 6,149.14 6,505.70 Islamic Holidays 2
Farmer's Day 1
216 216 216 Xmas day 1
Boxing Day 1

26.74 28.47 30.12 12

3.34 3.56 3.76

26.74 28.47 30.12

33.43 35.59 37.65


GRACE GROUP QSCE3-KNUST/IDL

PRICE LIST FOR BUILDING MATERIALS

REF. ITEMS UNIT BASIC PRICE GH¢ SOURCE % FOR DELIVERY AS DELIVERED

Excavation
1 Hardcore filling (laterite) m³ 24.00 10% 26.40
2 Tipper Truck and Driver (Hiring) day 380.00 10% 418.00
3 Excavator 320 (hiring) day 10% -
4 250-HP Buldozer and Operator (hiring) day 1,000.00 10% 1,100.00
5 7/5 Concrete Mixer (hiring) day -
6 Vibrator and Operator (hiring) day -
7 Compressor (hiring) day -
-
Concrete Works -
8 Stones (20mm) m³ 63.00 63.00
9 Stones (40mm) m³ 63.00 63.00
10 Stones (50mm) m³ 63.00 63.00
11 Rough Sand 5m³ -
12 Cement bag 16.50 16.50
13 Flexel Bituminus fibre (for flilling expansion gaps). m² -
14 Cork (2.4m x 1.2m) m² -
-
Timber for Moulds -
15 50mm x 75mm x 4.2m Scantlings (2" x 3") no. -
16 50mm x 100mm x 4.2m Scantlings (2" x 4") no. -
17 50mm x 150mm x 4.2m Scantlings (2" x 6") no. -
18 50mm x 300mm x 4.2m Scantlings (2" x 12") no. -
19 25mm x 300mm x 4.2m Scantlings (1" x 12") no. -
20 64mm x 300mm x 4.2m Scantlings(2½"x12") no. -
21 75mm x 100mm x 4.2m Scantlings (3" x 4") no. -
22 100mm x 100mm x 4.2m Scantlings (4" x 4") no. -
23 1" Nails (box) kg -
24 1½" Nails kg -
25 2" Nails kg -
26 2½" Nails kg -
27 3" Nails kg -
28 4" Nails kg -
GRACE GROUP QSCE3-KNUST/IDL

29 6" Nails kg -
-
Reinforcement -
30 6mm diameter (¼") Tonne 1,450.00 1,450.00
31 8mm diameter (⅜") Tonne 1,450.00 1,450.00
32 10mm diameter (⅜") Tonne 1,450.00 1,450.00
33 12mm diameter (½") Tonne 1,720.00 1,720.00
34 14mm diameter (⅝") Tonne 1,720.00 1,720.00
35 16mm diameter (⅝") Tonne 1,720.00 1,720.00
36 20mm diameter (¾") Tonne -
37 22mm diameter (1") Tonne -
38 25mm diameter (1") Tonne -
39 32mm diameter Tonne -
40 40mm diameter Tonne -
41 Binding Wire (coil) kg -
42 BRC Fabric No 65 (2m x 3m) Roll -
43 BRC Fabric No 125 (2m x 3m) Roll -
-
Cement Mortar -
44 White Cement (50kg) bag -
45 Whiting (50kg) (for pointing) bag -
46 5/7 Mixer & Operator (Hiring) day -
-
Walling -
47 100mm Clay Bricks no. -
48 150mm Clay Bricks no. -
49 225mm Clay Bricks no. -
50 100mm Hollow Blocks no. -
51 125mm Hollow Blocks no. -
52 150mm Hollow Blocks no. -
53 75mm Solid Blocks no. -
54 100mm Solid Blocks no. -
55 125mm Solid Blocks no. -
56 150mm Solid Blocks no. -
-
Roofing -
Corrugated Short Spans -
GRACE GROUP QSCE3-KNUST/IDL

57 Aluzinc (Gauge 0.35mm) 2.3m x 0.76m Packet -


58 Aluminium(Gauge 0.5mm) 2.4m x 1.2m Packet -
59 Aluminium(Gauge 0.6mm) 2.4m x 1.2m Packet -
60 Aluminium(Gauge 0.8mm) 2.4m x 1.2m Packet -
61 Standard Asbestos "Gold" 2.4m x 1.2m No. -
Corrugated Long Spans -
62 Aluminium(Gauge 0.5mm) 2.4m x 1.2m Packet -
63 Aluminium(Gauge 0.6mm) 2.4m x 1.2m Packet -
64 Aluminium(Gauge 0.8mm) 2.4m x 1.2m Packet -
65 Drive Screw (with Washer) set -
Ridge Cap -
66 Aluminium(Gauge 0.35mm) 9m x 1.2m No. -
67 Aluminium(Gauge 0.5mm) 9m x 1.2m No. -
68 Aluminium(Gauge 0.6mm) 9m x 1.2m No. -
69 Aluminium(Gauge 0.8mm) 9m x 1.2m No. -
70 Roofing Nails (with Washer) set -
Roofing members -
71 50mm x 75mm x 4.2m Scantlings No. -
72 50mm x 100mm x 4.2m Scantlings No. -
73 50mm x 150mm x 4.2m Scantlings No. -
74 25mm x 300mm x 4.2m Boards No. -
75 50mm x 300mm x 4.2m Boards No. -
76 64mm x 300mm x 4.2m Boards No. -
77 5mm x1.2m x 2.4m Plywood(⅛") No. -
78 6mm x 1.2m x 2.4m Plywood(¼") No. -
79 12mm x 1.2m x 2.4m Plywood(½") -
80 12mm x 20mm x 4.2m Batten No. -
81 12mm x 25mm x 4.2m Batten No. -
82 12mm x 40mm x 4.2m Batten No. -
83 12mm x 45mm x 4.2m Batten No. -
84 12mm x 50mm x 4.2m Batten No. -
85 20mm x 50mm x 4.2m Batten No. -
-
Carpentry & Joinery -
86 Panelled door (single) no. -
87 Panelled door (double) no. -
88 Flush door (single) no. -
GRACE GROUP QSCE3-KNUST/IDL

89 Flush door (double) no. -


90 1.2m x 2.4m Formica Sheet no. -
91 20mm x 75mm Flooring Board m³ -
92 T and G Boards (Wood) m³ -
93 T and G Boards (Rubber) m³ -
94 Formica Glue litre -
95 Mastic litre -
96 50mm x 50mm Weldmesh(1.2m x 2.4m) no. -
97 Expanded Metal(1.2m x 2.4m) no. -
98 Nylon Mosquito Gauze (1m x 30m) Roll -
99 Aluminium Mosquito Gauze (1m x 30m) Roll -
-
Ironmongry -
100 50mm Brass Butt Hinges pair -
101 64mm Brass Butt Hinges pair -
102 75mm Brass Butt Hinges(Medium section) pair -
103 100mm Brass Butt Hinges(Medium Section) pair -
104 150mm Brass Barrel Bolt (and Socket) No. -
105 225mm Mild Steel Barrel Bolt (Galvanised) No. -
106 300mm Galvanised Tee Hinges No. -
107 225mm Mild Steel Hasp and Staple (Galvanised) No. -
108 Cupboard Lock No. -
119 Heavy Rim Lock No. -
110 Mortice Lock No. -
111 Mortice Lock (Italian Type) No. -
112 Cylinder Night Latch Lock No. -
113 Drawer Locks No. -
114 Drawer Handles No. -
115 3-Blade Louvre Carrier pair -
116 4-Blade Louvre Carrier pair -
117 5-Blade Louvre Carrier pair -
118 6-Blade Louvre Carrier pair -
119 7-Blade Louvre Carrier pair -
120 8-Blade Louvre Carrier pair -
121 9-Blade Louvre Carrier pair -
123 10-Blade Louvre Carrier pair -
124 11-Blade Louvre Carrier pair -
GRACE GROUP QSCE3-KNUST/IDL

125 12-Blade Louvre Carrier pair -


-
Glazing -
126 2' Louvre Glass (Plain) No. -
127 2'-6" Louvre Glass (Plain) No. -
128 3' Louvre Glass (Plain) No. -
129 2' Louvre Glass (Obscure) No. -
130 2'-6" Louvre Glass (Obscure) No. -
131 3' Louvre Glass (Obscure) No. -
132 0.7kg Sheet Glass(24oz) m² -
133 0.9kg Sheet Glass(32oz) m² -
-
Plumbing -
134 (½") 12mm x 5.5m Copper pipe No. -
135 (¾") 20mm x 5.5m Copper pipe No. -
136 (1") 25mm x 5.5m Copper pipe No. -
137 (¾") 20mm x 6m Galvanised Pipe No. -
138 (1") 25mm x 6m Galvanised Pipe No. -
139 (1¼") 32mm x 6m Galvanised Pipe No. -
140 (1½") 40mm x 6m Galvanised Pipe No. -
141 (1¾") 45mm x 6m Galvanised Pipe No. -
142 (2") 50mm x 6m Galvanised Pipe No. -
143 (½") 12mm x 6m PVC Pipe No. -
144 (¾") 20mm x 6m PVC Pipe No. -
145 (1") 25mm x 6m PVC Pipe No. -
146 (1¼") 32mm x 6m PVC Pipe No. -
147 (1½") 40mm x 6m PVC Pipe No. -
148 (1¾") 45mm x 6m PVC Pipe No. -
149 (2") 50mm x 6m PVC Pipe No. -
150 (4") 100mm x 3m PVC Pipe No. -
151 (6") 150mm x 3m PVC Pipe No. -
152 (½") 12mm HP Stop Valve No. -
153 (¾") 20mm HP Stop Valve No. -
154 (1") 25mm HP Stop Valve(Brass) No. -
155 (1¼") 32mm HP Stop Valve(Brass) No. -
156 (1½") 40mm HP Stop Valve(Brass) No. -
157 (1¾") 45mm HP Stop Valve(Brass) No. -
GRACE GROUP QSCE3-KNUST/IDL

158 (2") 50mm HP Stop Valve(Brass) No. -


159 (½") 12mm Bib Valve (Tap)Brass No. -
160 (¾") 20mm Bib Valve (Tap)Brass No. -
161 (½") 12mm Pillar Tap No. -
162 (¾") 20mm Pillar Tap No. -
Stainless Steel Sink No. -
163 Single Bowl Single Drain No. -
164 Single Bowl Double Drain No. -
165 Double Bowl Single Drain No. -
166 Double Bowl Double Drain No. -
167 Wash Hand Basin (0.6m x 4m) No. -
168 W.C (Twyford) No. -
169 W.C (Plastic) No. -
170 Telephone rose Shower complete No. -
171 Bath (1.7m x 0.7m x 0.48m) No. -
-
Rendering and Finishing -
172 Smooth Sand m³ -
173 Hardener (liquid in gallon) litre -
174 Tongue and Groove m³ -
175 ⅛" Plywood (red) No. -
176 ¼" Plywood (red) No. -
177 4' x 4' Plasterboard No. -
178 4' x 4' Chipboard No. -
179 Terrazzo Pigment kg -
180 Terrazzo (Marble) Chippings bag -
181 Washed Terrazzo Chippings bag -
182 Dividing Strip No. -
183 14' Ebonite Strip No. -
184 Carbonrundum Stones set -
185 Acid (gallon) litre -
186 Mansion Polish(gallon) litre -
187 Wall Tiles (6" x 6") m² -
188 Porcelin Polish Tiles (12" x 12") m² -
189 Vinyl Floor Tiles m² -
190 Tile Adhesive (liquid) gallon litre -
191 ½" Insulation Fibre m² -
GRACE GROUP QSCE3-KNUST/IDL

192 Clout Nails kg -


193 Nails kg -
194 Cullamix kg -
195 Azar Vanish Gallon -
196 Yacht Vanish Gallon -
197 Sand Paper Roll -
198 Terrazzo Machine (Hiring) Day -
209 Tyrolean Machine (Hiring) Day -
-
Painting and Decoration -
200 Bituminous Paint (gallon) litre -
201 Snowcem Paint (gallon) litre -
202 Primer (Alkaline Resistant) litre -
203 Primer (Rust Inhibiting) litre -
204 Emulsion Paint (gallon) litre -
205 Oil Paint (gallon) litre -
206 Mordant Solution litre -
207 Pale Knoting litre -
208 Putty kg -
209 Interlocking Pavement Block (37) m² -
210 Rectangular Pavement Block (50) m² -
211 Wavis Pavement Block (50) m² -
UNIT RATES BUILD-UP

EXCAVATION & EARTHWORKS

Assumptions
All in Labour rate/day GH¢ 22.47
Ditto Artisan GH¢ 28.47

1.1 Site Clearance 1420 m²

Labour Output 100 m² / gang day

Method (Manual) 5 gang day

No. of Man days required 14.2


say 14 days

Total cost GH¢ 1,572.59

Unit Cost/m³ 1.11

Add:P &O 25% 0.28

Unit Rate 1.38 /m²

1.2 Excavate Oversite/Top Soil (150mm deep) 64 m²

Assumptions: Use of
Bulldozer (Cat D6) - 500 m² output/day
Operator 1 nr.

Plant
Buldozer(Cat D6) 1,100.00
Fuel(225ltrs) 399.38
Lubricants 8.50
Operator,s tip 50.00
Banksman 22.47

Total cost 1,580.34

Unit Cost / m² 3.16

Add:P & O 25% = 0.79

Unit Rate 3.95 /m²


UNIT RATES BUILD-UP

EXCAVATION & EARTHWORKS

Assumptions
All in Labour rate/day GH¢ 22.47
Ditto Artisan GH¢ 28.47

1.3 Trench Excavation (0-2m deep) 59 m3

Labour Output 3 m3/mday


All in Labour rate/day GH¢ 22.47

Soil factor(Laterite) 1
Method (Manual) 0.7
Effective Output 2.1 m3/mday

No of Mdays required 19.67


say 20 days

Total cost GH¢ 449.31

Unit Cost 7.62


Add:P &O 25% 1.90

Unit Rate 9.52 /m3

Ditto in US$ 6.90 /m3

1.4 Pit Excavation 0 - 2m 14 m³

Labour Output 3 m3/mday


All in Labour rate/day GH¢ 22.47

Soil factor(Laterite) multiplying factor 1


Method (Manual) 0.6
Effective Output = 3.0 * 1.0 * 0.6 1.8 m3/mday

No of Mdays rqd = 14.0 / 1.8 7.78


say 8 days

Total cost GH¢ 179.72

Unit Cost 12.84

Add:P &O 25% 3.21

Unit Rate 16.05 /m3


UNIT RATES BUILD-UP

EXCAVATION & EARTHWORKS

Assumptions
All in Labour rate/day GH¢ 22.47
Ditto Artisan GH¢ 28.47

1.5 Exc wkg space 65 m²

Plant
Excavator of an output 40 m²/pltday
Plt days reqd = 65 / 40 = 1.63
Say 2 pltday

Hiring cost/day 750


Fuel(112.50ltrs) 100.125
Banksman 22.47
Operator,s tip 50
plt. cost/day 922.60

Cost of 2 pl days 1,503.83

Add: Lowloader

TOTAL COST 1,503.83

Unit Cost 23.14

Add:P &O 25% 5.78

Unit Rate 28.92 /m3


UNIT RATES BUILD-UP

EXCAVATION & EARTHWORKS

Assumptions
All in Labour rate/day GH¢ 22.47
Ditto Artisan GH¢ 28.47

1.6 Disposal of Surplus off site 14 m3

Note: Actual Quantity is 10m³ but its too small so we assume 100m³

Soil Identification Laterite


Bulkage factor 22.00%
Method (Manual) 5m³ Tipper & 5 labourers

Haulage Cycle:
Loading time/trip (5x8x60) = 34.29
5x14

Effective Output/day 45 m3

No of Mdays required (34.29/45 0.762


say 1 days

Hiring cost/day 400


Fuel(12.50ltrs) 14.75
Labour 112.33
Banksman 22.47

Total Plant & Labour cost/day 549.54

Total Cost for 1 days 549.54

Unit Cost 39.25

Add:P &O 25% 9.81

Unit Rate /m3 49.07


UNIT RATES BUILD-UP

EXCAVATION & EARTHWORKS

Assumptions
All in Labour rate/day GH¢ 22.47
Ditto Artisan GH¢ 28.47

1.7 Disposal of Excavated Material in Spoil Heaps on Site 63 /m³

Labour Output 5 m³/manday

Soil Identification Laterite


Bulkage factor 22.00%
Method (Manual) 5 Labourers

No. of Man days required 15.372


say 15 days

Total cost GH¢ 336.98

Unit Cost/m³ 5.35

Add:P &O 25% 1.34

Unit Rate 6.69 /m³

1.8 Filling to excavations arising from excavations 35 m2

Labour Output 5 m³/manday

Soil Identification Laterite


Method (Manual) 5 Labourers for Spreading, Levelling and Compacting

No. of Man days required 7


say 7 days

Total cost GH¢ 157.26

Unit Cost/m³ 4.49

Add:P &O 25% 1.12

Unit Rate = 5.62 /m³


UNIT RATES BUILD-UP

EXCAVATION & EARTHWORKS

Assumptions
All in Labour rate/day GH¢ 22.47
Ditto Artisan GH¢ 28.47

1.9 Imported sand fill 63 m3

Materials Laterite as obtained from Suppliers offsite


Method (Manual) 5 Labourers for Spreading, Levelling and Compacting

Material
Cost/m3(Ex-Site) GH¢ 18.00
Matl 63.00 m3
Add:Bulk+waste 22% 13.86
Say 76.86 m3

Material Cost = 76.86m³ * 22.00 1,383.48

Labour
Labour Output m³/mday 5
All in Lab. rate/day GH¢ 22.47
No. of Mdays required 15.37
Say mdays 15.00

Labour cost = 17mdays * 21.97 336.98

Plant

Hiring cost/day 80.00


Fuel(22.5ltrs) 39.94
Operator's output 22.47

plant. cost/day 142.40

No of dys rqd @ output


of 20m3/dy 20 3.843
Say 4

Plant Cost/day = 4pltdays * 141.91 569.61

TOTAL COST (Mtl + Lab + PL) 2,290.07

Unit Cost 36.35

Add:P &O 25% 9.09

Unit Rate 45.44 /m3


UNIT RATES BUILD-UP

EXCAVATION & EARTHWORKS

Assumptions
All in Labour rate/day GH¢ 22.47
Ditto Artisan GH¢ 28.47

1.10 Surface Treatment (Lev & Compt) m2 85 m²

Plant
Plate Compactor 250 m2/pltday m²/pltday
Plt days reqd 0.34
Say 1 pltday

Hiring cost/day 80.00


Fuel(22.5ltrs) 25.20
Operator's output 22.47

plant. cost/day 127.67

Cost of 1plt days 127.67

Add: T & T to site 10% 12.77

TOTAL COST 140.43

Unit Cost 1.65


Add:P &O 25% 0.41

Unit Rate 2.07 /m2


UNIT RATES BUILD-UP

EXCAVATION & EARTHWORKS

Assumptions
All in Labour rate/day GH¢ 22.47
Ditto Artisan GH¢ 28.47
HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

CONCRETE WORKS
In situ Concrete Operator 50.00
Artisan/day 50.00
Labourer/day 40.00
Currency in Use GH¢

1.1 Concrete C15 (1:4:8-38mm aggregate) in Blinding assume 20

Method: Manual mixing, transporting, placing and compacting

Materials:

Cement; Asumming a nominal volumetric mix of 1 m³


29 bags @ 16.50 478.50
Unloading and stacking 120 /man day
0.241667 /man day @ 40.00 9.67

Sand: 4 m³ @ 24.00 96.00

Aggregate (38mm) 8 m³ @ 63.00 504.00

Sub - Total for Material 1,088.17

Allow for Shrinkage and waste 33% 359.10

Total material Cost as mixed for 20 m³ 1,447.26

Total Material Cost/m³ 72.36

Total Material Cost as mixed for 20 m³

Labour

Mixing + Transporting + Placing and Vibrating at a combined output of


(1 + ½ + ½) man days/m³ 2 /man day @ 20 40.00 /man day

Hence we use 40.00 /man day @ 40.00 1,600.00

Add for Masons Directing 2 nr @ 50.00 100.00

Total Cost of Labour

Total Cost (Material + Labour)

Total Cost of Concrete/m³

ADD: ON - COST 25%

UNIT RATE GH¢

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

CONCRETE WORKS
In situ Concrete Operator 50.00
Artisan/day 50.00
Labourer/day 40.00
Currency in Use GH¢
50mm blnd'g/m²

1.2 Concrete C20 (1:3:6-38mm aggregate) assume 10

Method: Machine mixing, Labour transporting, placing and compacting

Materials:

Cement; Asumming a nominal volumetric mix of 1 m³


29 bags @ 16.50 478.50
Unloading and stacking 120 /man day
0.241667 /man day @ 50.00 12.08

Sand: 3 m³ @ 26.00 78.00

Aggregate (38mm) 6 m³ @ 67.00 402.00

Sub - Total for Material 970.58

Allow for Shrinkage and waste 33% 320.29

Total material Cost as mixed for 25 m³ 1,290.88

Total Material Cost/m³ 51.64

Total Material Cost as mixed for 10 m³

Plant

Assume the use of 10/7 Diesel Concrete Mixer with an


Output/Batch Mix 0.2 m³
Mixing Cycle 10 mins 8 Working Hours
Operating Efficiency 75% 60 minutes/hour
All-in-rate 140.00 /plant day

Number of mixing cycles in a day would be (60 x 8)/10 = 48 mins


The achieved No. pf Batches/day would be 48 x 75% = 36 mins

Concrete Output/day 0.2 x 36 7.2 m³

No. of Working days for 10m³ of concrete = 25m3 25/7.2 1.39 days
Say 4 days

Cost/day 4 days @ 140.00 560.00

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

CONCRETE WORKS
In situ Concrete Operator 50.00
Artisan/day 50.00
Labourer/day 40.00
Currency in Use GH¢
Poker Vibrator with an All-in-Rate 55.00 /plant day
Cost of Plant for 2 days 4 days @ 55.00 220.00

Total Plan t cost of 4 days

Labour

Assuming a concrete gang of 10 comprising ng of 10

Mixer Operator 1 nr @ 50.00 50.00

Loaders 3 nr @ 40.00 120.00

Transporters 4 nr @ 40.00 160.00

Add for Masons Directing 2 nr @ 50.00 100.00

All-in-daily gang rate 430.00

Total Cost of Labour for 2 days 4 days @ 430.00

Total Cost For (Material + Plant + Labour)

Total Cost of Concrete/m³

ADD: ON - COST 25%

UNIT RATE GH¢

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

CONCRETE WORKS
In situ Concrete Operator 50.00
Artisan/day 50.00
Labourer/day 40.00
Currency in Use GH¢

1.3 Concrete C25 (1:2:4-20mm aggregate) Assume 10

Method: Machine mixing, Labour transporting, placing and compacting

Materials:

Cement; Asumming a nominal volumetric mix of 1 m³


29 bags @ 16.00 464.00
Unloading and stacking 120 /man day
0.241667 /man day @ 40.00 9.67

Sand: 2 m³ @ 25.00 50.00

Aggregate (38mm) 4 m³ @ 65.00 260.00

Sub - Total for Material 783.67

Allow for Shrinkage and waste 33% 258.61

Total material Cost as mixed for 7 m³ 1,042.28

Total Material Cost/m³ 148.90

Total Material Cost as mixed for 10 m³

Plant

Assume the use of 10/7 Diesel Concrete Mixer with an


Output/Batch Mix 0.2 m³
Mixing Cycle 10 mins 8 Working Hours
Operating Efficiency 75% 60 minutes/hour
All-in-rate 140.00 /plant day

Number of mixing cycles in a day would be (60 x 8)/10 = 48 mins


The achieved No. pf Batches/day would be 48 x 75% = 36 mins

Concrete Output/day 0.2 x 36 7.2 m³

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

CONCRETE WORKS
In situ Concrete Operator 50.00
Artisan/day 50.00
Labourer/day 40.00
Currency in Use GH¢

No. of Working days for 10m³ of concrete = 10/7.2 1.39 days


Say 2.00 days

Cost/day 2.00 days @ 140.00 280.00

Poker Vibrator with an All-in-Rate 55.00 /plant day


Cost of Plant for 2 days 2.00 days @ 55.00 110.00

Total Plant Cost for 2 days

Labour

Assuming a concrete gang of 10 comprising

Mixer Operator 1 nr @ 50.00 50.00

Loaders 3 nr @ 40.00 120.00

Transporters 5 nr @ 40.00 200.00

Add for Masons Directing 2 nr @ 50.00 100.00

All-in-daily gang rate 470.00

Total Cost of Labour for 2 days 2 days @ 470.00

Total Cost For (Material + Plant + Labour)

Total Cost of Concrete/m³

ADD: ON - COST 25%

UNIT RATE GH¢

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

CONCRETE WORKS
In situ Concrete Operator 50.00
Artisan/day 50.00
Labourer/day 40.00
Currency in Use GH¢

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

Reinforcement Operator
Gang/day 2 Steel Bender 100.00 Artisan/day
1 Labourer 40.00 Labourer/day
140.00 Currency in Use

m3 A Mild Steel Reinforcement Bar, 16mm Diameter assume

Assuming we have 1 Tonne of reinforcement to work on

Materials:

16mm Rebar 1 tonne 3,700.00


Waste 15% 0.15 tonne 3,700.00
Binding Wire 15 kg 2.00

Total Material Cost for 1 tonne

Labour:

Unloading and stacking 1 tonne at an output of 5 tonnes/manday


1/5 = 0.2 man days 0.2 @ 40.00

Cutting and bending + Fixing 1 tonne in foundations would require


(1/500 + 1/400) = 0.0045 gang days
Gang days per kg would be (1000 x 0.0045) = 4.5
Say 5 gangdays
1,447.26
Cost of 5 gangdays 5 @ 140.00

Total Labour Cost for 1 tonne

Total Cost (Material + Labour)

If 1 Tonne of Bar is = 1000 kg then

Total Cost/kg

1,700.00 ADD: ON - COST 25%

3,147.26 UNIT RATE / kg

157.36
/ tonne

39.34

196.70

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

Reinforcement Operator
Gang/day 2 Steel Bender 100.00 Artisan/day
1 Labourer 40.00 Labourer/day
140.00 Currency in Use
9.84

m3 B Mild Steel Reinforcement Bar, 12mm Diameter assume

Assuming we have 1 Tonne of reinforcement to work on

Materials:

12mm Rebar 1 tonne 1,730.00


Waste 15% 0.15 tonne 1,730.00
Binding Wire 13 kg 2.00

Total Material Cost for 1 tonne

Labour:

Unloading and stacking 1 tonne at an output of 5 tonnes/manday


0.10/5 = 0.02 man days 0.02 @ 40.00

Cutting and bending + Fixing 1 tonne in foundations would require


(1/500 + 1/320) = 0.005 gang days
Gang days per kg would be (100 x 0.005) = 0.5
Say 1 gangdays
516.35
Cost of 5 gangdays 1 @ 140.00

Total Labour Cost for 1 1.03 tonne

Total Cost (Material + Labour)

If 1 Tonne of Bar is = 1000 kg then 1003

Total Cost/kg

ADD: ON - COST 25%

UNIT RATE

/ tonne

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

Reinforcement Operator
Gang/day 2 Steel Bender 100.00 Artisan/day
1 Labourer 40.00 Labourer/day
140.00 Currency in Use

780.00

B Mild Steel Reinforcement Bar, 10mm Diameter assume

Assuming we have 1 Tonne of reinforcement to work on

Materials:

10mm Rebar 1 tonne 1,730.00


Waste 15% 0.15 tonne 1,730.00
Binding Wire 13 kg 2.00

Total Material Cost for 1 tonne

1,720.00 Labour:

Unloading and stacking 1 tonne at an output of 5 tonnes/manday


3,016.35 0.10/5 = 0.02 man days 0.02 @ 40.00

Cutting and bending + Fixing 1 tonne in foundations would require


301.64 (1/500 + 1/320) = 0.005 gang days
100 x 0.005) = 0.5
Say 1 gangdays
75.41
Cost of 5 gangdays 1 @ 140.00
377.04
Total Labour Cost for 1 tonne

Total Cost (Material + Labour)

If 1 Tonne of Bar is = 1000 kg then

Total Cost/kg

ADD: ON - COST 25%

UNIT RATE

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

Reinforcement Operator
Gang/day 2 Steel Bender 100.00 Artisan/day
1 Labourer 40.00 Labourer/day
140.00 Currency in Use
/ tonne

m3 Fabric Mesh Reinforcement assume 10

Materials:

Assuming we use a fabric mesh size of 7ft x 75ft = 2.10m x 22.50m then
Net Covering Capacity 1.90 x 22.30 = 42.37

Number of rolls required (100/42.7) = 2.30

Add for Waste 15% = 0.35


2.65
Say 3

Therefore Use 3 rolls @ 450.00

Total Material Cost

Labour 50 m² per gangday

1,488.97 Unloading, Cutting and Laying of 50m²/ gangday would require


100/ 50 = 2
Say 2 gangdays

2 Gang day 2 gangdays @ 140.00

Total Labour Cost

Total Cost (Material + Labour)

Total Cost / m² 10 m2

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

Reinforcement Operator
Gang/day 2 Steel Bender 100.00 Artisan/day
1 Labourer 40.00 Labourer/day
140.00 Currency in Use
ADD: ON - COST 25%

UNIT RATE / m²

390.00

940.00

2,818.97

281.90

70.47

352.37

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

Reinforcement Operator
Gang/day 2 Steel Bender 100.00 Artisan/day
1 Labourer 40.00 Labourer/day
140.00 Currency in Use

Formwork

Nails 0.1 kg 1.80

Add : Transport to site/ price excalation 10%

Labour

Carpenter 1.14 hr 2.35

1 Labourer 1.14 mdays 1.80

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

Reinforcement Operator
Gang/day 2 Steel Bender 100.00 Artisan/day
1 Labourer 40.00 Labourer/day
140.00 Currency in Use

Total Cost

Ditto/m2

ADD: ON - COST 25%

UNIT RATE

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

50.00 Formwork Operator


50.00 Gang/day 2 Carpenters 100.00 Artisan/day
40.00 1 Labourer 40.00 Labourer/day
GH¢ 140.00 Currency in Use

1000 kg A Formwork to slabs, staircase and horizontal soffit of a building

Assuming the dimensions of the area to be supported to be 10m x 10m then;

Materials

3,700.00 No. of Joist @ 750mm Centers would be (10 / 0.75) + 1 = 14.3


555.00 Approx. to = 15
30.00 Hence no. of props required = 15 x 15 = 225

4,285.00 Assume that Qantity of materials needed aftter the calculations are as follows

Nr. of Timber Basic Price Volume


25mm Wawa boarding 102 nr. 21.00 2.75
50 x 100mm props 232 nr. 8.50 4.17
25 x 150mm brace 113 nr. 7.00 1.44
8.36
4.49 Toatl Cost of Wawa including Waste

Nails; Assume 3 uses with utilization factor of (0.2 + (2 x 0.1))kg/m²


Weight of nails required for 3 uses for 100m² 40
Add waste 15% 6
46

700.00 Cost of Nails in kg 46 @

704.49 Total Cost of Timber and Nails for 3 uses

4,989.49 Material Cost per 1 use

Mould Oil at a utilization capacity of 30m²/4.5L


would require 100/30 (4.5L unit) = 3.33 4.5L units
4.99 Add for waste 15% 0.50
3.83

1.25 Cost of 4 units of mould oil = 4 @

GH¢ 6.24 Total material Cost / use

6,236.86 Labour

Unloading and stacking of 8.35m³ of timber at an output of 4.0m³/man day


would require 8.35 / 4.00 (man days) = 2.09 man days

Use 2 man days 2 @

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

50.00 Formwork Operator


50.00 Gang/day 2 Carpenters 100.00 Artisan/day
40.00 1 Labourer 40.00 Labourer/day
GH¢ 140.00 Currency in Use

100 kg Mould Oil application at 30m²/man day require 100/30 = 3.33

Use 3 man days 3 @

Fabrication + Erection + Striking of 100m² at an output of


(1 + 1 + 1) = 0.16 gang days / m³
1,730.00 18 15 30
259.50
26.00 Hence, No. of gang days req'd = 0.16 x 100 = 16.00

2,015.50 Therefore, Cost of 16 gang days = 16 @

Total Labour Cost

Total Cost (Material and Labour) for 100m²

0.80
Cost per 1m²

ADD: ON - COST 20%

UNIT RATE
140.00

140.80

2,156.30

2.16

0.54

GH¢ 2.70

2,695.38

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

50.00 Formwork Operator


50.00 Gang/day 2 Carpenters 100.00 Artisan/day
40.00 1 Labourer 40.00 Labourer/day
GH¢ 140.00 Currency in Use

A Formwork to sides of walls and associated features


100 kg
Materials

Timber
At an average utilization of 0.09m³/m² (for one use),
timber req'd, including waste = 0.09 x 100 = 9.00
1,730.00
259.50 Cost of 9m³ timber = 9 @
26.00
Nails
2,015.50 Assuming 3 uses and utilization as previous calculation above

Total Cost of (timber + nails) for 3 uses

Hence Cost / 1 use

Mould oil
0.80 Cost as calculated above

Total Material Cost

Labour

140.00 Unloading and stacking of 9m³ of timber at an output of 4.0m³/man day


would require 9.0 / 4.00 (man days) = 2.25 man days
140.80 Use 2 man days 2 @

2,156.30 Mould Oil application; Cost as calculated above

Fabrication + Erection + Striking of 100m² at an output of


(1 + 1 + 1) = 0.17 gang days / m³
2.16 16 14 28

Hence, No. of gang days req'd = 0.17 x 100 = 17.00


0.54
Therefore, Cost of 16 gang days = 17 @
GH¢ 2.70
Total Labour Cost

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

50.00 Formwork Operator


50.00 Gang/day 2 Carpenters 100.00 Artisan/day
40.00 1 Labourer 40.00 Labourer/day
GH¢ 140.00 Currency in Use
2,695.38 Total Cost (Material and Labour) for 100m²

Cost per 1m²

ADD: ON - COST 20%

UNIT RATE

m2

1,350.00

1,350.00

280.00

280.00

1,630.00

163.00

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

50.00 Formwork Operator


50.00 Gang/day 2 Carpenters 100.00 Artisan/day
40.00 1 Labourer 40.00 Labourer/day
GH¢ 140.00 Currency in Use
40.75

GH¢ 203.75

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

50.00 Formwork Operator


50.00 Gang/day 2 Carpenters 100.00 Artisan/day
40.00 1 Labourer 40.00 Labourer/day
GH¢ 140.00 Currency in Use

0.18

2.68

2.05

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

50.00 Formwork Operator


50.00 Gang/day 2 Carpenters 100.00 Artisan/day
40.00 1 Labourer 40.00 Labourer/day
GH¢ 140.00 Currency in Use

GH¢

say

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

50.00
Artisan/day 50.00
Labourer/day 40.00
Currency in Use GH¢

f a building 100 m²

o be 10m x 10m then;

ulations are as follows

Amount
2,142.00
1,972.00
791.00
4,905.00
4,905.00

x 0.1))kg/m²
kg

kg

2.00 92.00

4,997.00

1,665.67

4.00 16.00

1,681.67

of 4.0m³/man day
man days

40.00 80.00

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

50.00
Artisan/day 50.00
Labourer/day 40.00
Currency in Use GH¢

man days

40.00 120.00

gang days

140.00 2,240.00

2,440.00

4,121.67

41.22

8.24

GH¢ 49.46

7.67

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

50.00
Artisan/day 50.00
Labourer/day 40.00
Currency in Use GH¢

assume 100 m²

586.72 5,280.50

92.00

5,372.50

1,790.83

16.00

1,806.83

4.0m³/man day
man days
40.00 80.00

120.00

gang days

140.00 2,380.00

2,580.00

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

50.00
Artisan/day 50.00
Labourer/day 40.00
Currency in Use GH¢
4,386.83

43.87

8.77

GH¢ 52.64

Prepared By: Adomako Boateng Gabriel (6464411)


HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

BLOCK WORK
Operator 22.47
Artisan/day 28.47
Labourer/day 22.47
Currency in Use GH¢

Amount GH¢

150 mm Solid sandcrete blockwork in cement and


sand (1:4) mortar:

Material
A. MORTAR
Cement and sand mortar (1:4)
Assume a volumetric mix of 1m3 mortar,

I Cement 1m³
1m³ of Cement required would be 29 @ 16.50 = GH¢ 478.50

Unloading and stacking requires 29/120 man-day = 0.24 @ 22.47 = GH¢ 5.43

II Sand 4m3 4 @ 24.00 GH¢ 96.00

Therefore: Total material cost (5m3) 579.93

For shrinkage and waste, allow 33% 191.38

Total material cost / (5m3) 771.31

Therefore, material cost per meter cube = 757.18 / 5 = 154.26

III Labour - Mixing 1m3 requires one man-day 1 @ 22.47 22.47

Total Cost / m³ of Mortar 176.73

B. BLOCKS assume 100 m²

IV Using 150mm x 225 x 450 nominal size solid block

Area of 1 nominal size of block = 0.225 x 0.45 = 0.10125

No. of blocks required in 100m² area will be = 987.65

Add 10% waste = 98.77

Total no. of blocks required = 1,086.42 no.

Use, blocks 1087no. 1,087 @ 1.50 = 1,630.50

Prepared by : Raymond Kirk


()
HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

BLOCK WORK
Operator 22.47
Artisan/day 28.47
Labourer/day 22.47
Currency in Use GH¢

Let V = volume of mortar

V = [(0.225 X 0.45) - (0.2125 X 0.4375)] X 987.65 X 0.150

V = 0.0082813 x 148.148

V = 1.227m3

V Cost of 1.227m3 mortar 1.227 @ 176.73 = 216.84

Total Material Cost for Blocklaying 1,847.34

VI Labour

Blocklaying Output per gang day is 10 m²

Gang days required would be = 10.00


Say 10 gang days

Use 10 gang-days at bonus rate of 50.93 509.34

Total Cost Material and Labour 2,356.68

Then, Total Cost / m2 23.57

ADD - On - Cost for Profits and Overheads 25% 5.89

UNIT COST / m² 29.46

Prepared by : Raymond Kirk


()
HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

BLOCK WORK
Operator 22.47
Artisan/day 28.47
Labourer/day 22.47
Currency in Use GH¢

Amount GH¢

150 mm Hollow sandcrete blockwork in cement and


sand (1:4) mortar:

Material
A. MORTAR
Cement and sand mortar (1:4)
Assume a volumetric mix of 1m3 mortar,

I Cement 1m³
1m³ of Cement required would be 29 @ 16.50 = GH¢ 478.50

Unloading and stacking requires 29/120 man-day = 0.24 @ 22.47 = GH¢ 5.43

II Sand 4m3 4 @ 24.00 GH¢ 96.00

Therefore: Total material cost (5m3) 579.93

For shrinkage and waste, allow 33% 191.38

Total material cost / (5m3) 771.31

Therefore, material cost per meter cube = 757.18 / 5 = 154.26

III Labour - Mixing 1m3 requires one man-day 1 @ 22.47 22.47

Total Cost / m³ of Mortar 176.73

B. BLOCKS 100 m²

IV Using 150mm x 225 x 450 nominal size solid block

Area of 1 nominal size of block = 0.225 x 0.45 = 0.10125

No. of blocks required in 100m² area will be = 987.65

Add 10% waste = 98.77

Prepared by : Raymond Kirk


()
HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

BLOCK WORK
Operator 22.47
Artisan/day 28.47
Labourer/day 22.47
Currency in Use GH¢

Total no. of blocks required = 1,086.42 no.

Use, blocks 1087no. 1,087 @ 1.55 = 1,684.85

Let V = volume of mortar

V = [(0.225 X 0.45) - (0.2125 X 0.4375)] X 987.65 X 0.150

V = 0.0082813 x 148.148

V = 1.227m3

V Cost of 1.227m3 mortar 1.227 @ 176.73 = 216.84

Total Material Cost for Blocklaying 1,901.69

VI Labour

Blocklaying Output per gang day is 10 m²

Gang days required would be = 10.00


Say 10 gang days

Use 10 gang-days at bonus rate of 50.93 509.34

Total Cost Material and Labour 2,411.03

Then, Total Cost / m2 24.11

ADD - On - Cost for Profits and Overheads 25% 6.03

UNIT COST / m² 30.14

Prepared by : Raymond Kirk


()
HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

CLADDING / ROOF COVERING


Artisan/day 28.47
Labourer/day 22.47

ROOF COVERING GH ¢

Measured area 320 m²


Cost of sheet (size 2438 x1216mm) = GH¢ 21
Carpentry gang will fix 10m² of roof per hour

Soln
covering capacity 1.08 m²
2.24 m²

GH ¢ 2.42 m²

No of sheets required 320/2.42 132 sheets 300/2.24

Add 10% waste on sheet 13.2 sheets

Total sheets 145 sheets

Cost of 145 sheets @ Gh₵21.00 = 3,045.00

Nails (screws) with washers with utilisation of 5/m² 5 x 100


500 pieces =
Add 10 % waste 50 pieces
Total 550

But these are sold in packets of 100pcs = 550/100 = 5.5 packets


Say 6

Cost of 6 packets @ Gh¢ 18 = 108.00

Labour
unloading and fixing of 320m² at an out put of
70m²/gang day would require = 320/70 4.57 gang days

Assume 1 carpenter and 1 aprentise for 1 gang day 50.93 /gang day

4.57 gang days @ Gh₵50.93 = 232.77

Total cost = 3,385.77

Add 25% profit and overheads = 846.44

Total Cost / 300m² = 4,232.21

Cost of roofing /m² 7723.95/300 = 13.23

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

CLADDING / ROOF COVERING


Artisan/day 28.47
Labourer/day 22.47

Ridge cap

Measured length 24 m

Cost/m 7.50

Add 10% waste 0.75

Total cost 8.25

Labour

Assume 1 carpenter and 1 aprentise for 1 gang hour 50.93 /gang day

Carpentry gang will fix 10m² of roof per hour

But 2m length of ridge cap = 1m² of roof 24 m/ganghour


2 x10 =

Use 1 gang hour @ Gh₵50.94 50.93

Total cost 59.18

Add 25% profit and overheads 14.80

Total cost 73.98

cost/ m = 73.11 / 20 m/ganghour 3.08

cost/gangday = 3.66 x 8 24.66

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

PITCHED ROOF CARCASING


Artisan/day 28.47
Labourer/day 22.47

PLATE, 100MM X 50MM

MATERIALS LABOUR
1.TIMBER 3.CREOSOTE 1.UNLOADING, CUTTING, HOISTING AND FIXING
2.NAILS 4.BRUSH 2. APPLICATION OF CREOSOTE

TOTAL
MATERIALS PROJECT QTY. 85 m GH₵

1 TIMBER TYPE 50MM X 50MM PLATE

No. OF 3.6M PIECES REQ'D = 85M / 3.6M = 23.61

ADD 10% WASTE= 2.36


25.97

USE 22 PIECES @ GH₵ 5.27 115.94

2 NAILS

AT UTILAZATION OF 12KG / M3 OF TIMBER

WEIGHT OF NAILS USED = 0.10 X 0.05 X 70 X 12KG = 4.2 KG

USING 5KG@ GH₵ 2.10 10.50

3 CREOSOTE:

AREA/3.6M PIECE = ((3.6 X( 2 X 0.05 + 0.10)+(2 X 0.05 X 0.05)) = 1.09 m²

TOTAL AREA OF 22 PIECES = 25 X 1.09 = 22.94 m²

AT UTILISATION RATE OF 30M2 / 4.5LITRES

No. OF 4.5LITRES REQUIRED = 23.87M2 / 30M2 0.76

ADD WASTE 15% 0.11


0.88
USE 1QTY OF 4.5LITRES @ GH₵ 21.00 21.00

4 BRUSH: TOTAL AREA = 22.94 m²

AVERAGE LIVE COVERAGE / BRUSH = 120 m²

THEN, QTY REQ'D = 23.87M2 / 120M2 = 0.19 Nr.

USING 1Nr. @ GH¢ 2.10 2.10

Prepared By: Thomas Anwumanyi (20245849)and Edited by: Baah-Yamoah Godwill (6487211)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

PITCHED ROOF CARCASING


Artisan/day 28.47
Labourer/day 22.47

TOTAL COST OF MATERIALS GH₵ 149.54

LABOUR

5 UNLOADING, CUTTING, HOISTING AND FIXING

NET VOLUME OF TIMBER =25No X 0.10 X 0.05 X 3.6 = 0.45 M3

AT AN OUTPUT OF 1.4M3 / GANG-DAY

GANG DAYS REQUIERED WILL BE 0.396 / 1.4 = 0.32 GANG-DAYS

USE 1 GANG-DAYS @((GH¢ 28.47 X 2)+(GH¢ 22.47 X 2)) = 101.87

6 APPLICATION OF CREOSOTE:

MAN-DAYS REQUIRED FOR 15.95M2 SURFACES


AT AN OUTPUT OF 30M2 WILL BE = 15.95M2/30M2 = 0.53 MAN-DAYS

USING 1MAN-DAYS @ GH₵ 22.47 = 22.47

TOTAL COST OF LABOUR GH₵ 124.34

ADD

TOAL COST OF MATERIALS 149.54

TOTAL(MATERIAL+LABOUR) GH₵ 273.88

PRIME UNIT COST/M =GH₵ 598.00/73M 3.75

ADD

P&OH 25% 0.94


UNIT COST /M (SELLING PRICE) GH₵ 4.69

Prepared By: Thomas Anwumanyi (20245849)and Edited by: Baah-Yamoah Godwill (6487211)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

PITCHED ROOF CARCASING


Artisan/day 28.47
Labourer/day 22.47

50MM X 150MM PURLINS

MATERIALS LABOUR
1.TIMBER 1.UNLOADING, CUTTING, HOISTING AND FIXING
2.NAILS 2. APPLICATION OF CREOSOTE
3.CREOSOTE
4.BRUSH TOTAL

MATERIALS PROJECT QTY. 200 M GH₵

1 TIMBER TYPE 50MM X 150MM PLATE

No. OF 3.6M PIECES REQ'D ₌ 200M/3.6M = 55.55

ADD 15% WASTE= 8.33


63.88

USE 64 PIECES @ GH₵ 22.47 1,438.08

2 NAILS

AT UTILAZATION OF 12KG/M3 OF TIMBER

WEIGHT OF NAILS USED₌ 0.15 X 0.05 X 200 X 12KG ₌ 13.5

USING 14KG@ GH₵ 2.10 29.40

3 CREOSOTE:

AREA/3.6M PIECE₌((3.6 X( 2 X 0.15 + 0.05)+(2 X 0.15 X 0.05))₌ 1.46 M2

TOTAL AREA OF 60 PIECES₌ 64 X 1.46 ₌ 93.44 M2

AT UTILISATION RATE OF 30M2/4.5LITRES

No. OF 4.5LITRES REQUIRED₌ 89.06M2/30M2 3.11 (4.5L)

ADD WASTE 15% 0.47


3.58
USE 4 QTY OF 4.5LITRES @ GH₵ 22.47 89.88

SUB-TOTAL C/F GH₵ 1,557.36

Prepared By: Thomas Anwumanyi (20245849)and Edited by: Baah-Yamoah Godwill (6487211)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

PITCHED ROOF CARCASING


Artisan/day 28.47
Labourer/day 22.47

B/F GH₵ 1,557.36


4 BRUSH:

TOTAL AREA = 93.44 M2

AVERAGE LIVE COVERAGE/BRUSH = 120M2

THEN, QTY REQ'D= 87.6M2/120M2 0.78

USING 1No. @ GH₵ 2.10 2.10

TOTAL COST OF MATERIALS GH₵ 1,559.46

LABOUR

1 UNLOADING, CUTTING, HOISTING AND FIXING

NET VOLUME OF TIMBER =64No X 0.05 X 0.15 X 3.6 = 1.73 M3

AT AN OUTPUT OF 0.6M3/GANG-DAY FOR PITCH ROOFS

GANG DAYS REQUIERED WILL B1.73/0.6= 2.88 GANG-DAYS

USE 3 GANG-DAYS @((GH₵28.47 X 2 X3)+(22.47 X 2 X 3)) = 305.60

2 APPLICATION OF CREOSOTE:

MAN-DAYS REQUIRED FOR 89.06M2 SURFACES


AT AN OUTPUT OF 30M2 WILL BE = 89.06M2/30M2 = 2.97 MAN-DAYS

USING 3MAN-DAYS @ GH₵ 22.47 = 67.40

TOTAL COST OF LABOUR GH₵ 373.00

ADD

TOAL COST OF MATERIALS 1,559.46

TOTAL(MATERIAL+LABOUR) GH₵ 1,932.46

PRIME UNIT COST/M =GH₵ 1,566.00/190M 10.17

ADD

P & O. H 25% 2.54


UNIT COST /M (SELLING PRICE) GH₵ 12.71

Prepared By: Thomas Anwumanyi (20245849)and Edited by: Baah-Yamoah Godwill (6487211)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

Door frame 22 Nr

length of wood (900mm + 2100mm + 2100mm) x 21 110 m

Materials
i) Timber in Jambs

No of 4.2 pieces required = 107/4.2 26.19 pcs

Add 15% for waste 3.93 pcs

30.12 pcs

Cost /pieces ex-mills for (50 x 150mm) = Gh₵ 17.00


Transport, loading and unloading wroght
processing plant and site 0.70
planning of wood 0.30
cutting of rebate 1.00
Total cost/piece GHȻ 19.00

Cost of 30 piece @ 19 570.00

ii) Nails
Net volume of timber = 107 x0.05 x0.15m³ = 0.80 m³
weight of nails required = 0.80 x 12kg = 9.6 kg

Use 10kg @Gh₵2.0 20.00

iii) Wood Primer


Area to be primed = 2(0.05 +0.15) *107 = 27.50 m²

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

covering capacity of 30m²/4.5L units.

No. of units requi ired 27.5/30 0.92 unit

Add 15% waste 0.14 unit


1.06
Say 1.00 unit

But 1 of 4.5 L units @ GHȻ 16.00 16.00


Allow 5% for associated putty and glass paper work 0.80
16.80

Material cost 606.80

Labour cost

Unloading,fabrication and erection of 107 @ an output of 50m/gang day of 110 @ an out put of gang day
would require 3.6 /gang day

Use 4 gang days @ Gh₵50.44 110.00

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

surface priming of 42.8m² @ an output of 30m/gang day


would require 27.5/30 0.92
Say 1.00 Man-day

Use 1man-days @@ 22.47 22.47

Total Cost for Labour 132.47

Total cost (Material + Labour) 739.27

Add 25% profit and overheads 184.82

Total Cost for 110 m 924.08

Unit price 22 42.00

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

Window frame (W1) 7 Nr.

length of wood ( 900mm+900mm + 600mm+ 600mm + 600mm) x 6 21.6 m

Materials
i) Timber in Jambs

No of 4.2 pieces required = 21.6/4.2 5.14 pcs

Add 15% for waste 0.77 pcs


5.91
Say 6.00 pcs

Cost /pieces ex-mills for (50 x 150mm) = Gh₵ 17.00


Transport, loading and unloading wroght

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

processing plant and site 0.70


planning of wood 0.30
cutting of rebate 1.00
Total cost/piece GHȻ 19.00

Cost of 6 pieces s GHC 19 114.00

ii) Nails
Net volume of timber = 21.6 x0.05 x0.15m³ = 0.16 m³
weight of nails required = 0.16x 12kg = 1.944 kg

Use 2 kg @Gh₵2.0 4.00

iii) Wood Primer unit


Area to be primed = 2(0.05 +0.15) *21.6 = 8.91 m²
covering capacity of 30m²/4.5L units.

No. of units requireired =9 0.3 unit

Add 15% waste 0.045 unit


0.345

But 1 of 4.5 L units @ GHȻ 30.00 30.00


Allow 5% for associated putty and glass paper work 1.50
31.50

Material cost 149.50

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

Labour cost
Unloading,fabrication and erection of 12.60 @ an output of 50m/gang day
would require 0.432 /gang day

Use 0.43 gang days @ Gh₵ 50.44 22.00

surface priming of 8.64m² @ an output of 30m/gang day


would require 0.297 Man-day

Use 1 man-days @ Gh₵ 21.97 21.97

Total Cost for Labour 43.97

Total cost 193.47

Add 25% profit and overheads 48.37

Total Cost for 6 m 241.84

Unit price =219.82/6 34.55

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

Window frame (W2) 9Nr 10 Nr

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

length of wood (1800mm + 1800mm + 600mm+600mm+600mm + 600mm) x 9 54 m

Materials
i) Timber in Jambs

No of 4.2 pieces required = 54/4.2 12.85714286 pcs

Add 15% for waste 1.928571429 pcs

14.78571429 pcs

Cost /pieces ex-mills for (50 x 150mm) = Gh₵ 12.00 Gh C 17 Gh C 17


Transport, loading and unloading wroght
processing plant and site 0.60 0.7
planning of wood 0.30 0.3
cutting of rebate 3.20 1
Total cost/piece GHȻ 19

Cost of 54 piece s @ GhC 19 1026.00

ii) Nails
Net volume of timber = 54 x0.05 x0.15m³ = 0.41 m³
weight of nails required = 0.41x 12kg = 4.86 kg

Use 5 kg @Gh₵2.0 10.00

iii) Wood Primer


Area to be primed = 2(0.05 +0.15) *54 = 21.60 m²
covering capacity of 30m²/4.5L units.

No. of units required = 21.6/30 0.72 unit

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

Add 15% waste 0.108 unit


0.828 unit

But 1 of 4.5 L units @ GHȻ 30.00 30.00


Allow 5% for associated putty and glass paper work 1.50
31.50

Material cost 1067.50

Labour cost
Unloading,fabrication and erection of 54 @ an output of 50m/gang day
would require 1.08 /gang day

Use 1 gang days @ Gh₵50.44 50.44

surface priming of 21.6m² @ an output of 30m/gang day


would require 0.49 Man-day

Use 1 man-days @ 21.47 21.97

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

Total Cost for Labour 72.41

Total cost 1139.91

Add 25% profit and overheads 284.98

1424.89

Unit price 26.40

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

Window frame (W3 & W5) 2Nr 10 Nr

length of wood (1800mm+1800mm + 1200mm + 1200mm) x 2 12 m

Materials
i) Timber in Jambs

No of 4.2 pieces required = 12/4.2 2.857142857 pcs

Add 15% for waste 0.428571429 pcs

3.285714286 pcs

Cost /pieces ex-mills for (50 x 150mm) = Gh₵ 12.00 17


Transport, loading and unloading wroght
processing plant and site 0.60 0.7
planning of wood 0.30 0.3
cutting of rebate 3.20 1
Total cost/piece GHȻ 19

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

Cost of 4 pieces @ Gh₵16.10 GH C 19 76.00

ii) Nails
Net volume of timber = 12 x0.05 x0.15m³ = 0.09 m³
weight of nails required = 0.09 x 12kg = 1.08 kg

Use 1kg @Gh₵2.0 2.00

iii) Wood Primer


Area to be primed = 2(0.05 +0.15) *12 = 7.20 m²
covering capacity of 30m²/4.5L units.

No. of units required = 4.8/30 0.56 unit

Add 15% waste 0.084 unit


0.644 unit

But 1 of 4.5 L units @ GHȻ 30.00 30.00


Allow 5% for associated putty and glass paper work 1.50
31.50

Material cost 109.50

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

Labour cost

Unloading,fabrication and erection of 12 @ an output of 50m/gang day


would require 0.24 /gang day

Use 1 gang days @ Gh₵50.44 50.44

surface priming of 4.8m² @ an output of 30m/gang day


would require 0.24 Man-day

Use 1 man-days @ Gh₵21.97 21 97

Total cost 159.94

Add 25% profit and overheads 39.99

199.93

Unit price 99.96

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

Window frame (W4) 4Nr 5 Nr

length of wood (900mm+900mm + 1200mm + 1200mm) x 4 24 m

Materials
i) Timber in Jambs

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

No of 4.2 pieces required = 24/4.2 5.71 pcs

Add 15% for waste 0.86 pcs

6.57 pcs

Cost /pieces ex-mills for (50 x 150mm) = Gh₵ 12.00 17


Transport, loading and unloading wroght
processing plant and site 0.60
planning of wood 0.30
cutting of rebate 3.20
Total cost/piece 19.00 GHȻ 19

Cost of 7 pieces @ Gh₵16.10 133.00

ii) Nails
Net volume of timber = 24 x0.05 x0.15m³ = 0.18 m³
weight of nails required = 0.18 x 12kg = 2.16 kg

Use 2kg @Gh₵2.0 4.00

iii) Wood Primer


Area to be primed = 2(0.05 +0.15) *24 = 9.60 m²
covering capacity of 30m²/4.5L units.

No. of units required = 9.6/30 0.32 unit

Add 15% waste 0.048 unit


0.368 unit

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

But 1 of 4.5 L units @ GHȻ 30.00 30.00


Allow 5% for associated putty and glass paper work 1.50
31.50

Material cost 168.50

Labour cost

Unloading,fabrication and erection of 24 @ an output of 50m/gang day


would require 0.48 /gang day

Use 0.48 gang days @ Gh₵50.44 24.45

surface priming of 9.6m² @ an output of 30m/gang day


would require 0.32 Man-day

Use 1 man-days @ Gh₵21.97 21.97

Total cost 214.92

Add 25% profit and overheads 53.73

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

268.65

Unit price =242.86/4 67.16

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

Window frame (W4A) 6Nr 7 Nr

length of wood (1400mm +1400mm+ 1000mm + 1000mm) x 6 28.8 m

Materials
i) Timber in Jambs

No of 4.2 pieces required = 28.8/4.2 6.86 pcs

Add 15% for waste 1.03 pcs

7.89 pcs

Cost /pieces ex-mills for (50 x 150mm) = Gh₵ 12.00 17


Transport, loading and unloading wroght
processing plant and site 0.60
planning of wood 0.30
cutting of rebate 3.20
Total cost/piece 19.00 GHȻ 19

Cost of 8 pieces GHc 19 152.00

ii) Nails
Net volume of timber = 28.8 x0.05 x0.15m³ = 0.22 m³

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

weight of nails required = 0.22 x 12kg = 2.592 kg

Use 3kg @Gh₵2.0 6.00

iii) Wood Primer


Area to be primed = 2(0.05 +0.15) *28.8 = 11.52 m²
covering capacity of 30m²/4.5L units.

No. of units required = 11.52/30 0.384 unit

Add 15% waste 0.0576 unit


0.4416 unit

But 1 of 4.5 L units @ GHȻ 30.00 30.00


Allow 5% for associated putty and glass paper work 1.50
31.50

Material cost 189.50

Labour cost

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

Unloading,fabrication and erection of 28.8 @ an output of 50m/gang day


would require 0.576 /gang day

Use 0.58 gang days @ Gh₵50.44 29.34

surface priming of 11.52m² @ an output of 30m/gang day


would require 0.384 Man-day

Use 1 man-days @ Gh₵21.97 21.97

Total cost 240.81

Add 25% profit and overheads 60.20

301.01

Unit price 50.17

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

Window frame (W6) 5Nr 8 Nr

length of wood (2700mm +2700mm+ 200mm + 200mm) x 5 29 m

Materials
i) Timber in Jambs

No of 4.2 pieces required = 29/4.2 8.79 pcs

Add 15% for waste 1.32 pcs

10.11 pcs

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

Cost /pieces ex-mills for (50 x 150mm) = Gh₵ 12.00 17


Transport, loading and unloading wroght
processing plant and site 0.60
planning of wood 0.30
cutting of rebate 3.20
Total cost/piece 19.00 GHȻ 19

Cost of 10 piece 19 190.00

ii) Nails
Net volume of timber = 29 x0.05 x0.15m³ = 0.22 m³
weight of nails required = 0.22 x 12kg = 2.61 kg

Use 3kg @Gh₵2.0 6.00

iii) Wood Primer


Area to be primed = 2(0.05 +0.15) *29 = 11.60 m²
covering capacity of 30m²/4.5L units.

No. of units required = 11.6/30 0.386666667 unit

Add 15% waste 0.058 unit


0.444666667 unit

But 1 of 4.5 L units @ GHȻ 30.00 30.00


Allow 5% for associated putty and glass paper work 1.50
31.50

Material cost 227.50

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

Labour cost

Unloading,fabrication and erection of 10.5 @ an output of 50m/gang day


would require 0.58 /gang day

Use 0.58 gang days @ Gh₵50.44 29.54

surface priming of 11.6m² @ an output of 30m/gang day


would require 0.39 Man-day

Use 1 man-days @ Gh₵21.97 21.97

Total cost 279.01

Add 25% profit and overheads 69.75

348.76

Unit price 69.75

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

Window frame (W7) 1Nr 2 Nr

length of wood (900mm +900mm+ 2000mm + 2000mm) x 1 5.8 m

Materials
i) Timber in Jambs

No of 4.2 pieces required = 5.8/4.2 1.18 pcs

Add 15% for waste 0.18 pcs

1.36 pcs

Cost /pieces ex-mills for (50 x 150mm) = Gh₵ 12.00 17


Transport, loading and unloading wroght
processing plant and site 0.60
planning of wood 0.30
cutting of rebate 3.20
Total cost/piece 19.00 GHȻ 19

Cost of 3 pieces 19 57.00

ii) Nails
Net volume of timber = 5.8 x0.05 x0.15m³ = 0.04 m³
weight of nails required = 0.04 x 12kg = 0.522 kg

Use 1kg @Gh₵2.0 2.00

iii) Wood Primer


Area to be primed = 2(0.05 +0.15) *5.8 = 2.32 m²

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

covering capacity of 30m²/4.5L units.

No. of units required = 2.32/30 0.08 unit

Add 15% waste 0.01 unit


0.09 unit

But 0.1 of 4.5 L units @ GHȻ 30.00 3.00


Allow 5% for associated putty and glass paper work 0.15
3.15

Material cost 65.30

Labour cost

Unloading,fabrication and erection of 5.8 @ an output of 50m/gang day


would require 0.116 /gang day

Use 0.04 gang days @ Gh₵50.44 5.91

surface priming of 2.32m² @ an output of 30m/gang day

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

DOORS & WINDOWS

Artisan/day 28.47
Labourer/day 22.47
Gang day 50.93

would require 0.077333333 Man-day

Use 0.08 man-days @ Gh₵25.00 1.93

Total cost 73.14

Add 25% profit and overheads 18.29

91.43

Unit price 91.43

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

D236*54
D236/54

Prepared By: Dorcas Durowaa Wiredu (6489411) and Charlote Korsah (6491511)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

FURNITURE / EQUIPMENT

Sanitary Appliances / Fittings Artisan/day 28.47


Labourer/day 22.47

1.0 White glazed vitreous china wash down W.C complete. Twyford Classic 8 no.

Materials:

1 Unit of specified water closet complete with cistern is GH¢ 220.00

Therefore Required Units would be 8 @ 220.00 = 1,760.00

Add for damage 15% 264.00

Add for plugs and clips 2% 35.20

Total Material Cost 2,059.20

Labour:

Unloading, preparing and fixing 6 W.C's at an output of 4 /gang day

would require 8/4 2


Say 2 gang days

Therefore use 2 Gang days 2 @ 50.44 = 100.88

Add for plugging 5% 5.04

Total Labour Cost 105.92

Total Cost (Material and Labour) 2,165.12

Cost per 1 Unit 270.64

Add - On - Cost for P/O 25% 67.66

UNIT COST 338.30

Prepared By:Asare Nana Kwasi Gyamera (6487211) and Baah-Sekyere Emmanuel (6487111)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

FURNITURE / EQUIPMENT

Sanitary Appliances / Fittings Artisan/day 28.47


Labourer/day 22.47

1.1 White pedestal wash basin in vitreous china. Twyford Classic 6 no.

Materials:

1 Unit of specified water closet complete with cistern is GH¢ 180.00

Therefore Required Units would be 6 @ 180.00 = 1,080.00

Add for damage & storage 15% 162.00

Add for jointing couplings 10% 108.00

Add for painting on pairs of metal brackets 2% 21.60

Add for bedding brackets in blockwall 6% 64.80

Total Material Cost 1,436.40

Labour:

Unloading, preparing and fixing 6 W.C's at an output of 6 /gang day

would require 5 / 6 = 1
Say 1 gang days

Therefore use 2 Gang days 1 @ 50.44 = 50.44

Add for plugging brackets in blockwall 10% 5.04

Total Labour Cost 55.48

Total Cost (Material and Labour) 1,491.88

Cost per 1 Unit 248.65

Add - On - Cost for P/O 25% 62.16

Prepared By:Asare Nana Kwasi Gyamera (6487211) and Baah-Sekyere Emmanuel (6487111)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

FURNITURE / EQUIPMENT

Sanitary Appliances / Fittings Artisan/day 28.47


Labourer/day 22.47

UNIT COST 310.81

1.2 Double bowl double drainer stainless steel kitchen sink 2 no.

Materials:

1 Unit of specified water closet complete with cistern is GH¢ 180.00

Therefore Required Units would be 2 @ 180.00 = 360.00

Add for Heavy duty double tap 5% @ 9.00 0.45

Add for damage 5% 18.02

Total Material Cost 378.47

Labour:

Unloading, preparing and fixing 6 W.C's at an output of 6 /gang day

would require 2/6 0.333333


Say 1 gang days

Therefore use 2 Gang days 1 @ 50.44 = 50.44

Add for plugging brackets in blockwall 10% 5.04

Total Labour Cost 55.48

Total Cost (Material and Labour) 433.96

Cost per 1 Unit 216.98

Add - On - Cost for P/O 25% 54.24

Prepared By:Asare Nana Kwasi Gyamera (6487211) and Baah-Sekyere Emmanuel (6487111)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

FURNITURE / EQUIPMENT

Sanitary Appliances / Fittings Artisan/day 28.47


Labourer/day 22.47

UNIT COST 271.22

Prepared By:Asare Nana Kwasi Gyamera (6487211) and Baah-Sekyere Emmanuel (6487111)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

PIPED SUPPLY SYSTEM

Pipelines Artisan/day 28.47


Labourer/day 22.47

1.0 50mm Ø PVC Pipe as specified, laid in chase. 7 m

Materials:

PVC pipes 50mm Ø are sold in 6m lengths locally GH¢ 11.50

No. of lengths Required would be 7 / 6 = 1.17


Add for damage 15% 0.18
Total No. 1.34
Say 2 @ 11.50 = 23.00

Jointing compound for 10m at utilization of 0.025kg/m


would require 10 x 0.025kg = 0.25
Add for waste 10% 0.025
0.275

But it is sold in 0.25kg minimum containers


Therefore Buy 2 Containers 2 @ 5.50 = 11.00

Total Material Cost 34.00

Labour:

Making chases at an output / man day of 10 m


would require 10/10 = 0.7
Say 1 man day
Therefore use 1 man days 1 @ 22.47 = 22.47

Pipework in chase for 10m at an output of 15 m/gang day


would require 10/15 = 0.466667
Say 0 gang day
Therefore use 1 gang day 0 @ 50.44 = -

Total Labour Cost 22.47

Total Cost (Material and Labour) 56.47

Cost per 1 Unit 8.07

Add - On - Cost for P/O 25% 2.02

Prepared By:Asare Nana Kwasi Gyamera (6487211) and Baah-Sekyere Emmanuel (6487111)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

PIPED SUPPLY SYSTEM

Pipelines Artisan/day 28.47


Labourer/day 22.47

UNIT COST 10.08

1.1 20mm Ø PVC Pipe as specified, straight overflow pipe 10 m

Materials:

PVC pipes 20mm Ø are sold in 6m lengths locally GH¢ 4.95

No. of lengths Required would be 10 / 6 = 1.67


Add for damage 15% 0.25
Total No. 1.92
Say 2 @ 4.95 = 9.90

Jointing compound for 10m at utilization of 0.025kg/m


would require 10 x 0.025kg = 0.25
Add for waste 10% 0.025
0.275

But it is sold in 0.25kg minimum containers


Therefore Buy 2 Containers 2 @ 6.00 = 12.00

Total Material Cost 21.90

Labour:

Pipework for 10m at an output of 25 m/gang day


would require 10/25 = 0.4
Say 0.4 gang day
Therefore use 1 gang day 0.4 @ 50.44 = 20.18

Total Labour Cost 20.18

Total Cost (Material and Labour) 42.08

Cost per 1 Unit 4.21

Add - On - Cost for P/O 25% 1.05

UNIT COST 5.26

Prepared By:Asare Nana Kwasi Gyamera (6487211) and Baah-Sekyere Emmanuel (6487111)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

PIPED SUPPLY SYSTEM

Pipelines Artisan/day 28.47


Labourer/day 22.47

1.2 12mm Ø PVC Pipe as specified, laid in chase. 7 m

Materials:

PVC pipes 12mm Ø are sold in 6m lengths locally GH¢ 3.60

No. of lengths Required would be 10 / 6 = 1.17


Add for damage 15% 0.18
Total No. 1.34
Say 1 @ 3.60 = 3.60

Jointing compound for 10m at utilization of 0.025kg/m


would require 10 x 0.025kg = 0.25
Add for waste 10% 0.025
0.275

But it is sold in 0.25kg minimum containers


Therefore Buy 2 Containers 2 @ 6.00 = 12.00

Total Material Cost 15.60

Labour:

Making chases at an output / man day of 7 m


would require 7/10 = 0.7
Say 1 man day
Therefore use 1 man days 1 @ 22.47 = 22.47

Pipework in chase for 10m at an output of 30 m/gang day


would require 10/30 = 0.233333
Say 0.23 gang day
Therefore use 1 gang day 1 @ 50.44 = 50.44

Total Labour Cost 72.91

Total Cost (Material and Labour) 88.51

Cost per 1 Unit 12.64

Prepared By:Asare Nana Kwasi Gyamera (6487211) and Baah-Sekyere Emmanuel (6487111)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

PIPED SUPPLY SYSTEM

Pipelines Artisan/day 28.47


Labourer/day 22.47

Add - On - Cost for P/O 25% 3.16

UNIT COST 15.80

1.3 32mm Ø PVC Pipe as specified, laid in chase. 22 m

Materials:

PVC pipes 32mm Ø are sold in 6m lengths locally GH¢ 8.00

No. of lengths Required would be 22 / 6 = 3.67


Add for damage 15% 0.55
Total No. 4.22
Say 4 @ 8.00 = 32.00

Jointing compound for 10m at utilization of 0.025kg/m


would require 10 x 0.025kg = 0.25
Add for waste 10% 0.025
0.275

But it is sold in 0.25kg minimum containers


Therefore Buy 2 Containers 2 @ 6.00 = 12.00

Total Material Cost 44.00

Labour:

Making chases at an output / man day of 10 m


would require 22/10 = 2.2
Say 2 man day
Therefore use 1 man days 2 @ 22.47 = 44.93

Pipework in chase for 10m at an output of 20 m/gang day


would require 10/30 = 1.1
Say 1.1 gang day
Therefore use 1 gang day 1.1 @ 50.44 = 55.48

Total Labour Cost 100.42

Total Cost (Material and Labour) 144.42

Prepared By:Asare Nana Kwasi Gyamera (6487211) and Baah-Sekyere Emmanuel (6487111)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

PIPED SUPPLY SYSTEM

Pipelines Artisan/day 28.47


Labourer/day 22.47

Cost per 1 Unit 6.56

Add - On - Cost for P/O 25% 1.64

UNIT COST 8.21

Prepared By:Asare Nana Kwasi Gyamera (6487211) and Baah-Sekyere Emmanuel (6487111)
HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

Supply Installation Profit


Ovhds
&
Basic
ITEM DESCRIPTION QTY UNIT
Price 15% of 20% of 25%
Basic Baic

VENTILATION / AIR CONDITIONING SYSTEMS

General Ventilation

A Sweep ceiling fan (crompton type) 1400mm


complete with ceiling rose and regulator. 8 Nr. 58 8.7 11.60 19.58

Prepared By: Ankukumah Richard Kwame (6489611)and edited by: Arthur Kofi Gordon (20246136)
HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

Supply Installation Profit


Ovhds
&
Basic
ITEM DESCRIPTION QTY UNIT
Price 15% of 20% of 25%
Basic Baic

ELECTRICAL SUPPLY / POWER / LIGHTING SYSTEMS

Conduit and cable trunking

A Conduit, straight,20mm Diameter black


enamelled heavy gauge (measured seperately)
fixed in chases. 45 m 1.5 0.225 0.30 0.51

B Ditto, 20mm Diameter ditto in floor screeds. 80 m 1.5 0.225 0.30 0.51

C Ditto,20mm Diameter running in ceiling 24 m 1.5 0.225 0.30 0.51

HV /LV Cables and Wiring

D Cables, 4mm2 single core pvc insulated


colour coded drawn into conduit. 67 m 1.2 0.18 0.24 0.41

E Ditto, 2.5mm2 - do - 184 m 0.8 0.12 0.16 0.27

F Ditto, 1.5mm2 - do - 130 m 0.6 0.09 0.12 0.20

General Lv Power

G Cable and conduit in final circuits, cable and


conduit in ring main circuit, concealed
installation consisting of 4mm2 pvc
insulating colour coded cable drawn into
black enamelled heavy gauge (measured
seperately) conduit, embedded in screeded
floors, in circuit number W1 comprising
one switch socket outlets. 3 Nr. 700 105 140.00 236.25

H Ditto, consisting of 2.5mm2 pvc insulating


colour coded cable, drawn into black
enamelled heavy gauge(measured
seperately) conduit,embedded in screeded
floors, in circuit number S1 comprising
eight switch sockets outlets. 3 Nr. 178 26.7 35.60 60.08

J Ditto, S2 comprising two - do - 3 Nr. 182 27.3 36.40 61.43

Prepared By: Ankukumah Richard Kwame (6489611)and edited by: Arthur Kofi Gordon (20246136)
HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

Supply Installation Profit


Ovhds
&
Basic
ITEM DESCRIPTION QTY UNIT
Price 15% of 20% of 25%
Basic Baic

General Lv Lighting

K Cable and conduit in final circuits, cable and


conduit in lighting circuit, concealed
installation consisting of 1.5mm2 pvc
insulating colour coded cable drawn into
black enamelled heavy gauge (measured
seperately) conduit, concealed in masonry,
in circuit number L1 comprising seven lighting
points and two one way two gang switch. 2 Nr. 878 131.7 175.60 296.33

General Lv Lighting ( Cont'd )

A Cable and conduit in final circuits, cable and


conduit in lighting circuit, concealed
installation consisting of 1.5mm2 pvc
insulating colour coded cable drawn into
black enamelled heavy gauge (measured
seperately) conduit, concealed in masonry,
in circuit number L1 comprising seven lighting
points and two one way three gang switch. 3 Nr. 850 127.5 170.00 286.88

B Ditto, circuit number L2 comprising seven


lighting points and three one way one
gang switch. 3 Nr. 850 127.5 170.00 286.88

Consumer unit

C Include the provisional sum of GH¢……….


for works by Electricity Authority, bringing
mains cable to building, installating meter
and connecting to the switchgear. Item

Lv Switchgear and distribution board

D Distribution board, 6 way surface type metal


clad miniature circuit breaker, consumer
control unit with 100 Ampere main switch,

Prepared By: Ankukumah Richard Kwame (6489611)and edited by: Arthur Kofi Gordon (20246136)
HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

Supply Installation Profit


Ovhds
&
Basic
ITEM DESCRIPTION QTY UNIT
Price 15% of 20% of 25%
Basic Baic
manufacturer's reference km 100, two
5 ampere, and two 30 ampere m.c.b.s,
plugged and screwed to masonry. 2 Nr 610 91.5 122.00 205.88

Luminaries and Lamps

E Luminaries, flourescent fitting, 1200mm


long, 1 x 36w single tube and diffuser,
including connection block, 50mm diameter
loop in conduit box and one support bracket
comprising 600mm length of 20mm
diameter conduit and 2 number 50mm loop
in boxes, one box screwed to timber. 14 Nr. 42 6.3 8.40 14.18

F Luminaries, flourescent fitting, 1200mm


long, 1 x 36w single tube but weather proof,
including connection block, 50mm diameter
loop in conduit box and one support bracket
comprising 600mm length of 20mm
diameter conduit and 2 number 50mm loop
in boxes, one box screwed to timber. 12 Nr. 65 9.75 13.00 21.94

G Ditto, Globe fitting comprising ivory plastic


ceiling rose and connector block and brass
bayonet connection lamp holder with shade
ring and 3 - core 0.75mm2 pvc insulated
and protected flexible cable, drop not
exceeding 1.00m including 50mm diameter
loop in conduit box. 6 Nr. 40 6 8.00 13.50

Luminaries and Lamps ( Cont'd )

A Lamps, flourescent tube,1200mm long, 36w


warm white'. 14 Nr. 24 3.6 4.80 8.10

B Ditto, 20w Energy bulb as specified by ECG 5 Nr. 4 0.6 0.80 1.35

C Accessories, socket outlet 15 ampere 3 pin


shuttered flush ivory plastic pattern single
switched and steel knockout box, plugged

Prepared By: Ankukumah Richard Kwame (6489611)and edited by: Arthur Kofi Gordon (20246136)
HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

Supply Installation Profit


Ovhds
&
Basic
ITEM DESCRIPTION QTY UNIT
Price 15% of 20% of 25%
Basic Baic
and screwed to masonry. 4 Nr. 18 2.7 3.60 6.08
D
Ditto, 13 ampere - do - 15 Nr. 12 1.8 2.40 4.05

Ditto, 13 ampere but double - do - 5 Nr. 15 2.25 3.00 5.06


E
Ditto, lighting switch two gang two way
5 ampere single pole silent action, ivory
plastic plate and steel knockout box - do - 5 Nr. 8 1.2 1.60 2.70

F Ditto, one gang three way - do - 5 Nr. 15 2.25 3.00 5.06

G Ditto, one gang one way - do - 8 Nr. 10 1.5 2.00 3.38

H Marking position of holes mortices and


chases in the structure. Item

A Identification, lables, 125 x 100mm, white


plastic, marked 'DIS BOARD 1/12' with list
of each circuit beneath, plugged and
screwed to masonry. 2 Nr. 55 8.25 11.00 18.56

B Testing and commissioning as specified for


general lighting and power installation. Item

C Preparing drawings, 4 copies of 'as fitted'


prints showing circuits and conduit runs and
hand to maintenance engineer. Item

P30:General Builder's Work

D Cutting or forming holes, mortices, sinkings


and chases for electrical installations
concealed conduit 20mm diameter
luminaire points and make good. 15 Nr. 17 2.55 3.40 5.74

E Ditto, socket outlet point and make good. 15 Nr. 18 2.7 3.60 6.08

Prepared By: Ankukumah Richard Kwame (6489611)and edited by: Arthur Kofi Gordon (20246136)
HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

Supply Installation Profit


Ovhds
&
Basic
ITEM DESCRIPTION QTY UNIT
Price 15% of 20% of 25%
Basic Baic

Prepared By: Ankukumah Richard Kwame (6489611)and edited by: Arthur Kofi Gordon (20246136)
HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

RATE
(GHC)

97.88

Prepared By: Ankukumah Richard Kwame (6489611)and edited by: Arthur Kofi Gordon (20246136)
HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

RATE
(GHC)

2.53

2.53

2.53

2.03

1.35

1.01

1,181.25

300.38

307.13

Prepared By: Ankukumah Richard Kwame (6489611)and edited by: Arthur Kofi Gordon (20246136)
HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

RATE
(GHC)

1,481.63

1,434.38

1,434.38

2,500.00

Prepared By: Ankukumah Richard Kwame (6489611)and edited by: Arthur Kofi Gordon (20246136)
HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

RATE
(GHC)

1,029.38

70.88

109.69

67.50

40.50

6.75

Prepared By: Ankukumah Richard Kwame (6489611)and edited by: Arthur Kofi Gordon (20246136)
HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

RATE
(GHC)

30.38

20.25

25.31

13.50

25.31

16.88

300.00

92.81

100

300

28.69

30.38

Prepared By: Ankukumah Richard Kwame (6489611)and edited by: Arthur Kofi Gordon (20246136)
HOPE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

RATE
(GHC)

Prepared By: Ankukumah Richard Kwame (6489611)and edited by: Arthur Kofi Gordon (20246136)
GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

FINISHINGS
Plastering / Rendering Operator 22.47
Artisan/day 28.47
Gang = (2 Mason + 1 Labourer ) 79.40 Labourer/day 22.47
Currency in Use GH¢

A Mortar (1:4) - Machine Mixing assume 1m³

Materials
Cement and sand mortar (1:4), Assume a volumetric mix of 1m3 mortar,

Cement 1m³
1m³ of Cement required would be 29 @ 16.50 = GH¢ 478.50
Unloading and stacking requires 29/120 man-day = 0.24 @ 22.47 = GH¢ 5.43

Sand 4m3 4 @ 24.00 GH¢ 96.00

Therefore: Total material cost (5m3) 579.93

For shrinkage and waste, allow 33% 191.38

Total material cost / (5m3) 771.31

Therefore, material cost per meter cube = 771.31 / 5 = 154.26

Labour - Mixing 1m3 requires one man-day 1 @ 22.47 22.47

Total Cost / m³ of Mortar 176.73

13mm rendering (1 : 4) to Walls assume ### m2

Material

Mortar as mixed (1987m² x 0.013m) 25.83 m3


Add irregularity of surface, compression 60% 15.50
41.33 @ 176.73 37.11

Labour

1Mason+1Lab Output/ gang day 30 m²

No of gang days required 66.23


Say 66.00 g dys @ 79.40 ###

Total Cost (matl + Labour) ###

Unit Cost/m2 2.66

ADD: ON - COST 25% = 0.66

Prepared By: Baah-Yamoah Godwill (6487211)


GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

FINISHINGS
Plastering / Rendering Operator 22.47
Artisan/day 28.47
Gang = (2 Mason + 1 Labourer ) 79.40 Labourer/day 22.47
Currency in Use GH¢

UNIT RATE = 3.32

12mm rendering (1 : 4) to Walls 200 m2

Material

Mortar as mixed (10m² x 0.012m) 2.40 m3


Add irregularity of surface, compression 60% 1.44
3.84 @ 176.73 678.63

Labour

1 Mason+1Lab Output/ gang day 30 m²


No of gang days required 6.67
Say 1.00 g dys @ 79.40 79.40

Total Cost (matl + Labour) 758.04

Unit Cost/m2 3.79

ADD: ON - COST 25% = 0.95

UNIT RATE = 4.74

12mm rendering (1 : 4) to Soffits 220 m2

Material

Mortar as mixed (10m² x 0.012m) 2.64 m3


Add irregularity of surface, compression 60% 1.58
4.22 @ 176.73 746.50

Labour

2Mason+1Lab Output/ gang day 20 m²


No of gang days required 11.00
Say 11.00 g dys @ 79.40 873.42

Total Cost (matl + Labour) ###

Unit Cost/m2 7.36

Prepared By: Baah-Yamoah Godwill (6487211)


GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

FINISHINGS
Plastering / Rendering Operator 22.47
Artisan/day 28.47
Gang = (2 Mason + 1 Labourer ) 79.40 Labourer/day 22.47
Currency in Use GH¢

ADD: ON - COST 25% = 1.84

UNIT RATE = 9.20

Prepared By: Baah-Yamoah Godwill (6487211)


GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

FINISHINGS
Screedring / Roughcasting Coatings Operator
Artisan/day
Gang = (2 Mason + 1 Labourer ) 79.40 Labourer/day
Currency in Use GH¢

A Mortar (1:4) - Machine Mixing 1m³

Materials
Cement and sand mortar (1:4), Assume a volumetric mix of 1m3 mortar,

Cement 1m³
1m³ of Cement required would be 29 @ 16.50 = GH¢
Unloading and stacking requires 29/120 man-day 0.24 @ 22.47 = GH¢

Sand 4m3 4 @ 24.00 GH¢

Therefore: Total material cost (5m3)

For shrinkage and waste, allow 33%

Total material cost / (5m3)

Therefore, material cost per meter cube = 771.31 / 5 =

Labour - Mixing 1m3 requires one man-day 1 @ 22.47

Total Cost / m³ of Mortar

40mm Screeding (1 : 4) to Floors assume 450 m2

Material

Mortar as mixed (450m² x 0.040m) 18.00 m3


Add irregularity of surface, compression 60% 10.80
28.80 @ 176.73

Labour

2Mason+1Lab Output/ gang day 20 m²

No of gang days required 22.50


Say 23.00 g dys @ 79.40

Total Cost (matl + Labour)

Unit Cost/m2

ADD: ON - COST 25% =

Prepared By: Baah-Yamoah Godwill (6487211)


GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

FINISHINGS
Screedring / Roughcasting Coatings Operator
Artisan/day
Gang = (2 Mason + 1 Labourer ) 79.40 Labourer/day
Currency in Use GH¢

UNIT RATE =

12mm Screeding (1 : 4) to Floors 20 m2

Material

Mortar as mixed (20m² x 0.012m) 0.24 m3


Add irregularity of surface, compression 60% 0.14
0.38 @ 176.73

Labour

2Mason+1Lab Output/ gang day 35 m²


No of gang days required 0.57
Say 1.00 g dys @ 79.40

Total Cost (matl + Labour)

Unit Cost/m2

ADD: ON - COST 25% =

UNIT RATE =

Prepared By: Baah-Yamoah Godwill (6487211)


GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

FINISHINGS
22.47 Wall & Floor Tiling Operator
28.47 Artisan/day
22.47 Gang = (1 Tiler + 1 Labourer ) 50.93 Labourer/day
Currency in Use GH¢

Wall tiling 100 m2

Basic Prices
Tiles (300 x 200 x 6mm) spain m2 1 22.00
Tile cement ( coverage 5m2) Bag 1 7.00
478.50 White cement (coverage 10m2) Bag 1 26.00
5.43
Rate Analysis
96.00 Tiles 22 m2 22.00 484

579.93 Adhesive (Tile Cement + Ord. Cement) 4.50 Bag 23.50 106
Add: White cement (Grout) 10.00 Bag 26.00 260
191.38 850

771.31 Add: Waste, Transport damages, etc 15% 127


977
154.26
Add: T & T 5% 49
22.47
Total Material Cost
176.73

Labour

Preparation and tiling 1m² require = 1 = 0.167 gang days


6
Preparation and pointing 1m² require = 1 = 0.025
40
For both operations time require / m² = 0.192

5,089.73 Hence 22m² would require = 22x 0.192 = 4.22 gang days

Labour Cost of 30 gang days would be 4 x 50.93

Total Cost
1,826.24
Unit Cost
6,915.97
Add: Profit & Overheads 25%
15.37
Unit Rate m2 GH¢
3.84

Prepared By: Baah-Yamoah Godwill (6487211)


GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

FINISHINGS
22.47 Wall & Floor Tiling Operator
28.47 Artisan/day
22.47 Gang = (1 Tiler + 1 Labourer ) 50.93 Labourer/day
Currency in Use GH¢

19.21

Floor tiling 450 m2

Basic Prices
Tiles (400 x 400 x 10mm) from spain m2 1 26.00
Tile Adhesive ( coverage 5m2) Bag 1 7.00
White cement (coverage 10m2) Bag 1 23.00
67.86
Rate Analysis

Tiles 450 m2 26.00 11,700

Adhesive (Tile Cement + Ord. Cement) 90.00 Bag 7.00 630


79.40 Add: White cement (Grout) 45.00 Bag 23.00 1,035
13,365
147.26
Add: Waste, Transport damages, etc 15% 2,005
7.36 15,370

1.84 Add: T & T 5% 768

9.20 Total Material Cost

Labour

Preparation and tiling 1m² require = 1 = 0.167 gang days


6
Preparation and pointing 1m² require = 1 = 0.025
40
For both operations time require / m² = 0.192

Hence 450 m² would require = 450 0.192 = 86.25 gang days

Labour Cost of 30 gang days would be 86 x 50.93

Total Cost

Unit Cost

Add: Profit & Overheads 25%

Prepared By: Baah-Yamoah Godwill (6487211)


GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

FINISHINGS
22.47 Wall & Floor Tiling Operator
28.47 Artisan/day
22.47 Gang = (1 Tiler + 1 Labourer ) 50.93 Labourer/day
Currency in Use GH¢

Unit Rate m2 GH¢

Prepared By: Baah-Yamoah Godwill (6487211)


GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

22.47
28.47
22.47

1,026.07

203.73

1,229.81

1,229.81

12.30

3.07

15.37

Prepared By: Baah-Yamoah Godwill (6487211)


GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

22.47
28.47
22.47

16,138.24

4,379.98

20,518.22

20,518.22

45.60

11.40

Prepared By: Baah-Yamoah Godwill (6487211)


GRACE GROUP QSCE3 KNUST/IDL
UNIT RATES BUILD-UP

22.47
28.47
22.47

57.00

Prepared By: Baah-Yamoah Godwill (6487211)


PAINTING
Painting / Clear Finishes Operator 22.47
Artisan/day 28.47
Gang = (2 Painters + 1 Labourer ) Labourer/day 22.47
= 79.41 Currency in Use GH¢

A Prepare and apply 3 coats of emulsion paint on rendered walls 1987 m2

4.5 litres gallon of emulsion paint has a utilization/coverage of 40m²


Therefore 18 litres paint would give a utilization of = (40m² / 4.5litres) x 18litres = 160m² / coat

18litre paint 105.00 Coverage 160 m2/coat


Brush 3.00 Coverage 300 m2/coat

Materials

Qty reqd (3 x 1987) / 160 = 37.25625 pails


Add waste 15% 5.59
42.84
say 43.00 @ 105.00 4,515.00

Add: Brushes
Qty req'd (3 x 1987) / 300 = 19.87 @ 3.00 59.61

4574.61

Sand paper, T&T etc 15% 686.1915

Total for Material 5260.8015

Labour
Output for preparation and painting 3 coats per gang day is
1Lab+2Painters = 60 m2/gdy/ct

No. of gang days required (3 x 1987) / 60 = 99.35


say 99.00 @ 79.41 7861.1445

Total Cost (Material & Labour) for 100m² 13,121.95

Total Cost for m² 6.60

ADD: ON - COST 25% 1.65

UNIT RATE GH¢ 8.25


A ICI Oil Paint 124 m2

3.6litre gallon 22.00


Coverage 29 m2/coat
Materials

Qty reqd 4.28 pails


Add waste 15% 0.64
4.92
say 5.00 pails 36.00 180

Add: Brushes,Sand 20% 36.00


paper, T&T etc
216.00

Labour
Output
1Lab+2Painters 50 m2/gdy/ct

No. of days required 2.48


say 2.00 52.02 104.04

Plant

Total Cost 320.04

Unit Cost/m2 (total Cost / Qty) 2.58

ADD: ON - COST 25% 0.65

UNIT RATE GH¢ 3.23


USD 2.34

A ICI Weathershield paint 227 m2

18litre pail 64.70


Coverage 160 m2/coat
Materials

Qty reqd 4.25625 pails


Add waste 15% 0.64
4.89
say 5.00 pails 64.70 323.5

Add: Brushes,Sand 15% 48.53


paper, T&T etc
372.03

Labour
Output
1Lab+2Painters 60 m2/gdy/ct

No. of days required 11.35


say 11.00 61.9 680.9

Plant

Total Cost 1,052.93

Unit Cost/m2 (total Cost / Qty) 4.64

ADD: ON - COST 25% 1.16

UNIT RATE GH¢ 5.80


Screedring / Roughcasting Coati Operator 22.47 Wall & Floor Tiling
Artisan/day 28.47
Gang = (2 Mas 79.41 Labourer/day 22.47 Gang = (1 Tile
Currency in Use GH¢

A ICI Vinyl Emulsion 10888 m2

18litre pail 82.50

Coverage 160 m2/coat

Materials

Qty reqd 204.15 pails


Add waste 15% 30.62
234.77
say 235.00 pails 82.50 19387.5

Add: Brushes,Sand 20% 3,877.50


paper, T&T etc
23,265.00

Labour
Output
1Lab+2Painters 90 m2/gdy/ct

No. of days required 362.933


say 363.00 65.69 23845.47

Plant

Total Cost 47,110.47

Unit Cost/m2 (total Cost / Qty) 4.33


ADD: ON - COST 25% 1.08

UNIT RATE GH¢ 5.41

USD 3.81

A Texcote paint 151 m2

20litre pail 82.50


Coverage 25 m2/coat
Materials

Qty reqd 6.04 pails


Add waste 10% 0.60
6.64
say 7.00 pails 82.50 578

Add: Rollers, 15% 87


, T&T etc
664.13

Labour
Output
1Lab+2Painters 60 m2/gdy/ct

No. of days required 7.55


say 8.00 61.9 495.2

Plant

Total Cost 1,159.33

Unit Cost/m2 (total Cost / Qty) 7.68

ADD: ON - COST 25% 1.92


UNIT RATE GH¢ 9.60

Rate in US$ 6.95


Wall & Floor Tiling Operator 22.47
Artisan/day 28.47
50.94 Labourer/day 22.47
Currency in Use GH¢

You might also like