You are on page 1of 22

SUMMARY / ESTIMATED COST

ITEM NO. DESCRIPTION QTY. UNIT

I SITE WORKS 1 lot


II EARTHWORKS 1 lot
III CONCRETE WORKS all l.s.
IV REINFORCING BARS all l.s.
V FORMS / SCAFFOLDINGS all l.s.
VI MASONRY WORKS all l.s.
VII STRUCTURAL WORKS all l.s.
VIII ROOFING / TINSMITHRY WORKS all l.s.
IX CARPENTRY WORKS all l.s.
X DOORS WINDOWS all l.s.
XI TILEWORKS all l.s.
XII PLUMBING WORKS / SANITARY all l.s.
XIII WATERPROOFING all l.s.
XIV ELECTRICAL WORKS all l.s.
XV PAINTING WORKS all l.s.
XVI RAINWATER COLLECTOR all l.s.
XVII BILLBOARD & MARKINGS 1 lot

BREAKDOWN ESTIMATED COST

A. DIRECT COST
1.0 MATERIALS
2.0 LABOR

TOTAL DIRECT COST

B. IN-DIRECT COST

1.0 OVERHEAD, CONTINGENCY & MISCELLANUOUS (9%)


(Eng'n. Supervision, Quality Control, others)
2.0 CONTRACTOR'S PROFIT (8%)
TOTAL IN-DIRECT COST

C. VALUE ADDED TAX (12%)

TOTAL PROJECT COST

SAY
IMATED COST

% of TOTAL UNIT COST AMOUNT

5.70% P 1,609,367.50 P 1,609,367.50


3.58% 1,009,800.00 1,009,800.00
8.98% 2,535,891.00 2,535,891.00
33.60% 9,486,011.25 9,486,011.25
9.64% 2,721,854.20 2,721,854.20
4.26% 1,201,501.50 1,201,501.50
7.70% 2,173,143.00 2,173,143.00
3.02% 853,875.00 853,875.00
3.44% 972,067.50 972,067.50
7.69% 2,171,717.50 2,171,717.50
0.78% 220,950.00 220,950.00
3.20% 903,420.00 903,420.00
0.71% 199,500.00 199,500.00
3.48% 982,867.50 982,867.50
3.84% 1,083,645.00 1,083,645.00
0.35% 100,000.00 100,000.00
0.40% 10,000.00 10,000.00

100.37% P 28,235,610.95 P 28,235,610.95

P 18,481,989.00
9,753,621.95

TAL DIRECT COST P 28,235,610.95 28,235,621.95

31,765,074.69

P 2,541,204.99

P 2,258,848.88
AL IN-DIRECT COST P 4,800,053.86 33,035,664.81

P 3,964,279.78

P 36,999,944.59

P 37,000,000.00
3,529,452.74
DIRECT COST - SUMMARY

ITEM NO. DESCRIPTION QTY. UNIT % of TOTAL

I SITE WORKS 1 lot 5.70%


a. Mobilization all l.s.
b. Safety & Health Program all l.s.
c. Temporary Facility 1 lot
d, Temporary Utilyties 8 months
e. Soil Testing 4 holes
f. Material Testing 1 lot

II EARTHWORKS 1 lot 3.58%


a. Clearing, Removal of Obstruction 1208 sq.m.
b. Excavating Works 2258 sq.m.
c. Backfilling Works incld. Compaction 1765 cu.m.
d, Embankment 396 cu.m.

III CONCRETE WORKS all l.s. 8.98%


Material Cost
Gravel Tax
Equipment Rental
Labor Cost

IV REINFORCING BARS all l.s. 33.60%


Material Cost
Labor Cost

V FORMS / SCAFFOLDINGS all l.s. 9.64%


Material Cost
Labor Cost

VI MASONRY WORKS all l.s. 4.26%


Material Cost
Gravel Tax
Labor Cost

VII STRUCTURAL WORKS all l.s. 7.70%


Material Cost
Labor Cost

VIII ROOFING / TINSMITHRY WORKS all l.s. 3.02%


Material Cost
Labor Cost
IX CARPENTRY WORKS all l.s. 3.44%
Material Cost
Labor Cost

X DOORS WINDOWS all l.s. 7.69%


Material Cost
Labor Cost

XI TILEWORKS all l.s. 0.78%


Material Cost
Labor Cost

XII PLUMBING WORKS / SANITARY all l.s. 3.20%


Material Cost
Labor Cost cu.m. 285

XIII WATERPROOFING all l.s. 0.71%


(Toilet & Firewall)

XIV ELECTRICAL WORKS all l.s. 3.48%


Labor Cost
Material Cost cu.m. 285

XV PAINTING WORKS all l.s. 3.84%


Labor Cost
Material Cost cu.m. 285

XVI RAINWATER COLLECTOR all l.s. 0.35%


XVII BILLBOARD & MARKINGS 1 lot 0.40%
MMARY

%/ PHASE UNIT COST AMOUNT

P 1,609,429.82 P 1,609,367.50
3.106% 50,000.00 50,000.00
9.320% 150,000.00 150,000.00
51.285% 825,367.50 825,367.50
11.433% 23,000.00 184,000.00
18.640% 75,000.00 300,000.00
6.231% 100,000.00 100,000.00
100.0% P 1,609,367.50
P 1,009,800.00 P 1,009,800.00
8.9720% 75.00 90,600.00
55.902% 250.00 564,500.00
17.478% 100.00 176,500.00
17.6470% 450.00 178,200.00
100.00% 1,009,800.00
P 2,535,891.00 P 2,535,891.00
45.414% 1,151,650.00
4.541% 115,165.00
2.270% 57,582.50
47.773% 1,211,493.50 III 47.773
100.00% 2,535,891.00 IV 25.925
P 9,486,011.25 P 9,486,011.25 V 23.076
74.074% 7,026,675.00 VI 38.585
25.925% 2,459,336.25 VII 28.571
100.00% 9,486,011.25 VIII 25.926
P 2,721,854.20 P 2,721,854.20 IX 25.925
76.923% 2,093,734.00 X 13.043
23.076% 628,120.20 XI 28.038
100.00% 2,721,854.20 XII 25.925
P 1,201,501.50 P 1,201,501.50 282.787
59.807% 718,590.00
1.606% 19,305.00 28.2787
38.585% 463,606.50
100.00% 1,201,501.50
P 2,173,143.00 P 2,173,143.00
71.428% 1,552,245.00
28.571% 620,898.00
100.00% 2,173,143.00
P 853,875.00 P 853,875.00
74.074% 632,500.00
25.926% 221,375.00
100.00% 853,875.00
P 972,067.50 P 972,067.50
74.074% 720,050.00
25.925% 252,017.50
100.00% 972,067.50
P 2,171,717.50 P 2,171,717.50
86.956% 1,888,450.00
13.043% 283,267.50
100.00% 2,171,717.50
P 220,950.00 P 220,950.00
71.962% 159,000.00
28.038% 61,950.00
100.00% 220,950.00
903,420.00 903,420.00
74.074% 669,200.00
25.925% 234,220.00
100.00% 903,420.00
199,500.00 199,500.00
100.000% 199,500.00
100.00% 199,500.00
982,867.50 982,867.50
74.074% 728,050.00
25.925% 254,817.50
100.00% 982,867.50
1,083,645.00 1,083,645.00
74.074% 802,700.00
25.925% 280,945.00
100.00% 1,083,645.00
100,000.00 100,000.00
10,000.00 10,000.00
CONCRETE WORKS
TOTAL
DESCRIPTION LENGTH WIDTH DEPTH VOLUME QTY. VOL.
FOOTING 1 6.00 3.50 0.50 10.50 20.0 210.0
FOOTING 2 3.40 3.40 0.50 5.78 20.0 115.6
LEAN CONCRETE 6.00 3.50 0.10 2.10 20.0 42.0
F-GR COLUMN 0.59 0.59 2.10 0.72 20.0 14.4
GF-SF COLUMN 3.20 0.55 0.55 0.97 20.0 19.4
SF-TF COLUMN 3.20 0.55 0.55 0.97 20.0 19.4
TF-R COLUMN 3.20 0.40 0.40 0.51 20.0 10.2
TIE BEAM 1 2.50 0.30 0.50 0.38 19.0 7.1
TIE BEAM 2 7.00 0.30 0.50 1.05 20.0 21.0
TIE BEAM 3 4.50 0.30 0.50 0.68 19.0 12.8
GI BEAM-GF & SF 0.00 0.30 0.40 0.00 0.0 0.0
G2 BEAM-GF & SF 0.00 0.30 0.45 0.00 0.0 0.0
G3 BEAM-GF & SF 0.00 0.30 0.45 0.00 0.0 0.0
G4 BEAM-GF & SF 0.00 0.40 0.40 0.00 0.0 0.0
G5 BEAM-GF & SF 0.00 0.40 0.50 0.00 0.0 0.0
G6 BEAM-GF & SF 0.00 0.40 0.40 0.00 0.0 0.0
G7 BEAM-GF & SF 0.00 0.40 0.50 0.00 0.0 0.0
G8 BEAM-GF & SF 0.00 0.40 0.50 0.00 0.0 0.0

GF FLOOR SLAB 0.00 0.00 0.00 0.00 0.0 0.0


SF FLOOR SLAB 0.00 0.00 0.00 0.00 0.0 0.0
TF FLOOR SLAB 0.00 0.00 0.00 0.00 0.0 0.0

471.9
UNITS
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
MAIN BEAM SCH
SLAB MARK WIDTH DEPTH LENGTH QTY. VOL. UNIT

G1 0.30 0.40 3.50 19.0 7.980 cu.m.


G2 0.30 0.45 3.50 19.0 8.978 cu.m.
G3 0.30 0.45 4.50 19.0 11.543 cu.m.
2nd Flr. G4 0.40 0.45 2.50 2.0 0.900 cu.m.
G5 0.40 0.40 3.50 4.0 2.240 cu.m.
G6 0.40 0.40 2.50 18.0 7.200 cu.m.
G7 0.40 0.50 7.00 4.0 5.600 cu.m.
G8 0.40 0.50 7.00 24.0 33.600 cu.m.

G1 0.30 0.40 3.50 19.0 7.980 cu.m.


G2 0.30 0.45 3.50 19.0 8.978 cu.m.
G3 0.30 0.45 4.50 19.0 11.543 cu.m.
3rd Flr. G4 0.40 0.45 2.50 2.0 0.900 cu.m.
G5 0.40 0.40 3.50 4.0 2.240 cu.m.
G6 0.40 0.40 2.50 18.0 7.200 cu.m.
G7 0.40 0.50 7.00 4.0 5.600 cu.m.
G8 0.40 0.50 7.00 24.0 33.600 cu.m.

RG-1 0.30 0.40 4.50 57.0 30.780 cu.m.


RG-2 0.20 0.40 7.00 10.0 5.600 cu.m.
ROOF RG-3 0.20 0.40 9.50 2.0 1.520 cu.m.
RG-4a 0.20 0.40 6.89 2.0 1.102 cu.m.
RG-4a 0.20 0.40 6.89 2.0 1.102 cu.m.
TOTAL CONCRETE VOLUME 196.185 cu.m.

COLUMN SCHE
COL. MARK WIDTH DEPTH LENGTH QTY. VOL. UNIT
C1- F-GF 0.435 0.435 1.60 20.0 6.055 cu.m.
C1- GF - 2F 0.400 0.400 3.20 20.0 10.240 cu.m.
C1- 2F - 3F 0.400 0.400 3.20 20.0 10.240 cu.m.
C1- 3F - R 0.400 0.400 3.20 20.0 10.240 cu.m.
C2 - F-GF 0.610 0.610 1.60 20.0 11.907 cu.m.
C2 - GF - 2F 0.550 0.550 3.20 20.0 19.360 cu.m.
C2 - 2F - 3F 0.550 0.550 3.20 20.0 19.360 cu.m.
C2 - 3F - R 0.450 0.450 3.20 20.0 12.960 cu.m.

C3 - F-GF 0.585 0.585 1.60 20.0 10.951 cu.m.


C3 - GF - 2F 0.550 0.550 3.20 20.0 19.360 cu.m.
C3 - 2F - 3F 0.550 0.550 3.20 20.0 19.360 cu.m.
C3 - 3F - R 0.450 0.450 3.20 20.0 12.960 cu.m.
TOTAL VOLUME of CONCRETE 162.994 cu.m.

SEPTIC TANK VAULT (2 units)


ITEM WIDTH DEPTH LENGTH AREA VOLUME UNIT

WALL 1 8.6 0.15 1.8 15.48 4.644 cu.m.


WALL 2 8.6 0.15 1.8 15.48 4.644 cu.m.
WALL 3 4.6 0.15 1.8 8.28 2.484 cu.m.
WALL 4 4.6 0.15 1.8 8.28 2.484 cu.m.
BOTTOM 8.6 0.15 2.3 19.78 5.934 cu.m.
TOP 8.6 0.15 2.3 19.78 5.934 cu.m.
87.08 26.124 cu.m.

CONCRETING =

REBARS =

TOP 8.6 0.3 2.30 131.866667 mtr.


2.3 0.3 8.60 131.866667 mtr.
BOTTOM 8.6 0.3 2.30 131.866667 mtr.
2.3 0.3 8.60 131.866667 mtr.
WALL 1 8.6 0.3 1.80 103.2 mtr.
1.8 0.3 8.60 103.2 mtr.
WALL 2 8.6 0.3 1.80 103.2 mtr.
1.8 0.3 8.60 103.2 mtr.
WALL 3 2.3 0.3 1.80 27.6 mtr.
1.8 0.3 2.30 27.6 mtr.
WALL 4 2.3 0.3 1.80 27.6 mtr.
1.8 0.3 2.30 27.6 mtr.
WALL 5 2.3 0.3 1.80 27.6 mtr.
1.8 0.3 2.30 27.6 mtr.
WALL 6 2.3 0.3 1.80 27.6 mtr.
1.8 0.3 2.30 27.6 mtr.

1161.06667 mtr.

STRUCTURAL STEEL WORKS


STEEL TRUSSES

TOTAL in
ITEM DIM. UNIT CONFIG. QTY. TOTAL 6M.
TOP CHORD 6.89 Lmtr. 4.0 20.0 551.2 91.9
BOTTOM C. 4.50 Lmtr. 4.0 20.0 360.0 60.0
V1 1.92 Lmtr. 4.0 20.0 153.2 25.5
V2 3.04 Lmtr. 4.0 20.0 243.0 40.5
D1 4.77 Lmtr. 4.0 20.0 381.4 63.6
D2 2.91 Lmtr. 4.0 20.0 233.0 38.8
STRUT 15.00 Lmtr. 1.0 19.0 285.0 47.5
367.8

SAG ROD 6.89 4.0 19.0 523.6 87.3 Pcs. Of 12mm RB


CROSS BRACING 5.20 4.0 10.0 208.0 34.7
7.20 4.0 10.0 288.0 48.0
82.7 Pcs. Of 16mm RB
END BAY SUPPORT 0.6 15 4 36.0 6.0 PCS. OF 40mm. x 40mm. x 5mm
GUSSET PLATE 12.56 sq.mtr. of 6mm thk. Steel plate
8.85 sq.mtr. of 12mm thk. Steel plate
FASCIA 87.50 2.0 175.0 29.17
6.73 4.0 26.9 4.49
33.65 Pcs. Of 2"x 4"x6m., 1.2mmthk. C-purlins
33.65 Pcs. Of 2"x 6"x6m., 1.2mmthk. C-purlins
SHELF ANGLE 0.8 20 16 2.67 Pcs. Of 75"x 75" x 6m., 4.5mm thk.
J-Bolt
WELDING ROD 10 1 box of Welding rod
EPOXY PRIMER 110 1 gallons of Epoxy primer
OXYGEN/ACUTYLENE 1 lot
ROOF SEALANT
ROOFING
ROOF 6.9 87.5 2.0 1205.75 Lmtr. Of Pre Painted roof (rib type), 1.126w
RIDGE ROLL 87.5 4.0 - 350.00 144.0 Pcs. Of Pre-painted Ridge cap,
PURLINS 87.5 15.0 2.0 2625.00 437.5 Pcs. Of C-purlins, 2"x 6"x 6m, 0
FLASHING 6.7 4.0 26.93 11.1 Pcs. Of Pre-painted Ridge cap,
GUTTER 87.5 2.0 - 175.00 72.0 Pcs. Of Pre-painted GUTTER
DOWNSPOUT PIPE 11.7 4.0 10.0 466.40 155.5 Pcs. Of 3"ID. S1000 PVC pipe
3"ID. ELBOW 3.0 2.0 10.0 - 60.00 Pcs. Of 3"ID.PVC ELBOW
Sealant
Others

CARPENTRY
Ceiling (int.) 76.2 8.0 609.9 211.8
36.43 3 109.3 37.9
249.7 Pcs. Of 12mm thk. Gypsum Board

Metal Furring 6.7 15.0 8.0 804.0 268.0


C. Channel 8.6 5.0 8.0 344.0 114.7
Rod Suspension 6.0 5.0 8.0 240.0 240.0
Furring clip 15.0 5.0 8.0 600.0 600.0
C. channel hanger 6.0 5.0 8.0 240.0 240.0
Wall Angle 15.0 2.0 8.0 240.0 40.0

Metal Furring 2.2 15.0 8.0 264.0 88.0


C. Channel 8.6 2.0 8.0 137.6 45.9
Rod Suspension 2.0 7.0 8.0 112.0 112.0
Furring clip 2.0 7.0 8.0 112.0 600.0
C. channel hanger 2.0 7.0 8.0 112.0 240.0
Wall Angle 21.7 1.0 8.0 173.6 28.9

Metal Furring 8.9 7.0 3.0 186.9 62.3


C. Channel 4.1 7.0 3.0 86.1 28.7
Rod Suspension 2.0 7.0 3.0 28.0 28.0
Furring clip 2.0 7.0 3.0 28.0 600.0
C. channel hanger 2.0 7.0 3.0 28.0 240.0
Wall Angle 12.6 1.0 3.0 37.8 6.3

SPANDREL, std. 87.5 1.5 131.3 2.0 262.5


6.9 1.0 6.9 4.0 27.6
290.1
-24
266.1 Lmtr. Of Spandrel-105mm

SPANDREL, w/ vent. 0.4 1.5 0.6 40.0 24.0 Lmtr. Of Spandrel-105mm w/ v

PAINTING
EXTERIOR 912.0 2.0 1824 sq.m. 72.96

INTERIOR 820.8 1.0 820.8 sq.m.


246.2 1.0 246.2 sq.m.
812.3 1.0 812.25 sq.m.
1879.25 sq.m.

EXTERIOR
NUETRALIZER 21.0 5.3 gallons 2.6 tin
PRIMER (FLAT LATEX) 365.0 91.3 gallons 45.6 tin
PUTTY 608.0 152.0 gallons 76.0 tin
GLOSS LATEX 584.0 146.0 gallons 73.0 tin
REDUCER, PUTTY 76.0 19.0 gallons 9.5 tin

INTERIOR
NUETRALIZER 13.0 3.3 gallons 1.6 tin
PRIMER (FLAT LATEX) 213.0 53.3 gallons 26.6 tin
MASONRY PUTTY 356.0 89.0 gallons 44.5 tin
GLOSS LATEX 341.0 85.3 gallons 42.6 tin

CEILING
FLATWALL ENAMEL 162 40.5 gallons 20.3 tin
GLAZING PUTTY 271 67.8 gallons 33.9 tin
TOP COAT- GLOSS 260 65.0 gallons 32.5 tin
PAINT THINNER 139 34.8 gallons 17.4 tin

Roller w/ tray, 7"


Roller filler, 7"
Paint Brush
Sandpaper
Masking tape
Rags
MAIN BEAM SCHEDULE
REINFORCEMENT BARS
RB SIZE LEFT MID SPAN RIGHT STIRRUPS (10mm ID)
TOP BOTTOM TOP BOTTOM TOP BOTTOM CONFIG. TYPE
20mm 3 2 2 2 3 2 I A
20mm 4 2 2 2 4 2 II A
20mm 4 2 2 2 4 2 II A
20mm 3 3 3 3 4 3 I B
20mm 6 3 3 4 5 3 III A
20mm 4 3 3 3 4 3 I B
25mm 6 3 2 4 5 3 III A
25mm 5 3 2 4 5 3 III A

20mm 3 2 2 2 3 2 I A
20mm 4 2 2 2 4 2 II A
20mm 4 2 2 2 4 2 II A
20mm 3 3 3 3 4 3 I B
20mm 6 3 3 4 5 3 III A
20mm 4 3 3 3 4 3 I B
25mm 6 3 2 4 5 3 III A
25mm 5 3 2 4 5 3 III A

16mm 3 3 3 3 3 3 I A
16mm 2 3 2 3 2 3 I A
16mm 2 2 2 2 2 2 I A
16mm 2 2 2 2 2 2 I A
16mm 2 2 2 2 2 3 I A

COLUMN SCHEDULE
RB Vert. LENGTH QTY./COL. COL. NOS. TOTAL STIRRUPS LENGTH QTY./COL. COL. NOS.
25mm 2.60 12.0 20.0 104.00 10mm 1.73 12.0 20.0
25mm 3.70 12.0 20.0 148.00 10mm 1.51 21.0 20.0
25mm 3.70 12.0 20.0 148.00 10mm 1.51 21.0 20.0
25mm 3.70 12.0 20.0 148.00 10mm 1.51 21.0 20.0
25mm 2.60 12.0 20.0 104.00 10mm 2.24 12.0 20.0
25mm 3.70 12.0 20.0 148.00 10mm 2.10 21.0 20.0
25mm 3.70 12.0 20.0 148.00 10mm 2.10 21.0 20.0
25mm 3.70 12.0 20.0 148.00 10mm 1.65 21.0 20.0

25mm 2.60 12.0 20.0 104.00 10mm 2.24 12.0 20.0


25mm 3.70 12.0 20.0 148.00 10mm 2.10 21.0 20.0
25mm 3.70 12.0 20.0 148.00 10mm 2.10 21.0 20.0
25mm 3.70 12.0 20.0 148.00 10mm 1.65 21.0 20.0
TOTAL NOS. of 25mm REBARS 1644.00 TOTAL NOS. of 12mm STIRRUPS

Total Volume of Concrete

235.1 Nos. of cement 225.00 52,901.10


13.1 cu.m. of Sand 600.00 7,837.20
26.1 cu.m. of Gravel 100.00 2,612.40
40.0 pcs. 1/2"thk. Mar. Ply 750.00 30,000.00
50 pcs. 2"x3"x12' 300.00 15,000.00
6 Kgs. Assorted CWN 5.00 30.00
193.5 Nos. of 10mm Rebars 125.00 24,188.89
132,569.59 Materials
46,399.36 Labor (35%)
178,968.95
16,107.21 OCM (9%)
195,076.15
15,606.09 PM (8%)
210,682.24 Total Cost
Pcs. Of 2"x 2"x 6m., 6mm. Thk. Angular

Pcs. Of 12mm RB

Pcs. Of 16mm RB
PCS. OF 40mm. x 40mm. x 5mm.thk.

4"x6m., 1.2mmthk. C-purlins


6"x6m., 1.2mmthk. C-purlins
x 75" x 6m., 4.5mm thk.

e Painted roof (rib type), 1.126w, 0.40mm thk.


Pcs. Of Pre-painted Ridge cap, 2"x 6"x 6m, 0.2mm thk.
Pcs. Of C-purlins, 2"x 6"x 6m, 0.2mm thk.
Pcs. Of Pre-painted Ridge cap, 2"x 6"x 6m, 0.2mm thk.
Pcs. Of Pre-painted GUTTER
Pcs. Of 3"ID. S1000 PVC pipe
Pcs. Of 3"ID.PVC ELBOW

mm thk. Gypsum Board

Gypsum Board 249.7 pcs.


Metal Furring - 419.0 pcs.
C. Channel - 194.0 pcs.
Rod Suspension - 380.0 pcs.
Furring Clip - 380.0 pcs.
C. Channel hanger - 380.0 pcs.
Wall angle - 75.5 pcs.
2" wood corniche - 1487.0 Lft.
Spandrel, std. 266.0 Lmtr.
Spandrel, w/ vent holes. 24.0 Lmtr.

Lmtr. Of Spandrel-105mm

Lmtr. Of Spandrel-105mm w/ vent holes


820.8
91.2
912.0
MAIN BEAM REBARS

DESCRIPTION MAIN RBAR STIRRUPS QTY./B


1.167 2.100 3.500 20mm 10mm
1.167 2.100 3.50 G1 58.0 1.15 28.00
1.500 2.700 4.50 G2 73.0 1.10 28.00
0.833 1.500 2.50 G3 100.0 1.15 34.00
1.167 2.100 3.50 G4 5.0 1.30 22.00
0.833 1.500 2.50 G5 16.0 1.20 28.00
2.333 4.200 7.00 G6 58.0 1.20 22.00
2.333 4.200 7.00 G7 38.0 1.40 50.00
G8 39.0 1.40 50.00
387.0 Nos.of 20mm Rebars

TOTAL
69.20
105.70
105.70
105.70
89.60
147.00
147.00
115.50

89.60
147.00
147.00
115.50
1384.50
BEAM REBARS

no. of beam TOTAL LENGTH NO. OF PCS.

38.00 1223.6 203.9


38.00 1170.4 195.1
38.00 1485.8 247.6
4.00 114.4 19.1
8.00 268.8 44.8
36.00 950.4 158.4
8.00 560.0 93.3
32.00 2240.0 373.3
0mm Rebars 1335.6 Nos. of 10mm Rebars

You might also like