Data

- Panjang Jalan 358 meter


- Lebar Jalan 12 meter
- Tebal Urugan 0.5 meter
- Cut 14209 BCM
- Fill 7430 BCM
- SG Batu 2.3
- Bucket Capacity 0.93 BCM
- Jumlah Bucket 8
- Jarak Quary - centroid jalan 0.1 km
- Loading point sirtu 1
- Compactor Used 1 Unit

CUT AND FILL

FILL - STONE (BCM) 3,715


FILL - SOIL (BCM) 3,715
CAPACITY OF UNIT FILL (BCM/DAY) 541
UNIT USED
- EXCA PC 200 #NAME?
- BULDOZER #NAME?

QUARY
Jarak GEOMETRI JALAN
MATERIAL
(Km) PANJANG JALAN (m) LEBAR JALAN (m)

4.1 Sirtu 358 12

COMPACTING
GEOMETRI JALAN
PANJANG JALAN (m) LEBAR JALAN (m) TEBAL URUGAN (m) VOLUME
358 12 0.5 2,148.00
Result
dan TOTAL USED UNIT USE
EXCA PC 200 #NAME? Unit
Grader 1 unit
ROCKBREAKER 1 Unit
COMPACTOR 1 Unit
DT 14 Unit
TOTAL DAYS #DIV/0! Days

1 1

If DT not maksimum 1000 Unit EXCA PC 200 Grader ROCKBREAK

Note: isi data di cell warna kuning

GEOMETRI JALAN
JAM KERJA
TEBAL URUGAN (m) VOLUME EFEKTIF

0.5 2,148.00 4,940.40 0

PENGGUNAAN ALAT BERAT LAMA


JAM KERJA EFEKTIF PENGERJAAN
VOLUME COMPACTOR (HARI)
32,778 ton 0 1 #DIV/0!
UNIT USED
14

1 1 1

EXCA PC 200 Grader ROCKBREAKER COMPACTOR DT

PENGGUNAAN ALAT BERAT (maksimal)


LAMA PENGERJAAN
EXCAVATOR PC200 DT (HARI)

1 14 #DIV/0!
ROAD PROJECT PLANNING - SEGMENT C (
STONE)
WORKING HOURS

TOTAL DAYS AND SHIFTS :


MOHH 24 hours/day (hrs)
P5M 15 min/shift (min)
P2H 10 min/shift (min)
Take Operators to Location 10 min/shift (min)
Greasing 20 min/shift (min)
Refueling 20 min/day (min)
Rain 120 min/shift (min)
Meal and Rest 60 min/shift (min)
End of the Shift Preparation 15 min/shift (min)
Shift Change 60 min/shift (min)
Friday Pray 60 min/week (min)
Total Working Hours

CUT COMBINATION EQUIPMENT QUANTITY

PC200 (SUPPORT)
ROCK BREAKER

EQUIP. PHYSICAL AVAILABILITY


ROCK BREAKER 90%

EQUIPMENT USE OF AVAILIBILITY

ROCK BREAKER

EQUIP. PRODUCTIVITY BCM/JAM

ROCK BREAKER 10

EQUIPMENT CAPACITY

TOTAL EQUIPMENT CAPACITY (CUT) BCM


G - SEGMENT C (CUT-
Daily (Hours)
Sun Mon Tue Wed Thu Fri
Sun Mon Tue Wed Thu Fri
24.00 24.00 24.00 24.00 24.00 24.00
0.50 0.50 0.50 0.50 0.50 0.50
0.33 0.33 0.33 0.33 0.33 0.33
0.33 0.33 0.33 0.33 0.33 0.33
0.67 0.67 0.67 0.67 0.67 0.67
0.33 0.33 0.33 0.33 0.33 0.33
2.00 2.00 2.00 2.00 2.00 2.00
2.00 2.00 2.00 2.00 2.00 2.00
0.50 0.50 0.50 0.50 0.50 0.50
2.00 2.00 2.00 2.00 2.00 2.00
0.00 0.00 0.00 0.00 0.00 2.00
15.33 15.33 15.33 15.33 15.33 13.33

Daily (Hours)

Sun Mon Tue Wed Thu Fri

1 1 1 1 1 1
1 1 1 1 1 1

Daily (Hours)
90% 90% 90% 90% 90% 90%

Daily (Hours)

60% 60% 60% 60% 60% 51%

Daily (Hours)
10 10 10 10 10 10

Daily (Hours)
Sun Mon Tue Wed Thu Fri
Sun Mon Tue Wed Thu Fri
83 83 83 83 83 61

Stone Material (BCM)


Segment
Length (m) Area (ha) Cut
C 358 0.43 14,209
Total 358 0.43 14,209

Total Cut (BCM) 14,209


Length (m) 358
Total
Area (Ha) 0.43

CUT (BCM) 14,209


CAPACITY OF UNIT (BCM)/DAY 80
ESTIMATION COMPLETED (DAY) 179
Week
Sat
Sat
24.00 168.0
0.50 3.5
0.33 2.3
0.33 2.3
0.67 4.7
0.33 2.3
2.00 14.0
2.00 14.0
0.50 3.5
2.00 14.0
0.00 2.0
15.33 105

Week
Sat

1 1
1 1

Week
90% 90%

Week

60% 59%

Week
10 10

Sat Week
Sat
83 80
ROAD PROJECT PLANNING - SEGMENT C (FILL
WORKING HOURS

TOTAL DAYS AND SHIFTS :


MOHH 12 hours/day (hrs)
P5M 15 min/shift (min)
P2H 10 min/shift (min)
Take Operators to Location 10 min/shift (min)
Refueling 25 min/shift (min)
Rain 120 min/shift (min)
Slippery 120 min/shift (min)
Meal and Rest 60 min/shift (min)
End of the Shift Preparation 15 min/shift (min)
Shift Change 60 min/shift (min)
Friday Pray 60 min/week (min)
Total Working Hours

CUT and FILL COMBINATION EQUIPMENT QUANTITY

DUMP TRUCK
PC 200
PC200 (SUPPORT)

EQUIP. PHYSICAL AVAILABILITY


DUMP TRUCK 90%
PC 200 85%

EQUIPMENT USE OF AVAILIBILITY

DUMP TRUCK
PC 200

EQUIP. PRODUCTIVITY BCM/JAM

DUMP TRUCK 80
PC 200 80

EQUIPMENT CAPACITY

DUMP TRUCK BCM


PC 200 BCM
TOTAL EQUIPMENT CAPACITY (FILL) BCM
EGMENT C (FILL)
Daily
Sun Mon Tue Wed Thu
Sun Mon Tue Wed Thu
12.00 12.00 12.00 12.00 12.00
0.25 0.25 0.25 0.25 0.25
0.17 0.17 0.17 0.17 0.17
0.17 0.17 0.17 0.17 0.17
0.42 0.42 0.42 0.42 0.42
2.00 2.00 2.00 2.00 2.00
2.00 2.00 2.00 2.00 2.00
1.00 1.00 1.00 1.00 1.00
0.25 0.25 0.25 0.25 0.25
1.00 1.00 1.00 1.00 1.00
0.00 0.00 0.00 0.00 0.00
4.75 4.75 4.75 4.75 4.75

Daily

Sun Mon Tue Wed Thu

2 2 2 2 2
1 1 1 1 1
1 1 1 1 1

Daily
90% 90% 90% 90% 90%
85% 85% 85% 85% 85%

Daily

33% 33% 33% 33% 33%


29% 29% 29% 29% 29%

Daily
80 80 80 80 80
80 80 80 80 80

Daily
Sun Mon Tue Wed Thu
Sun Mon Tue Wed Thu
568 568 568 568 568
236 236 236 236 236
568 568 568 568 568

Soil (BCM) Stone (BCM)


Segment Length (m) Area (Ha)
FILL FILL
C 358 0.43 3,715 3,715
Total 358 0.43 3,715 3,715

FILL - STONE (BCM) 3,715


FILL - SOIL (BCM) 3,715
CAPACITY OF UNIT FILL (BCM/DAY) 541
ESTIMATION COMPLETED (DAY) 14
Week
Fri Sat
Fri Sat
12.00 12.00 84.0
0.25 0.25 1.8
0.17 0.17 1.2
0.17 0.17 1.2
0.42 0.42 2.9
2.00 2.00 14.0
2.00 2.00 14.0
1.00 1.00 7.0
0.25 0.25 1.8
1.00 1.00 7.0
1.00 0.00 1.0
3.75 4.75 32

Week
Fri Sat

2 2 2
1 1 1
1 1 1

Week
90% 90% 90%
85% 85% 85%

Week

24% 33% 32%


19% 29% 28%

Week
80 80 80
80 80 80

Fri Sat Week


Fri Sat
408 568 541
156 236 223
408 568 541
JAM KERJA
MA DT MA Exca UOA FF SF SG
EFEKTIF

90% 85% 61% 100% 1 2.3 0

Jarak GEOMETRI JALAN


MATERIAL PANJANG
(Km) LEBAR JALAN (m) TEBAL URUGAN (m) VOLUME
JALAN (m)
4.1 Sirtu 358 12 0.5 2,148.00 4,940.40
JUMLAH MATERIAL
GEOMETRI URUGAN (M)
VOLUME
PANJANG LEBAR TEBAL
(BCM) KAPASITAS BUCKET (M3)
358 12 0.5 2,148 0.93

PENGGUNAAN ALAT BERAT (maksimal)


JAM KERJA EFEKTIF LAMA PENGERJAAN (HARI)
EXCAVATOR PC200 DT

0 1 14 #DIV/0!
EXCA
CT EXCA
BUCKET/RIT
Digging time Swing time Dumping time Empty swing time KAPASITAS BAK M3
6 8 2 7 8 7.44
DUMP TRUCK
KECEPATAN CT DT
JARAK (KM) KECEPATAN ISI (KM/JAM) KOSONG
(KM/JAM) Manuver Time Loading Time
Hauling Time
4.1 10 15 30 184 1476
CT DT
PRODUCTIVITY EXCA PER JAM PRODUCTIVITY DT PER JAM MAX DT

Manuver Time
DumpingEmpty
Time Hauling Time
30 10 984 75.4755652173913 5.41798673544584 14
PRODUKSI PER HARI (BCM) WAKTU YANG DIBUTUHKAN (HARI)

0 #DIV/0!
Productivity
Exca Dozer DT Grader Compactor
200 m3/jam 2036.25 m2/jam 0.8
122 m3/jam 2000
12
0.5
800
66.67
60.00
2148.00
lama jam 35.80
lama hari #DIV/0!

GEOMETRI JALAN
JAM KERJA
PANJANG EFEKTIF
LEBAR JALAN (m) TEBAL URUGAN (m) VOLUME
JALAN (m)
358 12 0.5 2,148.00 32,778 ton 0
m
m/jam
lintasan
m

m3/jam

PENGGUNAAN ALAT BERAT


LAMA PENGERJAAN
COMPACTOR (HARI)

1 #DIV/0!