You are on page 1of 14

DAY SHIFT ACTIVITY& PERFORMANCE REPORT

FULA CPF, MOGA, FNE, JAKE, KEYI, HADIDA& Sufyan EPF


Date: Apr,04,2018
Report Number: 04,04,2018
Report Prepared By: Bashir Abdalla
Report Approved by: Amir Hamad
CPF
Site personnel:-

Name Company Position


Dayshift Personnel
Luai Gmarelden P.E CPF Supervisor
Abdelrahman Hussin P.E Operation Coordinator
Amir Hamad P.E CPF Foreman
Mohammed Alyas P.E CPF Operator
Khalid Tajeldin P.E CPF S. Operator
Anwar Mohamed P.E CPF C.R Operator
Bashir Abdalla P.E CPF C.R Operator
Mohamed Alshami P.E CPF Operator
Eltahir Okasha P.E CPF Operator
Siddig Abdelrahman P.E CPF Operator
Nightshift Personnel
Almaki Hamid P.E CPF Foreman
Badreldeen Eltahir P.E CPF S. Operator
Mutaz Abdalmonim P.E CPF C.R Operator
Ahmed Tajeldin P.E CPF C.R Operator
Hassan Elmogtaba P.E CPF Operator
Ibrahim Aljaily P.E CPF Operator

Ongoing Operations and Evaluation


CPF: Daily Activities
1. Patrol check for all production facilities has been done, monitor & record the parameters.
2. Routine maintenance for transfer pump P-1203A, circulation pumps P-1502A done.
3. Cooperated with DCS crew to check ESD hardware in CPF shipping tanks.
4. Cooperated with DCS crew to check shipping tank TK-1506 gas detector (Ongoing).
5. Cooperated with mechanical team to repair overheat at P-1951B, P-1952A and P-1952C (Ongoing).
6. Water drained from TK-1202/3, TK-1501/2/3/4/5/6 and TK-1507.
7. Average flow rate to CPF: 211 Sm3/hr., PS#1 318Sm3/hr., BV2:132Sm3/hr.
Shipping Tanks level

TK-1507 (mm) TK-1506 (mm) TK-1505 (mm) TK-1504 (mm) TK-1503 (mm) TK-1502 (mm) TK-1501 (mm)

1284 11308 2295 3569 2470 2422 4002

Chemical and Heater Operation Activities:.


1. Routine check for all chemical pumps and heaters has been done.
2. Cooperated with mechanical crew to fed lube oil to Hadida & Sufyan Chemical pump.
3. Received 3000L Reverse Demulsfier RSA 3952 & 3000L Light Demulsfier DCP3

Evaporation pond:
1. Reclaiming oil from retention pond by reclaim oil pump P-1602.
2. Reclaiming oil from evaporation pond NO#1 by vacuum truck.

Star Oil Ongoing Operations:-


1. Metering skid stream (A/B) online.

Metering skid and line parameters:

Time Pressure (K Pa) Temperature (C°) Flow rate(m3/h)


06:00 124 38 18.5
12:00 135 38 18.9
1.7 CPF AGR:
Site Personal

Dayshift Personnel
Name Company Position
Mosab Balla P.E AGR Operator
Wala omer P.E AGR Operator
Nightshift Personnel
- - -
Ahmed Ali P.E AGR Operator
Activities of AGR
1. Patrol check for engines, vessels and compressors have been done, monitor & record
its parameter.
2. Stopped unit C at 7:00 for 47k routine maintenance and back to normal at 15:00.
3. Fed lube oil to unit C and soft water for unit B.
4. Start unit B at 7:00 and stopped it due changeover to unit C at 15:00.
5. Unit B is standby.
6. Units A & C are running normally.

CPF AGR daily running and performance report:

AGR Units Running (hr) Outlet Pressure (Mpa) Flow Rate (m3/hr.)
1409-A 15 8.35 3974
1409-B 7 8.33 2496
1409-C 7 8.38 3789
Natural Gas treatment Package Outlet Pressure (Mpa) Total Flow Rate
1420-A Not lined up - -
1420-B Stopped - -
FNE 4.02 -
Total Outlet Gas Volume (m3)
103,598
1.4Fula Field
1.4.1 Site Personnel:

Name Company Position


Dayshift Personnel
Abdorhman G.Alden P.E Field Foreman
Ibrahim Osman P.E Field Operator
Mohamed Hamid P.E Field Operator
Yasir Fathelrhman P.E Field Operator
Nightshift Personnel
Sharif Salah P.E Field Foreman

Fula Field:-

1. Patrol check has been done normal and carefully.


2. Emptied sample barrels of four wells.
3. Update parameters of some wells.

Moga FPF:
Site Personnel:

Name Company Position


Dayshift Personnel
Moawia Mohammed P.E FPF Foreman
Momen Mohammed P.E FPF Operator
Mohamed Hashim P.E FPF Operator
Hassan Eltoum P.E C.R Operator
Nightshift Personnel
Mohammed Elkhalifa P.E FPF Foreman
Abdelkarim Osman P.E FPF Operator
Emadeldin Eltigani P.E C.R Operator
1.2 Ongoing Operations and Evaluation

1.3 Day Shift Activities

FPF
1. Patrol check for all production facilities has been done, monitor & record the parameter.
2. Flushed light crude trunk line by hot water and pump truck from 08:35 to 09:05.

Surge tank level: 3.5m.


Average transit line pressure: 0.48Mpa
Average transit line flow rate: 53m3/h

Field:
Field personnel:

Name Company Position


Dayshift Personnel
Nasr Elsir P.E Field Operator
Alamin Altayib P.E Field Operator
Nightshift Personnel
Mohamed Yousif P.E Field Operator

1. Routine check for all production wells and OGMs has been done.
2. Tested M18-4.
3. Started M7-5 (PCM) at 10:00 by 5Hz under rig test.

AGR Activities:
Name Company Position
Dayshift Personnel
Omer Mohiad P.E AGR Operator
Night shift
Salih Awad P.E AGR Operator

1. Patrol check for engines, vessels and compressors has been done, monitor & record its
parameters.
2. Unit (PK-2409-A) stopped on Feb.03, 2015 due to compressor 2nd stage piston damage.
Unit (PK-2409-B) Running normally.
1.3.3 AGR daily running and performance report:

Engine No. Running (hrs.) Outlet Pressure (Mpa) Average Flow Rate(m3/h)

A
B 15 7.27 2340

Total Gas Volume(m3) 35092

FNE FPF
1Site Personnel:

Name Company Position

Fadlalla Ahmed DayshiftP.EPersonnel FPF Operator


Ayman Ahmed P.E FPF Operator
Mohammed Alaa
Mutaz Bannaga P.E FPF Foreman
Operator

Nightshift Personnel
Medyan Ali P.E FPF Foreman
Neyazy Abdelmuniem P.E FPF Operator
Nazar Mohammed P.E FPF Operator

1.2 FPF Activities:


1. Patrol check for production facilities has been done, monitor & record its
parameters.
2. Drained bottom water of storage tank TK-8501.
3. Weekly Firefighting pump test has been done.
4. Received 1 load of soft water from VBU.
5. Housekeeping at FPF.

Tanks Level:

TK-8201-A TK-8201-B TK-8501


15487 mm 12358 mm 4655 mm

2.1 Field personnel:


Mohammed Salah P.E Field Operator
Faroug
Name Fadolelmola P.E
Company Field Operator
Position

Dayshift Personnel

Mohammed Ali P.E Field Operator


Abdalla Alnour P.E Field Operator

Nightshift Personnel

2.2Field Activities:
1. Routine check for all production wells and OGMs has been done.
2. FNE-07 shut-in from 08:00 to 14:00 due to low Pump submergence.
3. FNE-42 shut-in from 08:00 to 20:00 due to low Pump submergence.
4. Cooperated with electrician staff to repair OGM-4 transfer pump.
5. Cooperated with contractor & corrosion engineer to check CP of all wells.
6. Updated well head parameters.
7. Tightened stuffing box for some wells.

3.0 Sand Cleaning:


3.1 Sand Cleaning Personnel:

Name Company Position


Dayshift Personnel
Mohammed Bakheet P.E Sand clean
Sami Edris P.E Sand clean

3.2 Sand Cleaning Activities:


1. Launched 10” formal pig from OGM-2.
2. Cleaned sand trap online of OGM-2.
3. Flushed flow line of OGM-10.

Jake FPF
Site Personnel:-

Name Company Position


Dayshift Personnel
Mohammed Abdalla P.E Operation Supervisor
Yousif Abdelkhalig P.E FPF Foreman
Abdalla Ali Hamid P.E C.R Operator
Osama Yahia P.E FPF Operator
Alwathig Mohamed P.E FPF Operator
Nightshift Personnel
Rahama Mohamed P.E FPF Foreman
Subhi Amin P.E FPF Operator
Yassir Saeed P.E FPF Operator
1.2 Ongoing Operations and Evaluation
FPF Activities:-

1. Patrol check for production facilities has been done.


2. Transferred 18 empty chemical drums to OEPA yard.
3. Dismantled Skimming pump (P-7601-B) for maintenance.
4. Fed 1000kg DCP-3 chemical injection.
5. Repaired the lube oil leakage of air compressor unit (B).
6. Average flow rate to FPF 52.61 M³/hr. and to CPF 55.93 M³/hr.

Storage Tank parameter:-

Tank Number Level (M) Temp (˚C)


TK-7501 8.4 64

2. Field:-
2.1 Site personnel:-

Abubaker Mahjoub P.E Field Operator

Nightshift Personnel
Emad Ibrahim P.E Field Operator

Field Activities:-

1. Routine check for all production wells has been done.


2. Re-adjust flow rate for gas wells.
3. Continue N2 injection for JS-18 by (PSNI# 1).
4. Continue N2 injection for JS-19 by (PSNI# 2).
5. Shooting for JS-13, JS-32, JS36 and JS-37 has been done.
6. JE-1 stopped at 04:00 due to diesel generator tripped and resumed after repairs done by
maintenance staff at 10:30.
7. Tighten JS-37 stuffing box (ongoing).
8. OGM1 has been cleaned by steam truck.

Wells parameters (HP, MP& N2)


No. TP CP FLP T Choke Total Gas Total Gas Daily Injection
(Mpa) (Mpa) (Mpa) (˚C) Size Injection Injection injection Type And
(mm) (Open reading) (Close reading) (M3) AGR
(m3)(15:00) (m3)(15:00) (HP ,MP or
N2)

JS-1 9.1 N/A 0.84 66 50/50 103075980 103144321 68341 MP


JS-3 1.2 6.0 1.1 65 50 MP
JS-4 1.2 N/A 0.9 69 50 MP
JS-13 0.89 N/A 0.86 N/A - MP
JS-10 N/A N/A 1.05 66 50/50 84625380 84724147 98767 MP
JS-14 1.25 N/A 0.93 66 50
JS-15 1.5 N/A 0.90 66 50 35916930 35954784 37854 MP
JS-26 0.80 N/A
JS-28 1.5 N/A 0.95 68 50 MP
JS-35 8.0 0.95 1.2 70 50 34963320 35008663 45343 MP

3. JAKE AGR:-
3.1 Site Personnel:-

Name Company Position


Dayshift Personnel
Mohamed Dalil P.E AGR Operator
Eltayeb Ibrahim P.E AGR Operator
Elbarra Almubarak P.E AGR Operator
Nightshift Personnel
Almokashfi Albashier P.E AGR Operator
Mohamed Fawzi P.E AGR Operator

3.2 Jake M.P AGR Performance Report:-


Activities:-
1. Patrol check for engines, vessels and compressors has been done, monitor & record its
parameter.
2. Follow with maintenance staff to :
 Check the piston rod clearance and packing seal for AGR (B) 1st stage compressor
(ongoing).
 Repair AGR unit (A) miscommunication between PLC and DCS monitor screen
(ongoing).
3. AGR (A, C & D) are running.

Engine No. Running Status Outlet Pressure (Mpa)


Average Flow Rate(m3/h)

PK-7402-A Running 10.92 3800


PK-7402-B Stopped - -
PK-7402-C Running 10.95 4224
PK-7402-D Running 10.93 6113
Total Flow Rate 14137

3.3 Jake H.P AGR:


Activities:-
1. HP units (A&B) stopped for maintenance due to malfunctions.
Engine No. Running Status Outlet Pressure (Mpa) Suction (Mpa) Average Rate(m3/hr)
PK7403-A Stopped - - -
PK7403-B Stopped - - -
Total Flow Rate -

4. Reclaim System and retention pond progress:-


1. Level at evaporation pond#1 approximately 85%.
2. Retention Pond oil Level approximately 10%.
3. Continue reclaim pump from evaporation pond.

5. Vehicles utilized:-
Truck Contractor Work description Remark

flatbed - Transferred 18 empty drums to OPEA

Steam truck - Cleaned OGM1

KEYI FPF :-
Site Personnel:

Name Company Position


Dayshift Personnel
Mohammed Osman P.E FPF Foreman
Eltahir Abdalla P.E FPF Operator
Samih Talha P.E FPF Operator
Nightshift Personnel
Mohamed Mahadi P.E FPF Foreman
Mohamed Ahmed P.E FPF Operator
1.1 Ahmed Hassan P.E FPF Operator
Ongoing Operations and Evaluation:
1.2 Day Activities:
1. Patrol check for all FPF equipment’s has been done.
2. Continue draining water from Storage Tank TK-6501-A&B.
3. Cooperated with DCS staff to repair level transmitter of open drain. (Finished).
4. Cooperated with mechanic staff to clean filter of recovery oil tank. (Finished).

1.3 .Tanks level:


Tank Number Level (m) Temp. (˚C)
TK-6501-A 9.1 72
TK-6501-B 7.7 57
Total Flow rate to CPF (m3/hr.) 48 m3/hr

1. Field:
2.1. Site Personnel:

Day shift Personnel


Name Company Position
Wail Abbas P.E Field Operator
Night shift Personnel
Name Company Position
Faiz Elsedig P.E Field Operator

Day Activities:
1. Routine check for all wells & OGMs has been done.
2. Checked status of ESDV’s for Gas lifting wells & OGMs.
3. Released casing pressure of K-N-9 & K-N-7.
4. Tested one well

Well name Fluid bbl./day


K-N-11 901

1. AGR:
3.1 Site Personnel:
Name Company Position
Day shift Personnel
Omer Mohammed Omer P.E AGR Operator
Abdalaziz Elnazir P.E AGR Operator
Night shift Personnel
3.2 Day
Mustafa Ahmed P.E AGR Operator
Activities:

1. Patrol check for engines, vessels and compressors has been done, monitor& record parameter.
2. Unit B is running normally.

3. Unit C Under maintenance.   


4. Unit A stopped.

1.1 Units Performance:

Engine No. Running Status Outlet Pressure (Mpa) AV-Flow rate (m3/hr.)
A Stopped - -
B Running 8.2 5425
C Under maintenance - -
Total Flow rate (m3/hr.) 5425
Remark

HADIDA FPF :-
Site Personnel:-

Name Company Position

Dayshift Personnel
Musa Abu Makeen P.E Operation Supervisor
Abusofyan Ali P.E FPF Foreman
Abubaker Hassan P.E CR Operator
Hosam Eldin Musa P.E FPF Operator
Abdalla Omer P.E FPF Operator
Abdelrahman Hamad P.E Field Operator

Nightshift Personnel
Ammar Mohamed P.E FPF Foreman
Basil Ahmed P.E CR Operator
Awad Ali P.E FPF Operator
Bilal Ali Altahir P.E FPF Operator

1.2 Ongoing Operations and Evaluation


1.3 Day shift Activities
FPF:
1. Patrol check for all production facilities has been done, monitor & record the
parameters.
2. Water injection pump running for 24hrs.
3. Centrifugal pump P-4501B running for 24hrs.
4. Screw pump P-4501C standby.
5. Cooperated with Flowmetec company & DCS staff to check and repair the flowmeter of
transitline(Finished).
6. Diverted transit line flow from bypass line to normal process line throw flow meter
(under observation).

Storage tank level A:5.95m. B:6.06m.

Transit line pressure 3231 Kpa


Average flow rate 75 m3/h

Field:

1. Patrol check for all production wells has been done.


2. Tested H3-2.
3. Checked shut-in wells facilities.

Mud Pump Activity

1. Patrol check has been done, monitor & record the parameter.
2. Received 3000 Lt of diesel.
3. Mud pumps- A running for 13 hrs & B standby.
Sufyan FPF
Site Personnel:-

Name Company Position


Dayshift Personnel
Hitham Omer P.E Operation Supervisor
Ahmed Osman Elzubeir P.E FPF Foreman
Mohamed Badr P.E FPF Operator
Hosam Alden Ahmed P.E C.R Operator
Elhadi Noureldin P.E FPF Operator
Nightshift Personnel
Mansour Eltoum P.E FPF Foreman
Ali Mohamed Ali P.E C.R Operator
1.2 Hassan Ibrahim P.E FPF Operator Ongoing
Operations
and Evaluation:
1.3 Day Shift Activities:
FPF:

1. Patrol check for all production facilities have been done, monitor & record the
parameters.
2. Fuel gas scrubber’s condensate, was drained several times.
3. One load of hot water was loaded from FPF to well site for flushing job.
4. Performed housekeeping inside EPF has been done.

1.4 Parameters:-

Storage tank level A:5.0m B: 5.0m


Transit line pressure 2648Kpa
Transit line temperature 70°C
Average flow rate 9.8m3/h

2.0 Field:
2.1 Field personnel:

Name Company Position


Dayshift Personnel

Tarig Mohamed Ali P.E Field Operator


Alshazli Abdalrahman P.E Field Operator
2.2 Activities:

1. Routine check for all production wells and OGMs has been done.
2. Sufyan-4 flow line flushed by hot water.
3. Restarted OGM-2 transfer pump at 09:00.
4. Sufyan-E1 increased the frequency from 5Hz to 7Hz at 80:30 and then to 9Hz
at 15:10.
5. Sufyan-W6 increased the frequency from 53Hz to 55Hz at 12:30.
6. Sufyan-W8 tested.
7. Sufyan-S2 stopped from 08:45 to 09:45 due to repair the stuffing box leak.
8. Commissionied of OGM-2 test separator (under evaluation).

2.3 OGM Pumps Parameters:-


Transfer Pump OGM-2 OGM-3 OGM-4
Suction Pressure (Mpa) 0.89 0.79 1.39
Discharge pressure (Mpa) 2.79 52.43 2.69
Differential Pressure (DP)(Mpa) N/A N/A 0.07
Temp.(°C) 41 42 50
Set point (Mpa) 0.9 0.8 1.4
Freq. (Hz) 10 35 40

You might also like