Professional Documents
Culture Documents
PRACTICE (MIP)
Volume-II
MIP contains engineering tools and concepts that have proven useful in
planning, constructing, maintaining and operating the irrigation infrastructure
successfully. The manual is not a text book but contains sufficient background
knowledge so as to act as single book of theory and practice.
It is hoped that MIP would be a rich source of knowledge and guidance for
irrigation engineers.
ASAD ULLAH
Secretary to Government of Punjab
Irrigation Department
ACKNOWLEDGMENT
Foremost, Project Management Office (PMO) - Punjab Barrages, wants to extend this
endeavor to Almighty ALLAH for the prudence bestowed upon us, in order to suffice
the standard of this revised Manual of Irrigation Practice (MIP).
It is pertinent to mention that the completion of this task was attainable owing to the
exemplary knowledge and arduous efforts of our renowned authors (Syed Mansoob
Ali Zaidi, Mr. Sajjad Hussain Naseem, Dr. Bagh Ali Shahid, Malik Ahmed Khan, Mr.
Muhammad Azam Chaudhry, Mr. Muhammad Ehsan, Mr. Ahmad Khan Bhatti, Mr.
Habibullah Bodla, Mr. Muhammad Shamshad Gohar, Mr. Ghulam Hussain Qadri and
Mr. Shafiq Ali).
Amjad Saeed
Head/Project Director
Project Management Office (PMO)
Punjab Barrages Rehabilitation &
Modernization Projects,
Punjab Irrigation Department,
Lahore
Special Commendation and Deepest Gratitude to
Chapter 2: River Training & Flood Management Syed Mansoob Ali Zaidi,
Ch. Muhammad Azam
SMALL DAMS
Table of Contents
1. INTRODUCTION ........................................................................................................... 1
1.1. General ................................................................................................................... 1
1.2. Limitations .............................................................................................................. 1
2. TYPE, SITE SELECTION AND HYDROLOGICAL STUDIES FOR A DAM .................... 4
2.1. Types of Dam ......................................................................................................... 4
2.1.1. Selection of Site For a Small Dam ....................................................................... 7
2.1.2. Site for a Concrete Gravity Dam ........................................................................ 10
2.1.3. Site for an Embankment Dam............................................................................ 11
2.2. Planning and Design of Small Dams ..................................................................... 11
2.2.1. Required Surveys, Investigations and Other Studies ......................................... 11
2.3. Hydrological Studies ............................................................................................. 25
2.3.1. Data Requirement ............................................................................................. 25
2.3.2. Sources of Data................................................................................................. 26
2.3.3. Collection of Data .............................................................................................. 26
2.3.4. Water Availability Assessment........................................................................... 28
2.3.5. Design Flood ..................................................................................................... 30
2.3.6. Flood Routing .................................................................................................... 33
2.3.7. Reservoir Operation .......................................................................................... 34
2.3.8. Sediment Yield .................................................................................................. 35
2.3.9. Height of Dam ................................................................................................... 36
3. DESIGN OF DAM AND SPILLWAY ............................................................................. 39
3.1. Design of Dam ...................................................................................................... 39
3.1.1. Concrete Gravity Dam ....................................................................................... 39
3.1.2. Embankment Dam ............................................................................................. 50
3.2. Design of Spillway................................................................................................. 61
3.2.1. Location of Spillway ........................................................................................... 61
3.2.2. Type of Spillways .............................................................................................. 61
4. CONSTRUCTION OF SMALL DAMS .......................................................................... 71
4.1. Construction of Small Dams .................................................................................. 71
4.1.1. Construction Planning ....................................................................................... 71
4.1.2. Stream Diversion ............................................................................................... 80
4.1.3. ABAD Mini Dam – Ponds Schemes ................................................................... 88
ii
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
List of Tables
TABLE 2-1 ICOLD POTENTIAL HAZARD CLASSIFICATION (PHC) ............................................................ 5
TABLE 2-2 ALLOWABLE CONTACT PRESSURE ON FRESH JOINTED ROCK ............................................... 17
TABLE 2-3 ENGINEERING USE CHART FOR COMPACTED SOILS............................................................. 20
TABLE 2-4 AMOUNT OF LABORATORY TESTING AND SELECTION PARAMETERS ...................................... 24
TABLE 2-5 SEDIMENT YIELD FOR VARIOUS CATCHMENTS IN THE POTHOHAR REGION ............................ 36
TABLE 3-1 STABILITY AND STRESS CRITERIA AND FACTOR OF SAFETY (FS) ......................................... 41
TABLE 3-2 PARAMETERS FOR CONCRETE DAM DESIGN FOR PRELIMINARY DESIGN................................ 42
TABLE 3-3 SUMMARY OF EMPIRICAL FORMULA PROPOSED FOR DETERMINATION OF WAVE HEIGHTS ...... 51
TABLE 3-4 FREEBOARD .................................................................................................................... 51
TABLE 3-5 SUMMARY OF TRIAXIAL TESTS........................................................................................... 54
TABLE 3-6 SUMMARY OF DESIGN CASE, MINIMUM SAFETY FACTORS, AND SHEAR TEST ......................... 54
TABLE 5-1 FREQUENCY OF READINGS FOR THE MONITORING INSTRUMENTS ........................................ 91
TABLE 5-2 ROUTINE VISUAL INSPECTION FOR SMALL DAMS: RECOMMENDED FREQUENCY ..................... 92
TABLE 5-3 FORMAL INSPECTION FOR SMALL DAMS FREQUENCIES ....................................................... 92
TABLE 5-4 MAINTENANCE SCHEDULE FOR SMALL DAMS ...................................................................... 93
TABLE 5-5 ASSIGNMENT OF RESPONSIBILITIES................................................................................... 96
iii
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
TABLE 6-1 CALCULATION OF CROP WATER REQUIREMENT FOR 1,000 ACRE OF MAIZE CROP GROWN IN
DISTRICT RAWALPINDI .................................................................................................................... 127
TABLE 6-2 DURATION OF GROWTH STAGES OF VARIOUS VEGETABLES AND CROPS AND THEIR
CORRESPONDENCE KC VALUES ....................................................................................................... 128
List of Figures
FIGURE 1-1: TYPICAL CONCEPTUAL LAYOUT PLAN OF SMALL DAM PROJECT .............................................. 2
FIGURE 2-1 ICOLD CLASSIFICATION OF SMALL AND LARGE DAMS .......................................................... 4
FIGURE 2-2 COMPONENTS OF ZONED EMBANKMENT .............................................................................. 7
FIGURE 2-3 TYPICAL DAM SITE IN THE VALLEY ....................................................................................... 7
FIGURE 2-4 TYPICAL LAYOUT OF DAM AND SPILLWAY ............................................................................. 8
FIGURE 2-5 PROPOSED INVESTIGATION AREA OF GRAVITY DAM ............................................................ 13
FIGURE 2-6 MINIMUM DRILLING FOR INVESTIGATION............................................................................. 16
FIGURE 2-7 SINGLE OR DOUBLE PACKER SYSTEM ................................................................................ 18
FIGURE 2-8 MATERIAL GRADING ENVELOPES ....................................................................................... 22
FIGURE 2-9 ISOHYETAL MAP OF THE POTHOHAR REGION...................................................................... 27
FIGURE 2-10 MEAN ANNUAL RAINFALL IN THE POTHOHAR REGION .......................................................... 27
FIGURE 2-11 HYDROLOGICAL ZONING OF THE POTHOHAR REGION ......................................................... 28
FIGURE 2-12 RAINFALL (INCHES) V/S DIRECT RUNOFF (INCHES) ............................................................. 29
FIGURE 2-13 HYDROGRAPH FOR 1000 YEAR RETURN PERIOD ................................................................ 32
FIGURE 2-14 FLOOD ROUTING FOR THE 1000 YEAR RETURN PERIOD OF DOMELI DAM ............................. 34
FIGURE 2-15 HFL AND NORMAL POOL LEVEL AGAINST TIME FOR DOMELI DAM ........................................ 34
FIGURE 2-16 RESERVOIR STORAGE ZONES OF A DAM ............................................................................ 36
FIGURE 2-17 TYPICAL FLOOD ROUTING OF SMALL DAM........................................................................... 38
FIGURE 3-1 DIFFERENT FORCES ACTING ON A CONCRETE GRAVITY DAM ............................................... 40
FIGURE 3-2 SAMPLE DRAWING OF EARTHEN DAM FOR ANALYSIS ........................................................... 56
FIGURE 3-3 END OF CONSTRUCTION DOWNSTREAM SLOPE STABILITY CHECK (WITHOUT SEISMIC LOAD) .. 58
FIGURE 3-4 END OF CONSTRUCTION UPSTREAM SLOPE STABILITY CHECK (WITHOUT SEISMIC LOAD) ....... 58
FIGURE 3-5 STEADY STATE SEEPAGE ANALYSIS................................................................................... 59
FIGURE 3-6 STEADY STATE DOWNSTREAM SLOPE STABILITY CHECK (WITH SEISMIC LOAD) ..................... 59
FIGURE 3-7 RAPID DRAWDOWN SEEPAGE ANALYSIS (WITH SEISMIC LOAD)............................................. 60
FIGURE 3-8 RAPID DRAWDOWN UPSTREAM SLOPE STABILITY CHECK (WITH SEISMIC LOAD)..................... 60
FIGURE 3-9 FORMATION OF HYDRAULIC JUMP (ENERGY DISSIPATION) ................................................... 63
FIGURE 3-10 HEIGHT OF JUMP ON HORIZONTAL FLOOR FOR BASIN I, II AND III ......................................... 64
FIGURE 3-11 TYPE II BASIN RECOMMENDED PROPORTIONS FOR CHUTE BLOCKS AND DENTATED SILL ....... 65
FIGURE 3-12 TYPE III BASIN RECOMMENDED PROPORTIONS FOR CHUTE BLOKS,...................................... 66
FIGURE 3-13 TYPE III BASIN HEIGHT OF BAFFLE PIERS AND END SILL ....................................................... 66
FIGURE 4-1 PRESENT PRACTICE IN SMALL DAMS CONSTRUCTION.......................................................... 83
FIGURE 4-2 TYPICAL INSTALLATION OF VERTICAL SLIDE GATE AT PIPE INLET .......................................... 84
FIGURE 4-3 TYPICAL INSTALLATION OF INCLINED SLIDE GATE................................................................ 84
FIGURE 4-4 TYPICAL INSTALLATION OF VERTICAL SLIDE GATE IN DROP INLET TOWER ............................. 85
FIGURE 4-5 TYPICAL INSTALLATION OF VERTICAL SLIDE GATE IN TOWER WITH DIVIDER ........................... 85
FIGURE 4-6 SHOWING METHOD OF COMPACTION AROUND THE PIPE ...................................................... 88
FIGURE 5-1 DAMAGES IN EMBANKMENT AND FOUNDATION.................................................................... 89
FIGURE 5-2 PROCEDURAL GUIDELINES FOR A DAM SAFETY PROGRAM ................................................... 90
FIGURE 5-3 SPECIMEN OF NOTIFICATION INFORMATION FLOW CHART .................................................... 98
FIGURE 5-4 DIAGRAM OF A TYPICAL STREAM GAUGE WITH STILLING WELL ........................................... 103
FIGURE 5-5 CURRENT-METER DISCHARGE MEASUREMENTS ............................................................... 105
FIGURE 5-6 THE CURRENT-METER METHOD....................................................................................... 106
FIGURE 5-7 EROSION OF PART OF A CHANNEL RESULTS ..................................................................... 107
FIGURE 5-8 EXAMPLE OF A TYPICAL STAGE-DISCHARGE RELATION ON RATING CURVE.......................... 108
FIGURE 6-1 FREEBOARD DIAGRAM .................................................................................................... 111
iv
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
FIGURE 6-2 TYPICAL SECTION OF PRCC PIPE ................................................................................... 116
FIGURE 6-3 MANUFACTURING PROCESS OF PRCC PIPE ................................................................... 117
FIGURE 6-4 HYDRAULIC SEAL ........................................................................................................... 122
v
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
1. INTRODUCTION
1.1. General
This manual is designed specifically for engineers involved in the siting, design and
construction of small dams in the various parts of the Punjab, Pakistan. Such dams
are suitable for supplying water to irrigation schemes, for rural and other water
supplies (when properly operated and maintained) and for conservation measures.
The manual is derived from the standard practices in design and construction in the
World over and has been prepared to provide practical and useful guidelines for siting,
designing and constructing small dams and their appurtenants. Thus, the manual
essentially provides a comprehensive and pragmatic means for the practical
understanding of the principles and procedures used in small dam construction and
for the users to safely and competently construct small dams without recourse to the
costly, complex and sophisticated design and construction techniques associated with
dams on larger catchments.
1.2. Limitations
This manual provides guidelines for Small Dams with negligible potential hazard of
Low ICOLD Classification PHC-I with regard to height, H, of dam and volume of water,
V, stored in the reservoir. These dams are built over competent foundations using
acceptable construction materials. For dams over questionable problematic soils and
with materials of inferior quality, opinion of dam expert must be obtained. Furthermore,
the users of these guidelines must refer to standard text books or manuals given under
selected bibliography of this manual for planning, detailed design and construction
(Appendix A). Appendix B presents photographs of a number of dams completed by
Small Dam Organization (SDO), Punjab Irrigation Department (ID).
2
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
➢ Practice in Pakistan
Small dams are planned, designed and constructed in Pakistan by the following
Authority / Organization / Agency:
Water and Power Development Authority (WAPDA, Pakistan)
Small Dams Organization Irrigation Department (IDs) of Punjab, KPK, Sindh
and Baluchistan provinces of Pakistan
Mini Dam–Ponds Schemes for rainwater harvesting by Agency for Barani
Areas Development (ABAD)
For Small Dams Design and Construction, USBR Small Dam Design revised
edition 1977 is a widely used reference for planning, design and construction of
small dams in Pakistan which imposes height (H) restriction of 15 m for small dams.
However, in Pakistan restriction on height of small is not observed and dams of
height, H, > 40 m have been designed and constructed as small dams.
▪ Hazard Classification of Dams
The ICOLD recommends the application of the PHC (Potential Hazard Classification)
presented in Table 2-1, together with the parameter, for a general classification of the
hazard potential rating of the small dams. Although the PHC method can be
considered as a useful method for assessing potential risk downstream, it is also
recommended to consider local and natural conditions of each dam, such as, its
structure, people, properties and environmental conditions downstream.
Table 2-1 ICOLD potential hazard classification (PHC)
PHC I II III
𝐻 2 . √𝑉 𝐻 2 . √𝑉 < 20 20 ≤ 𝐻 2 . √𝑉 < 200 𝐻 2 . √𝑉 ≥ 200
Life Safety Risk ~0 < 10 > 10
Economic Risk Low Moderate High or Extreme
Environment Risk Low or Moderate High Extreme
Social Disruption Low (Rural Area) Regional National
I) High Hazard Potential Dam (III): dam’s failure or mis-operation will probably
cause loss of human life (even if it is only one person);
II) Significant Hazard Potential Dam (II): no probable loss of human life but can
cause major economic loss, environmental damage, disruption of lifeline
facilities, or impose other concerns;
III) Low Hazard Potential Dam (I): no probable loss of human life and low economic
and/or environmental losses (losses mostly limited to owner’s property).
Regardless of classification system a country adopts, it is important that the
Regulation establishes a Risk Prioritization Criteria and based on this
6
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
It is necessary for economic feasibility that the bulk of material required for the dam is
available in the close vicinity of the dam site and materials excavated from the
appurtenants are used in the construction of the dam for economy.
ii. Water tightness of reservoir
The rim of the reservoir should be water tight up to the proposed elevation of the dam
crest and free from slides.
iii. Site for spillway
In the case of masonry or concrete dams it is not very important; however, in case of
an embankment dam, the spillways are to be located away from the dam shown in
Figure 2-4:
i. Topographic surveys
Topo-Surveys are important for the planning and design of all storage schemes. The
following surveys are generally required.
ii. Preliminary location survey
Some reconnaissance field work is necessary for the selection of preliminary design
of various component of the proposed project. Survey maps on scale of 1:50,000 and
20 meter contours are available from Survey of Pakistan (SOP). From these maps,
assessment of catchment area and location of command area and alignment of
channel are made. For project design following further survey will be required.
i. Dam site survey
Scale 1 in 500
Contour interval 0.5 m
ii. Reservoir survey
Scale 1 in 2000
Contour interval 1m
iii. Command area survey
Scale 1 in 2000
Contour interval 1m
iv. Strip survey along channel
alignment
Scale 1 in 1000
Contour Interval 0.5 m
v. Structure survey
Scale 1 in 200
Contour interval 0.5 m
iii. Control survey points
The purpose is to provide permanent and accessible Bench Marks (BM) to be used as
reference points throughout implementation period of the project. These BMs are to
be connected with the existing BMs of Survey of Pakistan (SOP) in the vicinity of the
project.
iv. Extent of survey
Once the axis of the dam is finalized; the dam site survey should extend as per limit
shown in Figure 2-5 for Concrete Dams. Similarly, reservoir survey should extend up
to highest flood level (HFL). In case of Embankment Dam, survey should extend 600
ft upstream and downstream of the dam axis. Spillway survey should cover approach
control structures, chute and discharge channel up to nallah bed downstream of the
13
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
dam axis. Once the reservoir survey is completed, area capacity curve may be drawn
easily by an experienced cad operator.
d1 3m Minimum
Below Rock Surface
Augering
Rotary Drilling
It is of two types:
Straight rotary
Reverse rotary
- Straight rotary
The Drilling fluid is pumped through the drilling rods and it returns through the
space between wall of the holes and drilling rods to the surface. This method can
be used for all type of formations.
- Reverse rotary
The drilling fluid is run through the space between walls of the hole and drilling
rods, then pumped out through the drilling rods under cutting. This method is used
for big size holes and in collapsable strata.
Rock quality description (RQD)
The ratio of the core length to the distance drilled, expressed as percentage is the core
recovery. RQD is a quantitative measure of the core lengths >10 cm. Descriptive terms
as per BS 5930 are following and their respective allowable contact pressure on fresh
jointed rock are given in the Table 2-2.
R.Q.D Term
0% to 25% Very poor
25% to 50% Poor
50% to 75% Fair
75% to 90% Good
90% to 100% Excellent
Table 2-2 Allowable contact pressure on fresh jointed rock
Allowable pressure
Rock quality R.Q.D
T sf Kn/m2
Excellent 90-100 200-300 20,000-30,000
Good 75-90 120-200 12,000-20,000
Fair 50-75 65-120 6500,-12000
Poor 25-50 30-65 3000-6500
Very Poor 0-25 10-30 1000-3000
0 <10 <1000
Murree, hill station, situated at North East direction has rainfall of 1766 mm.
27
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
2000
1800
1600
1400
Rainfall (mm)
1200
1000
800
600
400
200
0
Chakwal
Durabi
Murree
Cheart
Islamabad
Jhelum
Mianwali
Gujjar
Talagang
Chaklala
Khan
For the calculation of monthly rainfall in a particular area, isohyetal map (Figure 2-9)
of the average rainfall drawn from the rainfall data of Pakistan Meteorological
Department can be used. Jhelum station that lies in the vicinity of the Domeli
catchment has mean monthly data from 1954 to 2015.
Step 1: Synthesize rainfall data of Jhelum data
Step 2: Using Equation for Zone C, determine the direct runoff (monthly)
Step 3: Multiply direct runoff with catchment area to determine mean monthly runoff
for the dam site using following equation.
𝑊𝑎𝑡𝑒𝑟 𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑖𝑙𝑖𝑡𝑦 𝑎𝑡 𝑑𝑎𝑚𝑠 𝑠𝑖𝑡𝑒 𝑖𝑛 𝐴𝑐𝑟𝑒 𝐹𝑒𝑒𝑡
𝑀𝑜𝑛𝑡ℎ𝑙𝑦 𝑟𝑢𝑛𝑜𝑓𝑓 𝑖𝑛 𝑚𝑚 𝑎𝑠 𝑝𝑒𝑟 𝑒𝑞𝑢𝑎𝑡𝑖𝑜𝑛 3
= ( ∗ 𝐴𝑟𝑒𝑎 𝑜𝑓 𝑐𝑎𝑡𝑐ℎ𝑚𝑒𝑛𝑡 𝑖𝑛 𝐾𝑚2 ∗ 1000 ∗ 0.0008107)
1000
If daily rainfall data is available, it is recommended to use US Soil Conservation
Service (US SCS) method to validate empirical method of water availability.
ii. US soil conservation service (US SCS)
The Soil Conservation Service (SCS) has developed a widely used curve–number
procedure for the estimation of runoff. The effects of land use and treatment, and thus
infiltration, are included. The procedure was developed empirically from studies of
small agricultural watersheds.
The SCS procedure consists of selecting a storm and computing the direct runoff by
the use of curves founded on field studies of the amount of measured runoff from
numerous soil cover combinations. A runoff curve number (CN) is extracted from the
table Runoff Curve Numbers for Hydrologic Soil-Cover Complexes (Antecedent
moisture condition AMC-II) [2].
Selection of Curve Number (CN)
where
Tc = Time of Concentration in hours
L = Length of longest water channel in mm
H = Elevation Difference between highest elevation and at dam site in
mm
Estimation of time to peak
The time to peak (Tp) is the time from the start of rising of hydrograph to the peak rate,
in hours. The Tp is calculated using the following equation:
D
Tp = + 0.6Tc
2
where
Tp = Time to peak, in hours
D = Duration of excess rainfall, in hours
Tc = Time of concentration, in hours
Estimation of Direct Runoff
The direct runoff generated from the rainfall data is calculated as follows
1000
𝐶𝑢𝑟𝑣𝑒 𝑁𝑜 𝐶𝑁 =
10 + 𝑆
where
CN = Curve No. selected based on the antecedent storm conditions
S = Maximum potential difference between rainfall P and direct runoff
Q, in inches
Q=
(P − 0.2S )2
P + 0.8S
where
Q = Direct runoff, in inches
P= Storm rainfall, in inches
Estimation of peak rate of flow for unit rate hydrograph
The peak rate of flow for unit rate hydrograph is calculated as:
484 A
qp =
Tp
where
qp =Peak discharge, in cfs
A =Drainage area, in sq. miles
Q =Total runoff, in inches
Tp =Time to Peak
32
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Unit hydrograph
The dimensionless hydrograph of Victor Mockus [3] was used to determine unit
hydrograph of each hydrological unit. This requires knowledge of unit storm duration,
time to peak and peak discharge of the unit hydrograph. Knowing peak discharge and
time to peak of the unit hydrograph, complete unit hydrograph was obtained by
multiplying time ratios and discharge ratios of the dimensionless hydrograph with time
to peak and peak discharge of the unit hydrograph, respectively.
Synthesis of flood hydrograph
The magnitude and distribution of rainfall are obtained for the design storm. The hourly
rainfall distribution used for further calculations. The runoff is redistributed according
to intervals of D-hours assuming that intensity of rainfall within D-hour to be uniform.
Cumulative and incremental precipitations are calculated from the redistributed pattern
considering the losses obtained by the adopted curve number. Incremental
precipitation is multiplied by the ordinates of unit hydrograph for each increment. All
such hydrographs are plotted with their order and place on the time axis and their
ordinates at the same time are summed up to get flood hydrograph. Figure 2-11 show
the unit hydrograph of Domeli dam using for 1000 year return period.
60000
50000
40000
Discharge (cusecs)
30000
20000
10000
0
0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00
Time (hrs)
Figure 2-13 Hydrograph for 1000 year return period
Hydrological Modelling System Model developed by Hydrologic Engineering Centre
(HEC-HMS) is very efficient and user friendly model that can be used for the rainfall
runoff modelling. This is freely available and can be downloaded from
http://www.hec.usace.army.mil/software/hec-hms/.
33
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
50,000
45,000
Inflow
40,000
35,000 Outflow
Discharge (Cusecs)
30,000
25,000
20,000
15,000
10,000
5,000
0
0 10 20 30 40 50
Time (hr)
Figure 2-14 Flood Routing for the 1000 year return period of Domeli dam
1193.00
1191.00
1189.00
1187.00
HFL
1185.00
Level (ft)
1179.00
1177.00
1175.00
0 5 10 15 20 25 30 35 40 45 50
Time (hrs)
Figure 2-15 HFL and Normal pool level against time for Domeli dam
2.3.7. Reservoir Operation
A reservoir operation and simulation study is carried out to determine the water
releases after storing the water for small dams. The aim of small dams are to store the
35
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
water during flood period and regulate it during low flow period during a year and on
long-term basis to meet the irrigation requirements.
➢ Water demand
Based on the agricultural survey, command area for the project is determined.
Computation of crop water requirements for irrigated crops is fundamental in designing
an irrigation system and scheduling of irrigation. The pattern of crop water use
determines the capacities of distribution system and storage capacity of dams. This
information is also needed in determining the volume of water required to meet
monthly and seasonal requirements for fields, farms and the project area as a whole.
The crop water requirements of various crops grown in the project area are calculated
by using Crop Coefficient Approach. According to this approach, crop evapo
transpiration (ETc) is calculated by multiplying the reference crop evapotranspiration
(ETo) by the crop coefficient (Kc).
ETc = KcETo
where
ETc = Crops evapotranspiration (mm/day)
Kc = Crop coefficient (unit less)
ETo= Reference evapotranspiration (mm/day)
➢ Irrigation releases
Several computer models such as Design Reservoir, HEC ResSim, can be used to
simulate reservoir operation to determine irrigation releases for the monthly or ten–
day basis. These models have proven capability to provide assessment of the probality
of failure at various demands levels.
2.3.8. Sediment Yield
The total amount of eroded material that is transported by water from catchment to a
downstream control point, such as a reservoir, is known as the sediment yield.
Sediment yield can be estimated by correlating observed sediment loads and water
discharge.
Sediment data is collected by Surface Water Hydrology Project, SWHP, WAPDA for
the adjoining catchment areas in the Pothohar region. Sediment record for 4 gauging
stations (Table 2-3) is available from where sediment yield per sq mile can be
estimated in the Pothohar region.
36
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Table 2-5 Sediment yield for various catchments in the Pothohar region
Mean
Mean
Catchmen Data annual
annual
Sr. t area record sediment
River Station runoff
No. yield
(ac-ft/sq- (ac-ft/sq-
(sq-mile) Years
mile) mile)
Siran
1 Phulra 408 36 1218.1 3.9
RIver
Haro
2 Garlia 1180 37 583.9 2.7
River
Haro
3 Khanpur 300 32 733.3 3.1
River
Soan Dhok
4 2500 42 444 5.17
River Pathan
2.3.9. Height of Dam
Note different reservoir storage zones of a dam to select its height shown in Figure
2-14.
are done backward to arrive at certain level in the reservoir which would be required
to bring the entire command area under flow irrigation.
The maximum level from above calculated gives the DSL.
(ii) Normal reservoir level (NPL)
Following are steps to set NPL:
1. Decide cropping pattern.
2. Calculate crop water requirement per 1,000 acres.
3. Determine total availability of water (refer Hydrology Section).
4. Simulate reservoir operation by using computer model (refer Hydrology
Section Reservoir Operation).
5. Work out different options by considering different command areas and
select live storage with permissible water shortages.
6. Once live storage is selected, corresponding level from storage capacity
curve, give the required NPL.
(iii)Flood routing
Data required
‒ The inflow hydrograph (refer Hydrology Section)
‒ Storage elevation curve for the reservoir (from contour survey of reservoir)
‒ Outflow elevation curve (from spillway rating curve)
Carryout flood routing by using the latest computer programme ([3] or Spread Sheet
Model) and draw inflow hydrograph and routed flood hydrograph corresponding level
from storage elevation curve. A typical flood routing of small dam is shown in Figure
2-15. This would give HFL.
38
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Discharge cusecs
Hours
Figure 2-17 Typical flood routing of small dam
(iv)Freeboard
Calculate freeboard by considering the factors explained in section freebaord Page
3-44 to page 3-46.
Add freeboard to HFL as calculated above to decide top of dam.
References
1. Small Dams, Design, Surveillance and Rehabilitation - PETITS BARRAGES
Conception, Surveillance et Réhabilitation, 2011
2. Theory and design of irrigation structure, Vol.-II, canal and storage works, 1993 by
R.L Gupta
3. Source: USBR Earth Manual
4. Stephens, T. (2010). Manual on small earth dams: a guide to siting, design and
construction (No. 64). Food and Agriculture Organization of the United Nations
(FAO).
5. Hyundai Engg. Co. Ltd., Design Manual for Small Dams – Geotechnical Field
Investigations
6. Design Manual Volume 1 Hydrology and Hydraulics for small dams projects
Hyundai Engineering co. Ltd. Korea, 1990
7. "Hydrology," Suppl. A to sec. 4, Engineering Handbook, U.S. Department of
Agriculture, Soil Conservation Service, 1968.
8. Scharffenberg, W. A., & Fleming, M. J. (2006). Hydrologic Modeling System HEC-
HMS: User's Manual. US Army Corps of Engineers, Hydrologic Engineering
Center.
39
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Figures 3-1 show the position and direction of the various forces acting on a concrete
gravity dam. Forces like temperature stresses and wind pressure are not shown. Ice
pressures being uncommon in Pakistan context have been omitted.
Loading combination
Designs should be based on the most adverse combination of probable load
conditions, but should include only those loads having reasonable probability of
simultaneous occurrence. Combinations of transitory loads, each of which has only
remote probability of occurrence at any given time, have negligible probability of
simultaneous occurrence and should not be considered as a reasonable basis for
design. Temperature loadings should be included when applicable.
Gravity dams should be designed for the appropriate loading combinations which
follow, using the safety factors prescribed in next sections.
Usual loading combination
Normal design reservoir elevation, with appropriate dead loads, uplift, silt, ice, and
tailwater. If temperature loads are applicable, use minimum usual temperatures.
Unusual loading combinations
Maximum design reservoir elevation, with appropriate dead loads, uplift, silt, minimum
temperatures occurring at that time if applicable, and tailwater.
Extreme loading combination
Normal design reservoir elevation, with appropriate dead loads, uplift, silt, ice, usual
minimum temperatures if applicable, and tailwater, plus the effects of the Earthquake.
Table 3-1 lists the stability and stress criteria and factor of safety for various loading
combinations.
Table 3-1 Stability and stress criteria and factor of safety (FS)
Resultant Foundation Concrete stress
Load Minimum
location bearing
condition sliding FS Compressive Tensile
at base pressure
Usual Middle 1/3 2.0 < allowable 0.3 f'c 0
Unusual Middle ½ 1.7 < allowable 0.5 f'c ′ 2/3
0.6 𝑓𝑐
Extreme Within 1.3 < 1.33 x 0.9 f'c ′ 2/3
0.5 𝑓𝑐
Base allowable
Note: f'c is 1-year unconfined compressive strength of concrete. The sliding factors of
safety (FS) are based on a comprehensive field investigation and testing program.
Concrete allowable stresses are for static loading conditions. Source EM 1110-2-2200.
• Properties of concrete
The specific properties of concrete used in the design of concrete gravity dams include
the unit weight, compressive, tensile, and shear strengths, modulus of elasticity, creep,
Poisson’s ratio, coefficient of thermal expansion, thermal conductivity, specific heat,
and diffusivity. These same properties are also important in the design of RCC dams.
Investigations have generally indicated RCC will exhibit properties equivalent to those
42
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
of conventional concrete. Values of the above properties that are to be used by the
designer in the reconnaissance and feasibility design phases of the project are
available in ACI 207.1R-87 or other existing sources of information on similar materials
(see Table 3-2). Follow-on laboratory testing and field investigations should provide
the values necessary in the final design. Temperature control and mix design are
covered in EM 1110-2-2000 and EM 1110-2-2006.
Table 3-2 Parameters for concrete dam design for preliminary design
Applicable ASTM
Description of properties Unit and value
standard
• Concrete
- Unit Weight (𝛾𝑐) 24 KN/m3
ASTM C39, ASTM C172
- Strength 14 MPa (mm)
and ASTM C31
Tensile (𝑓𝑡) 2.3 (𝑓 ′ 𝑐)2/3 ASTM C496
Shear (𝑓𝑠) 10% (𝑓 ′ 𝑐)
ASTM C 78 (Modulus of
- Modulus of Elasticity (E)
Rupture test)
- Creep ASTM C512
- Poisson’s Ratio (µ) ASTM C469
• Water
Unit weight (𝛾𝑤) for water
9.8 KN/m3
pressure competent
• Soil
Moist Unit Weight ((𝛾𝑠 ) 19.5 KN/m3
• Rock Foundation Unite ASTM D7012, ASTM
24 KN/m3
Weight (𝜸) D2113
• Silt
- For Horizontal Load 13.6 KN/m3
- For Vertical Load 19.25 KN/m3
PGA, from Seismic
From seismic map of
• Seismic Loads of Pakistan (OBE,
Pakistan
MCE)
For actual detailed design, these parameters must be established through field and /
or laboratory testing
43
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Overturning check
FOS = Resistive Moment / Overturning Moment = Mr / Mo
MR / Mo = 1.86 >1.5 OK
Sliding check
Factor of safety against sliding = µ*ΣV/ΣH
422.1
ΣV = kip/ft
9
233.9
ΣH = kip/ft
3
µ*ΣV/ΣH = 1.35 >1 OK
Overturning Check
FOS = Resistive Moment / Overturning Moment = Mr / Mo
Mr / Mo = 1.63 >1.5 OK
Sliding Check
Factor of safety against sliding = µ*ΣV/ΣH
ΣV = 389.43 kip/ft
ΣH = 254.99 kip/ft
µ*ΣV/ΣH = 1.15 >1 OK
Shear Friction Factor = (µ*ΣV+Bq)/ΣH
(µ*ΣV+Bq)/ΣH = 9.17 >2.7 OK
Compressive stresses
Calculation of Stresses
e = B/2 -x̄
x̄ = ΣM/ΣV
ΣM= 11048.4 kip-ft/ft
ΣV = 389.43 kip/ft
x̄ = 28.37 Note: resultant at a distance x̄ from toe
e = B/2 -x̄ 6.63
Overturning check
FOS = Resistive Moment / Overturning Moment = Mr / Mo
Mr / Mo = 1.54 >1.5 OK
48
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Sliding check
Factor of safety against sliding = µ*ΣV/ΣH
ΣV = 422.19 kip/ft
ΣH = 295.80 kip/ft
Compressive stresses
Calculation of stresses
e = B/2 -x̄
x̄ = ΣM/ΣV
ΣM= 9983.2 kip-ft/ft
ΣV = 422.19 kip/ft
x̄ = 23.65 Note: resultant at a distance x̄ from toe
Overturning check
FOS = Resistive Moment / Overturning Moment = Mr / Mo
Mr / Mo = 6.11 >1.5 OK
Sliding check
Factor of safety against sliding = µ*ΣV/ΣH
ΣV = 618.75 kip/ft
ΣH = 61.88 kip/ft
µ*ΣV/ΣH = 7.50 >1 OK
Shear Friction Factor = (µ*ΣV+Bq)/ΣH
(µ*ΣV+Bq)/ΣH = 40.57 >4 OK
Compressive stresses
Calculation of Stresses
e = B/2 -x̄
x̄ = ΣM/ΣV
12284.
ΣM= kip-ft/ft
4
ΣV = 618.75 kip/ft
Note: resultant at a distance x̄ from
x̄ = 19.85
heel
e = B/2 -x̄ 15.15
Normal compressive stress @ heel
Pmax = ΣV/B(1+6e/B) 20.32 kip/ft2 <26.6 OK
Allowable stresses 33% higher than for normal loading case
Normal compressive stress @ toe
Pmin = ΣV/B(1-6e/B) -2.64 kip/ft2
50
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Camber is ordinarily provided along the crest of earthfill dams to ensure that the
freeboard will not be diminished by foundation settlement or embankment
consolidation. It is based on the amount of foundation settlement and embankment
consolidation expected for a particular dam.
For dams on relatively non-compressible foundations, cambers of about 1 percent of
the height are commonly provided. Straight-line equations should be used to vary the
amount of camber and to make it roughly proportional to the height of the
embankment.
• Crest width
The crest width is, as a rule, determined empirically and largely by precedent. The
following formula is suggested for the determination of crest width for small earthfill
dams.
𝑧
𝑊 = + 10
5
where
W = width of crest in feet, and
z = height of dam in feet above the stream–bed
For ease of construction with power equipment, the minimum width should not be less
than 12 feet.
• Filter and drains
A material selected for the protective filter has to satisfy four main requirements as
follows:
(1) The filter materials should be more pervious than the base material in order that
there will be no hydraulic pressure buildup to disrupt the filter and adjacent
structures.
(2) The voids of the inplace filter material must be small enough to prevent base
material particles from penetrating the filter and causing clogging and failure of the
protective filter system.
(3) The layer of the protective filter must be sufficiently thick to provide a good
distribution of all particle sizes throughout the filter and also to provide adequate
insulation for the base material where frost action is involved.
(4) Filter material particles must be prevented from movement into the drainage pipes
by providing sufficiently small slot openings or perforations, or additional coarser
filter zone if necessary.
The following limits are recommended to satisfy filter stability criteria and to provide
ample increase in permeability between base and filter. These criteria are satisfactory
for use with filters of either natural sand and gravel or crushed rock and for filter
gradations which are either "uniform" or "graded":
53
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
𝐷15 𝑜𝑓 𝑡ℎ𝑒 𝑓𝑖𝑙𝑡𝑒𝑟
(1) 𝐷 = 5 𝑡𝑜 40, Provided that the filter does not contain more than
15 𝑜𝑓 𝑏𝑎𝑠𝑒 𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙
5 percent of material finer than 0.074 mm. (no. 200 sieve)
𝐷15 𝑜𝑓 𝑡ℎ𝑒 𝑓𝑖𝑙𝑡𝑒𝑟
(2) 𝐷 = 5 𝑜𝑟 𝑙𝑒𝑠𝑠
85 𝑜𝑓 𝑏𝑎𝑠𝑒 𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙
𝐷 𝑜𝑓 𝑡ℎ𝑒 𝑓𝑖𝑙𝑡𝑒𝑟
(3) 𝑀𝑎𝑥𝑖𝑚𝑢𝑚85𝑜𝑝𝑒𝑛𝑖𝑛𝑔 𝑜𝑓 𝑝𝑖𝑝𝑒 𝑑𝑟𝑎𝑖𝑛 = 2 𝑜𝑟 𝑚𝑜𝑟𝑒
(4) The grain size curve of the filter should be roughly parallel to that of the base
material.
If more than one filter layer is required, the same criteria are followed; the finer filter is
considered as the ''base material'' for selection of the gradation of the coarser filter.
In addition to the above criteria, the following requirements for graded filters should be
met:
(1) The filter material should pass the 3-inch screen for minimizing particle segregation
and bridging during placement. Smaller maximum particle sizes may be specified.
Also, filters must not have more than 5 percent minus No. 200 particles to prevent
excessive movement of fines in the filter and into drainage pipes causing clogging.
(2) The gradation curves of the filter and the base material should approximately
parallel in the range of finer sizes, because the stability and proper function of
protective filters depend upon skewness of the gradation curve of the filter toward
the fine, giving a support to the fines in the base material.
(3) The filter material adjacent to the drainage pipe should have sufficient coarse sizes
to prevent movement of filter material into the drainage pipe. The maximum size
of perforations or openings of the drainage pipe is selected as one-half of the 85-
percent grain size of the filter material.
Although normally specified, the following guides are given for filter construction:
(1) The subgrade before filter placement should be firm and, if necessary, be lightly
tamped or rolled.
(2) Clean filter material should have sufficient water content (3 to 10 percent) during
placement, and the placement method should be such that segregation is
prevented.
(3) Thin filters are usually firmly compacted with light flat rollers, or are tamped to a
firm condition. Unless otherwise specified, thick filters are compacted to 70 percent
relative density in a manner similar to free-draining sand-gravel backfill to prevent
settlement.
(4) The filter layers for coarse filter material (3-inch maximum size) are usually not less
than 8 inches in thickness, and layers of finer filter material are often 6-inch
minimum thickness. However, for severe field conditions such as high head,
variations in base material, or filter gradations which are near the extreme coarse
54
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
limit, the minimum thickness of 8 inches may be specified. For zoned filters these
minimum thicknesses may be specified and are maintained for each layer.
(5) Where drainage pipe is used in a filter system, the capacity of the pipe should be
sufficient to collect the seepage water and to conduct it to a place of discharge.
(6) While the pipe is being laid, the openings are often protected from inflow of fines
of the filter material by burlap or other suitable permeable material.
• Selection of shear parameter
The selection of shear parameter to be tested meeting site conditions is normally
based on specific test methods. A summary and explanation are given in Table 3-5.
Table 3-5 Summary of triaxial tests
Test method Application in stability analysis
UU Test represents end of construction condition
(Undrained, for core zones. Also applicable to impervious
Unconsolidated) foundations where consolidation is slow in
also known as quick test “Q” comparison with rate of earthfill placement.
CU (Consolidated, Test represents behaviour of impervious or
Undrained) semi-pervious materials of embankments or
also known as Rapid test “R” foundations which consolidated during
construction and which were exposed to stress
change during sudden draw down conditions.
Test also used to analyse stationary conditions
in downstream slope.
CD (Consolidated, Test applicable to impervious and semi-
Drained) pervious soils with hydrostatic pore pressures,
also known as Slow test “S” before or after shear, under slow increase in
load is revealed. Also used to evaluate shear
values under setting out conditions where
excess hydrostatic pressure during the life of
the dam is determined.
• Minimum safety factors against slip circle failures
A summary of recommended minimum safety factors, shear test and application is
shown in Table 3-6.
Table 3-6 Summary of design case, minimum safety factors, and shear test
Minimum
Shear Applicable to slope of
Design case safety
test embankment
factor
UU or CD Upstream & downstream
End of construction 1, 3
* slopes
Sudden draw from full Upstream slope of full
1, 2 CU or CD
supply level section
55
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Minimum
Shear Applicable to slope of
Design case safety
test embankment
factor
Normal operation 1, 5 CD Downstream slope
Seismic forces, (cases
1, 1 Both slopes
above)
* In zones where no significant hydrostatic pore pressures are expected, use strengths
as determined in CD test.
Note: Effective stresses are to be used.
• Slope stability analysis of earthen dam
Introduction to Geostudio (Slope W, Seep W)
GeoStudio is a product suite for geotechnical and geo-environmental modeling, broad
enough to handle all your modeling needs.
Slope/W
SLOPE/W is the leading slope stability CAD software product for computing the factor
of safety of earth and rock slopes. SLOPE/W can effectively analyze both simple and
complex problems for a variety of slip surface shapes, pore-water pressure conditions,
soil properties, analysis methods and loading conditions.
Seep/W
SEEP/W is a finite element CAD software product for analyzing groundwater seepage
and excess pore-water pressure dissipation problems within porous materials such as
soil and rock. Its comprehensive formulation allows you to consider analyses ranging
from simple, saturated steady-state problems to sophisticated, saturated/unsaturated
time-dependent problems. SEEP/W can be applied to the analysis and design of
geotechnical, civil, hydrogeological, and mining engineering projects.
Procedure
Basically there are four major steps for the computation of results:-
1. To create a project
2. Defining a Stability Model
3. Designate properties and Boundary Conditions
4. Solve Manager and Viewing the analysis results.
Step 1: To create a project
For example to run analysis for slope stability or seepage, we will go to new project to
create new project for slope stability.
Step 2: Defining a stability model
56
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
• Hydraulic conductivity, K
• Volume of compressibility, Mv
Stability Analysis Conditions
End of Construction - Unconsolidated Un-Drained (UU) test
Steady State - Consolidated Drained (CD) test
Draw down - Consolidated Drained (CD) test
Factor of safety
Refer Table 3-6 Summary of design case, minimum safety factors and shear test.
Sample example
End of construction downstream slope stability check (Figure 3-3)
Materials assumed
Drain
Model: Mohr-Coulomb
Unit Weight: 130 pcf
Cohesion: 0 psf
Phi: 30°
Core
Model: Mohr-Coulomb
Unit Weight: 120 pcf
Cohesion: 630 psf
Phi: 0°
Shell material
Model: Mohr-Coulomb
Unit Weight: 115 pcf
Cohesion: 75 psf
Phi: 22°
Foundation
Model: Mohr-Coulomb
Unit Weight: 120 pcf
Cohesion: 105 psf
Phi: 32°
Critical Slip Surface
Sr. Radius
Number FOS Center (ft) Entry (ft) Exit (ft)
# (ft)
(5.044, (17.6068, (2.53316,
1 218 2.295 16.109
18.084) 8) 2.17184)
58
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Figure 3-3 End of construction downstream slope stability check (without seismic load)
Similarly other cases like steady state (with or without seismic load) and Rapid draw
down (with or without seismic load) can be analyzed by following the above procedure.
Their final output Figures 3-4 to 3-8 are given below.
Figure 3-4 End of construction upstream slope stability check (without seismic load)
59
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Figure 3-6 Steady state downstream slope stability check (with seismic load)
60
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Figure 3-8 Rapid drawdown upstream slope stability check (with seismic load)
61
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
minimize head loss through the channel. A greater approach depth with the
accompanying reduction in approach velocity will result in large discharge coefficient
and shorter crest length for a given discharge.
o Discharge over the spillway
The discharge over spillway crest is determined from the following formula
𝑄 = 𝐶 𝐿𝑒 𝐻𝑒1.5
where
C = Coefficient of discharge
Le = Effective length of spillway
He = total specific emergency load above the crest
o Chute section
The chute section extend from the control section to the terminal structure. Steepest
slope may be adopted depending on site condition to minimize cutting. Generally chute
slopes range from 3H : 1V to 4H : 1V and have given satisfactory hydraulic
performance in completed small dams.
Terminal structure / stilling basin
Terminal structures are used to safely pass the spillway discharge into the outlet
channel/ main river channel. Typical types used in chute spillways are: a hydraulic-
jump stilling basin, a flip bucket, and plunge pool combination. Downstream of the
terminal structure, riprap is ordinarily provided to prevent scour and erosion of the
outlet channel.
For design of basin, the following steps are followed:
Discharge intensity in the basin is calculated by unit discharge, q = Q/W, where Q is
the design discharge and W is the selected width of the basin.
Then head Z from surcharge upstream water level to stilling basin floor level is
calculated, which is equal to E1 i.e., the actual energy level at stilling basin. This is
given by the equation and shown in Figure 3-9.
E1 = D1+ C/D1^2
where
C = q2/2g
D1 = water depth entering the basin
E1 should become equal to Z by iteration of D1 values.
Velocity entering the basin V1 is calculated as q/D1.
63
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Figure 3-10 Height of jump on horizontal floor for basin I, II and III
Source: USBR, 1987
ii) Factors in design of stilling basin
Several parameters govern the design calculations of stilling basin, such as
a. Nature of foundation,
b. Approach Froude number,
c. Impact angle of flow with respect to stilling basin floor,
d. Tailwater level and
e. Economical considerations.
iii) Types of basin
Type II and Type III basin are generally adopted for spillway design. Type II basin is
adopted for high dams, earth dam spillways and large canal structures while type III is
a short basin adopted for canal structures, small outlet works, and small spillways.
Type II and III basin may be used for Froude numbers greater than 4.5. Selection
criteria for a basin depend on the flow velocities entering the basin and the unit
discharge.
Type II
This stilling basin is for spillways up to 200 ft high and for flows up to 500 cfs. per foot
of basin width and velocities greater than 60 fps, provided the jet entering the basin
has reasonably uniform velocity and depth as shown in Figure 3-11.
65
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Figure 3-11 Type II basin recommended proportions for chute blocks and
dentated sill
Source: USBR, 1987
Chute Blocks
Spacing, width and height, D1 = water depth entering the basin
Side space = 0.5D1
Dentated sill
Height of dentate sill, h2 = 0.2 D2 = 0.2 * downstream conjugate depth (height of jump)
Width w2 and spacing s2 = 0.15 D2
Top width = 0.02 D2
Type III
This basin is developed for a class of smaller structures in which velocities at the
entrance to the basin are moderate or low (up to 50-60 feet per second) and
discharges per foot of width are less than 200 cfs.
The energy dissipation arrangement includes chute blocks, baffle piers and end sill.
Their size and spacing are given in Figure 3-12.
66
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Figure 3-12 Type III basin recommended proportions for chute bloks,
baffle piers and end sill
Source: USBR, 1987
Chute blocks
Spacing s1, width w1, height h1= D1= depth entering the basin
Side spacing = 0.5 D1
Baffle pier
Distance from chute block= 0.8D2
The height of baffle pier and end sill may be calculated by obtaining h 3/D1 and h4/D1
against Froude no. from Figure 3-13.
Figure 3-13 Type III basin height of baffle piers and end sill
Source: USBR, 1987
67
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Additionally, Weight of concrete floor and anchorage to the rock, if provided, shall be
designed to withstand uplift and dynamic pressures with ample factor of safety to take
care of limitations in accurate evaluation of such pressures.
The relief wells shall be connected to a grid of drains under the energy dissipators.
The grid of drains shall be connected below the energy dissipators to lead water into
sumps generally provided below the energy dissipators and/or on backsides of the
end training walls. Water is pumped out from sumps for its disposal from suitable
locations above the maximum tailwater level.
The spacing of drain/relief holes may vary from 3 to 10 m (9.84 to 32.81 ft) in both
directions and their depth may vary from 20 to 40 percent of tail water depth when no
other supporting data is available.
The drains holes are usually of 75-100 mm (3 to 4 inches) diameter. They shall be
drilled after completion of the foundation grouting in their vicinity, if any, to avoid their
clogging.
Design example:
Design an ogee type spillway with crest at 1470 ft. amsl and design discharge
of 8755 cusecs, clear width at crest equal to 100 ft and width at basin equal to
80 ft with elevation of stilling basin at 1331 ft. amsl. The tail channel has invert
of 1336 ft. aml with bed slope of 1:1000.
Solution:
Discharge over spillway
Design Discharge required 549 cfs
Spillway crest level EL. 2023.00 ft amsl
head at crest ( by trial /
ho 3.918 ft
assumption)
Clear width of spillway W 15.50 ft
Approach 2020.75 ft amsl
P 2.25 ft
P/Ho 0.50
Discharge coefficient, C0 3.8
Stilling basin Elevation EL. 2001.00 ft amsl
Discharge intensity q = Q/W
q 35.42 cusecs / ft
Approach velocity Va = q/(P+ho)
Va 5.74 ft/sec
Head due to approach velocity ha =q2/2g(P+ho )2
ha 0.512 ft
Maximum Surcharge Level EL. 2027.43 ft amsl
Ho 4.4296 ft
Discharge passing Q=CLHo3/2 549.1 cusec
Ho/2 2.21
69
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
ha/Ho 0.1156
Stilling Basin
width of basin W 15.50 ft
Discharge intensity in basin q 35.42 cusecs / ft
Distance from surcharge water
Z 26.43 ft
level to stilling basin
Ho/2 2.21
Velocity at Entrance to basin V1 39.48 fps
Depth of flow entering basin D1 0.897 ft
Froude No. F 7.35
Subsequent Depth
D2/D1 = 1/2*((1+8 F2)0.5-1)
Depth of flow in stilling Basin D2 8.88 ft
water surface elevation in stilling
EL. 2009.88 ft amsl
Basin
Minimum tail water depth Ref fig 11.
T.W.D/D1 8.10
Peterka
T.W.D 7.27 ft
Tail channel invert 2003.65 ft amsl
water depth at start of channel 6.23 ft
Ref fig 12.
L/D2 2.60
Peterka
Length of Cistern L 23.10 ft
Type III basin
Chute blocks Spacing s1= D1 0.897 ft
width w1, height h1 0.897 ft
0.5d1, side space 0.449 ft
Baffle pier
0.8D2 ,Distance
7.107 ft
from chute block
h3/D1 1.800 Ref fig 18.
Peterka
h3, height of baffle
1.615 ft
pier
0.2h3, top width 0.323 ft
0.75h3, width w3
1.211 ft
and spacing s3
0.375h3, side
0.606 ft
space
End sill
Ref fig 18.
h4/D1 1.40
Peterka
h4, height of end
1.26 ft
sill
70
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
The sizing of the tail channel should be such that it passes a discharge of 549 cusecs
at a water depth of 6.23 ft.
The width of the basin is 15.5 ft, so the tail channel is also taken as 15.5 ft wide.
Longitudinal slope is given as 1:500. The side slope cutting depends on the rock type.
In this case it is taken as 1 vertical 0.5 horizontal, z = 0.5.
Flow area is calculated as:
A = 6.23 (15.5 + 6.23 x 0.5) = 115.97 ft2
Wetted perimeter is calculated as
P = 15.5 + 2 x 6.23 (1+0.5)0.5 = 29.43 ft
𝐴 115.97
Hydraulic Radius = 𝑅 = = = 3.94 𝑓𝑡
𝑃 29.43
1.486 1 1/2
𝑉 = 0.035 (3.94)2/3 (500) = 4.74 𝑓𝑡/𝑠 (n = .035, roughness coefficient depends on
the rock / soil type)
Q = V.A
= 4.74 x 115.97
= 549.40 cusecs
Hence the channel section selected can safely pass a discharge of 549 cusecs.
References:
1. Module 4, Hydraulic Structures for Flow Diversion and Storage, Version 2 CE IIT,
Kharagpur
2. MANUAL-EM, E. N. G. I. N. E. E. R. "1110-2-2200. 30 June 1995." US Army Corps.
of Engineers. ENGINEERING AND DESIGN. Gravity Dam Design.
3. Manual, Engineers. "EM 1110-2-2000 Standard practice for concrete for civil works
structures, Department of the army." US Army Corps of Engineers, Washington,
DC (1994): 20314-1000.
4. Concrete, Mass. "ACI 207.1 R. 87." ACI Manual of Concrete Practice, Part I,
American Concrete Institute, Detroit, MI (1993).
5. Hyundai Engg. Co. Ltd. Korea, Design Mnaula for Small Dams
i. Fill Dam
ii. Concrete Gravity Dam
iii. Hydrology and Hydraulics
6. Design of Small Dams, United States Department of the Interior. Bureau of
Reclamation (USBR).
7. Design of Concrete Gravity Dam, USBR.
8. Hydraulic Design of Stilling Basin and Energy Dissipation by AJ Peterka.
9. Hydraulic Energy Dissipators by Ed ward A. Elevatorski.
10. Federal Emergency Management Agency (FEMA), 2005.
11. Earth and Earth Rock Dams by James L. Sherar
71
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
a) Foundation cutoff:
Sometime it is necessary to provide a cutoff trench. The cutoff is constructed of
impervious material and is generally located near the centerline of the dam. Ideally the
cutoff should extend to an impervious layer in the foundation, either soil or rock. Cutoff
trenches prevent excessive seepage from moving under the dam, by lengthening the
seepage path.
Care must be taken not to place cutoff trenches on untreated fractured bedrock, as
material in the trench could be piped into the fractures or exposed to high erosive
water force.
If the dam is located on permeable soils, it is necessary to provide a cutoff trench that
extends down to a low permeability layer. The cutoff should extend the full width of the
dam, including to above the normal water line in each abutment.
Caution: If a cutoff to bedrock or to an impervious soil layer cannot be achieved, there
is a good chance the reservoir will have seepage problems, perhaps even to the extent
where the reservoir will not hold water at all. This is very common. There are several
creative solutions to dealing with this situation. If you suspect this may be the case
with your dam, it is highly recommended that you consult an experienced dam
hydraulic engineer.
b) Fill placement - compaction
Two variables that greatly influence the embankment fill density are the compactive
effort (i.e., degree of compaction, DC) and the moisture content (Optimum Moisture
Content, OMC). Both are described below.
Compaction: Compaction is the process of mechanically increasing the density of the
soil. By increasing the density, the strength of the soil is dramatically increased. A well-
compacted soil is less likely to settle. Earth embankments are constructed in layers,
commonly referred to as lifts. Dense, well-compacted lifts paramount to having a safe
dam. Compaction can be enhanced by increasing the weight of the roller on the soil,
by increasing the number of passes, or by decreasing the thickness of each lift as it is
added to the embankment. The maximum diameter of stone or cobble allowed in
compacted fill is generally limited to about 75 percent of the thickness of the
compacted layer.
Proper compaction at the contact between the embankment, abutments, outlet pipes,
and concrete structures is important. It is generally recommended that thin lifts using
hand-operated tampers or hand operated vibratory plate compaction be used in these
situations. The fill is commonly compacted to a maximum compacted lift thickness of
4 inches. To improve bonding of lifts, scarify the compacted surface with a roto-tiller
or similar tool.
When the material that is being compacted is impervious. It should be as fine-grained
as practicable. The soil must be plastic enough to penetrate all irregularities and form
a well-bonded seal. The moisture content is often increased slightly to produce more
74
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
plasticity in these areas. The plasticity of the contact zone of soil is sometimes
increased by mixing bentonite with the available impermeable soil.
Caution: If compacting around plastic pipes, be careful that rocks are removed. Rocks
can easily damage plastic pipes. Rocks with a diameter greater than 1 inch must be
removed within 6 inches of the pipe.
Fill placement – optimum moisture content (OMC): Moisture is vital to proper
compaction. Moisture acts as a lubricant within the soil, sliding the particles together.
Too little moisture means inadequate compaction, too much moisture leaves water-
filled voids that weakens the soil.
The water content at maximum soil density is termed as Optimum Moisture Content
(OMC). Generally, it is recommended to have soils either at optimum moisture content
or slightly above optimum. Soils compacted substantially drier than optimum water
content may settle upon saturation. Settlements can cause embankment cracking, and
even failure. Soils compacted substantially wet of optimum will be weak and non-
supportable.
For pervious material, the need for water control during compaction depends on grain
size. If the pervious material is gravel, no water-content control is necessary. If the
material is sand or contains significant proportion of sand sizes, the material should
be maintained in as saturated a condition as possible during rolling. The effect of
insufficient water in pervious sand causes the sand to “bulk” which will results on low
strength and density when it dries up. Soils that have “bulked” might also tend to settle
upon saturation.
Dry soils are treated by sprinkling water on the soil after it has been spread, but before
it is compacted. The soil must then be worked to thoroughly blend the added water
into the soil. This is typically accomplished by disking with a disk plow or by blading
the material back and forth with a grader. If water is retained in pockets of wet soil,
very poor compaction will result. The coarser and less plastic the soil, the more easily
water can be added and worked into it uniformly.
Note-1: For clays, sometimes it is impossible to get a uniform moisture distribution by
adding water on the fill as it is placed. Pre-wetting of borrow materials will result in
more uniform moisture distribution and may be more economical. If the soil is being
processed through a screening plant to remove oversize cobbles, a considerable
quantity of water can be blended into the soil by sprinkling at that time.
Note-2: The design of an embankment is strongly influenced by the natural water
content of borrow materials. While natural water content can be decreased to some
extent, some borrow soils are so wet they cannot be used in an embankment unless
slopes are flattened. Excessively moist impervious soils may be unusable as
embankment fill, and reducing moisture content would be impractical because of
anticipated rainfall during construction. The cost of using drier material requiring a
longer haul should be compared with the cost of using wetter materials and flatter
slopes. It is generally easier to add water to dry soil than to reduce the water content
of wet soil.
75
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
• Field density tests are performed on compacted layer using ASTM D1556 or
other ASTM D standard methods suitable to site conditions.
• Compute Degree of Compaction (DC) and moisture content. DC ≥ 95% and
Moisture Content should be ± 2 OMC of ASTM D698 or ASTM F1557 whichever
is applicable.
2. Hand methods
• Lightly hammering a piece of rebar into newly compacted fill can tell you a lot.
3. Keeping track of passes
• Generally 8 to 10 passes are necessary to get adequate compaction.
(i) Foundation preparation and treatments
Before you begin to construct your embankment, attention must be given to the
foundations. A properly prepared foundation is critical to the safety and long life of the
embankment. First you must do an assessment of the foundation materials. What soils
are present in the foundation? How thick are soil layers? How deep is bedrock? This
can be easily done by examining a test pit dug with a backhoe.
Caution: Gravels and sands make a poor embankment foundation. Gravels are highly
permeable and could allow excessive seepage, which could in turn lead to
embankment or dam failure or inability to hold water. Do not build your embankment
or dam on gravels.
Preparation of a soil foundation
• Scarification: loosen soils to ensure that the engineered fill bonds well with the
underlying soils (usually to a depth of 6 inches).
o During the scarification process it is not unusual for large rocks and cobbles
to be brought to the surface. Any material larger than 6 inches in diameter
should be removed before the placement of fill material.
• Apply adequate moisture, so that a good bond is made.
• Smooth and lessen the angle of abutment slopes.
o It is difficult to compact fill against slopes steeper than 2:1. Poor compaction
can cause a seepage path to develop.
o Steep abutment slopes can cause cracking of the embankment fill.
Preparation of a rock foundation
• Remove loose material.
• Seal fractures with an overlay of dental concrete.
Caution: Failure to properly seal bedrock fractures has been the cause of many
embankment or dam failures! Embankment material can easily be piped into open rock
fractures! If you encounter rock or porous soils in the foundation, an experienced dam
engineer should be consulted.
77
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
• Permeable soils, on the other hand, easily transmit water, and are often used
in filter and drains. Sands and gravels are considered to be pervious. Note that
the addition of only 10% clay or silt can render sand impervious and
dramatically effect performance. Thus, it is very important during construction
to keep pervious and impervious soils separate.
Outlet foundation preparation
• The outlet conduit (pipe) trench should be excavated from the intake location in
the reservoir basin to the downstream toe of embankment, preferably through
the abutments in natural formation.
• Make sure bottoms and sides of trench are firm and well compacted.
• The bottom of the trench should be at least 6 inches below bottom of the pipe,
and there should be a minimum of 6 inches of space between the pipe and
sides of the trench.
• trench sides should be sloped 2:1 (horizontal: vertical) to facilitate compaction
(the trench walls provide lateral containment so that all energy of compaction
is directed to compaction rather than moving the material laterally).
• a hand compactor must be used to compact around outlet pipes. most hand
compactors have shoes that are at least 1 foot wide. the trench must be sized
to accommodate this.
(ii) Filter and drains for seepage control
Soil particles can be transported out of the dam through a concentrated leak. This is
known as piping. Piping proceeds very slowly and can go unnoticed for years. Finally,
at some point, enough material has been moved, and the surrounding soil caves in.
The surface manifestation of such as “cave in” is called a sinkhole. Sinkholes are a
sign that failure of the dam could be imminent.
Piping is one of the leading causes of dam and embankment failures. The key to the
prevention of piping is to install a proper filtering system that prevents the movement
of soil within the embankment and foundation. A dam filter is similar to a coffee filter:
water is allowed through, but soil particles are not.
Seepage can be safely controlled using filters and drains:
• Filters are designed to protect embankment soils from being carried away.
• Drains are designed to carry water away from the embankment, keeping the
soils as dry as possible.
• Both filters and drains must be comprised of very pervious soils (clean sands
and gravels).
• Often it is necessary to use both.
• It is important to make sure that the grain size of the filter material is compatible
with the grain size of the embankment. As the size of the embankment material
decreases, the grain size of the filter should also decrease.
79
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
• Gravel has very high permeability and works well as a drain material. However,
gravel is generally too large to be placed directly next to clay soils. If a very
coarse-grained soil is placed directly next to a fine-grained soil, piping could
result.
In most cases, filter and drain material will be a processed material purchased from
an aggregate supplier. Pit run borrow is usually too dirty.
Caution: The above material criteria can perform well in many situations. However,
the drain and filter criteria must be satisfied and must be consulted.
The free water surface through a dam is referred to as the phreatic surface. Below the
phreatic surface, the embankment soils are saturated. Above the phreatic surface, the
embankment soils may contain some moisture, but are not fully saturated.
In many cases, water can move safely through the dam and foundation for years.
Seepage becomes a problem when:
• The downstream embankment face becomes excessively saturated.
• Concentrated leaks develop in the embankment or foundation.
Excessive saturation of the embankment can lead to instability and slope failure.
Because soil becomes more prone to failure when saturated, as the phreatic surface
rises, the dam can become less stable.
(iii)Surface protection
Embankment surfaces must be protected from surface erosion. Upstream slope
protection usually consists of rip-rap. Downstream slope protection is typically native
grass cover 9 inch gravel over the surface.
Upstream slope protection
Protects against:
• Wind
• Wave erosion
• Weathering
• Ice damage
• Potential damage from floating debris
Downstream slope protection
Protects against:
• Surface runoff
• Wind erosion
Caution: Excessive upstream face erosion can seriously threaten the dam by
shortening the crest width. A dam with a narrow crest is much more susceptible to
failure from overtopping or slope instability.
80
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Cofferdams are often constructed in two stages: first, a small diversion cofferdam is
constructed upstream of the main embankment, and then the main cofferdam is
constructed. It is preferable to make cofferdam a permanent part of the fill.
Cofferdam design
Major cofferdams are those cellular or embankment cofferdams, which, upon failure
would cause major damage downstream and/or considerable damage to the
permanent work. Minor cofferdams are those which would result in only minor flooding
of the construction site. All major cofferdams should be planned, designed, and
constructed to the same level of engineering competency as that for main dams.
Design considerations should include minimum required top elevation, hydrologic
records, hydrographic and topographic information, subsurface exploration, slope
protection, seepage control, stability and settlement analyses, and sources of
construction materials. The rate of construction and fill placement must be such as to
prevent overtopping during initial closure of the cofferdam. Minor cofferdams can be
the responsibility of the contractor. Excavations for permanent structures should be
made so as not to undermine the cofferdam foundation or lead to instability.
Adequate space should be provided between the cofferdam and structural excavation
to accommodate remedial work, such as berms, toe buttresses, and foundation
anchors should they be necessary.
Protection of embankment
Where hydrologic conditions require, emergency outlets should be provided to avoid
possible overtopping of the incomplete embankment by floods that exceed the
capacity of the outlet works. As the dam is raised, the probability of overtopping
gradually decreases as a result of increased discharge capacity and reservoir storage.
Should overtopping occur, however, damage to the partially completed structure and
to downstream property increases with increased embankment heights. It is prudent
to provide emergency outlets by leaving gaps or low areas in the concrete spillway or
gate structure, or in the embankment during winter. Excavation of portions of the
spillway approach and discharge channels, combined with maintaining low concrete
weir sections, may provide protection for the later phases of embankments
construction during which the potential damage is the greatest.
When a portion of the embankment is constructed before diversion of the river,
temporary riprap or other erosion protection may be required for the toe of the
embankment adjacent to the channel. This temporary protection must be removed
before placement of fill for the closure section.
In some cases the cost of providing sufficient flow capacity to avoid overtopping
becomes excessive, and it is more appropriate to provide protection for possible
overflow during high water conditions. In this case, special provisions such as
anchoring into rockfill should be considered.
82
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Closure section
Where the valley is wide, it is advisable to leave part of the embankment for flood
diversion. This would need special attention as explained below:
Because closure sections of earth dams are usually short in length and are rapidly
brought to grade, two problems are inherent in their construction. First, the
development of high excess pore-water pressures in the foundation and/or
embankment is accentuated, and second, transverse cracks may develop at the
juncture of the closure section with adjacent already constructed embankment as a
result of differential settlement. When the construction schedule permits, excess pore-
water pressures in the embankment may be minimized by providing inclined drainage
layers adjacent to the impervious core and by placing gently sloping drainage layers
at vertical intervals within semi-impervious random zones. However, acceleration of
foundation consolidation by means of sand blankets and vertical sand drains or
reduction of embankment pore pressure by stage construction is generally
impracticable in a closure section. A more suitable procedure is to use flatter
slopes or stabilizing berms. Cracking because of differential settlement may be
minimized by making the end slopes of previously completed embankment sections
no steeper than 1 vertical on 4 horizontal. The soil on the end slopes of previously
completed embankment sections should be cut back to well-compacted material that
has not been affected by wetting, drying, or frost action. It may be desirable to place
core material at higher water contents than elsewhere to ensure a more plastic
material which can adjust without cracking, but the closure section design must then
consider the effects of increased pore-water pressures within the fill. The stability of
temporary end slopes of embankment sections should be checked.
Control services
i. Intake and outlet structure
For small dams, a gate is almost always the device of choice to control flow through
outlet pipes. Using a valve is generally not recommended. However, current small
dams are fitted with a sluice valve in intake tower to control flow through the conduit
(Figure 4-1).
A valve is a device used to control flow in a conduit and that permanently obstructs
the waterway. Valves are constructed so that the closing member remains in the
passage way for all operating conditions.
83
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Figure 4-4 Typical installation of vertical slide gate in drop inlet tower
Gate in tower on dam crest or inside the reservoir (Figure 4-5) [preferable
choice]
• Very reliable configuration, if installed correctly.
• Provides ease of access for operation and repair.
• Is less susceptible to ice damage.
• The “divider” can have slot for stop logs.
• Obtaining adequate compaction of the supporting and surrounding soils is
critical to prevent settlement.
• Tower points must be completely water-tight as well to prevent seepage.
• In many cases, there is no divider and the gate is simply located on the
upstream end of the tower.
Figure 4-5 Typical installation of vertical slide gate in tower with divider
86
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Note: Your best resource for assistance in what kind of gate system to use may be
your local pipe and steel company. They stock many different kinds of gates and will
help you find the right equipment for your application. They often also provide
installation instructions as well.
ii. Pipes / conduits
From the tower water is carried through pipe to downstream of the dam. In general,
there are two (2) types of pipes that are used in small dams, corrugated or concrete.
Each is briefly discussed below
Corrugated metal
In low water depths, simple corrugated metal pipe (CMP) with watertight bands may
be sufficient.
Some of the advantages are:
• Low cost.
• Wide variety of available sizes.
• Widespread local availability.
Some of the disadvantages are:
• Improper installation can lead to seepage.
• Subject to corrosion.
o Outside coating is scratched, as often happens during installation.
o Depends on the quality of water that passes through the pipe. High alkaline
water can wreak havoc on any metal within a pipe or conduit system.
o Internal inspection cannot detect extent of corrosion damage (corrodes from
outside-in).
• Subject to abrasion from sand, silt, and rocks.
• Short design life.
• Easy to be damaged during installation.
In some cases, corrugated metal has lasted 50 years, and while in others it has lasted
less than 10. Consideration should be given to adding a protective coating.
Many dams have failed due to water flowing along the outside of a conduit. Recent
example is of Lehri Dam, built by Small dams Organization, that is non-functional, with
the operation stopped due to safety hazard. Adequate compaction around the pipe is
key (refer to
Figure 4-6).
Concrete
Concrete pipes designed and constructed according to (ASTM C361) are used
extensively.
Some of the advantages are:
• Available in a wide variety of sizes.
87
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
ii) Objectives
The objective of a safety program comprise of short and long term-measures, as
explained below:
i) assessing the condition of the dam and its components
ii) conducting preliminary and detailed inspections
iii) identifying repairs and continued maintenance needs
iv) establishing periodic and continuous monitoring over the long-term
v) establishing an emergency action plan to minimize adverse impacts should the
dam fail
vi) establishing operations procedures which recognize dam failure hazards and
risks
vii) documenting the safety program so that the information developed is available
at times of need and can be readily updated
iii) Dam safety plans
Following plans are required:
a) Instrumentation and monitoring plan
b) Operation and maintenance (O&M) plan
c) Emergency preparedness plan (EPP) or emergency action plan (EAP)
Figure 5-2 presents a procedure guidelines for dam safety.
Further detail of (a) through (c) above are discussed in the following sections:
iv) Instrumentation and monitoring
Typical monitoring instrumentation at dams include:
• Weirs, flumes, pipes, and other appurtenances means to measure seepage flow
or leakage, gauges and discharge measurement devices to record reservoir
inflow and outflows.
• Monitoring wells to measure water levels, and piezometers to measure pore
pressures within the embankment and/or foundation,
• Survey monuments to measure horizontal and vertical movements,
• Staff gauges to measure reservoir levels,
• Flumes, weirs, and/or gauges to measure reservoir inflow and/or outflow.
• A raingauge to measure precipitation.
v) Calendar and assignment of responsibilities
• Calendar
Frequency of recording reading of the monitoring instruments, frequency of
inspection and operation & maintenance (O&M) are discussed in Table 5-1.
Table 5-1 Frequency of readings for the monitoring instruments
First
Parameter Construction First year of
reservoir operation
measured period operation
filling
Every 2 6 Months to
Settlements Monthly Weekly
Months Yearly
Uplift Pressure Weekly 3 per week Weekly Fortnightly
Pore Water
Weekly 3 per week Weekly Fortnightly
Pressure
Leakage - Daily 2 per Week Weekly
vi) Inspections
A proper inspection program should involve the following four types of inspections:
i) Routine, informal inspections
ii) Annual safety inspections (Formal inspections)
iii) 5-year Periodic Inspections (Formal inspections)
iv) Special Inspections (Emergency inspections)
Routine inspections
Frequency of inspection are as follows (Table 5-2):
92
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
first responders in the event of a dam failure resulting from a natural event (such as a
big storm or earthquake), from an accident or from a manmade event (e.g. sabotage).
Table 5-5 presents Assignment of responsibilities and Figure 5-3 presents the
specimen of notification information flow chart. Appendix D includes the specimen
forms for monitoring, recording, inspection forms and inspection checklist.
Table 5-5 Assignment of responsibilities
Type of inspection Responsible person
Informal routine inspection Assist Engineer and an experienced
inspector
Formal inspection
- Annual inspection Dam safety Engineer alongwith SDO*
XEN, Assistant Engineer and Inspector
- 5 years periodic inspection Dam safety specialist / expert alongwith
dam Design Engineer, SDO XEN,
Assistant Engineer and Inspector
Special emergency inspection Dam Safety Expert alongwith his team
and XEN, SDO with his team.
* Small Dam Organization
Emergency action plan (EAP)
(1) General
The EAP is a useful tool intended to minimize the impacts of a dam failure or
malfunction, on the population living downstream.
Initially the EAP was applied to medium and large dams. But nowadays it is also
applied to small dams as a consequence of the large number of such structures.
The dam safety and security of people, property and environment downstream of
dams is the responsibility of the Government, who must legislate and enforce the rules
through administrative agencies, departments and offices.
(2) Methodology for developing EAP
The process of developing an EAP for a small dam generally consisting of following
steps:
• Determine the potential inundated area downstream in case of a dam failure.
Two scenarios are to be considered: inundation at maximum probable flood
through the spillway without dam failure, and inundation with dam failure.
• Prepare inundation maps.
• Determine and identify the situations and events that could initiate an
emergency action and specify the corresponding actions to be taken and by
whom.
• Identify all entities, jurisdictions, agencies and individuals, who will be involved
in the emergency actions. Coordinate the development of the EAP with all
relevant parties.
97
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
DAM 1
After the following reservoir of
the situation and request that a EMERGENCY Note:
coordinated draft begin for each CONDITION This is only a sample notification Chart.
downstream reservoir to prepare The order of notification on the flowchart
for passing flows. should be prioritized. Alternate means of
communications should be included in
the flowchart as appropriate.
Sub-Engineer
CE (2)
AC: Assistant Commissioner Development (2) District Disaster
CE: Chief Engineer Irrigation Management
DCO: District Coordination Officer
DG: Director General
PID: Punjab Irrigation Department
PD: Project Director
(3)
SDO: Sub Divisional Officer Secretary PID (3)
XEN: Executive Engineer
ACs
Note:
Owners of all small dams, mini dams and other services built and / or planned on a stream (i.e. cascade dam
Owners) must inform SDO so that necessary safety measures are ensured in case of Failure of any dam in
cascade.
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
________________________
DOWNSTREAM NOTIFICATION: (list all downstream people business which may be
affected by potential flood water) i.e. Utilities (oil, gas, etc.) Railway, Hydro,
Municipalities, Regional District.
Name: _________________ Location: ___________________ Phone#: _________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
________________________________________________________
Official Contacts
Local Police / RCMP Office: Phone #:
__________________________ __________
Local Radio Station: Phone #:
_________________________________ __________
Local Highway Office: Phone #:
_______________________________ __________
Local Highway Contractor: Phone #:
___________________________ __________
Regional Dam Safety Officer: Phone #:
_________________________ __________
Home # :
__________
Water Management Branch (alternate): Phone #:
__________________ __________
Home # :
__________
Regional P.E.P. Officer: Phone #:
_____________________________ __________
(Provincial Emergency Program) Home # :
__________
102
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Subsection
In each subsection:
Width
Velocity
Depth Area = Depth
Discharge x Width
= Area x Velocity
of stage. The discharge measurements are made at most stream gauges every 6 to 8 weeks,
ensuring that the range of stage and flows at the stream gauge are measured regularly.
Special effort is made to measure extremely high and low stages and flows because these
measurements occur less frequently. An example of a stage-discharge relation is shown in
(see Figure 5-7).
(iv)Hydraulic gradient
A value of 1V : 6H is adopted for hydraulic gradient. It however depends on the type
of soil. An additional earth cover in the form of pushta should be provided where the
hydraulic gradient line is not contained within the channel embankment.
(v) Planning, design and construction of inverted syphon
Introduction
Syphons or inverted syphons are used to convey water across a natural depression
under a road or under a canal.
Syphons are usually made of circular concrete pipe, PVC or steel pipe.
Syphons may have a straight lateral alignment, or may have changes in direction.
When going across a depression, syphons should be completely buried, usually with
a minimum of about 1 meter cover.
Syphons can be problematic with sediment laden water because sediment may tend
to deposit at the low points.
Sometime gravel and rock can enter the syphon especially in rainy season.
Trashracks / screens should always be provided at the inlet.
Blow off structures
A blow off structure is a valved outlet on top or side of the pipe at a low point in syphon.
These structures are used to help drain the syphon in an emergency for routine
maintenance and to periodically remove sediment from the pipe.
Sluice valves of adequate capacity could be used for blow off structure.
Type of pipes
Precast reinforced cement concrete (RCC) pressure pipes, prestressed reinforced
cement concrete (PRCC) pipes, welded steel pipes and pipes of other materials are
used where required in conveyance system depending upon the site requirements and
flow condition i.e. whether under gravity or under pressure.
RCC pressure pipes
RCC pipes for Hydraulic head up to 125 ft can be used if manufactured as per ASTM
C-361 standards. The diameter, wall thickness, compressive strength of the concrete
and the area of circumferential reinforcement shall be as prescribed for the classes of
combined hydrostatic head and external loading given in Table 1 of ASTM C-361 (copy
of Table 1 upto 42"ϕ pipe are attached as Appendix E). However, this Table may be
used conservatively for Hydraulic heads upto 100 ft.
The ASTM standard lays down standards for Hydrostatic testing of pipes, jointing and
rubber gasket requirements which must be ensured by proper testing and inspection
before installation at site.
113
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
PRCC pipe
When the hydrostatic head exceeds 100 ft PRCC pipe may be used. The design
requirements along with design example are given below. The manufacturing process
is also explained therein step wise to ensure quality control. The pipes should be
manufactured in a factory suitably equipped with testing arrangement, under strict
quality control and following proper manufacturing process.
Example:
Design requirements
1. Concrete
a) Concrete Strength
Requirements
i) Minimum compressive 5800 Psi
strength (28 days strength
on 6" cubes)
ii) Minimum strength at the 2175 Psi or two times the initial longitudinal
time of release of prestress, which-ever is greater
longitudinal tensioned
wires
iii) Minimum strength at the 3625 Psi
time of circumferential
prestressing
b) Core Thickness Minimum core (wall) thickness of pipes:
Requirements For Pipes upto 1.5' dia = 1.5"
For 2.0' dia pipe = 1.75"
For 3.0' dia pipe = 2.25"
For 4.0' dia pipe = 2.75"
For 5.0' dia pipe = 3.25"
For 6.0' dia pipe = 4.0"
c) Cover Coating Over ➢ Minimum thickness
Circumferential Prestressing i) Mortar coating = 3/4"
Wires ii) Concrete Coating = 1"
➢ Compressive Strength = 5000 Psi
➢ Application = Preferably within
16 hours of
winding
➢ Water Curing = 7 days Minimum
2. Prestressing Steel Wires
a) Ultimate Tensile Strength Generally 235,000 - 250,000 Psi
b) Wire Dia Generally 3 mm ̴ 4 mm
c) Spacing
i) Longitudinal prestressing Not greater than 6" or twice the core
wires thickness, whichever is greater
ii) Circumferential Clear spacing not less than ¼" and not
prestressing wires greater than 2"
114
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Design example
Design of prestressed reinforced cement concrete (PRCC) pipes
Data
Pipe Internal Dia = 42 inches (3.50 ft)
Wall Thickness = 3.0 inches (0.25 ft)
Head of Water = 50 ft
High Tensile Steel Wire:
Wire Dia = 3 mm
X-Section Area of Wire = 7.0686 mm2 or 0.011 in2
Ultimate Tensile Strength (UTS) = 235000 psi
Modulous of Elasticity (Es) = 29 x 106 psi
Maximum Initial Strress (ƒsi) = 65 % of UTS = 152750 psi
Concrete:
28 days cube strength = 5800 psi
Calculations:
Hydraulic Pressure = 50 x 62.4
= 3120 lbs/ft2
Hoop tension / one foot length of pipe
= ½ x 3120 x (3.50 + 0.25)
= 5850 lbs / ft length of pipe
5850 1
Hoop stress = 0.25 x 144
= 162.5 psi
Residual compression under working load after all losses of prestress = 145 psi
(minimum required).
Prestress required before losses = 162.5 + 145 = 307.5 psi
100
Initial prestress required (assuming 20% losses) = (307.5) x 100 −20 = 384 psi (ƒci)
Prestress losses:
i) Elastic deformation of concrete = 3.2 ƒci = 3.2 x 384 = 1229 psi
ii) Relaxation of wire = 0.16 ƒsi = 0.16 x
152750 = 24440 psi
iii) Deformation due to creep = 2.5 ƒci = 2.5 x 384 = 960 psi
iv) Deformation due to shrinkage = 0.0001 Es = 0.0001 x 29 x 106 =
2900 psi
Total Losses = 29529 psi
or 19.33 % of ƒsi
Therefore losses Assumed as 20% of initial wire stress are O.K.
115
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Initial prestressing force required / one foot length of pipe = 384 x 3 x 12 = 13824 lbs
13824
Area of prestressing steel required / one foot length of pipe = 152750 = 0.0905 in2
Required Spacing or pitch of 3 mm wire for circumferential prestressing
12 𝑥 0.011
= 0.0905 = 1.4586 in, or 37 mm
Longitudinal Prestress:
It may be conservatively taken as 40% of the initial prestress
Area of prestressing steel required / one foot length along circumference
= 0.0905 x 0.4 = 0.0362 in2
12 0.011
Required spacing along the Circumference = 0.0362 = 3.64 in, or 92 mm
Manufacturing Process of PRCC Pipes
The process of Manufacturing Prestressed Concrete Pipe consists of the following
steps, illustrated diagrammatically in the Figures 6-2 and 6-3.
1. Longitudinal Prestressing
Longitudinal wires of specified diameter and length are placed between two end
rings of the mould assembly, and stretched to the required tension.
2. Batching & Mixing of Concrete
Required quantity of aggregates, cement and water are mixed to produce high
strength concrete.
3. Spinning
Concrete is fed into the mould and is compacted by centrifugal spinning process to
produce a high strength concrete core pipe.
4. Demoulding
The tension in the longitudinal wires is released, making longitudinal pre-
compression to the core pipe and then the core pipe is taken out of the mould.
5. Core
The core pipe is put in sprinkler yard until the concrete in the core pipe has attained
adequate strength to withstand circumferential prestressing load.
6. Winding
The core pipe is wrapped with high tensile wire at pre-determined pitch and tension
to induce the desired pre-compression in the body of the core pipe.
7. Coating
The steel wrapping is covered with a dense cement mortar coat. This coat creates
and maintains a high alkaline environment around the prestressing wire and protects
it from corrosion.
8. Curing
The completed pipe is cured until it attains the desired strength.
116
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
9. Hydrostatic Testing
Each and every pipe is subjected to hydrostatic pressure test in the factory before
dispatch.
The wall thickness of steel pipe is affected by a number of factors including the
following:
1. Internal pressure
a. Maximum design pressure
b. Surge or water-hammer pressure
2. External pressure
a. Trench loading pressure
b. Earth-fill pressure
3. Special physical loadings
4. Practical requirements
The thickness selected should be that which satisfies the most severe requirement.
When designing for internal pressure, the minimum thickness of a cylinder should be
selected to limit the circumferential tension stress to a certain level, This stress is
frequently termed hoop stress. The internal pressure used in design should be that to
which the pipe may be subjected during its lifetime. In a transmission pipeline, the
pressure is measured by the distance between the pipe centerline and the hydraulic
grade line. Surge or water-hammer pressure must also be considered.
With pressure determined, the wall thickness is found using the Equation.
𝑝𝑑
𝑡=
2𝑠
Where:
t = minimum specified wall thickness (in.)
p = pressure (psi)
d = outside diameter of pipe (in.) steel cylinder (not including coatings)
s = allowable stress (psi).
Tension Stress and Yield Strength
The allowable working stress for steel is equal to 50 percent of the specified minimum
yield strength which is often accepted for steel water pipe. With the use of given
methods of stress analysis and proper quality control measures, these allowable
design stresses are considered conservative for the usual water-transmission
pipelines.
119
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Corrosion Allowance
An allowance of 2 mm should be made in the wall thickness of steel pipes for corrosion
and deformities in pipe manufacture.
Minimum Wall Thickness
Minimum plate or sheet thicknesses for handling are based on two formulas adopted
by many specifying agencies. They are:1
𝐷
𝑡=
(𝑝𝑖𝑝𝑒 𝑠𝑖𝑧𝑒𝑠 𝑢𝑝 𝑡𝑜 54 𝑖𝑛𝑐ℎ 𝐼𝐷)
288
𝐷 + 20
𝑡= (𝑝𝑖𝑝𝑒 𝑠𝑖𝑧𝑒𝑠 𝑔𝑟𝑒𝑎𝑡𝑒𝑟 𝑡ℎ𝑎𝑛 54 𝑖𝑛𝑐ℎ 𝐼𝐷)
400
In no case shall the shell thickness be less than 14 gauge (0.0747 inch.)
As a general rule it is recommended that the minimum wall thickness of steel pipes
should be as under:
Internal Dia ≤ 36", Minimum wall thickness = 6 mm
Internal Dia > 36", Minimum wall thickness = 8 mm
The above thickness will ensure satisfactory performance of pipe in most cases of
external loading (earthfill etc.) except live loads, and provide adequate stiffness to
keep the deflection within acceptable limits and at the same time resist buckling under
the normal range of loads.
Design Example
Data:
Pipe Internal Dia = 42 inches
Ultimate Tensile Strength of Steel = 60, 000 psi
Yield Strength of steel = 35,000 psi
Allowable tensile stress in steel = ½ x 35,000 = 17500 psi
Head of Water = 200 ft
Calculations:
a) Internal Pressure Consideration
200 62.4
Hydraulic Pressure = = 87 psi
144
1
Hoop tension per inch length of pipe = 2 87 42 = 1827 psi
1827
Thickness of steel plate required = 17500 = 0.1044 inch = 2.65 mm
b) Handling Consideration
Minimum thickness required for handling consideration
𝑃𝑖𝑝𝑒 𝐼𝑛𝑡𝑒𝑟𝑛𝑎𝑙 𝐷𝑖𝑎 42
Thickness required = = 288 = 0.1458 inch = 3.70 mm
288
Thickness required for handling consideration governs
1
PARMAKIAN, J. Minimum Thickness for Handling Pipes, Water Power and Dam Construction. (June 1982.)
120
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
c) Corrosion Allowance
A 2 mm allowance should be provided for corrosion and deformities in pipe
manufacture.
d) Total thickness (b+c) = 3.70 + 2.0 = 5.70 mm
Adopt 6 mm
RCC Pipes (Gravity Flow)
RCC pipes to be provided as non-pressure flow pipes (gravity flow) conforming to the
requirements of ASTM C 76 are generally used. These pipes must not run full.
Sufficient space has to be allowed at the top to ensure that the water flows under
gravity without any hydrostatic head.
Design requirements for class I to IV pipes showing the diameter, wall thickness,
compressive strength the concrete, and area of circular elliptical / reinforcement
(inner/outer cage) etc. are given in Table 1 to 5 of this standard.
It is however recommended that to be on the conservative side, design of RCC pipes
as per ASTM C 361 mentioned above for RCC pressure flow pipes may be adopted
for RCC non-pressure pipes as well, following design requirements for the lowest
hydrostatic head of 25 ft as per Table 1 of the ASTM C 361.
a. Selection Criteria for PRCC v/s Steel Pipe
PRCC pipe is considered the most economical option provided it is manufactured
as per laid down specification and is manufactured in the pipe factory. As no pipe
factory in Pakistan is manufacturing PRCC pipes, it is better to adopt steel pipe
option for syphons in small dams.
b. Pipe Bedding
The pipe bedding is of vital importance. Field installation procedure for RCC &
PRCC pipes is attached at Appendix G and for MS Pipes is attached at Appendix
H.
Design of Syphons
Syphon are usually designed for full pipe flow.
Syphons are usually designed to minimize head loss.
Velocity at design discharge should be between 3.5 ƒps to 10 ƒps.
In general, lower pipe velocities are fine for small syphons, but in large capacity or
long syphons, it is justifiable to design for high velocities.
• Head Losses
Most of the loss in a syphon is from pipe friction.
Total head loss is the sum of inlet, outlet, bend and pipe friction losses.
121
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
If the total syphons head exceeds available head (difference in U/S and D/S canal
elevations and water depths), the syphon will operate at a lower discharge and cause
the U/S water level to increase.
Sample hydraulic calculations are given below:-
Head Loss Calculation
Given Parameters:
The Length of syphon = 10993 feet
No. of Bends, N = 14
Inside Dia of Pipe, D = 3 feet (36 inch)
Discharge Q = 12 Cusecs
Manning’s n = 0.015
c = Hazen-Williams roughness constant = 100
Solution
1) Hazen William formula
The Darcy-Welsbach equation with the Moody diagram are considered to be the most
accurate model for estimating frictional head loss in steady pipe flow. Since the
approach requires not so efficient trial and error iteration an alternative empirical head
loss calculation like the Hazen-Williams equation may be preferred:
Hf = 0.2083 (100 / c) 1.852 q1.852 / dh4.8655 (1)
Where
Hf = friction head loss in feet of water per 100 feet of pipe (fth20/100 ft pipe)
c = Hazen-Williams roughness constant
q = volume flow (gal/min)
dh = inside hydraulic diameter (inch)
2) Manning’s Formula
Hf = 2.8775×n2×L×V2/ D1.333 (2)
Hf= Friction Head Loss ft
n = Manning’s coefficient
L = Length of the Siphons ft
v = Mean pipe velocity ft/sec
D = Inside Diameter of Pipe ft
By Using Manning’s Formula
Friction Loss Hf = 2.8775*n2×L×V2/ D1.333 = 2.8775×0.0152×10993×1.72/31.333 = 4.75
feet
By Using Hazen William formula
Friction Loss Hf = (0.2083 (100 / 100) 1.852 44821.852 / 364.865)100 = 3.55 feet
1) Area of X section of Pipe A = π D2/4 = 3.14×32/4 = 7.07 feet2
2) Hydraulic Radius of Pipe R = D/4 = 3/4 = 0.75 feet
122
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
- Design the syphon layout according to the existing terrain and proposed canal
elevations at the inlet and outlet. Route selected should have minimum
maintenance problem and damage due to rain water.
- Determine pressure requirements of the pipe according to the head (at the
lowest point) during operation.
- Determine the total head loss in the syphon at designed discharge.
- If the head loss is too high, choose a large pipe or different pipe material or
consider adjusting the canal elevation at inlet and outlet.
• Syphons Pressures Rating
- The maximum pressure is equal to the maximum of:-
1. Water surface elevation at the outlet minus the elevation of the lowest point
in the syphons.
2. Water surface elevation at the inlet minus the elevation of lowest point in
syphon minus the friction loss from the entrance to the low point.
- In any case the maximum pressure will be at or very near the location of
minimum elevation in an inverted syphons.
- Due to possible water surging in the pipe, the pressure may be
somewhat higher than calculated above; so consider adding 10% safety
factor.
• Thrust Restraint
Thrust forces are unbalanced forces which occur in pressure pipelines at changes in
direction (such as in bends, wyes, tees, etc.), at changes in cross-sectional area (such
as in reducers), or at pipeline terminations (such as at bulkheads). These forces, if not
adequately restrained, tend to disengage joints. Thrust forces of primary importance
are: (1) hydrostatic thrust due to internal pressure of the pipeline, and (2)
hydrodynamic thrust due to changing momentum of flowing water as explained in
Appendix I. Since most water lines operate at relatively low velocities, the dynamic
force is insignificant and is usually ignored when computing thrust.
• Testing of Pressure Pipe
After the pipe is in place, and before any backfilling, it should be tested for leakage
applying pressure through the use of compressed air. The weak point will be at the
joints. Testing should be carried out at a pressure of 150% of the maximum working
pressure, as used in Australia (Lewis, 2002). No leakage is permitted over a two-hour
test period. Where pipes that are prone to damage are used, such as rubber ring-
jointed PVC pipes, a further test is recommended after 1.0 meter of soil cover has
been placed. Failure at this time can be corrected at a much lower cost than after
completion of the embankment.
124
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
The agriculture activities are carried out in the command area of small dams resulting
in increased cropped area, yield, production and farm incomes ameliorating the
farmers standard of living. The major strategies and actions as follows.
6.2.3. Crop Water Requirements
Computation of crop water requirements for irrigated crops is of fundamental
importance for designing an irrigation system and scheduling of irrigation in a particular
project. The pattern of crop water use determines the capacities of distribution system
and storage capacity of dams. This information is also needed in determining the
volume of water required to meet monthly and seasonal requirements for fields, farms
and the project area as a whole.
The crop water requirements of various crops grown in the project area are calculated
by using Crop Coefficient Approach. According to this approach, crop
evapotranspiration, ETc, is calculated by multiplying the reference crop
evapotranspiration, ETo, by the crop coefficient, Kc.
ETc = KcETo
where
ETc = Crops evapotranspiration (mm/day)
Kc = Crop coefficient (unit less)
ETo = Reference evapotranspiration (mm/day)
According to the FAO, the reference crop evapotranspiration, ET o, is defined as the
rate of evapotranspiration from an extensive surface of 3 to 6 inches tall green grass
cover of uniform height, actually growing, completely shedding the ground and not
short of water. While estimating ETo, most of the effects of various weather conditions
are incorporated into ETo estimate. Therefore ETo represents an index of the climate
demand. Reference evapotranspiration, ET o, and Crop Coefficient, Kc, developed by
Punjab Irrigated-Agriculture Productivity Improvement Project (PIPIP) can be used for
calculating crop water requirements. The rainfall plays important contribution in
meeting water requirements and sometime completely compensate the crop for any
addition of irrigation water application. The rainfall data for nearest metrological station
to the dam command area can be used for calculating effective rainfall using approach
developed by US Bureau of Reclamation. The four basic stages of crop growth (Initial,
Development, Middle and Late stage) as identified by FAO are used for calculating Kc
values. The crop water requirements are calculated for the proposed cropping pattern
and intensity for command area by deducting effective rainfall. These values represent
month-wise crop water requirements at root zone and by applying, efficiencies at
various reaches water requirement at Nakka, water course head and canal head are
worked out. Detail calculations for computing crop water requirements for maize crop
with cropping intensity of 20% for command area of 1,000 acres is shown in Table 6-
1. The duration of growth stages of vegetables crops and correspondence kc values
are given in Table 6-2, whereas summary of crop water requirement for a typical
126
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
APPENDICES
134
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
18. JSIDRE (2006) – The Guidelines for Designing of Agricultural Land Improvement
Projects, “Tameike Small Dams”, Japanese Society of Irrigation, Drainage and
Reclamation Engineering, February 2006.
19. CEDERGREN, H.R. (1973). Seepage, Drainage, and Flow Nets, 3rd ed. John
Wiley & Sons, New York.
20. BUREAU (1975) – Earth Manual – A Water Resources Technical Publication,
U.S. Department of the Interior, Bureau of Reclamation;
21. USACE CORPS (1995) – Instrumentation of Embankment Dams and Levees,
US Army Corps of Engineers, EM 1110-2-1908, 30 June;
22. FRENCH COMMITTEE ON LARGE DAMS (2002) - Small Dams: Guidelines for
Design, Construction, and Monitoring. Coordinator Gérard Degoutte. ISBN 2-
85362-551-6.
23. MCCOOK, D. (2005). “A Comprehensive Discussion of Piping and Internal
Erosion Failure Mechanisms,” Proc. Assoc. State Dam Safety Officials, Annual
Meeting, Sept 26-30, Phoenix, Arizona, USA.
24. Engineering Design Manuals – Hyundai Engineering Company Ltd Korea.
Recommended Reference Books
4. Design of Small Dam, United States Department of the Interior (Bureau of
Reclamation).
5. Design of Concrete Gravity Dam, United States Department of the Interior
(Bureau of Reclamation).
6. Earth and Earth Rock Dams by James L. Sherard (Engineering problems of
Design and construction)
Hydraulic Design of Stilling Basins and Energy Dissipation by A.J. Peterka
137
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
PHOTOGRAPHS
Khai Dam
Sr.
State Minor
No.
US State
1 Colorado (CO) "Minor Dam" is a jurisdictional size dam that does not
exceed 20 feet in jurisdictional height and/or 100 acre-
feet in capacity.
2 Kansas (KS) “Class Size 1”- Height of less than 25 feet and an
effective storage of less than 50 acre-feet.
3 Massachusetts “Non-jurisdictional Dam”- Storage not in excess of 15
(MA) acft regardless of height; height not in excess of 6 ft,
regardless of storage capacity.
4 New Hampshire “Class A structure” means a dam that is not a menace
(NH) because it is in a location and of a size that failure or
misoperation of the dam would not result in probable
loss of life or loss to property, provided the dam is: (a)
Less than 6 feet in height if it has a storage capacity
greater than 50 acre-feet; or (b) Less than 25 feet in
height if it has a storage capacity of 15 to 50 acre-feet.
5 New Jersey (NJ) A “Class IV” dam is any project which impounds less
than 15 ac-ft of water to the top of the dam, and has less
than 15 feet height of dam (as measured to the top of
the dam) and which has a drainage area above the dam
of 150 acres or less in extent.
6 New York (NY) A “Class A” dam is a “negligible or no hazard” dam also
Potential Hazard Class (PFC) – I of ICOLD.
7 Ohio (OH) A “Class IV dam” will be twenty-five feet or less in height
and have a total storage volume of 50 acre feet or less.
141
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Sr.
State Minor
No.
8 South Carolina A “very small dam” will have an impoundment structure
(SC) less than 50 acre-feet and a height less than 25 ft.
9 United States, USDA and NRCS: Mini dam–pond of height (H) < 10.7
Department of m, storage capacity of 50 aft and PHC-I.
Agriculture
(USDA) and
Natural Resources
Conservation
Services (NRCS)
Pakistan
10 Pakistan, ABAD Mini Dam site having a Pondage Capacity of more than
40 Aft and Command Area of at least 20 acres.
Pond site having capacity 20 Aft and Command Area of
at least 15 acres. However, height of existing mini dams
constructed by ABAD ranges from 20 ft to 50 ft.
2. Site selection
- Dam Sites with steep bed slopes (i.e. over 4 ~ 5 percent) are rarely economical as
embankment give limited storage and therefore be given low priority.
- A good dam site should have a catchment area that is not so big that an expensive
spillway may be required but is also not so small that the yield from the reservoir
is too low or erratic to be able to supply an economic area for any irrigation
schemes.
- Where rock bars perpendicular to the stream flow are found at site, it would provide
good spillway site and safe embankment.
- In case of cascade of dams built in the catchment above the selected site, the total
catchment area of the dam under consideration including the catchment area of
dams built above, should be taken while calculating peak flood for design of
spillway. This factor will be the governing factor in selection of site as larger spillway
capacity will be required to safely pass the designed discharge.
- Dams should not be sited on catchments which are so small that they are unlikely
to fill in an average year.
- Estimations of peak flood are required for spillway design, the dimensions and
physical characteristics of which are extremely important. If a suitable spillway of
sufficient size is not available at a particular site, or would prove too expensive, it
is advisable to move on to a better alternative site where spillway conditions can
be met.
142
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
- Suitable clayey soils for building the dam wall should be available from a borrow
pit in the reservoir and from excavating the spillways.
3. Hydrology
There is a large spatial rainfall variation in the Pothohar region. Annual average varies
from 487 mm in the sub-humid south western to 1766 mm at Murree in the
northeastern area as shown in Figure below:
The runoffs generated by1 Km2 of catchment area for various regions of Pothohar are
shown in table given belwo. This information could be used for estimating by the run-
off from the catchment area of the RHS under consideration.
Runoff (AFT) by 1 Km2 catchment area in the various regions of the Pothohar
Mean
Mean
Catchment Data annual
area
annual
Sr. record sediment
River Station runoff
No. yield
(ac-ft/sq- (ac-ft/sq-
(sq-mile) Years
mile) mile)
Siran
1 Phulra 408 36 1218.1 3.9
RIver
Haro
2 Garlia 1180 37 583.9 2.7
River
Haro
3 Khanpur 300 32 733.3 3.1
River
Soan Dhok
4 2500 42 444 5.17
River Pathan
II) Design flood
As per standard practice around the world, RHSs are normally designed on 10 to 50
year return period. After studying the climatic conditions, topography and risk
associated with these structures, below mentioned criteria is suggested:
a. Earthern dams
Spillways will be designed on 25 year return period flood, whereas freeboard will
be determined on 50 year return period flood.
b. Concrete dams
Spillway will be designed on 25 year return period flood.
Design flood for each rainwater harvesting scheme will be determined using Unit
Hydrograph Method or by empirical formula. One day annual maximum rainfall data
of Gujjar Khan, Mianwali, Islamabad, Talagang, Rawalpindi and Fateh Jhang will be
adopted for respective catchments.
4. Irrigation requirements
I) Crop water requirement
After taking into account the evaporation and seepage losses of rainwater harvesting
structure, the remaining water amount will be available for irrigation. The crop water
requirements for proposed cropping pattern and intensities will be worked out and
CCA will be adjusted according to the available water. Based on the proposed
cropping pattern and intensities and CCA, agriculture benefits will be worked out for
economic analysis.
For computing crop water requirement, Crop Coefficient Approach will be used.
According to this approach crop evapotranspiration (ETc) is calculated by multiplying
the reference crop evapotranspiration (ETo) by the crop coefficient (Kc) as under:
144
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
table below were based on wind velocities of 160 km/hour (100 miles/hour) for
estimating normal freeboard and 80 km/hour (50 miles/hour) for minimum freeboard.
Freeboard requirements for preliminary studies of small dams for rock faced slope (USBR, 1987, 1992)
Minimum Freeboard –
Longest fetch (km) Normal Freeboard (m)
MFL (*) (m)
< 1.6 1.2 0.9
1.6 1.5 1.2
4.0 1.8 1.5
(*) MFL = Maximum Flood Level.
A large number of water retaining structures (earthfill) have failed due to overtopping
and consequently greater attention must be paid to this feature. Freeboard should not
be less than 1.0 m, even for small RHS.
ii) Crest width
Table below presents the crest width criteria as per USBR.
Crest width criteria
6" SPAWL
Homogeneous embankment
b. Zoned embankment
When material available contains high percentage of gravel and sand with no fine
particles, impervious core be placed in the centre of the fill with horizontal filter, as
shown in
Figure below.
Zoned embankment
(8) The grain size curve of the filter should be roughly parallel to that of the base
material.
147
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
If more than one filter layer is required, the same criteria are followed; the finer filter is
considered as the ''base material'' for selection of the gradation of the coarser filter.
Although normally specified, the following guides are given for filter construction:
(7) The subgrade before filter placement should be firm and, if necessary, be lightly
tamped or rolled.
(8) Clean filter material should have sufficient water content (3 to 10 percent) during
placement, and the placement method should be such that segregation is
prevented.
(9) Thin filters are usually firmly compacted with light flat rollers, or are tamped to a
firm condition. Unless otherwise specified, thick filters are compacted to 70 percent
relative density in a manner similar to free-draining sand-gravel backfill to prevent
settlement.
(10) The filter layers for coarse filter material (3-inch maximum size) are usually not
less than 8 inches in thickness, and layers of finer filter material are often 6-inch
minimum thickness. However, for severe field conditions such as high head,
variations in base material, or filter gradations which are near the extreme coarse
limit, the minimum thickness of 8 inches may be specified. For zoned filters these
minimum thicknesses may be specified and are maintained for each layer.
vi) Upstream protection
The upstream slope should be protected by 1' thick rip-rap laid over 6" thick spawl
filling, at least in the upper 2/3rd of the slope.
7. Spillway types
• Only those sites should be selected where spillway cost is not prohibitive.
• In case of rock on abutments, open channel spillway be provided without lining,
close to the main dam or at a natural depression in the banks.
• In case soil on spillway site is erosive, chute spillway and stilling basin with proper
protective cover of concrete should be adopted for energy dissipation.
8. Construction of RHSs
Important things to remember (Earthfill RHSs):
• Construction should begin with a cutoff trench;
• The embankment should be properly keyed into the banks.
• Construct in nearly horizontal lifts that extend abutment to abutment;
• Borrow materials should be hauled onto lift (or layer) placement areas and NOT
PUSHED IN PLACE.
• Once dumped, soils should be spread by dozing equipment so that their
thickness is no greater than 9 inches (or as directed by the Engineer);
148
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
• After fill has been spread and moisture properly adjusted, the soil should be
compacted by either rubber tired equipment (front end loader with bucket filled)
or equipment specifically designed for soil compaction (i.e. suitable rollers).
• The embankment should be built up fairly uniformly over the entire width and
length of each section as it is constructed.
• Caution: Bonding between lifts is important to prevent problems. Prior to
placing the next lift (or layer), the prior lift should be scarified a maximum of 2
inches deep. Do not leave lift surfaces to become too dry. Organic content of
soil, and other deleterious matter should be removed.
a. Foundation cutoff:
Sometime it is necessary to provide a cutoff trench. The cutoff trench is constructed
of impervious material and is generally located near the centerline of the dam. Ideally
the cutoff should extend to an impervious layer in the foundation, either soil or rock.
Cutoff trenches prevent excessive seepage from moving under the dam, by
lengthening the seepage path.
b. Fill placement - compaction:
Two variables that greatly influence the embankment fill density are the compactive
effort (i.e., degree of compaction, DC) and the moisture content (Optimum Moisture
Content, OMC).
How to determine adequate compaction:
4. Field and laboratory testing
• Samples of earthfill materials are tested in the on-site laboratory to determine
OMC and maximum dry density relationship of each earthfill materials, using
ASTM D698.
• Field density tests are performed on compacted layer using ASTM D1556 or
other ASTM D standard methods suitable to site conditions.
• Compute Degree of Compaction (DC) and moisture content. DC ≥ 95% and
Moisture Content should be ± 1 to 2% OMC of ASTM D698.
5. Keeping track of passes
• Generally 8 to 10 passes are necessary to get adequate compaction.
(iv)Foundation preparation and treatments
Before beginning to construct embankment, attention must be given to the
foundations. A properly prepared foundation is critical to the safety and long life of the
embankment.
Caution: Clean gravels and sands make a poor embankment foundation. Gravels are
highly permeable and could allow excessive seepage, which could in turn lead to dam
failure or inability to hold water. Do not build dam on open gravels foundation.
149
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Stripping:
Stripping is the removal of any unsuitable soils. Generally, this involves the excavation
and removal of top soil (about one ft), which commonly contains large amounts of
organic matter.
(v) Surface protection
Embankment surfaces must be protected from surface erosion. Upstream slope
protection shall usually consist of rip-rap over 6" spawl filling.
Borrow area investigation and lab testing
The availability of suitable material for building RHS is a determining factor in selecting
a pond site. Enough suitable material should be located close to the site so that
placement costs are not excessive.
Materials selected must have enough strength for the dam to remain stable and be
water tight enough, when properly compacted, to prevent excessive or harmful
percolation of water through the dam. Soils described as acceptable for foundation
material generally are acceptable for fill material. The exceptions are organic silts and
clays and dispersive clays.
The best material for an earthfill contains particles ranging from small gravel or coarse
sand to fine sand and clay in the desired proportions (i.e. well graded). This material
should contain about 15 to 20 percent, by weight, clay particles.
Soils containing a high percentage of gravel or coarse sand with no fines are pervious
and can allow rapid seepage through the dam. When using these soils, place a core
of clay material in the center of the fill and flatten the side slopes to keep the line of
seepage from emerging on the downstream slope.
Soils used in embankment dams:
There are five different types of earth material used in embankment construction. For
simple identification of fine grained soils follow the flow chart shown in Figure below.
Clay
y
Flow chart for identification of fine grained soils
150
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
General
Dam Name: _________________________________________________________
Date of Inspection: ____________________________________________________
Owner’s Name: ______________________________________________________
Address: ____________________________________________________________
Telephone: __________________________________________________________
Inspected by: ________________________________________________________
Weather: ___________________________________________________________
Reservoir Data
Reservoir Level at Time of Inspection: _________________________ (feet below
dam crest)
Reservoir Inflow at Time of Inspection: _________________________________ (cfs
or gpm)
Reservoir Outflow at Time of Inspection: ________________________________ (cfs
or gpm)
Condition of Dam
Crest: _____________________________________________________________
___________________________________________________________________
___________________________________________________________________
(Check for: surface cracking, animal burrows, low areas, horizontal alignment, ruts,
trees, brush)
Upstream Face: _____________________________________________________
___________________________________________________________________
___________________________________________________________________
(Check for: slumps, slides, scarps, sinkholes, animal burrows, slope protection, wave
erosion, trees, brush)
Downstream Face: __________________________________________________
___________________________________________________________________
___________________________________________________________________
(Check for: wet areas [no flow], seepage [note location], slides, slumps, scarps,
change in slope, animal burrows, erosion, unusual movements, trees, brush, water
loving vegetation)
158
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Spillway(s):
− Earthen Channel; __________________________________________________
___________________________________________________________________
___________________________________________________________________
(Check for: slide, slump, scarp, erosion protection, vegetation, debris)
− Concrete Lined Channel; ___________________________________________
___________________________________________________________________
___________________________________________________________________
(Examine: sidewalls, channel floor, approach area, weir, discharge area. Check for:
alignment, movement, cracking, spalling, undermining, etc.)
− Drop Inlet; _______________________________________________________
___________________________________________________________________
___________________________________________________________________
(Examine: intake structure, trashrack, conduit, stilling basin)
Outlet Works: (visible elements) _________________________________________
___________________________________________________________________
___________________________________________________________________
(Examine: intake structure, trashrack, stilling basin, control mechanism, outlet pipe.
Check for: seepage, undermining, erosion, corrosion)
Maintenance Deficiencies: ____________________________________________
___________________________________________________________________
___________________________________________________________________
Additional Comments:
_______________________________________________________
___________________________________________________________________
___________________________________________________________________
Sketch of Dam and Reservoir Site
159
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
2
Control of External Corrosion on Underground or Submerged Metallic Piping Systems. NACE Standard RP-0 l-69. NACE, Houston, Texas (1983 revision).
165
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Coal-tar enamel, coal-tar epoxy, and fusion-bonded epoxy exhibit excellent corrosion-
resistance properties and provide the required smoothness to maintain flow capacity.
When reinforced, the coatings provide additional resistance to physical damage.
Regardless of the lining material selected, consideration should be given to the effects
of cavitation and silts on the lining.
Recommended Coatings and Linings
Current AWWA standards list coatings and linings for steel water pipe that are believed
to be the most reliable, as proved in practice. The AWWA Steel Pipe Committee is
alert, however, to the possibilities of new developments, and additions to and
modifications of existing standards will be made as deemed advisable. The current list
of AWWA coating and lining standards for pipe protection is as follows:
AWWA C203, Standard for Coal-Tar Protective Coatings and Linings for Steel
Water Pipelines—Enamel and Tape—Hot-Applied. AWWA C2033 describes the
material and application requirements for shop-applied coal-tar protective coatings
and linings for steel water pipelines intended for use under normal conditions when
the temperature of the water in the pipe will not exceed 90ºF (32°C). The standard
covers coal-tar enamel applied to the interior and exterior of pipe, special sections,
connections, and fittings; it also covers hot-applied coal-tar tape applied to the exterior
of special sections, connections, and fittings.
Coal-tar enamel is applied over a coal-tar or synthetic primer. External coal-tar enamel
coatings use bonded asbestos-felt and fibrous-glass mat to reinforce and shield the
coal-tar enamel. The applied external coating is usually finished with either a coat of
whitewash or a single wrap of kraft paper.
Internally, the coal-tar enamel is used without reinforcement or shielding. The hot
enamel is spun into the pipe and provides a smooth internal lining having low hydraulic
frictional resistance.
The standard provides a rigid yet reasonable manufacturer’s guide for the production
of the coating, calls for tests of material and its behavior to ensure the purchaser that
the product has the desired qualities, and furnishes directions for the effective
application of the coating.
AWWA C205, Standard for Cement-Mortar Protective Lining and Coating for
Steel Water Pipe—4 In. and Larger—Shop Applied. AWWA C2054 describes the
material and application requirements to provide protective linings and coatings for
steel water pipe by shop application of cement mortar.
Cement mortar is composed of Portland cement, sand, and water, well mixed and of
the proper consistency to obtain a dense, homogeneous lining or coating. Internally,
the cement mortar is centrifugally compacted to remove excess water and produce a
smooth, uniform surface. Externally, the coating is a reinforced cement mortar,
pneumatically or mechanically applied to the pipe surface. Reinforcement consists of
3
Coal-Tar Protective Coatings and Linings for Steel Water Pipelines—Enamel and Tape—Hot Applied. AWWA Standard C203-78. AWWA, Denver, Colo. (1978).
4
Cement-Mortar Protective Lining and Coating for Steel Water Pipe—4 in. and Larger—Shop Applied. AWWA Standard C205-80. AWWA, Denver, Colo. (1980).
166
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
spiral wire, wire fabric, or ribbon mesh. The standard provides a complete guide for
application and curing of the mortar lining and mortar coating.
AWWA C209, Standard for Cold-Applied Tape Coatings for the Exterior of
Special Sections, Connections, and Fittings for Steel Water Pipelines. AWWA
C2095 covers the use of a cold primer and cold-applied tape on the exterior of special
sections, connections, and fittings for steel water pipelines installed underground in
any soil under normal or average conditions. Tapes with both polyvinyl chloride and
polyethylene backing are listed. The thicknesses of the tapes vary; however, all tapes
may be sufficiently overlapped to meet changing performance requirements. Cold-
applied tapes provide ease of application without the use of special equipment and
can be applied over a broad application temperature range. If severe construction or
soil conditions exist where mechanical damage may occur, a suitable overwrap of an
extra thickness of tape or other wrapping may be required.
AWWA C210, Standard for Liquid Epoxy Coating Systems for the Interior and
Exterior of Steel Water Pipelines. AWWA C2106 describes a liquid epoxy coating
system, suitable for potable water service, which will provide corrosion protection to
the interior and exterior of steel water pipe, fittings, and special sections installed
underground or underwater. The coating system consists of one coat of a two-part
chemically cured inhibitive epoxy primer, and one or more coats of a two-part
chemically cured epoxy finish coat. The finish coat may be a coal-tar epoxy coating,
or it may be an epoxy coating containing no coal tar. The coating system may
alternately consist of two or more coats of the same epoxy coating without the use of
a separate primer, provided the coating system meets the performance requirements
of AWWA C210.
These coatings are suitable when used for corrosion prevention in water service
systems at temperatures up to 140°F (60°C). The products are applied by spray
application, preferably airless.
The liquid epoxy system described in the standard differs from the customary product
commercially available in that it has a very high flexibility, elongation, and impact
resistance. Any liquid epoxy offered for water utility purposes must meet the
requirements of AWWA C210.
AWWA C213, Standard for Fusion-Bonded Epoxy Coating for the Interior and
Exterior of Steel Water Pipelines. AWWA C2137 describes the material and
application requirements for fusion-bonded epoxy protective coatings for the interior
and exterior of steel water pipe, special sections, welded joints, connections, and
fittings of steel water pipelines installed underground or underwater under normal
construction conditions. The epoxy coatings are suited for corrosion prevention in
potable water systems operating at temperatures up to 140ºF (60ºC).
5
Cold-Applied Tape Coatings for the Exterior of Special Sections, Connections, and Fittings for Steel Water Pipelines. AWWA Standard C209-84. AWWA, Denver, Colo.
(1984).
6
Liquid Epoxy Coating Systems for the Interior and Exterior of Steel Water Pipelines. AWWA Standard C210-84. AWWA, Denver, Colo. (1984).
7
Fusion-Bonded Epoxy Coating for the Interior and Exterior of Steel Water Pipelines. AWWA Standard C213-79. AWWA, Denver, Colo. (1979).
167
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Fusion-bonded epoxy coatings are heat activated, chemically cured coating systems.
The epoxy coatings are furnished in powder form. Except for welded field joints, they
are plant- or shop-applied to preheated pipe, special sections, connections, and fittings
using fluid bed, air, or electrostatic spray.
AWWA C214, Standard for Tape Coating Systems for the Exterior of Steel Water
Pipelines. AWWA C2148 covers the materials, the systems, and the application
requirements for prefabricated cold-applied tapes for the exterior of all diameters of
steel water pipe placed by mechanical means. For normal construction conditions,
prefabricated cold-applied tapes are applied as a three-layer system consisting of (1)
primer, (2) corrosion preventive tape (inner layer), and (3) mechanical protective tape
(outer layer). The primer is supplied in the form of a liquid consisting of solid
ingredients carried in a solvent. The corrosion preventive tape and the mechanical
protective tape are supplied in suitable thicknesses and in roll form. The standard
covers application at coating plants.
AWWA C602, Standard for Cement-Mortar Lining of Water Pipelines—4 In. (100
mm) and Larger—In Place. AWWA C6029 describes the materials and application
processes for the cement-mortar lining of pipelines in place, covering both newly
installed pipes and older pipelines. Detailed procedures are included for surface
preparation and application, surface finishing, and curing of the cement mortar.
Coating Application
This manual does not furnish details on methods of coating and paint application, but
the importance of obtaining proper application cannot be overemphasized. Effective
results cannot be secured with any coating material unless adequate care is taken in
preparing the surfaces for coating, in applying the coating, and in handling the pipe
after coating.
8
Tape Coating Systems for the Exterior of Steel Water Pipelines. AWWA Standard C214-83. AWWA, Denver, Colo. (1983).
9
Cement-Mortar Lining of Water Pipelines–4 in. (100 mm) and Larger–in Place. AWWA Standard C602-83. AWWA, Denver, Colo. (1983).
168
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
(a) Cohesive Soil or Granular Soil Containing More Than 5 % Fines–If the haunch
support backfill material is a cohesive soil or is a granular soil containing more
than 5 % material passing the number 200 sieve, the material shall be placed
170
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
supported by the sling while preparing to make the joint. The coating on the underside
of the pipe should be inspected while it is suspended from the sling, and any visible
damage to the coating should be repaired before lowering the pipe into the trench.
Pipe should be laid to lines and grades shown on the contract drawings and
specifications. All fittings and appurtenances should be at the required locations.
The pipe trench should be kept free from water that could impair the integrity of
bedding and joining operations. On grades exceeding 10 percent, the pipe should
be laid uphill or otherwise held in place by methods approved by the Engineer.
2. INSTALLATION OF PIPE
Handling and Laying
Care similar to that exercised during loading, transporting, unloading, and stringing
should be observed during installation of the pipe in the trench. Dielectrically coated
pipe may require additional special care when handled at temperatures below that
recommended by the manufacturer, or when the coating temperature is above that
recommended by the manufacturer.
Coated pipe should not be strung on rough ground when stored at the trench site, nor
should it be rolled on such a surface. Rolling of coated pipe should be permitted only
when joint ends are bare and rails are provided on which to roll the exposed steel.
175
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Thrust Restraint
Thrust Forces
Thrust forces are unbalanced forces which occur in pressure pipelines at changes in
direction (such as in bends, wyes, tees, etc.), at changes in cross-sectional area (such
as in reducers), or at pipeline terminations (such as at bulkheads). These forces, if not
adequately restrained, tend to disengage joints. Thrust forces of primary importance
are: (1) hydrostatic thrust due to internal pressure of the pipeline, and (2)
hydrodynamic thrust due to changing momentum of flowing water. Since most water
lines operate at relatively low velocities, the dynamic force is insignificant and is
usually ignored when computing thrust.
A. Hydrostatic Thrust
Typical examples of hydrostatic thrust are shown in Figure below. The thrust in dead
ends, outlets, laterals, and reducers is a function of internal pressure, P, and cross-
sectional area, A, at the pipe joint. The resultant thrust at a bend is also a function of
the deflection angle, D, and is given by:
𝑇 = 2𝑃 𝐴𝑠𝑖𝑛 (∆⁄2)
where: T = hydrostatic thrust, lbs.
P = internal pressure, psi
Δ = deflection angle of bend, deg.
A = (𝜋/4)𝐷2 = cross-sectional area of pipe O.D., sq. in.
B. Thrust Resistance
For buried pipelines, thrust resulting from angular deflections at standard and beveled
pipe with rubber gasket joints is resisted by dead weight or frictional drag of the pipe,
and additional restraint is usually not needed. Other fittings subjected to unbalanced
horizontal thrust have two inherent sources of resistance: (1) frictional drag from dead
weight of the fitting, earth cover, and contained water, and (2) passive resistance of
soil against the back of the fitting. If this type of resistance is not adequate to resist the
thrust involved, then it must be supplemented either by increasing frictional drag of the
line by “tying” adjacent pipe to the fitting or by increasing the supporting area on the
bearing side of the fitting with a thrust block. Unbalanced uplift thrust at a vertical
deflection is resisted by the dead weight of the fitting, earth, cover, and contained
water. If this type of resistance is not adequate to resist the thrust involved, then it
must be supplemented either by increasing the dead weight of the line by “tying”
adjacent pipe to the fitting or by increasing the dead weight with a gravity type thrust
block.
C. Thrust Blocks
Thrust blocks increase the ability of fittings to resist movement by increasing the
bearing area.
Thrust block size can be calculated based on the bearing capacity of the soil:
Area of Block = Lb x Hb = (T/)
where: L b x Hb = area of bearing surface of thrust block, sq. ft.
T = thrust force, lbs.
= safe bearing value for soil, psf
Determining the safe bearing value, s, is the key to “sizing” a thrust block. Values can
vary from less than 1000 pounds per square foot for very soft soils to several tons per
square foot for solid rock. Knowledge of local soil conditions is necessary for proper
sizing of thrust blocks. Design of the block for a bottom bend is the same as for a
horizontal bend, but the block for a top bend must be sized to adequately resist the
vertical component of thrust with dead weight of the block, bend, water in the bend,
and overburden.
Uplift thrust restraint provided by gravity type thrust blocks for the top bend may also
be provided by the alternate method of increasing the dead weight of the line by tying
adjacent pipe to the vertical bend.
Most thrust block failures can be attributed to improper construction. Even a correctly
sized block can fail if it is not properly constructed. A block must be placed against
undisturbed soil and the face of the block must be perpendicular to the direction of and
centered on the line of action of the thrust.
D. Anchors and Thrust Blocks on Slopes
178
MANUAL OF IRRIGATION PRACTICE
SMALL DAMS
Pipelines laid on slopes, particularly above ground, always have a tendency to creep
downhill. It is necessary to provide anchor blocks placed against undisturbed earth at
sufficiently frequent intervals on a long, steep slope to reduce the weight of pipe
supported at each anchorage to a figure. Where pipe is located in a position where
disturbance of the trench is unlikely, concrete thrust blocks may be used to resist the
lateral thrust. Vertical angles with resultant thrust in a downward direction require no
special treatment if the pipe is laid on a firm and carefully trimmed trench bottom, but
vertical angles with a resultant thrust upward should be properly anchored.
i
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
List of Tables
TABLE 1: VALUES OF RUNOFF COEFFICIENT ‘C’ ............................................................................ 241
TABLE 2: JINNAH BARRAGE’S DATA ........................................................................................................ 248
TABLE 3: CHASHMA BARRAGE’S DATA .................................................................................................... 249
List of Figures
FIGURE 1: SUB-MOUNTAINOUS RIVER ..................................................................................................... 180
FIGURE 2: AREAL CHANGE OF RIVER CHANNEL TYPES .............................................................................. 181
FIGURE 3:AGGRADING RIVER .............................................................................................................. 182
FIGURE 4: MEANDERS IN DELTA RIVER .................................................................................................... 183
FIGURE 5: PERMANENT BANKS ............................................................................................................... 184
FIGURE 6: EMBANKMENT WITH THROUGH SEEPAGE ................................................................................. 192
FIGURE 7: TYPICAL RELIEF WELL (AFTER EM-1110-2-1913).................................................................... 194
FIGURE 8: CUT-OFF WALL ...................................................................................................................... 195
FIGURE 9: PERVIOUS TOE DRAIN ............................................................................................................ 196
FIGURE 10: HORIZONTAL DRAINAGE LAYER ............................................................................................. 196
FIGURE 11A&B: INCLINED DRAINAGE LAYER ........................................................................................... 197
FIGURE 12: BUND WITH BACK BERM (PUSHTA) ........................................................................................ 206
FIGURE 13: SLOPE PROTECTION MEASURES (TEMPORARY) ...................................................................... 209
vii
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
1. INTRODUCTION
Rivers have played an important role in development of civilizations and their evolution
from early times till today. Most of the ancient civilizations had flourished along banks
of river Nile, Indus, Euphrates, Yangtze and many others. Besides serving as source
for food and water, these rivers have been providing important facilities for navigation,
fisheries and Irrigation. With ushering-in of industrial era, their importance increased
manifold. These are also vital for hydropower and recreation. Besides the tremendous
advantages, the rivers also have potential problems of floodings when these spill out
of their banks in to the flood plains and result in damages to infrastructures and
sometime loss of life and property. The floods also have long term beneficial effects
such as deposition of fertile soils in agriculture fields and recharge of ground water
reservoir. The floods are a resource of huge volume of water, if managed and
controlled can enhance quality of life and economic health.
2. CLASSIFICATION OF RIVERS
Rivers can be generally classified on the basis of flow and on the basis of topography
as described below:
2.1. Based on Flow
2.1.1. Perennial Rivers
These rivers flow the year round with seasonal fluctuations. The inflow to these rivers
is mainly derived from snow, glacier melt and rainfall in the catchment areas. In winter
season the river discharge decrease while high discharges are recorded in summer
season due to heavy rainfall. Punjab Rivers are of this type with high discharges due
to monsoon rains and a modest base flow of snowmelt and winter rains, in the
catchment. The Indus River and its tributaries are the main source of surface water in
Pakistan.
2.1.2. Non-Perennial Rivers
These rivers flow for a part of the year and are dry in the remaining part of the year.
These may or may not be snow fed but get their flow mostly from precipitations spread
over a part of the season. Rivers can be categorized as non- perennial type because
they are fed by Monsoon Rains during July to October.
2.1.3. Flashy Rivers or Hill Torrents
These Rivers usually originate from Rocky Mountains which get occasional heavy
rains bringing flash floods in torrents for a small period of time which can play havoc
while flooding. The Nullahs emanating from Hindu Kush Suleman, Salt and Kirther
range this category. The arid or semi-arid land at foot of the hills, gets its moisture
supply for crops of one season.
2.1.4. Dry Rivers
In Arid Regions and Deserts some low flow rivers may run completely dry due to
evaporation, and deep percolation. The flow just ceases to exist. Hakra River in
180
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
Cholistan Desert is one such example in Punjab. It used to carry the water of the Sutlej
in ancient times but is now dry.
2.2. Classification Based on Topography and Ground Relief
All the rivers in Punjab originate in mountainous regions of Karakorum Range and the
Himaliyas. In mountainous regions the rivers flow in gorges with much more depth
compared to width. As these rivers emerge in the plains, depth starts decreasing and
rivers become wider. The rivers can be classified in various reaches depending upon
topography and ground relief.
2.2.1. Mountainous Rivers
Rivers in mountainous reaches have deep cut channels with steep bed slopes and
very high velocity. The bed is rocky and is littered with boulders to granular pebbles
conglomerated in coarse aggregates. The river slope and bed is continuously in a
process of abrasion and grinding and boulders of assorted sizes are transported
downstream along with material eroded from watershed. The depth is typically greater
than width and is non uniform.
2.2.2. Sub-Mountainous Rivers
As the water moves further downstream, it enters into sections which are still steep
but have relatively gentle slope. The river slope and bed is made of smaller rocks,
pebbles, gravels, shingles and very coarse sand generally known as river run material.
Now the river has well• defined cross-section and a meandering trend with an incised
channel. The depth is still greater than width, but gradually adjusting in conformity with
available slope and sediment load as the stream is slowly transformed into a plain
alluvial river.
Of the three types mentioned above, meandering type is the final stage of river
development whereas the other two types are of interim nature. The meandering
patterns are not permanent to a river regime. However, there is definite regime of each
river reach due to the magnitude and variation of its discharge and sediment load and
composition of alluvial materials.
2.2.3.5. Straight Reach Rivers
In the straight reach of the river, the river channel is straight; usually this form is
situated in upper reaches of the alluvial river in a short length. The section of the
channel is in shape of a trough and maximum velocity of flow is in the middle of the
section. There could also be straight river reaches in between the meanders. In low
flows, sand bars can be seen located alternatively along the banks. The reach of Ravi
river in Sidhnai Barrage area is probably the only example in Punjab.
2.2.3.6. Tidal or Delta Rivers
Before discharging into the sea or lake, the rivers become highly braided. This activity
allows building up of deltas in between the branches. Near the river outfall, periodic
changes in water levels can occur due to tides, while the river continues to spread its
sediments load to convert swamps into delta. This lower part of the system is called a
Tidal River.
3) Keep the bund at an optimal distance from the active river channels. In
addition to technical conditions, the socio – economic political conditions
have to be negotiated with.
4) Both anchor points should be at a safe elevation.
5) Ensure protection of the important salient intended to provide protection.
6) Avoid tortuous routes and sharp curves / bends.
7) Neighbourhood of villages should be avoided, if possible as their
proximity generally entails heavy trespass.
III. Investigations
A) Geotechnical investigations to identify the formation soil characteristics
and soil category available along the bund alignment should be carried
out comprising:
a. Grain size analysis
b. Atterberg limits
c. Permeability
d. Soil classification
e. Bulk density
f. Compressive strength
g. Shear strength
B) Geophysical investigations
a. Electrical resistivity profiling will reveal soil stratification.
b. Ground penetrating radar can be used to determine cavities, weak
soil strata and buried objects.
4.3.1.3. Types of Flood Bunds
1. Marginal Bunds
2. Bunds Protecting Strategic locations
3. Bunds along open reaches of the rivers
4.3.1.3.1. Marginal Bunds
Marginal Bunds (or afflux embankments) are provided to contain river spill generated
by raising of water levels at the barrage, bridge or syphon. Due to backwater effect the
marginal bunds could extend up to 12 – 13 miles upstream of a structure depending
upon channel slope and afflux imposed.
The basic design parameters currently prescribed for Marginal Bunds in the Punjab by
FFC are as under:
• Crest width = 25 ft
• Riverside slope earthen = 3:1
• Riverside slope protected = 2:1
188
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
• Provide adequate freeboard to mitigate the rise in flood levels and wave ride
The first option is in fact impossible and goes out of reckoning, leaving only the second
option of providing adequate effective freeboard which is recommended.
5.2. Breaching
The breaching is the most common cause for failure of embankments. A breach occurs
when a bund/embankment gives way to water at a certain location and flood water
gushes out towards the protected flood plain through the opening caused by the
breach which widens to a greater width depending upon head across and vulnerability
of soil against erosion. Breaches generally occur gradually and develop into a full
breach with time. Nevertheless breaches can develop suddenly due to poor soil
conditions, porosity, intensity of rodent activities and poorer maintenance.
Following are major causes of breaching:
• All possibilities of overtopping listed above
• Inadequate downstream slopes not covering hydraulic gradient line
• Piping action through foundation
• Movement of fine materials through boils
• Solutioning of soluble materials under saturated embankment conditions
• Erosion by river action and scour
• Erosion by wind generated waves and hydraulic pressures
• Ground shaking due to seismic activities resulting in slicing and slumping
• Runnels and runners caused by rodents like porcupines, rats, ants, jackals, etc.
• Long rooted trees and old tree roots can give rise to runnels, when they die and
rot
• Tresspassing or vandalism
• Sloughing and ravines caused by heavy rains
• Encroachments of downstream slopes
• Cracking of poor quality of soil due to freezing and thawing/. temperature
change affect
5.3. Erosion
Erosion of embankment body can be caused by direct attack of river currents or waves
generated in medium depth ponds / water bodies enclosed by levees. This is a
common mode of damage to flood bunds in most of the national and international
locations.
Mitigation measures are:
i. Robust design and construction
ii. Strengthening the weak / inadequately strong reaches
iii. Providing erosion protection interventions like stone pitching, mattresses,
studs, spurs etc.
5.4. Seepage through the embankment body
191
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
There are several causes for this phenomenon, but the major ones are;
i. Exposure of phreatic line
ii. Cavities due to solutioning / subsidence of plastic strata
iii. Cavities caused by rodents through burrow holes
iv. Runnels caused through decay of dead roots of trees and other growth
v. Deep ravines formed by torrential rains
There are several remedies for each type, details of which appear in the following
paragraphs.
5.5. Foundation Failure
Foundation failure occurs at high flood depths in locations where the flood bund body
rests on highly permeable alluvium like coarse sand / quick sand / plastic strata.
The remedial measures comprise, replacement of foundation soil, reworking of
foundation soil, or providing an impermeable curtain in the embankment to cover
foundation weakness.
5.6. Seismic Events and Other Natural Elements
Seismic events and other natural elements like storms and hurricanes occur without
warning and solutions are good design and operational efforts. Such events occur all
over the World.
6. SEEPAGE CONTROL
6.1. Foundation Underseepage
6.1.1. General
Without control the underseepage in pervious foundations beneath bunds may result
in:
a) Excessive pressure beneath an impervious top stratum on the land side
b) Sand boils
c) Piping beneath the bund
Underseepage problems are most acute where a pervious substratum underlies a
bund and extend both riverside and landside of the bund. Principal seepage control
measures for foundation underseepage are:
i) Cut off trenches
ii) River side impervious blankets
iii) Land side seepage berms
iv) Pervious toe trenches
v) Pressure relief wells.
192
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
a) the additional weight needed to counteract these upward seepage forces and
b) the additional length required to reduce the uplift pressure at the toe of the berm
to tolerable values
Seepage berms may reinforce an existing impervious or semi impervious top stratum
or if none exists be placed directly on pervious deposits.
6.1.5. Types of seepage berms
Four types of seepage berms have been used, with selection based on available fill
materials, space available landside of the levee proper and relative costs.
1. Impervious berms. A berm constructed of impervious soils restricts the
pressure relief that would otherwise occur from seepage flow through the
top stratum, and consequently increases uplift pressures beneath the top
stratum. However, the berm can be constructed to the thickness necessary
to provide an adequate factor of safety against uplift.
2. Semi-impervious berms. Semi-impervious material used in constructing this
type of berm should have an in-place permeability equal to or greater than
that of the top stratum. In this type of berm, some seepage will pass through
the berm and emerge on its surface. However, since the presence of this
berm creates additional resistance to flow, subsurface pressures at the
levee toe will be increased.
3. Sand berms. While a sand berm will offer less resistance to flow than a
semi-impervious berm, it may also cause an increase in substratum
pressures at the levee toe if it does not have the capacity to conduct
seepage flow landward without excessive internal head losses. Material
used in a sand berm should be as pervious as possible, with a minimum
permeability of 100 x 10-4 cm per sec. Sand berms require less material
and occupy less space than impervious or semi-impervious berms providing
the same degree of protection.
4. Free-draining berms. A free-draining berm is one composed of random fill
overlying horizontal sand and gravel drainage layers (with a terminal
perforated collector pipe system), designed by the same methods used for
drainage layers in dams. Although the free-draining berm can afford
protection against under seepage pressures with less length and thickness
than the other types of seepage berms, its cost is generally much greater
than the other types, and thus it is rarely specified.
6.1.6. Pervious Toe Trench
Where a levee is situated on deposits of pervious material overlain by little or no
impervious material, a partially penetrating toe trench, can improve seepage
conditions at or near the levee toe. Where the pervious stratum is thick, a drainage
trench of any practicable depth would attract only a small portion of the seepage flow
and detrimental under seepage would bypass the trench. Consequently, the main use
194
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
of a pervious toe trench is to control shallow underseepage and protect the area in the
vicinity of the levee toe.
6.1.7. Pressure Relief Wells
Pressure relief wells may be installed along the land side of bunds to reduce uplift
pressure which may otherwise cause sand boils and piping of foundation material.
Wells accomplish this by intercepting and providing controlled outlets for seepage that
would otherwise emerge uncontrolled land side of the bund. Pressure relief wells are
used where pervious strata under a bund are too deep or too thick to be penetrated
by cut off or toe drains.
b) Wind Set-Up
An appreciable rise in water level may be caused on one slope of reservoir or pond
by wind action, particularly in shallow water. The wind set-up can be estimated by Zui-
Der-Zee formula:
U 2F
S= Cosθ
1400 D
Where:
S = set-up above still pond level (ft.)
U = wind velocity (mile/hour)
F = fetch (mile)
D = average water depth (ft.)
θ = angle of fetch and wind (degree)
For combined effect of wind set-up and storm wave the total rise in water level is equal
to wind set-up plus two third of wave run-up.
c) River Set
At curves the deepest point of the river cross-section is near the concave (or outer)
bank and the water surface there is higher than at the convex (or inner) bank. The
“river set” may cause a super elevation of the water surface at the concave (or outer)
bank and this can be estimated by Schoklitsch formula:
V2 R2
h = 2.3 . log
g R1
Where:
h = river set (ft.)
V = average velocity at the upstream straight reach (ft/s)
g = acceleration of gravity (ft./s²)
R1 = radius of curvature of convex (or inner) bank (ft.)
R2 = radius of curvature of concave (or outer) bank (ft.)
The “Government of Sind Bund Manual” (Ref: 3.6) indicates that “river set” may cause
a rise of the water surface at the concave (or outer) bank as much as 2.0 feet (0.6 m).
d) Recommended Freeboard
Sufficient freeboard should be provided above the design flood level for safety against
overtopping. For arriving at appropriate freeboard, the design flood level, the wave
run-up, wind set-up and river set be calculated. These figures should be added
accordingly and one foot additional freeboard be provided for contingent requirement
as factor of safety.
200
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
The ultimate foundation and fill settlement will be neglected against one foot
contingent provision.
By keeping in view the current local practices on freeboard for the typical flood
protection structures, influenced by different hydraulic conditions and design wind
velocity over land (U land ) assumed as minimum 50 miles/hour (80 km/hour), the
recommended minimum freeboard provisions for various types of flood protection
bunds are listed in the following table:
Recommended
Flood Protection
Hydraulic/ Wind Conditions Minimum Freeboard
Structure
(ft.)*
CONTAINING
STRUCTURES
(*) The recommended minimum freeboard values include one foot additional freeboard
for contingent requirement as factor of safety.
Sample calculations for determination of freeboard and design of stone protection on
or embankment are placed at Annexure-B.
6.2.2. Slope Stability
The slopes of the embankment must be stable under all conditions of construction,
design flood discharge, rapid flood draw-down, low flow level and earthquake forces.
The stability depends on the strength of the fill soil and foundation characteristics.
Similarly, the river banks needing protection will be designed for stable slopes.
Slope stability analysis requires a comparison between the state of stress in the soil
and soil shear strength along an assumed failure plane. The detailed slope stability
201
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
analysis will be carried out according to Method of Slices, by using Simplified Bishop
Method with computer package. The needed information will include the:
• Geometry of embankment
• Soil properties
• Design flood level and low water level of the river
• Phreatic line and pore water pressure
• Surcharge on the embankment
• Earthquake loads
a) Geometry of Embankment
The calculations will be carried out according to the typical cross-section of the
embankment for two different scanrios.
• The river-bed stone apron is intact and taken into account
• The scour of the river bed is modelled with assumed fully launched stone apron
b) Soil Properties
The following soil parameters will be derived from laboratory tests:
• Bulk density.
• Saturated density.
• Cohesion “c”
• Angle of internal friction “”
• Unconfined shear strength
• Permeability “k”
c) River Flow Levels
The design flood level and low flow level of the river will be established for the
particular embankment site to determine the phreatic line (high flood condition) and
subsequent draw-down (low flow condition).
d) Phreatic Line and Pore Water Pressure
i. Phreatic Line
In homogenous (isotropic) soils, the phreatic line is independent of fill material
properties and depends solely upon the geometry of and differential head across the
embankment. However, in case of more permeable fill material it will take less time to
develop as compared to materials having less permeability. The position of emergence
of phreatic line on landside slope is not influenced by the permeability of the
homogeneous fill material. The less pervious material will take longer to attain the
steady state position, but the ultimate position of the phreatic line in all cases will be
the same. Location of the phreatic line (or hydraulic gradient ) in the embankment will
be determined for the relevant seepage condition at the design flood level, by using
Casagrande’s Solution. The two Casagrande equations are:
202
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
S = h2 + d 2
a = d 2 + h 2 − d 2 − h 2 cot 2 α
Where:
S = length of parabolic line of seepage ( or phreatic line ) from riverside water
entrance point to the toe of landside slope (ft)
h = design flood depth on riverside slope (ft)
d = horizontal distance from riverside water entrance
point to the toe of landside slope (ft)
α = landside slope angle with horizontal (degree )
a = length of surface of seepage upward from the toe landside slope (ft)
The phreatic line will be taken as boundary between the below saturated and above
dry embankment soil properties for use in the stability analysis of side slopes.
ii. Pore Water Pressure
Pore pressure ratio (ru),which is defined as the ratio of pore water pressure to vertical
load at the base of each slice, will be used for the slip circles analysis for all given
conditions except for riverside slope at flood draw-down condition. For this condition
only pore water pressure will be used. The pore water pressure equation is:
u = r u .γ.h
Where:
u = pore water pressure
ru = pore pressure ratio
γ = total unit weight of soil (dry weight above phreatic line and saturated
weight below phreatic line)
h = depth of soil from top surface
The Simplified Bishop Method computer package will facilitate the pore pressure ratio.
For draw-down condition analysis the pore water pressure will be determined by the
above equation and utilized for determining the pore water pressure conditions. For
common soils the value of “ru” ranges between 0.3 and 0.1
e) Surcharge
A surcharge of 200 lbs. per ft2 (975 kg/m2) on the top surface of embankment will be
applied for stability analysis.
f) Earthquake Load
The acceleration due to earthquake will be adopted on the basis of fifty percent (50%)
reduction for the horizontal and vertical components for the pseudostatic method
calculations. For example the effect of a maximum ground acceleration (in central
Punjab area) due to an Open Basis Earthquake (OBE) of 0.12g (pseudostatic) in the
free field will be taken for the stability analysis. Thus on the basis of 0.12g OBE and
fifty percent (50%) reduction in accelerations the earthquake loads adopted in analysis
will be:
203
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
periods of low river flows when the drilling and other auxiliary equipment could be
mobilized and deployed in the river bed. The investigation will essentially provide the
following information:
• Material type and zoning
• Permeability of river bed material
• In-situ density
• Hardness of cobles and boulders
• Bearing pressure capacity
6.2.4. Hydraulic Gradient
When water flows along flood embankment, the water seeps into the embankment soil
from river side towards the country side. It is a line which demarcates the saturated
soil zone with the dry zone of the embankment. The profile of this saturation line is
called Hydraulic Grade line (HGL) or Phreatic Line. This line is a flat parabola in nature.
but for practical purposes it is taken as straight line. The slope of hydraulic grade line
depends on the type of soil of the embankment. The cohesive soils offer more
resistance to flow, hence the line is steeper while in the non-cohesive soils, it is flatter.
Usually a gradient of 1V:6 H is taken in well graded loamy soil. The HGL can however
be measured by installation of small stand-pipes of say 2 inches (5 cm) diameter
installed at different locations across the embankment. The water levels thus observed
will plot the HGL. Typical values of hydraulic gradients for different soils are listed in
the following table:
Type of Soil HGL Slope Hydraulic
Gradient (H:V)
Clay 4:1
Clayey Loam 6:1
Sandy Loam 5:1
Silty Loam 6:1
Fine Sand 8:1
Coarse Sand 10:1
For safety of embankments HGL should have enough cover of soil over it so that it is
not exposed in any conditions of rain cut and soil erosion or poor maintenance. The
bad, erodible alkaline, and sodic soils should have bigger factor of safety. The Exit
Gradient along the base of the embankment shall also be covered by increasing base
width or providing a foundation cutoff/key.
After the size of flood embankment has been established with a given top width and
side slope, the existing practice is to test the cross-section against hydraulic gradient
and if found necessary, back berm (or pushta) is provided to keep the hydraulic
gradient within the cross-section. The hydraulic gradient is an assumed line of
saturation in the embankment body. Normally, for common soils (natural deposits) it
206
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
is assumed as 6:1 and it should lie at least 2 ft below NSL at the toe of the bund. A
minimum cover of 4 ft is provided above hydraulic grade line if it exits on the landside
in made up soils (Figure 12).
For the first category, it is recommended to design the embankments on the basis of
hydraulic gradient line as per current practices. The second category of embankments
will be designed by ensuring stability of slopes and preventing their failure through
piping.
When fill material of the embankment is not sufficiently homogeneous the flood water
may reach the landside slope with a sufficient hydraulic head to cause instability or
piping of the fill material. This may result in complete breaching of the embankment.
In such cases a horizontal drainage layer will be designed to deliver the seepage water
safely to the landside toe of the embankment. A rock toe may be provided at the
landside slope.
The introduction of landside filter will establish a definite exit for the seepage water.
Landside toe of the embankment will not become wet and pushta will no longer be
needed. Also, the piping and internal erosion of the embankment will be controlled and
chances of embankment breaches due to these factors will be minimized.
The drainage layer shall be selected to be free draining as well as maintaining filter
compatibility with the embankment fill. In general for filteration:
d15 filter
≤5
d 85 base
For drainage, where the base can be embankment fill or the foundation material under
the filter.
d15 filter
>5
d15 base
In some cases, the drainage layer may consist of a coarse granular material enveloped
by a filter material.
a) Landside Toe Filter/Toe Drain
When fill material of the embankment is not sufficiently homogeneous the flood water
may reach the landside slope with a sufficient hydraulic head to cause piping of the fill
material. This may result in complete breaching of the embankment. In such cases a
sloping filter connected with a horizontal filter will be designed to deliver the seepage
water from sloping filter to the landside toe of the embankment. The sloping filter will
be covered with compacted protective material. For protecting and keeping the filters
in place a rock toe will be provided at the landside slope.
The introduction of landside filter will establish a definite exit for the seepage water.
Landside toe of the embankment will not become wet and pushta will no longer be
needed. Also, the piping and internal erosion of the embankment will be controlled and
chances of embankment breaches due to these factors will be minimized.
Normally, filter material shall comprise hard and durable gravel or crushed rock
conforming to the following gradation limits:
208
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
Sherad et al in their publication Earth and rock dams recommend the following data
for rip-rap and filter beneath.
6.2.7.3. Recommended Riprap Design Criteria
Maximum Wave Height Minimum average Rock Size Layer Thickness
(feet) (D50) (Inches) (Inches)
0-2 10 12
2-4 12 18
4-6 15 24
6-8 18 30
8-10 21 36
MINIMUM THICKNESS OF SINGLE LAYER FILTER UNDER RIPRAP BLANKETS
Computed Wave Height Minimum Filter Thickness
(feet) (Inches)
0-4 6
4-8 9
8-10 12
Dumped rip-rap is, however, very costly and should be provided where absolutely
necessary.
214
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
It is kept filled with water throughout the flood seasons to soak / saturate the
bund body thoroughly and expose any routes of leakage enabling the operators
take remedial action in time.
Wetting channel concept was introduced in Punjab in 1965 with the construction
of the first wetting channel along right marginal bund of Panjnad Barrage, which
was quite successful. The concept thus gained popularity and now a sizeable
number of flood embankments have the support of wetting channels.
f) Normally on all barrages the Wetting Channels have become deshaped and
filling of the wetting channels by pumping from tubewells operated on diesel oil
is very expensive and Electric tubewells cannot be relied upon due to load
shedding.
g) Unfortunately the wetting channels and soaking operations are receiving casual
attention with adverse results i.e. bunds even with wetting channels still leak;
as was experienced during the floods of 2014.
A typical cross-section for wetting channel is placed as Figure 16.
7. BREACHING SECTIONS
Breaching sections are safety valves / fuse plugs provided on the Right Marginal
Bunds of the barrages and some bridges. The concept of breaching sections was
introduced after super floods of 1973. General land slope in Pakistan is roughly from
North East to South West in direction, and thus water escaping from a breach in LMB
does not return to the same river but travels to next river inundating area enroute and
spreading misery in its wake, while the water escaping through a breach in RMB flows
back to the same river after some distance with low or moderate losses.
This fact was the basis for specifying / identifying the locations for breaching sections
on Right Marginal Bunds in 1977. The size of breaching sections was intended to allow
an escapage of about 100,000 cs.
The activation of breaching section was made subject to approval by a standing
committee and the pre-requisite site conditions were.
a) The rate of inflow to the structure is most likely to be more than the discharging
capacity of the structures.
b) The critical / emergency gauge at a fixed location on left marginal bund or
elsewhere has exceeded the limiting value and the river discharge still rising.
Taunsa barrage was not expected to essentially need a breaching section and so none
was provided. However it was laid down that in case of a rare emergency the link bund
and shank of spur / may be cut. But there has been no need to activate this section
uptill now. With the remodeling of Taunsa barrage, this section is likely to remain
redundant. In the past, the breaching sections at Alexandra Railway Bridge, Chiniot
Railway Bridge, Riwaz Railway Bridge, Sher Shah Railway Bridge, Jinnah Barrage,
Khanki Headworks, Sulemanki Barrage, Balloki Barrage, Trimmu Barrage, Panjnad
Barrage and Sidhnai Barrage have been activated in various years.
The present conditions demand a detailed review of this phenomenon for future
guidance.
7.1. Activation of Breaching Sections
The breaching section can be activated through,
• Mechanical means
• Blowing up the body of the bund through use of explosives
The first option of machinery usage involves;
• Planning the activation sufficiently ahead of the activation time deadline. This
will require careful study of flows and possible hydrograph to reach a realistic
and clear positive decision.
• Keeping the required machinery units at the breaching site ready for action well
before the designated activation time.
• Providing lighting arrangements for night working if so needed.
218
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
It is necessary to be decisive and specify the exact number of resources required. The
urgency should also be impressed. The probable route, the floods will take, should be
reported, after making local enquiry and verifying it on a contour map and topo sheet
and flood flow diverted along the valley line or where they would do the least damage.
Immediate intimation of any breach should be given to the Railway, Highway, Gas
Transmission authorities by the Sub-Divisional Officer, and the Executive Engineer, if
any of them likely to be affected.
The Executive Engineer should also immediately inform the Superintending Engineer
(and in very serious cases also the Chief Engineer directly), the Collector, other
Executive Engineers and the Divisional Forest Officer. Later, the Executive Engineer
should make a detailed report to the Superintending Engineer, indicating the measures
taken and the steps proposed to be taken for protecting the ends, closing the breach,
and diverting the water where it would do the least damage.
Immediately a breach occurs, the first step to be taken is to prevent the breach
widening. Very often velocity at the ends will be found very high and simple protection
of ends is not likely to prove successful. In such cases, attempt should be made to
divert the side current away from the breached ends of the bund. For doing this, the
following procedure is suggested:
• A cross groyne about 20 to 25 feet in length and at right angles to the bund line
should be constructed as near the breached end of the bund as possible where
people can stand and work even with some difficulty.
• If the depth of water is 6 feet and under, single groyne will suffice. For greater
depths double groyne will be necessary. The construction of this groyne will
reduce the velocity on the downstream side of it, in some portion.
• Similar groynes should then be constructed, as far apart from the first groyne,
as will permit people to stand and work, till the breached end of the bund is
reached and the current diverted away from the bund.
• Sometimes it will so happen that the water while coming out of the breached
section will hug the rear side of the bund and start eroding it The only course to
be adopted in such cases is to construct groynes at right angles to the bund as
stated above till the velocity against the bund is reduced and no erosion is likely.
• Once the current is diverted there will be no need to protect the ends as there
will be no velocity of water against the ends and no erosion will occur.
8.1.3. Preliminary Measures Necessary for Successful Closing of
Breaches
The closing of a large or difficult river breach is always a very serious business,
involving large expenditure, not likely to be undertaken before studying the river
conditions and the practicability of closing the breach and the proper time and manner
of doing so. A fully considered plan has to be immediately formulated to close the
221
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
breach successfully at the first attempt. The sooner the closing of a breach is
undertaken the less difficult the close operations will be and lesser damage will result.
The following preliminary investigations are essential to the successful closing of a
large or difficult breach and should be taken in hand as soon as possible.
i. An estimate of the establishment required.
ii. A detailed survey of the site to determine the best location for an armoured ring
bund enclosing the breached ends;
iii. A true appraisement of the river course upstream and downstream of the
breach and a fairly accurate forecasting of the river conditions in respect of
gauge and discharge ;
iv. A liberal estimate of the materials required and the organization necessary for
getting them ;
v. A liberal estimate of different kinds of labour required and the steps necessary
to obtain the required strength in due time;
vi. An appreciation of the improvements in communication necessary for transport
of materials, labour, etc.
8.1.4. Improvement in Communications Required
The first step is to improve the communications to enable speedy transport of materials
and carriage of labour from, the most suitable railway or road station. Similarly
adequate housing and sanitation arrangements for the labour and arrangements for
provision of food steep should be made in advance of the labour being brought on the
site. The Sub-Divisional Officer, overseers, and sectional mistries should be provided
thatched huts at site of work.
Ramps, pathways, turning platforms for vehicles, and all such necessary
arrangements to facilitate quick transport to each site of work without delay and
hindrance should be made, as this saves time and waste of energy in the long run.
8.1.5. Earth Required
The quantity of dry earth and sand that will be required should be carefully estimated
and then the place from where the most suitable earth can be obtained with the least
effort and at minimum lead should be carefully decided in advance.
8.1.6. Definite Plan of Action Essential
The final details of the plan for closing the breach would have to be filled in on the
results of the preliminary investigations mentioned above.
A definite plan of action must, however, be made as soon as possible having due
regard to all the circumstances of the case, and once a plan has been made it should
be rigidly adhered to, in all essentials. There is always a tendency, on such occasions,
particularly at the first sign of difficulties, for every-body, from the individual diver
upwards to shower ill digested gratuitous suggestions, particularly suggestions
222
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
following the line of least resistance. It is best not to be diverted from the determined
pursuit of a reasoned plan of action, as hesitation does not inspire confidence in the
minds of the establishment or labour and confidence essential to the success of the
plan.
8.1.7. Closing process for a Large River Breach
The details of closing a breach must be adapted to the circumstances of each case.
The method consists, in essence, of connecting the two ends of the breach with an
armoured ring bund. The ring has vertical side slopes and is, therefore, protected on
either side by a strong crib-work fencing (longitudinal killa bushing to be also called
'muhari') (Figure-17) consisting of a double row of vertical posts and intermediates,
tied longitudinally and transversely, and propped with stays. The 'muharis' are lined
with mats and filled with brushwood or sand-bags, to break the force of the current
and to minimize the earth in the ring bund being carried away by the flowing water.
1. In order to decide where to align the ring bund, detailed under water soundings
are taken on the river and land side in a regular grid.
The soundings should be 50 feet apart and more detailed soundings may be
required near the proposed line of muhari. The grid has to be accurate and
should be taken for big breaches by direction and pivot flags in the same way
as the position of a boat observing discharges is fixed from the shores. The grid
will extend beyond the scour-hole and until reasonable soundings (not more
than 15 to 18 feet depending on the available maximum length of vertical
stakes) are encountered. At the same time soil samples should be obtained,
especially from the proposed alignment in order to avoid taking it through or just
upstream of a sandy bed.
Other things being equal, an upstream ring bund is always to be preferred, on
account of (a) the additional strength obtained due to arch action, (b) the lesser
lead of earth as foreshores begin to be deposited on the sides as the ring is
built on the upstream, (c) a downstream ring is subject to the full earth and
water pressure after it is closed, without any support due to arch action, (d)
upstream 'muharis' themselves are excellent protection against widening of the
ends of the breach and (e) in the event of a sudden flood, before the ring is
joined, the ends of an upstream ring will act as diversion groynes, tending to
deflect the current to the main river.
2. The site of the killa busing cannot be too carefully selected. In fixing the
alignment, the main considerations are low depths and good, inerodible bed
soil. A long line in shallow water, or in good hard clay soil resistant to erosion,
is far easier to construct, and far more likely to be successful than a short line
in deep water or in sand. The length of the available vertical posts governs the
limit of depth upto which the work is possible. For example, if the maximum
length of vetical is 22 feet and looking to the nature of the soil a 6 feet
penetration is desirable, with a required freebord of 4 feet, the work can only be
223
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
done upto soundings of 12 feet, as between suitable depths or suitable soil the
more important consideration is suitability of soil.
3. The ring bund, is so aligned as to leave sufficient space on the up-stream side
of it for the new bund. It is not desirable to take the ring bund itself on the final
alignment for the embankment, since the fencing and brush-wood will be
perpetual sources of trouble.
4. Having decided the alignment of the 'muhari' the time schedule would be made
out so as to close the breach during the most favourable river conditions
possible. Accordingly, the closing of the final gap should be timed to coincide
with the maximum fall in the river, or, at any rate, the final closing should not
coincide with a rise in the river.
5. Materials and labour required are carefully estimated and arranged for. The
estimate should be liberal, allowing at least 25 percent extra for contingencies,
as it is fatal to run short of materials during the critical stages of the work.
Arrangements should be made in advance to see that materials and labour are
sufficient at all stages to continue unhindered, even if the first attempt fails.
6. It is necessary to decide from the start where the gap for final closing should
be. In fact, on the proper selection of the closing gap, depends the success or
failure of the closing operations. The more difficult portions, that is those where
the depths are large and the current rapid, should be tackled, if not first, early
in the proceedings, and the final gap should be, comparatively, less difficult in
construction. Even though it may be necessary to do substantially more than
half, say even three-fourths the works, from the more difficult end, where
materials are more scarce and other conditions more severe, in the interest of
having the best site for the final gap, this has to be done. The labour is
organised, accordingly, so that the earthwork in the more difficult portions is
completed well ahead of the attempt to close the ends.
7. The closing gap is selected with great care and forethought and after detailed
examination of the site, with particular regard to the following factors:-
a. It is sited where the bed is made up of soil which is more resistant to
scour and erosion, hard inerodible clay being the best and coarse sand
the worst;
b. It is on a ridge so that the depths and velocities of flow are comparatively
low ; the ridge should extend for some distance, particularly on the
downstream side of the gap, to avoid the depths and velocities
increasing due to cutting back by retrogression when the flow through
the gap increases ;
c. It should not be in the direct line of the main current but as far away from
the main current as possible so that the flow would only spill over the
gap.
225
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
8. Having decided where the final closing of the two ends is going to be, the flow
through the breaches can be regulated, if and as necessary, by 'chhabbing' /
whittling the muharis'.
Subject to this, however, it is desirable to do the killa bushing framework only
short while in advance of the earthwork, in order to avoid the framework being
scoured away. In the deep 'ghara' portions particularly, the earthwork should
immediately follow the framework.
9. Having selected the position where the ring bund should be on the plan
prepared from the observation of soundings, the exact location should be laid
out on the ground with stakes, pegged in the ground, at roughly 10 to 20 feet
apart. The muhari work is then commenced simultaneously from both ends.
The progress of the work should be so arranged that the muharis from both
ends duly strengthened by earth work should reach the proposed ends of the
gap simultaneously. If it is decided to have an upstream ring bund, it may be
necessary to have diversion groynes to enable the ring bund to proceed as
otherwise the current may hug one of the ends of the ring bund and make
further progress difficult.
10. The fencing ('muhari') consists of double groynes, 4 feet wide, the main
verticals ('munas') in each row being 4 feet apart, with 4 feet to 6 feet
penetration below bed, and having at least 4 feet free board above the
anticipated maximum level for the rest of the season. Longitudinal horizontals
('waras') 10 feet to 12 feet long, connect the tops of three vertical posts, with 1
foot overlap at either end by means of holes drilled at 4 feet to 5 feet centres,
which fit chamfered or tapered ends of the vertical posts ('munas').
Intermediate verticals ('panjars') 1 foot apart with less penetration below bed,
say 3 feet to 4 feet, have their top ends tied by strings to the longitudinals. The
function of the intermediaries is to act as stiffeners and prevent displacement
of the packing and the mats.
Cross distance pieces ('patties'), 6 feet long, with holes drilled at 4 feet centres,
tie together transversely the two ends of vertical posts at the proper distance
apart, as well as distribute the load evenly between the two rows. In places,
bracings of wire or strong rope are also provided, if the strain appears, or is
likely to be, too great and tending to displace the verticals.
Such double groyne muharis lined with mats and filled with brushwood packing,
are provided both on the upstream and on the downstream side of the earth
ring bund, which is 8 feet to 12 feet wide. If the earth ring bund is made 10 feet
wide, the inner rows of the double groynes will be 10 feet apart. The earth ring
bund is with advantage kept 12 feet wide to permit free work by donkeys, unless
there is shortage of earth.
Transverse pieces ('makris') connecting the two groynes together, are
temporarily provided at every alternate vertical; they are 12 feet long with holes
at 10 feet centres for a ring bund 10 feet wide, and may be removed when
226
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
earthwork reaches them, if found to hinder the progress of the earthwork. After
the earthwork is completed, they are preferably, replaced to serve as additional
bracings.
Inclined diagonal struts or stays ('thunies' or mals') are provided on both sides
at every alternate vertical, unless the height of the ring bunds is large, when it
should be provided at every vertical on the land side and at every alternate
vertical, on the river side. It is better to have natural Y-shape forks for fixing to
the vertical posts; but where natural forks are not available in sufficient number
and size, they may be got prepared with suitable joints. They have a taper at
the lower end, and are embedded at least to the same level as the main vertical
posts. It is best to fix the Y of the struts about two-thirds the distance up a
vertical.
11. Boats are very useful for constructing the muhari, as the verticals (munas) as
can be driven from the boat conveniently where the water is more than 3 feet
deep. Where the velocity is high, the boat can be anchored and tied with guy
ropes from the banks, thereby fixing its position.
12. In the 'ghara' (i.e., where the 'muhari.' crosses a deep water channel), one or
both sides of the double 'muhari 1 may need to be filled with sand bags instead
of brushwood, if the current is so swift that ilait packing will not prevent undue
wastage of earth filling. In case sand bags are used, it is necessary to see that
the rows are laid consecutively in headers and stretchers to minimize leakage
through the joints. A little initial care in laying the bags saves a lot of trouble
later. Throughout the width of the deep water channel an apron of gunny bags,
50 feet wide x2 feet thick, is provided on the downstream (land) side of the
muhari to prevent scouring of the channel with the disturbance caused by the
flow through the muhari. In this channel, at the ends and in all low or dangerous
portions, the downstream line of verticals and the props are supported and
protected by sand bags placed round their feet.
13. Immediately following the framework, comes the lining with mats and next the
packing of the two compartments, on each side of the space left for earthwork,
with brushwood, the upstream packing being intended to deaden the flow and
the downstream packing to prevent the intermediate earth from being washed
away. Where the velocity is high, it will be advantageous to inter-twine lai brush-
wood to the stakes as it would then prevent the inner brush-wood filling from
being carried away by the current. The 'lai' brush-wood due to greater depth
may also float and it may be necessary to weight the brush-wood down with
empty cement bags, filled with sand or earth.
The inner lines of the two outer compartments are lined with mats to support
earthwork vertically and to minimize the wastage of earth. The most suitable
position for the mats is along upstream face of the second row and along the
downstream face of the third row of vertical stakes, counting from the upstream
side. The fixing of the mats precedes the filling with brushwood.
227
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
For the deep water channel and the final gap, where the current is swift, a close-
weave mat, or two or three thicknesses stitched together, are used. The mats
are prepared outside in advance, stitched in long lengths, and are laid in situ
with sufficient over-lap, so that they do not shift or buckle out of position, leaving
voids interfering with the earthwork.
Following the packing, comes the earthwork in the central compartment. Before
the earthwork commences; it is seen that the framework is as strong as
possible, since the earth has to be held vertically constraining it from assuming
its natural angle of repose.
14. Earthwork done by means of donkeys, carrying earth from the two ends, may
with advantage be supplemented by earth from tip-wagons, motor lorries and/or
barges towed by tugs or launches. If there is dry earth available nearby,
anywhere in the vicinity, basketeers may be employed to supplement the work
by donkeys. Work has to be organised to see that the main work which is done
by donkeys, is not interfered with, but helped by other arrangements. Space
being limited, the outturn and progress of works will depend greatly on proper
organization.
15. In the deep 'ghara' portions earth should be not thrown but carefully deposited,
so as to minimize avoidable wastage. As earth, particularly sand, takes a very
flat slope under water, in order to accelerate the progress of work, in addition
to the double thickness of mats along the inner rows of verticals, screens of
mats are also temporarily constructed across muhari, every 20 feet apart,
pegged down by bamboo 'panjar'. The panjar and mats are removed carefully
as earthwork reaches them.
16. A critical stage is reached when the earthwork ends have to be joined and the
gap closed. Owing to the constructed waterway and the consequent high
velocity, earth is then liable to be carried away as fast as it is deposited. For the
junction, sufficient earth is collected at the two ends approximately to cover a
gap of three times the volume, after filling the compartments on either side with
sand bags, earth is dumped into the narrow gap as quickly as possible.
If there is any difficulty in joining the two ends, a third row of 'muhari', of similar
design, is constructed on the downstream side, some 30 to 40 feet below the
lower groyne in the form of a ring 'muhari'. This acts as cushion or stilling
chamber and is a further check to the flow, facilitating the joining of the ends
and minimising wastage of earth.
Divers are made to stand in line, shoulder to shoulder, with mats abreast of
them, while the earth is being fast dumped in from the two ends. They puddle
the earth with their hands and feet, till the ends are successfully joined.
Where possible, arrangement should be made to supplement the earthwork
from the two ends by earth from a barge placed along side the closing gap.
228
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
17. As soon as the ends are joined, care is taken to see that the framework does
not collapse due to the excessive earth pressure by providing more props or
stays and gunny bag supports, behind the rear line and also in front of the
upstream line if there is no water against it. The cross-pieces joining the
upstream and downstream muharis are restored and bracings of wire and
strong rope are also provided, tying the two groynes together.
The earth ring bund, too, has to be immediately strengthened by providing front
and rear slopes of pucca earth, particularly in the width of the deep water
channel, removing the brushwood packing if necessary.
All earthwork is done in layers 6 inches deep, freely watered and clods broken.
The earthwork is throughout kept at a safe level against the increasing river
levels.
Work cannot be considered completed till the ring bund is raised 4 feet above
the highest likely levels during the rest of the season and until adequate front
and rear slopes have been provided.
18. The method suggested in sub-paragraph 16 supra for closing final gap always
gives anxious time as the quick rush of water through a narrow gap scours out
the muharis and makes the closing of gap very difficult. It is therefore suggested
that as soon as it is noticed that the velocity through the site selected for closing
the breach is increasing and that if there be the slightest doubt that soil
underneath may be scoured out, the entire length of the gap selected which
may be anything from 50 ft. to 100 ft. long, should be paved with a layer or two
of gunny bags to prevent the soil from scouring. The gap can then be easily
filled by placing gunny bags layer by layer, one layer being put in the entire
length before the second layer is started. By this way the scour in the central
gap will not occur and breach will be easily controlled. As soon as the layers of
bags have come to within 2 feet below the water level the ends should be raised
above and the central gap diminished and earthwork commenced in front of the
gunny bags to prevent any leakage through the bags thereby washing away the
earth from the bags. As soon as the central gap is reduced to 10 feet, the bags
should then be laid layer by layer throughout this length and the flow of water
through that narrow portion also stopped. Earthwork should then be pushed
through and the entire gap in earth filled up. When this method is adopted,
enough bags filled with earth, should be kept ready. A boat or two may also be
required to deposit the bags and they too should be kept handy.
19. If after closing a breach, there is a 'blow-out' i. e., a serious leak in the ring bund
threatening into a breach, the following method of tracking it has been found
successful. If it is impossible to trace the upstream face of the leak, a small ring
bund of gunny bags, protected with juckwork, say 8 to 10 feet diameter is
therefore constructed around the downstream end of the leak and water is
allowed to pond up in the cistern so formed. As soon as the level in the
compartment cistern becomes nearly the same as the upstream water level,
the leak ceases to flow. The cistern is then wholly filled in with good soil and
229
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
consolidated and thereafter, the original 'ring bund' is opened up and the leak
traced right upto its upstream end and plugged in its full course.
The methodology and resources deployed for closing breaches in flood bunds in
Punjab have in the past been those explained above. However with passage of time
and changed circumstances machinery use has largely replaced manual effort.
8.1.8. International Practice
International Practice in general almost exclusively utilises the deployment of required
machinery due to more expensive and rather non availability of required human
resource but generally the procedures are similar to those employed in Pakistan and
India.
However for small breaches and flood proofing requirements some innovations have
been devised, which are prohibitively expensive to be adopted in Pakistan e.g. Aqua
fencing, rubber dam and sheet piling etc.
The best practical option for Pakistan is to follow our own practices with improvements
necessitated by unique conditions prevailing in our country.
9. RIVER TRAINING WORKS
Shifting channels of the river, have sometimes to be trained to flow within a certain
Khadir width and course. The structures constructed to achieve this end are generally
termed as River Training Works. These are permanent structures normally
constructed with earth and in some cases with stone armour. These can be groynes
spurs and studs of various types and design, diversion bunds and cunnettes
(temporary diversion measures) and guide walls etc.
For details of design etc., the readers are advised to refer to Chapter 5 in Volume-1.
10. RIVER DIVERSION AND DIVERSION BUNDS
River diversion is essentially required when
• A bridge or barrage is constructed outside the active river channels but within
flood way. After completion of the structure, the is diverted into the structure by
closing the active river creeks by diversion bunds also called Ganda Bunds,
water is thus raised to flow into a cunnette leading to the structure. The river is
forced to flow in the new course by construction of guide banks, spurs and
embankments. It is usually a site specific scenario in which various options are
critically reviewed based on past experience, knowledge of river engineering
and hydraulic model studies. Diversions of Indus river through Ghazi Ghat
Bridge and Taunsa Barrage during its original construction are good examples.
A study of those diversions from research publications imparts good knowledge
of river control and engineering.
• In order to protect towns, abadies, infrastructures, canal systems and important
roads, the river diversion is sometime necessitated. When meandering loop of
an alluvial river deepens too far that the above mentioned structres or any other
strategic installations are prone to erosion, then it becomes imperative to cut
230
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
this loop at its neck by an artificially dug channel called leading cut or cunnette.
At downstream of this cut the active river channel is closed by Gunda Bund to
raise the water levels so that it directs flow in the cunnette widening it to
accommodate Main River. Sometimes it is also assisted by spur and
embankments. Hydraulic model studies are a good support to decide these
interventions.
The typical layout of diversion bunds and cunnette is shown in Figure 18.
control points and around cities and other strategic locations, where river is trained to
flow in a predetermined course, the flood heights are contained and floodplains are
protected and checked with embankments, called Marginal Bunds. The area behind
the Marginal Bunds are supposedly safe if there is no breach because the land beyond
margins could be lower than the flood heights.
The topography of the Punjab is such that, during high floods, the water spilled over
the right bank of the rivers returns back to the same river but the one which breaches
the left bank seldom returns to the same river because of the natural land slope.
Therefore, this induces very severe flood damage to life and property. Throughout the
Punjab, and in the world in general, alluvial soils are one of the most fertile and easy
for tillage and also subject to flooding with regimented alluvium, thereby replenishing
fertility. From ancient times, all the great civilizations flourished along river for these
reasons. These lands are highly populated and inhabited in the world. Their dwellings
and infrastructures are naturally subjected to onslaught of floods.
The flood water, in fact, is a treasure which needs to be preserved and conserved. It
should be collected by making detention structures and reservoirs or should be
diverted and dispersed where it is required. A catastrophic nature of flood situations
can be converted into fortune by adopting effective flood management and planning.
The water creating flood is an immense resource for forthcoming dry seasons.
In the mountainous reaches of the river, the majority of rain falls on steep slopes of
hills and plays significant role in developing the flood peaks. The water is collected in
stream with low time of concentration and stream slopes are also steep to improvise
the flood carrying capacity thus causing flooding in the sub-mountainous and plain
regions. Each river has its catchment area comprises of watershed. The bushy,
cropped and forested watershed slopes create lower peak and longer duration of flood
with low sediment yield than barren, naked and eroded slopes which generate higher
peaks of shorter duration with high sediment yields due to excessive erosions.
In Punjab, the Indus and its five tributaries are aligned from North-West to South-East;
one joining the other with the right bank higher in elevation than the left bank. The
other general slope of Punjab plains is from west to east. This setting of the Punjab
topography has made it natural land where this treasure of flood water is carried due
to gravity almost all over. There are also sufficient number of sites in the mountainous
regions where the excess water can be stored for use during the dry weather
conditions for irrigation of early and late Rabi and Kharif crops, in addition to cost-
effective hydro-power generation. If we ignore to utilize these free and scarce water
resources efficiently, these lands will be converted from the green fields into arid and
semi-arid barren lands during the forthcoming global climate change and
environmental degradation.
12.3. Formation of River Channel
The river behaviors and its fluvial impact on fertile alluvial flood plains, depends on the
relationship between flood water, sediments conveyance, meandering pattern
frequency of its occurrence and general topography. The size of river channel
234
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
dimensions, however, does not depend on the maximum or minimum flows. How much
water a channel will carry depends on the frequency of occurrence of the dominant
flows. Low flows, which occur quite frequently, are not important in the characteristics
of the channel formation, neither does infrequently occurring extra-ordinary floods.
Channel characteristics depend on the dominant discharges of moderate magnitude
which has high frequency of occurrence. In very high and exceptionally high floods,
the river rises above the banks and overflows into the flood plains.
12.4. Watershed Characteristics
The watershed or catchment is the natural land mass of river streams where
substantially all hydrologic processes occur in space and time. Topography, rock and
soil, geology, forest, vegetation cover, land-use, land erosion, stream network, shape,
slope etc. are the principal factors which generate variability of flood-producing
mechanism.
Watershed characteristics pertain to the land and river channel elements of watershed.
Channel elements are hydraulic properties of the river tributaries, such as, size, shape,
channel cross sections, slope, roughness, and length of channels in the network.
These characteristics are somehow responsible for runoff volume, peak discharge,
timing of runoff, base-flow, infiltration, evaporation, interception, deposition, erosion,
etc.
12.5. Watershed Size
The watersheds can be classified as small, medium and large. This classification looks
vague but may be used to understand the characteristics mainly on the basis of area.
As a rule of thumb, the area of small watershed is less than 250 km2, the medium size
is 250 to 2500 km2 and the large is more than 2500 km2. These ranges are rough
guidelines and may vary from one geological area to another.
To produce flood on these watershed, two phases are considered simultaneously;
Land phase and channel phase. Large watershed have well-developed channel
networks and thus the channel storage is dominant. These watersheds are less
sensitive to high-intensity rainfall of short duration. On the other hand, the small
watersheds are opposite of this. The behavior of watershed of same size may differ if
they do not have similar land and channel phases.
12.6. Velley Storage and Dispersion
The flooding severity may be checked if the detention and dispersion strategies are
adopted for protection of downstream floodplains.
Interception is one element of valley storage which is defined as the precipitated
water retained on the drainage basin through its adherence to abstract objects, such
as dykes, vegetation, forests, forest floor cover, buildings, infrastructure, or any other
resistance objects above surface of the ground.
The principal factors effecting the amount of water that is intercepted in a valley
storage are: storm characteristics, vegetation characteristics, such as, plant species,
235
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
leaf coverage, age, heights, density, directions of plant rows, forest floor cover and
the season of the year.
Dispersion of flood to other drainage lines and towards the natural depressions is
another area that helps for the attenuation of peaks. Dispersion through terraced
cropped land with dykes on their edges is an ancient practice for saving moisture for
the crops and attenuation of the flood peaks.
12.7. Surface Runoff Volume
Runoff volume is the total volume of the flowing water over a period of time. This is
actually the area under the flood hydrograph. The peak of the flood at a certain point
may be attenuated due to various resons.; This results in increasing the base time of
the hydrograph since the volume remains the same.
An estimate of runoff volume from a watershed depends on the precipitation,
infiltration, evaporation, transpiration, and interception and depression storage. Each
of these characteristics are complex in nature and may interact with other variables to
either enhance or reduce runoff. The manner in which these variables interact in time
and space makes direct determination of runoff very difficult. Therefore, the runoff is
estimated using methods that reflect the combined effect of variables in an individual
watershed. Thus each watershed has a different solution, but general approach of the
solution may be similar may be alike. The text books provide variety of solutions for
the estimation of surface runoff, such as SCS Curve Number Method include
references and Water Balance Method, etc.
12.8. Streamflow Hydrograph
A streamflow hydrograph at any point on a stream is a graph of the time variation of
discharge at that point. The graph is plotted with the discharge on the ordinate and
time on the abscissa. A recording stream gauge if plotted on time distribution gives a
continuous flow hydrograph but it is customary to refer to the term hydrograph as to
the time variation of flood discharge for a particular storm.
A hydrograph of a given storm reflects the influence of all the physical characteristics
of the river basin and, also to some extent, the storm causing the flood. The shape of
hydrograph actually reflects the flood producing characteristic of the river and the
intensity of storm, its drainage basin. When a stream flow hydrograph is plotted using
short time interval, the influence of contribution of tributary channels in main river flow
becomes apparent. No two drainage basins produce identical hydrograph for the same
storm. Hydrograph from similar drainage basins may be similar but are not the same.
Hydrograph from the same drainage basin for successive storms of similar intensity
are not be the same.
Total runoff depicted on a hydrograph corresponds to a given storm event. A
hydrograph has two components: direct flow and base-flow. Direct flow is the sum of
overland flow and quick interflow resulting from a particular storm. The base-flow
comprises of groundwater flow and delayed interflow. The volume of total runoff is
determined by including in stream flow hydrograph all runoff between the base-flow
236
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
discharges occurring prior to the storm up to the same base-flow discharge after the
storm.
Effective rainfall is that portion of the rainfall that results in direct runoff. Similarly
rainfall excess constitutes that portion of the rainfall that contributes to surface runoff.
The difference between the effective rainfall and the excess rainfall is that former
includes the later plus some abstractions. But these are sometimes used
interchangeably. Thematically a rainfall storm is considered to be composed of two
portions: one that contributes to runoff and the other that contributes to abstractions,
including interceptions, evaporation, transpiration, depression, detention and
infiltration. The hydrograph prepared on the basis of effective rainfall is called the
effective rainfall hydrograph.
12.8.3. Unit Hydrograph
The concept of Unit hydrograph (UH) was developed in 1932 for determining surface
or direct runoff hydrograph (DRH) from the effective rainfall hydrograph (ERH). The
unit Hydrograph (UH) of a watershed can be defined as DRH resulting from one unit
(1 in. or 1cm.) of effective rainfall(ER) occurring uniformly over the watershed at a
uniform rate during a unit period of time. The unit period of time may not necessarily
be equal to unity; it can be any finite period of time up to time of concentration. As a
matter of fact, unit period of ER is the period for which UH is determined. As soon as
this period changed, so does the UH for a specified watershed. Usual practice is
having 1-hour UH, 6-hour UH, 12-hour UH, or 1-day UH.
Since the UH is applicable for direct or surface runoff only, the base-flow is separated
from the total runoff hydrograph. In order to derive the DRH, several assumptions are
made in applying the UH method. It is not possible to fit these assumptions perfectly,
but they must be reasonably satisfied before UH method can be used so that
erroneous results are not obtained.
12.8.4. Instantaneous Unit Hydrograph (IUH)
If the duration D of the ER does not depend on UH by letting D be diminished
indefinitely, the UH so obtained is called Instantaneous Unit Hydrograph (IUH). Thus
IUH is a hypothetical UH due to the ER whose duration tends to zero as a limit, but
whose volume remains unity. It is then evident that IUH is independent of ER.
12.8.5. Application of Unit Hydrograph for Flood Management
The UH of a specified duration has many uses in environmental and water resource
development. The UH can be used to determine the watershed response due to a
given rainfall event if an estimate could be made of the abstractions not contributing
to the runoff. This has immediate application for flood forecasting and warning. With
the knowledge of the time distribution of the runoff response, both the flood peak and
its time of occurrence are known. For the maximum possible rainfall, the maximum
possible flood can be determined. Thus the UH can serve as an indicator of flood
producing characteristics of a given watershed.
Another application is in determining the effect of flood protection works on water shed
response. This can be done by comparing the UH of a stated duration derived prior to
the protection works with the UH of the same duration derived after the completion of
238
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
the works. The UH after completion of protection works shall have an attenuated peak
with milder rising limb and larger time base.
Still another advance application is to determine soil erosion from upland watersheds
if this idea is applied on sediment flow. If the sediment concentration of a given
watershed is known, the unit sediment graph for a specified duration can be
constructed. This in turn can be utilized to estimate erosion due to a specified rainfall
on the given watershed.
12.8.6. Limitations of Unit Hydrograph Application
The unit hydrograph should be derived from fairly large floods; otherwise it may not be
representative of the actual conditions during large floods. All the propositions adopted
in the theory of UH are empirical without any mathematical accuracy demonstrating
rational hydraulic analysis. As a matter of fact, the knowledge of applied hydraulics
and hydrology is not based on pure science but have been derived from practical
operational experiences to formulate empirical formulas. Nevertheless, therefore,
many hydrologists support application of UH as a useful powerful practical tool for
runoff analysis. This theory is particularly adequate in the range of flood experienced
on natural watersheds, such as in Punjab. These results are very useful predictions
well in-advance for meaningful flood control and management.
13. FLOOD FREQUENCY ANALYSIS
Flood frequency analysis is performed to determine the frequency of the likely
occurrence of flood. This information is required for the design of reservoirs, barrages,
flood ways, embankments, bridges, highways, railways and canal infrastructure
protection. This is also useful in network layouts, hydro-electric power plants,
economic analysis of flood plain development, change in land use and draught
mitigation etc.
It requires hydrological data, like length/duration of flood record, randomness of data
and homogeneity. The length of record should be like more than 25 years for the
derived distribution to be credibly acceptable. It must be understood that the factors
causing winter floods are quite different for those during summer floods. These two
type of floods cannot be combined in single record. Stochastic processes and missing
data interpolation is sometimes estimated using regional analysis from other, so-
called, similar watershed basin.
13.1. CONCEPT OF PROBABILITY, P
To simplify, let us assume tossing of a coin, for Head or Tail. The probably of
occurrence of either head or tail is 50% since there are only two possibilities in this
case. The probability of getting Head is ½ and for tail is also ½. If the coin is defect-
free and the tossing is unbiased, the number of appearance of Head or Tail will be one
half of the number of tossing. In more than one trial, the probability of an event is equal
to the number of successes divided by number of trials. Therefore, the probability of
an event is non-negative and is less than 1. The sum of probabilities of all possible
outcomes in any trial is equal to 1. For two independent mutually exclusive events, the
239
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
probability of each event is equal to the sum of probability of two events. Also for two
independent events, the probability of their occurrence is product of individual events.
For two different events, the probability of each event is equal to probability of the
other event minus the joint probability of both events. These rules of probability can
be successfully applied in describing the flood events.
13.2. RETURN PERIOD, T
Return period is reciprocal of probability. Suppose the coin is tossed once a year. On
the average, its ‘head’ will appear once in two year. So the ‘return period’ of getting
head is once in two year where the probability of getting head is ½.
Thus
Return Period T=1/P
T is an average value of period of occurrence
Therefore, the flood that has exceeded on the average in 100 year (called 100-year
flood) has a probability of exceedance on the average of any one year equal to 1/100
or 0.01.
The probability that flood will not occur (P’) in any year is
P’ = 1 – P (1 - T1 )
The probable value of storm not occur in ‘n’ successive year
(P’)n = (1-P)n = (1-1/T)n
The probability that flood will occur at least once in n successive years
= 1-(1-1/T)n
The concept of Return period is very important. A 100-year flood, Q100 is the quantum
of flood having average chance of exceedance once every 100 year over a long period
of time.
The matter can be further illustrated with examples.
Example: 1
Compute the Return Period of Design Flood to be used for the design of a bridge.
There is 5% probability that that the storm will occur in next 5 years.
0.05=1-(1-1/T)5
T= 1/ (1- (0.95) ^ 0.2) = 97.98 years
Example: 2
At a rainfall station established years ago, there has been rain only on a single day in
April. Estimate the probability of (a) having rain in the entire month of April and (b)
having at least one rainy day in April.
Data period of each April during 3 years = 90 days
Probability of having rain on any one day of April = 1/90
Probability of not having a rain in any one day of April = 1-1/90
Probability of having rain in entire month of April = (1-1/90) ^30
240
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
= 71.52%
Probability of having at least one rainy day in April = 1-(89/90) ^ 30
= 28.48%
Example: 3
What is the probability of occurrence of a flood equal to or greater to 20 year (a) in
next 3 years (b) in next 20 year?
P = i/20= 0.05
Probability of not having a flood next year =1-0.05= 0.95
Probability of not having a flood in next 3 year =1-(0.95)3
=14.3%
Probability of not having flood in next 20 year = 1-(0.95)20
= 64.20%
13.3. FREQUENCY DISTRIBUTION
Water resources projects often require frequency distribution of magnitudes, volumes,
durations etc. For example, the frequency with which the flood of a particular
magnitude will be equaled or exceeded is frequently needed. The observed data forms
the very basis. Some of the widely used distribution are:
• Binomial Distribution
• Geometric Distribution
• Poisson Distribution
• Exponential Distribution
• Gamma Distribution
• Normal Distribution
• Log-Normal Distribution
• Gumble Distribution
• Log-Pearson Type III Distribution
For detailed description and calculation strategy, refer to a good text book of Hydrology
for Engineers.
Out of all these, the last four distribution methods are widely used in flood frequency
analysis.
13.4. PEAK FLOOD ESTIMATION
The estimation of peak discharge is required for flood protection and prevention works,
design of hydraulic structures, flood plain management, disaster management etc.
There are many empirical methods developed specific to each particular catchment.
An empirical method follows:
13.4.1. Rational Methods
241
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
routing can also be reversed to estimate upstream floods from the known downstream
hydrograph.
13.6.1. Methods of Flood Routing
There are many methods and each method has its own assumptions and empirical
characteristics which may make it distinctly suitable for a particular application.
Therefore, an extreme caution should be exercised in choosing particular methods.
These methods can be classified as: hydrologic and Hydraulics. The hydrologic
method simply uses equation of inflow, outflow and storage.
It is pertinent to mention that these methodologies are based on assumptions of well-
defined and flood plain. The application to natural rivers takes into consideration the
irregular shape and complexity of channel section. The backwater effect, river
junctions and effect of a dam cannot be accounted for in a hydrologic method. The
hydraulics method are may be used provided, these effects are properly simulated.
13.6.2. Flood Routing Through Reservoirs
When a flood wave passes through a reservoir, the peak is attenuated and its time
base is elongated.
The operation of the reservoir can have significant effect on the routing because water
stored in a reservoir may be discharged in a controlled and uncontrolled manner.
There is a continuous change in probability that reservoir will be filled to its
conservation level by releasing some flows downstream during a particular flood
season while keeping some room for the forthcoming monsoon season lest it might
remain empty due to any probable mistake in flood forecasting. Therefore, based on
continuous knowledge of Flood Forecast, a Rule Curve for filling the reservoir is drawn
and followed with the careful risk analysis both for flood damages and non-filling of
reservoir.
To illustrate, the operation of Mangla and Tarbela Reservoirs are discussed below.
Based on the irrigation demands, forecasted river inflows and available storage
capacities, reservoir operation studies have been carried out to develop the reservoir
operation criteria in the form of Rule Curves. This process was initiated with
commissioning of Mangla reservoir in 1968.
Mangla Reservoir and its operation during 1992 Floods is very critical to look at. The
primary function of Mangla Dam Project is to conserve 5 MAF of surplus river flows
and then utilize them for supplementing the natural flows in Jhelum and eastern rivers
during scarcity periods. Its secondary function is to generate hydropower from the
water released for irrigation purposes. The project initially did not have exclusive
capacity for flood regulation. Since most of the catchment area of river Jhelum is in
held Kashmir, so there is a difficulty in having credible flood forecasting.
1992 flood during was caused by the extremely unusual and freak meteorological
events of the combined effect within 24 hours of monsoon depression and westerly
disturbances, which resulted in intense rainfall in Mangla catchment creating a flood
244
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
hydrograph of twin peaks occurring at short interval. Historically high floods, in excess
of 700,000 cfs had single peak with generally sharp fall. In this particular case point of
time, the first peak of 987,000 cfs was formed within a short duration of 11 hours on
September.9, whereas second peak of 1,090,000 cfs followed on September, 10. In
quantitative terms, the combined flood was to the tune of 2.70 cfs (ever highest in
recorded history). At this stage Mangla had virtually no regulating capacity for design
constraints and poor flood forecasting. Out of the first peak 342,000 cfs were absorbed
in the reservoir and 645,000 cfs were discharged through the spillway which was a
considerable attenuation. In succession, the second peak, was also managed by
absorbing only 157,000 cfs and the remaining 933,000 cfs played a havoc downstream
which is a highly developed populated area.
This story tells us how important a reservoir could be for flood mitigation if initial
capacity for regulating floods could have been kept in design and accurate flood
forecasting. A most realistic Rule Curve then could be drawn for reservoir filling and
operation at various inflow/outflow scenario at different elevations.
With the raising of Mangla Dam, and consequently the conservation level, the capacity
of flood storage is considerably enhanced at Mangla reservoir. Hopefully the 1992
flood scenario shall not repeat.
In a similar context, Tarbela dam is also a storage reservoir, where irrigation
requirements dictate power generation. The Rule Curve for filling and operation of
Tarbela reservoir was developed and it was contained in the special report by project
consultants entitled “Procedures for First Filling of the Reservoir in summer 1974”.
Tarbela dam was not primarily designed for flood management. However, within the
design limitations and management procedures followed, the Tarbela reservoir
provides limited flood peaks attenuation. The prevailing low to very high flood limits
below Tarbela varies between 250,000 to 800,000 cfs. The valley immediately
downstream of Tarbela can take high discharges safely without causing extensive
damage. It is, however, desirable to temporarily hold Indus flood peaks in reservoir
and then controlled subsequent release to prevent synchronization with peaks of other
tributaries at downstream locations. For this purpose, the design criteria for flood
routing through Tarbela reservoir is based on three elements: First,, all major floods
are routed at the maximum conservation level through the spillways. Second, the
design flood of 1,775,000 cfs be routed through the existing outlet facilities with a
nominal surcharge of 2 ft. above the maximum conservation level. Thirdly, probable
maximum flood of 2,128,000 cfs is handled by various outlets with a surcharge of about
2.13m. above the conservation level, still having a free board of about 2.43m to top
embankment elevation. Reservoir filling criteria developed from safety considerations
provide limited flood regulation. Ensuring the availability of catchment information at
Tarbela and using flood routing procedures, and simultaneously having information
about the inflows from downstream tributaries, i.e., Kabul, Soan and Kurram rivers and
Panjnad discharge before its confluence with Indus, flood peaks can be somewhat
attenuated at Tarbela and later to little extent at Chashma to avoid high peaks in
downstream locations. Flood regulation is, therefore, an incidental aspect of Tarbela
245
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
while the most important element is assured impounding in the reservoir to use stored
water in the following low flow periods. Filling of the reservoir is accomplished based
on 'Rule Curve' criteria evolved from estimated inflows and irrigation requirement.
During actual filling of the reservoir, ‘Rule Curve’ is followed as far as possible with
incidental flood regulation within this envelope. However, it does not eventually make
much of an impact on flood situation except for occasional damping of high peak during
the filling season.
13.6.3. Flood Routing Through River Channel and Flood Plains
The river channel and flood plain routing is more complicated than reservoir routing in
which storage and outflow is uniquely related. When a flood wave propagates from an
upstream reach of a river in a flood plain, it encounters differential resistance along its
course due to various reasons and interventions and thus water flows at different
velocity relative to each other owing to relative slowdown effect on flood plain area
compared to active river channel area. If flood plains are scientifically and strategically
managed with empirical knowledge base, floods peaks can be attenuated with an
appreciable lag time. The correct estimation of resulting channel and flood plain
storage is somewhat complex. The different methods developed for the stream flow
routing differs in the mechanics they account for the relationship between inflows,
outflow and storage. Some of the methods are indicated for further reading from
hydraulics text books and their application should be carefully applied depending upon
their assumptions.
• Convex Method
• Muskingum Method
• Muskingum crest-segment routing
13.6.4. Flood Routing Through Watershed Management
The flood water levels can be lowered and flood peak discharge can be reduced if
water shed and catchment slopes are forested with dwarf leafy trees, shrubs and
bushes. These would have an essentially good affect to prevent soil erosion, reduction
in sediment yield and preservation of top fertile humus layer of soil. In other reaches
with bare slopes, check structures across flow ravines, the small height detention and
dispersion structures if constructed, would result in delay action for flow to accumulate
thus lowering the peak and increasing time lag. The offered resistance to flow not only
slow down eroding velocities preventing sediment erosion and rapidly help in
vegetation and crop growth. These actions are strongly recommended in combination
on mountainous and sub-mountainous reaches of river. Watershed management also
increases the life of the capacity of reservoirs and is a sustainable tool for flood control
/ prevention.
Even in the Alluvial Flood Plain if bush plantations are forested or low height dykes
are erected transverse to the river flow axis in the flood plain, the time lag can be
induced in flow within river course and that of over the flood plain. These interventions
surely attenuate the flood height but increase time for flood volume to pass. The crops
should therefore be resistant to the time lag envisaged.
246
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
2,120 1,996 93 32 9 2.100 3.18 (p) Thal 950 3,781 / 1946 Five (5)
Districts 3,353 Km d/s of
Mianwali, Kalabagh
Khushab, Town,
Bhakkar, District
Layyah & Mianwali
Table 2: Jinnah Barrage’s Data
Muzaffar
garh
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
barrage due to silt free water flows through the barrage This Retrogression resulted in
occurrence of abnormally high velocities downstream of the barrage due to lowering
of downstream water levels thereby washing of hydraulic jump got of stilling basin
resulting in repeated structural damages of friction blocks, inverted filter blocks and
stone apron. The safety of barrage was thus jeopardized.
The barrage was remodeled, refurbished and modernized through PMO Barrages,
Irrigation and Power Department, Government of the Punjab during 2012 to 2016. The
safety of the structure has been ensured by providing a subsidiary weir downstream
of the barrage in order to contain hydraulic jump and achieve favorable flow conditions.
14.2.1.2. Chashma Barrage
Chashma Barrage was part of Indus Basin Replacement Works. It is located on river
Indus about 56 km2 downstream of Jinnah Barrage. Its purpose is to supply water to
CJ-Link Canal on the left and Chashma Right Bank Canal on its right side. Unlike other
barrages, a small storage reservoir has been provided at the Barrage to re-regulate
the supplies of Tarbela reservoir.
Table 3: Chashma Barrage’s Data
D G Khan
Khan and
Punjab in
Comman
Comman
d area of
KPK and
Water to
Transfer
Jehlum,
Ismaeel
District
d Area
Indus
Dera
(Cusecs)
Capacity
21,700
5000
C J Link
CRBC
Name
Discharge
(Cusecs)
9,50,000
Design
between
Abutments
Length
3,556
(ft)
1967-71
Year of
Const
Km d/s of
in District
Barrages
Khushab
Location
Kundian
Five 56
Jinnah
near
250
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
This barrage is different from other barrages for it has a storage capacity in the pond
area of its lake which was originally 0,8 MAF but same had reduced to 0.1 MAF in
2016 due to sediment deposition. A low head hydel power station has been
constructed in 2001 on the right side of Chashma Barrage for power generation.
14.2.1.3. Taunsa Barrage
Taunsa Barrage is third and last diversion structure in Punjab on river Indus. It is
situated 12 km from tehsil Kot Addu of Muzaffargarh District of southern Punjab. The
Barrage was completed in 1958. Three command canals and one link canal off take
from this barrage; Taunsa- Punjnad Link Canal and Muzaffargarh canal from its left;
DG khan canal and Kachi canal from its right P Link canal has a capacity of 12000 cfs.
Muzaffargarh canal has a designed capacity of 5908 cfs which irrigates irrigated
agriculture of Muzaffargarh and Rajanpur districts. DG khan canal having designed
capacity of 8790 cfs is a ridge canal which mostly irrigates on left side along foothills
of koh e Suleiman range spread up to river Indus. Kachi is a lined canal having
capacity of 5000 cfs at head, runs parallel to DG Khan Canal on mountainous side
which transfer Indus water share of Baluchistan through blind reach from Punjab. Both
canals are subjected to heavy and recurrent spate floods from hill torrent floods
emerging from Suleiman range and therefore are prone to severe damages.
14.2.2. River Jhelum
River Jhelum constitutes the western most of the five tributaries rivers of Indus that
merges with the River Chenab upstream of Trimmu Barrage near Jhang City. The
Jhelum rises from a deep spring at Vernag, in the held state western Jammu and
Kashmir .The river meanders northwestward from the northern slope of the Pir Panjal
Range to Wular Lake at Srinagar, which control its flow. Emerging from the lake, the
Jhelum flows westward and crosses the Pir Panjal in a gorge some 7,000 feet deep
with almost perpendicular sides. At Muzaffarabad, the Jhelum receives the Neelam
River from left and Kunhar River from right and then bends southward. Near Mangla
dam the Jhelum breaks through into broad alluvial plains. At the city of Jhelum the
river flows along the Salt Range to Khushab, where it again bends south to join the
Chenab River near Trimmu. The total length of the Jhelum is about 720 km.
In accordance with Indus water treaty, Pakistan has exclusive rights on the flows of
this river and India is restrained from building any storage reservoir.
In Pakistan two major structures have been built across River Jhelum, Mangla Dam
and Rasul Barrage
14.2.2.1. Mangla Dam
Prior to Mangla Dam, a head works was constructed close to this site near Mir Pur
Azad Kashmir to off take Upper Jhelum Canal. This was part of triple canal project
comprising Upper Jhelum Canal, Upper Chenab Canal from Marala on River Chenab
and Lower Bari Doab Canal from Balloki on River Ravi. The project was conceived in
early nineteenth century and in December 1915, the Viceroy of India inaugurated
Upper Jhelum Canal.
251
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
In 1961 it was decided to build storage facilities to enable transferring of excess waters
of western rivers in the command area of eastern rivers. The Mangla Dam was the
first of the two dams constructed on River Jhelum at Mangla site to reduce the
shortcomings of eastern rivers, the other being Tarbela Dam on River Indus.
The construction of Mangla Dam was started in 1961 and completed in 1967. The dam
had a storage capacity of 9.12 km3 (5.88 MAF) with a lake spread over 251 km2. The
dam has an embankment length of 3140m. It has installed capacity of 1000 MW. The
upper Jhelum canal now take supply from tailrace of Mangla Dam. The capacity of the
dam is continuously and rapidly reducing due to sedimentation. To counteract this
phenomenon, the Mangla Dam Raising Project was started in 2004 and the main dam,
spillway and its allied works were completed in 2009. This project effectively raised
the dam height by 30ft to 482ft (10m to 147m), thereby raising the maximum water
conservation level from 1202ft to 1242ft (367m to 379m). This increased the dam's
storage capacity by an additional 2.88 MAF from 4.51 MAF to 7.39 MAF. Besides, it
is expected that after raising the height of the Mangla Dam by 30ft (10m), the power
house will continue to generate 12 percent additional energy per year and that
increases its installed capacity from 1,000 MW to 1,120 MW.
tributaries of Jhelum and Indus Rivers at feasible sites. Besides flood control, these
can also be utilized for power generation, irrigation and other domestic usages in
remote areas.
15.5.2. Alignment of Flood Retaining Embankment
Considering the meandering action of the alluvial rivers in the alluvium of flood plains,
the flood retaining embankments should be placed nearly parallel to the meandering
axis of the river at a fair distance from the meandering belt based on model studies
through considered opinion of River Engineers and socio- public considerations. As a
guiding principle, there shall be minimal chance of active parallel flow along the
embankment in order to avoid possible erosion/scour by swinging of sinusoidal
meandering channels. The lateral translation of meandering pattern shall also be kept
in view in particular. The alignment essentially depends on general topography,
infrastructure location of canal, road, power networks, and dwelling concentration and
geo-tech parameters of foundation soil. In special cases, the embankments require
protection with revetments, aprons and armored spurs protruding in to the river course.
15.5.3. Height of Flood Retaining Embankments
This is primarily determined by the accepted probability of exceedance (Return Period
which eventually fixed the Design Flood) and degree of protection based on economic
analysis. The additional protection necessitated by adopting a smaller probability of
exceedance may give relatively large increase in the incremental cost. Height of
embankment is, thus determined by design flood and the wave height generated by
winds and/or earthquake plus-factor of safety. The height of flood embankment is also
governed by the subsidence of embankment in poor soil conditions, sub-soil water
level after construction, sedimentation pattern and degree of protection required.
Federal flood commission of Pakistan recommends a free board of 2.13m. above 1973
Flood heights which is close to 100-year return period flood.
15.5.4. Attenuation of Flood Height along Flood Retaining Embankment
Wider the flood plains better the influence on attenuation of flood waves because of
the larger storage capacity of flood water which is further improved due to different
discharging capacity of the main river channels within the flood plain sandwiched
between left and right flood marginal bunds. As a matter of fact, during floods, river
comes out of its channels and starts flowing into the flood plain, the roughness offered
by flood plain is much more than that of river channel because of vegetation, trees
bushes and other obstructions. This results in to faster flow in river channel and slower
flow in flood plain. This differential effect lower the flood heights if the flood plains are
made to offer greater resistance by planting leafy bushes in rows transverse to flow
and raising dividing fields in the same manner systematically. The duration of flood
increased but flood heights are lower. A non-uniform flood water storage in flood plain
can thus be created temporarily.
260
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
15.5.5. Spurs
The spurs are one of the most favorite river training embankments in Pakistan. Spurs
usually take starts from afflux embankments and protrude in the river at angles
transverse to flow in order to engage and encounter the high-velocity currents of flood
water in order to create no or low flow zone in vicinity of the embankment. The head,
or nose of the spur so to say, is armored with revetment and protection against
potential scour. It should be strong enough to deflect the river currents on the desired
path. It is essential that a scale physical model study be done based on fresh river
survey to ascertain the result of prototype placement. The spurs have potential to
change the entire river morphology and fluvialogy. Therefore, extreme vigilance should
be exercised before these are constructed at site. These are, though, very successfully
applied at barrages, bridges, and dams etc. to have control on the river when
meandering courses are squeezed to flow in a restricted channel to pass through the
structures. These are also indicated for their application where a particular strategic
areas are in need to be protected from river erosion. The spurs may not attenuate
flood heights but are very effective to control erosion and river deflection.
15.5.6. The Negative side of Flood Embankments and spurs
The flood management practices in Pakistan certainly carries benefits for some
segments of the rural communities, specifically those rich famers who huge farming
lands along with effective political powers. However, with their cause and affects,
some of the areas can experience utter disasters leading to loss of property,
husbandry and human lives. Engineer and planners have given insufficient and
inefficient consideration to the sediment load ingress carried within the banks of river
channels through the interventions of embankment infrastructures. This in turn causes
unfriendly unpredictable flow patterns and swollen peaks. The richer farmers with the
state support problems influence building of embankments and spurs for solution of
their localized benefits and allowed ‘Straight Jacketing’ of river reaches through by
disturbing natural meandering patterns. Transferring miseries of one area to another
area should not be a solution. When excessive amount of water is drawn out of a river
leaving behind sediments and then by constructing narrow width levees along the
banks give rise the bed levels of river channel compared to surrounding areas. This
tantamount to create a situation in which water flows at higher peaks attracted to come
out of river into flood plains. The risk of flood becomes ‘anthropogenic’. The careless
and unscientific planning can exacerbate the flooding.
15.5.7. Flood Control by Storage of Flood Water
This is the most direct method of Flood Control. The flood in some situation is totally
prevented or the peak of flood wave is attenuated by detention of flood water in the
reservoir or lake. The stored water can subsequently be utilized for power generation,
irrigation and other industrial and domestic use. In fact this is one of the best methods
of water conservation and management for arid/semi-arid land development which is
a typical case in Punjab. There are two types of Reservoirs, controlled reservoirs like
Tarbela and Mangla dams and uncontrolled reservoirs like detention basins for hill
torrents and tributaries of rivers.
261
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
plans are approved by the Chief Engineer drainage and flood. A sample outline of
flood fighting plan is given below:
16.1. Salient Feature of The Concerned Division
• Location
• General description
• Administrative setup
16.2. Flood Protection and River Training Works
• Design parameter of training works
• Location map
16.3. Brief History of Past Flood Events
• Hydrograph of past floods
• Flood eventualities
• Flood damages
• Remedial works
• Flood stage wise inundation plans
• Lag times between control points
16.4. Design Data
• Flood limits
• Highest historic peak floods
16.5. Flood Fighting Strategy
• Review of previous flood damages and restorations
• Pre-flood inspections
• Embankment safety analysis
• Identification of vulnerable reaches prone to breaches
• Identification of river reach engagement close to embankments
• Strategy of flood fighting at highlighted vulnerable
16.6. Flood Fighting Arrangements
• Pre-flood arrangement
• Selection of watching camp locations
• Watching establishment
• General arrangement at various sites
• Special arrangements at strategic and vulnerable sites
• Watching materials specific to site
• Arrangement for bathymetric surveys
• Illumination arrangement
• Logistic arrangements for staff
• Communication arrangements
264
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
• Transportation arrangements
• Law and order control requirement
• Health, safety and environment protection
• Liaison with other department
• Role of the army and when to call
• Role of the civil administration and when to call
16.7. Detail of Encroachments
• Identification of Locations
• List of encroachers
• Steps taken to remove encroachments
• Impediments of encroachments to flood fighting
• Action plan to remove encroachments
16.8. Duty Roster/Flood Fighting Program
• Strength of gang at each location
• Regular establishment roster
• Work charge establishment roster
16.9. Training to Watching Establishment
• Patrolling
• Reporting and logging of emergencies
• Communicating to whom and when
• Regular repairing
• Detection of rodent activates and its culmination
• Repairing leakages and boils
• Use of various flood fighting materials
• Deployment of machinery and equipment
• Seeking help from whom and when
16.10. Important Telephone Numbers
16.11. Operation of Breaching Sections
• Government procedures for operating breaching section
• Conditions for operating breaching section
• SOP for operating breaching section
• Strategy for inducing breach
• Liaison with concerned departments
• Inundation maps with flood wave heights
• List of affected human and animal abodes and other assets
• Evacuation strategies by civil authorities
• Flood relief measures
• Operation strategy of the breaching section
• Military establishment arranging explosive and detonation
265
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
before the flood season so that necessary remedial works could be satisfactorily
executed before onslaught of the flood season. The hydraulic data during high flow
season and flood seasons must be observed during rising and receding flows.
A three-member team comprises of competent engineers for each group of
embankments shall be nominated to conduct checking and inspections, before, during
and after the flood for comprehensive observations and analysis, thereby suggesting
remedial works to be carried out and extent of vigilance to be exercised by the incharge
incumbents. At vulnerable and strategic locations the arrangements could be
enhanced in accordance with site-specific requirement.
SOP must include:
• Inspection schedule before, after, and during the flood
• Collection of data
• Interpolation of existing data with designed / proposed data
• Safety analysis
• Probability of floods
• Identification of vulnerable reaches and their short term and long term remedial
works.
• Identification of reaches prone to breaches, erosion or scour
• Efficiency of existing gauges and need for new gauges
• Calibration and authentication of rating curves
• Locations of flood fighting camps
• Checking the effectiveness of flood fighting camps
• Procedures for fighting various flood situations
• Setting requirements of transport and equipment
• Bathymetric surveying and mapping arrangement
• Laying procedures for fighting incoming floods
• Step by step arrangement for operation of breaching section and its S.O.P
• Readiness of inundation plans for possible breaches.
• Inundation plan of flood plain at various stages of low, medium, high, very high
and extra ordinary high floods.
• Routing of flood through breaches with possible inundation and damages
thereof to private, public and strategic infra-structures.
• Review of adequacy of design of flood protection and control structures.
• Encroachments and their effects on flood protection activities, vandalism etc.
• Deletion of rodent activities and presence of “boils” on country side.
• River embayment and its possible translation inducing erosion and scour.
• Suggestion of remedial measures for direct river action.
• Land subsidence if any
• Conditions of armored head of spurs and revetments.
• Identification of cut-off in a meandering loop for internal river management.
• Poor quality soil reaches and its remedial measures.
268
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
• Recommendations for provision of sand or clay, core and rock-toes in a high fill
embankments.
• Necessity for providing foundation key, cut-off and a Pushta in a high fill
embankments.
• Adequate Free-board against wind generated flood waves.
• Physical inspection and Analysis report
269
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
References
i ADB Publications
Indus Basin Floods
Mechanism, Impacts and Management (2013)
ii Proceeding Diamond Jubilee Session
Pak Engineering Congress Vol-62 (1987)
iii Msc. Dissertation on Guide lines for location, protection and operation
of River Diversion Weir on Alluvial Plains by Muhammad Azam Ch:
(1990)
iv Safety Evaluation of Flood Bunds by Engr. S.M.A Zaidi (2010)
v Papers for P.E.C Proceedings Vol-IV (1986)
vi Weir and Barrages across Alluvial rivers
Iqtidar H Siddiqui (2007)
vii Principles of River
Engineers PPh Jansen , L Van Bendegom
viii Flood Control Technique for Effective Alluvial River Management
Prof. Engr. Ali Rizwan, Engr. Muhammad Azam Ch:
Paper # 559 66 Annual session PEC (1996)
ix On Flood Frequency Analysis at important Discharges Masonry sites
of Pakistan Rivers.
Prof. Engr. Ali Rizwan, Engr. Muhammad Azam Ch:
Paper # 554 66th Annual session PEC (1996)
x Irrigation Engineering
B.L. Gupta Amit Gupta Satya Prakashan, New Dehli
xi Symposium on Flood Management in Pakistan 65th Annual session
P.E.C (1994)
xii Irrigation and hydraulic structures Dr. Iqbal Ali (1993)
xiii Water Resources of Pakistan
Dr. Nazir Ahmad (1993)
xiv Managing the Indus River Basin in light of Climate Change
Janes L Wescoat, (1991)
xv A productive and Water secure Pakistan
270
MANUAL OF IRRIGATION PRACTICE
RIVER TRAINING AND FLOOD MANAGEMENT
List of Tables
TABLE 1: SALIENT FEATURES OF D G KHAN HILL TORRENTS ................................................................... 273
TABLE 2: IMPROVED FLOOD W ATER DISPERSION AND INCREASE IN CULTIVATED AREA . ........................... 291
TABLE 3: RESULTS OF FREQUENCY ANALYSIS......................................................................................... 296
TABLE 4: SALIENT FEATURES OF MAIN TRIBUTARIES OF CHENAB RIVER................................................... 301
TABLE 5: SALIENT FEATURES OF MAIN TRIBUTARIES OF RAVI RIVER ........................................................ 302
List of Figures
FIGURE 1: MAJOR HILL TORRENTS AREAS OF PAKISTAN ......................................................................... 272
FIGURE 2: CATCHMENT AREA OF DG KHAN HILL TORRENTS .................................................................... 274
FIGURE 3: TYPICAL HILL TORRENT IRRIGATION SYSTEMS ......................................................................... 279
FIGURE 4: DIFFERENT CONSTRUCTED HILL TORRENT STRUCTURES ........................................................ 283
FIGURE 5 TYPICAL FLEXIBLE HILL TORRENT STRUCTURES ...................................................................... 284
FIGURE 6: EXISTING AND PROPOSED DRAINAGE SYSTEM ........................................................................ 293
FIGURE 7: POTOHAR AREA .................................................................................................................... 295
FIGURE 8: TRIBUTARIES OF RIVER JHELUM ............................................................................................. 299
FIGURE 9: W EIR WITH UNLINED STILLING POOL FLOOR ............................................................................. 306
FIGURE 10: GRAPH OF X AND (ZO-FG).................................................................................................... 307
FIGURE 11: DEPTH OF SCOUR ACCORDING TO SCHOKLITSCH FORMULA ................................................... 308
FIGURE 12: COUNTER W EIR .................................................................................................................. 309
FIGURE 13: DENSITY OF GABIONS .......................................................................................................... 310
FIGURE 14: FORCES ACTING ON THE W EIR STRUCTURE........................................................................... 311
FIGURE 15: W EIR WITH LINED STILLING POOL FLOOR, JUMP CONTROL BY BROAD CRESTED WEIR ................ 312
FIGURE 16: GRAPH OF (Z1-FB) .............................................................................................................. 313
271
MANUAL OF IRRIGATION PRACTICE
HILL TORRENTS MANAGEMENT
Period Designed
Cultivated Area
Year Of Observ-
25 years Return
Area Flow
Elevation (ft)
Originating
above msl
Discharge
SR. NO
NAME
Ation
Sq miles
Hectare
Sq km
Cusec
Acres
The catchment area can be primarily divided into four units. About 16 percent of the
area lies at an elevation higher than 1,524 m (5,000 ft) above msl, 24 percent between
914 m and 1,524m (3,000 ft-5,000 ft) above msl, 46 percent is situated between 305m
and 914m (1,000 ft-3,000 ft) above msl, while the remaining 14 percent of the area is
below 305m (1,000 ft) above msl. The slope of the area is generally from west to east.
The area situated in the foothills is called “Pachad Area” or the piedmont plain has
been formed by the rich alluvial deposits brought by hill torrents from the Suleiman
Range. Basin irrigation is practised since the time immemorial by constructing earthen
bunds/levees around the huge fields to store about one meter depth of water which is
percolated and used subsequently for crop growth.
Climate of the area is arid and is characterised by the movement of Monsoon in
summer and Western waves in winter. Summer temperatures are fairly high and
winters are cold. Average annual rainfall varies from about 125 mm to 300 mm (5 - 12
inch). Pattern of rainfall is erratic, patchy and unpredictable.
1.4.1. Major Hill Torrents In DG Khan Distt Above Tounsa Barrage
Three Major hill torrents join River Indus within boundary of Punjab province upstream
of Tounsa Barrage, these are kaura, Vehova and Sanghar. When there is heavy
rainfall in catchment area of these hill torrents, these contribute significant quantum of
discharge upstream Tounsa barrage. One of such event observed was in year 2010
floods.
a) Kaura Hill Torrent
Kaura Hill Torrent Basin is situated in the northern area of the DG Khan District. It is
the only basin which shares area from the three provinces of the country - Balochistan,
Khyber Pakhtoon Khwah (KPK) and Punjab. However, the sub mountainous and plain
area of the basin is in Punjab Province where the hill torrent debauches from their
'Darrah'/terminal gorges and fans out to disperse the flows.
Kaura Hill Torrent originates in the form of a small stream in Baluchistan Province. The
stream flows southward and. after covering a small distance takes an eastward turn.
Hereafter, the flow direction remains almost same up to its confluence with a
neighbouring torrent The torrent retain the name of 'Guzai River' upto its crossing of
the Provincial boundary of Baluchistan, where it receives the flows of Mashkha Khwar
from the left. After the union, it enters NWFP and assumes its name as 'Kaura' which
continues to receive flows of a number of small stream inlets from both the sides, and
enters Punjab Province a little above the Darrah.
After passing through the Darrah, it fans out extensively and the main part of its flows
joins 'Vehowa' Hill Torrent on its right. Kaura Hill Torrent encompasses a catchment
area of 523 sq kms (202 sq miles) and flows towards the Indus River after crossing
the CRBC and the Indus Highway. A number of Hill torrent crossing structures of a
cumulative capacity of about 100,000 cusec has been constructed over the CRBC with
a leading channel convey out flow into Indus River.
276
MANUAL OF IRRIGATION PRACTICE
HILL TORRENTS MANAGEMENT
of the hill torrent are i) Misnit Lahar; and ii) Sorgaric Chur. The torrent finally joins Indus
River near Shah Sadar Din.
b) Vidore Hill Torrent
Vidore Hill Torrent has the same source of origin as that of the Sori Lund. It rises from
the mountains in the form of 'Rud Chur' and, after receiving flows of some small
tributaries, assumes the name 'Jahand Chur'. Khandar Nadi, joins it with drainage of
the areas in the right. The combined channel takes the name of Vidore. Ranghan
Lahar and Sandani Nallah draining large areas join Vidore from the right. The
combined stream flows out of the Darrah and spreads into numerous creeks. The
overspills hit Kachi Canal, DG Khan Canal, communication system, canal irrigated
area and D G Khan City.
c) Sakhi Sarwar Hill Torrent
Sakhi Sarwar torrent is the smallest of 13 major hill torrents of DG Khan area, it rises
in Punjab Province and flows past Sakhi Sarwar Town from the left. The nallah splits
up into a number of channels near Sherwali Gand and its overspills inflict damage to
Kachi Canal, DG Khan Canal, its command area and communication system.
d) Mithawan Hill Torrent
Mithawan Hill Torrent rises in the Suleiman Range. The catchment area is almost
polygonal, wherein, the originating streams flow along the northern and north-eastern
boundary. Major part of the catchment is drained by the Siri Nallah; Rakhi Nallah;
Sahaki Nallah; Nangar Nai Nallah; and Choti Nallah tributaries, nearly all of which join
the main stream above the Darrah. Part of the catchment area has a pleasant weather
during summer. Fort Munro, having a cool weather is situated at the western apex of
the catchment area. D.I. Khan - Fort Munro - Loralai road crosses the catchment area
almost through its middle.
Mithawan Hill Torrent leaves the mountains near Choti Bala and fans out in Pachad
Area into a number of creeks namely i) Kachwala/Chhuri Nallah; ii) Ari Chah; Dirghi
Lahar; iii) Wandoi Lahar; iv) Chang Nallah, v) Hanki / Kharcha vi) Nadi;and vii) Gujji
Nallah.
The surplus flows of the nallah hit Under Construction Kachi Canal, DG Khan Canal
and Dajal Branch, their command area and the communication system.
e) Kaha hill Torrent
Kaha is the largest torrent of the Suleiman Range in DG Khan Area and primarily has
three main sub-catchments: Rakhni; Gand and Philawagh.
Kaha is formed by the union of Rakhni and Gand Nallahs and Philawagh Nallah joins
Kaha below the confluence of upper two major tributaries. Kaha Hill Torrent leaves the
Darrah, upstream of Harand and fans out into numerous small nallahs and wahs in the
downstream area. The surplus spills of kaha hill torrent branches cross Kachi Canal,
DG Khan Canal and Dajal Branch, their command area and the communication
system. Major tributaries are i) Rakhni Nallah, ii) Gand Nallah, iii) Philawagh Nallah.
278
MANUAL OF IRRIGATION PRACTICE
HILL TORRENTS MANAGEMENT
Kaha in general is the trained nullah through thirteen (13) flexible stone dispersion
structures constructed during 1993-1998 and in result of the dispersion very small
discharge reach DG Khan Canal crossing.
f) Chachar Hill Torrent
The Chachar catchment lies in an east-west direction to the right of Kaha Basin. It
continues to flow in an eastern direction upto its exit from the mountains, whereafter it
turns rightward and flows past Drigri Village on the left.
Surface flows of Chachar Hill Torrent hit the Kachi Canal, Dajal Branch Canal, its
command area and the communication system.
g) Pitok Hill Torrent
Pitok Hill Torrent originates from Suleiman Range and has a small part of its
catchment in Balochistan Province, while the remaining lies in the Punjab.
Pitok Hill Torrent leaves the Darrah near Sabzal Kot and fans out into numerous
branches which damage the Kachi Canal, local irrigation and communication systems.
Pitok Hill Torrent carries saline runoff which is not fit for human and agriculture uses.
h) Sori Shurnali Hill Torrent
Sori Shurnali rises in Balochistan Provihce and below the Darrah, it fans out into a
number of branches and crosses Kachi Canal, and proposed Dajal Branch
(Extension). Its flows damage the canal command area and rail-road communication
system in the area. The waters of this torrent are brackish and not fit for drinking and
crop production.
i) Zangi Hill Torrent
Zangi Hill Torrent rises from a hill on Punjab - Baluchistan boundary. The originating
stream is called Khalgiri while the other two main streams - Hingani and Hathai join it
from the left and right. Zangi leaves the Darrah near Dilbar Village, whereafter, it fans
out and damages the under construction Kachi Canal, Dajad Irrigation Branch System
and communication facilities of the area.
j) Sori Janubi Hill Torrent
Sori Janubi is the fourth largest hill torrent of the area. Due to the unfavourable
topographic conditions of the area, bund irrigation is not widely practised in the area.
The flows of this torrent, after debauching from the Darrah, fan out and cross Kachi
Canal, proposed Dajal Branch Extension, damage communication system and outfall
into the River Indus near Shahwali Town.
1.5. Traditional Management of Hill Torrent Water
Spate Irrigation is traditionally practised for diverting hill torrents into cultivable
command areas for growing seasonal crops. The farming system is characterized by
extreme events of floods and droughts. So, a unique irrigation system for hill torrent
area is being practiced, known as “Kamara Irrigation”.
279
MANUAL OF IRRIGATION PRACTICE
HILL TORRENTS MANAGEMENT
The intermittent and erratic patterns of precipitation events, being the unique source
of stream flow irrigation, have become the sole basis for the evolution of Kamara
Irrigation System since centuries. This system enforces the sequential water rights
and dictates the irrigation pattern from upper to lower riparian, without consideration
of the duration and magnitude of the storm generated flow. Under the system
sometimes, the far flung lower riparian remain deprived of irrigation facilities during a
low flow year. It usually entails the construction of an earthen diversion weir across
the torrent with large channel on one or both sides of the hill torrentr to convey flood
water across large distances. These earthen diversion structures and water
conveyance system has traditionally been constructed by the beneficiaries /
communities themselves, making use of traditional technology. Farmers construct field
by making embankments from 3 to 6 feet (1.8 m) high to store the water depending
upon the soil type, share in water and various other factors. Upon drying up water in
the field box, crops are sown which thrive on the moisture stored in the soil. There is
no further irrigation except rains, if any occurs. Figure 3 Shows layout of the system.
are categorized in accordance with the water rights. These are Haqooq wahs and Non-
haqooq wahs
Haqooq wahs are those off-taking channels which have the priority rights to use hill
torrents flows. Non-haqooq wahs can only draw the flood flows which are in excess of
the needs / capacity of the haqooq wahs
1.7. Components of Hill Torrent Structures
Generally, the following types of structural/non-structural measures are considered for
hill torrent management in DG Khan Area:
• Construction of a weir along whole width of hill torrent flow path which is a
dispersion structure (such no of weirs are constructed, as per channels sites
along the torrent flow).
• Upstream, downstream and central cut off walls on the basis of worst scour.
• Off taking channels on right and left side with regulators upstream of weir.
• Abutments, wing walls and retaining walls
• Bed fixer on downstream of main weir.
• Protection bunds / embankments/ Dispersion/ Distribution Structures across hill
torrent to divert share water for Irrigation
• Nullah Training Works
• Protection Works for existing infrastructure
• Check and Control Weirs
• Disposal of Surplus Flood Water into river through defined channels
• Studs/Groynes for training of active channels
• Cross drainage structures on Canals & Roads
• Watershed Management/ Delay Action / Storage Dams / Check Dams
Flows from these structures are being used through the following modes:
• Diversion Channels;
• Tube-wells;
• Open/Dug Wells etc.
In upper reaches, delay action dams are constructed and upstream of the gorge
(where the torrent enters plan area) usually a suitable location for a storage dam could
be found.
At downstream of the gorge, flood distribution / dispersion structures are constructed
to divert flow for agriculture. Salaiis /guide embankments/diversion dykes are
constructed in the flood channels to divert water towards the distribution channels for
feeding the fields.
281
MANUAL OF IRRIGATION PRACTICE
HILL TORRENTS MANAGEMENT
channels. The crest lengths and elevations are designed to hydraulically distribute
the incoming flows to pre-determined proportions according to water rights of various
user groups. Sizing of the structure is based on a 25-year return period flood peak,
which is the optimal for most of hill torrents of the semi-arid zone in Pakistan. The
free-board is selected to pass the 50-year peak in which case minor damages to the
downstream apron are to be tolerated. A breaching section, if required, is provided in
the marginal bund for release of higher flood peaks.
The intended breaching/ fuse portion of earthen embankment is constructed with a
top level that gets overtopped as soon as the incoming flow exceeds the critical value
and gets washed away thus automatically releasing the excess flow.
Flood distributors generally accommodate off-takes of irrigation channels on the
upstream of the weir. These off-takes withdraw proportionate discharges and feed
these to the conveyance channels (Canals) leading to the cultivated areas.
b) Dykes and Embankments
For single off-takes in the head reaches below gorge, cross weirs are not economically
viable. Instead, diversion dykes projecting obliquely to the flow direction are used to
divert the flow into open flume type off-take mouths. Farmers construct such dykes
with earth, gravel and brush wood called "Salaiis" which can only stand against low to
medium floods. High floods erode and wash away these dykes depriving the riparian
of the diversions for rest of the season.
Gabion can be advantageously used for constructing such diversion dykes. An anti-
scour apron of gabion mattresses or hand packed stone on the upstream side and
around the nose of these dykes is necessary. Alternatively, rubble mounds of large
size stones may be constructed with appropriate scour aprons. Regular maintenance
is essential for satisfactory operation of the diversion dykes (Salaiis).
c) Channels
Occasionally, earthen channels to divert flood from one stream to another or branches
thereof, have to be constructed for proper utilization of flood flows, and damage
control. Such diversion channels are usually required to off-take from streams that
carry ample flow but are deficient in cultivable land resources in their flood plains.
283
MANUAL OF IRRIGATION PRACTICE
HILL TORRENTS MANAGEMENT
Completed main Weir Qallandar Wah Complex, Kaura Hill Jam – Jat Wah Complex (Dispersion structure) Sanghar Hill
Torrent Torrent
Budhu Head Regulator on Sanghar Hill Torrent Kobhi Wah Complex on Vehova Hill Torren
Off-taking Structure at Jewan Wah Bed Fixer Structure D/S Vidore Hill Torrent
Figure 4: Different Constructed Hill Torrent Structures
284
MANUAL OF IRRIGATION PRACTICE
HILL TORRENTS MANAGEMENT
Disposal Channels are constructed in the tail reaches of the torrents. The torrents
generally get divided into several shallow channels that pond up against high
embankments of roads, railways and irrigation canals etc. in the settled area near the
recipient major river. These channels connect the cross-drainage structures (culvert,
super passage etc) on the road, railway or canal to the recipient body for safe disposal
of residual flows.
Regular maintenance is essential for efficient working of diversion and disposal
channels, as deposition, weed growth, encroachments and erosion tend to render
these channels ineffective.
d) Spurs/Groynes and Studs
These measures are generally implemented in the upper catchment areas where
orchards have been developed close to the stream banks. The process of bank
erosion often threatens the strenuously developed orchards and has to be checked by
corrective measures.
Spurs are constructed to modify the approach of incoming currents towards a
vulnerable location on bank or a weir, bridge or head-works. Gabions have
successfully been employed for constructing spurs, groynes and studs. Physical
model testing is generally required to determine the shape and size of spurs, groynes
and studs.
e) Scour Calculations
The scour calculations for hill torrent structures conveying heavily silt laden flows of
high velocities and short durations are to be done following models/equations different
from those used for normal alluvial regime channels. For hill torrent flows Brown
formulae for scour is used which is explained as following:
i) For Hilly areas
➢ River subject to sustained floods D= 1.32(Q/Cr)3/10
Maximum scour depth = 1.7 D
➢ Rivers and Torrents subject to sudden and short-lived spates:
D=1.0(Q/Cr)3/10
➢ Rivers subject to fluctuating discharge throughout the year:
D=0.78(Q/Cr)3/10
➢ Rivers and Torrents in Gorges with inerodible banks and deep alluvium bed:
D= 1.32(Q/Cr)3/1 For Gorges width => 2.4(Q/Cr)0.5
D=2.25(Q/(Wr *Cr))3/5 For Gorges width < 2.4(Q/Cr)0.5
Where
D=Maximum scour depth from design flood level to down (ft)
Q= Flood Design discharge (cusec)
Wr= width of gorge feet
Cr= Kennedy’s velocity factor chosen from following table
286
MANUAL OF IRRIGATION PRACTICE
HILL TORRENTS MANAGEMENT
A. Structural Measures
The structural measures include:
i) Flood Control Storage Dams
The construction of such dams, although an important part of the water-shed
management, comes up at the stage when the sediment charge in the flood water can
be controlled otherwise the high sediment load can silt up the dam very quickly
rendering it useless. This is why no storage dam could be taken up till now.
ii) Check Dams
Check dams are very helpful and structures of choice in slope and sediment control in
steep tor torrent channels. The check dams induce deposition of sediment till the
upstream reservoir is almost filled up and the erosion valley widened and slope
flattened, if the valley remains still active, additional check dams can be inserted in
between the existing ones to reduce the slopes further and achieve a stable erosion
valley.
Large check dams more than 50 ft. high fall in the storage dam category and has to
be considered in the latest stage of Water-shed management. In some locations
medium size check dams (up to 50 ft. high) when a reasonable reservoir capacity can
be achieved with reasonable cost, can be a suitable choice. A series of low check
dams of 15 ft. height is the most efficient series of structures to reduce the sediment
yield from an erosion valley and is considered to be the first step in structural measures
for hill torrent channel slope stabilization.
It has been observed that in general a Slope of 10 degrees or about 16% is safe for
most sediment sizes. The number of such check dams will vary for different
parameters of the torrent channel. Sometimes a very large No. of check dams has to
be provided for stabilizing a very steep valley. In Australia, the Schesatoble valley,
required 84 low dams. The Japanese Engineers working in erosion control wing are
working on Yoshino and Water asse Rivers for the last almost a full century and have
future plans that could go on for another century. Watershed management is thus a
trying job and requires a lot of patience and money.
The Japanese and other developed countries use concrete for construction of such
dams but in Pakistan gabions are the better choice and have also been adopted by
JICA Consultants for Mithawan Hill Torrent Pilot Project.
iii) Debris Breaker Screen Structures
These structures constitute a screen supported on side walls and central piers with
training wings to hold the stones and other debris and let the water flow. This is a
recent research development and has been introduced at a few places in Japanese
rivers.
288
MANUAL OF IRRIGATION PRACTICE
HILL TORRENTS MANAGEMENT
Natural terraces, of sometimes three to four meters high, one built up behind the
vetiver hedge and soil and moisture losses are minimized. Steep and rolling country,
too steep or not suitable for cultivation of cereal or pulses crops, can be successfully
planted with perennial tree crops on the contour cultivation other countries have
started similar programs , such as Nigeria, using Vetiverianigrantana, and the
Philippines and Sri Lanka with Vetiverzizanioides. Most recently, the Peoples Republic
of China has started the project which will concentrate initially on protecting existing
terraces and on reducing runoff and also initiate some trials for protecting tea gardens
on very steep erode able soils.
Vetiverzizanioides has the following characteristics that make it ideal for soil and
moisture conservation:
- It thrives under very wet (6,000 mm) and very dry (200 mm) rainfall conditions from
sea level to 2,600 mm above IvtSL
- It grows well as far north as 39 degrees, surviving freguent frosts and temperatures
as low as -9 ° c.
- The main constraint to expansion is the lack ofnurseries and planting materials.
- It does not produce viable seeds and practically sterile, it has to be planted
vegetatively, meaning that it will not become a weed in farmer's field.
- The plant is extremely drought tolerant; slips for planting have withstood 60 days
without rain.
- In dry areas, it normally takes two to three seasons with constant 'gap- filling' to
establish the hedge.
- Once established, maintenance cost is virtually zero, and it is generally
unpalatable to livestock-It is fire resisting i.e. the roots remain intact and sprout
again.
It is resistant to most pests and diseases.
- So called Vetiver oil can be extracted from the roots. It is used as raw material for
perfumes and medicines.
SACCHRUM MUNJA a self growing grass found in our hill torrent catchments, can
also usefully replace Vetiveriazizanioides which is to be imported.
However both the grasses need to be propagated in nurseries for maintaining supply
of saplings for planting of hedges.
C. Range Management
The range management, if implemented properly, provides good dividends through
proper grazing control and protection of vegetation by rotational use of different sector
of the water shed.
D. Fan area (Pachad area) Management
Based on “Master Feasibility Study for hill torrent management”, 1998 conducted by
NESPAK, Government of Punjab is constructing Dispersion structures in “Pachad
area” to divert hill torrent flows to existing channels to spread water over large area for
irrigation, land development, environment improvement and partially flood
management, which should be continued.
290
MANUAL OF IRRIGATION PRACTICE
HILL TORRENTS MANAGEMENT
E. Institutional Measures
The main institutional measures would include:-
a. Training of trainers for local people.
b. Motivation and training of local people for carrying out small scale, site specific
work like raising vetiver hedges, construction and maintenance of gully plugs,
small check dams weirs and bunds.
c. Appointment of grazing areas into suitable compartments for rotational grazing
and formulation of implementation control rules in consultation with the users
and local leaders and their enforcement.
d. Improvement in modern methods and aid for hydrological measurements like
automatic stage and rain recorders and other logistics for correct and reliable
data collection and record.
e. Installation of weather Radars in Suleman range for achieving the objectives of
better early warning system.
f. Motivation of local people for active and useful participation in catchment and
pachad improvement works and small irrigation schemes.
g. Improvement of facilities like education, health, communication, transport and
marketing.
F. Drainage of hill torrent floods into River Indus.
After crossings of hill torrent water from D.G.Khan Canal and Dajal Branch effective
and efficient flood water drainage system is paramount. Existing seepage drains in
District D.G.Khan cannot drain out the flood water.
Flood carrying channels from each crossing of Kachi Canal/ D.G.Khan Canal / Dajal
Branch to River Indus is the real solution
Alternatively, existing flood flows routes / drains be improved and strengthened and
water to be drained off through enhanced capacity of existing drains / new drains with
protection dykes
1.15. Impact Evaluation and Monitoring of Completed Projects
The Flood management for Kaha hill torrent was carried out during 1993-1996 through
construction of number of dispersion structures under Flood Sector Protection Project
phase-1. Evaluation of hill torrent Management was made by NESPAK and report
submitted in 2004. After completion of structures, flood peaks of various magnitudes
recorded at the Darrah and at hill torrent crossings on Dajal Branch from the year 1997
to 2003 are substantially reduced.
Similar evaluation was made on Koura, Vehova and Sanghar Hill Torrents in 2012
which is given in Table 2.
291
MANUAL OF IRRIGATION PRACTICE
HILL TORRENTS MANAGEMENT
system would involve the remodeling of the existing system in addition to construction
of a few new drains.
From the view point of surface drainage and final disposal of excessive flood flows,
the DG Khan torrents can be divided into four groups as under: -
Group 1 Group 2 Group 3 Group 4
Kaura Sori Lund Kaha Pitok
Vehowa Vidore Chachar Sori Shumali
Sanghar Sakhi Sarwar Zangi
Mithawan Sori Janubi
Figure 6 shows existing and proposed surface drainage system in Canal Command
area. The surface drainage characteristics of these groups have been discussed in
the following:
a) Group 1
Before construction of CRBC canal, the three torrents namely, Kaura, Vehowa and
Sanghar have direct outfalls into Indus but after its construction the flood water
accumulates on the right side of CRBC canal and then escapes through the hill torrent
crossing structures and well-defined channels take surplus flows to the River Indus. In
low floods command area is not affected but on high floods the flood channels spillage
causes damages to crop area. In last few years through ADB financial assistance,
number of dispersion/distribution structures are constructed to utilize the hill torrent
water for irrigation and is quite successful.
b) Group 2
Sori Lund, Vidore, Sakhi Sarwar and Mithawan are the torrents where maximum flood
dispersion structures have been constructed which have substantially reduced the
quantum of residual flood water crossing the Kachi canal/DG Khan Canal. However,
in very high floods, the spillage is much more which damages the City of Dera Ghazi
Khan as well as cropped area upto Jampur city. The capacity of hill torrent structures
built on Kachi canal is more than those of DG Khan Canal and DG Khan Xing
structures require remodeling. There is, however, no proper system of channels to
lead this water safely towards the River Indus. This results in ponding of water for long
period, thereby, causing large damage to standing crops and infrastructure. The
existing Manka and Kappar drains have been proposed to be remodeled and extended
to outfall into Indus River shortly downstream of Jampur town. The remodeling of
Manaka and Kappar drains shall involve re sectioning and excavation.
c) Group 3
The third group of torrents causing inundation in command area comprises Kaha and
Chachar hill torrents. The residual flood water from these torrents crosses the Dajal
Branch and in absence of proper lead channels, causes inundation in large tracts
between Jampur and Rajanpur. A system of two main drains, namely, Forest Drain
(29kms) and Bukhari Drain (23kms) has been proposed for safe disposal of excess
flood flows to the River Indus.
293
MANUAL OF IRRIGATION PRACTICE
HILL TORRENTS MANAGEMENT
d) Group 4
This fourth and last group consists of Pitok, Sori Shumail, Zangi and Sori Janubi. The
first two streams i.e Pitok and Sori Shumail have saline effluent which is unfit for
irrigation. Accordingly, no flood dispersion structures etc have been proposed on these
torrents and the entire flow has been planned to be escaped into the River Indus.
Presently, the flood water from these torrents ponds up along the right bank of Kadra
Canal due to insufficient capacity and unfavorable location of the cross drainage
structures for these torrents.
A collector drain (40kms) parallel to the right bank of Kadra Canal has been proposed
to intercept flows for Pitok, Sori Shumali and a part of Zangi. The drain is proposed to
outfall in river Indus. In addition, two independent drains have also been proposed to
dispose of the excess flood flow crossing Kadra Canal and Dhundi Qutub Canal
upstream of the start of Collector Drain. These drains namely Umar Kot Drain and
Safdar Drain, shall be 7Km and 10kms in length respectively. The last torrent i.e. Sori
Janubi has a direct outfall into the Indus near the town of Rojhan.
1.17. Potohar Area Hill Torrents
Islamabad Capital Area, District Attock, Rawalpindi, Chakwal and Jehlam constitute
the Potohar area. Figure 7 shows details of Potohar Area.
Major part of the area is drained off to tributaries of River Indus and part area of District
chakwal and jehlam is drained off in River Jehlam.
A. Tributaries of River Indus
The following major river basins are tributaries of River Indus:
(a) Soan River and its tributaries,
(b) Kurang River
(c) Ling River
(d) Silo River, Large Number of Nallahs/Kus(s) and Haro River
(e) Soan & Haro Rivers are tributaries of Indus River while Kanshi, Kahan and
Bunha rivers are tributaries of Jhelum River. In addition to these rivers, there
are other numbers of nallahs which individually drain small areas.
(f) Major source of flow in the rivers is rainfall with small contribution of snow melt.
Principal volumes of run-off occurs during July-September and constitutes
about 60% of the total annual flow.
(g) The average annual rain fall varies from 305 mm (12 inches) in south west to
1520mm (60 inches) in the north east around Murree. North eastern part of
Area is one of the highest precipitation region of Pakistan. The Monsoon rainfall
increases from north west in Attock area to south east in Jhelum area. The
average annual rainfall for the Area is about 675mm. Soan River and its
tributaries drain major part of Area. The flow of Soan River is measured at
Chirah, Rawalpindi and Dhok Pathan. The drainage area of Soan River at
Chirah is 325 sq km (126 sq miles). Mean annual flow of Soan River is
182xx106m3 (148,000 acre-ft). It is not a perennial river and remains dry for a
295
MANUAL OF IRRIGATION PRACTICE
HILL TORRENTS MANAGEMENT
The drainage area of Soan River near Rawalpindi gauging station is 1684 sq km (650
sq miles). The mean annual run-off is 655x106m3 (531000 acre-ft).
The average annual rainfall is 686mm (27 inches). The maximum peak of 4530 m 3/sec
(160000 cfs) was observed on 7th August 1982. The river is perennial at this point with
a minimum flow of 0.25 m3 /sec (9 cfs).
Soan River has a drainage area of 6475 sq km (2500 sq miles) upto the gauge site
near Dhok Pathan. The mean annual flow is 1406x103m3 (1,440,000 acre-ft).
Maximum peak of 7335m3/sec (259000 cfs) was recorded on 2nd August 1976 which
is equivalent to 8.55 inches of average annual run-off. Average annual rainfall upto
Dhok Pathan is about 675mm (27 inches). Dhok Pathan site almost represents the
accumulative run-off of the entire area because of its location.
Estimation of peak discharge for the design flood is an essential pre-requisite for flood
management structures, while annual run-off volumes of known return period with
monthly distribution together with available area for dispersion facilities form primary
requirements for planning of irrigation system. Table 3 shows the frequency analysis
for Haro, Soan, Ling, Kurang and Sil rivers at different sites for different return periods:
Table 3: Results of Frequency Analysis
Sr. Name of Return 2.33 –Yr. 5 – Yr. 10 – Yr. 25 – Yr. 50 – Yr. 100 – Yr
No. Station period
Unit
• Prospective Planning
Many of the Hill torrents in Potohar region have been dammed for storage, water
supply and command area development and about all have met the targets
substantially. For the remaining a detailed study is underway for harnessing them.
Up till now 62 Small dams have been constructed in Potohar area for drinking as well
as for agriculture use. Small Dams in Pothowar Area have been extremely useful and
have played a vital role in the development of agriculture. However, the statistics
indicate that there is sufficient potential for further land and water resources
exploitation. These resources, if fully utilized, can play vital role in the economy, social
uplift and develop positive environments in the Potohar area. The results in the
development of agriculture have been quite encouraging. The public has realized the
importance of water for agriculture which has provided an impetus for increase in
intensity and yield of crops in the area. The results are summarized as under:
- Net farm income has increased by 70%,
- Cropping intensity has increased by 25%,
- Livestock development has increased,
- Fish development has been initiated,
- Migration of farmers to urban areas has been reduced,
- Cost of land has gone up and
- Potable water supply to the area has increased
• Present Status
So for 62 small dams have been constructed and 8 dams are under feasibility stage.
In order to study development potential of the area, team of experts of various
disciplines carried out field visit of the area and observed that:.
- Beneficiaries have started taking keen interest in the development of agriculture of
the area
- The orchards / vegetables of the area have a very good market in the nearby twin
cities Rawalpindi/ Islamabad.
- Generally, the maintenance of existing dams was not upto the standard and there
was room for improvements, and recently World Bank has given loan for
Rehabilitation of constructed Small Dams including development of command area
and construction of few new dams.
- Average cost/acre of benefitted area is about Rs. 60000. This cost is much higher
than the cost of canal irrigated area, and three to four times the cost of development
in Baluchistan where mostly the local material is used for construction but is
sustainable in the particular scenario of Potohar.
- So far about 171 dam sites have been identified by Consultants of which Twenty
six sites are of high development potential. 20 high priority schemes have been
constructed in last 20 years and at present 5 schemes are under feasibility study
stage.
298
MANUAL OF IRRIGATION PRACTICE
HILL TORRENTS MANAGEMENT
Huge drainage network shall protect the canal command area as this spillage cannot
be stored elsewhere
All these tributaries except Ujh join Ravi in Pakistan. These tributaries drain a total
catchment area of about 5727 sq km (2211 sq miles). High flows of these tributaries
sometimes synchronize with Ravi River discharge which results in higher flood peaks
in the channel. Snow-melt does not have significant influence on the flood peaks due
to the fact that its contribution does not synchronize with the flows generated by the
rainfall.
1.19. DESIGN OF FLEXIBLE WEIRS
Assume a weir is to be built in a stream with characteristics as follows:
Slope of the stream bed i = 1.5%
Design discharge Q = 30 cumecs.
Width of the torrent bed I = 20 m
Depth of the uniform flow
𝑄 3/5 30 3/5
(z3 – f3) = ( ) =( ) = 0.58 m
𝐶 𝑋 𝑙 𝑋( 𝑖)0.5 30 𝑋 20 𝑋( 0.015)0.5
Value considered for coefficient C = 30 (Strickler)
𝑄 30
Velocity of the uniform flow: V = ( ) = (20 𝑋0.58) = 2.58 m/sec
𝑙(𝑧3−𝑓3)
Critical Velocity Vc = ( g(z3-f3)) 0.5 =( 9.81 X 0.58) 0.5 =2.38 m/sec
Since V> V c, the flow is supercritical
Case 1: Weir with unlined stilling pool floor. Figure A
Height of Crest
Suppose the width of the rectangular crest is kept 75 % of channel width lg = 7.5 m
𝑄 30
q = 𝐼𝑔 = 7.5 = 4 cu.m/s/m
Assuming q = 4 cu.m/s/m, from the straight line corresponding to µ = 0.4 in Figure B
303
MANUAL OF IRRIGATION PRACTICE
HILL TORRENTS MANAGEMENT
we get: zo - fg = 1.7 m.
The same result is obtained by applying the formula:
Q=u x lg (Z0 – f g ) ( 2g (Z0 – f g )) 0.5
The height of the crest is therefore established as follows:
fa – fg = 2 m.
Depth of scour from Schoklitsch’s formula:
Z3 - fb = ( 4.75 (Z0 – Z3 ) 0.2 x q 0.57 ) / d t 0.32 Assuming dt = 100 mm.
Z3 - fb = ( 4.75 (4.12 ) 0.2 x 4 0.57 ) / 100 0.32 = 3.18 m
The same result is obtained if z3 - fb is taken from the straight line q = 4 cu.m/s/m, with
dt = 100 mm, in Figure C.
Therefore, f3 – fb = 3.18 – 0.58 = 2.6 m.
In order to avoid having to construct deep foundations (50 cm at least below elevation
fb) it is decided to build a counter weir Figure D to increase the downstream water
level, thus reducing the scour depth.
The width of the counter weir crest is assumed Ic = 12 m, (60 % of the bed width of
channel) therefore:
𝑄 30
qc = = = 2.5 m3/s/m
𝐼𝑐 12
The flow over the counter weir is given by:
Q=u x lc (Z2 – fc ) ( 2g (Z2 – fc )) 0.5
𝑄 0.667 30
Z2 - fc = ((𝑢 0.5 ) =( )0.667 = 1.26 m
𝑋 𝑙𝑐 𝑋(2𝑔) (0.4 𝑋 12 𝑋(2 𝑋 9.81)0.5
result is obtained from Figure B with q = 2.5 cu.m/s/m and µ = 0.4.
Once established that the height of the counter weir must be fc – f3 = 0.5 m,
from the Schoklitsch formula or from Figure C, with q = 4 cu.m/s/m and
zo – z2 (≅ z3) = 2.95 m, we find from the straight line dt = 100 mm that z3 – fb = 2.97 m,
therefore f3 – fb = 1.22 m,
The foundation level can thus be established 2 m below f b
The counter weir is located 10 m away from the weir.
Calculation of zv:
𝑄2 302
𝑍𝑉 − 𝑓0 = (𝑓𝑔 −𝑓𝑏 )( 3 )0.22 = (3 )((9.81 )0.22 = 1.10 m
(𝑔 𝑋 𝐥𝟐𝐛 𝑋(𝑓𝑔 −𝑓𝑏 ) 𝑋 𝟏𝟖𝟐 𝑋(3)3
1 2 960
Htv = h X λa 2 X22 X0.27 =518 kg applied at 0.66 m above
2 5
EF.
6700+3100
Sw = 2
X 6 = 29,400 kg applied at 3.35 m from F.
Pg1 = (4x2) x 1800 = 14,400 kg (weight of dry gabions)
Pg2 = (5x2+6x1) x 2120 = 33,920 kg (weight of saturated gabions)
5𝑥2.5+5𝑥2.5+6𝑥3
Coordinates of the center of gravity of the saturated part Xg2 = = 2.69 m
16
6𝑥0.5+5𝑥1.5+5𝑥2.5
Yg2 = = 1.44 m
16
Weight of the water over the crest:
Pw1 = ≅ (1.13x4) x 1000 = 4,520 kg applied at 2 m from F.
Weight of the water over the steps:
Pw2 = ≅ (1.13x2) x 1000 = 2,260 kg applied at 5 m from F.
Pt = ≅ (4x1+2x1) x 1960 = 11.760 kg applied at 5.17 m from F.
Checking of the overturning
𝑀𝑠 𝑃𝑔1𝑋𝑿𝑔1+𝑃𝑔2𝑋𝑿𝑔2+𝑃𝑤1𝑋2,00+𝑃𝑤2𝑋5,00+𝑃𝑡𝑋5,17+𝐻𝑤𝑤𝑋1,03+𝐻𝑡𝑣𝑥0,66
Sr =
𝑀𝑟
= 𝐻𝑤𝑀𝑥2,23+𝐻𝑡𝑀𝑥1,66+𝑆𝑤𝑋3,35
1400𝑋2,00+33920𝑋2,69+4520𝑋2,00+2260𝑋5,00+11760𝑋5,17+4805𝑋1,03+518𝑋0,66=
= = 1,37> 1,3
𝐻𝑤𝑀𝑥2,23+𝐻𝑡𝑀𝑥1,66+𝑆𝑤𝑋3,35
Pressure distribution
𝐵 𝑀𝑠−𝑀𝑟 6 206,475−150,698
e= 2
- ∑𝑉
= 2
- 37,460
= 1.51 m
The resultant is external to the middle third:
∑𝑉 37,460
Ómax = 2 3𝑥𝑋𝐹𝑥100 = 2 3𝑥149𝑥100 = 1.68 kg/cm2
305
MANUAL OF IRRIGATION PRACTICE
HILL TORRENTS MANAGEMENT
Second Case
Weir with lined stilling pool floor, jump control by broad crested weir. Figure G
Crest
See the preceding calculation
Design of the counter weir and stilling pool
Considering Ib = 18 m,
𝑄2 𝑄2
from formula (zo - fb) + = (z1-fb) +
2𝑔ᾨ𝑜^2 2𝑔 (𝑍1−𝑓𝑜)2 ∗𝑓𝑏^2
which by applying the allowed approximation may be simplified as follows:
𝑄
Z1-fb =
𝑓𝑏(2𝑔 (𝑍1−𝑓𝑜))0.5
Or, in a shorter way , from Figure H being
𝑄
𝐼𝑏
= 1.66 cu.m/s/m, it results from interpolation z1 - fb = 0.165 m
From the formula:
(𝑧1−𝑓𝑏) 2𝑄2 (𝑧1−𝑓𝑏)^2
(z2 - fb) =
2
+( 2 2 + 4
)^0.5
𝑔𝑓𝑏 (𝑍1−𝑓𝑏)
𝑄
as well as from Figure H with z1-fb = 0.165 and 𝐼𝑏 = 1.66 cu.m/s/m
a value of z2-fb = 1.65 m is obtained on the dashed segments.
The flow over the counter weir is given by the formula applied in the preceding case, therefore
z2-fb = 1.25 m
The height of the counter weir will therefore be fc-fb = 1.65-1.25 = 0.4 m
The developed length of the stilling pool must be:Lb=Lg1+L12=3.36 + 6.9 (1.65-0.165) = 13.61
m. A value of Lb=14 m will be adopted
Check of seepage
According to Bligh’s formula, L must be equal to or larger than c ^∆ H; assume the weir as
built on sediments (c-6)
L ≅6x4.12 = 24.72 m,
The developed length of the designed weir foundation is sufficient.
An apron is constructed downstream the counter weir to prevent the latter from being
undermined: the length of this apron will be approx. 3 m.
Check of the uplift
The most dangerous point is considered to be in the proximity of point X, in correspondence
with which z1 is formed.
The foundation of the apron is lowered by 1m between points F and G in order to increase the
weight of the apron in correspondence with point X.
𝑍𝑜−𝑧3
P = Yw [(z0-zx) – 𝐿1 y] = 1000
4.12
[7.7- 33 16.64] = 5622 kg.
Sg = (Yg1 + Yw h)=(1960x3+1000x0.165)=1.07
5622
The check is acceptable, in as much the results are satisfactory at the contiguous points.
Check of the stability
Same as in the first case
306
MANUAL OF IRRIGATION PRACTICE
HILL TORRENTS MANAGEMENT
Figure 15: Weir with lined stilling pool floor, jump control by broad crested
weir
313
MANUAL OF IRRIGATION PRACTICE
HILL TORRENTS MANAGEMENT
1.20. References
1. National Engineering Services Pakistan (PVT) Limited, Master Feasibility
Studies for Flood Management of Hill Torrents of Pakistan, November 1998,
Seven Volumes.
2. Kachhi Canal Project, Management of KC-2 & KC-4 Hill Torrents, July 2006.
3. National Engineering Services Pakistan (PVT) Limited, Flood Management of
D. G. Khan Hill Torrents, December 1984.
4. Feasibility Studies of Small Dams
5. Hydrology of Jalalpur Canal Project updated by Nespak
6. Flexible weirs for River Training and water supply MACCAFERRI GABIONS
YOGOSLAVIA
7. Pakistan Engineering Congress International Symposium on Management of
Hill Torrents 1995
8. Zaidi, S.M.A Management of Kaha Hill Torrent Paper No. 189. 1995- Pakistan
Engineering Congress
9. Ch Shafique Ahmed Hilltorrent management initiatives in southern part of
Punjab, an overview impact analysis & way forward Paper No 746 - Pakistan
Engineering Congress
i
MANUAL OF IRRIGATION PRACTICE
GROUNDWATER – OPTIMAL USE & MANAGEMENT
List of Figures
FIGURE 1: HISTORIC BEHAVIOR OF GROUNDWATER LEVELS IN PUNJAB.................................................... 316
FIGURE 2: GROUNDWATER LEVELS IN PUNJAB ........................................................................................ 323
FIGURE 3: GENERAL DISTRIBUTION OF GROUNDWATER QUALITY IN PUNJAB ............................................ 324
FIGURE 4: GROWTH OF TUBEWELLS IN PUNJAB....................................................................................... 326
FIGURE 5: STRATA CHART AND DESIGN OF A SHALLOW TUBEWELL .......................................................... 332
FIGURE 6: AREAS WITH DECLINING GROUNDWATER LEVELS (FT/GLS) .................................................... 338
FIGURE 7: RISING GWL TRENDS IN DGK IRRIGATION ZONE 2003-16 (FEET/GLS)................................... 338
FIGURE 8: INCREASING SALINITY IN SOME AREAS 2003-13 (DS/M) .......................................................... 340
FIGURE 9: W OMEN COLLECTING DRINKING WATER FROM SKIMMING HAND PUMP IN RY KHAN ..................... 341
FIGURE 10: DECLINE OF GWL IN KAMALIA AREA (FEET/GLS) ................................................................. 345
315
MANUAL OF IRRIGATION PRACTICE
GROUNDWATER – OPTIMAL USE & MANAGEMENT
sub-divided into six hydro-geological areas/Doabs by the Indus River and its tributaries
viz.:
1)Thal Doab, 4) Bari Doab,
2) Chaj Doab, 5) Bahawalpur area &
3) Rechna Doab, 6) D.G. Khan Area –at the foot of Suleiman Range.
Before the introduction of the weir controlled irrigation system - rivers were the major
source of groundwater recharge in addition to the rainfall. In those times – the
groundwater levels were relatively shallow near the rivers and ranged up to more than
30m (100 feet) depth below the land surface towards the central parts of the Doabs –
which were relatively higher. Groundwater flow was from the rivers towards the central
parts of the Doabs. With the implementation of the irrigation system - seepage water
from the canals, water courses and irrigated farms became the major source of
groundwater recharge and reversed the groundwater flow system – and the rivers
became effluent during low flows. Based on the groundwater investigations by
WAPDA in 1960s the groundwater table conditions in Rechna Doab - before and after
the irrigation system are shown in the Figure 1 – given below.
Figure 1: Historic Behavior of Groundwater Levels in Punjab
up. Indus and Soan rivers flow in this part of the province. Sub-surface
strata underlying these parts of the province form intercalations of clay,
sands of various grades and gravels and conglomerates.Groundwater,
generally, occurs under water table conditions in these areas and is
being exploited through a large number of small capacity tubewells
(commonly less than 1.0 cusec discharge) for drinking purposes and
meeting the crop water requirements in dry seasons. Depth to
groundwater level (DTW) ranges from 4-5 m to more than more than 20.
Near the base of hills the DTW is generally more and central parts of the
small valleys or near the rivers (such as Soan) the DTW is relatively
shallow. Quality of groundwater is generally fresh except in some areas,
e.g. near Khewra Salt Mines, and is being used for drinking and
agricultural purposes.
II. Piedmont Areas along Suleiman Range: These areas comprise
the piedmont slopes from the base of Suleiman Range towards Indus
River and are underlain by the intercalations of gravels, sand and clays
– with clay deposits increasing in thickness towards the Indus River –
before inter mixing with the alluvial sediments laid by Indus River, which
are predominantly sands. Under Poleflucraft Force, due to rotation of
earth from west to east, the rivers in the northern hemisphere have been
shifting their beds towards the right bank – and Indus River also kept on
shifting its bed towards right bank and near DG Khan it flows on a higher
limb like a hockey. Groundwater in this part of the province – generally -
occurs under water table conditions and the depth to water gradually
decreases from the base of the hills towards Indus River. DTW ranges
from more than 30 m (even more in some areas) near the base of hills
to about 4-5 m as we move towards the river. Groundwater quality is
generally fresh at the base of the hills and deteriorates towards the lower
parts. Another phenomenon - impact of the “Hill Torrents” emerging from
The Suleiman Range - also influences the groundwater quality. Some of
the Hill Torrents originate in the saline rocks and carry highly saline
groundwater in spite of the fact that these carry the surface flows.
III. Alluvial Plains of Central Punjab: These areas comprise areas
underlain by active and abandoned flood plains of the five rivers and Bar
Uplands in the central parts of the Doabs (interfluves), forming the
divides between the two rivers. Strata underlying these areas comprise
the alluvial sediments deposited by the rivers comprising sands of
various grades with intercalations of clay and gravel. Groundwater
occurs under water table conditions with depth to water table (DTW)
ranging from less than a meter to more than 30 meters (>100 feet)
depending upon the distance from the rivers, as DTW is generally
shallow along the rivers and increases towards the central parts of the
Doabs. Quality of groundwater is generally fresh along the rivers and
saline in the central parts of the Doab.
318
MANUAL OF IRRIGATION PRACTICE
GROUNDWATER – OPTIMAL USE & MANAGEMENT
IV. Cholistan Desert: The Cholistan Desert, also locally known as Rohi,
sprawls thirty kilometers from Bahawalpur, Punjab, Pakistan and covers
an area of 26,300 square kilometers. It adjoins the Thar Desert,
extending over to Sindh and into India. The Cholistan Desert is underlain
by alluvial sediments from the Indus River System and also in some
parts the abandoned bed of Hakra River sediments – predominantly
sands of various grades intercalated with clay layers. Depth to water
table ranges from a few meters to more than 25 m in the area and
sediments being tapped for groundwater in the bed of the Hakra River
system. Practically there are two water tables viz. in the sediments under
the influence of existing irrigation system and the ones deposited by
Hakra River.Groundwater quality is generally fresh along the main
canals and in Hakra River Bed – however, excessive pumping in the
area is resulting in continuous decline of water levels in the wells
installed in the abandoned river bed.
1.1.2. Aquifer Characteristics
General Picture of Prevailing Field Conditions: Around 1,000,000 public and
private tubewells are being operated in the province to meet, drinking, industrial and
agricultural requirements and around 90% of groundwater is being used for
augmenting the irrigation supplies by the farmers though private tubewells.
Parameters Controlling Groundwater Development: The major parameters
governing the groundwater development in an area include aquifer characteristics
controlling storage and flow of groundwater and existing pumping pattern in an area.
Naturally certain groundwater investigations are carried out (particularly in a new area
– as WAPDA carried out detailed groundwater investigations in the province during
1960s). Other modern techniques – such as satellite imagery are also available –
however, these are normally beneficial in case of a large scale groundwater
development - such as a basin or Doab – and only give broad picture. For the
development of dependable water source (s) for drinking, agriculture or industrial use
– it may be adequate to take a clear look around on the groundwater conditions, its
use and response of the aquifer – based on the previous investigations and existing
monitoring data.The major parameters controlling groundwater development and
sustainable use include:
Aquifer’s characteristics – or water bearing properties of the underlying
strata and their distribution in aerial and vertical as discussed below;
Groundwater quality – and its variation in aerial and vertical extent –
particularly for drinking water sources;
Depth to water table – and its long term behavior - based on some
monitoring data;
Existing groundwater use and future plans – particularly in case of large
scale development project.
Aquifer Parameters: During the detailed groundwater investigations by WAPDA
– in the Punjab Province around 2500 deep test bore holes were drilled – ranging in
319
MANUAL OF IRRIGATION PRACTICE
GROUNDWATER – OPTIMAL USE & MANAGEMENT
depth from 600 feet to 1500 feet - to ascertain the distribution of alluvial sediments
underlying the Province. For determining the aquifers’ hydraulic characteristics – 140
pump-out tests on the tubewells installed as part of investigational program were also
conducted. The main aquifer characteristics – which govern the groundwater flow and
storage, are:
Permeability (K) of the Aquifer Material – the property of sediments to
transmit water under a unit gradient. Value of horizontal permeability as
compared to vertical permeability is very high say even more than 20 -
30 times.
Transmissivity (T) of Aquifer – or property of aquifer material to
transmit water through a particular section;
Storage Coefficient or Specific Yield of the aquifer(S) – controlling
the volume of water per unit volume of aquifer;
Specific Capacity of Tubewell – is drawdown inside the well in
response to various rates of pumping. This parameter reflects the
aquifers’ property and also the appropriate design – as excessive
drawdown increases pumping cost – apart from the construction cost the
tubewell. Under the given field conditions – appropriate selection of
depth and diameter of the bore holes and pipes and screens affects the
specific capacity of tubewell - saving long term expenditure on pumping.
Based on the detailed groundwater investigations by WAPDA and analysis of data
from the long pump out tests range of aquifer parameters for the four Doabs are given
in Table 1.
1.1.3. Groundwater Recharge and Discharge Parameters
Major sources of groundwater recharge and discharge in the Punjab Province are as
discussed below:
Recharge Parameters: Major groundwater recharge parameters are as below:
❖ Recharge from the rainfall varies from about 20 % in the northern
Punjab to about 5 % in the southern part of the Province (average 10%
of 388 mm rainfall over 20.6 M ha (or 51 MA). Studies carried out under
Punjab Private Sector groundwater Development Project (PPSGDP) by
PID – WB, 1997-2001) indicated the rainfall recharge in different
hydrogeological zones, viz. Multan, Faislabad, Lahore and Sialkot as
below:
Zone Average Average Percent of
Rainfall (in) Recharge (in) Rain
Multan 6 1.0 16.6
Faisalabad 10 2.3 23.0
Lahore 16 3.6 22.5
Multan 25 5.6 22.4
320
MANUAL OF IRRIGATION PRACTICE
GROUNDWATER – OPTIMAL USE & MANAGEMENT
Regular checks on the groundwater quality are necessary to avoid any negative
impact on the groundwater regime – as it provides more than 90% of water for drinking
as well as for agriculture. Intensive pumping from about 1,000,000 PTWS also plays
a large role in deterioration of groundwater quality – as the farmers’ TWs are mainly
concentrated in the FGW areas and intensive pumping in these areas lowers the
watertable inducing groundwater flow from the SGW zones. Use of irrigation water
and groundwater for agriculture also promotes salinization of the irrigated lands –
whereas leaching by farmers and sometimes floods also help in washing down the
salts.
1.1.7. Groundwater Use in Punjab
Annual groundwater abstraction in Punjab has increased from about one MAF in 1947,
to 35-40 MAF depending upon the crop water requirements from year to year. As a
result of this development, the cropping intensity gradually increased from 80 % in
1947 to 100 % around 1960 and lately around 130 % (up to more than 150 % in some
of the areas) in the Province. Population growth and increasing demand of water for
irrigation, water supply, industry and environmental needs would further boost its
importance in the years to come
At the time of independence – we inherited a twin menace of water logging and salinity
– due to continuous seepage from the weir controlled irrigation system in operation
since the previous century. Under the salinity control and water logging program
around 10,000 SCARP tubewells were installed. Initial success of these tubewells in
lowering of water table in the water logged areas and provision of timely irrigation
water “at the farm level” inspired the farmers to install their own tubewells for
supplementing canal supplies. This suited the government also as it helped in
producing more food through the participation of private sector and the then policy of
pumping more water for controlling water logging.
Transfer of the responsibility for the development of fresh groundwater to the private
sector in 1981 – through agricultural policy and availability of 12-16 HP centrifugal
pumps (Peter Pumps) enticed framers for a marathon race for private tubewells and
currently there are around 1,000,000 tubewells in the Province – and 90% of
groundwater being pumped is used for agriculture.Of these, around 90 % of private
tubewells (PTWs) are being operated by the farmers and their pumping capacity is
generally within one cusec. Growth of tubewells in the province is shown in Figure 4
given below. Existing groundwater pumping is of the order of 40 MAF (50 BCM).
Groundwater abstraction varies in accordance with rainfall and canal water availability
during dry and wet years.
326
MANUAL OF IRRIGATION PRACTICE
GROUNDWATER – OPTIMAL USE & MANAGEMENT
of these dams have already provided great help for provision of “potable
water” to certain rural areas in Attock and near Fateh Jang through
construction of “percolation wells and infiltration galleries” near the lake
bed. A small Quantity of irrigation water (tapped through infiltration
gallery – say 0.5 cusec) can help to provide drinking water to a few
villages; and
Any other areas with excessive groundwater abstraction – such areas
have been demarcated in the previous studies by the department as
“Critical Areas” needing immediate attention.
1.2. Conjunctive Use
What is Conjunctive Use: Conjunctive use of surface and groundwater means
the best possible utilization of surface and groundwater resources for boosting the
agricultural production – with minimum negative impact on the land and water
resources. Keeping in view the limitations on the surface water availability conjunctive
use of surface and groundwater is encouraged.
Existing Situation in the Province: Ironically, around 1,000,000 private
tubewells being operated by the farmers for augmenting canal supplies in irrigated
areas to meet the crop water requirements – and already provides a good example of
the “conjunctive use”. In the Punjab Province, groundwater is saline in certain parts
and farmers are practicing conjunctive use by:
Mixing surface and groundwater for irrigation purposes; and/or
Use groundwater only – for the sustenance of the crops during canal
closures or lack of canal water availability.
Points Needing Attention: Following parameters will have to be given due
consideration:
Some farmers in the U/S areas may like to use excessive water – if
available - as was the practice in the past. Education, awareness and
involvement of the farmer brothers is necessary for application of
irrigation water in accordance with the crop water requirementsand
applying necessary improvements in the irrigation technologies (precise
land leveling, bed and furrow techniques etc.). Joint teams of Irrigation
and Agriculture departments can provide the necessary guidelines to the
farmers in the field;
Groundwater is saline in the central parts of the Doabs, some areas
along Suleiman Range and Cholistan. Hence, the farmers should be
encouraged to select the cropping pattern in accordance with the water
quality of the available groundwater – there are salt resistance crops.
Here the advice and participation of agriculture department is required
at field level.
In the past PID conducted some studies in critical area for groundwater
management involving the farmers to change the cropping pattern from
sugarcane to maze or other less water consuming crops – but in such
329
MANUAL OF IRRIGATION PRACTICE
GROUNDWATER – OPTIMAL USE & MANAGEMENT
PID helped the farmers under PPSGDP1 for the installation of “Community Tubewells
(CTWs)” at the time of closure of unnecessary SCARP tubewells (STWs) where the
water tables had already gone down below 15-20 feet. In this case the community
members (a group of small farmers who could not install and operate their own wells)
were trained and handed over STWs by installing a small capacity pump and or were
encouraged to install a small irrigation TW - as per their requirements.
Following are the major components of tubewells or open dug wells fitted with pumps,
which need due consideration during the design stage. Design or rather the desired
discharge of the tubewell – is the controlling factor for deciding other parameters –
keeping in view the field conditions
I Depth and diameter of the borehole – in accordance with the local sub-
surface lithology (sand, gravel, clay etc.);
II Pump housing casing - its length and diameter;
III Screen length and diameter, its slot size and material;
IV Length and diameter of the blind pipes to be placed against the clay
zones;
V Gravel pack or shrouding material to be placed in the annular space
between the borehole and the tubewell casings;
Vi Selection of the pump and prime mover - based on the specific capacity
of the tubewell and expected drawdown at various discharge rates
determined after conducting the pumping test on the tubewell.
Cost of Tubewells: The total cost of a tubewell is the function of its capital cost and
operation and maintenance cost. Accordingly, the cost of pumped water from a
PTW/CTW will depend upon the capital invested and the annual recurring costs. A
large part of the recurring element derives from the pumping cost. Capital and pumping
cost are inter-dependent because the design of TW affects the drawdown and thus
the pumping cost. For example:
A short screen section will produce a large drawdown than a long screen
for a given discharge, thus saving in capital cost is off-set by increased
pumping cost; similarly
A screen of smaller diameter produces excessive friction losses (well
losses) resulting in increased recurring cost;
On the other hand, some increase in the capital cost (by selecting
suitable construction material and pumping equipment) may reduce
pumping head and hence, pumping cost.
Points Needing Attention: For each chosen design parameter, there is
optimum solution for the least possible cost.The capital cost would vary for each of the
individual PTW/CTW, depending upon the following parameters:
❖ Drilling of borehole, including pit digging;
❖ Pump housing, blind pipe type, diameter and length
For the estimation of horsepower of the prime mover, the following factors are
considered:
I) Discharge of the well or pump (Convenient field method to check TW
discharge is given in Practitioners’ Tool Kit)
II) Depth to water table and pumping water level
III) Expected lowering of water table in future
IV) Over all pumping head (considering from the pumping water level below
the ground level to the overhead tank including losses in the
transmission system)
Selection of Pumping Equipment: For the selection of suitable pump, following
factors have to be given a due consideration:
Present static water level;
Estimated draw down at design discharge and pumping water
level under present conditions;
Future pumping water levels due to general lowering of water
table in the area and the reduction in the specific capacity of the
well;
Convenience of operation and maintenance and economic
capability of user(s);
Following types of pumps are normally being used for withdrawing water from
tubewells and open wells:
I) Centrifugal Pump: These types of pumps are being most commonly
used on the small capacity wells – particularly in the private sector
especially by the farmers on more than 90 % of tubewells installed in the
Punjab (0.5 to 1.0 cusec discharge capacity wells). These types of
pumps are normally used in the areas with shallow depth to groundwater
level so as the suction involved is within about 20 feet from the pump
setting horizon
II) Vertical Turbine Pump: These types of pumps have been most
extensively used in the country, mainly, in the public sector. These
pumps are quite suitable for deep water table conditions and large
variation in discharge and pumping head. The cost normally is relatively
very high as compared to centrifugal pumps but the overall convenience
of use and O&M override the cost factor – keeping in view the long-term
operation.
III) Submersible Pump: These types of pumps are generally used
under deep water table conditions – particularly when the water table is
deeper than 80 feet. These pumps are normally used in the deep wells
in Balochistan and some parts of the Punjab Province.
IV) Jet Pump: Jet pumps or double suction pumps are normally being
used in the private sector on small capacity wells. The main advantage
334
MANUAL OF IRRIGATION PRACTICE
GROUNDWATER – OPTIMAL USE & MANAGEMENT
with these types of pumps is that these can draw water from 40-50 feet
depths. However, these are generally available in small sizes, as these
have not become popular in the public sector
One of the major factors for the selection of suitable pump would be long-term
convenience in the operation, maintenance and monitoring of hydraulic efficiency of
tubewells. Some of the merits and demerits of the above types of pumps are discussed
below.
Estimation of Horse Power: Horsepower can be defined as “the force
required for lifting a weight of 550 pounds for one foot in one second”. It is expressed
as:
HP = W*H (work * head) hence,
HP = discharge of water in pounds per second * head in feet/550
Or in case the discharge is known in pounds per minute, then
HP = W * H/33,000 ………… which is … (550*60)
The break horsepower (BHP) is estimated by dividing the HP with the efficiency of
pump and prime mover.
BHP = W*H/550* where is the efficiency factor. Normally, next higher size
available in the market is selected. Value of for pumps with electric motors is taken
as 0.6 to 0.7 and for pumping sets with diesel engines is taken as 0.5.
Efficiency of Pump & Prime Mover: Literature available from the pump
manufactures indicates that the:
Efficiency of the pumps in general is around 75 % (i.e. input/output)
Manufacturers of turbine pumps (KSB and PECO) claim that the pump
bowl assembly has the efficiency of 80 % whereas the pump efficiency
at the head is 75 % of total head (although pump efficiencies differ for
different makes of the pumps);
The efficiency of electric motors (Siemens) is claimed to be 87%,
preferably should be taken as 80%;
Diesel engines manufactures also show that the efficiency of their
products is about 75 %;
Accordingly, the over-all efficiency of the electric pump and prime mover
is taken as 60 % and that of diesel pump and engine as 50 %.
1.2.2. Safe Yield
The annual amount of water that can be taken from a source of supply over a period
of years without depleting that source beyond its ability to be replenished naturally in
"wet years”. Safe yield of a tubewell, well field (group of tubewells), an aquifer or a
basin is the quantity of water which can be pumped /exploited without any continuous
drawdown and /or undesirable effect on the groundwater regime. This varies greatly
depending upon the hydraulic characteristics of the subsurface sediments (viz. sand,
gravel, clay, etc.) and needs to be determined through appropriate investigations and
systematic monitoring of groundwater recharge and discharge components. Major
335
MANUAL OF IRRIGATION PRACTICE
GROUNDWATER – OPTIMAL USE & MANAGEMENT
be estimated at the “well face” and can be correlated with the specific capacity. This
draw down just outside the well or at the well face will denote the aquifer loss.
The draw down measured inside the well will include both the aquifer loss and well
loss. The well loss is associated with the turbulent flow, it is indicated as:
sw =(2.3 Q / 2*π*T) * Log (r2 / r1) + C * Qn ………or
sw =B * Q + C * Qn (by considering (2.3 / 2*π*T) * Log (r2 / r1) as “B”…Where:
B =Aquifer loss component; and
C =Well loss component
Value of “n” is a time variable factor and ranges from 1 to 2. However, generally the
value of “n’ is taken as 2. Accordingly, the total draw down in the well can be expressed
as:
sw = B * Q + C * Q2
During the past investigation by WAPDA and other public sector departments a large
number of studies have been conducted and hence, if need be the field engineers can
refer to such studies.
B. Safe Yield of an Aquifer:
Pragmatically speaking the safe yield of the aquifer, a basin or an area may be defined
as the quantity of groundwater which can be safely pumped on long term basis without
any:
Continuous decline of groundwater levels, and/or
Any deterioration of groundwater quality due to lateral or vertical
movement of saline groundwater into fresh groundwater zones.
Under the normal field conditions – there will always be some variation in the
groundwater components and hence, the pumpage will also vary but some minor
groundwater decline or rise and change in GWQ can be acceptable – as long as there
is no continuous harm to the groundwater regime.
1.3. Monitoring of Groundwater
Historic Background: Historically groundwater monitoring was initiated by
Irrigation Department in start of the 20th century for keeping an eye on the response
of groundwater levels due to the seepage induced by the weir controlled irrigation
system. Control points were selected (generally open wells in those times) along
particular cross-sectional lines in each Doab) for the measurement of groundwater
levels. These data have been used in the development of a large number of technical
reports on the groundwater regime in the Punjab Province and implementation of
Salinity Control and Reclamation Projects (SCARPs).
Groundwater Monitoring by WAPDA: With establishment of WAPDA in 1958, the
role of groundwater monitoring was transferred to SCARP Monitoring Organization
(SMO) for the monitoring of the groundwater levels and quality in the province before
337
MANUAL OF IRRIGATION PRACTICE
GROUNDWATER – OPTIMAL USE & MANAGEMENT
and after the implementation of the SCARP projects for the eradication of the twin
menace of water logging and salinity in the various parts of the province.
Groundwater Monitoring by DLR (PID): After the formation of PIDAs the role
of groundwater monitoring and management was entrusted to the provincial
governments. Hence, from 2003 onwards the groundwater monitoring has been
conducted by Directorate of Land Reclamation (DLR) of Irrigation Department. Main
objective of the groundwater monitoring is to keep a watch on the “time-rate changes”
in groundwater levels and quality in response to the variation in the groundwater
recharge and discharge components – such as variation in annual precipitation, canal
flows and pumping from tubewells for agriculture. As per DLR records:
there are 3,338 GWL monitoring points and of these 1,896 points are
active (2016); whereas
there are 4,014 monitoring points for GWQ of which 3,094 were
operative in 2013.
Relevant data are placed at the web site of Irrigation Department.
1.3.1. Monitoring of Groundwater Levels
Main objective of the GWL monitoring is to identify:
Aerial distribution of groundwater levels in various parts of the Province
with shallow and deep groundwater zones;
Time rate changes in GWL due to the interaction among various
sources of GW recharge and discharge; for
Provision of drainage measures in case of shallow GWL or assessment
of the necessary interventions in areas with continuously declining GWL
for the sustainability of the resource.
Trends in Groundwater Levels: Variations in hydro-climatic conditions, surface
water flows and uncontrolled pumping from around 1,000,000 tubewells keep on
affecting the groundwater storage and quality. Groundwater regime in the Province –
and rather in the Indus Basin keeps on showing small changes which demand
continuous monitoring. Based on the monitoring of groundwater in the Province - the
areas showing conspicuous changes needing attention are discussed below. A broad
picture of GW conditions in the Province is being given.
Areas with Declining GW levels: Such areas - located relatively in the tail
reaches of the main canals and /or in the central parts of the Doabs - include
Khanewal, Lodhran, Multan, Toba Tek Singh, Fort Abbas and Pakpatan districts as
shown in Figure 6:
338
MANUAL OF IRRIGATION PRACTICE
GROUNDWATER – OPTIMAL USE & MANAGEMENT
Jun-05
Jun-06
Jun-07
Jun-08
Jun-09
Jun-10
Jun-11
Jun-12
Jun-13
Jun-14
Jun-15
Jun-16
Period
Oct-05
Oct-06
Oct-07
Oct-08
Oct-09
Oct-10
Oct-11
Oct-12
Oct-13
Oct-14
Oct-15
-40.00
-50.00
-60.00
-70.00
-80.00
-90.00
Field data shows that GWL decline in the “tail end areas” from 2005-16 ranges from 8
feet in Lodhran to about 12 feet in Khanewal. Some other areas are also showing
declining GWL – as per field data. However, the above data shows that there is a need
for cross checks by GW Management Cell atv PID.
Areas with Rising GW levels - located relatively in the head reaches of the main
canals and /or in the near vicinity of the rivers forming topographically low areas
include districts of Rajanpur, DG Khan, Muzaffargarh and Bahawalpur. GWL trends in
DGK area shown in Figure 7, given below:
Figure 7: Rising GWL Trends in DGK Irrigation Zone 2003-16 (Feet/GLS)
339
MANUAL OF IRRIGATION PRACTICE
GROUNDWATER – OPTIMAL USE & MANAGEMENT
Some areas in DG Khan zone falling under the command of CRBC have shown
conspicuous rise after the commissioning of the canal. However the above data shows
that there is a need for cross checks by GW Management Cell atv PID.
1.3.2. Monitoring Groundwater Quality
Main objective of the GWQ monitoring in the area is to identify zones with:
Fresh, marginal and saline groundwater underlying different areas;
Distribution of groundwater quality in aerial and vertical extent;
Time rate changes in GWQ due to the interaction among various sources
of groundwater recharge and discharge; for
The identification of critical areas needing immediate attention in case of
continuous deterioration of GWQ - through appropriate interventions for
the sustainability of the resource.
General standards for the identification of fresh and saline groundwater followed by
DLR in line with FAO guidelines are as shown in Table 3 given below.
Table 3: Irrigation Water Quality Criteria of DLR (PID)
Areas with Deteriorating Groundwater Quality: In the last decade efforts have
been made by the Department to obtain equity of canal water distribution and control
seepage losses in the shallow groundwater areas. However, intensive and
uncontrolled pumping by the farmers particularly in the areas adjacent to the SGW
zones is causing deterioration of groundwater quality.
As a matter of fact there is less recharge in the dry years whereas the farmers have
to pump more groundwater to meet their crop water requirements resulting in induction
of SGW from the saline zones and/or due to the up conning effect in the areas with
shallow layers of FGW overlying SGW. These types of areas /patches can be
observed all over the province – particularly in the areas where the farmers have to
use brackish/saline groundwater to augment canal water to meet crop water
requirements. Based on the monitoring data by DLR some negative changes in GWQ
can be seen in different parts of the province – particularly in the areas located in the
tail reaches and/or near SGW zones – as shown in Figure 8 given below:
340
MANUAL OF IRRIGATION PRACTICE
GROUNDWATER – OPTIMAL USE & MANAGEMENT
Jun-04
Jun-05
Jun-06
Jun-07
Jun-08
Jun-09
Jun-10
Jun-11
Jun-12
Jun-13
Oct-05
Oct-03
Oct-04
Oct-06
Oct-07
Oct-08
Oct-09
Oct-10
Oct-11
Oct-12
Oct-13
Shjaabad-GIS-301 Shorkot HCC-18 Samundri-GIS-356
BWNG GIS-304 Minchinabad GIS-268
Data on groundwater monitoring – on bi annual basis – are available with DLR and
can be used to study the behavior of groundwater regime. These data are also placed
at the PID Web Site.
1.4. Groundwater Management Challenges
Population growth and increasing demand of water for irrigation, water supply, industry
and environmental needs would further boost the importance of groundwater in the
years to come. Drought conditions during 1998-2003 led to acute water shortages and
illustrated just how close water use is to the limit of the resource. The importance of
groundwater for our food and fiber is increasing as we have to ensure the sustainability
of this invaluable resource which is under great threat due to:
Uncontrolled development of groundwater resulting in groundwater
mining showing continuous decline of groundwater levels and
deterioration of groundwater quality due to induction of saline
groundwater through lateral or vertical movement; and
Unchecked discharge of agricultural, industrial and sewerage effluents
into surface and groundwater regimes - making our groundwater “unfit”
for drinking /agricultural purposes due to salinity and/or bacterial
infection.
The aquifer has already started showing adverse side effects of groundwater mining,
quality deterioration and ultimately to hamper the agricultural growth and threat to the
availability of “safe drinking water”. Accordingly, there is a need for systematic
management and regulation of the resource for its optimal but sustainable utilization.
GW Management Problems in Punjab: GW management problems can be
attributed to physical, social, institutional and policy constraints – interacting & tied to
each other. Major GW management problems in the province include the following
aspects –as briefly discussed below (box):
341
MANUAL OF IRRIGATION PRACTICE
GROUNDWATER – OPTIMAL USE & MANAGEMENT
3Studies by Irrigation Department & World Bank under PPSGDP 1997-2001 & Surveys conducted by
Agriculture Extension in Mandi Bahauddin, Sargodha, Muzaffar Garh etc.
344
MANUAL OF IRRIGATION PRACTICE
GROUNDWATER – OPTIMAL USE & MANAGEMENT
-10.00
-20.00
-30.00
-40.00
-50.00
Envisaged institutional set up under the future (desired) and existing scenarios is
discussed below
1.5.3. Institutional Set-up under Future Scenario
A broad outline of the future institutional set-up under future (desired) scenario is
discussed below. There will be an elaborate arrangement for GW monitoring and
management with linkage among various agencies involved in management of water,
agriculture and environment – with an independent body to oversee all the operations
at provincial level – with:
The major role to be played by the Irrigation Department in collaboration
with PIDA, Agriculture Department, PHED / WASAs and PIDA at local
level - with active participation of FOs & WUAs;
The farmers - with help from AWB, FO, KPs and WUA - will automatically
take care of these aspects on optimal and judicious use of groundwater
349
MANUAL OF IRRIGATION PRACTICE
GROUNDWATER – OPTIMAL USE & MANAGEMENT
4“Legal
and Regulatory Framework for Punjab Province by Groundwater Regulatory Framework
Team” Technical Report # 48, February 2001
353
MANUAL OF IRRIGATION PRACTICE
GROUNDWATER – OPTIMAL USE & MANAGEMENT
Permeability of a material (e.g. sand, gravel, sand stone, fractured lime stone, etc.) is
measured in terms of groundwater flow in cubic feet per unit area of cross section. It
is normally denoted, as “K” and the values are expressed as below:
I) Cubic feet of water per unit time per square foot of area (e.g.; 100 cubic
feet per day per foot square). It is also expressed as feet per day (or feet
per second)
II) Gallons per day per square foot – in field units.
354
MANUAL OF IRRIGATION PRACTICE
GROUNDWATER – OPTIMAL USE & MANAGEMENT
Precaution: The pipe should be full and X and Y coordinates should be measured at
right angle with X being parallel to the pipe. In case the orifice flow is partial then the
discharge factor is as below:
Q = 0.00632 * (D)2 * X * a/A / (Y)0.5 - - - -- - - where;
a /A is the ratio of the area of the jet (a) and area of pipe (A).
Example – Tubewell Q: We know that farmers’ tubewells are generally installed
with discharge varying from 0.5 to 1.0 cusec and their delivery pipes are (around 90%)
5-inch diameter. A hypothetical example, in line with the field conditions, is given
below. Say:
D = 5 inches
X = 10 inches
Y = 5 inches
Q = 0.00632 *(5)2 *X / (Y)0.5 = 0.71 cusec
This is in line with our common observation for farmers’ tubewells.
A. Orifice Flow Method
During the pumping tests on the tubewells – particularly using turbine pumps the
discharge is measured by fixing an orifice at the outer end of the discharge pipe. A
mono metric tube is fixed for the measurement of head due to the check on flow at the
orifice. Diameter of the discharge pipe, orifice and the head in the mono metric tube is
checked for the estimation of the discharge – as shown in the figure given below and
the equation and the example. In this case the following figures can be used:
"D"
"d"
5 Punjab Private Sector Groundwater Development Project (PPSGDP), implemented from 1997-2001.
359
MANUAL OF IRRIGATION PRACTICE
GROUNDWATER – OPTIMAL USE & MANAGEMENT
List of Tables
TABLE 1: SAMPLE MOISTURE BALANCE CALCULATIONS ........................................................................... 369
TABLE 2: PARTICLE SIZE CLASSIFICATION............................................................................................... 376
TABLE 3: RANGE OF DRAINAGE COEFFICIENTS “C” FOR LOWER INDUS PLAIN ......................................... 384
TABLE 4: MAXIMUM RECOMMENDED VELOCITIES FOR EARTHEN CHANNELS ............................................. 389
TABLE 5: MANNING “N” FOR EARTHEN CHANNELS ................................................................................... 389
TABLE 6: RECOMMENDED B/D RATIOS .................................................................................................... 390
TABLE 7: RECOMMENDED SIDE SLOPES .................................................................................................. 390
TABLE 8: DESIGN CRITERIA FOR DROP IN W ATER LEVEL ......................................................................... 395
TABLE 9: VALUES OF C FOR USE IN THE AUGERHOLE METHOD ................................................................ 419
TABLE 10: SHAPE FACTOR C/R FOR USE WITH THE PIEZOMETER METHOD ............................................... 423
TABLE 11: W ATER QUALITY CRITERIA .................................................................................................... 424
TABLE 12: COMPUTER IRRIGATION SIMULATION DATA FOR COTTON......................................................... 426
TABLE 13: RANGE OF DRAINAGE COEFFICIENT ....................................................................................... 428
TABLE 14: DAIN SPACING CRITERIA USED IN PROJECTS IN PAKISTAN ........................................................ 430
TABLE 15: EQUIVALENT DEPTH “D” FOR COMMONLY USED PIPE DRAINS..................................................... 433
TABLE 16: GRADATION RELATIONSHIP BETWEEN BASE MATERIAL ........................................................... 442
TABLE 17: GRAVEL ENVELOPE GRADATION ............................................................................................ 443
TABLE 18: CLASSIFICATION OF SALINE AND SODIC SOILS ........................................................................ 461
List of Figures
FIGURE 1: DRAINAGE SYSTEM CLASSIFICATION ...................................................................................... 364
FIGURE 2: W ATER TABLES IN THE SOIL ................................................................................................... 371
FIGURE 3: TYPICAL HYDROGRAPHS OF W ATER TABLE ELEVATIONS ......................................................... 372
FIGURE 4: SIMPLE PIEZOMETER SUITABLE FOR DRAINAGE STUDIES......................................................... 373
FIGURE 5: TYPICAL USE OF PIEZOMETERS .............................................................................................. 374
iv
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
1. INTRODUCTION
1.1. Definition
Land drainage is the removal, by artificial means, the excess water from the land
surface or from the soil to make the soil more suitable for agriculture by increasing
production, sustaining yields and reducing production costs.
Adequate drainage provides proper balance between soil moisture and oxygen both
of which are required by plants to grow and survive. Drainage is essential to maintain
supply of oxygen and helps to maintain a favourable salt balance in the root zone.
When saline water table rises and remains in the root zone for more than 48 hours,
agricultural production is seriously affected.
1.2. History and Importance
Importance of irrigation is easily understood and appreciated. Without water, the crops
do not grow. Without drainage, some sort of agriculture is possible, though crop yields
are seriously affected. Operation and maintenance of surface drains is also a major
issue. Professionals as well as farmers are, therefore, much less enthusiastic about
drainage as compared to irrigation.
During the development of irrigation network in Pakistan, surface drainage received
limited attention; partly this could be due to the fact that natural drainage at that time
was fairly effective since infrastructure was not fully developed and natural drainage
paths were not blocked. Water table at that time was between 6 to 30 m below the
land surface, subsurface drainage was not, therefore, considered seriously during
planning.
Lack of adequate surface drainage, seepage from irrigation networks and deep
percolation from the irrigated fields have brought the water table and the salts close to
the surface. Agriculture in seriously affected areas came to a halt. The need and
importance of subsurface drainage, thus got recognized at professional and policy
making levels.
1.3. Benefits of Drainage
Surface and subsurface drainage promote conditions that:
• improve soil structure and workability,
• help intake of water and nutrients and develop root growth,
• provide aeration in the root zone thus ensuring oxygen supply to crops,
• encourage aerobic bacteria which are needed to provide nitrogen for crops,
• improve preparation, planting, cultivation and harvesting operations,
• cause warming of soil which promotes biological and chemical activity that is
important for seed germination and plant growth (saturated soils are 7 oF to
14oF cooler than drained soil), thereby making early plantation possible for 2
to 3 weeks,
• promote deeper root development leading to healthier and more vigorous plant
growth,
362
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
• drain capacity takes into account the escape discharge from irrigation
channel,
• sheet flow does not enter surface drains,
• saline tubewells operation is staggered to let the surface runoff peak pass,
• urban base flows are considered as additional flows in the drain capacity
calculations. However, irrigation excess flows is not considered since the
drain designed for storm runoff handles these flows.
Figure 1: Drainage System Classification
365
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
a year or more. There are no short cuts to save time at this stage. Allowing reasonable
time is a pre-requisite for a sound engineering plan.
Detailed Design Stage
This is the final stage for project implementation. While the Feasibility Report provides
the basic information, the final design may vary from the feasibility level design. At this
stage more elaborate field investigation is carried out. This may take more time than
what was required for feasibility. All plans and drawings are detailed so that these
serve as working drawings for implementation.
1.12. Scope of the Manual
The manual updates Chapter 12 (relating to drainage) of the 1943 Manual of Irrigation
Practice and supplements the Surface Drainage Manual for Pakistan which do not
cover subsurface drainage. Its objective is to sensitize the professionals of Irrigation
and Agriculture Departments to the importance, need and benefits of drainage for the
success and sustainability of irrigated agriculture. It is not meant to be a text book on
drainage nor can it cover the full aspects for the design of surface and subsurface
drainage. It does however provide broad design principles and guidelines for planning,
design and maintenance of drainage systems.
The manual includes engineering techniques and practices that have proved useful
over the years for successful irrigated agriculture. It provides drainage engineers, a
ready reference and a guide for the assessment of drainage requirements and
provides tools and procedures for the design of drainage system.
2. GENERAL INVESTIGATIONS
2.1. Topography
Topographic maps are indispensable for the planning of a drainage project.
Information from these maps determines whether or not and to what extent drainage
facilities are required. Favourable topography may provide adequate natural drainage
and reduce the need for artificial drainage.
• For feasibility study, topographic survey with a scale of 1:10,000/25000
and contour interval of 0.6 to 1.5 m (2 to 5 ft) suffice. For detailed design,
more detailed maps are needed, usually to a scale of 1: 5000/10,000 with
contour interval of 0.3 to 0.6 m. For flat land, contour interval of 0.3 m is
normally required.
• Map scale should match the contour interval so that the contour lines are
not more than 5-10 cm and not less than 0.5-1.0 cm apart.
• For the design of groundwater drainage systems, somewhat lower
standard for the mapping may be acceptable.
• Topographic maps should also show the main elements of any existing
drainage system (natural as well as artificial) and all relevant
infrastructural features, such as roads, railways private buildings etc.
368
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
(evapotranspiration)
(Precipitation)
Excesses
(storage)
Deficits
P-E
P
S
mm mm mm mm mm mm
End of January S = Smax =75
February 54 ___ +54 75 54
March 49 24 +25 75 25
April 69 70 -1 74
May 90 102 - 12 62
June 101 116 - 15 47
July 85 136 - 51 0 4
August 81 112 - 31 0 31
September 80 65 +15 15
October 67 30 +37 52
November 102 10 +92 75 69
December 79 5 +74 75 74
January 60 ___ +60 75 60
(Source: Land Drainage, BT Batsford Ltd. London)
2.4. Hydrogeological Survey and Mapping
Hydrogeological map is a dynamic tool for groundwater management, particularly the
demarcation of aquifer and may be used as a ready reckoner for groundwater quality
and quantity.
Hydrogeology Directorate of WAPDA prepared a hydrogeological map of Pakistan to
a scale of 1:250,000. The map was prepared in 2001 to international legend
established by UNESCO.
Following information is available from these maps:
• demarcation of principal groundwater bodies,
• demarcation of groundwater scarcity areas,
• demarcation of saline groundwater and surface body,
• variation in groundwater quality,
• groundwater pollution threat areas,
• demarcation of precipitation data in the form of isohyetal contours,
• geological features to help understand groundwater regime,
• groundwater potential for each province and region,
• tubewell yield ranges for different basins,
370
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
The information available in these maps may not be relevant in certain respects. The
survey is supposed to be updated every 10 years, which has not been done. To
exercise a vigilant control of groundwater and for maintaining salt balance,
hydrogeological mapping should be part of investigation for long-term planning of
drainage.
2.5. Geological Investigation and Soil Characteristics
These investigations are needed for the design of surface as well as subsurface
drainage systems. The most widespread soil material in irrigated lands of Pakistan is
alluvial in character. These water deposited materials range from clays to coarse
sands. Most alluvial soils have good hydraulic conductivity for the design and
development of an economically viable drainage system because of adequate
hydraulic conductivity of soil. Geological investigations are required at the site of
structures for designing suitable foundations for structures and for the stability of side
slopes in designing the earthen sections of surface drains.
An impermeable barrier, (mostly horizontal), its thickness, its spatial occurrence and
its gradient affect the flow pattern to the subsurface pipe drains. The barrier restricts
vertical movement of water although in some cases, vertical barriers can restrict
horizontal movement of water.
2.6. Aquifer Characteristics
Aquifer of different types may occur at various depths. The groundwater in the
permeable strata may be freewater under normal static or dynamic pressure or it may
be subjected to an over-pressure. The later may occur where an aquifer is overlain
by a poorly permeable layer. Such aquifers are termed as confined aquifer.
Agricultural drainage is primarily concerned with the free groundwater directly below
the surface i.e. the “Phreatic Groundwater”. Its surface is termed as “Phreatic level or
water table” (Fig. 2 (a)).
Phreatic groundwater 25-50 m below the soil surface is of little direct concern for
agriculture drainage. If water table is less than 5 m below the soil surface, it has
relevance to agricultural drainage.
For the calculation of design discharge for subsurface drainage, determination of the
existence or otherwise of artesian aquifers is essential. An artesian aquifer which is
under sufficient pressure and causes the piezometric water surface to rise to near the
ground surface contributes additional discharge for the subsurface drains. In such
situations, the drain discharge comprises deep percolation from irrigation and artesian
water.
2.7. Water Table (Phreatic Level) and Perched Water Table
The location of water table is determined by sinking a borehole into the body of
groundwater. The borehole is fitted with a perforated pipe, water from the adjoining
soil flows into the pipe and fills it to the water table level.
371
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
1128
OBSERVATION
1
WELL (O.W) 1128
4 2 N - 2E
1127 1127
1126 1126
1125 1125
1124 1124
Ground Surface Elevations -1137.0
QW. 3 12 S - 4 34W
1131 1131
1130 1130
1129 1129
1142 1142
1141 1141
TYPICAL HYDROGRAPHSOF
1140 WATER TABLE ELEVATIONS 1140
5 10 15 2025 5 10 15 2025 5 10 15 2025 5 10 15 2025 5 10 15 2025 5 10 15 2025 5 10 15 2025 5 10 15 2025 5 10 15 2025 5 10 15 2025 5 10 15 2025 5 10 15 2025
JAN. FEB. MAR. APR. MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC.
top of the perforation. At this point, 1 to 1 bentonite – soil mixture should be tapped
around the casing and mounded on the ground surface so as to prevent surface water
entering the sand and then to the casing. For permanent observation wells, a concrete
collor may be placed at ground surface. A careful log of the soil should be preserved
while auguring. The depth of observation hole should be below the lowest expected
groundwater level.
Figure 5: Typical Use of Piezometers
TEXTURAL CLASSES
TEXTURE SAND % SILT % CLAY %
SAND (S) 85 to 100 0 to 15 0 to 10
LOAMY SAND (LS) 70 to 90 0 to 20 0 to 15
SANDY LOAM (SL) 43 to 85 0 to 50 0 to 20
LOAM (L) 23 to 52 28 to 50 7 to 27
SILT LOAM (SiL) 0 to 50 50 to 100 0 to 27
SANDY CLAY LOAM (SCL) 45 to 80 0 to 28 20 to 35
CLAY LOAM (CL) 20 to 45 15 to 53 27 to 40
SILTY CLAY LOAM (SiCL) 0 to 20 40 to 73 27 to 40
SANDY CLAY (SC) 45 to 65 0 to 20 35 to 55
SILT (Si) 0 to 20 80 to 100 0 to 12
SILTY CLAY (SiC) 0 to 20 40 to 60 40 to 60
CLAY (C) 0 to 46 0 to 40 24 to 100
BASIC TEXTURAL CLASS MODIFYING TERM
378
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
SAND GRAVEL
Diameter, U.S Term Content
millimeter Standard Percent Term
sieve
numbers
0.05 to 0.10 300 to 140 Very fine sand (VFS) 20 to 50 Gravelly (Gr)
0.10 to 0.25 140 to 60 Fine sand (FS) 50 to 90 Very (VGr)
gravelly
0.25 to 0.50 60 to 35 Medium sand (S)
0.50 to 1.00 35 to 18 Coarse sand (CsS)
1.00 to 2.00 18 to 10 Very coarse (VCsS)
sand
Coarse sand :25% or more CVsS and less than 50% of any other grade of sand.
Sand :25% or more VCsS, CsS, and S, and less than 50% of F or VFS.
Fine sand :50% or more FS and less than 25% of VCsS, CsS, and S and less than 50% of
VFS
Very fine :50% or more VFS
sand
(Source: Drainage Manual, US Deptt. of the Interior Bureau of Reclamation)
2.11. Specific Yield
It is defined as the volume of water released from a known volume of saturated soil
under the force of gravity and the inherit soil tension.
𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟 𝑑𝑟𝑎𝑖𝑛𝑒𝑑
𝑠𝑝𝑒𝑐𝑖𝑓𝑖𝑐 𝑦𝑖𝑒𝑙𝑑 𝑆 = 𝑥 100
𝑡𝑜𝑡𝑎𝑙 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑠𝑎𝑡𝑢𝑎𝑡𝑒𝑑 𝑠𝑜𝑖𝑙
For optimum crop growth, the specific yield should be in the range of 6 to 10%. In this
range, the soil has sufficient aeration, hydraulic conductivity and water holding
properties. If S is less than 3%, drainage becomes difficult.
Specific yield can be determined using undisturbed soil sample of known volume. Both
laboratory and field tests of specific yield are difficult to perform and are expensive.
Field offices may not be equipped to do the test. U.S.B.R has developed a relation
between hydraulic conductivity and specific yield on the basis of 2000 lab tests.
Specific yield may be determined from Fig. 7.
3. DESIGN OF SURFACE DRAINAGE SYSTEM
3.1. General
The design of surface drainage system may be divided into:
a. Selection of type and layout of the system, including alignment of sub,
branch and main drains.
b. Determination of the hydraulic dimension of the different components.
379
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
The main function of a surface drainage system is to convey the excess water from
agriculture fields to the outlet point. The system may also have to receive and convey
discharge from urban drainage system. The layout of the system is based mostly on
the geography and topography of the area. It has an interrelationship with the layout
of irrigation system as well as the road network in an area.
3.3. Alignment
Main drains are generally aligned considering topography and location of the outlet
point. Existing infrastructure also impacts on the alignment. The main drain mostly
follows the depression. However, major depressions should be avoided due to
constructability problems and subsequent maintenance issues relating to sloughing of
side slopes. Cost optimization studies influence the alignment and it should be the
shortest route within the basin. The alignment and the bed levels should be such that
it directly provides relief to the adjoining farm lands.
The sub-drains also follow the depressions and sometimes, the requirement for main
branch/sub drains, are in conflict with regard to levels. A compromise solution is
developed for the most suitable alignment for the network.
A serious consideration is given to maintain the source of irrigation when a farm is
severed by the drain alignment. This involves construction of a large number of water
course crossings or else the drains alignment should follow the chakbandi lines. For
main drains, the transfer of land from one source of irrigation to the other may also be
considered if the cost of water course crossings becomes excessive.
The alignment should not be close to potential or important wetlands, as the drainage
tends to dry the wetlands with a negative environmental impact on ecology.
3.4. Design Rainfall
The design rainfall is the most critical rainfall event that the drainage system has to
handle. Although higher than design rainfall may occur and may cause damages, yet
these events are rare. It may be economical to accept occasional damages than to
construct a foolproof expensive system capable of handling extreme rainfall events.
The selection of design rainfall is based on the return period for the rainfall event.
3.5. Return Period
Return Period is the frequency of occurrence of a rainfall event. As the rainfall depth
increases, its frequency of occurrence decreases. This relationship is plotted as
frequency curve. An example is shown in Fig. 8.
From Fig. 8, a 48 hours rainfall higher than 40 mm is expected to occur once every
year, while a depth higher than 85 mm is likely to occur once every 5 years (5 year
Return Period). Selecting higher period, the capacity of the system increases and
damages are reduced but the cost of constructing and maintaining the system
exponentially increases. The selection of design rainfall which in turn depends on the
return period is an economic parameter involving optimization of benefits in relation to
cost. Cost optimization curves can be drawn, as shown in Fig. 9 to determine the
lowest cost corresponding to a return period.
381
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
125
rainfall depth (mm)
100
uncontrolled rainfall
75 design rainfall
50 controlled rainfall
25
0.5 1 3 5 7 9 11
total costs
200 annual costs
of the drainage
system
100
Rainfall data is available from MET offices, WAPDA Hydrology Directorate and the
rainfall gauging stations installed at important locations. A minimum of 10 years data
should be required for doing full frequency analyses. Collection of fresh rainfall data is
seldom needed.
If a particular drainage basin does not have the requisite rainfall data, data for a
nearest rainfall gauging station may be utilized.
3.6. Design Discharge
Design discharge at a particular point in a drainage network is generally based on
rainfall since this is almost always the most critical source of excess water which is
required to be removed. Intense storm of short duration normally produces the peak
flow. Urban uniform flows and subsurface flows are added to the rainfall runoff. The
rainfall runoff relationship is a complex matter which is dependent upon lot of variables,
primarily the storage and flow resistance. The soil has potentially the largest storage
capacity (storage underground through deep percolation and storage on the surface
within the bunded cultivated fields). The factors offering resistance to flow include the
land-use, its roughness and gradient.
Effect of Time of Travel
In addition to the runoff generated from different sub-basins, the effect of time of travel
from different sub-basins to the point of concentration is also a relevant consideration.
Even if the rainfall intensity and its duration for different sub-basins might be the same,
the peak from farthest sub-basin does not coincide with the peak of nearest sub-basin
from the point of concentration.
Due to the complexity of these variables, the statistical method for calculating the
design discharge is the simplest and most reliable method.
Statistical Method
In this method, the existing discharge data from different stream gauging stations
within an area is analyzed to compute the design discharge. This method is more
relevant if an existing drainage system is to be remodeled or if new drainage sub-
basins are to be added in the existing drainage system. Stream gauging discharge of
20 to 25 years suffices for the design of agriculture drainage systems.
During planning and design of various SCARPs (Salinity control and Reclamation
Projects), lot of basic data relating to rainfall and steam gauging has been and is being
collected for most of the Indus Basin. The stream gauge data may be obtained from
Chief Engineer, Surface Water Hydrology, WAPDA.
A sample discharge data from the gauging station is analyzed in Table 3-1.
383
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
for outfall drains if justified on the basis of economic analysis – optimizing annual
drainage cost compared with the benefit of reduction in losses.
Since all the sub drainage basins do not contribute runoff uniformly, a reduction factor
has to be applied as the catchment area increases. A reduction factor commonly used
is an exponent of 5/6 = 0.833. It was first used in Pakistan by Tipton and Kalmbach,
WAPDAs consultants in 1963. For large catchments, the Empirical equation is
Q = CM0.83.
To simplify the application of this method, the value M0.83 can be determined from the
graph of Fig. 11:
The range of drainage coefficients are given in Table 3.
Table 3: Range of Drainage Coefficients “C” for LOWER Indus Plain
C
(cusecs per square mile)
Region Crop & Mgt. Factor Minimum Maximum
North Punjab Bunded Rice Fields 4 10
& KPK Bunded Veg. & 6 15
Grain
South Punjab Bunded Rice Fields 2 8
& Baluchistan Bunded Veg. & 3 10
Grain
Sindh & Bunded Rice Fields 2 4
Baluchistan Bunded Veg. & 2 6
Grain
(Source: Surface Drainage Manual for Pakistan)
Within this range, the designer selects a value considering the local conditions, i.e.,
rainfall, irrigation, soil infiltration, crops, topography, flooding etc. For a varying land-
use, a composite value of drainage coefficient may be applied based on judgment and
performance of older drainage system in the areas.
385
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
Figure 11: Catchment Area (M) to 5/6 (o.833) power versus catchment area in square miles
(Source: Surface Drainage Manual for Pakistan)
386
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
R
E
B
6 M
U 0
DIRECT RUNOFF (Q) IN INCHES
N 10
VE 95
R
U 90
C
5 85
80
75
4 70
65
60
55
3
50
45
40
2
35
30
1
25
20
0
0 1 2 3 4 5 6 7 8 9 10 11 12
RAINFALL (P) IN INCHES
Figure 13: Direct Runoff Based on Curve Number and Rainfall
(Source: Drainage Manual, US Deptt. of the Interior Bureau of Reclamation)
A given catchment might have different soil types and soil covers. For these conditions
a weighted average number may be computed by multiplying respective CN by the
areas and dividing the summation by the total catchment area.
Procedure for Determining Runoff
After obtaining CN number for an area from Fig. 12, of 68 and the rainfall of 3 inches
(75 mm), the runoff for a given area is directly derived from Fig. 13 as 0.65 inches
(16mm) /per acre. For a catchment of 800 hectare (2000 acres), the runoff will be
2000 𝑥 0.65
= 108.3 acre ft.
12
If this is to be removed in two days (48 hours), the design discharge is 108/4 = 27
cusecs (one cusec running for 24 hours is equal to 2 acre ft).
3.7. Hydraulic Design
In general this part of the design is fairly straightforward, based on well-established
hydraulic engineering principles and practices. The hydraulic design of surface drains
is almost always based on steady uniform flow; discharge is constant in time and also
constant along the length of the drain. Under these conditions, the following formula
applies:
Q = VxA
388
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
return period; less freeboard for higher return periods. Freeboard defines the bankfull
capacity of the channel. Alternate approach could be to specify bankfull capacity of
channel and determine the incremental capacity of the channel above Qd for the given
return period. The difference between the depths for bankfull capacity (say, for a
return period of 1 in 25 years) and the depth for Qd for return period 1 in 5 years is the
freeboard.
In practice, freeboard of 1 ft (0.3 m) may be used for small drains with discharge up to
70 cusecs (2 m3 /s) and freeboard of 2 ft (0.60 m) may be used for discharge for 70 to
130 cusecs (2 to 3.7 m3 /s). For larger capacity drains, 3 ft (1 m) freeboard is commonly
recommended.
Drain Intersections
The sub-drains should enter the branch drains with their water surface at the same
level or allow a fall in head of 0.25 to 0.5 ft (7.6 cm to 15 cm). If the discharge of sub-
drain is more than 15 cusecs (0.4 m3 /s), the bottom grade must be curved downstream
to make the flow lines of the drains nearly parallel at the point of junction. It is not
necessary for smaller drains but may be applied, as it could reduce maintenance costs
at the point of intersection.
Transition Sections
Variation of the drain depth or bed width should be gradual. A transition should be
designed for gradual widening or deepening. For the junction of a shallow and a
deeper drain, 10 to 100 ft (3 to 30 m) transition in the upstream shallow drain is
provided on a zero grade at the elevation of the deeper drain before the beginning of
the transition. The transition should have a non-erosive grade not to exceed 1 percent.
If the difference in the bed levels of two drains is significant, a fall structure may be
provided.
Berms
Berm is a setback between the cut section of the drain and the bank. This is provided
to meet various requirements. The depth and width of drain influence the decision
whether or not a berm is to be provided. For large sections, berms provide a track for
the excavator. But if the berms are eroded, they become a hurdle during maintenance
since distance increases between the service road the drain. For cut section deeper
drains, they prevent excavated material from falling back into the drains. They also
prevent sloughing of banks by shifting bank load away from the edge of the drain.
Banks
Banks are constructed to prevent sheet flow entering the drain and also to prevent the
flow going out of the drain. Depending upon the size of the drain, and the purpose
they serve, these can be classified as follows:
i. Inspection Road: Usually 15 to 20 ft (4.5 to 6 m) wide and maximum 3 ft
(1 m) above the natural ground level or 3 ft (1 m) above the design
discharge / water level whichever is higher,
392
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
For possible future deepening or widening the drain bed, the top of the open
foundation should be placed 2 ft (0.6 m) below the bed level. It is also a practice to
provide protected end piers rather than permanent abutments on both sides.
Culverts
Culverts usually consist of pipes when the discharge is small (Q <15 cusecs (0.4 m3
/s)). For larger discharges, more pipes may be installed. However, for the discharge
in the range of 30 to 70 cusecs (0.8 to 2 m 3 /s), box type culverts are generally
preferred. The invert of the culverts is usually laid flush with the drain bed and the top
of the culvert should have a minimum clearance of 4 inches (100 mm). The exit
velocities should be checked. If these are found to be too high, preferably the cross-
section should be increased rather than providing anti-scouring measures. In any case
it is a question of relative economy of the two options.
Syphons
In most cross drainage structures for irrigation channels, the levels permit free flows
in both cases. In a few situations, a syphon may be necessary. The drainage flow
should not be passed through a syphon because variable flow and low velocities may
cause sediment deposits, producing maintenance problems.
Drop structures
For a significant differential level at a control point, a drop structure, should be used.
Table 8 lists the design criteria.
Table 8: Design Criteria for Drop in Water Level
Drop in water
Structure
surface level
0 to 2 ft (0 to 0.6 m) No structure, but riprap protection
Rock cascade drop, with sheet
2 to 5 ft (0.6 to 1.5 m)
piles
5 ft and above (1.5 m Proper fall structure to be
and above) designed with baffled apron/chute
(Source: Surface Drainage Manual for Pakistan)
Drainage Inlets
Storm flows/excess water should enter the drain, not as a sheet flow, but through
drainage inlets. These should be liberally provided in irrigated cultivated areas. The
catchment should be subdivided into mini catchments, taking into consideration the
topography. The inlet is placed at the lower point of the catchment along the drains.
The capacity of the structure should be according to the flow generated from each sub
catchment. However, minimum diameter of the pipe should not be less than 1.5 ft (0.45
m). While the invent level of the pipe is at the lowest field level, its outlet in the drain
should be atleast 1.5 ft (0.45 m) above the normal water surface elevation and should
396
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
extend 1 ft (0.30 m) beyond. The velocity in the pipe should not exceed 10 ft/s (3m /s)
and the minimum pipe slope should be 0.01.
The concrete entry box of the drainage inlet should have orifices at three levels. The
first level is at the invent level of the pipe, the second about 1 ft (30 cm) above and the
third level, a few inches below the top of the box. The orifices should be 4 inches (100
mm) to 6 inches (150 mm) in diameter. The number varies according to its catchment
area. The purpose of control entry box is to restrict entry into the surface drains. The
total entry area of the orifices should be sized so that runoff from the catchment is
stored in the fields for about 48 hours.
Controlled entry through the entry box via orifices has the following advantages:
• erosion of top fertile soil is minimized,
• entry of sediments and debris in the surface drains is restricted, leading to
lower maintenance cost,
• it provides time lag for peak flows from different catchments, making it
possible to maintain design discharge within various reaches of the drain,
• flushing of salts in the field due to deep percolation,
• groundwater gets recharged.
If the groundwater table in a specific area is high, the evacuation should be within 24
hours. The area of the orifices and their levels are adjusted accordingly.
All drainage inlets should be inspected after a major rainfall event to check their
performance with respect to the catchment. If the storage in the field has been reported
to exceed 48 hours, additional orifices at appropriate level may be added or the
diameter of the orifices can be increased.
Head loss in Structures
The headloss for flow through structure may be calculated using the following formula:
Q = µ A √2𝑔ℎ
Where:
Q = discharge rate, in m3/s
A = wet cross section area, in m2
g = gravitational acceleration (= 9.8 m/s2)
h = headloss, in m
µ = coefficient
The value of “µ” depends on the entry and exit conditions for the water to flow
into and out of the structure under normal conditions. Typical values of
coefficient are:
- Short culverts length < 30 ft (10 m) µ =0.8
- Long culverts length 50 to 100 ft (15 to 30m) µ =0.7
- For bridges a value of 0.8-0.9 is commonly used
397
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
Figure 16: Main Characteristics and Layout of a Land Drainage Pumping Station
Pump House
Water flows
Water flows spirally
outwards at right
along axis
angle to axis
(Axial Flow)
(Radial Flow)
Top Mounted
(Pump Submerged ) Mixed Flow
400
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
It is affected by
• Hydraulic losses in the pump
• Mechanical losses in the bearing, seal
• Leakage of water
Figure 19: Shapes of Rotodynamic Pumps
pumping. This additional head comprises friction losses in the suction pipe, and in the
delivery line.
𝑉𝑑2
H = Hs + Hfs + Hd + Hfd + 2𝑔
Where:
H = total dynamic head
Hs = suction head
Hd = delivering head
Hfs = friction loss in the suction
Hfd = friction loss in the delivery
Vd = flow velocity at the outlet of the delivery
Figure 20: Components of the Dynamic Head
To simplify selection of a suitable pump for various discharges and head combinations,
selection chart of Fig. 21 should be helpful.
Figure 21: Selection Chart for Pumps
vibration. This limits the maximum height between the lowest invert level in the sump
and the pump. The limit for radial pump is 25 ft (7.5 m) and for an axial flow pump, 5
ft (1.5 m).
Figure 23: Principal Dimensions of a Well-Designed Intake Sump
Where:
E = power consumption (kWh)
Q = discharge (m3/s)
H = total dynamic head (m)
rho = density of water (kg.1-1); normally p = 1.0 but values are higher when
the water is salty or dirty
e1 = site correction factor; equal to 1.0 at MSL and 15°C (reference)
increasing by 1% for each 100 m rise in elevation and by another 1% for
each 5°C rise in temperature
e2 = safe load factor, taking into account the fact that the engine should not
run fully loaded continuously; normally e2 is about 1.3-1.4 (engine 70-
75% loaded)
ᶯ1 = transmission efficiency, normally is of the order about 0.90 to 0.95
ᶯp = pump efficiency; for axial and mixed flow pumps, ᶯp= 0.65 for H~1.0 m,
increasing to ᶯp = 0.80 for H = 2.5-3.0 m and higher; for radial flow
pumps, ᶯp = 0.60 for H = 1.0 m increasing to ᶯp = 0-80-0.85 for H>4.0m.
Annual Operating Cost Estimation
Capital cost annuity:
𝑇𝑜𝑡𝑎𝑙 𝑐𝑎𝑝𝑖𝑡𝑎𝑙 𝑐𝑜𝑠𝑡
𝐷𝑒𝑝𝑟𝑒𝑐𝑖𝑎𝑡𝑖𝑜𝑛 𝑟𝑎𝑡𝑒
(equipment life range from 4 to 25 years; on the average take 10 years depreciation
period).
406
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
Energy cost:
i. For Electricity = E x N x P1
E = kWh (unit)
N = running hours per annum
P1 = Electricity unit rate (per KWH)
ii. For Gasoline / Diesel
Cost = E x N x P2 x U
P2 = Rate of fuel per liter
U = Fuel consumption; for gasoline 0.50 to 0.80 liter/KWH,
for diesel, 0.30 to 0.65 liter/KWH
5. OPERATION AND MAINTENANCE OF SURFACE DRAINS
5.1. Introduction
The performance of drainage systems depends on how the system is operated and
maintained. Even a best constructed system does not perform properly if not
maintained adequately. The O&M of drainage system is, however, more demanding
and challenging as compared to that of an irrigation network. In irrigation, the operation
is more demanding as compared with maintenance, in the case of drainage, it is the
other way around.
An effective maintenance program cannot be developed without regular monitoring of
the drainage network. Special monitoring is also warranted after major rainfall events.
Unfortunately this important aspect is commonly overlooked and O&M estimates are
prepared based on standard operation. The requirement for and maintenance of a
drainage system widely vary. Sub drains, in stable soils with low flow and low ground
water table may require desilting after 4 to 5 years. On the other hand, the surface
drains with seepage flow in unstable soil require different criteria and benchmarks for
O&M.
5.2. Maintenance Problems
The flow in the surface drains may be blocked due to one or more of the following
reasons:
• reduction in velocities and accumulation of sediments due to aquatic
weeds,
• sloughing of side slopes due to high water table,
• erosion of slope and soil bank during rainfall, particularly in freshly
constructed drains / or freshly rehabilitated drains,
• erosion of top soil from agricultural fields and its entry in the surface drains
via uncontrolled drainage inlets,
• malicious cutting of banks by farmers to dispose of their excess water due
to lack of availability of drainage inlets,
• blockage at cattle ghats due to raised bed level at these spots,
• entry of untreated sewerage/industrial waste that carries lot of debris,
407
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
• poor condition at the outfall that blocks the flows, causing backwater curve
and overtopping of banks,
• surface drains are commonly built in depressions which are waterlogged
and affected by salinity. The drainage structures are, therefore, subjected
to sever chemical attack and deteriorate faster.
5.3. Weed Control and Clearance
General
The aquatic weeds are broadly categorized as floating weeds (mainly Algaee and Gul
Bakaoli or water hyacinth) and weeds with roots (Gul Abbasi etc.). The flow is reduced
due to weeds and washed down material from the side slopes starts to accumulate in
the bed, further blocking the flow (Fig. 24).
Figure 24: Weed Growth
Mechanical Removal
A wide variety of equipment is available to perform different functions, such as
mowers, weed rakes, weed harvesters and conventional excavators that clear the
weed and sediments in a single operation. It may not be feasible for the department
to keep an inventory of a wide variety of equipment and machinery. The weeds
clearing equipment should preferably be standardized on the basis of commonly
available and operated equipment in the country. The standardization is a compromise
solution for overall economy of operation.
Chemical Control
The use of herbicides is quite effective provided the appropriate chemicals for the
weeds are employed and their application is scheduled in accordance with the growth
cycle of the weeds. Fully grown weeds may not be easy to control with the chemicals.
The herbicide use has associated health hazards and they may also destroy the
vegetation on the slopes which is needed for slope stability. The dead weeds have, in
any case, to be removed and disposed off. Since the water in drains is consumed by
cattle and also recirculated to irrigation systems, its extensive use can be hazardous.
Because of these serious drawbacks, this option has limited applications.
Biological Weed Control
Grass carp (a fish variety) has been successfully utilized in many parts of the world.
Carp survives in conducive environment and die if the water level falls or dries. It may
not be possible to control fishing if the population in the adjoining areas start fishing
and eating the catch.
Burning Weeds
Channels which become dry during a part of the year, burning the weeds is the most
economical solution provided it is done with care. If should be done immediately after
harvesting of wheat crop and before the monsoon. Care should also be exercised that
the desirable vegetation on the side slope does not get burnt in the process.
5.4. Silt Clearance / Re-Sectioning
The silting of drainage channels is different as compared to the irrigation channels.
The material deposited in the drain bed is from the sloughing of side slopes, rain
washed material from the sides, berms and spoil banks. A substantial amount of earth
also enters the drains through the drainage inlet structures. The low velocities of
surface drains cannot carry and discharge sediment load.
Most of the sub-drains with relatively small sediment load can be desilted manually.
For large drains particularly those with regular flows, mechanized desilting is the only
option. A bucket attached with a large size 4x4 tractor preferably of local brand is
most suitable (Fig. 25). For heavy work, regular excavators or draglines are more
suitable. If resectioning is also involved, then the dragline that cuts groves in the side
slopes is unsuitable. The material on the side slope with groves is more prone to be
washed back into the drain during rainfall.
409
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
• providing liberal and controlled drainage inlets so that land erosion from
agricultural fields is minimized and the farmers do not have to cut drain
banks in order to dispose off excess rainfall runoff,
• planting grass and shrubs on side slope and spoil banks to stabilize
slopes,
• lowering the bed at cattle Ghatt sites,
• providing interceptor drains to avoid sloughing of slopes,
• cutting cunet to generate sufficient velocities during period of low flows,
• avoiding sheet flow entry of runoff by constructing banks on both sides as
water retaining structures.
5.9. Scheduling of Maintenance
The primary consideration from an operational point of view is that the system should
be able to carry the design runoff before the Monsoon. A drainage system comprising
the outfall/main drain, its branches and the sub drains should be considered as a
drainage unit. The priority in terms of scheduling is for the main drain, then the
branches and sub drains. Similarly, seepage drains have priority over storm water
drains, since seepage drains provide continuous relief by keeping the water table
down. Scheduling for silt and weed clearance is related to the depth of silt deposit.
The silt in seepage drains should be cleared as soon as it is about 6 inches (0.15 m)
deep. Historic record of the silt deposit is a good guide to schedule a maintenance
programme.
Those drains which receive the ground water effluent from subsurface drainage
projects are very important to remain capable to efficiently dispose off the excess flow.
If these are choked, the operational costs of sumps/tubewell will be a wasteful
expenditure.
5.10. Inspection Check List
Routine inspection by the sub-engineer should include collection and transmittal of
gauging station data, condition of the service road, sloughing of banks and silt
accumulation.
The sub-divisional officer should prepare inspection notes on the condition survey,
prior to annual or periodic maintenance including weed control, silt clearance, and
repair to structure. The executive engineer, on the basis of this report should inspect
and verify the extent of works involved in the maintenance before preparing final
estimates.
After Monsoon or any other major rainfall event, the following items need to be
specifically checked and recorded:
• the highest flood level marks at the structure site (this can also be checked
immediately after rainfall at road crossing structure sites),
• whether the main drain overflows in the outfall reaches or at any other
location,
412
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
• any breach in the banks by farmers (justifying the need for additional
drainage inlet),
• the ponded areas along the drain, particularly the depressions,
• the condition of drainage inlet, particularly the inlets with pipe diameter
smaller than 18 inches (46 cm) which can be choked with debris or brush
wood,
• rain cuts on the slopes and banks,
• any damage to structures, stone pitching in ghat sites/or drainage inlet
sites,
• any evidence of weeds and sediment cleared as a result of storm flow.
5.11. History of Drainage System
It is important to keep the original history of a drainage system updated. This can only
be done on the basis of a monitoring and evaluation data. The history should record
the following:
• remodeling of the system and the reasons for remodeling,
• notes on the design parameter and criteria used for the remodeling,
• drawings and plans of the revised section should be added as annexures,
• details of additional drainage inlets added in the system,
• any new sub drains added with design and details of new sub drain,
• remodeling or replacement of structure with detailed design,
• addition in the catchment area due to addition of a new sub drain,
• reduction in the catchment area (This happened with the construction of
Link Canals which are also serving as drainage channels and many
branch/sub drains are outfalling into them). The reduction in catchment
area reduces the design discharge of the existing main drains,
• notes on the blockages of flow as a result of construction of Motorways
and other highways projects,
• major changes in the catchment which have bearing on the runoff,
• data on the groundwater levels in the catchment area over the years,
• identification of areas which have not been provided with the drainage
relief and where new sub drains need to be provided,
• notes on any ON-Farm drains constructed by Agriculture Department and
their connection with the sub drains.
5.12. Performance Assessment of Surface Drainage Systems
The expenditure on O&M must be linked with its performance relating to the
achievement of the objective for which the system has been designed and
constructed. Performance indicators should be established to assess the
performance.
Performance Indicators for Surface Drainage
• flooding and ponding of agriculture land,
413
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
variables are well-established. The subsurface drainage manual covers only the
design and construction of horizontal subsurface pipe drainage which is conventionally
termed as “Tile-Drainage”. Tubewells in any case are covered under the chapter on
groundwater.
6.2. Subsurface Drainage Options
Groundwater can be controlled through: (a) deeper and extensive network of surface
drains, (b) tubewells i.e. vertical drainage (c) horizontal buried pipes (tile drainage), (d)
lining of irrigation conveyance channels including water courses and to some extent
by equitable distribution of irrigation supplies.
Open Surface Seepage Drains
Open-surface drains with field drains deep enough to intercept seepage flow can serve
the purpose. Following issues are involved in this option:
• land acquisition cost and the loss of agricultural benefits in perpetuity,
• severance of farm lands and restricted movement for farm operations,
• O&M issues; with choking of drains adversely affecting the efficiency of
drainage.
• surface drains are unsightly and involve environmental issues.
Tubewells
In fresh-water zones, tubewells are the best choice for groundwater drainage. The
benefit of drainage is a by-product of irrigation. In saline areas, the tubewell pumping
develops a cone of depression far below the desired water table level, as shown in
Fig. 27.
Water is pumped from deeper aquifer which is usually more saline than the upper
layer. The poor-quality effluent deteriorates the water quality in surface drains which
ultimately inflows into irrigation network. In a few cases, this effluent was disposed off
in evaporation ponds. The accumulated salts in the evaporation ponds became a
serious environmental hazard for the adjoining areas. Evaporation ponds are,
therefore, no more an option. The deep tubewells require larger drive units and high
energy costs during operation.
Alternatively, a large number of shallow tubewells could be installed in order to
maintain the desired groundwater level. This could involve huge initial costs.
Unless a National Outfall Drain is available for disposal of saline and toxic effluent to
sea, saline tubewells are not feasible. Lower riparians have serious reservations
against any proposal of an outfall drain as they presume that it would destroy their
lands when the drain overflows in the outfall reaches. LBOD (Left Bank Outfall Drain)
is cited as having damaged lands in Badin Distt. of Sindh.
Lining of Irrigation Channels
Lining of irrigation channels definitely helps the affected lands to the extent of the
seepage. It does not however provide relief for the drainable surplus resulting from
rainfall or from the flooding of depressions. Rainfall events and flooding are by far the
most significant factors causing rise of water table on a larger scale. Inequity in
irrigation supplies is also a factor in groundwater recharge and discharge. It needs to
be improved but would help groundwater control marginally unless water allowances
in different canals are rationalized. There is little possibility of that because of political
expediencies.
Horizontal, Subsurface Pipe Drains
The buried pipe system receives groundwater which is above the pipe level. The
pumps in the sump operate only based on the incoming flow. The pumping costs are,
therefore, considerably less. Water quality of the pumped water also relatively
improves with the passage of time, which can then be locally used. The system in
buried and no acquisition is involved. These advantages make the tile drainage system
a preferred choice and the only technically viable option. It is, however, expensive and
involves foreign equipment and expertise.
Irrigation, surface drainage and subsurface drainage are all interlinked and
complimentary. Even a well-designed and a well-constructed subsurface drainage
system does not perform effectively in the absence of a properly functional irrigation
and surface drainage network. Project planning and design, therefore, require holistic
approach.
6.3. Hydrological Cycle
The design of subsurface drainage system requires a good understanding of the
occurrence, nature and movement of water in the soil (Fig. 28), illustrates the main
components of hydrological cycle related to drainage.
416
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
applicability may be limited. The laboratory procedure itself has many limitations.
Laboratory tests of hydraulic conductivity are not reliable for drainage design. For
design, in situ measurement is common.
Augerhole method is most common for field measurement provided the water column
in the bore hole is at least 0.6 m. In dry conditions, the shallow well pump-in test
(inverted well test) is used. In case there is piezometric pressure, the piezometer
method is considered practical.
Augerhole Method
The augerhole method (also described as bailout method) is used both for
homogeneous and layered soils if the layers being measured are thicker than 10 time
the diameter of the auger hole. The augerhole test measures the average horizontal
hydraulic conductivity of the saturated soil profile (from the static water table to bottom
of the hole).
Initially an auger of small diameter 3 inches (7.6 cm) is used and the hole is later
widened by 4 inches (10 cm) dia auger. The procedure is necessitated to remove
scaling of the sides of the hole. With a scaled hole, the measured hydraulic
conductivity is less than actual. This usually is the case with finer soils.
The hole should be augered vertically and as straight as possible. If the water table is
shallow, 10 ft (3 m) depth of hole should suffice. The augering should continue to
ensure a minimum of 2 ft (0.6 m) of static water in the whole subject of course to the
limit of hand augering.
Because of unstable nature of sandy soils, a well casing procedure is used. In this
procedure, a casing is inserted in the hole and the water and sand are removed from
the bottom of the casing. As the sand is removed, the casing sinks deeper and deeper
till the bottom depth is reached. At this point, some sand usually remains inside the
casing and is measured prior to final baling for the test run. When the water table is
stabilized (usually after 10 to 15 minutes), the final bailing of sand is made before the
start of the test. The depth of hole is measured before and after the test. The test
computation is based on the average of two holes.
Equipment used for borehole method comprises:
• hand Auger 3 inches and 4 inches (7.6 cm and 10 cm) with extension
handles for various depths,
• recording rod/tape and float apparatus,
• perforated casing for the hole, the diameter of the casing should be the
same or slightly larger than dia of the hole (the perforated area of the
screen should be at least 10%),
• bailer,
• stop watch,
• tripod.
418
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
After the water has stabilized in the hole, the water is bailed out as quickly as possible
and all reading are completed before the water level rises to half its original height.
One or two passes of the bailer are usually sufficient. The stop watch is started at the
moment of withdrawing the first bailer and continued till the test is completed.
Measurement are continued until the recovery of water in the hole equals about 0.2 to
0.25 of the depth initially bailed out. Rise of water level in the hole is measured using
equal time intervals as the recording board and float rises in the hole. A detailed record
of rising water level is maintained over an appropriate time period. Standard
nomenclature used in augerhole method, shown in Fig. 29, is as follow:
Figure 29: Standard Nomenclature Used in Augerhole Method
Calculations:
The following equation is used to calculate the value of hydraulic conductivity “k” from
the data observed from the auger hole:
∆ℎ
K = C ∆𝑡
where
K = hydraulic conductivity, m/day
∆ℎ
= rate of rise of water table, cm/day
∆𝑡
C = factor (dimensionless) which depends upon the radius of hole, the depth
of water in the hole and the depth to an impermeable layer. It can be
determined from Table 9:
Table 9: Values of C for Use in the Augerhole Method
Example:
The recorded values of t and h may be plotted on a normal log paper, where they
should form a straight line. The value of “K” can be determined from the slope of line.
Piezometer Method
Augerhole method cannot be used if there is piezometeric pressure or where depths
exceed 3 m. For these situations, and for a layered soil, piezometeric method is used.
It is similar to augerhole method. A tube (ID=3-8cm) is installed inside the hole. A
cavity is formed below the tube as shown in Figure-32. It is simply an unlined part of
the hole. A series of tests can be carried out by deeping the holes and lowering the
tube to different levels.
422
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
Table 10: Shape Factor C/r for Use with the Piezometer Method
Density of Hydraulic Conductivity Tests
The number of required in-situ tests depends on the soil variability in the project area.
In alluvial soils, normally there are two distant layers: the upper layers are fine textured
with lower hydraulic conductivity while deeper layers are coarse textured with high
hydraulic conductivity. The density of investigations for the two layers is different.
For large project areas, which usually is the case in Pakistan, a grid is established on
topo sheets and the tests are performed on the nodal points – usually two at each site.
In Fourth Drainage Project, Faisalabad, a topo sheet represented an area measuring
9000 ft by 6000 ft (2743 m by 1828 m) containing 1240 acres. A grid of 2000 ft by 6000
ft (609 m by 1828 m) was established with 27 nodal points, each point representing
46 acres. For deeper high permeability layers, six deep holes representing 200 acres
were analyzed for soil texture classification.
In-situ field investigation is expensive and time consuming. After some investigations,
a correlation may be established between the soil classification and hydraulic
424
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
conductivity. For deeper layers, deep well pumping tests may be used. In Fourth
Drainage Project, the hydraulic conductivity of deeper layer was conservatively taken
as 50 ft /day (15 m /day) although the pump test values were higher.
There is also a relationship between the number of tests required with expected drain
spacing. For wider spacing the test density can be reduced. Similarly if the soils tend
to be homogenous, the density of hydraulic conductivity tests is less as compared with
the heterogeneous soils. In all cases, however, benefitting from the correlation
between soil texture/structure with the hydraulic conductivity is indispensable as this
reduces the number of tests.
Depth to Barrier
The information relating to depth to barrier is used for locating subsurface pipe drains,
estimating quantity of groundwater flow and calculating drain spacing. If there is no
barrier up to a depth of 76 m, it has little impact on the design of subsurface drainage
system.
A barrier is characterized by a relatively low hydraulic conductivity compared to
𝐷
overlying soil or high resistance for vertical flow. This hydraulic conductivity, C = 𝑘𝑣 ,
where D is thickness of the layer, and Kv is its vertical hydraulic conductivity.
A layer constitutes a real barrier if C=250 or more. If C is = 50 or less, it can be
assumed that there is no barrier. For C values between 50 and 250, the barrier
significantly affect subsurface drainage flow. USBR has defined a barrier zone as a
layer which has a hydraulic conductivity one-fifth or less of the weighted hydraulic
conductivity of the strata above it. This simplified approach is satisfactory.
Groundwater Quality
Before deciding whether an intervention is required for groundwater control, a full
understanding of the water quality of the groundwater should be available to the
planner. If the water quality is such that its use for irrigation purpose is not hazardous
for the crops normally grown in the area, then its groundwater development control
should be left to the farmers.
The Revised Action Plan for fighting waterlogging and salinity provides general
guidelines to determine suitability of water supply for irrigation. The criteria (Table 11)
must, however, be adjusted to specific conditions, including cropping pattern, water
management practice, availability of canal/tubewell water and existing drainage
facilities.
Table 11: Water Quality Criteria
EC RSC
Quality SAR
mmhos /cm mg/l
Usable Directly 01 – 1,500 0 - 10 0 – 2.5
Usable after mixing with canal water* 15,00 – 2,700 10 – 18 2.5 – 5.0
Hazardous > 2,700 > 18 > 5.0
(Source: Fourth Drainage Project, Faisalabad Region, Pakistan)
425
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
* Canal water delivered to agricultural lands is low in salt and alkali content with TDS
(Total Dissolved Salts) between 80 and 160 mg/liter and SAR of less than 5.0.
Different hazards related to water quality include:
Salinity hazard: Refers to the danger that the use of water for irrigation
(expressed as EC in will lead to osmotic problems in the soil/plants.
mmhos/s)
Sodicity hazard: The same with respect to sodic problem.
(expressed in term of
SAR)
Carbonate Problem: Appraised as residual sodium parameter (RSC)
Toxicity hazard: Refers to the danger with respect to toxic problem.
Toxicity is primarily appraised for chloride concentration
and boron concentration.
Water quality of drainage effluent affect the surface drain and eventually the water
quality of irrigation water. Project planning must take into consideration the safe
disposal of effluent.
Salt Balance and Leaching Requirements
For drainage design, the salt balance is considered as it relates to the leaching
requirement; the amount of water required to remove the salts out of the root zone. It
depends upon the electrical conductivity (EC) of irrigation water, EC of the deep
percolated drainage water and the sensitivity of individual crops grown in the project
area. The salt balance of soil profile can be upset, when the water table is at shallow
depth, water evaporates and the salts are left behind in the root zone. Eventually the
salt accumulation reaches a concentration level that is toxic to plant growth.
Soil salinity surveys identify and categorize the salt affected areas into saline, sodic
and saline sodic. Project planning include measures for reclamation of the affected
soils, including gypsum requirement for individual area depending upon the level of
sodicity.
The leaching requirement is the percentage of irrigation water (of known quality) that
must pass the root zone to maintain a favorable salt balance. Assuming the average
EC of irrigation water is 0.4 umhos and the maximum EC of saline water solvent
0.4
acceptable for most crops is 2, then the leaching requirement is 2.0 = 0.2 or 20%. In
the case of the Fourth Drainage Project, the leaching requirement was as 20%. The
leaching requirement defines the minimum parameter for design drainage rate (or
drainage coefficient).
Drainage Coefficient (Design Drainage Rate)
The drainage coefficient is used for calculating drain spacing and also for determining
the pipe size. The drainage coefficient is the excess flow to the groundwater that is
required to be removed. It comprises the following:
426
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
Aug 07 –
2.4 3 28 1.05 .0031 81
Sept 04
Sept 04 –
0.3 3 26 0.57 .0018 82
Sept 30
Sept 30 –
0.1 3 29 1.19 .0034 62
Oct 29
July 13 –
7.1 9 61 5.98 .0082 63
Sept 30
(Source: Fourth Drainage Project, Faisalabad Region, Pakistan)
The irrigation efficiency can range from 41% to 89% for the same area. If the irrigation
application during monsoon was reduced, the deep percolation and the drainage
coefficient would be reduced considerably.
The deep percolation from privately owned irrigation tubewells have to be considered
in addition to canal water supplies. However, in areas where there are private
tubewells, high water table conditions do not exist.
The design rate, Qs may be computed from the following equation.
Qs = Rf + Sc + Si – Dn
where
Qs is the excess water to be removed by field subsurface pipe drains
Rf = Recharge to groundwater, including rainfall and deep percolation from
fields due to irrigation.
Sc = seepage from canal network
Si = in seepage (groundwater flow into the area including artesian inflow)
Dn = natural drainage i.e. groundwater flow out of the area.
In-seepage, Si, and natural drainage, Dn are related to water table depth and
groundwater salinity. High salinity and a shallow water table more likely indicate in-
seepage (from adjoining areas) and little natural drainage. A deep water table and low
salinity indicate good natural drainage. Topography is also a factor. In depressions,
water table close to the surface increases evapotranspiration, causing movement of
groundwater towards the depression. If in-seepage is suspected, more quantitative
investigations are needed. If natural drainage or in-seepage is negligible (which
usually is the case), the range of drainage coefficients listed in Table 13 are used.
The combined effect of irrigation on deep percolation is shown in Fig. 33.
428
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
Y = H1 + H2 + H3
Pip e drain
H1 1
1 Gravel en velop e
head loss
1
3 K1
H3
BOUNDARY LAYER
H2
K2 = 50 FEET PER DAY
2 D
BARRIER
Drain spacing “L” can be computed from Donnan equation (with correction for
convergence):
𝐻
8𝐾2 𝐻2 ( 2 +𝐷 ′ )
2
L2 = 𝑄
L (m)
D(m)
5 7.5 10 15 20 25 30 35 40 45 50 75 80 85 90 100 150 200 250
0.50 0.45 0.50 0.50 0.50 0.50 0.50 0.50
0.75 0.60 0.65 0.70 0.70 0.75 0.75 0.75 0.75 0.75 0.75 0.75
1.00 0.65 0.75 0.80 0.85 0.90 0.90 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 1.00 1.00 1.00 1.00 1.00
1.25 0.70 0.80 0.90 1.00 1.05 1.10 1.10 1.15 1.15 1.15 1.15
1.50 0.90 0.95 1.10 1.20 1.25 1.30 1.30 1.35 1.35 1.35
1.75 1.00 1.20 1.30 1.40 1.45 1.50 1.50 1.55 1.55
2.00 1.10 1.30 1.40 1.50 1.55 1.60 1.65 1.70 1.70 1.80 1.80 1.80 1.85 1.85 1.90 1.90 1.95
2.25 1.15 1.35 1.50 1.70 1.70 1.75 1.80 1.85 1.85
DRAINAGE & SALINITY CONTROL
Table 15: Equivalent depth “d” for commonly used pipe drains
45.00 12.00 13.80
50.00 12.10 14.30
60.00 14.60
~ 0.70 0.95 1.15 1.55 1.90 2.25 2.60 2.90 3.25 3.55 3.90 5.40 5.75 6.00 6.25 6.80 9.55 12.20 14.70
433
434
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
If the drainage flow from above the drain base is insignificant as compared to the flow
from below the drainage base, then the following simplified version of Hooghoudt
Equation may be used:
8𝐾𝑑ℎ
L2 = 𝑞
Depth of Drains
Depth of pipe drains is to be determined taking into consideration topography, level of
the outlet, layering of the soils, and their respective hydraulic conductivities and the
capability of available machinery. The deeper drains mean wider drain spacing and
consequently an economical layout. If the H.C of the lower layers is higher (which is
usually the case in most of Indus Plains), installing deeper drains lets the drains be
placed farther apart. However, at deeper depths, the progress of installation is slow
and consequently the cost increases. The decision essentially is based on the cost
optimization studies. In large projects, it is advisable to place drains as deep as
435
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
possible and arrange the pipe-laying machines taking into consideration the depth and
size of the pipes. Deeper drains are also safe from clogging by roots of plants and
trees and also safe from rodent attack.
For lateral drain, the outlet is its junction with the collector pipe and for the collector
pipe the outlet is the surface drain or the sump. In case the collector drain discharges
into the sump, the collector pipe should be as deep as possible, subject to the capacity
of the trenching machine. If the labour costs are high as in the United States and
Europe, the rate of installation by the trencher might become the overriding
consideration. In Pakistan, the high material costs favour deeper drains.
Determination of Pipe Diameter
The objective of subsurface drainage is to remove excess groundwater so that water
table stays deep enough from the root zone. The pipe capacity has to be sufficient for
this purpose. If the lateral pipe line is long, its capacity increases due to incoming flow
along its length. If a pipe drain serves an area of say 200 acres, all of it is not irrigated
at one time. A reduction factor may be applied to account for this. On the other hand
if a drain is placed parallel to an irrigation channel, its capacity is increased to
accommodate seepage flow from the channel.
In practice, a pipe drain starts with the smallest pipe size 4 inches (100 mm), placed
at the shallowest required depth, (about 1.8 m for our conditions), and then
progressively increase the pipe diameter in steps at minimum slope (ranging between
0.001 to 0.005) till the pipe is running full or the maximum depth is reached. Pipe size
must have about 33% additional capacity to allow for partial siltation due to low flow.
The hydraulic design of pipe is based on the standard pipe flow formulas which relate
to discharge “Q” as a function of hydraulic gradient (i), the pipe diameter (d) and the
wall roughness. For corrugated pipes, the diameter can be determined from the
flowing equation for steady sate flow:
Q = 22 d2.67, i0.5
where:
Q = the discharge along the pipe, in m3/s
d = internal diameter of pipe, in m
i = the hydraulic gradient, m.m-1
However, if discharge increases along the length of the pipe (non-uniform flow) as is
the case of most field drains, the equation is modified as follows:
Q = 38 d2.67 i0.5
The inside diameter of pipe can be more conventionally determined from the
nomographs for corrugated pipes (Fig. 35) in mm or from nomograph (Fig. 36), in
inches
436
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
• land slope,
• the design pipe slope,
• the level in the disposal channel (in case the pipe drains directly flow into
surface drains.),
• capacity of the trenching machine,
• maximum depth at the outlet in the sump,
• physical constraint of infrastructure boundaries.
Figure 36: Flow in Drains of Various Diameter Based on Slope
SLOPE IN FEE PER FOOT
0.0002
0.0003
0.0004
0.0005
0.0006
0.0007
0.0008
0.0009
0.003
0.004
0.005
0.001
0.002
0.0001
0.01
N = 0.015
0.03
0.05 0.07 0.09
0.3
0.5 0.7 0.91
If the land slope is favourable, it is possible to have long pipe lines up to 3000 ft (0.9
km) or more. However in flat areas, the usual length of pipe drains ranges between
800 to 1500 ft (240 to 460 m). If the drains are placed against the slope, the drains
become deeper at a faster rate, and the length is much shorter. Maintenance of pipe
drainage also influences the pipe length to a certain extent as pressure jets of flushing
machines can handle pipes upto 1000 ft (300m). This limitation can, however, be
overcome by constructing manholes at suitable locations.
Pipe Layout
The layout of the subsurface pipe system is site specific. The primary consideration is
the location of the sump which is sited at the lowest spot within the area to be drained.
The sump should be close to an existing surface drain so that the length of carrier
drain is as short as possible. It should also be close to a metalled road for convenience
of operation and maintenance and inspection by senior staff.
The layout is then plotted on the reverse of the top sheet (which is on a tracing paper).
Various layout configurations are tried and adjusted for the average drain spacing.
General layout requirements are:
• avoid built up property,
• avoid tender lands,
• minimize interference with surface drains, irrigation channels and other
infrastructure, such as roads and railways,
• avoid large ponds (trenching will not be possible in such locations without
expensive dewatering).
Collector pipes generally follow the slope towards the sump. Lateral pipes are then
added to the collector. Manholes are established at all major junctions between the
collector and lateral. Additional manholes are placed no further apart than 3000 ft (0.9
km) on main collectors and 4000 ft (1.2 km) on lateral. The office design is then laid
out at site and changes are marked in consultation with the design team.
If high H.C layer is available at the minimum pipe depth of 6 ft (1.8 m), then a singular
pipe as collector without any need of lateral can directly be taken to the sump by
stepping up pipe sizes along its length.
Singular Layout System
In certain situations (like Mardan SCARP) deep open surface drains serve as
collectors. Here the lateral pipes directly discharge into the surface drains. This is
called a “Singular System”. Length of laterals as well as their depths are controlled by
the water level in the surface drain. The singular system has the advantage that the
outlet of the pipe can be conveniently inspected and evaluated from the out flow of
each lateral. The system as such is economical to install. However, it has the
disadvantage that pipes could get damaged during desilting of drains by excavators.
If land is flat, the lateral pipes can be aligned in a “grid pattern”. In the “herringbone
pattern” the collector pipes are aligned along the main slope while the lateral are
aligned across the slope but at a slight angle. If the drain is placed along the contours,
439
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
then the pipe slopes downwards to the collector but remains at a constant depth below
the surface. The depth uniformity is not, however, a major consideration in favour of
herringbone pattern. The choice of layout configuration is essentially dictated by the
site condition.
wet spots
NATURAL SYSTEM
co
in
lle
f ield d ra
ct
)
(L ateral
ro
HERRINGBONE SYSTEM
natural stream
Figure 38: Schematic Layouts of Singular and Composite Pipe Drain Systems
(Source: Land Drainage, BT Batsford Ltd. London)
440
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
completely removed during manufacturing. Tabs provide high entry resistance and
increased head loss at the entry.
thick synthetic materials, i.e., polypropylene mats or polystyrene granules are also
used. Organic materials have limited life while synethetic materials are reported to
have varying degree of success and are still being tested. Gravel envelope although
slightly more expensive due to transportation and handling costs, is suitable for most
soils and has been successfully tested in Pakistan. Design criteria for granular
envelope has been developed by the United States Bureau of Reclamation (1978) by
US Soil Conservation Services (1973) and by FAO (1975). All have important
restrictions on the quantity of fine material in the filter material.
The envelope should be well graded, free of vegetation matter, clays and other
deleterious substance which could in time change the hydraulic conductivity of the
envelope. For sieve analysis of the material 100% should pass the 1.5 inches (38
mm) clear square sieve opening and not more than 5 percent should pass the No.50
US standard sieve. An envelope material is considered well-graded when all particle
from the largest size to the smallest (within the specified range) are available.
Coefficient of uniformity and coefficient of curvature define whether a material is well
graded or not.
𝐷
Coefficient of Uniformity, Cu = D 60
10
(𝐷30 )2
Coefficient of Curvature, Cv = D
10 x D60
D10, D30 and D60 = diameter of particles in millimeters passing the 10, 30, 60 percent
points on the base material gradation curve. The Cu must be greater than 4 for gravel
and greater than 6 for sands and Cv must be between 1 and 3 for both gravel and
sands.
Gravel envelope has to be designed considering the texture of the base material. It is
not, however, advisable to change the gradation frequently unless there are distinct
classification of soils covering large areas.
Table 16 lists the gradation relationship between the base material and the gravel
material for most soils.
Table 16: Gradation Relationship Between Base Material
and diameters of graded envelope material
(diameter of particles in millimeters)
Base material, Lower limits, percent passing
60 percent
100 60 30 10 5 0
passing
0.02 – 0.05 9.52 2.0 0.81 0.33 0.3 0.074
0.05 – 0.10 9.52 3.0 1.07 0.38 0.3 0.074
0.10 – 0.25 9.52 4.0 1.30 0.40 0.3 0.074
0.25 – 1.00 9.52 5.0 1.45 0.42 0.3 0.074
(Source: Drainage Manual, US Deptt. of the Interior Bureau of Reclamation)
It is also specified that carbonate content of the envelope material should not exceed
5 percent and the material should have a minimum permeability of 50 ft /day (15
443
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
m/day). Table 17 shows the gradation used in the Fourth Drainage Project,
Faisalabad.
Table 17: Gravel Envelope Gradation
Percent by weight passing given
Screen size screen sizes
Minimum Maximum
1 to 1.5
inches (25 to 100 --
38 mm)
0.75 inches
75 100
(19 mm)
#4 20 60
#8 10 35
#30 0 15
#50 0 5
#200 0 3
(Source: Fourth Drainage Project, Faisalabad Region, Pakistan)
The crushed rock envelope even though meeting the gradation requirement was not
found suitable. This material was tested in the Fourth Drainage Project and did not
perform well in the field trial as sediments moved in the pipe. The hydraulic
conductivity of this material exceeds 8000 ft /day (2438 m /day). In contrast the
hydraulic conductivity of natural or river run gravel ranges between 400 to 700 ft /day
(120 to 210 m /day). If sink holes develop in the envelope with natural material, they
tend to heal themselves after a relatively short time after placement as against crush
material. While specifying gradation of the envelope materially, it must also be
mentioned that the material will be from natural sources only.
Sump Design
In flat areas, the surface drains are shallow and direct disposal into surface drains
benefit a small area along the drain. Pumping despite being costly is the best option
in relatively flat areas. Flow via collector buried pipes is collected in a sump from
where it is pumped to the surface drains, through a carrier open channel or buried
concrete pipe.
Location and Size
The sumps is sited close to the surface drain, power transmission line and road. The
site selection is done by comparing estimated costs.
The capacity of the sump is determined by the incoming flows. If an area that is
drained with the sump is 1000 acres (404 hectares) and the drainage rate is 0.008 ft 3
per square foot per day, the discharge coming into the sump will be:
1000 × 43560 × 0.008
= 4.03 cusecs
24 × 60 × 60
444
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
This inflow into the sump is through a number of collector drains carrying varying
discharges depending upon area served by each collector drain. The collector pipe
diameters range from 10, 12 and 15 inches (254, 304 and 380 mm) and they enter the
sump at different levels. The sump bottom is determined by the minimum volume of
water required for reasonable cycle time by pumps. A circular sump structure is
preferred for its strength against side pressure and for the method of construction if
well sinking method is used.
Even though the inflow into each sump is different, a standardized size is normally
specified. A sump of internal diameter of 10 ft (3 m) and depth of 7 ft (2 m). below the
invert of the lowest collector pipe, provides a reasonable volume of water for pumps
to operate with a reasonable cycle time. The cutoff level for pumping is 2 ft (0.6 m).
above the bottom slab so that the impellers of the pumps always remain submerged
and self-primed. The effective volume of water for pumping is a column of water 5 ft
(1.5 m) deep and 10 ft (3 m) in diameter.
Pump Design and Operation
Depending upon the number of collectors discharging into the sump, the incoming flow
could vary from 1.5 cusecs (0.04 m3/s) to 6.5 cusecs (0.18 m3/s). Because of flow
variation there could be one, two or three pumps each with a discharge of
approximately 2 cusecs (0.05 m3/s) or there could be three different types of pumps
of 2, 4, 6 cusecs (0.05 m3/s, 0.11 m3/s, 0.16 m3/s) each, so that only one pump is
installed in each sump matching the incoming flows. Having pumps of different
capacities would require much larger inventory of spare parts and a large number of
spare pumps and motors. To avoid this, a single pump is designed which can be
installed in combination of one, two or three to suit different discharges.
In the Fourth Drainage Project the initial plan was to install 1.5, 2 and 2.5 ft /s (0.45,
0.60 and 0.76 m/s) capacity so that pump combination could exactly match with the
incoming flows. Scarifying some efficiency of sump operation, a standardized sump
of 2.25 cusecs (0.06 m3/s) capacity was selected and installed in combinations of 2.25,
4.5 or 6.75 cusecs (0.06, 0.12 or 0.19 m3/s).
When the water rises above the level of the incoming pipe, a float activities one of the
pumps to start. The other pumps (in case there are more than one pump) start in
sequence with a time lag of 1 minute so as to avoid electrical surge on the electrical
system. As the water level in the sump drains to 2 ft (.6 m) above the sump flow,
another float switches off the pump. In the case of load shedding, the water level in
the sump keeps on rising till it reaches normal groundwater level in the area. This
situation does not arise if the load shedding is scheduled on hourly basis.
Power Requirement
The horsepower requirement for the pump can be worked out from the following
equation:
gpm x H x S.G
Bhp = 3960 x pump efficiency
445
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
where
Bhp = brake horsepower required at the pump
gpm = gallon per minute pumped
H = head (lift in ft)
S.G = specific gravity of fluid (in case of water = 1)
Brake horsepower calculated from this equation is used to compute requirement of the
electric horsepower of the Motor (HP).
Bhp
HP = Motor efficiency
Electrical demand in kilowatt is determined from the following equation:
Bhp x 0.746
kW = Motor efficiency
The pumps selected for Fourth Drainage Project are centrifugal pumps. The motor is
installed above the ground level in the sump and is connected to the pump via a shaft.
The pump remains submerged all the time and is thus self-primed.
The sump design includes a baffle wall (an inner ring) to eliminate turbulence and the
resulting air entrainment due to cascading flow from the pipe as the water level falls.
The entrained air reduces pump efficiency, causes additional vibration of the pump
system and increases wear and tear. The baffle wall directs the flow vertically
downwards from the annular space between the sump wall and the baffle wall, and
enables its entry to the sump from openings in the baffle wall near the bottom of the
sump. In addition to the bottom slots on the baffle wall, 5 inches (127 mm) diameter
holes are provided on the baffle wall slightly above each incoming collector to provided
convenient access for the nozzle of the drain clearing jet.
Normally in a multi pump installation, vortex or rotational flow occurs at the entry of the
impeller. This causes the water to enter the pump impeller at different angle than the
designed requirement resulting in undue loading on the impeller and bearings, excess
noise and vibration. To minimize the rotational flow around the pump, flow vanes are
attached to the impellers of the pump.
The sump design is shown in Fig. 41.
446
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
Manholes
Manholes are required to serve as:
• sediment trap,
• access point for the monitoring of discharge and sediments,
• access point for the clearing of drains with jetting machine.
Manholes are normally located at each junction point but not necessarily at all junction
points if these are too closely spaced (less than 700 ft (210 m)). These are installed at
major changes of alignment and also in between a single long line of drain if the length
exceed 3000 ft (910 m). They need not be installed at the start of the drain (the end
point). However these points should be identifiable with reference to any landmarks in
the vicinity. Manholes are also not required to be installed at the changes in the pipe
gradient. Manholes should be minimum 3 ft (0.9 m) internal diameter, extending 1 to
2 ft (0.3 to 0.6 m) above the ground surface and about 18 inches (0.45 m) below the
invert level of the pipes. Sediments trapped inside the manholes should be periodically
cleaned.
Figure 42: Design of a Typical Manhole
the depth increases, it requires huge draught force. Trenchless machines can also
simultaneously place the gravel envelope like the trenching machines.
However, due to its operational methodology, the soil around the pipe is compacted,
resulting in increased entry resistance. Although some machines have been designed
to lift and crack the soil around the pipe to reduce entry resistance, this cracking also
increases the possibility of piping. Other drawbacks are that the filter cannot be
inspected and due to its faster installation, the grade and alignment are more difficult
to control. The available information is not sufficient to make general recommendation
about its use.
Trenching Machines
Trenching machines have wide range of capacities. A combination of different sizes
of trenchers can be procured for various sizes of pipes and depth of drains. Even for
large machines, various sizes of pipe boxes can be arranged to make them more
versatile. The trenchers have laser receivers attached to the hydraulic system for
laying the pipe according to the designed grade. The continuous trencher can lay the
pipe in saturated and unstable soil. Besides the trenchers, other support equipment
including gravel trailers with tractors, front-end loaders, scrapers, backhoes and laser
equipment, are also required for pipe installation.
Construction Method
The installation of pipe drains starts from the sump and progresses upstream. The
collector pipes are the first to be installed. Immediately after the installation the
groundwater starts to flow into the sump and pumped out to the surface drains.
Lowering of water table with the installation of collector helps pipe laying in the rest of
the area by improving conditions for the movement of machinery. Lateral pipe drains
are then installed and connected with the collectors through a manhole. End of each
pipe is properly plugged and marked on ground. Where the pipe drains pass under the
open drains and water courses, unperforated pipe, slightly longer than the length of
the crossing, should be used to avoid entry of excess flow into the pipe drains.
Grade and Depth Control
The laser transmitter is installed along the side of the drain alignment. It is set to
transmit laser beam at a plane parallel to designed grade of the pipe. As a counter
check, the pipe box is also marked with a depth scale. The depth at which the trench
box should be at a particular distance can be manually checked by the inspector. The
operation should proceed smoothly with constant speed avoiding sudden changes in
the grade. The inspector must constantly move along the trencher and watch the
marks on the pipe box.
Gravel and Pipe Installation
Gravel is continuously placed through a conveyor belt of the gravel trailer that moves
alongside the trencher (Fig. 45 shows gravel trailer conveying gravel through a
conveyor belt). The gravel is placed on the bed before the pipe is laid and then it
covers the pipe all around to a minimum thickness of 4 inches (100 mm). For laying a
10 inches (250 mm) pipe, the width of the pipe box is 10+4+4 = 18 inches (250 + 100
+ 100 = 450 mm). This needs to be checked prior to the start of the operations. At
times, due to handling and transportation, the graded gravel gets segregated. Samples
from the hopper need to be checked to ensure that these meet the gradation
requirement. Gravel placement can be checked visually immediately after placement.
Figure 45: Gravel Trailer Conveying Gravel Through a Conveyor Belt
451
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
ft (300 mm) of fill should be carefully placed over the envelope before starting the
general backfilling operation. During backfilling, care should be taken that the drain is
not disturbed either vertically or horizontally.
Figure 47: Clearing of Silt with Float from Manhole
No more than 1000 ft (300 m) of trench should be open at any time. In unstable
conditions, this limit may be reduced to 25 ft (7 m) or less. Special compaction of the
backfill is not required except under structures. In these cases, the backfill needs to
be properly compacted to a depth of 3 ft (1 m) below the level of the structure. In case
the excavated material has dried, careful puddling can be allowed. The excess
excavated material should be mounded above the trench to prevent irrigation or rainfall
runoff entering the trench.
Monitoring and Evaluation
Immediate monitoring of the newly installed system is required to get the defects
rectified while the construction contractor is still at site. Water samples from the
manholes give a good idea of the sediment content in the water. After a couple of
days, it should be clear water. If not, there could be gaps in the placement of filter or
filter gradation during placement was not proper. The variation in the quantity of water
flowing from different drains with similar water table level, can indicate blockage.
Long-term monitoring during O and M has a different intent. The main objective of
subsurface drainage is to see that water table midway between two parallel drains,
should remain below 4 ft (1.2 m) except where there are intense rainfall events
exceeding the design frequency rainfall. If water table is not under control, then either
453
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
the design assumption was wrong or the system is not being operated adequately.
This monitoring data is very valuable feedback for future design of the projects.
7. OPERATION AND MAINTENANCE OF SUBSURFACE PIPE
DRAINAGE SYSTEM
7.1. Monitoring of Pipe Drains
A well-designed and well-constructed subsurface drainage system generally requires
little maintenance after the system has stabilized. However, newly installed system
requires strict monitoring and vigilance, starting immediately after installation and
extending over a couple of years. Performance of each drain can be checked at the
manhole by checking the quality and quantity of flow. Some fines do move into the
pipe after initial installation but water should be clear of silt after a couple of days. The
quantity of flow at the outlet in the manhole can be quickly assessed with respect to
the catchment of the drain and the depth of water table.
The flow can also be assessed by comparing the flows of the incoming pipes into the
manhole. In case of problem, the entire lengths of the pipes have to be inspected.
7.2. Inspection of Pipe Drains
In case of any problem observed in the manhole, the respective buried pipe alignment
should be thoroughly inspected to check the following:
• Sinkholes,
• wet spots,
• trees growing along the alignment,
• sugarcane planted over the alignment,
• vandalization of manholes.
Sinkholes are indication of fines/ or soil entering into the pipe either through pulled
joint broken pipe or from the gap in the placement of filter. Sink holes usually develop
after initial installation. Wet spots indicate partially or completely blocked drain due to
collapsed pipe or due to accumulation of sediments. Clogging of pipe by tree roots
and iron ochre, also results in wet spots.
7.3. Repair and Clearing of Pipe Drains
If the sinkholes are not massive, these should be filled and re-inspected to check if the
problem persists. In case it does, the spot should be excavated and the pulled joint
replaced by a coupler or with a piece of same pipe size replacing the damaged part
and connected to the two ends. The gravel envelope is replaced with fresh envelope
material. This operation is usually possible after the water table has dropped below
the pipe bed. Alternatively localized dewatering is required to replace the pipe.
Pipe Clearing
The partial blockage can be removed by pulling plugs of floats of different diameters,
but smaller than the pipe dia. Initially a relatively smaller dia plug is passed and pulled
454
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
up and down through strings on both sides to dislodge the accumulated sediments.
The same process can be repeated with larger plugs to completely clear the drains.
Clearing by Jetting Nozzle
Self-propelling jetting nozzles under varying pressures and lengths may be used to
flush silt and remove the blockage. Water pressure should be gradually increased.
High pressure can disturb the gravel envelop and even the surrounding soil causing
further movement of soil in the pipe. Jetting is normally started from the downstream
end but can be done from both upstream and downstream due to length limitation of
the jetting pipe. The effective reach of the flushing machine ranges
between 250 to 300 m.
Apart from clearing the troubled spots, the drain should be regularly cleared with a
flushing machine at interval of one to two years after installation and 5 to 10 years
after the system has stabilized.
7.4. Root Management and Clearance
The best management practice is to disallow tree plantation along the alignment.
Trees in farms sometime grow randomly. These and other aquatic shrubs should be
destroyed by spraying with appropriate chemicals after the crops have been
harvested. If for certain reasons this cannot be done and the roots are penetrating into
the pipes through perforations, the young roots can be removed with regular pipe
clearing operation using medium pressure jetting.
For mature roots which have formed into bundles, copper sulphate injected into the
drain system usually kill the roots. These can then be removed by jetting. Chemical
treatment with copper sulphate is required to be repeated annually, if trees are growing
all over or near the drains.
7.5. Clearing of Manholes
Manholes should be inspected periodically. If sediments have deposited in the bed,
these should be regularly cleared. The accumulation of sediments can be checked by
taking soundings. Manholes should be inspected each week after initial installation. If
neglected, the accumulated sediments in the manholes can plug the downstream pipe.
Manholes should also be cleared after each drain clearing operation. Manholes are
also a trouble spot if the top cover is not properly secure. They can be vandalized by
farmer who have been found dumping unwanted waste material into the manholes.
For those systems which have been well constructed and there is no evidence of
sinkholes or blockage, it might be worthwhile to bury the manholes.
7.6. Chemical Clogging (Iron Ochre, Gypsum)
In soils holding iron sulphide (Fe S2), water soluble ferrous sulphate (Fe S4) may form
after the soils are drained and oxidized. At low pH, the ferrous sulphate may enter the
drains, where it may oxidize to more soluble ferric hydroxide Fe (OH)3 which is
deposited in and around the pipe. With aging and drying, the ferric hydroxide
455
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
eventually turns into ferric oxide deposits which clog the pipe perforations and, in
extreme conditions, may totally clog the envelop and the pipe. The problem usually
appears some two to three years after the pipe installation, subsequently falling off
and eventually ceases to be a problem.
7.7. Outlet Condition
In a singular system, the pipes directly outlet into surface drains and each pipe may
be inspected at these locations. During high floods, there is a possibility of back flow
into the subsurface drains pipes. If feasible, flap values should be installed at the
outlets to stop backflow. Singular outflowing drains are also access point for the
rodents, which cut holes into the PVC pipes. If suspected, rodent screens should be
installed at the outlets.
7.8. Sump Operation
Pumps in the sump operate automatically and should take care of the incoming flow.
Although no operators are required, yet the sumps should be regularly inspected to
check and note the operation of electrical/mechanical system. Sound and vibration
indicate of problems with the bearings on the shaft which need to be timely replaced
before other components of the pumping system are damaged.
Control panels should also be inspected particularly the protective relays that protect
against low and high voltage. Vandalism of the transformers is a serious problem, as
is the stealing of conductors. This unfortunately is a problem, specific to Pakistani
conditions. When this happens, the drainage gets suspended for sometimes unless
there are spare transformers.
7.9. Performance Assessment of Subsurface Drainage System
The primary objective of sub-surface drainage is to keep the groundwater below the
root zone of the crops and to reduce soil salinity. It is, therefore, essential to know
whether or not this objective is being achieved. Following indicators and benchmarks
may be specified:
• average seasonal water table depth does not rise about 4 ft (1.2 m) for
more than two days after the design rainfall event,
• water table fluctuation over time,
• occurrence of perched water table,
• soil salinity in the root zone during critical growing stages of the crops.
• overall salt balance in the project area,
• effluent quality,
• overall and seasonal cropping intensities.
These indicators establish the state of performance of subsurface drainage system
and may be applied to determine the cause of underperformance. At the operational
level, following maintenance indicators can be useful to know the standard of
maintenance:
• water level in the manholes,
456
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
The salinity level in soil varies in time and in vertical and horizontal directions. This
variation is due to highly dynamic nature of soil water regime. The upward movement
(due to capillary action) and downward movement (irrigation and rainfall) frequently
changes the vertical distribution of salts. Changes in salt distributions are more
pronounced at shallow depths. At greater depths, the salt content remains more or
less constant due to slight changes in the soil moisture conditions.
Horizontal distribution of salts is influenced by the field levels, the crop, the irrigation
application and the soil texture. In fields, this variation of salt distribution shows up as
patchy growth of crop. In case of furrow irrigated fields, the salt concentration on top
of the ridges will be much higher as compared with the valleys. At regional level the
topography, cropping pattern irrigation water allowance in a canal command will affect
the spatial salt distribution.
8.3. Salinity Effects
The salinity problems can be diagnosed and assessed by relating these to the
following aspects of soil salinity:
Osmatic Problems
High total salt concentration of the soil solution raises the osmotic pressures that can
be exerted by soil solution. This makes it more difficult for the plant roots to withdraw
water from the soil.
Salt concentrations are normally expressed in mg/liter. Indirectly, soil concentrations
are commonly expressed as electrical conductivity value (EC-value) of the soil
solution. The osmotic forces increase linearly with the soil concentration. A linear
relationship between the osmotic forces and EC value was developed by US
Department of Agriculture (Fig. 48).
affects the hydraulic conductivity. Even an impervious layer can be formed due to
downward movement of clay particles.
For successful farming, the salt must be changed chemically be replacing excessive
sodium with calcium. The replaced sodium has to be removed through the subsurface
drainage system. The dispersion problem generally increases with ESP
(Exchangeable Sodium Percentage) value. In general problems are not experienced
in soil with ESP value <15%.
Determination of SAR (Sodium Adsorption Ratio) and ESP (Exchangeable
Sodium Percentage)
Soils have the capacity to adsorb cations (ads). This capacity is possessed by the
negatively charged surfaces of the soil colloids which attract cations from the soil
solution. The cation exchange is a complicated process. Following equilibrium
relationships have been developed for salty soil.
CEC (cation exchange capacity) = Ca + Mg++ads + Na+ads
𝑁𝑎+ 𝑎𝑑𝑠
ESP (exchange sodium percentage) = 𝑥 100%
𝐶𝐸𝐶
𝑁𝑎+ 𝑠𝑜𝑙 +
SAR (sodium adsorption ration) = + +
√(𝐶𝑎+𝑀𝑔 )𝑠𝑜𝑙
2
100 (0.015 𝑆𝐴𝑅)
ESP = 1+0.015 𝑆𝐴𝑅
expensive. In practice the system is designed for the normal leaching needs. Crops
with large amount of foliage also tend to remove salts. Leaching requirement is also
related to the salt tolerance limit of the crop. Formally stated, leaching requirement is
inversely proportional to the salt tolerance of the crop.
𝐸𝐶 𝑖𝑤
LR = 𝐸𝐶 𝑑𝑤
Where
EC iw is of irrigated water and EC dw is the maximum permissible salinity of
drainage water or soil water.
8.6. Determination of Leaching Requirement (LR)
The leaching requirement may be defined as the percentage of irrigation water that
must pass through the root zone to maintain the desired salt balance. Many factors
affect its requirement. Some of the assumptions made in the determination are not
always strictly valid. For example, the salt tolerance of different crops widely vary.
Similarly, if appreciable amounts of carbonate and sulphate salts precipitate in the soil,
less leaching will be required. Other factors that affect the leaching requirement
include the frequency of irrigation, irrigation efficiency, the aerial uniformity of irrigation
application, the losses from irrigation conveyances system and the soil stratification.
Because of these variables, there is little justification to do overly precise estimation
of LR values. For planning purpose the leaching requirement may be estimated from
the following equation:
𝐸𝐶 𝑖𝑤
LR = 𝐸𝐶 𝑑𝑤 𝑥 100
Where
LR = is leaching requirement in percentage
EC iw = electrical conductivity of irrigation water in mmhos per centimeter
EC dw = electrical conductivity of drainage water in mmhos per centimeter
The value of EC dw is based on the least salt tolerance crop
Illustration for rice – wheat cropping pattern.
Assuming we allow 10% reduction in crop yield.
EC for wheat = 10 (taken from figure 50)
EC for paddy rice = 6 (taken from figure 50)
Rice in this case is less salt tolerant crop. Therefore, the EC of the saturated extract
should not exceed 6 mmhos /centimeter.
Assuming that groundwater of 1200 ppm is used for irrigation. The EC value of this
water can be reasonably assessed by dividing the ppm value by 640.
There
1200
EC iw = 640
1200/640
LR = 𝑥 100 = 31%
6
463
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
In case, both groundwater and canal supplies are used for irrigation, an average
electrical conductivity value can be used applying weightage for the proportion for
each source of irrigation.
Determination of Infiltration Rate
Apart from the determination of leaching requirement (LR), it is also required to
estimate the minimum infiltration rate (INF) to achieve proper leaching.
Total infiltration is the sum of the Total Readily Available Moisture (TRAM) and the
deep percolation (DP).
INF = TRAM + DP
The DP is product of LR and INF
Therefore
INF = TRAM + LR x INF
𝑇𝑅𝐴𝑀
INF = 𝐼−𝐿𝑅 (𝐿𝑅 𝑒𝑥𝑝𝑟𝑒𝑠𝑒𝑑 𝑎𝑠 𝑎 𝑑𝑒𝑐𝑖𝑚𝑎𝑙 𝑓𝑟𝑎𝑐𝑡𝑖𝑜𝑛)
From the previous example, in case of paddy crop, the TRAM can be 3 to 4
inches (75 to 100 mm) depending upon the puddling practices. Taking an
average value of TRAM as 85 mm,
85
INF = 1−0.31 = 123 𝑚𝑚 (4.86 𝑖𝑛𝑐ℎ𝑒𝑠)
Deep percolation for salt balance,
DP = INF – TRAM
= 123 – 85 = 38 mm = 1.5 inches
Therefore, 1.5 inches (38mm) water must percolate below root zone as drainable
surplus for maintaining salt balance.
Salt Balance
Salt balance may be considered at farm, project or regional level. On the whole, in
Punjab, the salt balance is in the negative. Following the “project approach” salts were
evacuated from different projects and transported to the downstream regions via
surface drains, rivers, headworks, irrigation system and back to farms. Regional
balance is rather difficult to achieve in the absence of a Trans Basic Drain which is no
more feasible for various reasons. The local management of salt has to be the target
of drainage engineers.
The salt balance in the root zone is more seriously affected when a shallow water table
exists. Therefore keeping the water table below the capillary fringe should be, by far
the most important consideration for salt balance. Effective drainage both surface and
subsurface is a perquisite for the salt balance.
The other important factor that helps in controlling salinity and maintaining salt
balance, is ensuring a net downward flux – for example through drip irrigation or
ponding water as in the case of paddy.
Salt balance is essentially a relationship of salt input to salt output for the area. If the
mass of the salt input exceeds the mass of salt output the salt balance is regarded as
464
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
adverse. The basic design approach for salt balance is to provide for removal of salt
from the root zone that is added by irrigation water.
Operationally, a salt balance evaluation involves measuring the amount and
composition of irrigation water directed into the project and the amount, composition
of drainage discharge from the project. Such measurements should continue to be
made even after the project completion with a view to taking corrective steps and for
feedback for future planning.
While the salt balance concept can provide valuable information, its general
applicability is limited. The limitations include the following:
• Limited availability of adequate data,
• It indicates the total net salt balance in a project with regard to internal
distribution, absolute salinity levels or salt constituents. A satisfactory
project salt balance on an average basis does not guarantee a favourable
salt balance for any one given tract of land. Individual farmers may suffer
yield depression due to local salt accumulation,
• A positive salt balance value, supposedly an indication of satisfactory
conditions, can result from addition to salt load in the drainage water from
that stored in groundwater,
• While the overall salt balance may be satisfactory, sodium and chloride
concentrations in the soil water may be increasing relative to calcium,
magnesium, bicarbonate and sulphate. Specific toxicities will cause different
effects.
The salt balance cannot therefore be taken as a meaningful criterion for designing
drainage facilities for large project.
8.7. Reclamation of Salty Soils
Reclamation of Saline Soil
Saline soils can be reclaimed with relative ease by leaching. The quantity of water
needed to reclaim saline soil is different from what is required for maintaining salt
balance. That is the reason reclamation chutes are required to be sanctioned in highly
saline soils to achieve initial leaching: (usually 30 cm of good quality water for each
30 cm depth of soil will provide enough ponded leaching).
Depending upon the depth of water table, soil texture and drainage facilities,
reclamation supplies for one season will reduce salinity by 70 to 80%. In case of
subsurface drainage system, the leaching of salts is more effective and fast in the
vicinity of subsurface of pipes than midway between the pipes. The depth of
subsurface pipe drain also govern to what depth the soil profile will be leached.
Reclamation of Sodic Soil
Sodic soils (sodium affected soils) are more difficult to reclaim than saline soil because
they require replacing sodium with calcium. The calcium needed for replacing
exchangeable sodium is supplied by adding a chemical amendment.
465
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
Gypsum is the most commonly used amendment for reclamation. High quality gypsum
is readily available in Punjab at low cost.
The rate of reaction of gypsum in replacing sodium is affected by its solubility in water
and the permeability of sodic soils.
Approximately 1 meter of irrigation water is sufficient to dissolve 7.34 metric tons /ha
of gypsum having a fineness such that 85% will pass a 100 mesh sieve. On this basis,
it will require 12.5 metric tons of gypsum /ha-m of soil to replace 1 mg/100g
exchangeable sodium.
Initially the soil permeability is too low to allow reclamation to be achieved in a single
leaching. Normally 4.5 metric tons of gypsum is applied as first application with about
1.5m depth of water for leaching. Subsequently repeated yearly applications are made
for a period of 4 to 5 years with normal irrigation to reclaim the complete soil profile.
Reclamation of poorly permeable soil is more difficult to achieve. In such cases, crop
rotation including shallow rooted crops like vegetables rotated with rice can help.
The drainage system should have sufficient capacity to take care of the leachant and
to keep the water table below the capillary fringe.
466
MANUAL OF IRRIGATION PRACTICE
DRAINAGE & SALINITY CONTROL
References:
1. American Society of Agronomy, publication No17, 1974: Drainage for Agriculture
3. FAO Irrigation and Drainage Paper 38, 1979: Drainage Design Factors, Paper 38
6. Smedema, Lambert K and Rycraft, David W, 1983: Land Drainage, Planning and
Design of Agricultural Drainage System
8. Water and Power Development Authority (WAPDA), 2005: Drainage Master Plan
of Pakistan
9. Water & Power Development Authority, NESPAK and Euroconsult: Design of Pipe
Drainage Systems
10. World Bank November 178, 1992: Developing and Improving Irrigation and
Drainage System, Technical Paper
i
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
List of Tables
TABLE 1: DATA OF PUNJAB BARRAGES GATES ........................................................................................ 468
TABLE 2: GENERAL CHECK .................................................................................................................... 505
TABLE 3: JOB CORRECTION FACTORS .................................................................................................... 515
TABLE 4: LOAD FACTORS FOR DIFFERENT APPLICATIONS OF WORK .......................................................... 518
TABLE 5: HOURLY FUEL CONSUMPTION FOR CATERPILLAR EXCAVATORS M315D ...................................... 519
TABLE 6: APPROXIMATE TIRE LIFE IN HOURS ........................................................................................... 521
TABLE 7: OPTIMUM DEPTH OF CUT & IDEAL PRODUCTION OF SHORT BOOM DRAGLINES ........................... 522
TABLE 8: EFFECT OF DEPTH OF CUT & ANGLE OF SWING ON THE PRODUCTIVITY OF DRAGLINES............... 523
List of Figures
FIGURE 1: J TYPE AND ANGLE SHAPED RUBBER SEALS ........................................................................... 473
FIGURE 2: STEM DEFLECTION AT PROPER INSTALLATION OF J SEAL .......................................................... 473
FIGURE 3: LAY OF WIRE ROPES – FROM LEFT TO RIGHT: (A) RIGHT-REGULAR LAY; ..................................... 474
FIGURE 4: EFFICIENCY OF FITTINGS ........................................................................................................ 474
FIGURE 5: USE OF CLIPS ........................................................................................................................ 475
FIGURE 6: SCADA SYSTEM ARCHITECTURE FOR JINNAH BARRAGE ......................................................... 496
FIGURE 7: CENTRIFUGAL PUMP PRINCIPLE OF OPERATION ....................................................................... 543
FIGURE 8: HORIZONTAL CENTRIFUGAL PUMP .......................................................................................... 544
FIGURE 9: TYPICAL PUMP PERFORMANCE CURVE .................................................................................... 546
FIGURE 10: A VIEW OF DEEP W ELL TURBINE PUMP ................................................................................. 551
FIGURE 11: VERTICAL TUBULAR CASING PUMP ....................................................................................... 554
FIGURE 12: HORIZONTAL SPLIT CASING PUMP ........................................................................................ 554
467
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
and fixed path, the frictional resistance during movement of gate is low requiring fewer
loads for the hoist. Fixed wheel gates are therefore the appropriate choice for the
larger gates. Other important characteristics of these gates are as under:
• Seals are provided at sides and at sill to avoid leakages.
• The gate height is kept 1 – 1.5 ft more than pond level to prevent discharge
of splash over the gate due to waves created by wind in the pond/ reservoir.
• Gate guides are extended above the operating deck in order to allow the
gate to be lifted above the pond/reservoir maximum level.
• A service bridge is installed at the top of the guides for housing the hoist
system.
• For high depth of water (at barrage ponds), gates installed at canal head
regulators are split into two gates one above the other. In this way the dead
load for movement of gate and consequently the required forces to move
the gate are divided into two parts and both gates are lifted separately with
less effort.
1.2.4. Radial Gates/Segment Gate:
In the simplest form it consists of a curved skin plate formed to a cylinder segment,
supported by radial compressed arms which transfer the hydraulic forces to fixed
bearings. The radial gate rotates about a horizontal axis, which passes through the
bearing centre and usually coincides with the centre of the skin plate curvature radius.
By this arrangement, the resultant thrust from the water pressure passes through the
point of rotation and has no tendency to open the gate. In some cases, the centre of
curvature of the skin plate is located above the bearing axis so as to provide a lifting
moment, which helps the winch in the opening of the gate. The curved surface, long
radial arms and trunnion bearings allow the gate to close with less effort than a flat
gate. Radial type gates become a viable option when the heads are comparatively
much higher. In Punjab Irrigation Department, Radial Gates are fitted at Marala,
Rasool and Qadirabad barrages and the newly constructed New Khanki Barrage.
1.2.5. Flap Gate or Walton Gate:
This type of gate consists of a straight or curved retaining surface, pivoted on a fixed
axis at the sill. The bearings are rigidly anchored to the sill and spaced from 2.5 m to
4 m. In its fully raised position, the flap gate makes an angle from 60 to 70 degrees
with the horizontal. In the fully lowered position, the skin plate forms a continuous
surface with the weir bottom, presenting no obstacle to the water flow. These gates
were fitted at the canal head regulators of Suleimanki Barrage and have now been
replaced (in 2016) with Fixed Wheel Gates during rehabilitation of Suleimanki Barrage.
1.2.6. Stop Logs:
Stop logs are primarily used for maintenance and repair of main equipment or gates
by placing them on upstream of the gates/equipment to be repaired. The construction
of stop logs is similar to that of the slide gate. Depending on the height to be sealed,
the stoplog may comprise of more than one element called stoplog panels. Stoplog
471
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
panels are placed and removed by means of cranes, travelling hoists or gantry cranes,
with the help of lifting beams. Stop logs are provided with seals on their sides, sill and
between the panels.
In case a gate of barrage or tunnel gate of a reservoir is damaged or stuck due to
some defect, then the stoplog gate can be lowered up stream of this gate to isolate it
and the defective gate can be repaired. In Punjab Irrigation Department there is no
such provision for using stoplog gates at any barrage except New Khanki Barrage
under construction.
1.3. Hoists and their Types:
The hoisting arrangement is the part of the gate system that provides the necessary
movement to the gate, and the operating platform provides access to the operating
mechanism of the hoist. Hoists can be broadly be divided into four types namely,
1. Screw hoists
2. Rope drum hoists
3. Hydraulic pressure hoists
4. Movable hoists
1.3.1. Screw Hoists:
The hand operated screw lift has its use confined to small slide or fixed wheel gates
subjected to low head, and usually comprises a vertical threaded stem connected to
the gate leaf and prevented from rotating, a stem lift nut and a mechanism that permits
nut rotation in the desired direction. The nut is operated directly by a hand wheel or
indirectly by means of a worm gear system. The nut has also a strut function and is
usually supported on roller bearings. In general nuts are made of aluminum bronze
which presents good mechanical strength and a low friction coefficient. This
mechanism is normally installed within a frame and mounted on a cast iron pedestal
screwed to the operating deck.
1.3.2. Rope Drum Hoists:
Rope drum hoists are suitable for gates that would close under their own weight with
sufficient force to effectively press the bottom seal to prevent leakage. Their use is
very common in barrage gates in which the friction forces to be overcome are always
less than the gate weight.
On each side of the gate a drum with helical grooves (where the steel wire rope
connected to the gate leaf is wound) is installed and operated by gear box/speed
reducer and/or electric motor/manually operated handle. The number of grooves on
drum should be such that it can accommodate wire rope for total lifting of gate in a
single layer plus two holding turns. In addition, with the gate closed, two turns of the
wire rope should remain coiled on the drum. Drum grooves are machined with radius
equal to 0.53 times the wire diameter. As a thumb rule, a diameter not less than 25
times the wire diameter is adopted for drums and pulleys.
472
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
more flexible. The strands are wrapped in spirals about a central element, usually fiber
or steel wire. Fiber core gives greater flexibility to the cable; steel core have high
resistance to permanent deformation and increases the tensile strength. Wire ropes
are classified either Regular lay or Lang lay, as illustrated in Figure below. In regular
lay, the wires in the strand are laid in the opposite direction to the lay of the strands in
the rope. In Lang lay, the wires and strands are laid in the same direction.
Figure 3: Lay of wire ropes – from left to right: (a) right-regular lay;
(b) left-regular lay; (c) right Langlay; (d) left Lang lay.
Lang lay ropes have greater flexibility than regular lay ropes and are more resistant to
abrasion. Regular lay rope has fewer tendencies to spin. Lang lay ropes with fiber core
should not be used as they present little stability and low resistance to permanent
deformation. The German DIN 19705 standard recommends the use of regular lay,
heavily galvanized cables with a steel core covered with artificial fibers.
The rope ends are fastened by means of loops with clips or cast in sockets. The
strength of a clip fastening is usually 80 per cent of the strength of the rope. When
properly prepared, the strength of a socket fastening is approximately equal to that of
the rope itself. Figure below shows the correct application of clip fastening.
d. Seal bolts
d. AISI 304, ASTM A-193-B6 or
Brass
477
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
in respect of joints between roller cages and gates, Guide rollers and gates, shaftlocks,
etc. The splice joints of bridge girders and joints between main and cross members,
foundation bolts and base plates of hoist bridges, gear box to frames, Plummer boxes
holding down bolts to frame, Gear shaft keys, flexible or rigid coupling bolts of shafts
are some critical areas.
v. Oversize/Additional holes/undersize bolts:
During maintenance if oversize holes or undersize fasteners are provided or holes
made unplugged after completions of process, water/moisture or trash enters in the
gaps and damage the joints and structural members.
vi. Drain holes:
Accumulated water on girders, joints etc, due to non-provision of adequate number
and size of drain holes or jammed holes due to trash intrusion, particularly on the
horizontal girders or at the joint areas between trunnion and radial arms and radial
arms to horizontal girders and also between the cross ribs on the web of horizontal
girders is an item of concern It results in corrosion and loss of load bearing capacity
.In certain gates where large quantity of water is accumulated on the horizontal girders,
due to leakages or overflow and if cannot be drained off through holes, the self-weight
of gate increases and overload the hoist capacity which may lead to failure of gate.
vii. Short projection of bolts:
While providing threaded bolts at various load bearing or load transmission joints, if
the projection is insufficient, the main or locknuts cannot be properly fastened to the
required depths. This will reduce bearing strength and weaken the joint which may
ultimately result in joint failure.
viii. Welds:
All weld joints made shall be checked for cracks, rusting and aging factors and
maintained. The strength of a welded joint gets affected due to many factors. Weld
defects, cracks, residual stresses, metallurgical transformations, stress concentration
due to abrupt change in weld geometry are the critical factors which lead to weld
failure.
ix. Rollers and lubrication:
Effective function of all the rollers should be ensured by proper lubrication and
checking the condition of bearings and other components. The rolling action could be
simply checked by rotating with one or two hands when the gate is above waters or
when there is no water thrust. If they are not freely moving, immediate action is
required to repair or replace the damaged components. It may be noted that the
rollers if jammed, offer sliding friction in gate operation which is 10-15 times higher
than the rolling friction.
479
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
tensions released totally. The gear system even after release of load may be locked,
as sometimes the self weight of ropes and attachments may allow down ward rotation
of drum gear unit.
xv. Meshing of Gears:
Check for the full face width contact of teeth of gears and pinions and their uniform
meshing. The meshing of teeth forits full contact could easily be checked by observing
area of wear. The clearances between the meshing teeth should be within specified
limits. Necessary adjustments should be made only on release offload and locking the
gear and pinion. The broken teeth, if any, have to be rectified by adopting proper
methods in shop. If the damages are beyond economical repairs, replace the gears.
xvi. Bearings:
Check for the function of antifriction bearings and rectify/replace, if not working
properly. In case of excess gap between bush and shaft or oval shape of bush
diameter or damaged pin, the reasons should be probed and immediate action is
required to rectify the deficiency. This phenomenon is complex if the wearing trunnion
bush or pin is not uniform and necessary rectification/replacement should be taken up
under expert guidance. For all types of anti-friction bearings, effective supply of
lubricant should be ensured.
xvii. Hose Couplings:
In hydraulic control hoist systems only use standard hoses and couplings. Mixing and
matching couplings from one manufacturer with hoses from another manufacturer can
lead to premature or catastrophic assembly failure. That’s because hoses, couplings,
assembly equipment and crimping tolerances vary from one manufacturer to another,
and they’re not interchangeable.
Drive Unit components: The following important checks should be made
xviii. Electro-magnetic/Thruster brake:
Check for, clearance between brake shoe and drum, wear of brake shoes and function
of solenoid/magnetic coil. Ensure that the Brake drum and liners are free from grease
/ oil. Check the solenoid/magnetic coil for its rating.
xix. Worm Reducer:
Check for oil level and smooth operation, examine the oil in the sump for any metal
particles, which establishes that there is wear of teeth of worm wheel and remedial
action taken immediately.
Check function of safety switch and ensure the cranking handles are removed, before
operating the gate on power.
Ensure condition of chain links and its meshing with sprockets provided for manual
operation.
481
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
3. In case of jammed rollers, roller train should be dismantled, all the rollers,
their pins and bushes should be examined carefully and be replaced
immediately.
4. Thickness of roller train/side plates should be checked each year and if
found less than permissible limits should be replaced.
5. It is strongly recommended to replace the whole roller trains after continuous
use of maximum 20 years.
6. Roller trains should be repaired in each closure, under the direct supervision
of XEN incharge.
xxv. Seals:
Seals of the gate should be checked for wear and tear as well as deterioration. These
should be adjusted/replaced, as necessary. Few sets of spare seals should be kept in
stock and stored for emergency in such a way that these seals do not get damaged
during storage with the passage of time.
1.8.2. Maintenance of Wire Ropes:
The life of a steel wire rope is solely dependent on its construction, grade, the
surroundings in which it is being used and the manner of application, along with
maintenance procedure being adopted. It is possible by means of periodical inspection
to increase ‘the effective life span’ of a steel wire rope. The wire ropes should be
inspected at regular intervals which should include not only visual examination but
also non-destructive examinations like electromagnetic testing. Close examination will
not only indicate when it is time to put on a new rope but it will also reveal many other
things about the way the rope does its work and whether it is suited to the job. For
instance, wires breaking without showing wear indicate excessive bending, that is,
sheave and drums are too small or rope construction is too coarse. Whenever rope is
cut for recapping, the cut off portion of the rope should be specially examined.
1.8.2.1. Rope failures:
The diameter of wire rope reduces as it degrades due to continuous use. It may be
due to abrasion, corrosion, inner wire breakage, stretch etc. Before installation the
diameter of new wire rope should be measured and recorded for reference. During
installation there is some stretch in wire which reduces the diameter but this decrease
is nominal. During constant use, the diameter should be measured periodically and
recorded for historical reference. A small amount of stretch takes place over an
extended use; however, if a marked stretch is noticed then it is a signal of degradation
of rope from wear and fatigue. The rope should then be replaced.
1.8.2.2. Lubrication of Wire Ropes:
During manufacture, wire ropes are fully lubricated (including fiber core and layers) to
reduce internal abrasion, to exclude external moisture and delay corrosion. In service,
the initial lubricant will tend to dry out and, therefore, it is desirable to lubricate all ropes
at regular intervals. There are many methods of applying lubricant, such as vertical or
horizontal grease boxes through which the rope runs, application by brush, leather
483
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
gloves, drip or by spraying. Regular lubrication plays important role in prolonging the
life of a wire rope. The lubricant should preferably be of mineral origin rather than
animal or vegetable origin and should be of a light grade that may penetrate between
the wires and the strands of the rope before being wiped off or absorbed by surface
dirt. It is very desirable that the rope must be cleaned and dry before application of
lubricant. A jet of air or wire brushing is some of the cleaning methods used
preparatory to apply the lubricant.
1.9. Painting:
Hydraulic gates, embedded parts, hoists and super structures are required to be
protected against corrosion due to climatic conditions, biochemical reaction and
abrasion due to different forces acting on these items. For this purpose all the
equipment is painted after certain interval depending upon the working conditions to
which they subjected to (contact with water, weather exposure, aggressiveness of the
environment, mechanical friction and so on). Stainless steel parts, non-ferrous metal
or galvanized parts do not need any protective treatment.
Painting is carried out either in the workshop after manufacture or in the field. In the
latter case, the metal surfaces protected at the workshop with a coat of shop primer,
are removed by sandblast before painting. All surfaces to be painted should be free
from dust, grease, mill scale, oxides and foreign matter. Surface preparation may be
either manual or mechanical, through wire brushes, sand blasting machines.
Up till recently gates at barrages and canal regulators were painted annually with
Khanki Mixture which has the following composition:
100 Wt of Khanki Mixture includes:
84 lbs of Bitumen Asphalt
10 lbs Mineral Pitch
9 lbs Kerosene oil
9 lbs slacked lime
Total = 112 lbs
100 wt Khanki Mixture covers 2500 ft2 area in 2 coats and applying temperature is 35o
– 45oF. The old Khanki Mixture should be removed before painting new. In view of
practical limitations for surface preparation and temperature control during application,
the alternative way is to use epoxy paint. Interseal 670HS is an epoxy paint
internationally known and manufactured in Pakistan by ICI and Burger Paints. It is a
two component epoxy paint suitable for use in both maintenance and new construction
of structural steel immersed in alkali and acidic waters, and provides excellent anti-
corrosive protection. The two parts consist of an epoxy resin and a co-reactant or
hardener that are mixed prior to application
The most accepted standard in steel surface preparation is the Swedish standard SIS-
05-5900-1967 ‘Pictorial Surface Preparation Standards for painting steel surfaces.
484
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
Therefore surfaces to be coated should be free from all weld spatters, sharp edges
and free from contamination. Grease and oil should be completely removed by solvent
wiping. Sand blast cleaning should be applied 4 to 6 hours before painting. The old
paint should be removed before repainting an old surface.
1.10. Instructions for Smooth Operation and Maintenance of Gates
1.11. Lubrication
1.11.1. Lubricants list
Lubrication
Sr.# Item Recommended Lubricants Replacement Time
Methods
1st replace after 3
1 Reducer Pouring 1. SHELL – Omala S2 G 220 months afterwards
2. MOBIL – Mobilgear 600 XP annually
220
Manual 1st replace after 3
3. CHEVRON – Meropa 220
2 Machine Pouring months afterwards
4. CASTROL – Alpha SP 220
(Clutch) annually
1. SHELL – Albida EP2
2. CHEVRON – Starplex EP2
3. CHEVRON – Multifak EP 2
4. TOTAL – Epexa 2
6 Months
Open-type 5. MOBIL – Mobilith SHC PM 460
3 Coating (Annual closure and
gear 6. SHELL – GADUS S3 V220C 2
before flood season)
7. SHELL – Cardium Compound
EP200
8. SHELL – Retinax Grease
CMX2
1. SHELL – Alvania EP 1
Gear 2. MOBIL – Mobilux EP 1
4 Grease gun Annually
coupling 3. CALTEX – Multifax EP 1
4. TOTAL – Multia EP 1
1. SHELL – Malleus Grease GL
300
6 Months
2. MOBIL – Mobilta C-LL
5 Wire rope Coating (Annual closure and
3. CALTEX – Crater 10R 1X
before flood season)
4. TOTAL – Compound B
5. CASTROL – Grippa – 33
1. SHELL – Alvania EP 1
2. MOBIL – Mobilux EP 1
6 Chain Coating Annually
3. CALTEX – Multifax EP 1
4. TOTAL – Multia EP 1
1. SHELL – Albida EP2
2. TOTAL – Epexa 2
Bearing
3. CHEVRON – Starplex EP2
7 seat & Grease gun Annually
4. CHEVRON – Multifak EP 2
Shaft
5. MOBIL – Mobilith SHC PM 460
6. SHELL – GADUS S3 V220C 2
1. SHELL – Alvania EP 1
Roller 2. MOBIL – Mobilux EP 1
8 Grease gun Annually
Train 3. CALTEX – Multifax EP 1
4. TOTAL – Multia EP 1
486
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
Tighten additionally
using Toque
Reducer Wrench upto
There should be no loose or
mounting Looseness specified tightening
missing bolts.
bolts torque or install new
bolts if any bolts are
missing.
The drum bearing and
Identify the cause
Operation intermediate gear bearing
Winding and repair.
should move smoothly.
drum
Bearings should be free from
bearing and
severe stains of discoloration
intermediate
Lubrication from lubricant but may be Refill
gear bearing
slightly stained with lubricant
at their ends.
After cleaning with a
wiping cloth apply
new lubricant. The
Visible dirt lubricant should be
No dirt or dust should be
foreign wiped clean with
visible on wire rope
matter cleaning oil once
Wire Rope every two years and
replaced with fresh
lubricant
the wire rope surface should Apply lubricant
be slightly wet with lubricant using a brush or a
Lubrication
(to the extent that the surface wiping clot (wire
feels sticky when touched) rope oil grease)
Loose lock There should be no loose
Tighten and secure.
nuts double nuts
Adjust. When the
When the gate is at its lower gate is at its lower
Wire rope position, the right and left position, swing the
Rope and
length wire ropes should have rope with a width of
clamp
proper slack of equal length. approximately 200
to 300 mm.
Install new cotter
Cotter pins are properly
Socket pins if any cotter
installed.
pins are missing
Remove the see-
through cover,
clean the indicator
The see-through front cover face with a wiping
Position Mist on
should have good cloth and dry the
indicator indicator face
transparency. internal parts on a
fine day. If
necessary replace
the packing.
Repair if the
Plain The temperature should be
Over heating temperature gets
bearing around 70°C
high often.
488
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
Interval: Annually
There should be no Repair by painting
General Painting corrosion, blister, peeling or or point the entire
cracks surface
Tighten additionally
Bolts and Looseness, There should be no loose or or supply new bolts
nuts detachment missing bolts and nuts. and nuts to replace
the detached
Deflection, There should be no abnormal
Check in detail
deformed deflection or deformation
Main and
Main and side girders have a Repair or check in
End girders Decrease in
Gate thickness greater than the detail (check after
thickness
design thickness earth quake)
If no specific tolerance is
given, any deformation
should be at a low level and
Deformation Check in detail
distributed over a broad
Skin plates zone, its and height shoult be
with ½ of the thickness
Skin plates should have a
Decrease in
thickness greater than the Check in detail
thickness
design thickness
Wear or
abrasion,
Roller Train, damage, There should have no wear
Rollers and operation, or abrasion or damage, and
Check in detail
Spacer and abnormal no abnormal condition during
Side Pates sound and the gate operation
jamming of
rollers
Apply
Roller train The bearing nshould be
Lubrication recommended
Bearing properly lubricated
lubricant
Roller Trains Aging,
Sealed
of Gates derange
section There should not be any Repair / replace
deformation,
(Rubber abnormal condition after check in detail
wear or
seals)
abrasion
Damage, There should be no damage Repair or check in
deformation or deformation detail
Sill beam
Water There should be no water Repair or check in
leakage leakage detail
Damage, There should be no damage Repair or check in
deformation or deformation detail
Seal plate
Water There should be no water Repair or check in
leakage leakage detail
Aging,
Sealed
derange
Gate with section There should not be any Repair / replace
deformation,
Wheel Track (Rubber abnormal condition after check in detail
wear or
seals)
abrasion
490
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
Bearing
Damage There should be no cracks Repair or replace
housing
Bearing
There should be no loose
mounting Looseness Tighten additionally
bolts
bolts
1.12.2. Electric System for hoist control & SCADA
Elements Control
Check Criteria for acceptance
to be (Inspection) Action
Points or rejection
controlled method
At each Operation
Check and identify what
There should be no causes the overloading of
considerable variation the winch, and remove
from the normal current. the cause.
The current values Foreign object attached to
Current Use of a should not exceed the a gate leaf roller.
values ammeter rated current shown on Damaged gear
the motor nameplate. Seized bearing
(they should not exceed Insufficient lubrication
+20% of the current in Open-Phase operation
normal operation.) Freezing
Brake failure
The voltage values
Voltage Use of a should be within a range
Check the power source.
Values voltmeter of + 10% of the rated
voltage.
Overheat, These should not
Visual check
abnormal significantly differ from Check the cause and
and check by
sound, their levels in normal perform maintenance
touch
vibration operation.
Motors The gate should stop
Performanc
0.1-0.5 seconds after the
e (Breaking Visual Check Adjust
“STOP” button is
efficiency)
pressed.
There should be no dirt,
Dirt build- such as oil stains and
Visual Check Clean Up.
up dust (particularly in the
braking section.)
Interval: Monthly
There should be no
cracks or other damage
Wear or in the lining, and dust Clean up or replace any
Visual Check
abrasion from a worn-out lining heavily worn-out linings.
should not be widely
scattered.
Visual Check
Tighten additionally, or
and There should be no loose
Looseness install new bolts if any
hammering or missing bolts.
bolts are missing.
test
492
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
Interval: Annually
Use of a
Insulation
insulation The values should be 5
resistance Check the cause.
resistance M ohm or greater.
values
tester
The values should be 10
ohm or less for motor
Use of a with a rated voltage of
Ground
ground 300 V or greater. The
resistance Check the cause.
resistance values should be 100
values
tester ohm or less for motor
with a rated voltage of
300 V or less.
There should be no
uneven contact, and the
Use of a Adjust or replace the
Clearance limits specified in the
feeler gauge linings.
brake operation manual
should be observed.
gates and include built in intelligence to prevent damage to the gates, the gate hoisting
mechanism and associated structure by shutting down the gate hoist motors and
raising appropriate alarms in case of abnormal situations. In addition to the remote
control, local control of gates is also provided whereby electrical control panels located
on the barrage in close proximity to the gates which can enable switching on and off
of gate control motors by staff stationed at the gate itself. Interlocks (safety and
administrative) is built in to prevent unauthorized operation of gates from both the
control building and the local control panels.
The key features of the gate control system are as under:
• Successive Gate Opening
Standard operating procedure dictates that a particular gate is not operated in
isolation, but rather openings of neighboring gates are successively adjusted in
relation to the opening of a particular gate. This successive gate opening is determined
by the regulation staff present at the site. This practice is adopted to prevent abnormal
hydraulic stresses from developing which can cause damage to the barrage structure.
This existing practice has been built into the control algorithm so that the degree of
adjacent gate openings are determined and implemented automatically based on the
primary gate opening. The procedure of determination of adjacent gate openings is
implemented into the control software.
• Incremental Gate Operation
Under this mode of operation, a gate raise or lower command shall restrict the
movement of gates to no more than one foot at a time. Accordingly a command issued
at the HMI to raise a gate by three feet shall cause the gate to be raised by one foot
and then pause for an adjustable duration ranging from one to five minutes followed
by two subsequent cycles for raising one foot and pausing till the desired gate
movement has been achieved. Under local control gates shall move by no more than
one foot at a time upon pushing of the gate raise or lower button by the operator.
• Switching between Local/Remote mode of operation
The system operator can choose between local and remote control modes from the
control building HMI. Local/remote mode of operation shall also be selectable from the
local control panel for each gate. The Local/remote switch at the control panel have
priority over HMI selection of local and remote modes.
• Automated gate control
An automatic mode of gate control is also provided through software control whereby
the gates of barrage and canal can be automatically adjusted based upon
predetermined water releases into the canal and downstream of barrage. The criteria
for gate control are programmed into the SCADA system as per requirement.
Capability is also built in to the system for the operators to manually override this
feature.
499
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
motion is electronically converted to information about the position of the gate. Two
GPS per each gate are installed for redundancy. Provision is built in the software to
compare the values to the two GPS as a check of bona fide operation and isolate a
GPS found to be defective.
Other techniques like use of inclinometer is considered for measuring Gate position of
radial gates.
II. Video Surveillance Sub-System
The Video Surveillance system comprises of a number of camera sites transmitting
digital (i.e., encoded) images to the Network Video Recorder (NVR) installed at control
room and receiving camera control commands from the system operator or the system
monitor located at the barrage. The Video Surveillance system includes the control
room head-end electronic subsystem, which receives, decodes, and disseminates
images and data from the field and commands the control and display infrastructure.
Video surveillance system serves as a barrage security tool. System design is flexible
to permit extension to give video coverage of key areas of the barrage to help identify
any unusual activity. All CCTV cameras are mounted on a suitable structure poles to
allow a clear view of barrage and off taking canal etc.
➢ Functional Description of Video Surveillance
The Video Surveillance system is being managed with commands and control from a
system operator who may decide which visual images should be collected from the
camera sites. The system operator shall prescribe those images through control of the
CCTV camera's field of view with the pan, tilt, and zoom feature. The Video
Surveillance system manage the transmission of the prescribed images based on the
system operator's designated monitoring terminal in the control room. The images are
processed and, at the option of the system operator, displayed as commanded on
monitors and/or wall mounted LCD mimic board. The system operator has the ability
to control all internal and external functions of the camera assembly from the
monitoring terminal.
III. Three node Barrage Data WAN
The three node barrage data WAN (wide area network) comprises:
i. Transmission and receiving equipment at the remote nodes.
ii. Central transmission and receiving equipment in the control room at
Barrage.
The system is capable of data transmission by provision of point-to-point WAN links
from the Control Room to the specified remote nodes as per requirement. The type of
information transmitted from the barrage comprises gate position, water level and
instantaneous and archived water discharge data. The following solution is deployed
to accomplish the job using IT Switch/Router for data transfer in a secure manner.
A VPN (virtual private network) is provided comprising dedicated virtual or switched
data channel using connectivity by third party bandwidth providers.
501
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
The Historian Server is the heart of the Barrage Historian System. It is able to get the
data and route it in real time throughout the Historian System and entire information
infrastructure, making it possible for everyone to work from a common set of real data.
Operators, engineers and managers, may connect to the Historian Server and view
manufacturing data from Historian Data Storage.
➢ Data Archival server
An optical, write-able digital video disk drive serve as data archive which can store
historical water network data such as gate openings and water levels in real time for
later access.
➢ Engineer/Operator’s Workstation
This is an IBM compatible server computer based on the Intel Core i5 microprocessor
and equipped with 4GB of RAM and 500 GB hard disk drive (minimum).
➢ Video Display Unit
This is 60 inch LED monitors each connected with servers and operator’s
workstations.
➢ 85 inch” LED VDU for Dynamic Mimic Board
This is a 85 inch LED display capable of graphically displaying the status of Barrage
and off-taking Canal
➢ Input Devices
A keyboard, mouse or LCD panel serves as means of human-machine interfaces
between the operator and the main processor.
➢ Printer
An A3/A4 size laser printer for reports and hard copies as desired by the operator is
provided in the control room for printing of drawing and hard copies.
➢ Operating System
The operating system is user friendly based on Microsoft Windows. It is structured to
have an open architecture, which allows the system to run in a multitasking
environment with support for on-line, dynamic data exchange with other applications
such as expert systems, spreadsheets, and database programs.
1.13.7. SCADA and HMI Software
The SCADA and HMI software are standard off the shelf package(s) configured to suit
the Barrage requirements but with minimal customization. It includes the following
functions:
• Data acquisition.
• Alarm/Events processing.
• Data computation and logical analysis.
• Supervisory control.
503
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
• Logging.
• Reporting and Printing.
1.13.8. Human Machine Interface (HMI)
Human machine interface (HMI) is a session interface between the operator and
SCADA; it has many graphical user interface (GUI) windows, which have different
functions. The main functions configured for Jinnah Barrage are as following:
1) User Login
Operator enters his user name and password to enter the system, the operator has
two levels, Administrator and Client. Operators at different levels have different
passwords, they have different privileges. Administrators can browse screen, query
data, output file, change the alarm tag and conditions, and control gate operation.
Whereas the Client can only browse screen, query data and output file, but cannot
control the barrage gates.
2) Supervisory function
It is responsible to display the overall information about monitoring systems such as
water level, water discharge, gate position, status of the hoist , LAN status and alarm
state etc.
Graphical interface with multiple windows is available; operator can change a
window to display different information and can select the tag and date to query
historical data.
The prompt of real-time alarm is always displayed in the current window; Historical
data can be inquired to generate a report text. The Hoist status and alarm messages
are displayed with text and indications.
The water discharge of Main Barrage and Thal Canal are also displayed on the
interface.
Real-time alarm & events information is displayed. The attributes of alarm\event
information include multiple field, such as type of alarm, level of alarm, date & time,
operator name, group name, alarm limit, value of variable, etc.
Operator can browse and query all historical data records, and trend curve can be
generated based on the water level and discharge data. Alarm, messages and
historical data can be generated in EXCEL format to take a print.
1.13.9. Gate Control Function
When the Local control panel LCP is switched to remote mode of operation, the
operator can operate those gates of the Barrage and Canal though HMI/SCADA
terminal in the control room. All the gates are configured in several groups; when
several gates running at same time, the starting interval time is limited for each
adjacent gate to reduce vibration in the Barrage.
504
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
The following safety prevention needs to be practiced for efficient operation of the
SCADA system.
i. Smoke prohibited in Central Control building.
ii. The UPS System loads should be not more than prescribed design limits and it
is also forbit to increase any electric facilities on the installed UPS before
detailed analysis.
iii. Preventive measures to be taken against rain leakage, water remains in cable
trench and groove of cabling system.
iv. It is not permissible to store any other items except equipment in the cabinet or
the console of the control room.
v. It is not allowed to change the configuration of hardware or software such as in
Programmable Logic Controller (PLC), Servers, Computers, Communication
Switches etc.
vi. It is not recommended installing any other software in computer of the SCADA
System.
vii. In case of any abnormal smell, big sound or smoke, the operator should take
immediate action of cutting off the breaker between the batteries room and the
power supply.
viii. In case of any problems scenario the operator should refer to the relevant
technical instructions and record the experience of the problem.
General Check
General Check Plan is given in the table;
Table 2: General Check
Maintenance
Device Components Method Task
Cycle
Fan Electricity and
One week
Door-switch test
Switch
Data Acquisition PLC Clean & replace
Panel (DAP) SPD spare & record
One week Visual check
Fuse
Terminal
connection
Door-switch Electricity and
One week
Lamp test
Central Control Switch Clean & replace
Panel (CCP) PLC spare & record
One week Visual check
Terminal
connection
Optical
Distribution One week Visual check Clean & Record
Frame (ODF)
UPS One week Visual check Clean & Record
Battery One week Visual check Clean & Record
506
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
Plan all resources and define daily and weekly task activities for the field teams,
including routine & planned activities, data fills and manage resources to meet
the departmental deliverables. Prioritize activities within the barrage sites.
Staff Management
Ensure staff performance is reviewed regularly and plans are designed and
executed for adequate training and development in order to improve
performance and productivity.
Inventory & Resource Management
Responsible for spares inventory and barrages resource management. Ensure
proper records for the utilization of resources and the nodes spares.
Occasional Tasks and Responsibilities
Any responsibility / assignment other than mentioned above entrusted by the
Government time to time.
510
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
References:
1. Design of Hydraulic Gates by Paulo C.F. Erbisti
2. Preventive Maintenance of Gates and Hoisting System of Jinnah Barrage ----
by Project Contractors M/s DESCON
3. Operation and Maintenance Manual for Taunsa Barrage Gates by M/s
KORIMOTO Ltd, Japan
4. Paper on Operation & Maintenance of Radial Gates and Fixed Wheel Gates --
-- By E.R.N. Kannaiah Naido Technical Advisor India
5. Bureau of Indian Standards IS3973-1964- code of Practice for Selection,
Instructions and Maintenance of Wire Ropes
6. Maintenance of hydraulic gates- Important Parameters by Mr. P. Madanaiah,
Consultant, Centre for Good Governance
7. Hydraulic Gate Seals by Industrial Rubber Supply Manufacturers of Quality
Industrial Products, 55 Dunlop Avenue, Winnipeg, Manitoba, Canada
511
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
2. EARTHMOVING MACHINERY
2.1. Introduction
Punjab Irrigation Department (PID) is maintaining earthmoving machinery in three
Divisions namely (i) Excavator Division Faisalabad, (ii) Machinery Division Lahore and
(iii) Machinery Division Multan under Machinery Circle at Lahore. The machinery is
broadly categorized as
I. Excavation machinery
II. Earthmoving and compaction equipment
Excavators and draglines are used for excavation and de-silting of drains while dozers,
scrapers and dump trucks are used for earthmoving in connection with making new
flood bunds or maintaining existing flood bunds. In a way the departmental machinery
is like a fire brigade because it is readily available for use by the field formation to
combat floods in order to protect the departmental infrastructure.
All the departmental earthmoving machinery is of imported nature and was acquired
under some foreign assistance such as US AID Program in 1984-87 or under ADP in
2004-6. It is therefore very essential to operate and maintain this expensive machinery
with proper care so that it works economically and efficiently for a longer period.
2.1.1. Types of Earthmoving Machinery Used In Irrigation Department
I) Bulldozer
II) Excavator
III) Draglines
IV) Motor Grader
V) Dumper Trucks
VI) Loader
VII) Scraper
VIII) Cranes
I) Bulldozer:
Bulldozers are considered one of the strongest and toughest heavy equipment used
in the construction industry. Over short distances (up to 100 meters) bulldozing is the
cheapest way of cutting and moving spoil. They are used for dozing and spreading
earth or pushing / loading scrapers. Bulldozers are classified into two types
(a) Crawler mounted Bulldozer
(b) Wheel mounted Bulldozer
(a) Crawler Mounted Bulldozer:
The crawler type bulldozer has greater tractive force and can travel on any rough
terrain, muddy surface/soil and can push large blade loads. It has greater flotation and
less chances of bogging down due to wide tracks; however, its travelling speed is slow
and is good for hauling loads over short distances.
512
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
draw the bucket assembly horizontally. By skillful maneuver of the hoist and the
dragropes the bucket is controlled for various operations.
The primary limitations of draglines are their boom height and boom length, which
limits where the dragline can dump the waste material. Another limitation is their dig
depth, which is limited by the length of rope the dragline can utilize. A dragline is most
efficient for excavating material below the level of its base. While a dragline can dig
above it, it does so inefficiently and is not suitable to load piled up material (as a rope
shovel or wheel loader can).
IV) Motor Grader:
It is a self-propelled wheeled machine with a long blade that can be adjusted to meet
certain angles to create a flat surface positioned between the front and rear axles. The
machine is primarily designed for grading, shaping, bank sloping, ditching and
scarifying of materials through its forward motion.
Graders are commonly used in the construction and maintenance of earthen roads
and gravel roads. In the construction of paved roads they are used to prepare the base
course to create a wide flat surface for the asphalt to be placed on. Graders can
produce inclined surfaces, to give can’t (camber) to roads. Motor graders can also be
fitted with a second blade in front of the front axle for leveling/grading/scraping.
V) Dumper:
Dumper, also known as dump truck is a heavy-duty truck specially designed &
constructed for carrying heavy loads under various operating conditions. It transports
and dumps or spreads materials like soil, rocks, coal, minerals, aggregate etc, by
hydraulically raising and lowering the container carrying the load.
VI) Loader:
It is a self-propelled crawler or wheeled machine which has front-mounted equipment
primarily designed for loading operation (bucket use) and which loads or excavates
through forward motion of the machine. A loader work cycle normally comprises filling,
elevating, transporting and discharging of material.
VII) Scraper:
It is a self-propelled or towed crawler or wheeled machine which has a bowl with a
cutting edge positioned between the axles, and scraps the ground, loads it
simultaneously, transports over a distance, discharges and spreads material at the
desired place through its forward motion. On the return trips to borrow pits the cutting
blades of scrapers may be lowered enough to remove high spots, thereby assisting in
maintaining the haul roads. The loading through a forward motion can be assisted by
a powered mechanism (elevator) fixed on the scraper bowl. Scrapers can be self-
loading or be assisted by another scraper or a bulldozer. A Scraper that is not self-
propelled but which is propelled by a towing machine is called a towed scraper.
514
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
VIII) CRANES:
Cranes are hoisting equipment used for lifting or carrying the loads and placing them
at desired place such as trailers, dump trucks, belt conveyors or at other required
places.
2.1.2. Fundamental Terminology Used For Estimating Production:
Production: Production is the hourly rate at which the material is moved. It can be
expressed in various units.
Cycle Time: Time for the round trip. The sum of the time required to complete the
actions involved in a cycle is called cycle time. For a dozer it can be represented as
Cycle Time = Load + maneuver + spread + return time
Cycles per hour = 60 min/hour
Total Cycle time (minutes)
Bank Cubic Yard (BCY): one cubic yard of material as it lies in the natural bank state.
Loose Cubic Yard (LCY): one cubic yard of material which has been disturbed and
has swelled as a result of loading.
Compacted Cubic Yard (CCY): one cubic yard of material in compacted state and
has become denser as a result of compaction.
For example, one cubic yard of earth in natural condition occupies a volume of 1.25
cubic yards after digging (loose earth) and becomes 0.9 cubic yard after compaction.
Swell: When soil is removed from its natural resting place, it swells or puffs up. Swell
of materials is expressed as a percentage of the increase in volume. For example the
swell of dry clay is 40% which means that a cubic yard of clay in the bank will fill a
space of 1.40 cubic yard in a loosened state.
Generally, earthmoving jobs are calculated on the basis of BCY, thus in order to
estimate production, the relationship between bank measures, loose measures, and
compacted cubic measure should be known.
Production / hour = Load/cycle x cycles/hour
Load Factor may be obtained if the % of swell of material is known by using the
following relationship
100%
Load Factor (LF) = 100%+% SWELL
Therefore,
1 cubic yard of clay (loose state) = 1 or 0.72 cubic yard of clay (bank state).
1.4
This means that if a scraper is carrying 25 LCY of dry clay, it is carrying (25 x 0.72) =
18 BCY
Load (BCY/hr) = Load (LCY/hr) x load factor
515
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
Shrinkage factor: The ratio between compacted measure and Bank measure is
called the shrinkage factor.
Compacted Cubic Yard (CCY)
Shrinkage Factor (SF) = bank Cubic yard (BCY)
To obtain estimated production in bank cubic yards the appropriate load factor (LF)
from tables is applied to the corrected production as calculated above
Production (bcy/hr) = (lcy/hr) x LF
Steps for estimating dozer production:
1: Note the Ideal maximum dozer production rate from production charts provided for
the particular dozer model and type of blade.
2: Assume different correction factors for less than ideal conditions.
a. weight Correction Factor for material – (CF = 2,300lb/LCY(ideal)/actual lb/LCY)
b. Operator Efficiency correction factor - use table provided
c. Material type Correction Factor - use table provided
d. Operating technique Correction Factor - use table provided
e. Visibility Correction Factor - use table provided
f. Grade Correction Factor - use chart/graph provided
3: Total Correction Factor = multiple all correction factors
Production = Ideal maximum production x Total correction factor
Note: Make sure it is in the right units of production ex. BCY, CCY, LCY per hour. g).
Machine transmission factor - use the shrinkage or swell factor given to calculate or
use tables.
To determine how much time is needed to complete the job
Total time (hours) = Q / (P x N) where Q = quantity of material to be moved
P = hourly production rate per dozer
N = Number of Dozers
To determine the number of dozers required to complete project within specific
time:
Total number of dozers = Q / (P x T) where Q = quantity of material to be moved
P = hourly production rate per dozer
T = maximum allowable duration in hours
Example: determine average hourly production of a dozer moving hard packed clay
an average distance of 150 feet down a 15% grade, using a slot dozing technique.
Estimated material weight is 2650 lbs/lcy. Operator is average. Job efficiency is
estimated at 50 min/hr. Uncorrected maximum production is 600 lcy/hr
Applicable correction factors:
Hard packed clay is “hard to cut” material 0.80
Grade correction (from Graph) 1.19
Slot dozing 1.20
Average Operator 0.75
Job efficiency (50min/hr) 0.83
Weight correction (2300/2650)
Production = Maximum production x correction factors
517
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
=(600) lcy/hr)x(0.80)x(1.19)x(1.2)x(0.75)x(0.83)x(0.87)
= 371 lcy/hr
2.2.2. Excavator Production:
3600 Sec xQxF E
Production per hour = [60][ Volume correction]
t
Where
Q = heaped bucket capacity (lcy)
F = bucket fill factor
t = cycle time in seconds
E = efficiency (min per hour)
Volume correction for loose volume to bank volume 1
1+Swell Factor
2.3. Guidelines for Preparing Annual Estimate for Excavator/Dragline
(Rate per Hour and Rate per Cft):
The Machinery Divisions have got Draglines and Excavators of different make, boom
length, bucket size and engine horse power. The guidelines hereunder are of general
nature applicable to each machinery unit with minor changes, however, an estimate
for a tire mounted Excavator is discussed with assumption that the unit works for a
total of 1600 hours in a year.
Name of Machine: Hydraulic Excavator (Tire Mounted)
Model M315D
Make Caterpillar
Bucket sizes 1.0 cyd
Engine Brake Horse Power (BHP) 137
Boom Length
Year of Purchase
2.3.1. Owning Charges:
In order to protect his investment in equipment and be able to replace it, the machine
owner recovers the cost of machine during useful life of the machine plus other
charges such as interest on investment, taxes and insurance. Since the earthmoving
machinery of Machinery Circle is utilized on the departmental work, and has been
procured through government funds, therefore these charges are not included in the
analysis of rates. However, if the equipment is deployed on rental basis for private
work or on contract work, these charges should be recovered in the form of
“departmental charges” as a %age (normally 12.5%) of the rate calculated for the
departmental work.
2.3.2. Operation charges:
These include;
I. POL charges
II. Replacement of Filters
III. Establishment charges
518
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
In the Irrigation Department, excavators are generally used for de-silting of drains
where the soils are not too hard, so the LF between 50-65% can be applied. Thus, if
the fuel consumption per Bhp at 100% LF has been specified by a manufacturer as F,
then the fuel consumption per hour for a 137 Bhp engine at 0.6 LF will be
Hourly Fuel Consumption = 137 x F x (0.6)
Taking the example of an excavator from Caterpillar Co. whose specifications in the
Caterpillar Performance Handbook indicate hourly fuel consumption for model M315D,
at different LF as below.
519
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
For desilting of drains, we can therefore use 15.5 (average of 13 & 18) liters diesel
consumption per hour. The POL consumption as stated below is based on the
capacities and maintenance instructions indicated by Caterpillar for the particular
model M315D.
• Mobil Oil change:
a. Engine Crank Case = 8 liters after 200 hours
For 1600 hours = 1600x8/200 = 64 litres
b. Daily engine oil make up = (0.0006 liters /Bhp/hr)x Bhpx1600 = 131.5
liters
Total for engine oil = 64 + 131.5 = 195.5 liters x cost /liter = Rs. ------
• Gear Oil change:
a. Rear Axle Housing (Differential) oil change = Cap.14 liters, after 1000
hours
= (14/1000) x 1600 = 22.4 liters
b. Front Axle Housing (Differential) = Cap.10.5 liters, after 1000 hours
=(10.5/1000)x1600 = 16.8 liters
c. Final Drive oil change = Cap. 2.5 liters, after 1000 hours
= 2.5 x (1600/1000) = 4 liters
d. Power Transmission oil change = Cap. 2.5 liters, after 1000 hours
= 2.5 x (1600/1000) = 4 liters
Total for Gear oil = 22.4 + 16.8 + 4+4 = 47.2 liters x cost /liter =Rs ------
• Hydraulic oil change: tank capacity 135 liters after every 2000 hours
= 135 x (1600/2000) = 108 liters
Hydraulic oil daily make up = 0.0001/Bhp/hr = 0.0001 x 137x 1600 = 22 liters
Total for Hydraulic oil = (108 +22) x cost /liter = Rs. -------
• Greasing of parts: It should be checked at site (or approximately 1.0 kg per 8
hr shift)
= 1x 1600/8 = 200 kg x cost/kg = Rs. ------
II. Replacement of filters: This should be scheduled as per maintenance instructions
in the handbook. According to the maintenance instructions of M315D, the Filters
should be replaced as per following timings
➢ Engine oil filter after 250 working hrs
➢ Air Filter (Primary Element) once a year
➢ Air Filter (secondary Element) twice a year
➢ Fuel Filter after 500 working hours
520
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
Table 8: Effect of Depth of Cut & Angle of Swing on the Productivity of Draglines
%age of Angle of Swing
Optimum Depth 30 45 60 75 90 120 150 180
20 1.06 .99 .94 .90 .87 .81 .75 .70
40 1.17 1.08 1.02 .97 .93 .85 .78 .72
60 1.24 1.13 1.06 1.01 .97 .88 .80 .74
80 1.29 1.17 1.09 1.04 .99 .90 .82 .76
100 1.32 1.19 1.11 1.05 1.00 .91 .83 .77
120 1.29 1.17 1.09 1.03 .98 .90 .82 .76
140 1.25 1.14 1.06 1.0 .96 .88 .81 .75
160 1.20 1.10 1.02 .97 .93 .85 .79 .73
180 1.15 1.05 .98 .94 .90 .82 .76 .71
200 1.10 1.10 .94 .90 .87 .79 .73 .69
a. Walk around the machine to check people and objects that might be in the
way;
b. Just before starting, check all controls such as forward and reverse, steering
and transmission to ensure they are in the correct start-up position.
c. After starting the engine, check gauges, instruments and warning lights, all
controls and all warning and safety devices and indicators. Check operation
of service and parking brakes on level ground. Particular attention should be
focused on abnormal noise, undue vibration and smell;
d. Check service brakes in both forward and reverse operation on level ground;
e. When operating a machine, fasten the seat belt. Never mount or dismount a
machine unless it is stationary. Ensure that the cabin door is securely closed;
f. Always operate the machine slowly until fully familiarized with its control;
g. Prevent suffocation. If you must operate in an enclosed area, be sure that
there is sufficient ventilation for effective dispersion of the engine exhaust.
h. When working on slopes, avoid side hill travel whenever possible. The danger
of sliding and tipping during side hill travel is always present regardless of
how heavy or stable your machine may appear to be.
i. Avoid operating the machine too close to an overhang, deep ditch or hole and
be alert to potential caving edges, falling rocks and slides, rough terrain,
obstacles and overhead lines;
j. In case of restriction of the view of the operator, do not operate the machine
unless a helper is available for giving signals for safe operation;
k. Under wet or rainy conditions when the ground became too slippery for the
machine, stop the earth moving operation;
l. Never operate the machine in case of inadequate lighting. Adequate lighting
should be arranged for operation at night time;
m. Never leave the machine while the engine is running and ignition key is on
the machine; and
n. Never use the machine for any purposes other than it is designed for.
2.5.3. Parking:
Having finished the earth moving operation, the machine should be stationed in a
place off the work area or access road. Following points should be noted:
(a) Park on level ground, with the parking brake firmly applied and blocked by
suitable wedges, where appropriate. For wheeled machine, the wheels should
be chocked by suitable wedges and never chock the wheels with rocks. Avoid
parking near edges of slopes and excavations;
(b) Lower the attachments or working tools to the ground
(c) Remove the ignition key and hand it back to the site personnel for safe custody.
2.5.4. Loading and unloading
Machines always involve potential hazards. The procedure recommended by the
manufacturer should always be followed. For Excavators; swing lock must be engaged
before loading/unloading the machine.
526
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
• Linkage: Each hinge is a point where lubrication is required, and where a pin
may loosen and come out. Steering linkage acting on the wheels is subject to
damage from collision with rocks or other objects. Check for slackness in the
steering and lever controls and worn brake pedals and rectify and replace as
necessary
• Leaks: Surfaces of the machine, and the ground under it, should be inspected
for evidence of leakage of lubricating or hydraulic oil, or coolant. In the hydraulic
system, leaks are usually at joints. Leakage for fuel oil and air-system should
also be inspected. Any evidence of leak should be investigated and rectified
with defective parts replaced immediately.
• Radiator: The fluid levels should be checked at the beginning of each shift. For
engine with an auxiliary container for coolant, the level of the coolant should be
maintained within the upper and lower levels as indicated in accordance with
the manufacturer's instruction manual. Never loosen the filler cap of the radiator
until the engine is cooled down.
• Reservoirs: All equipments have a fluid reservoir whose level is checked by a
dip stick, usually while the engine is shut off. The operator must be sure to use
the dip stick, and add oil if necessary, before starting. The tank for hydraulic
system should be checked either by a sight gauge, a dip stick or a look through
the filler cap opening, after it has been depressurized and cooled down. Air
reservoirs (or air-vessels) should be regularly drained to remove condensation
water to maintain their efficiency.
• Air Cleaner: Open and check the presence of trash in the air cleaner. Remove
any trash and replace worn out parts. Keep the air cleaner in a serviceable
condition at all time.
• Roll Over Protection Structure: Look for any loose or damaged bolts.
Replace damaged bolts or missing bolts with original equipment parts only.
Replace the structure mounting supports if the structure rattles or makes a
noise when the machine is operated on a rough surface.
• Seat and Seat Belt: Inspect condition of seat, seat belt and associated
mounting hardware. Replace any damaged or worn parts.
• Battery: Check battery condition, including connections, level of electrolyte,
and leakage.
• Reverse Warning Signals: Check both audible alarm and flashing light
warning signals on the machine.
• Other safety features: Check control buttons, lights and mirrors.
528
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
8. Air Filters, Hydraulic Filters, Oil Filters etc and hydraulic pipes shall be
purchased from reliable sources, of proper quality and replaced at proper time.
The old ones shall be deposited in the stores to ensure that the item has been
replaced. These items shall be purchased at Divisional level and issued from
stock as and when required.
9. The Executive Engineer shall ensure that purchase of lubricants is made
through Oil Companies (PSO, Shell, Caltex etc.) directly and not through the
Petrol Pumps.
10. Purchase of Diesel for machinery shall be made at Divisional level on demand
by SDOs direct from Oil Companies (PSO, Shell, Caltex etc.) and no local
purchase shall be made through petrol pumps.
11. There shall be no work charge staff chargeable to the estimates, all field staff
should be made regular in service.
Work done during the month shall be got verified at the end of the month from
the Indenting Division on the logbook of machine with reference to MB No: and
page
12. The Log Book of the machine shall be available at the machine in the custody
of machine operator and every check, replacement of part or lubricant shall be
entered into the Log Book. Copy of the Log Book shall be submitted by the Sub
Engineer in charge to the Sub Division after his counter signatures up to 5 th of
next month.
13. As the machines are imported ones, most of the spare parts are also of
imported nature and have high cost. Expenditure incurred for R&R shall be
carefully monitored by observing following precautions
• No providing-and-fitting of parts shall be allowed through the contractors.
The parts supplied by contractors shall be taken on stock register of the
Division and then issued.
• The contractors shall provide supporting documents regarding import of
parts or local manufacturers.
• The indent for issue of a part from stock shall be approved by the SDO in
charge for a cost up to Rs.25000/- and beyond this cost the indent for
issue of part shall be approved by the Executive Engineer. These limits
may be reviewed subject to approval by the Chief Engineer Development
as and when required.
14. Mughalpura and Bhalwal Irrigation Workshops are equipped with machinery
for overhauling/ major repairs of earthmoving machinery, therefore heavy
repairs of machine components shall be done from government workshops. In
this connection, the SE Machinery Circle shall fix a limit above which all repairs
shall be referred to the government workshops.
15. Old parts taken out from the machine shall be returned to stores and declared
as unserviceable and disposed off on yearly basis.
530
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
16. Condition of every machine unit more than 10 years old or completing more
than 20,000 working hours shall be checked by a Committee constituted by the
Department to assess its condition whether useful for deployment on work or
not. If the unit is no more usable for work (due to its obsolete model,
deteriorated condition or non availability of parts) then it shall be shifted to a
specified parking yard of the Division concerned, and no further expenditure
should be incurred on that unit. The procedure for declaring the unit as
unserviceable and its disposal shall be processed as per rules. New equipment
shall be procured to replace the unserviceable item.
17. All the Trailers shall be kept in good working order and ready to perform shifting
of machinery on short notices. The Executive Engineer incharge of Trailers
should personally inspect the trailer before start of flood season to ensure
about the satisfactory working condition of the Trailer.
18. O&M budget allocated by the Government shall be spent for repairs and
replacement (R&R) of parts of machinery. No extra provision for R&R charges
shall be made in the manufacture estimates. Major repairs shall be taken up
through MIW and BIW, while routine repairs of working machines shall be done
by the concerned machinery Divisions.
19. For construction of flood bunds, spurs, cunnets/river diversions, the scraper
dozer unit of Machinery Circle shall be utilized.
531
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
17 Radiator Clean
20 Scarifier Teeth Inspect/Replace
43 Scarifier Lift Link Socket Lubricate
45 Tire Inflation Check
Swing System
Problem Cause Remedy
No swinging motion Swing brake valve faulty. Replace brake valve.
Hydraulic timer faulty. Replace timer.
Swing brake valve faulty. Low brake release pressure. Adjust pressures.
Swing motor failed. Replace swing motor.
Remote control valve failed. Replace control valve.
Wrong pilot line connection. Reconnect pilot lines.
Swing motion jerky Swing gear worn out. Replace swing gear
Swing bearing damaged Replace bearing
Improper lubrication Add grease
Electrical System
Problem Cause Remedy
Battery will not hold a Low battery power. Clean and retighten.
charge Alternator belt loose or bad. Tighten or replace belt.
Loose or corroded terminals. Tighten or replace as required.
Alternator faulty. Repair or replace as required.
Low battery power Internal battery short. Replace battery.
Short circuit in wiring. Repair as required.
Engine speed is not Speed control dial failed. Replace control dial.
controllable Throttle controller failed. Replace controller.
Speed control motor failed. Repair or replace as required.
Blown fuse. Replace fuse.
Wiring harness damaged. Repair or replace as required.
Connector failed. Repair or replace as required.
Power mode selector Blown fuse. Replace fuse.
does not work Power mode selector switch Replace switch.
failed.
Connector failed. Replace connector.
Wiring harness damaged. Repair or replace as required.
542
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
Travel System
Travel motion does not Center joint leaking. Repair or replace as required.
function
Parking brake will not Repair parking brake.
release.
Travel motor failed. Repair or replace as required.
References:
1. Construction Planning, Equipment and Methods by Peurifoy RL, Mc Graw Hill
Publication
2. Construction Equipment Management for Engineers Estimators and Owners –
Douglas D. Grans Berg Calin M. Popascu Prichard C. Ryan
3. FAO Corporate Document Repository --- calculation of Machine rates
4. Caterpillar Performance Handbook No:29
5. Caterpillar Maintenance Manual for D8K Dozer
6. Construction Operation and Methods “Equipment Production” ---
WWW.learncivilengineering.com
7. Operation and Maintenance Manual --- DOOSAN Solar S220LC-V Hydraulic
Excavator
543
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
3. PUMPS
3.1. Introduction
Pumps are installed in the Irrigation Department for lifting canal water from a lower
NSL to higher NSL and for extraction of ground water for salinity and reclamation
control of lands. For Lift Irrigation purpose, Centrifugal pumps are installed at sites
where small quantities (up to 10 cusecs) of irrigation water are lifted at low heads. For
greater quantities of water, either split pumps or vertical tubular axial flow pumps are
installed. For extracting groundwater, T/wells of centrifugal type are installed for low
depths and deep well turbine pumps for greater depths.
3.2. Centrifugal Pump:
Centrifugal pump works on the principle that an impeller rotates inside a pump casing
fitted with a drive shaft. The liquid entering the pump is rotated by the impeller and the
centrifugal force generated in the fluid due to rotation is converted to pressure head
by a volute chamber called Discharge Head. As a result, the fluid is transported to the
outlet opening of the pump with pressure. At the same time, a negative pressure zone
called Suction Head is created at the inlet opening, which draws the fluid further into
the pump. Fig.7 below explains this principle of operation.
The pump’s efficiency varies throughout its operating range. Each pump will have its
own maximum efficiency point. The best efficiency point (BEP) is the point of highest
efficiency of the pump. All points to the right or left of the BEP have a lower efficiency.
• Pump can be shut down by switching off power supply to the motor, however,
if there are no provisions against liquid hammer, the flow regulating valve in
discharge piping should be closed prior to stopping the pump
• While doing maintenance work on pump, ensure to switch off the electric power
supply
• Never over lubricate the bearings with grease or oil as it will cause overheating
of bearings
• Do not use grease or oil contaminated with solid particles. Always use
oil/grease type recommended by the pump manufacturer
• For pumps fitted stuffing box and gland packing, dripping of water /pumped
liquid should continue from the glands to remove the heat generated due to the
friction between gland packing and the rotating shaft. The quantity of dripping
liquid depends upon the size of pump and the pressure in the stuffing box
housing.
• Adjustment of gland packing should not be done when the pump is running
• If the pump remains out of service for long period of about two months or more,
replacr the gland packing prior to start up as the gland packing gets hard.
3.6.3. Trouble Shooting
Sr.
Trouble Check for
No:
1 Pump fails to build head pressure : a. Pump not primed.
b. Incorrect pump rotation.
c. Motor speed too low.
d. Suction line restricted.
e. Motor failure.
f. Plugged or damaged impeller.
g. Pump or impeller under sized.
h. Pump cavitations
i. Improper impeller clearance.
Pump fails to provide enough flow
2 a. System resistance too high.
rates.
b. Pump under sized.
c. Pump not primed.
d. Driver speed too low.
e. Poor suction conditions.
f. Improper impeller clearance.
Excessive noise or vibration during
3 a. Motor bearing failing.
operation.
b. Pump cavitations.
c. Improper impeller clearance.
Trouble Shooting
In majority of cases, operational difficulties are external to the pump and following
causes should be carefully investigated before undertaking repairs:
I. No Water Delivered
• Pump not primed – indicated by no pressure on discharge.
• Speed too low – indicated by low pressure on discharge.
• Valve closed – indicated by high discharge head.
• Impeller completely plugged up – indicated by low discharge pressure.
II. Abnormally Small Quantities Delivered
• Air leaks in suction pipe or stuffing boxes.
• Speed too low.
• Discharge head higher than anticipated.
• Impeller partially plugged up.
• Obstruction in suction line.
• Mechanical defects: casing rings worn, impeller damaged, casing or seal
defective.
III. Insufficient Pressure
• Speed too low. Might be caused by low voltage or current characteristics
different from nameplate reading on the motor.
• Air in water will cause the pump to make a cracking noise.
• Mechanical defects: worn casing rings, damaged impeller, defective casing
or seal.
IV. Intermittent Operation
• Leaky suction line.
• Water seal plugged (hence, a leaky stuffing box).
• Suction lift too high.
• Air, gas or vapor in liquid.
V. Pump Overloads Motor
• Speed too high.
• Head lower than rated, hence, pumping too much water. (This is valid for
low specific speed pumps).
• Mechanical defects: stuffing boxes too tight, shaft bent, rotating element
binds.
• Rubbing due to foreign matter in the pump between the case rings and the
impeller
VI. Pump Vibrates
• Misalignment.
• Foundation not sufficiently rigid.
556
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
4. IRRIGATION WORKSHOPS
4.1. Introduction
With the advent of canal irrigation system in the Sub Continent, the need for repair of
gates and gearings of barrages and canal head regulators was felt, so a workshop
was established in Amritsar (India) in early 20th century, named as Central Irrigation
Workshop Amritsar. Subsequently, Mughalpura Irrigation Workshop (MIW) was
established in Lahore, in 1944 as a branch of Central Irrigation Workshop Amritsar.
After Independence in 1947, the MIW was the only workshop in the country to cater
for the fabrication and repair of gates and hoisting systems for barrages and head
regulators of canals.
A Central Stores Division Lahore and an Excavator Division Faisalabad (previously
Lyallpur) were also established along with the MIW in 1944 under a Mechanical Circle
Lahore to administer and control the working of machinery and mechanical equipment
of the department. During construction of Taunsa barrage on river Indus, another
workshop was established at Bhalwal (District Sargodha) in 1955 for fabrication of
gates and hoisting system of Taunsa Barrage. A design section for designing gates is
working in Mechanical Circle Lahore, to provide detailed designs of gates and allied
equipment required to be fabricated.
4.2. Mughalpura Irrigation Workshop (MIW):
As already stated above, the MIW was commissioned in 1944 for fabrication and repair
of gates and hoists for barrages and canal head regulators. The workshop is headed
by an Executive Engineer supported by two Assistant Engineers (SDOs) and has been
meeting the requirements for gates and hoisting systems all over Punjab as well as
NWFP (Khyber Pakhtoon Khaw) till 1990s’. In addition, repair of departmental
earthmoving machinery, vehicles and T/Well pumps was also done by the MIW.
During 1984-86, the Workshop was renovated under US AID Program, old buildings
were repaired, new buildings were constructed and some new equipment for
overhauling of heavy earthmoving machinery was installed. The Workshop has
following shops
1. Electric Shop 6. Vehicle Repair Shop 11. Carpenter Shop
2. Engine Shop 7. Transport Shop 12.Painter Shop
3. Steel Shop 8. Machine Shop 13. Civil Shop
4. Welding Shop 9. Fitting Shop
5. Smithy Shop 10. Foundry Shop
The Workshop is capable to perform following functions:
❖ Repair, fabrication and installation of gates and gearings of barrages and canal
regulators
❖ Repairs of pumping machinery of Lift Irrigation Schemes & T/wells
❖ Rewinding of electric motors
558
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
4) Cost of liveries
5) Pay of work-charge staff and idle labour
6) Transportation charges in connection with management of workshop
7) Expenditure in connection with court cases
Office Charges: These include
• interest on capital value of T&P, its depreciation and M&R Charges
• interest on capital value of buildings, its depreciation and M&R Charges
• Establishment Charges, TA, Contingencies, Electric and Telephone charges
Store Supervision Charges: These include
➢ Interest on capital value of stock in hand
➢ Depreciation and maintenance of tools and plants (T&P) of store
➢ Share of Establishment Charges (other than work-charge) and a proportionate
share of General Office Charges
In the commercial accounting system, all direct and indirect charges are recovered
from the jobs executed by the workshop. Thus for every job executed in the MIW, a
job order is opened and direct expenditures (Labour and Material charges) incurred
on the job in relevant shops (such as Foundry, Machine etc) are recorded and
compiled when the job is completed.
The Indirect Charges under the sub heads mentioned above are estimated for the
whole year on the basis of anticipated as well as previous year’s expenditures and a
proportionate share of Indirect Charges is charged to the job on the basis of total
estimated cost of jobs to be done by the Workshop during the whole year.
An analysis of the actual expenditures under General Charges, Factory Charges,
Office Charges and Store Supervision Charges was done in the past decades (when
there was sufficient workload in the workshop), and it was observed that these are
proportional to the labour charges in the following ratio.
General Charges (GC) : 70% of labour charges
Factory Charges (FC) : 50% of labour charges
Office Charges for work at site : 22.5% of labour charges at site
Store Supervision Charges 10% cost of material
Thus, since last 20 – 25 years, Indirect Charges are being levied on the jobs executed
in the workshop in the above proportion. Since the workshop is getting much less work
load (few jobs) than its full capacity, the labour is not fully utilized and consequently
the Indirect Charges, especially GC and FC are not fully recovered (100%) on the
basis of above percentages. The result is that the Balance Sheet shows workshop
going in loss. Therefore, this proportion needs to be reviewed after a certain interval
of time so as to balance the income and expenditures in the Balance Sheet prepared
on annual basis. At the same time, there is a need to provide more work load to the
workshop to utilize its working capacity.
An example for calculating the cost to be charged from a job is given below.
560
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
References:
1. Mechanical Circle Irrigation Department, Lahore
562
MANUAL OF IRRIGATION PRACTICE
MECHANICAL, ELECTRICAL WORKS & SCADA
i
MANUAL OF IRRIGATION PRACTICE
HYDRAULIC MODELING
HYDRAULIC MODELING
Table of Contents
1 HYDRAULIC MODELING .......................................................................................... 563
1.1 Introduction ......................................................................................................... 563
1.2 Physical Models .................................................................................................. 563
1.2.1 Hydraulic Similitude ..................................................................................... 563
1.2.2 Geometric Similarity ..................................................................................... 563
1.2.3 Types of Physical Model .............................................................................. 571
1.2.4 Data Requirements for Physical Hydraulic Modeling. ................................... 573
1.3 Introduction to Mathematical Modelling ............................................................... 575
1.3.1 General: ....................................................................................................... 575
1.3.2 Categories of Modelling ............................................................................... 576
1.3.3 Model Calibration and Validation.................................................................. 582
1.3.4 Performance Evaluation Criteria of Mathematical Models ............................ 583
1.3.5 General Description of Some Models ........................................................... 584
1.4 Modelling Facilities of Punjab Irrigation Department ............................................ 586
1.4.1 Irrigation Research Institute ......................................................................... 586
1.5 Reference used in Mathematical Modelling Section ............................................ 589
List of Figures
1 HYDRAULIC MODELING
1.1 Introduction
The design process includes hydraulic modeling to confirm the hydraulic behavior of
various components of the Project. Two different techniques are used for hydraulic
modelling. These include:
(i) Physical Modelling
(ii) Mathematical Modeling
Initially physical modeling was the only tool available. However, with the increase of
computational capacity of computers, mathematical modelling is also extensively used
now. Initially various options may be studied through mathematical modeling and the
most promising option is then subjected to physical modeling for confirmation of the
projected results. In the Punjab hydraulic modeling is done at the Irrigation Research
Institute laboratories at Lahore and Nandipur. A brief introduction of the Institute is
provided in Section 1.4.
1.2 Physical Models
Physical models involve physical testing of designed project parameters on a model
built on a reduced scale. This requires a clear and accurate understanding of the
principles of similitude. Similitude is the study of similarity between prototype and the
model. A brief description of hydraulic similitude is given in Section 1.2.1.
1.2.1 Hydraulic Similitude
After collecting the data and information relating to the problem(s) to be studied, the
second stage is the fixation of model scales i.e. the ratio between the prototype values
and the model values. This requires a clear and accurate understanding of the
principles of similitude.
Experience indicates that it is necessary to confine similarity to a single force. Since
in most open channel flow problems, the force of gravity is the primary force, therefore,
only similitude in open channel flow problems is considered for the purpose of keeping
this discussion as simple as possible. This is the principal type of similitude which is
required in most of the works in Pakistan. Complete similitude requires conformity with
respect to geometric, kinematic and dynamic factors in model and prototype.
1.2.2 Geometric Similarity
Two objects are said to be geometrically similar if the ratios of all corresponding
dimensions are equal. Thus, the geometric similarity refers only to similarity in form.
For geometric similarity to exist, all linear dimensions are related by the equation;
Lm
= Lr
Lp
Where L stands for length and the subscripts m and p stand for model and prototype
respectively. The ratio of the two i.e. Lr is known as length ratio or linear model scale
564
MANUAL OF IRRIGATION PRACTICE
HYDRAULIC MODELING
such as 1/15 or 1/50 etc. depending upon the space and discharge available for the
model. Similarly, Area ratio is expressed as:
Am L2m
Ar = = = L2r
Ap L2p
Volume ratio,
Volm L3m
Volr = = = L3r
Vol p L3p
Kinematic similarity
Kinematic similarity implies that the ratio of the velocities at all corresponding points is
the same. It is expressed as:
𝑉
Vr=𝑉𝑃
𝑚
Its value in terms of scale ratio (Lr) will be determined by dynamic considerations as
explained in the subsection 1.2.2.2.
As time T is dimensionally L/V, the time scale is
Tr = Lr/Vr
𝐿𝑟
Similarly, acceleration is: 𝑎𝑟 = 𝑇 2
𝑟
Dynamic Similarity:
Dynamic similarity is similarity of forces. Forces that may act on a fluid element include:
Gravity FG= m g = 𝜌L2 𝑔
Pressure FP = (∆𝑝)𝐴 = (∆𝑝)𝐿2
𝑑𝑢 𝑉
Viscosity Fv = 𝜇 (𝑑𝑦 ) 𝐴 = 𝜇 (𝐿 ) 𝐿2 = 𝜇𝑉𝐿
Elasticity FE = 𝐸𝑉 𝐴 = 𝐸𝑉 𝐿2
Surface Tension FT = 𝜎𝐴
𝐿
Inertia FE = 𝑚𝑎 = 𝜌𝐿3 𝑇 2= 𝜌𝐿4 𝑇 −2 = 𝜌𝑉 2 𝐿2
Dynamic similarity will be achieved if following condition is satisfied and ratio of all
forces is equal i.e.,
𝐹𝐺 𝑝 𝐹𝑃𝑝 𝐹𝑉𝑝 𝐹𝐼𝑝
= = = (1.1)
𝐹𝐺 𝑚 𝐹𝑃𝑚 𝐹𝑉𝑚 𝐹𝐼𝑚
Fm Vm / gd m
Or = =1
Fp V p / gd p
Lm / Vm L
tr = = 1r
Lp / Vp
hr2
Distance
If acceleration is defined as;
Time2
am Lm / tm2 Lr Lr
Acceleration ratio = = = 2 = = 1 in case of geometric model.
a p Lp / t p2 tr Lr
L3
Discharge can be expressed as so that
t
5
Qm L3m / tm L3r
Discharge ratio Qr = = = 1 = Lr2 for geometric model.
Qp L3p / t p
Lr2
3
For distorted model as defined in section 1.2.3.1(b) Qr = LrYr2
Should the fluids in model and prototype be different, as can happen in special cases,
the term g would not be dropped as was done in deriving the velocity ratio because
in that case gm g p and g r would occur in each of the above expressions of Kinematic
similarity.
So Vr = ( yr g r )
t r = ( yr g r )
567
MANUAL OF IRRIGATION PRACTICE
HYDRAULIC MODELING
5 1
and Qr = yr 2 g r 2
w w
The density of any fluid is = then g =
g
w
if g is replaced by the above ratios would then read as
w 1 w 1 5
1 1
w 2
Vr = Lr ( ) 2 , Tr = Lr ( ) 2 , Qr = Lr 2 ( )
2
Thus for similarity in model and prototype, the Froude Law states that ratio of forces
on model & prototype will be proportional to each other.
Fm M m am
Fr = =
Fp M p a p
Or
Fm M m g m
Fr = =
Fp M p g p
Note that ' a ' has been replaced by ' g ' since acceleration in open channels is
produced by gravity. By assuming that the fluid in model and prototype is the same,
gm
=1
gp
Lm3 m
So mass ratio, M r = = L3r since m = p
Lp p
3
Similarly, other dynamic ratios can be obtained from those already developed. Since
Energy = Force x Distance
Fm Lm
Energy ratio Er = = L3r Lr = L4r
Fp LP
L 3 Lr Lr 4
7
Fm Lm / tm
Power ratio pr = = r = 1 = Lr in case of single scale model.
2
Fp Lp / t p tr
Lr 2
568
MANUAL OF IRRIGATION PRACTICE
HYDRAULIC MODELING
1 7
Fmtm
Ir = = Lr 3 Lr = Lr
2 2
Impulse ratio Fp t p
1 7
FmVm
Mr = = Lr 3 Lr = Lr
2 2
If impulse and momentum are equated, it will be found that they bear the same
dimensions
F t = M V
Or
MLt ML
Mat = 2
= = MV
t t
The above scale ratios are shown summarized in the following table for convenient
use.
Summary of Scale Ratios
Characteristics Dimension Scale ratio for
Froude law Reynold’s Law
(Geometric)
Length L Lr Lr
Area L2 Lr2 Lr2
Volume L3 Lr3 Lr3
Hydraulic Radius R Rr Lr
(Kinematic)
Time t Lr1/2 (L2 ρ/µ)r
Velocity L/t Lr1/2 (µ/Lρ)r
Acceleration L/t2 1:1 (µ2 ρ-2 L-3)r
Discharge (L µ/ρ)r
Channel Roughness L2/3/L1/2 Lr1/6
(Dynamic)
Mass L3 Lr3 (L3 ρ)r
Force L3 Lr3 (µ2/ρ)r
Energy FL Lr4 (L µ2/ρ)r
Power F L/t Lr7/2 (µ3 L-1ρ-2)r
Impulse and momentum F x t = MV Lr7/2 (L2µ)r
569
MANUAL OF IRRIGATION PRACTICE
HYDRAULIC MODELING
(s − 1) g
1/ 3
24
Coefficient of Drag, C D = + 1.5 Engelund and Hansen (1967)
Re
4
( s − 1) gd
And hence fall velocity s = 3
CD
Let
Vr = Scale Ratio for Velocity = Vm/Vp
Lr = Scale Ratio for Horizontal distance
Yr = Scale Ratio for vertical distances (depths)
Rr = Scale Ratio for Hydraulic Radius
dr = Scale Ratio for sediment size
ʋr = Scale Ratio for Kinematic viscosity = 1
gr = Scale Ratio for acceleration due to gravity = 1
1Refer to “Open Channel Hydraulics” by Terry W Sturm, Page 375 to 377, equations 10.4, 10.8, 10.9
and 10.10
570
MANUAL OF IRRIGATION PRACTICE
HYDRAULIC MODELING
2
Rr Yr d r
=1 (1)
Lr r
2
Lr
dr =
Rr Yr
gd
where α = s – 1
d is particle diameter
s is the specific gravity of the sediment particle
This results in
Rr Yr
=1 (2)
r Lr d r
Rr Yr
dr =
r Lr
Solving 1 and 2 simultaneously results in relation between r and dr
−1 / 3
dr = r (3)
Note: To satisfy both Equation (1) and (2), equation (3) must be fulfilled, otherwise
only one equation can be satisfied
Ratio of Shear Velocity to fall velocity
u*
=1
w r
which implies
wm = w p R r (4)
For simulation of sediment transport, equations (1) through (4) need to be satisfied.
Dynamic similarity for a movable-bed river model requires that conditions given by
Eqs. (1) to, (4), be satisfied. As in case of fixed bed models, all the conditions cannot
be satisfied. Thus, to simulate mobile bed models, following considerations are made:
(i) Review of Shields diagram show that influence of grain Reynold number
on initiation of motion is not significant for Re*>70. In practice, problems
of sediment transport in rivers mostly involve this range.
571
MANUAL OF IRRIGATION PRACTICE
HYDRAULIC MODELING
(ii) Equation 1 above can be ignored for such conditions. However for such
cases, sediment scaling shall be carried such that Re* in model is also
above 70 while fully satisfying conditions of Equation (2) above. This
results in following relationships
Yr2
dr = for distorted scale
r Lr
and
Lr
dr = for Geometric Scale Model
r
If same specific gravity sediment is used, then very small sediment size will be required
to be used in model, which will result in change in roughness characteristics as well
as type of sediment (cohesionless transport will be transformed to cohesive transport).
Therefore to truly represent the model, it is necessary that bed material be composed
of lighter weight material such as lignite, haydite and cornmeal.
In practice, procurement of lighter weight material is difficult and costly. Thus phyiscal
models are generally constructed of sand, which has nearly same specific gravity as
that in prototype. This implies that mobile bed models in such case can only be used
for qualitative judgement
1.2.3 Types of Physical Model
The main function of a hydraulic model is to produce a flow situation in the model
similar to that in the prototype. In order to reproduce the results of the prototype, the
model must be similar to the prototype. The research engineer would prefer the model
to be an exact replica of the prototype, have all relationships mathematically correct,
be of as big a size as possible to reduce error and have a bed material that would
move in the model similar to the bed material in the prototype. However, practical
limitations of available space, funds, time and the model bed material make this
impracticable in many model studies.
Therefore, special modelling techniques are required to accurately reproduce
prototype occurrences.
Physical Models are classified on following two basis:
(i) Classification based on Scale Representation
a. Geometric Scale Models
b. Distorted Scale Models
(ii) Classification based on Representation (Whole or part models)
a. Comprehensive Model
b. Sectional Model
A brief description of various types of physical models is given below:
572
MANUAL OF IRRIGATION PRACTICE
HYDRAULIC MODELING
such as Manning’s Equation, Chezy Equation, Standard Step Method for water
surface profile computation etc. In other words, a model is a system that will convert
a given input (geometry, boundary conditions, force, etc.) into an output (flow rates,
levels, pressures, etc.) to be used in civil engineering design and operation. Simulation
may be direct by the use of hydraulic models, semi-direct using analogues or
indirect by making use of theoretical and computer-based analysis, including
mathematical, computational and numerical models.
1.3.2 Categories of Modelling
There are two main categories of modeling techniques used in water resources field
which are explained here;
1) Hydrologic Modelling
2) Hydraulic Modelling
3) Groundwater Modelling
4) Crop Water / Irrigation Scheduling Models
5) Decision Support System Models
Hydrologic Model:
A hydrologic model is a simplification of a real-world system (e.g., surface water, soil
water, wetland, groundwater, estuary) that aids in understanding, predicting, and
managing water resources. Both the flow and quality of water are commonly studied
using hydrologic models. Hydrological models are divided into two categories; one is
physical models which involve physical representation of natural phenomena making
small scale physical models and second one is abstract models which represent
system in mathematical form with set of governing equations. Some of the commonly
used hydrological models include HEC-HMS, HEC-SSP, DHI Mike HYDRO, SWAT
etc.
a) Categories of Hydrological Models
Hydrological Models can be further categorized into following types of models:
• Black Box Models
• Lumped Models
• Semi-Distributed Models
• Distributed Models
Black Box models
Models describe mathematically the relation between variables (e.g. rainfall and
surface runoff) without describing the physical process by which they are related e.g.
unit hydrograph approach, Artificial Neural Network (ANN); Rational formula etc.
Below. Figure 4 is example of Black box.
Lumped Models
A Lumped model considers the whole catchment as a single unit. Hydrological
parameters are averaged for the watershed. For example, Slope elevation, soil type,
land cover and all other associated properties. Lumped parameters models don’t
explicitly take into account the spatial variability of inputs, output or parameters. They
577
MANUAL OF IRRIGATION PRACTICE
HYDRAULIC MODELING
take all the data for sub catchment and combine it into a single number or set of
numbers, that define the response of the basin to certain inputs. This model is not
suitable for spatial GIS database; however, GIS-based spatial parameters can be
lumped to run lumped parameter watershed models. Examples of Lumped Model are
the Stanford Watershed Model (SWM) and Hydrological Modeling System (HEC-
HMS) [2].
• MIKE SWMM
• Storm Water Management Model (SWMM)
• HEC-HMS and HEC-GeoHMS
• Soil and Water Assessment Tool (SWAT)
c) Data Requirements for Mathematical Models
The accuracy of the model result is highly dependent on the input data, before using
the data it is necessary to check the data source and accuracy. The designer must
compile the data that are specific to the subject site. Following are the major types of
data that may be required.
• Watershed characteristics
• Stream reach data (especially in the vicinity of the facility)
• Other physical data in the general vicinity of the facility such as utilities
or easements;
• Hydrologic and Meteorological data (stream flow and rainfall data
related to maximum or historical peaks as well as low flow discharges
and hydrographs applicable to the site)
• Existing and proposed landuse data in the subject drainage area and in
the general vicinity of the facility
• Anticipated changes in landuse and/or watershed characteristics
(MODIS Satellite)
• Grid based data (elevation, land use, water shed characteristics for
distributed / semi-distributed models)
d) Selection of Type of Model to be Used
Type of Model to be used is highly dependent on following factors:
(i) Available time for analyses
(ii) Quality of available data
(iii) Accuracy desired
(iv) Computational skill of modelling team
If available data is limited then black-box models or lumped models are better suited.
If distributed / semi-distributed models are used, then more detailed data is required,
which needs to be pre-processed before input into the model to ensure good quality
output.
e) Steps of Hydrologic Modelling
Various steps involved in hydrologic modelling are shown in Error! Reference source n
ot found.
Data Collection
Phase I Model Input Preparation
Parameter Evaluation
579
MANUAL OF IRRIGATION PRACTICE
HYDRAULIC MODELING
Model Calibration
Phase II Model Validation Model Testing
2 https://membersfloodplain.site-ym/resource/.../Comparison-and-Utilization-o.pdf
3 https://membersfloodplain.site-ym/resource/.../Comparison-and-Utilization-o.pdf
581
MANUAL OF IRRIGATION PRACTICE
HYDRAULIC MODELING
4 https://membersfloodplain.site-ym/resource/.../Comparison-and-Utilization-o.pdf
582
MANUAL OF IRRIGATION PRACTICE
HYDRAULIC MODELING
most effective when interactive, graphical software is available to view the results and
make parameter changes. The calibration is finished when the user subjectively
determines that the objectives have been met
The second method is automated calibration, in this method various computer
algorithms are used to achieve the best simulated reproduction of observed values,
typically mean daily discharge. The algorithms contain strategies for varying the values
of user specified parameters in an attempt to obtain an optimal fit. Typically the user
can apply limits on the range over which parameter values can vary in the hope of
obtaining more physically realistic results. The quality of the reproduction is often
determined by a single statistical objective function, such as minimizing the daily root
mean square error. Sometimes a series of steps are used where different groups of
parameters and different objective functions are used at each step (e.g. the objective
function used for parameters affecting low flows may differ from the function used for
parameters that primarily control storm runoff). In some approaches multiple objective
functions are used to try to find a group of parameters sets that will produce good
results based on several criteria. Then the user can choose subjectively from this
group of parameter sets. Automatic optimization has been primarily used for the
calibration of individual watersheds, mainly headwater drainages. There are limited
strategies available for using automated optimization over entire river basins.
Model Validation
The ultimate goal of modeling is to make prediction for periods or situations
where there is no available data and only by the use of model, one can gain
information about them. Hence, the calibrated model in previous stage is tested on
another set of data (known as validation data) to test goodness of fit. If the results are
acceptable, the model calibration is said to be validated. If results are not acceptable,
then the calibrated parameters are modified suitably so that both calibration results
and re-validation results are within acceptable range.
It may be noted that this step, which is very critical, is mostly omitted due to lack of
validation data. However, maximum effort should be made that model can be validated
on at least one additional set of data to achieve better and more reliable results.
1.3.4 Performance Evaluation Criteria of Mathematical Models
A sensitivity analysis is a technique used to determine how different values of an
independent variable impact a particular dependent variable under a given set of
assumptions. Every model consists of different parameters. A sensitivity analysis is
performed to check which parameter is most sensitive. A little / minor change in value
of most sensitive parameters have a significant effect on the output /results of model.
From a scientific or practical point of view, the application of mathematical models
aims to reproduce measurements with acceptable accuracy (Seibert, 2001). Various
statistical tools are utilized in order to assess a model’s quantitative performance
(Moriasi et al., 2007). Quantitative assessment of the models’ prediction accuracies is
done by calculating root mean square error (RMSE) (Deshmukh et al., 2013), Nash–
584
MANUAL OF IRRIGATION PRACTICE
HYDRAULIC MODELING
Sutcliffe efficiency (NSE) (Nash and Sutcliffe, 1970), and percent bias (PBIAS)
(Moriasi et al., 2007). Mathematically, these performance evaluation indicators are
respectively expressed as follows:
Where Qcomp and Qobs are the computed / predicted and observed runoff values for
storms events, respectively. Qobs is the mean of the observed runoff values from a
watershed.
RMSE is widely used as a goodness-of-fit indicator that describes the difference
between the observed and predicted values in the same units. Smaller RMSE values
(optimum = 0.0, perfect fit) describe a better model runoff prediction.
In addition, the NSE is widely used for efficiency determination of hydrologic models
ranging from -1 to 1.0 (optimum = 1.0, perfect fit). A model is judged to be satisfactory
with NSE > 0.50 (Moriasi et al., 2007). Ritter and Muñoz-Carpena (2013) established
a hydrologic model performance rating where NSE < 0.65 (unsatisfactory) was
deemed a lower threshold. Other model performance ratings were acceptable (0.65 ≤
NSE < 0.80), good (0.80 ≤ NSE < 0.90), and very good (NSE ≥ 0.90).
Similarly, the PBIAS quantifies a model’s tendency to underestimate or overestimate
values, where a value of zero (optimum) shows perfect fit. A performance rating based
on PBIAS can be found in Moriasi et al. (2007). Positive (negative) bias results indicate
model underestimation (overestimation). These quantitative evaluations were
reinforced by visually evaluating the model performance in comparison to the
combined observed and estimated runoff values through scatter plots.
1.3.5 General Description of Some Models5
General brief introduction of some models used in research institutes and by
professionals is descried below;
a) MIKE-SHE
The purpose of MIKE SHE is the simulation of coupled hydrologic processes with
emphasis on surface water, groundwater interactions, channel flow, unsaturated zone
flow and groundwater flow. It is Physically based, distributed and integrated hydrologic
modeling system.
5 http://hydrologicmodels.tamu.edu/models.htm
585
MANUAL OF IRRIGATION PRACTICE
HYDRAULIC MODELING
b) HEC-HMS
The program began as an event-oriented, precipitation-runoff simulator for surface
water hydrology studies. It now includes evapotranspiration, snowmelt, and infiltration
models for continuous simulation studies. It is increasingly becoming a land surface
process simulator operating for event and continuous time periods. The program is
designed to simulate the land surface processes of the hydrologic cycle.
Consequently, it contains components for precipitation, potential evapotranspiration,
snowmelt, canopy interception, surface storage, infiltration, surface runoff, baseflow,
channel routing, and channel losses. It also includes components for simulating
reservoirs and diversions. It is intended to be used singly or in combination with other
HEC software for studies of water availability, urban drainage, flow forecasting,
environmental enhancement, future urbanization impact, reservoir spillway design,
flood damage reduction, floodplain regulation, and system operation.
c) HEC-RAS
HEC-RAS is an integrated system of software, designed for interactive use in a multi-
tasking environment. HEC-RAS is designed to perform one dimensional hydraulic
calculation for a full network of natural and constructed channels. It contains four one
dimensional river analysis components for: (1) steady flow water surface profile
computations; (2) unsteady flow simulation; (3) movable boundary sediment transport
computations; and (4) water quality analysis. A key element is that all four components
use a common geometric data representation and common geometric and hydraulic
computation routines.
d) DHI Mike-11
MIKE 11 is a professional engineering software package for the simulation of flows,
water quality, and sediment transport in estuaries, rivers, irrigation systems, channels
and other water bodies. MIKE 11 is a fully dynamic, user-friendly, one-dimensional
modelling tool for the detailed design, management and operation of both simple and
complex river and channel systems. Due to its exceptional flexibility and speed, MIKE
11 provides a complete and effective design environment for engineering, water
resources, water quality management and planning applications. MIKE 11 utilizes a
fully Windows integrated Graphical User Interface.
e) DHI Mike Basin
MIKE BASIN is a general multi-purpose river network model for river basin
management and planning. The purpose of MIKE BASIN is the simulation of natural
inflows, multiple multipurpose reservoir operation and water right allocation in river
basins based on a prioritized water accounting procedure. It allows for conjunctive use
of surface water and ground water. An extension to the basic module includes water
quality simulation based on point and non-point sources.
f) Integrated Water Flow Model (IFWM)
IWFM is a water resources management and planning model that simulates
groundwater, surface water, stream-groundwater interaction, and other components
586
MANUAL OF IRRIGATION PRACTICE
HYDRAULIC MODELING
acres by the side of Upper Chenab Canal (UCC) where a gravity fall of 15’ to 20’ft is
available. About 1/4th of the station area is occupied by the colony and offices for the
staff in the South - West corner of the station and the remaining 3/4 of the area is
divided in twenty-two experimental trays of various sizes. The triangular area
consisting of 6 trays is fed by 75 cusecs supply channel running parallel to UCC while
the escape/disposal channel of this portion lies along the Sialkot - Gujranwala Road
and then after crossing the road runs parallel to UCC till it goes out of the station after
passing under the Kamoki Distributary to join the escape/disposal channel of the
trapezoidal area in the South of the station. Leaving the South - West corner for the
colony and offices, the remaining big rectangle divided in 16 trays is bifurcated by the
main escape channel running through it. The two high level supply channels carrying
225 cusec and 200 cusec discharge run along three sides of the big rectangle to supply
gravity flow to be disposed off through the bifurcating escape channel after use for
experiments. Escape channels of both the areas join together at the East of the Station
to carry the total discharge back to the Upper Chenab Canal below the power house
constructed on the parent canal half a mile below (Error! Reference source not found.).
In addition to gravity flow, there are two pump houses at the station with self-circulation
system which can be used if gravity flow is not available for a short period in winter
when UCC is closed for annual inspection. One pumping system with 14 pumps
capable of lifting about 50-60 cusec discharge is equipped with 25 feet high reinforced
concrete tank for testing of models of high head structures of tunnels and spillways on
as large a scale as 1/18.
Nandipur
flumes is about 8 feet high to house sectional models of high head structures of low
dams. The glass flumes are fitted with mobile over-head trollies for observations of
water levels and velocities at different points along the flumes.
A number of trays are provided with sheds, some of which are 100'x100' to house and
protect the perspex models from direct heat of sun and direct cold of night to keep the
difference of temperature of perspex models as low as possible so that perspex
models do not get cracked.
The station is also provided with a field workshop consisting of machine shop, smithy
and carpenter shop. The machine shop is equipped with lathe machines, shaper
machines, drilling machines, cutters and grinders. The carpenter shop is equipped
with Benson Saw machine, round Saw machine and planer whereas the smithy shop
is equipped with cutting machine, oven and drilling machines. Moreover an electric
oven is also available in workshop which is capable of heating perspex sheets of 4’x8’
size to mould perspex models.
All the fabrication work of bridges for models, gates of model spillways and other
structures required for model construction is done in this local workshop.
A silt laboratory exists at the station. The laboratory is equipped with all necessary
implements like graduated cylinders, flasks, sieve meshes and visual accumulation
tubes to make analysis of silt/sand used in the experiments. The concentration of
suspended silt can also be determined, if required, from the water complex samples
taken from certain models.
The Institute is now catering to the needs of all the provinces of the country and the
Federal Government in all the departments such as Buildings, WAPDA, Highway,
Irrigation, NHA & Railways etc. There is no major flood protection work or a major
hydraulic structure such as highway bridge, railway bridge, or a barrage across one of
the rivers, the basic design and layout feature of which have not been worked out
through model testing in the Institute. Moreover, technique of protection against river
erosion which is common feature on controlled rivers have been developed and
different geometries of spurs have been tested and modified with the result that
geometries for highly efficient and effective spurs have now been evolved which are
used to train the rivers wherever necessity arises.
A photographic laboratory manned by a photographer and dark room assistant is set
up at the premises of the station for documentation of model data. The laboratory is
equipped with Rolliflex Camera and wide-Angle camera to take still photographs to
show current directions in models during operation. Movie camera and V.C.R. facility
is also available to prepare movies of important model studies.
IRI has now also purchased computer software (Flow 3D) and has initiated training of
its staff members to enable use of the model in future.
589
MANUAL OF IRRIGATION PRACTICE
HYDRAULIC MODELING
1.6. Estimating Historical and Replacement Costs of PID Assets .................................. 596
condition of assets. In order to establish the physical condition of the assets the rating
of each asset was carried out by the concerned staff of various IPD Zones on a scale
of 1 to 5, as per following definitions.
Rating Condition
5 Practically new
4 Generally good with no damage, only routine
maintenance required.
3 Generally good but with some deterioration or
damage. Need attention.
2 Significantly damaged or deteriorated. Suffering
from deferred maintenance. Needs urgent
rehabilitation.
1 Very poor and dilapidated condition requiring
partial restoration or complete replacement.
Replacement cost of asset was full amount needed to acquire such an asset and not
necessarily replicating the present designs. Precise calculations of the costs of the
entire infrastructure of PID, however, could not be made nor were these needed. The
estimates of gross value of the assets were based on review of cost data of other
projects which had been completed or were in planning or construction stage at that
time. In some cases where comparable data was not available preliminary estimate of
cost were prepared for the replacement of an existing asset. The assets of PID were
estimated to have an overall replacement value of Rs. 1,170,311 Million 1 (about US $
19,505 million2).
Rehabilitation and Upgrading (R&U) costs were based on the existing physical
condition of infrastructure and keeping in view the policy adopted by PID about
preparing rehabilitation plans, the estimates of rehabilitation works were prepared.
Maintenance and Repairs (M&R) costs: Periodic maintenance and repairs of the
infrastructure are carried out through maintenance funds allocated for each
component based on approved yardsticks which are mainly based on general
parameters for yearly maintenance and operational features. The system of yardsticks
was used for equitable distribution of funds for different components of irrigation and
drainage networks, etc.
Supervision and Administration costs were the emoluments of sanctioned staff
strength of 48,503 (1,072 officers BS 16 to 20 and 47,431 other staff in BS 1 to 15) in
FY 2005-06.
In March 2007, after working for about one and half years completing activities of the
six stages mentioned in section 28.2 which generated the above information, an APM
was prepared by PID. This APM provided the estimated costs of yearly M&R,
rehabilitation and upgrading costs for the ten year period 2007-17 along with its
1 Based on 2005 prices
2 Based on conversion rate of one US$=PKR 60, applicable in 2005
595
MANUAL OF IRRIGATION PRACTICE
ASSET MANAGEMENT PLAN
phasing on the basis of FY 2006-7 MRS rates. The soft copy of this AMP, along with
its Annex 1 and Annex 2, is available in Strategic Planning/Reform Unit (SPRU)
located in the Irrigation Secretariat, Lahore. For producing these two annexes several
hundred interlinked MS Excel worksheets were prepared using the information
supplied by offices of zonal chief engineers, which are also available in SPRU.
Since an APM is a living document it should be periodically revised/updated,
preferably yearly with the data to be provided by offices of zonal chief engineers. The
maximum interval between two consecutive APMs should not exceed three years.
1.4. Steps Involved in Revising/Updating or Preparing Fresh AMP
To an extent the process, employed for preparing the original AMP, has to be repeated
to update the information required for the preparation of the revised/updated or fresh
AMP. It will involve: (a) confirmation/verification of the inventory prepared in year 2005;
(b) revising historical and replacement costs of PID assets; (c) estimating maintenance
and repairs (M&R) costs and preparing M&R plan; and (d) estimating rehabilitation
and upgrading (R&U) costs and preparing R&U plan.
Confirmation/verification of the existing inventory is needed to account for the
reduction in CCA due to urbanization of the cultivable land. The exercise is required
to take care of any additions and deletion to the assets so that a revised/updated or a
fresh AMP can be prepared accurately.
Rehabilitation and upgrading (R&U) costs required for revising/updating will be based
on the condition survey of the infrastructure which will be carried out by the offices of
chief engineers. Physical condition will be rated 1-5 (non-functional to proper working
order) during the condition survey exercise. Rehabilitation and upgrading (R&U) costs
will be computed in accordance with the applicable policy of PID.
In order to estimate maintenance and repair (M&R) costs, O&M yardsticks based on
prevailing MRS will be needed. The O&M yardsticks for each zone were prepared in
year 2007 using the respective criteria of O&M for each zone. These yardsticks were
prepared using interlinked MS Excel worksheets so that changing the prices of labour
and materials would automatically change the values in the yardsticks. The soft copies
of these Excel worksheets are available in SPRU located in the irrigation secretariat.
Supervision and Administration costs are the emoluments of sanctioned staff strength
of officers BS 16 to 20 and other staff in BS 1 to 15.
1.5. Confirmation/Verification of Inventory of PID Assets
The inventory prepared in 2005 is available in SPRU in the irrigation secretariat. For
its confirmation/verification, the field staff working with the zonal chief engineers will
revise the existing inventory by physical check noting additions and deletions in the
assets. Each office of the zonal chief engineer will also carry out condition survey using
the rating 1-5 (non-functional to proper working order).
596
MANUAL OF IRRIGATION PRACTICE
ASSET MANAGEMENT PLAN
items involved in the construction of these categories of canal. For the structures of
the canals such as falls, bridges, aqueducts, syphons, etc. similar approach will be
adopted as used for barrages. For computing the replacement cost of different types
of structures on the basis of similar structures constructed in the near past will be used
as a reference structure. Per unit discharge cost will be worked out for different types
of structures, which will be applied to each structure according to their discharge
capacity. The rates will be worked out for one Km length of the respective channels.
In the 2005 exercise, the quantities required for constructing Awagat Distributary. Khiki
Distributary, Mianwali Distributary, Rakh Branch, Lower Gugera Branch, Upper
Gugera Branch and Q.B. Link constructed in the past were considered. The prevalent
market rates were applied for the items involved in the construction of these channels.
For the structures of the canals such as Falls, Bridges, Aqueducts, Syphons, etc. same
criteria was adopted as was used for barrages for computing the replacement cost of
different types of structures on the basis of similar structures constructed in the near
past i.e. structures constructed on Burala Branch in Faisalabad Irrigation Zone.
Drains: The replacement cost of the drains will be worked out by estimating the earth
work involved in branch drain and main drain and applying market rates to the
quantities involved in the excavation of new drains. The same unit costs of land and
earthwork will be applied as those used for canals. The average cost of drains with
different bed widths will be estimated for 1 km length. The cost of structures will be
taken from the different structures constructed on a reference drain. The cost for 1 foot
of bed width of the sample drain will be computed and applied to all the structures
involved in the inventory.
In the 2005 exercise, the replacement cost of the drains was worked out by estimating
the earth work involved in Nasrana Branch Drain and Khairwala Main Drain and
applying market rates to the quantities involved in the excavation of these drains. The
same unit costs of land and earthwork were applied as were used for canals. The
average cost of drains with different bed widths was estimated for 1 km length. The
cost of structures was taken from the cost of different structures constructed on
Fatehpur Branch Drain having 8 feet bed width. The cost for 1 foot width was computed
and applied to all the structures involved in the inventory. The replacement cost of
subsurface drains was estimated using a unit rate of Rs 50,000/ha.
Small dams: A group of small dams of various heights will be selected and their costs
will be calculated by estimating quantities involved in their main structures and
ancillary works (including their command water works maintained by PID), multiplied
with the prevailing market rates of items of works used in the construction of these
small dams. The average cost of these small dams will be multiplied with the existing
number of small dams owned by PID.
Embankments, spurs, etc.: The replacement cost of embankments will be
established on the basis of average cost of embankments with one spur for 1 mile.
The earth work required for 15 feet height embankment will be computed for
determining the quantity per 1 mile. The prevalent market rates will be applied for the
quantities involved in the construction of embankment.
598
MANUAL OF IRRIGATION PRACTICE
ASSET MANAGEMENT PLAN
Buildings: The cost of the buildings will be computed according to the categories of
the buildings on the basis of the unit rates of covered area. The unit rates will be based
on the market rates.
Land: PID owns lands in all districts of Punjab. The details of available land with the
Department will be collected from field formation/Divisions. The rates for lands will be
obtained from the concerned district revenue officer through canal collectors of zones.
The cost of land owned by PID in various districts will be estimated using average
market rates.
Miscellaneous assets: The costs of other assets such as tubewells, workshops,
machinery and vehicles etc. will also be estimated using basic criteria of replacing
them on the basis of prevailing market rates.
Alternative methods for estimating historical and replacement costs of PID assets:
There can be alternative methods for estimating historical and replacement costs of
assets in case that the historical and replacement costs of assets have previously
been established. These alternative methods could be using the price indexing, etc.
In year 2005, an exercise for estimating historical and replacement costs of PID assets
was done. It will be easier to establish updated replacement costs by using appropriate
price indices of PID assets established previously. Of course the updated inventory
taking into account additions and deletions in the assets will be taken into account.
1.7. Estimating Rehabilitation Costs (Deferred Maintenance) of Assets
1.7.1. Cause of Rehabilitation Need:
Main reason for rehabilitating irrigation and drainage assets is the deferred
maintenance which accumulates over the years for various reasons. Primary reason
for deferred maintenance is perpetually inadequate annual budgeting particularly for
maintenance (M&R) by PID.
Furthermore, due to fiscal constraints the allocations by PID is generally made on
budget precedence of the previous years without regard to ground conditions or
requirement of increased costs due to inflation. Further the actual releases depend
upon the availability of funds and seldom match the realistic requirements. As a result,
the M&R needs are not normally met as envisaged in annual yardstick. This causes
accumulation of maintenance works over the years.
1.7.2. Cause of Rehabilitation Need
Barrages are the gated structures across rivers, built to affect better control and
command for the off-taking canals. They play a pivotal role in providing sustained
water supplies to millions of hectares of irrigated lands in the Province. They also
control diversion of water to the inter-river link canals that serve command areas
previously commanded by the eastern rivers allocated to India under the Indus Waters
Treaty. Thus, the barrages are important hydraulic structures, which are essential to
sustain irrigated agriculture.
599
MANUAL OF IRRIGATION PRACTICE
ASSET MANAGEMENT PLAN
Periodic inspections of the barrages will be made to assess the need of rehabilitation
work (maximum interval between two consecutive inspections should not exceed three
years). The periodic inspections of the barrages will be carried out by a group of field
staff headed by the concerned chief engineer. The group inspecting the barrages will
keep in view PID’s policy for rehabilitation of barrages as is presented below.
➢ Assured capacity to pass the highest expected flow estimated on the
basis of stream of flow data and computed using internationally accepted
formulae, preferably without resorting to use of breaching sections;
➢ Safety of the main weir structure under the expected maximum loading
condition;
➢ Instrumentation to facilitate monitoring of the safety of the main and
appurtenant structures
➢ Assure credibility of flood protection works (guide bunds, marginal
bunds, spurs, etc.); and
➢ Improvement in gates and gearing system for efficient regulation, where
needed.
The recommendations/suggestions given in the report of inspecting group will be
considered for determining rehabilitation works (deferred maintenance), and those will
be costed to form basis of rehabilitation plan of barrages. The rehabilitation work will
be prioritized and the rehabilitation plan will include the phasing accordingly.
Canal Systems deteriorate due to utilization beyond designed capacities, tampering
control structures, damage to canal banks caused by human and cattle trespassing
and inadequate routine and preventive maintenance. Beside the deterioration of
conveyance channels a large number of major structures on the canals will need major
repairs due to aging and long neglect. Therefore, the rehabilitation needs will also
cover besides the rehabilitation of canal systems, systematic replacement of old
structures, adopting new practices and technology besides meeting other needs of the
system.
Periodic inspections (maximum interval between two consecutive inspections should
not exceed three years) of the canal systems will be made to assess the need of
rehabilitation work. The periodic inspections of the main and branch canals by a
groups of field staff headed by the concerned superintending engineer in the case of
main and branch canals, and the concerned executive engineer in case of the
distrbutary and minor channels. The groups inspecting the canal systems will keep in
view PID’s policy for rehabilitating and upgrading canal systems as is presented below.
➢ Restore canal prisms to the original or revised parameters (by observing
performance data of canal, reviewing it and revising L-Section, if
needed) in order to pass authorized discharge of the canal;
➢ Rehabilitate hydraulic structures on the canal that can be retained for
long service periods merely restoring those by carrying out repairs and
maintenance;
➢ Reconstruct/replace those structures that have deteriorated to an extent
that those are unsafe and/or cannot adequately cope with the present
600
MANUAL OF IRRIGATION PRACTICE
ASSET MANAGEMENT PLAN
➢ Revisit the need of inlet structures and augment the existing inlets, as
required; and
➢ Restore fixtures i.e. RD Markers, Barrier Gates on patrol roads, ROW
markers etc.
The recommendations/suggestions given in the report of inspecting groups will be
considered for determining rehabilitation works (deferred maintenance), and those will
be costed to form basis of rehabilitation plan of drainage systems. The rehabilitation
work will be prioritized and the rehabilitation plan will include the phasing accordingly.
Accordingly, rehabilitation and upgradation of drainage systems will include weed and
debris clearance; bed clearance; maintenance of banks inlets, bridges, outfalls and
other structures; and monitoring the drain flows to evaluate its effectiveness and
identify the need to remodel.
Flood Embankments and Spurs are damaged due to very sharp flood peaks on
account of intense monsoon rainstorms in the upper river catchments. The
construction of flood protection works, viz. flood embankments, spurs, studs, etc. has
been carried out to protect irrigation infrastructures and to safeguard agricultural lands,
cities, towns and villages from the onslaught of floods.
Since the sizeable part of the flood protection infrastructure is associated with the
barrage structures, periodic inspections of the barrages will determine the need of
rehabilitation work for this part the infrastructure.
PID’s policy in respect of flood protection embankments and spurs is that these are
inspected before the advent of flood season every year for assessing their reliability
to withstand flood onslaught. Their deficiencies are removed prior to flood season and
flood fighting plan is prepared annually. As such in ideal conditions there should not
exist any deferred maintenance requiring rehabilitation of this type of the infrastructure.
Small dams exist in rainfed (barani) areas of the Pothohar Plateau in the Punjab
Province. The rehabilitation works for dams may consist of repairs/restoration of of
slopes embankment slopes, filter, catch water drains, spillway channel protection,
riprap and retaining walls etc. The works for channel mainly includes
repairs/restoration of existing channels lining, spillway, aqueducts, extension of
channel, replacement of pipes, and repairing/providing cross-drainage works.
Periodic inspections (maximum interval between two consecutive inspections should
not exceed three years) of the small dams will be made to assess the need of
rehabilitation works. The periodic inspections of small dams will be made by the
concerned field staff who is responsible for their maintenance and repairs. They should
follow PID’s policy in respect of dam safety.
The observations of the concerned field staff will be considered for determining
rehabilitation works (deferred maintenance), and those will be costed to form basis of
rehabilitation plan of small dams. The rehabilitation work will be prioritized and the
rehabilitation plan will include the phasing accordingly.
602
MANUAL OF IRRIGATION PRACTICE
ASSET MANAGEMENT PLAN
Tubewells which pump out only saline ground water will be rehabilitated. The
rehabilitation works will include re-boring, changing strainers/filters, replacing pumping
machinery, renovating pump house, etc.
Buildings were constructed during the construction and development of irrigation
systems in the Punjab Province. There are four types of building in PID: (i) Office
Buildings; (ii) Residential Buildings; (iii) Rest Houses; and (iv) Other Buildings. Most
of the building are old and need major renovation/reconstruction.
1.8. Operational Expenditure (OPEX)
The Operational Expenditure (OPEX) includes the following costs:
➢ Maintenance and Repair (M&R) Costs; and
➢ Supervision and Administration Costs.
1.8.1. Nature of M&R Works:
M&R works for any irrigation and drainage asset may involve any one or more of the
following three activities: (i) preventive maintenance; (ii) repair works; and (iii)
replacement of parts of and/or complete facility.
Preventive Maintenance works required to avoid unnecessary deterioration of an
asset other than normal wear and tear such as, painting gates of hydraulic structures
in an irrigation and drainage system, oiling moving parts of gates and gearing, cleaning
and painting walls of the buildings, repairing “gharas” in the earthen embankment of a
canal or a drain or a flood embankment, etc.
Repair-works involve removal of defects that may occur due to improper use or by
accident or otherwise, which if not repaired may endanger safe use of the asset and
can become cause of its complete destruction. Includes making up of worn out earthen
embankments to the designed dimensions, and desilting of the channels as well as
the repairing embayment etc.
Replacement of parts of and/or complete facility may involve replacement of a
spare part that might have worn out, replacement/reconstruction of a facility that might
have spent its useful life or damaged to an extent that it cannot be beneficially used.
In order to carry out durable M&R works of required quality, periodic inspections
should be undertaken to determine the M&R needs of major structures, such as
barrages, large hydraulic structures, main canals and large flood control facilities.
1.8.2. M&R Costs
The periodic maintenance and repairs of the infrastructure are carried out through
maintenance funds allocated for each component based on approved yardstick which
is mainly based on general parameters for yearly maintenance and operational
features. The system of yardsticks is used for equitable distribution of funds for
different components of irrigation network.
603
MANUAL OF IRRIGATION PRACTICE
ASSET MANAGEMENT PLAN
Phasing of Work
Total
FY 2007-08 FY 2008-09 FY 2009-10 FY 2010-11 FY 2011-12 FY 2012-13 FY 2013-14 FY 2014-15 FY 2015-16 FY 2016-17
FY 2007-17
Multip. Yearly M&R
ApprovedYa
Length FSD C.C.A/ C.A Factor Programas
Sr. No. IMIS CODE Description rdstick 2005 Multip-Factor Multip-Factor Multip-Factor Multip-Factor Multip-Factor Multip-Factor Multip-Factor Multip-Factor Multip-Factor Multip-Factor Remarks
(RD) (Cusecs) (1000 AC) Yardstick per 2005
(Rs./Mile) to bring to bring to bring to bring to bring to bring to bring to bring to bring to bring
2005 Level Yardstick Cost Cost Cost Cost Cost Cost Cost Cost Cost Cost Cost
yardstick yardstick yardstick yardstick yardstick yardstick yardstick yardstick yardstick yardstick
(M.Rs) (M.Rs) (M.Rs) (M.Rs) (M.Rs) (M.Rs) (M.Rs) (M.Rs) (M.Rs) (M.Rs) (M.Rs)
2005 to 2007 2005 to 2008 2005 to 2009 2005 to 2010 2005 to 2011 2005 to 2012 2005 to 2013 2005 to 2014 2005 to 2015 2005 to 2016
Level Level Level Level Level Level Level Level Level Level
(iii) Kot Sujana Minor M 23 14 3 23,000 1.000 0.106 1.100 0.116 1.100 0.116 1.100 0.116 1.100 0.116 1.100 0.116 1.100 0.116 1.100 0.116 1.100 0.116 1.100 0.116 1.100 0.116 1.164
(iv ) Chandhar Minor M 25 25 6 23,000 1.000 0.115 1.100 0.127 1.100 0.127 1.100 0.127 1.100 0.127 1.100 0.127 1.100 0.127 1.100 0.127 1.100 0.127 1.100 0.127 1.100 0.127 1.265
4 Pathanke Disty D 58 48 15 23,000 1.000 0.267 1.100 0.293 1.100 0.293 1.100 0.293 1.100 0.293 1.100 0.293 1.100 0.293 1.100 0.293 1.100 0.293 1.100 0.293 1.100 0.293 2.935
ASSET MANAGEMENT PLAN
5 Warpal Disty D 104 128 28 23,000 1.000 0.478 1.100 0.526 1.100 0.526 1.100 0.526 1.100 0.526 1.100 0.526 1.100 0.526 1.100 0.526 1.100 0.526 1.100 0.526 1.100 0.526 5.262
(i) Wazirke Minor M 25 17 5 23,000 1.000 0.115 1.100 0.127 1.100 0.127 1.100 0.127 1.100 0.127 1.100 0.127 1.100 0.127 1.100 0.127 1.100 0.127 1.100 0.127 1.100 0.127 1.265
(ii) Bucha Minor M 19 22 2 23,000 1.000 0.087 1.100 0.096 1.100 0.096 1.100 0.096 1.100 0.096 1.100 0.096 1.100 0.096 1.100 0.096 1.100 0.096 1.100 0.096 1.100 0.096 0.961
Total Nokhar Branch 180 4.408 4.849 4.849 4.849 4.849 4.849 4.849 4.849 4.849 4.849 4.849 48.486
Total Main Line Upper 180 6.057 6.663 6.663 6.663 6.663 6.663 6.663 6.663 6.663 6.663 6.663 66.627
Main Line Lower (UCC) MC 283 11375 - 62,000 1.000 3.509 1.100 3.860 1.100 3.860 1.100 3.860 1.100 3.860 1.100 3.860 1.100 3.860 1.100 3.860 1.100 3.860 1.100 3.860 1.100 3.860 38.601
1 Talwandi Disty D 52 76 13 23,000 1.000 0.239 1.100 0.263 1.100 0.263 1.100 0.263 1.100 0.263 1.100 0.263 1.100 0.263 1.100 0.263 1.100 0.263 1.100 0.263 1.100 0.263 2.631
(i) Trigri Minor M 39 29 7 23,000 1.000 0.179 1.100 0.197 1.100 0.197 1.100 0.197 1.100 0.197 1.100 0.197 1.100 0.197 1.100 0.197 1.100 0.197 1.100 0.197 1.100 0.197 1.973
2 Nurpur Disty D 182 436 38 23,000 1.000 0.837 1.100 0.921 1.100 0.921 1.100 0.921 1.100 0.921 1.100 0.921 1.100 0.921 1.100 0.921 1.100 0.921 1.100 0.921 1.100 0.921 9.209
(i) Ruriala Minor M 36 19 6 23,000 1.000 0.166 1.100 0.182 1.100 0.182 1.100 0.182 1.100 0.182 1.100 0.182 1.100 0.182 1.100 0.182 1.100 0.182 1.100 0.182 1.100 0.182 1.822
(ii) Qila Mian Singh Minor M 81 52 12 23,000 1.000 0.373 1.100 0.410 1.100 0.410 1.100 0.410 1.100 0.410 1.100 0.410 1.100 0.410 1.100 0.410 1.100 0.410 1.100 0.410 1.100 0.410 4.099
(iii) Ladhewala Sub Minor SM 38 13 4 23,000 1.000 0.175 1.100 0.192 1.100 0.192 1.100 0.192 1.100 0.192 1.100 0.192 1.100 0.192 1.100 0.192 1.100 0.192 1.100 0.192 1.100 0.192 1.923
(iv) Dhariwal Sub Minor SM 5 5 1 23,000 1.000 0.023 1.100 0.025 1.100 0.025 1.100 0.025 1.100 0.025 1.100 0.025 1.100 0.025 1.100 0.025 1.100 0.025 1.100 0.025 1.100 0.025 0.253
(v) Gobindpura Minor M 74 76 22 23,000 1.000 0.340 1.100 0.374 1.100 0.374 1.100 0.374 1.100 0.374 1.100 0.374 1.100 0.374 1.100 0.374 1.100 0.374 1.100 0.374 1.100 0.374 3.744
(vi) Musa Sub Minor SM 24 10 3 23,000 1.000 0.110 1.100 0.121 1.100 0.121 1.100 0.121 1.100 0.121 1.100 0.121 1.100 0.121 1.100 0.121 1.100 0.121 1.100 0.121 1.100 0.121 1.214
(vii) Argan Minor M 79 96 31 23,000 1.000 0.363 1.100 0.400 1.100 0.400 1.100 0.400 1.100 0.400 1.100 0.400 1.100 0.400 1.100 0.400 1.100 0.400 1.100 0.400 1.100 0.400 3.997
(vii) Jhar Minor M 49 35 11 23,000 1.000 0.225 1.100 0.248 1.100 0.248 1.100 0.248 1.100 0.248 1.100 0.248 1.100 0.248 1.100 0.248 1.100 0.248 1.100 0.248 1.100 0.248 2.479
3 Kamoke Disty D 154 231 30 23,000 1.000 0.708 1.100 0.779 1.100 0.779 1.100 0.779 1.100 0.779 1.100 0.779 1.100 0.779 1.100 0.779 1.100 0.779 1.100 0.779 1.100 0.779 7.792
(i) Abdal Minor M 13 7 2 23,000 1.000 0.060 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 0.658
(ii) Ferozewala Minor M 12 10 3 23,000 1.000 0.055 1.100 0.061 1.100 0.061 1.100 0.061 1.100 0.061 1.100 0.061 1.100 0.061 1.100 0.061 1.100 0.061 1.100 0.061 1.100 0.061 0.607
(iii) Machike Minor M 38 30 7 23,000 1.000 0.175 1.100 0.192 1.100 0.192 1.100 0.192 1.100 0.192 1.100 0.192 1.100 0.192 1.100 0.192 1.100 0.192 1.100 0.192 1.100 0.192 1.923
(iv) Eminabad Minor M 43 38 10 23,000 1.000 0.198 1.100 0.218 1.100 0.218 1.100 0.218 1.100 0.218 1.100 0.218 1.100 0.218 1.100 0.218 1.100 0.218 1.100 0.218 1.100 0.218 2.176
(v) Toleke Minor M 13 7 2 23,000 1.000 0.060 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 0.658
4 Nandipur Feeder F 29 52 0 23,000 1.000 0.133 1.100 0.147 1.100 0.147 1.100 0.147 1.100 0.147 1.100 0.147 1.100 0.147 1.100 0.147 1.100 0.147 1.100 0.147 1.100 0.147 1.467
5 Mehlowala Disty D 49 48 8 23,000 1.000 0.225 1.100 0.248 1.100 0.248 1.100 0.248 1.100 0.248 1.100 0.248 1.100 0.248 1.100 0.248 1.100 0.248 1.100 0.248 1.100 0.248 2.479
(i) Attawa Minor M 35 21 5 23,000 1.000 0.161 1.100 0.177 1.100 0.177 1.100 0.177 1.100 0.177 1.100 0.177 1.100 0.177 1.100 0.177 1.100 0.177 1.100 0.177 1.100 0.177 1.771
6 Bhikhi Disty D 15 14 3 23,000 1.000 0.069 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 0.759
7 Gilgitti Disty D 13 5 2 23,000 1.000 0.060 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 0.658
8 Sadhoke Disty D 151 360 4 23,000 1.000 0.695 1.100 0.764 1.100 0.764 1.100 0.764 1.100 0.764 1.100 0.764 1.100 0.764 1.100 0.764 1.100 0.764 1.100 0.764 1.100 0.764 7.641
(i) Ananta Minor M 22 18 5 23,000 1.000 0.101 1.100 0.111 1.100 0.111 1.100 0.111 1.100 0.111 1.100 0.111 1.100 0.111 1.100 0.111 1.100 0.111 1.100 0.111 1.100 0.111 1.113
(ii) Ghulab Singh Minor M 34 28 6 23,000 1.000 0.156 1.100 0.172 1.100 0.172 1.100 0.172 1.100 0.172 1.100 0.172 1.100 0.172 1.100 0.172 1.100 0.172 1.100 0.172 1.100 0.172 1.720
(iii) Wandho Minor M 41 41 11 23,000 1.000 0.189 1.100 0.207 1.100 0.207 1.100 0.207 1.100 0.207 1.100 0.207 1.100 0.207 1.100 0.207 1.100 0.207 1.100 0.207 1.100 0.207 2.075
(iv) Dholan Minor M 61 84 14 23,000 1.000 0.281 1.100 0.309 1.100 0.309 1.100 0.309 1.100 0.309 1.100 0.309 1.100 0.309 1.100 0.309 1.100 0.309 1.100 0.309 1.100 0.309 3.087
(v) Sher Garh Sub Minor SM 19 23 6 23,000 1.000 0.087 1.100 0.096 1.100 0.096 1.100 0.096 1.100 0.096 1.100 0.096 1.100 0.096 1.100 0.096 1.100 0.096 1.100 0.096 1.100 0.096 0.961
(vi) Tamboli Minor M 13 12 3 23,000 1.000 0.060 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 1.100 0.066 0.658
(vii) Ghanian Minor M 8 9 2 23,000 1.000 0.037 1.100 0.040 1.100 0.040 1.100 0.040 1.100 0.040 1.100 0.040 1.100 0.040 1.100 0.040 1.100 0.040 1.100 0.040 1.100 0.040 0.405
9 Changa Disty D 11 12 3 23,000 1.000 0.051 1.100 0.056 1.100 0.056 1.100 0.056 1.100 0.056 1.100 0.056 1.100 0.056 1.100 0.056 1.100 0.056 1.100 0.056 1.100 0.056 0.557
10 Naddha Disty D 9 8 2 23,000 1.000 0.041 1.100 0.046 1.100 0.046 1.100 0.046 1.100 0.046 1.100 0.046 1.100 0.046 1.100 0.046 1.100 0.046 1.100 0.046 1.100 0.046 0.455
11 Dandian Disty D 69 94 17 23,000 1.000 0.317 1.100 0.349 1.100 0.349 1.100 0.349 1.100 0.349 1.100 0.349 1.100 0.349 1.100 0.349 1.100 0.349 1.100 0.349 1.100 0.349 3.491
(i) Aima Minor M 20 13 3 23,000 1.000 0.092 1.100 0.101 1.100 0.101 1.100 0.101 1.100 0.101 1.100 0.101 1.100 0.101 1.100 0.101 1.100 0.101 1.100 0.101 1.100 0.101 1.012
(ii) Mangat Minor M 17 11 3 23,000 1.000 0.078 1.100 0.086 1.100 0.086 1.100 0.086 1.100 0.086 1.100 0.086 1.100 0.086 1.100 0.086 1.100 0.086 1.100 0.086 1.100 0.086 0.860
12 Kali Disty D 18 10 3 23,000 1.000 0.083 1.100 0.091 1.100 0.091 1.100 0.091 1.100 0.091 1.100 0.091 1.100 0.091 1.100 0.091 1.100 0.091 1.100 0.091 1.100 0.091 0.911
MANUAL OF IRRIGATION PRACTICE
13 Gulloke Disty D 51 59 13 23,000 1.000 0.235 1.100 0.258 1.100 0.258 1.100 0.258 1.100 0.258 1.100 0.258 1.100 0.258 1.100 0.258 1.100 0.258 1.100 0.258 1.100 0.258 2.581
14 Hacher Disty D 23 19 5 23,000 1.000 0.106 1.100 0.116 1.100 0.116 1.100 0.116 1.100 0.116 1.100 0.116 1.100 0.116 1.100 0.116 1.100 0.116 1.100 0.116 1.100 0.116 1.164
15 Gharial Disty D 9 10 2 23,000 1.000 0.041 1.100 0.046 1.100 0.046 1.100 0.046 1.100 0.046 1.100 0.046 1.100 0.046 1.100 0.046 1.100 0.046 1.100 0.046 1.100 0.046 0.455
Total Main Line Lower 322 11.095 12.204 12.204 12.204 12.204 12.204 12.204 12.204 12.204 12.204 12.204 122.041
1 Muridke Branch BC 60 714 14 62,000 1.000 0.744 1.100 0.818 1.100 0.818 1.100 0.818 1.100 0.818 1.100 0.818 1.100 0.818 1.100 0.818 1.100 0.818 1.100 0.818 1.100 0.818 8.184
2 Muridke Disty D 167 304 41 23,000 1.000 0.768 1.100 0.845 1.100 0.845 1.100 0.845 1.100 0.845 1.100 0.845 1.100 0.845 1.100 0.845 1.100 0.845 1.100 0.845 1.100 0.845 8.450
3 (i) Chakian Minor M 45 45 12 23,000 1.000 0.207 1.100 0.228 1.100 0.228 1.100 0.228 1.100 0.228 1.100 0.228 1.100 0.228 1.100 0.228 1.100 0.228 1.100 0.228 1.100 0.228 2.277
4 (ii) Nangle Isa Minor M 12 15 2 23,000 1.000 0.055 1.100 0.061 1.100 0.061 1.100 0.061 1.100 0.061 1.100 0.061 1.100 0.061 1.100 0.061 1.100 0.061 1.100 0.061 1.100 0.061 0.607
5 (iii) New Minor M 10 10 3 23,000 1.000 0.046 1.100 0.051 1.100 0.051 1.100 0.051 1.100 0.051 1.100 0.051 1.100 0.051 1.100 0.051 1.100 0.051 1.100 0.051 1.100 0.051 0.506
6 (iv) Khanna Minor M 26 38 6 23,000 1.000 0.120 1.100 0.132 1.100 0.132 1.100 0.132 1.100 0.132 1.100 0.132 1.100 0.132 1.100 0.132 1.100 0.132 1.100 0.132 1.100 0.132 1.316
7 (v) Boali Minor M 15 16 4 23,000 1.000 0.069 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 0.759
8 (vi) Kuthiala Minor M 31 30 7 23,000 1.000 0.143 1.100 0.157 1.100 0.157 1.100 0.157 1.100 0.157 1.100 0.157 1.100 0.157 1.100 0.157 1.100 0.157 1.100 0.157 1.100 0.157 1.569
9 (vii) Shamke Minor M 16 15 3 23,000 1.000 0.074 1.100 0.081 1.100 0.081 1.100 0.081 1.100 0.081 1.100 0.081 1.100 0.081 1.100 0.081 1.100 0.081 1.100 0.081 1.100 0.081 0.810
10 (viii) Qila Sattar Shah Minor M 7 10 2 23,000 1.000 0.032 1.100 0.035 1.100 0.035 1.100 0.035 1.100 0.035 1.100 0.035 1.100 0.035 1.100 0.035 1.100 0.035 1.100 0.035 1.100 0.035 0.354
11 Kala Shah Kaku Disty D 141 265 32 23,000 1.000 0.649 1.100 0.713 1.100 0.713 1.100 0.713 1.100 0.713 1.100 0.713 1.100 0.713 1.100 0.713 1.100 0.713 1.100 0.713 1.100 0.713 7.135
12 (i) Dala Wagha Minor M 15 12 3 23,000 1.000 0.069 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 1.100 0.076 0.759
13 (ii) Dargahi Minor M 101 94 19 23,000 1.000 0.465 1.100 0.511 1.100 0.511 1.100 0.511 1.100 0.511 1.100 0.511 1.100 0.511 1.100 0.511 1.100 0.511 1.100 0.511 1.100 0.511 5.111
14 (iii) Dharor Hindu Sub Minor SM 7 6 1 23,000 1.000 0.032 1.100 0.035 1.100 0.035 1.100 0.035 1.100 0.035 1.100 0.035 1.100 0.035 1.100 0.035 1.100 0.035 1.100 0.035 1.100 0.035 0.354
15 (iii) Chaura Minor M 1 4 1 23,000 1.000 0.005 1.100 0.005 1.100 0.005 1.100 0.005 1.100 0.005 1.100 0.005 1.100 0.005 1.100 0.005 1.100 0.005 1.100 0.005 1.100 0.005 0.051
605
606
MANUAL OF IRRIGATION PRACTICE
ASSET MANAGEMENT PLAN
Phasing of Work
Total Rehabilitation
C.C.A/ FY FY FY FY FY FY FY FY FY FY Total
Required
Lengt FSD C.A 2007- 08 2008-09 2009-10 20010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 FY 2007-17
Description Sourse of funding
h (RD) (Cusecs) (1000 Qty of
Cost Cost Cost Cost Cost Cost Cost Cost Cost Cost Cost
AC) L(RD) E/Work Cost (M.Rs)
(M.Rs) (M.Rs) (M.Rs) (M.Rs) (M.Rs) (M.Rs) (M.Rs) (M.Rs) (M.Rs) (M.Rs) (M.Rs)
(M.Cft)
Upper Chenab Canal
Main Line Upper
MC 133 16850 - 200.000 100.000 100.000 200.000 ISRP/ADP
1.10. References:
1. Asset Management procedures and techniques, Water Supply and
Sewerage Industry of England and Wales, 1989.
2. Microsoft Excel work sheets for computing M&R Yardsticks, prepared
under World Bank’s Development Program (DPL I&II) in 2006 and 2007
3. IPD, Assets Inventory of Bahawalpur Zone, March 2007
4. IPD, Assets Inventory of D.G Khan Zone, March 2007
5. IPD, Assets Inventory of Multan Zone, March 2007
6. IPD, Assets Inventory of Faisalabad Zone, March 2007
7. IPD, Assets Inventory of Lahore Zone, March 2007
8. IPD Assets Inventory of Sargodha Zone, March 2007
9. IPD, Asset Management Plan, prepared under World Bank’s Irrigation
Sector Development Policy Loans (DPLs I&II) – March 24, 2007
608
MANUAL OF IRRIGATION PRACTICE
ASSET MANAGEMENT PLAN
i
MANUAL OF IRRIGATION PRACTICE
PREPARING OF ANNUAL O&M BUDGET
List of Tables
TABLE 1: ZONE SPECIFIC ITEMS INCLUDED IN M&R YARDSTICKS ............................................................. 613
TABLE 2: MAINTENANCE CRITERIA OF IRRIGATION AND DRAINAGE INFRASTRUCTURE ................................ 617
TABLE 3: INVENTORY OF PID INFRASTRUCTURE ...................................................................................... 639
List of Figures
FIGURE 1: IMAGE OF AN INTERLINKED MS EXCEL SPREAD SHEET SHOWING CALCULATIONS OF EARTHWORK
.................................................................................................................................................... 631
FIGURE 2: IMAGE OF AN INTERLINKED MS EXCEL SPREAD SHEET SHOWING AN M&R YARDSTICKS UNIT COST
.................................................................................................................................................... 632
FIGURE 3: IMAGE OF AN INTERLINKED MS EXCEL SPREAD SHEET SHOWING COMPUTATIONS FOR AN M&R
YARDSTICK UNIT COST ................................................................................................................... 632
FIGURE 4: IMAGE OF ONE OF THE INTERLINKED MS EXCEL SPREAD SHEETS SHOWING FACTORS PERTAINING A
FEW ITEMS IN THE ZONE-SPECIFIC CRITERIA, WHICH CHANGE UNIT COSTS, IF VARIED ......................... 634
ii
MANUAL OF IRRIGATION PRACTICE
PREPARING OF ANNUAL O&M BUDGET
FIGURE 5: IMAGE OF ONE OF THE INTERLINKED MS EXCEL SPREAD SHEETS SHOWING MRS RATES OF A FEW
ITEMS, WHICH CHANGE UNIT COSTS, IF VARIED ................................................................................ 635
FIGURE 6: IMAGE OF ONE OF THE INTERLINKED MS EXCEL SPREAD SHEETS SHOWING QUANTITIES PERTAINING
TO A BARRAGE, WHICH CHANGE IN UNIT COSTS, IF VARIED ................................................................ 636
FIGURE 7: IMAGE OF ONE OF THE INVENTORY MS EXCEL SPREAD SHEETS................................................ 638
FIGURE 8: IMAGE OF SHEET SHOWING O&M BUDGET OF 2006-07 ............................................................ 641
609
MANUAL OF IRRIGATION PRACTICE
PREPARING OF ANNUAL O&M BUDGET
using the MRS rates in vogue and/or changing criteria pertaining to unit quantities, if
deemed necessary.
1.3.2. General Classifications of M&R yardsticks’ Items
The yardsticks for the purpose of annual grant No.9 for M&R of PID works, as
approved Finance Department of by Government of Punjab, includes the following
items:
(i). Small dams, including roads, channels and buildings;
(ii). Office Buildings;
(iii). Residential Buildings;
(iv). Other Buildings;
(v). Un-lined Main & Branch Canals, upto 6,000 cusecs discharge;
(vi). Un-lined Main & Branch Canals, more than 6,000 to 10,000 cusecs
discharge;
(vii). Un-lined Main & Branch Canals, more than 10,000 cusecs discharge;
(viii). Link Canals, upto 10,000 cusecs;
(ix). Link Canals, more than 10,000 cusecs;
(x). Lined Main & Branch Canals;
(xi). Tributary and other subsidiary Links, Distributaries, Minors & Sub-
minors etc.;
(xii). Barrages & Headworks (including all training and protection works) –
13 barrages & headworks and 2 siphons across rivers;
(xiii). Flood Embankments other than those connected with barrages or
headworks, without wetting channels;
(xiv). Flood Embankments other than those connected with barrages or
headworks, with wetting channels;
(xv). J-Head/T-Head Spurs (including shanks) other than those connected
with barrages or headworks– along River Ravi;
(xvi). J-Head/T-Head Spurs (including shanks) other than those connected
with barrages or headworks– along River Jhelum & Chenab;
(xvii). J-Head/T-Head Spurs (including shanks) other than those connected
with barrages or headworks– along River Indus;
(xviii). Mole Head Spurs & Sloping Spurs
(xix). Stone Studs along River Ravi;
(xx). Stone Stud along Rivers Jhelum & Chenab;
(xxi). Stone Studs along River Indus;
(xxii). Perennial Lift Irrigation Canals, including electricity charges;
(xxiii). Non-Perennial Lift Irrigation Canals (working for 125 days), including
electricity charges;
(xxiv). Non-Perennial Lift Irrigation Canals (working for 200 days), including
electricity charges;
(xxv). Gandas and cross regulators on Hill Torrents of Jampur Construction
Division;
612
MANUAL OF IRRIGATION PRACTICE
PREPARING OF ANNUAL O&M BUDGET
Figure 2: Image of an interlinked MS Excel spread sheet showing an M&R yardsticks unit cost
(ii). Unit quantities for operating each of the thirteen barrages in good
working condition taking care of general wear and tear;
(iii). Unit quantities for operating each of small dams and facilities
constructed at locations each hill torrent in good working condition taking
care of general wear and tear, based on the design of each type of small
dam and appurtenant works, and hill torrent structures and appurtenant
works;
(iv). Unit quantities for maintaining miscellaneous facilities such as Ghazi
Ghat bridge, etc. in good working condition taking care of general wear
and tear, based on their respective design;
(v). MRS rates applicable to each zone taking the average of rates of all
districts located in the respective zone;
Figures 4, 5 and 6 show the images of MS Excel spread sheets containing some of
the above factors pertaining to a few items in the zone-specific criteria, MRS rates of
a few items and quantities pertaining to a barrage respectively, as samples. Any
change in these elements will automatically change unit costs in the yardsticks.
634
MANUAL OF IRRIGATION PRACTICE
PREPARING OF ANNUAL O&M BUDGET
Figure 4: Image of one of the interlinked MS Excel spread sheets showing factors pertaining a
few items in the zone-specific criteria, which change unit costs, if varied
635
MANUAL OF IRRIGATION PRACTICE
PREPARING OF ANNUAL O&M BUDGET
Figure 5: Image of one of the interlinked MS Excel spread sheets showing MRS rates of a few
items, which change unit costs, if varied
636
MANUAL OF IRRIGATION PRACTICE
PREPARING OF ANNUAL O&M BUDGET
Figure 6: Image of one of the interlinked MS Excel spread sheets showing quantities pertaining
to a barrage, which change in unit costs, if varied
637
MANUAL OF IRRIGATION PRACTICE
PREPARING OF ANNUAL O&M BUDGET
The zone-wise inventory of the infrastructure was prepared using MS Excel spread
sheets containing particulars of the elements of the infrastructure. These spread
sheets are available in Strategic Planning/Reform Unit (SPRU) located in the Irrigation
Secretariat, Lahore. Figure 7 shows the image of one of the MS Excel spread sheets
showing the inventory of a branch canal subsystem in Faisalabad zone.
In the 33 existing small dams in 2005, 22 more dams have been constructed and more
dams are under construction. There has been reduction in covered area of buildings,
as a number of buildings are being abandoned such as rest houses in remote places
since the time the above inventory was prepared. There has also been reduction in
CCA of 8.41 Mha since the time the above inventory was prepared due to urbanization
of agriculture land in the proximity of towns and cities.
1.6. Preparation of O&M Budget
Annual O&M budget contains two types of expenditures: (i) M&R costs; and (ii)
Supervision and administration costs.
1.6.1. Approach for estimating M&R costs
As mentioned above, realistic M&R costs could be estimated after carrying out the
condition surveys of the infrastructure to ascertain their M&R needs, annually. But this
exercise would be too costly and time consuming to repeat every year. As an
alternative, PID framed M&R yardsticks providing unit costs for M&R in order to
expeditiously compute the annual M&R costs, In order to compute M&R costs,
therefore, updating/revising of the M&R yardsticks and verification of inventory of
elements of the infrastructure need be done every year. The most important data
required for updating/revising unit costs for the yardstick are MRS rates of the
applicable quarter.
Section 4 describes the methodology for updating/revising of the M&R yardsticks. The
inventory, contained in Section 5, can be easily verified by the respective field
operators with the help of the MS Excel spread sheets which include particulars of
various elements of the infrastructure in all zones, which are available in Strategic
Planning/Reform Unit (SPRU) located in the Irrigation Secretariat, Lahore. The
supervision and administrative costs relate to the remuneration and allowances paid
to the operational staff, staff in the secretariat and other related offices of PID such as
Irrigation Research Institute, Punjab Engineering Academy, and Directorate of Land
Reclamation etc. It is reflected in the annual budget of recurring expenditure and is
based on the sanctioned positions of the staff and the operating costs of PID offices
and other related institutions.
641
MANUAL OF IRRIGATION PRACTICE
PREPARING OF ANNUAL O&M BUDGET
Figure 6.1 presents image of sheet showing O&M budget of 2006-07 - part related
with the Establishment. As prevailing ‘Heads’ can be different from those contained in
Figure 8, it should be used as a guidance only for preparing the estimate of supervision
and administrative costs.
GOVERNMNET OF THE PUNJAB
IRRIGATION AND POWER DEPARTMENT
O&M BUDGET 2006-07 PC21009 (009)
BUDGET ESTIMATES 2006-07
HEAD
ESTABLISHMENT REMARKS
9.150 Grant in Aid to Engineering. Academy, Lahore
014110 OTHERS 1.402 Grant in Aid to D.G. Khan (Hill Torrents)
0.304 Grant in Aid to Rajanpur (Hill Torrents)
106.596 Chief Engineers
9.631 Chief Engineer (Water Treaty Implementation Cell)
042201 ADMINISTRATION
20.983 Chief Engineer (Planning & Review)
112.229 Superintending Engineers
042202 IRRIGATION DAMS 41.694
4.392 CRB Irr. Proj. 67&68 - Canal Div.Taunsa Sharif
- Establishment of (PMIU)
1.284 CRB Irr. Proj. 67&68 - Canal Div.Taunsa Sharif
042203 CANAL IRRIGATION 1,617.506 Canal Irrigation (Executive)
624.236 Canal Irrigation (SR)
2.208 CRB D.G Khan (SR)
5.321 CRB D.G Khan (Executive)
16.527 Greater Thal canal (SR)
042204 TUBE WELLS 536.046
042205 EQUIPMENT 52.446 Excavator & Store Div.
MACHINERY 42.144 MIW
WORKSHOPS 23.407 BIW
042206 IRRIGATION RESEARCH 63.543 Research Institute
& DESIGN 7.684 Director Design
042250 OTHERS - Director Land Reclalmation
042301 ADMINISTRATION 24.920
WATER LOGGING AND
042302 67.168
SALINITY CONTROL
6.146 CE (Flood Cell)
107105 FLOOD CONTROL 6.162 Director Hydrology
246.621 Flood Control & Drainage
Total:- 3,649.750
Figure 8: Image of sheet showing O&M budget of 2006-07
1.7. Timeline for preparation of the annual O&M Budget
Several offices starting from the divisional offices, circle offices, zonal chief engineers’
offices to the PID Secretariat are involved in preparing the annual O&M budget.
Therefore, a well-coordinated effort is required. As such a Standard Operating
Procedure (SOP) for preparing annual O&M budget should be devised. The timeline
should match the date by which PID is required to submit the annual O&M budget to
Finance Department for further inclusion in the annual provincial budget for approval
by the provincial assembly.
It is imperative that the updating/revising unit costs in the yardsticks on the basis of
the most recent MRS rates is done. As a first step, before preparing the annual O&M
642
MANUAL OF IRRIGATION PRACTICE
PREPARING OF ANNUAL O&M BUDGET
budget, which activity should logically be carried out by zonal offices. MRS rates for
the quarter ending September will be available for using in updating/revising the
yardsticks. The consent of the PID secretariat is essential before using
updated/revised zonal yardsticks. Therefore, the updating/revising unit costs is a
critical activity in the exercise of preparing O&M budget.
643
MANUAL OF IRRIGATION PRACTICE
PREPARING OF ANNUAL O&M BUDGET
1.8. References
1. Report of Assets Inventory, IPD, January 2006
2. Microsoft Excel work sheets for computing M&R Yardsticks, prepared
under World Bank’s Irrigation Sector Development Policy Loans (DPLs
I&II) in 2006 and 2007
3. IPD Revised Criteria for Computing M&R Yardstick of Bahawalpur Zone,
March 2007
4. IPD, Revised Criteria for Computing M&R Yardstick of D.G Khan Zone,
March 2007
5. IPD, Revised Criteria for Computing M&R Yardstick of Multan Zone,
March 2007
6. IPD, Revised Criteria for Computing M&R Yardstick of Faisalabad Zone,
March 2007
7. IPD, Revised Criteria for Computing M&R Yardstick of Lahore Zone,
March 2007
8. IPD, Revised Criteria for Computing M&R Yardstick of Sargodha Zone,
March 2007
9. IPD files and procedures
644
MANUAL OF IRRIGATION PRACTICE
PREPARING OF ANNUAL O&M BUDGET
i
MANUAL OF IRRIGATION PRACTICE
PREPARING ANNUAL M&R WORK PLANS AND THEIR IMPLEMENTATION
the PID for checking of schemes, third party validation of the quality of work performed
by contractors and using force account (direct labour), and measurements and
payments. In case the services of consultants are acquired, their terms of reference
(TOR) may include providing assistance in procurement processes, as well.
1.2 PREPARATION OF ANNUAL WORK PLANS
1.2.1 General
As mentioned above, the annual work plans for M&R are prepared by the XEN with
the help of SDOs and Sub-Engineers of his Division. The XEN submits the annual
work plans of his Division to the SE who recommends it to the respective CE of the
Zone. The CE approves the annual work plans prioritizing the proposed M&R works
keeping in view the available budget. This process is carried out before the advent of
a fiscal year (FY) and is completed immediately after the annual grant/budget
allocation is approved for the FY. The work plans are based on the applicable criteria
of the yardstick. The work plans approved in the beginning of the fiscal year may be
revised for the following reasons;
(i). Directives during inspection of senior officers;
(ii). Complaints by the water users;
(iii). Emergent repairs; and
(iv). Curtailment of budgets and release of lesser funds for M&R activities.
1.2.2 Preparation of Annual Work Plans
The work plans should not only be in the form of lists of works but should also indicate
timeline for design, preparing bidding documents, procurement method, seasonal
constraints such as rainy season and arrangements of supervision needed. The
timeline for implementation of schemes should be set apart so that supervision of the
implementation schemes with available staff becomes doable.
The annual work plans should aim at execution of activities as per the unit quantities
included in the approved yardstick. This will avoid accumulation of M&R works in case
the funds are not adequately provided. The mode of execution i.e. whether to procure
requisite works through contactors (out sourcing) or force account (direct labour) or
Machinery Circle (in-house) should be planned in advance. For works to be procured
through contractors, the work plans should also take into account time required to
prepare bidding documents, bidding process and seasonal constraints such as rainy
season for establishing completion dates. The execution of works should be planned
in such a manner so as to ensure execution of the works throughout the fiscal year
without allowing a large number of works going on simultaneously towards the end of
a fiscal year.
It is important that the works are divided into following categories;
(i). Preventive Maintenance;
(ii). Repair-works;
(iii). Replacement of parts of and/complete facility; and
(iv). Works that can be carried out only in the annual closure period.
647
MANUAL OF IRRIGATION PRACTICE
PREPARING ANNUAL M&R WORK PLANS AND THEIR IMPLEMENTATION
Since the yardstick includes nominal earthwork for canals and drains that is expected
to erode in a year, it is impracticable to recoup this small earthwork along the entire
length of a canal or drain each year. The earthwork (filling and compaction/tamping)
can be carried out in the reach of a drain or canal, where the required earthwork is in
an appreciable quantity to a sizeable depth. Therefore, the earthwork on canals and
drains should be carried out in a manner that the entire length of a canal or drain is
restored to its designed parameters in a cyclic manner, say in 5 years. This will
determine the sizes of contract packages of M&R works.
Divisional offices shall commence preparation of annual M&R Work Plans from the
first day of May each year. By end of May these work plans shall be submitted to the
respective SE offices. The concerned SE shall be the authorized officer to
recommend/approve the Divisional work plans. The SE shall modify/amend/approve
these work plans latest by third week of June. After approving the work plans the SE
shall collate the information for the entire Circle and send it to the concerned CE. The
CE shall modify/amend/approve these work plans latest by end the first week of July
after the receipt of approved budget from the Punjab Irrigation Department (PID). The
CEs shall send the approved work plans for information to the PID after compiling
those on Zonal basis.
Table below shows the time frame for preparing M&R work plans:
Commencement of work plans preparation by XENs 1stMay
Submission to the Circle Office. 31stMay
Approval Divisional work plans by SEs. Submission of 22ndJune
collated Circle work plans to Zonal Office.
Approval of Circle work plans by CEs. Submission of 7th July
collated Zonal work plans to PID.
contracts and repair packages. Column 4 should indicate approximate cost estimate,
which may be based on yardsticks or inquiries made and/or experience. This cost
estimate will of course be refined as the bidding documents and/or other procurement
documents are prepared. Mode of execution to be indicated in column 5 will be either
of the following:
(i). Local Purchase (LP) through quotations.
(ii). Small Work Orders (WOs) to get repair work done expeditiously from the
market.
(iii). Out Sourcing (OS) through Competitive Bidding.
(iv). Force Account (FA) by engaging temporary labour.
(v). Force Account (FA) by utilizing departmental machinery.
It is important that realistic completion periods should be indicated in column 6 of the
proforma included as Annexure 1. These completion periods should also guide
establishing dates in columns 7 to 10. It is also important that between bidding date
and award, there should be provided adequate time for preparation of bids, after
invitation of bids at least 30 days may be allowed for evaluation of bids.
1.2.4 Criteria for selecting modes of execution
Out sourcing (OS) through competitive bidding (using the contractors) would be the
mode of procurement of works in following cases;
(i) Planned earthwork (routine maintenance) to make up eroded banks of
main canals, branch canals, distributaries, minors, flood embankments
and small dams;
(ii) Planned repairs (routine maintenance) or special repairs
(modifications/improvements) of structures related to main canals,
branch canals, distributaries, minors, flood embankments and small
dams; and
(iii) Planned repairs (routine maintenance) or special repairs
(modifications/improvements) of offices, residential buildings and Rest
Houses.
Force Account’ would be the mode of procurement of maintenance work in following
cases only;
(i) Desilting of drains, using the equipment of Machinery Circle;
(ii) Emergency repairs of eroded/under attack/breached flood
embankments during the flood season; and
(iii) Emergency repairs of breached canal banks, by employing temporary
labour or using the equipment of Machinery Circle or combination of
both.
1.3 Implementation of annual M&R Work Plans
The implementation of annual M&R work plans is done through execution of schemes
included in the annual M&R work plans. The size of schemes should be such that it is
convenient to prepare documentation and achieve implementation involving contract
649
MANUAL OF IRRIGATION PRACTICE
PREPARING ANNUAL M&R WORK PLANS AND THEIR IMPLEMENTATION
For the allotment of work of such emergent nature either of the following three
procedures may be used depending upon the nature and estimated cost of emergency
work:
(i). Short notice /gallop tenders are invited from the approved list of
contractors for a certain probable amount and then after completion of
work, the estimate is prepared on actual work done basis and submitted
to the competent authority for sanction;
(ii). Work is allotted to a contractor registered with PID by the Superintending
Engineer at prevailing MRS under para 6.17 of P.W.D. code to avoid
wastage of time in bidding;.and
(iii). Executing work by “Force Account”, by employing temporary labour or
using the equipment/Machinery Circle or combination of both.
1.3.12 Desilting in drains by FA
Prior to implementation of desilting work in drains under ‘Force Account’, the
Engineer’s estimate will be prepared, checked and sanctioned in the same manner as
that of OS, described in the sections above. The rates for the BOQ items shall be
those prevalent in the Machinery Circle and/or as approved by the competent
authority.
1.4 Monitoring of M&R Work Plans
1.4.1 Monitoring of M&R Work Plans
The implementation of M&R Work Plans will be monitored regularly by concerned
officers/ officials of the Sub Division/Division/Circle.The SEs shall send the monitoring
report of the Circle to the concerned CE at the end of third week of every month, who
will prepare a summary of the monitored information and forward to the Punjab
Irrigation Department (PID) Secretariat by end of each month.
1.4.2 Progress Monitoring Reports
Monthly Progress Report for each contract shall be prepared by the SDO and
submitted to his XEN by end of the first week of every month. The report should be
brief giving particulars of the contracts, progress achieved against the scheduled
progress, quality test results, status of payments, issues, if any, and actions taken/to
be taken to resolve the issues. This progress report should remain as permanent
record. It must include a suitable number of digital photographs that can demonstrate
the nature and quality of work carried out.
The XEN will prepare completion report for each work, which shall be attached with
the final bill. In addition, the XEN will collate the information provided by SDOs and
prepare Quarterly Progress Reports as per the following time frame.
testing should also be prescribed in the bidding documents. There should always be
adequate/suitable work-charged staff (such as: foremen, work mistaries, helpers and
unskilled labour) available to the Sub-Engineer to assist him in collecting samples for
testing, testing at site if required, supervision of on-going works for compliance with
specifications, measurements and documentation.
As per codal procedure, SDOs and XENs should check the implementation of
M&R works. If the items of work are under water, the SDO is required to check 100%
work. In other cases where the items of work are not under water after completion, the
mandatory check by SDO is of the order of at least 35%. The underwater works are
also supposed to be verified to an extent of at least 15% by the XEN. In order to attain
the codal level of checks and to assure the proper quality of work, SDOs should visit
the site at appropriate occasions to ensure that it shall be possible to perform the
requisite quantum of checks without any difficulty. SDO should make at least three
visits; one as soon as the work commences, second during the middle of the contract
period and third at the time of completion. If the construction period is large then the
construction supervision visits should be more than three and frequent. All visits by
SDOs should be documented by writing ‘Inspection Notes’ for the guidance of the Sub-
Engineer and for information of higher officers.
The XENs should also visit site of works at appropriate occasions. In the case
of the M&R works with large construction period, XENs should make frequent visits to
the site. All visits by XENs should be documented by writing ‘Inspection Notes’ for the
guidance of SDO and the Sub-Engineer. The Superintending Engineer during
inspection of the barrages, main canals & branches and other small channels in the
Division must call for the list of works in progress and exercise random inspection and
check the quality of works. The instructions issued by the PID vide letter No. SOB
(I&P)7-40/2006-07 dated 2.3.20061 must be strictly followed.
1.5.3 Payments
Interim payments of works executed should be made in accordance with the conditions
of contract. The bill for interim payment shall be submitted by the Contractor and the
Sub-Engineer shall enter it in his Measurement Book (MB) after verification of quality
and quantity. The codal checks must be performed by the SDOs and XENs prior to
processing disbursement of payments. Before submission of final bill by the contractor
a joint inspection by the concerned staff (SDO and Sub-Engineer) and the contractor’s
representative should be made to prepare a ‘punch list’ of outstanding items of works
that must be completed before processing of the final payment. This ‘Punch List’ must
be signed by all parties and retained in the permanent record of the Division. The
Payment should be released as soon as defects, if any, are removed.
1.6 Documentation
For performance monitoring of M&R works, following documentation shall be
prepared;
1 Or revised instructions changing the contents letter No. SOB (I&P)7-40/2006-07 dated 2.3.2006
656
MANUAL OF IRRIGATION PRACTICE
PREPARING ANNUAL M&R WORK PLANS AND THEIR IMPLEMENTATION
1.7 References
1. IPD files and procedures
i
MANUAL OF IRRIGATION PRACTICE
PROJECT MANAGEMENT AND IMPLEMENTATION OF PROJECTS
List of Figures
Like all projects of the government of Punjab implementation of PID projects, small or
big, has to follow a process involving: (i) conceive the aim and objectives ofthe project;
(ii) establish its feasibility by carrying out feasibility studies; (iii) design it in practical
detail; (iv) construct it; and (v) operate and maintain (O&M) it for getting benefit of the
completed project. Duration of the first four items, which is factually the project
implementation period, may last from less than a year to five years or even more while
fifth item is recurrent activity.
1.4 Conceiving a Project
Conceiving a project involves defining the function(s) the project envisages to perform.
The conceived projects are planned to correspond with the government’s policy and
are included in long term plans or short-term plans described in the section which
follows hereunder. The conceived projects are building blocks the plans formulated in
order to achieve the envisaged goals. A plan is a general statement of objectives and
targets relating to the economy as a whole and its various component sectors. It is not
an authorizing document in the sense that it does not authorize expenditure to the
relevant operating agencies. It provides a broad framework for formulation of
ADP/PSDP. In some cases, the projects, though not included in a plan, are executed
due to special directives of the government and/or to address complaints of
stakeholders.
1.5 Development plans
Perspective Plan: Its main purpose is to provide a long-term (15-25 years) economic
and social policy framework so that the objectives to be achieved over a much longer
period can be incorporated in a medium-term framework. Presently Vision 2025 is the
Perspective Plan.
The period is necessarily arbitrary and there is no profound reason for its
determination but it seems to be, on the one hand, long enough to permit a meaningful
structural change in the economy and, on the other, not so long as to be without direct
interest to the present working generation,
Five Year Plan: A single year is too short a period to accomplish anything. A five-year
plan is a general statement of objectives and targets relating to the economy as a
whole and its various component sectors. It is not an authorizing document in the
sense that it does not authorize expenditure to the relevant operating agencies. It
provides a broad framework for formulation of ADP.
Role-on Plan: In order to bring flexibility into the five-year plan and to relate the
sectorial and project-wise allocation with (a) the financial position, and (b) project
implementation, a roll-on plan of medium term is designed in which the sectorial and
project-wise position is adjusted according to the foregoing year.
Annual Development Plan: The principal instrument for adjusting the five year plan
to current realities is ADP, which has proved a dependable method for translating plan
objectives into an operational programme. In other words, it is regarded as the
implementation side of the five-year plan. ADP includes an evaluation of past
663
MANUAL OF IRRIGATION PRACTICE
PROJECT MANAGEMENT AND IMPLEMENTATION OF PROJECTS
Project layout and elements would be developed to the degree of detail necessary to
provide a fair comparison between the alternatives considered. Other important
aspects which will be considered: materials requirement/production including its
transport; foundation conditions, water handling problems if hydraulic structures are
involved, etc.
In order to support the conclusions of the comparative study the available physical
data (geological, topographical, geotechnical, and hydrological) shall be reviewed,
assessed and updated for rehabilitation projects. Available material on site
investigations, hydrological records, topographical surveys and mapping will be
utilized to the maximum extent.
A comparison of alternative project schemes: optimization studies for each alternative
considered, taking into account: present economic conditions shall be carried out
before establishing preferred solution/ option.
1.8.4 Environmental Aspects
Issued in 1983 the Pakistan Environmental Protection Ordinance (PEPO) was
replaced by the Pakistan Environmental Protection Act, 1997. The Act is directed to
provide a basic environmental policy and set up a management structure for pollution
control. Under the Act, the Pakistan Environmental Protection Council (PEPC) has
been established as the highest environmental body in the country to formulate policy
and ensure its implementation within the framework of the National Conservation
Strategy (NCS), which was adopted in 1992. The goal of the NCS is transforming
attitudes and practices and influencing consumption patterns and ensuring that the
development is not destructive to the natural resource base on which it rests.
The Environmental Protection Act, 1997requiresestablishing federal and provincial
Environmental Protection Agencies (EPAs). The provincial and federal EPAs are in
place, though in Punjab it is called the Environmental Protection Department (EPD).
The Act has placed pollution control as a priority issue and provides the framework for
the establishment of standards for the quality of air, water and land. Accordingly,
National Environmental Quality Standards (NEQS) have been instituted to regulate
municipal and industrial wastewater discharges as well as major air and car emissions.
It is possible to maintain a better quality of water in natural water bodies applying these
standards.
The Federal EPA has delegated its powers to provincial EPAs/EPD to carry out the
same functions in the provinces as the federal EPA performs at the federal level. This
includes the authority to inspect industrial establishments, obtain samples of their
effluents and take action against the violators of NEQS.
The “IEE and EIA Regulation – 2000” contains a more detailed environmental
regulation describing the contents of Environmental Impact Assessments (EIAs) and
IEEs, their submission process, approval modalities, fees, monitoring programmes,
time schedules, etc. The provincial EPAs are responsible to review and either accept
the EIAs and issue No-Objection Certificate (NOC) or recommend that the project be
modified or rejected in the interest of environmental objectives.
669
MANUAL OF IRRIGATION PRACTICE
PROJECT MANAGEMENT AND IMPLEMENTATION OF PROJECTS
Table below shows the major environmental legislations in Pakistan, which are
required to be used or referred to while considering environmental aspects i.e. carrying
out environmental impact studies during preparing a project.
SECTOR LEGISLATION
Solid Waste and - The Balochistan, NWFP, Punjab and Sindh Local
Effluents Government Ordinance(s) (1979/80)
- Pakistan Environmental Protection Act, No. XXXIV of
1997
Economic Benefits: The benefits of the projects may include; enhanced production,
increase in employment, increase in the value of output due to quality improvement or
otherwise, etc.
Financial Analysis: The financial analysis of the Project is carried out to assess
Project funding requirements, compute financial internal rate of return (FIRR) of the
Project and estimate the cost benefits. Project outflows comprise Project investment
costs which correspond to the costs actually incurred i.e. capital costs including price
escalation and interest accrued on the amounts borrowed, both, local and foreign till
completion of the Project. The interest paid during the repayment period also forms
part of the cash out flows. The financial costs and revenues expressed as cash
outflows, cash inflows and net inflows over the analysis period have been computed.
Net Present Worth (NPW): It is simply the present worth of the incremental net benefit
or incremental cash flow. It is the difference between discounted benefits and
discounted costs of a project. NPW criterion suggests to us to accept all independent
projects with a zero or greater net present worth when discounted at opportunity cost.
No ranking of acceptable, alternative independent project is possible with the present
worth criterion because it is an absolute and not relative measure. A small, highly
attractive project may have a smaller net present worth than a larger marginally
acceptable project. If both have positive NPW then both projects should be
undertaken.
Benefit-Cost Ratio (BCR): This ratio is obtained when the present worth of the
benefit-stream is divided by the present worth of the cost stream. Note that the
absolute value of BCR will vary depending on the interest rate chosen. The higher the
interest rate, the smaller the resultant benefit-cost ratio and, if a higher enough rate is
chosen, the benefit-cost ratio will be driven down to less than 1. The BCR criterion
suggests to us to accept all independent projects with a benefit-cost ratio of 1 or
greater, when the cost and benefit streams are discounted at the opportunity cost of
capital. The benefit-cost ratio discriminates against projects with relatively high gross
returns and operating costs, even though these may be shown to have a greater
wealth-generating capacity than that of alternatives with a higher benefit-cost ratio.
Internal Rate of Return (IRR): It is the discount rate that makes the NPW of the
incremental net benefit-stream or incremental cash flow equal to zero. It is the
maximum interest that a project could pay for the resources used if the project is to
recover its investment and operating costs and still break even. It is the rate of return
on capital outstanding per period while it is invested in the project. IRR criterion
suggests to us to accept all independent projects having an internal rate of return equal
to or greater than the opportunity cost of capital.
Sensitivity Analysis: Sensitivity analysis is done to test the sensitivity of various
assumptions made in the base case. It is carried out to confirm the robustness of the
result obtained from the assumptions made for assessing the effect on the computed
EIRR and FIRR with respect to changes in the key parameters used in the analysis.
The following parameters are varied:
676
MANUAL OF IRRIGATION PRACTICE
PROJECT MANAGEMENT AND IMPLEMENTATION OF PROJECTS
and checking erosion of the canal banks, brick masonry, brick lining, plain cement
concrete (PCC), reinforced cement concrete (RCC), stone pitching, spurs (groynes),
stone studs.
1.9.4 Electrical and Mechanical Works
The mechanical works are but not limited to steel gates for barrages, gates for head
regulators, gates for various other types such as fall structures, silt ejectors and small
off-take structures Minors, hoisting mechanisms of gates, superstructure for housing
hoisting mechanisms and handrails.
The electrical would include but not limited to: (i) Low Voltage Switch Gear and
Control Gear Assemblies; (ii) SCADA; (iv) Electrical Power Motors; (v) Transformers;
and (vi) Equipment in Control Rooms.
1.9.5 Design Criteria
Design criteria are standards to be followed in designing the works, which should be
project specifically compiled. Before the doing the detailed design of works
pertaining to any project the design criteria should be compiled. The criteria for the
parameters and performing the procedures generally used for designing the PID
works is but not limited to the following:
1). Design Criteria of Hydraulic Design
- Flow, Water Level and Discharge;
- Stilling Basins and Energy Dissipation;
- Seepage Analysis and Exit Gradient;
- Seepage Analysis and Exit Gradient;
- Allowable Exit Gradients;
- Floor Thickness and Uplift:
- Scour Depth;
- Froude Number;
- Coefficient of Discharge;
- Manning’s “n” Values;
- Lacey’s Silt Factor for Different Types of Soil; and
- Khosla's Safe Seepage Gradient.
2). River Training Works & Erosion Protection
- Spurs; and
- Revetment.
3). Structural Design Criteria
- Design Codes and Standards;
- Loading;
- Factors of Safety; and
- Units of loading to be used.
4). Structural Stability Analyses:
678
MANUAL OF IRRIGATION PRACTICE
PROJECT MANAGEMENT AND IMPLEMENTATION OF PROJECTS
- Geotechnical Considerations;
- Overturning Stability;
- Sliding Stability; and
- Bearing Capacity.
5). Structural Strength Requirements:
6). Material, Properties & Permissible Stresses:
- (i) Concrete; and
- (ii) Reinforcing Steel.
7). Design Loads:
- Dead Loads;
- Live loads;
- Bridge Loading;
- Silt Pressures; and
- Earthquake Load.
8). Geotechnical Design Criteria:
- Seismicity; and
- Soils and their classifications.
9). General Mechanical Design Criteria:
- Gate Equipment;
- Design Loads;
- Hoists, Platforms and Walkways;
- Hoists;
- Head Regulator Gates; and
- Head Regulator Hoist Equipment.
10). Electrical Works
- Electrical Installation;
- Low Voltage Switch Gear and Control Gear Assemblies;
- SCADA; and
- Control Rooms.
1.9.6 Design Mehods
The detailed design of various elements is prepared using accepted procedures and
formulae relevant to respective element in accordance with adopted criteria. The
drawings produced should provide details sufficient to enable the bidders in preparing
the bids, if the adopted method of procurement of works is ‘out sourcing’ on the basis
of competitive bidding.
The completion of detailed design of works ends up in preparing, environment
management plan (EMP), social action plan (SAP), cost estimates and the bidding
documents. The purpose of preparing environment management plan (EMP) and
social action plan (SAP) are discussed in section 8.4 and section 8.5 respectively.
679
MANUAL OF IRRIGATION PRACTICE
PROJECT MANAGEMENT AND IMPLEMENTATION OF PROJECTS
international sources. Due to the substantial sums involved, this activity should begin
as early as possible.
After availability of the Feasibility Report, the PC-I Proforma will have to be prepared
and got approved from the concerned authorities. As soon as the detailed design is
substantially completed it will be appropriate to commence process of prequalification
of the contractors and manufacturers. Invitation bids will follow the preparation of
contract documents and prequalification of the contractors.
1.10.2 Contract Packaging
For a large size and complex project, it is desirable and usually necessary, to subdivide
the work into a number of contract packages for the following reasons:
i). The amount of risk, bonding capacity and financial strength required would
be excessive for many, otherwise qualified, contractors;
ii). Should the works be awarded on a single contract basis, competition would
necessarily be limited to a small number of very large firms, with a
consequent increase in bid prices; and
iii). Should any of the major contractors fail to perform adequately, it will be
possible to continue construction without excessive delays by assigning
work to other contractors.
However, in view of constraint of working space and approaches at the site on some
projects, it is considered more practicable to have as few contracts as possible. In
the case of splitting a project into more than one contract, an overall implementation
schedule should be prepared to establish completion period. The implementation
schedule should be preferably prepared by employing user friendly software
generating Gantt chart.
1.10.3 Modes of Construction Activites
PID may use different modes of executing project works. For construction activities,
PID may choose to employ capable to carry out the construction activities using ‘Force
Account’ and PID’s machinery. Generally, the use of this mode of execution is adopted
for preparing in-house design such as projects involving accumulated M&R works
(rehabilitation works) or M&R schemes. Alternatively, the execution works is done by
out sourcing (OS) through Competitive Bidding.
For using out sourcing (OS) through competitive bidding mode, the project works are
split into various contract packages in order to facilitate the construction activities, if
need. For each contract package, separate bidding documents are prepared. And,
each contract package is go through same rigmarole of; inviting expression of interest
(EoT), prequalifying and shortlisting the contractors, inviting bids, evaluation of bids
and award the contract by a competent authority4. Bids are evaluated as per procedure
mentioned in the bidding documents.
4 The authorized amounts of various competent authorities are defined and may vary from time to time.
682
MANUAL OF IRRIGATION PRACTICE
PROJECT MANAGEMENT AND IMPLEMENTATION OF PROJECTS
Various types of contract documents are in use such as; prepared by PEPRA and
Engineering Council and approved P&D department for use in all departments
associated with projects involving, construction works, FIDIC, those desired by
international donor (WB, ADB, etc.) The compliance to provisions in the signed
contract is done personnel designated in the General Condition (GC) of contract.
1.10.4 Key Players in the construction Contract
The employer, the contractor and the engineer are key players for satisfactorily
completing the work under a construction contract.
The Contractor has the responsibility of delivering the completed in accordance with
requirements of the signed contract in that he is obliged to: abide by the general items
like insurance requirements, HSE obligations, etc., use the drawings diligently to
complete the works according to desired lines and grades, adhering to relevant
specifications, etc. Contractor’s Site Typical Staff are shown in the Figure 10.1. A wise
contractor tries to keep his site staff and plant and equipment to the minimum for
economic construction of the works.
The Engineer may one of the staff of the Employer or the designated staff of a
consulting firm and/or a JV having power of attorney to act on behalf of the consultants
whose services has been retained to provide supervision, management and contract
administration. He would act on basis of the provisions in the construction contract.
He would have generally no powers to vary the price of the construction contract
without the consensus of the Employer. He is responsible for testing materials for
suitability and compliance with specifications, checking workmanship to see it
complies with the specifications and checking line and grade of the work and see that
it conforms to the drawings. The Engineer’s Site Typical Staff are shown in the Figure
10.2.
The Employer is PID or special office/organization created in PID by a competent
authority. One of the staff of PID or the person specially hired from market for the
implementing a project, acts as the Project Director (PD). PD is responsible to provide
general supervision and management of the project. In case the foreign funded
project, PD liaises with donor agency. PD is responsible for arranging all approvals
pertaining to budgets, PC-Is, payments to the contractors and consultants. PD is also
responsible to monitor progress activities of projects. The Employer’s typical staffing
is shown in organogram contained in the Figure 10.3.
683
MANUAL OF IRRIGATION PRACTICE
PROJECT MANAGEMENT AND IMPLEMENTATION OF PROJECTS
Figure 1: Typical Site Organization of the Contractor
684
MANUAL OF IRRIGATION PRACTICE
PROJECT MANAGEMENT AND IMPLEMENTATION OF PROJECTS
Figure 2: Typical Site Organization of the Engineer
685
MANUAL OF IRRIGATION PRACTICE
PROJECT MANAGEMENT AND IMPLEMENTATION OF PROJECTS
Figure 3: Typical Organogram of an IPD PMO (Employer)
686
MANUAL OF IRRIGATION PRACTICE
PROJECT MANAGEMENT AND IMPLEMENTATION OF PROJECTS