You are on page 1of 33

Babai River Bridge

BAR BENDING SCHEDULE OF PILE CAP OF PIER


SN Sketch dia.(mm) Bar mark Nos Bar length(m) Total length(m) Unit weight(kg/m) Total Weight(Kg)
1 32 PP1 63 12.05 759.15 6.321 4798.58
900
10250
2
900 25 PP2 88 12.05 1060.4 3.858 4091.05
7250

3 10250
900 20 PP3 38 12.05 457.9 2.469 1130.62

4 7250
900 20 PP4 53 12.05 638.65 2.469 1576.91
Total 11597.16

BAR BENDING SCHEDULE oF Pile


SN Sketch dia.(mm) Bar mark Nos Bar length(m) Total length(m) Unit weight(kg/m) Total Weight(Kg)
1 200 25 P1 16 14.4 230.4 3.858 888.89
14200

2 12 P2 99 2.67 264.37 0.889 234.99

Total 1123.88
Babai River Bridge

BAR BENDING SCHEDULE OF PIER STEM


Bar Total Unit Total
dia. Bar
SN Sketch Nos length length weight(k Weight
(mm) mark
(m) (m) g/m) (Kg)
1 6890.00000000003
1600 32 PS1 51 8.49 432.99 6.321 2736.924

2
12 PS2 36 3.770 135.717 0.889 120.637

100
3
2100 16 PS3 9 2.3 20.700 1.580 32.711
100 Total 2890.273

BAR BENDING SCHEDULE OF PIER CAP


Bar Total Unit Total
dia. Bar
SN Sketch Nos length length weight(k Weight
(mm) mark
(m) (m) g/m) (Kg)
1 7400
600 32 PCC1 34 8.6 292.400 6.321 1848.257

2 4400
600 25 PCC2 31 5.6 173.600 3.858 669.753

3 500 25 PCC3 31 8.508 263.748 3.858 1017.546

2704
2100

4 4400 16 PCC4 88 5.6 492.800 1.580 778.746


600
6175
5 600 25 PCC5 20 7.375 147.500 3.858 569.059

6 10 LEGGED
1400 12 PCC6 30 18.4 552 0.889 490.667
Varries

7
co
8 LEGGED 16 PCC7 11 61.86 680.48 1.580 1075.325
co 7400
Varries

8 co 8 LEGGED
co 4400 16 PCC8 11 37.86 416.48 1.580 658.140

9 1500 10 MESH 4 48.47 193.88 0.617 119.682

100 mm pitch
1500
Total 7227.174
BAR BENDING SCHEDULE OF STOPPER BLOCK
Bar Total Unit Total
dia. Bar
SN Sketch Nos length length weight(k Weight
(mm) mark
(m) (m) g/m) (Kg)
1 500
16 AST1 10 2.225 22.25 1.580 35.16
1725

2 500
12 AST2 10 2.46 24.60 0.889 21.87
1960

3 550 8 AST3 3 2.2 6.60 0.395 2.61


100 hook
1450 Each stopper Block 59.63
Babai River Bridge

Total in 2 stopper 119.27


Babai River Bridge

BAR BENDING SCHEDULE OF Bearing Block (Pedestal)


Bar Total Unit Total
dia. Bar
SN Sketch Nos length length weight(k Weight
(mm) mark
(m) (m) g/m) (Kg)

1 1050 16 ACP1 25 1.25 31.25 1.580 49.38

200

2 1050 16 ACP2 25 1.25 31.25 1.580 49.38


200
900
3 900 12 ACP3 3 1.9 5.70 0.889 5.07
100 hook

800 10 MESH 2 20.51 41.03 0.617 25.33

800
In one
pedestal 129.16
Total in 2 pedestal 258.31
Babai River Bridge

BAR BENDING SCHEDULE OF ABUTMENT AND BACK WALL


Bar Unit Total
dia. Bar Total
SN Sketch Nos length weight Weight
(mm) mark length (m)
(m) (kg/m) (Kg)
1 6940.00000000003
25 AS1 91 8.19 745.29 3.858 2875.35
1250

2 6960.00000000003 20 AS2 71 7.96 565.16 2.469 1395.46


1000

3 10884 16 AS3 57 12.47 710.68 1.580 1123.04


1384
100

4 1250 16 AS4 51 1.45 73.95 1.580 116.86


100

5 1250 12 AS5 134 5.15 690.10 0.889 613.42


3900

6 10884
300 12 AS6 18 22.57 406.22 0.889 361.09
100

7 550 10 AS7 111 0.55 61.05 0.617 37.69

8 600 10 AS8 56 0.60 33.60 0.617 20.74

9 10900 20 AS9 1 10.90 10.90 2.469 26.91

10 10900 16 AS10 2 10.90 21.80 1.580 34.45

11 200 16 AS11 56 0.80 44.80 1.580 70.80


600
Total 6675.801
BAR BENDING SCHEDULE OF ABUTMENT CAP
Bar Unit Total
dia. Bar Total
SN Sketch Nos length weight Weight
(mm) mark length (m)
(m) (kg/m) (Kg)
1 10900 16 AC1 39 10.9 425.10 1.580 671.76

2 1800
16 AC2 74 5.6 414.40 1.580 654.85
900
100

3 1400 10 AC3 4 46.40 185.59 0.617 114.56


100 mm pitch

1400
Total 1441.18
BAR BENDING SCHEDULE OF WING WALL
Bar Unit Total
dia. Bar Total
SN Sketch Nos length weight Weight
(mm) mark length (m)
(m) (kg/m) (Kg)
1 3700 12 ARW1 28 3.9 109.20 0.889 97.07
100
2 `
1450
4480 25 ARW2 4 7.43 29.72 3.858 114.66
1500

3 2800avg 12 ARW3 88 2.8 246.40 0.889 219.02

4 1850avg 16 ARW4 56 1.85 103.60 1.580 163.71


Total 594.46

BAR BENDING SCHEDULE OF STOPPER BLOCK


Bar Unit Total
dia. Bar Total
SN Sketch Nos length weight Weight
(mm) mark length (m)
(m) (kg/m) (Kg)
1 500
16 AST1 10 2.225 22.25 1.580 35.16
1725

2 500
12 AST2 10 2.46 24.60 0.889 21.87
1960

3 550 8 AST3 3 2.2 6.60 0.395 2.61


100 hook
1450 Each stopper Block
59.63
Total in 2 stopper 119.27
Babai River Bridge

BAR BENDING SCHEDULE OF Bearing Block (Pedestal)


Bar Unit Total
dia. Bar Total
SN Sketch Nos length weight Weight
(mm) mark length (m)
(m) (kg/m) (Kg)

1 1050 16 ACP1 25 1.25 31.25 1.580 49.38

200

2 1050 16 ACP2 25 1.25 31.25 1.580 49.38


200
900
3 900 12 ACP3 3 1.9 5.70 0.889 5.07
100 hook

800 10 MESH 2 20.51 41.03 0.617 25.33

800
In one
pedestal 129.16
Total in 2 pedestal 258.31
BAR BENDING SCHEDULE oF Approach Slab
Bar Unit Total
dia. Bar Total
SN Sketch Nos length weight Weight
(mm) mark length (m)
(m) (kg/m) (Kg)
1 3420 12 AS1 74 3.82 282.68 0.889 251.27
200
3420
2 200 12 AS2 74 3.82 282.68 0.889 251.27

3 7420 12 AS3 100 7.42 742.00 0.889 659.56


Total 1162.10
BAR BENDING SCHEDULE oF Pile Cap
Bar Unit Total
dia. Bar Total
SN Sketch Nos length weight Weight
(mm) mark length (m)
(m) (kg/m) (Kg)
1 10300 32 PC1 85 12.1 1028.50 6.321 6501.14
900

2 11200
900 32 PC2 90 13 1170.00 6.321 7395.56

3 10300
900 16 PC3 50 12.1 605.00 1.580 956.05

4 11200
1080 20 PC4 34.333 13 446.33 2.469 1102.06
TOTAL 15954.80

BAR BENDING SCHEDULE oF Pile


Bar Unit Total
dia. Bar Total
SN Sketch Nos length weight Weight
(mm) mark length (m)
(m) (kg/m) (Kg)
1 1250 25 P1 18 17.45 314.1 3.858 1211.81
16200

2 12 P2 111 2.87 318.61 0.889 283.21

Total 1495.01
Babai Bridge

Provincial Government
Ghorahi Sub-Metropolitan City
Office of Municipal Executive
Ghorahi Dang
Name of Project: Construction of Babai River along ward no 5 Dharna, Dang
PAVEMENT QUANTITY CALCULATION SHEET

X-sectional area from drawing Avg. X-sectional area from drawing Quantity
SN Chainage Capping Sub Sub Capping Sub Sub Length Capping
Base Base Sub Grade Sub Base Base
Layer Grade Base Layer Grade Base Layer
1 0 3.75 1.125 1.5 1.5 3.75 1.125 1.5 1.5
2 20 3.75 1.125 1.5 1.5 3.75 1.125 1.5 1.5 20 75 22.5 30 30
3 40 3.75 1.125 1.5 1.5 3.75 1.125 1.5 1.5 20 75 22.5 30 30
4 60 3.75 1.125 1.5 1.5 3.75 1.125 1.5 1.5 20 75 22.5 30 30
5 80 3.75 1.125 1.5 1.5 3.75 1.125 1.5 1.5 20 75 22.5 30 30
6 100 3.75 1.125 1.5 1.5 3.75 1.125 1.5 1.5 20 75 22.5 30 30
7 120 3.75 1.125 1.5 1.5 3.75 1.125 1.5 1.5 20 75 22.5 30 30
8 140 3.75 1.125 1.5 1.5 3.75 1.125 1.5 1.5 20 75 22.5 30 30
9 156.1 3.75 1.125 1.5 1.5 3.75 1.125 1.5 1.5 16.1 75 22.5 30 30
BRIDGE (156.1-314.15)
10 314.15 3.75 1.125 1.5 1.5 3.75 1.125 1.5 1.5
11 320 3.75 1.125 1.5 1.5 3.75 1.125 1.5 1.5 5.85 75 22.5 30 30
12 340 3.75 1.125 1.5 1.5 3.75 1.125 1.5 1.5 20 75 22.5 30 30
13 360 3.75 1.125 1.5 1.5 3.75 1.125 1.5 1.5 20 75 22.5 30 30
14 380 3.75 1.125 1.5 1.5 3.75 1.125 1.5 1.5 20 75 22.5 30 30
15 400 3.75 1.125 1.5 1.5 3.75 1.125 1.5 1.5 20 75 22.5 30 30
16 420 3.75 1.125 1.5 1.5 3.75 1.125 1.5 1.5 20 75 22.5 30 30
17 440 3.75 1.125 1.5 1.5 3.75 1.125 1.5 1.5 20 75 22.5 30 30
18 460 3.75 1.125 1.5 1.5 3.75 1.125 1.5 1.5 20 75 22.5 30 30
19 476 3.75 1.125 1.5 1.5 3.75 1.125 1.5 1.5 16 75 22.5 30 30
TOTAL 1275 382.5 510 510
Babai Bridge

Provincial Government
Ghorahi Sub-Metropolitan City
Office of Municipal Executive
Ghorahi Dang
Name of Project: Construction of Babai River along ward no 5 Dharna, Dang
EARTHWORK QUANTITY CALCULATION SHEET
X-sectional area Avg. X-sectional
Quantity
SN Chainage from drawing area from drawing Length
Cut Fill Cut Fill Cut Fill
1 0+000 0 1.505 0
2 0+020 0 9.585 0 5.545 20 0
3 0+040 0 49.548 0 29.5665 20 0 591.33
4 0+060 0 52.8 0 51.174 20 0 1023.48
5 0+080 0 61.525 0 57.1625 20 0 1143.25
6 0+100 0 75.23 0 68.3775 20 0 1367.55
7 0+120 0 74.825 0 75.0275 20 0 1500.55
8 0+140 0 69.243 0 72.034 20 0 1440.68
9 0+156 0 76.725 0 72.984 16.1 0 1175.0424
BRIDGE (156.1-314.15)
10 0+314 0 14.095 0
11 0+320 0 13.008 0 13.5515 5.85 0 79.276275
12 0+340 0 65.988 0 39.498 20 0 789.96
13 0+360 0 65.705 0 65.8465 20 0 1316.93
14 0+380 0 34.97 0 50.3375 20 0 1006.75
15 0+400 0 7.945 0 21.4575 20 0 429.15
16 0+420 0 7.945 0 7.945 20 0 158.9
17 0+440 0 15.963 0 11.954 20 0 239.08
18 0+460 4 1.938 0 8.9505 20 0 179.01
19 0+476 6.713 1.125 5.3565 1.5315 16 107.13 24.504
TOTAL 107.13 12465.4427
Ghorahi Sub-Metropolitan City
Office of the Municipal Exctutive
Ghorahi, Dang
Province No.5, Nepal
Rate Analysis for F.Y 2076/077
1) Labour 4) Material
District Unit district
S.N. Description Unit S.N. Description Unit Remark
Rate rate
1 Skilled md 850 1 Sand m 3
2140.00
2 Semiskilled md 600 2 Rubble (stone) m3 2340.00
3 Unskilled (Labour) md 520 3 Cement mt. 12580.00
4 Operator md 755 4 Water lit. 0.15
5 Engineer md 1400 5 Crushed Aggregate
6 Technician md 1064.40 5.a 10 mm ( Small) m3 2240.00
5.b 20 mm ( Intermediate) m3 2190.00
5.c 40 mm ( Large ) m3 2140.00
2) Fuel and 5.d Chips m3 1975.00
Lubricant
1 Diesel lit. 87.00 6 RCC Hume Pipes
2 Petrol lit. 101.00 6.a 300 mm diameter rm 3080.00
6.b 450 mm diameter rm 4400.00
6.c 600 mm diameter rm 6050.00
6.d 900 mm diameter rm 10450.00
3) Equipment 7 Reinforcement
DoR hire
S.No. Description Unit With Vat 7.a 8-16 mm dia mt. 73000.00
rate
7.b 16-32 mm dia mt. 74000.00
1 Truck ( 3 tonnes) hr. 460.00 8 Binding Wire
2 Truck ( 5 tonnes) hr. 630.00 8.a Binding wire Black kg 85.90
3 Truck ( 8 tonnes) hr. 1290.00 8.b Binding wire White kg 85.90
4 Grader ( 75 HP) hr. 1500.00 9 G.I Wire heavy coated
5 Pump 10cm dia hr. 170.00 9.a 7 gauge kg 100.00
6 Vibrator Roller hr. 800.00 9.b 10 gauge kg 100.00
7 Roller ( 8 - 10 ton) hr. 700.00 9.c 12 gauge kg 100.00
8 Water bowser hr. 550.00 10 Geo - Textile Sqm 280.00
Loader hr. rm
GI Pipe 50mm medium class 670.00
9 1000.00 11
10 Boiler hr. 140.00 12 MS steel mt.
11 Sprayer hr. 260.00 13 Enamel ltr 500.00
12 Air compresser hr. 130.00 14 Jute kg 75.00
13 Hand Sprayer hr. 260.00 15 Plywood 9mm thick sqm 396.00
14 Aggregate Spreader hr. 130.00 16 Nuts & bolts kg 200.00
15 Pneumatic Tyred Roller hr. 1200.00 17 bentonite kg 25.00
16 mixer hr. 470.00 18 Planks 38mm thick. m3 35320.00
17 Vibrator hr. 150.00 19 struts, ballies, etc. m3 35320.00
18 Generator hr. 150.00 20 Nails,spikes,etc. kg 100.00
19 Bitumen Distributor hr. 1280.00 21 Graded filter material m3 1165.56
20 Chip Spreader hr. 130.00 22 timber m3 49448.00
21 Tractor hr. 350.00 23 bearing no. 60000.00
22 20t crane hr. 3500.00 24 expansion joint rm 17825.00
23 Boring equipment with pump and all m3
suitable material 300.00
accessories. hr. 3500.00 25
24 Crane for handling reinforcement m3
hr. 3500.00 subbase aggregate 925.00
cage and tremie pipe 26
25 Gas cutter hr. 1150.00 27 aggregate m3 1400.00
26 Welding machine hr. 1150.00 28 Grass slips no 50.00
27 10t-crane with grab & accessories hr. 3500.00 29 Line string m2 100.00
28 Screw jack hr. 25.00 Prestressed additional
29 Electical heating plate hr. 50.00 30 tendon/wire t 130000
30 Electrical hand drill hr. 50.00 31 tendon sheath m 330
31 Asphalt mixing plant hr. 700.00 32 anchorage assembly no 8200
32 Asphalt paver hr. 260.00 33 Bitumen tonne 89550
33 Steel tyred roller hr. 440.00 34 Brick no 11.035
34 Tipper trucks 5 cum hr. 1454.00 35 Plywood 12mm thick sqm 626.00
35 Prestressing jack hr. 800 36 Stone dust cum 1400.00
36 Grouting Pump hr. 800 37 Road marking
37 Drilling machine hr. 130
38 Excavator 111 to 150 HP hr. 3597.99
39 Excavator with breaker hr. 2100
40 Dozer hr. 3000
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang

Rate Analysis

Description of Work: Earthwork Excavation in Cutting., Roadway Excavation in all types of Soil by Mechanical Means ., Road way Excavation in all types of soil as per Drawing and technical specifications including removal of stumps and
360 cum
other deleterious matter, all lifts and lead as per Drawing and instruction of the Engineer.
Spec. cl. No: 905
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.1.I.B Skilled day 1 850 850.0 Hydraulic Excavator hour 6 3597.99 21587.9
Unskilled day 3 520 1560.0
Sub total of A = 2410.0 Sub total of B = 0.0 Sub total of C = 21587.9 Sub total of D = 0.0
Sub total of A +B + C = 23997.9 Sub total of A + B + C + D= 23997.9 Contractor's overhead expenses 15% = 3599.7 Norms Rate = 27597.6
Unit Rate = 76.66

Excavation for Structures Foundation, Earth work in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and other deleterious matter and backfilling with approved
90 cum
Material as per Drawing and Technical Specifications., Ordinary Rock (not requiring blasting) by Mechanical Means, Depth upto 3 m
Spec. cl. No: 907
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.4.II.B Skilled day 1 850 850.0 Hydraulic Excavator hour 6 3597.99 21587.9
Unskilled day 3 520 1560.0
Sub total of A = 2410.0 Sub total of B = 0.0 Sub total of C = 21587.9 Sub total of D = 0.0
Sub total of A +B + C = 23997.9 Sub total of A + B + C + D= 23997.9 Contractor's overhead expenses 15% = 3599.7 Norms Rate = 27597.6
Unit Rate = 306.64

Description of Work:
Providing and laying of hand pack Stone soling with 150 to 200 mm thick stones and packing with smaller stone on prepared surface as per Drawing and Technical Specifications. 5 Cum
Spec. cl. No: N/A
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
10.8. Skilled day 6 850.0 5100.0 Stone cum 6 2340.00 14040
Unskilled day 12 520 6240.0
Sub total of A = 11340.0 Sub total of B = 14040.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 25380.0 Sub total of A + B + C + D= 25380.0 Contractor's overhead expenses 15% = 3807.0 Norms Rate = 29187.0
Unit Rate = 5837.4

Description of Work:
Providing and laying of Plain Cement Concrete M 10 ( or 1:3:6 for nominal mix) in Foundation complete as per Drawing and Technical Specifications. 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.1 Skilled day 2 850.0 1700.0 Aggregate 40 mm cum 13.5 2140.00 28890 Concrete Mixer hour 6 470.00 2820.0
Unskilled day 22 520 11440.0 Coarse Sand cum 6.75 2140.00 14445 Generator hour 6 150.00 900.0
Cement tonne 3.45 12580.00 43401
Water KL 2 200 400
Sub total of A = 13140.0 Sub total of B = 87136.0 Sub total of C = 3720.0 Sub total of D = 0.0
Sub total of A +B + C = 103996.0 Sub total of A + B + C + D= 103996.0 Contractor's overhead expenses 15% = 15599.4 Norms Rate = 119595.4
Unit Rate = 7973.03

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, RCC Grade M 35, Height upto 5 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang

Rate Analysis
Basic Cost of Labour,
Material & Equipment
20.4.H.p Skilled day 3 850.0 2550.0 Cement tonne 6.33 12580.00 79631.4 Concrete Mixer hour 6 470.00 2820.0 0.0
(a+b+c) of Item 20.2
(H)
Add 10 % of cost of
Material, Labour and
Unskilled day 30 520 15600.0 Coarse Sand cum 6.75 2140.00 14445 Generator hour 6 150.00 900.0 15395.4
Equipment (a+b+c) for
Formwork
Aggregate 20 mm cum 8.1 2190.00 17739
Aggregate 10 mm cum 5.4 2240.00 12096
Water KL 3 150 450
Admixture kg 25.32 305 7722.6
Sub total of A = 18150.0 Sub total of B = 132084.0 Sub total of C = 3720.0 Sub total of D = 15395.4
Sub total of A +B + C = 153954.0 Sub total of A + B + C + D= 169349.4 Contractor's overhead expenses 15% = 25402.4 Norms Rate = 194751.8
Unit Rate = 12983.45

Description of Work:
Providing and laying Stone Masonry work in cement mortar 1:4 in structure complete as per Drawing and Technical, Random Rubble Masonry, Using Concrete Mixer 5 cum
Spec. cl. No: 2607
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
26.5.A_a Skilled day 7 850.0 5950.0 Stone cum 5.75 2340.00 13455 Concrete Mixer hr 0.75 470.00 352.5
Unskilled day 15 520 7800.0 Cement tonne 0.66 12580.00 8302.8
Sand cum 1.85 2140.00 3959
Water KL 1 150 150
@ 5 per cent of cost of Labour and material for scaffolding 1980.8
Sub total of A = 13750.0 Sub total of B = 27847.6 Sub total of C = 352.5 Sub total of D = 0.0
Sub total of A +B + C = 41950.1 Sub total of A + B + C + D= 41950.1 Contractor's overhead expenses 15% = 6292.5 Norms Rate = 48242.7
Unit Rate = 9648.53

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 mm X 120 mm,, Box size 3 X 1 X 1 m ( 16 sqm) 6 cum
Spec. cl. No: 2401
Norms
Labour (A) Material (B) Equipment (C) Formworks (D)
No.
Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.A.i Unskilled day 7 850.0 5950.0 Mesh wire kg 70.2 100.00 7020
Skilled day 3 520 1560.0 Selvedge Wire kg 7.82 85.90 671.738
Binding Wire kg 3.62 85.90 310.958
Boulder cum 6.6 2340.00 15444
Sub total of A = 7510.0 Sub total of B = 23446.7 SubContractor's
total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 30956.7 Sub total of A + B + C + D= 30956.7 overhead expenses 4643.5 Norms Rate = 35600.2
15% = Unit Rate = 5933.37

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 mm X 120 mm,, Box size 2 X 1 X 1 m ( 11 sqm) 6 cum
Spec. cl. No: 2401
Norms
Labour (A) Material (B) Equipment (C) Formworks (D)
No.
Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.A.ii Unskilled day 7 850.0 5950.0 Mesh wire kg 72.45 100.00 7245
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang

Rate Analysis
Skilled day 3 520.0 1560.0 Selvedge Wire kg 8.88 85.90 762.792
Binding Wire kg 3.9 85.90 335.01
Boulder cum 6.6 2340.00 15444
Sub total of A = 7510.0 Sub total of B = 23786.8 SubContractor's
total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 31296.8 Sub total of A + B + C + D= 31296.8 overhead expenses 4694.5 Norms Rate = 35991.3
15% = Unit Rate = 5998.55

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 mm X 120 mm,, Box size 1.5 X 1 X 1 m ( 9 sqm ) 6 cum
Spec. cl. No: 2401
Norms
Labour (A) Material (B) Equipment (C) Formworks (D)
No.
Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.A.iii Unskilled day 8 850.0 6800.0 Mesh wire kg 79 100.00 7900
Skilled day 3 520.0 1560.0 Selvedge Wire kg 10.8 85.90 927.72
Binding Wire kg 5 85.90 429.5
Boulder cum 6.6 2340.00 15444
Sub total of A = 8360.0 Sub total of B = 24701.2 SubContractor's
total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 33061.2 Sub total of A + B + C + D= 33061.2 overhead expenses 4959.2 Norms Rate = 38020.4
15% = Unit Rate = 6336.73

Description of Work:
Laying and fixing of Geo-Textile all complete as per specification., Providing and laying and fixing of Geo-membrane all complete as per specification. 300 sqm
Spec. cl. No: 2404
Norms
Labour (A) Material (B) Equipment (C) Formworks (D)
No.
Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.06 Skilled day 1 850.0 850.0 Geotextile sqm 360 280.00 100800

Unskilled day 2 520.0 1040.0


Sub
Sub
total of 1890.0 Sub total of B = 100800.0 SubContractor's
total of C = 0.0 Sub total of D = 0.0
totalAof
= 102690.0 Sub total of A + B + C + D= 102690.0 overhead expenses 15403.5 Norms Rate = 118093.5
A +B +
15% = Unit Rate = 393.65
C=

Description of Work:
Construction of Subgrade and Earthen Shoulders with approved Material ( capping layer), Providing and laying sub-grade and earthen shoulders with approved Material obtained from borrow pits with all lifts & leads as
600 sqm
per Drawing and Technical Specifications.
Spec. cl. No: 1004
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
10.3.A Skilled day 1 850.0 850.0 Water KL 72 150 10800 Mortar Grader hour 6 1500.00 9000.0
Unskilled day 6 520.0 3120.0 Capping Layer Material cum 750 940 705000 Vibratory Road Roller hour 6 800.00 4800.0
Sub total of A = 3970.0 Sub total of B = 715800.0 Sub total of C = 13800.0 Sub total of D = 0.0
Sub total of A +B + C = 733570.0 Sub total of A + B + C + D= 733570.0 Contractor's overhead expenses 15% = 110035.5 Norms Rate = 843605.5
Unit Rate = 1406.01

Description of Work: Compacting Original Ground, Compacting original ground supporting sub-grade, Loosening of the ground upto a level of 500 mm below the sub-grade level, watered, graded and compacted in layers as per Drawing and
600 sqm
Spec. cl. No: 1003, Technical Specifications.
1005
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang

Rate Analysis
10.4.I_a Skilled day 1 850.0 850.0 Water KL 24 150 3600 Tractor with Ripper hour 12 1142 13704.0
Unskilled day 5 520.0 2600.0 Mortar Grader hour 6 1500.00 9000.0
Vibratory Road Roller hour 12 800.00 9600.0
Sub total of A = 3450.0 Sub total of B = 3600.0 Sub total of C = 32304.0 Sub total of D = 0.0
Sub total of A +B + C = 39354.0 Sub total of A + B + C + D= 39354.0 Contractor's overhead expenses 15% = 5903.1 Norms Rate = 45257.1
Unit Rate = 75.43

Description of Work:
Providing and laying granular sub-base on prepared surface, mixing at OMC, and compacting to achieve the desired density, complete as per Drawing and Technical Specifications., By Mechanical means 300 cum
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Sub-base Material S1 type or
12.1.A Skilled day 2 850.0 1700.0 cum 384 925.00 355200 Mortar Grader hour 6 1500.00 9000.0
S2 type

Unskilled day 12 520.0 6240.0 Water KL 18 150 2700 Vibratory Road Roller hour 12 800.00 9600.0
Tractor / Loader hour 12 1000.00 12000.0
Sub total of A = 7940.0 Sub total of B = 357900.0 Sub total of C = 30600.0 Sub total of D = 0.0
Sub total of A +B + C = 396440.0 Sub total of A + B + C + D= 396440.0 Contractor's overhead expenses 15% = 59466.0 Norms Rate = 455906.0
Unit Rate = 1519.69

Description of Work: Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC laying in uniform layers in sub- base / base course on well
225 cum
prepared surface and compacting to achieve required density as per Drawing and Technical Specifications., Base course with B1 material, Vibratory Road Roller
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Macadam Aggregate 45-22.4
12.14.A Skilled day 3 850.0 2550.0 cum 89.1 2140.00 190674 Wet Mix Plant hour 9 1623 14607.0
mm
Macadam Aggregate 22.4-
Unskilled day 10 520.0 5200.0 cum 118.8 2190.00 260172 Electric Generator hour 6 150.00 900.0
2.36 mm
Macadam Aggregate 2.36
cum 89.1 2240.00 199584 Paver Finisher hour 6 4775 28650.0
mm-75 micron

Water KL 18 150 2700 Vibratory Road Roller hour 6 800.00 4800.0


Sub total of A = 7750.0 Sub total of B = 653130.0 Sub total of C = 48957.0 Sub total of D = 0.0
Sub total of A +B + C = 709837.0 Sub total of A + B + C + D= 709837.0 Contractor's overhead expenses 15% = 106475.6 Norms Rate = 816312.6
Unit Rate = 3628.06

Description of Work:
Tack Coat, Tack coat with Bitumen By Mechanical Means, Providing and applying tack coat with hot Bitumen at specified rate on the prepared non-bituminous surfaces including cleaning as per Technical Speciation . 5000 lit
Spec. cl. No: 1302
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.2.A Skilled day 3 850.0 2550.0 Bitumen tonne 5.25 89550 470137.5 Air Compressor hour 6 130.00 780.0
Unskilled day 20 520.0 10400.0 Bitumen Distributor hour 6 1280.00 7680.0
Boiler hour 6 140.00 840.0
Generator hour 6 150.00 900.0
Sub total of A = 12950.0 Sub total of B = 470137.5 Sub total of C = 10200.0 Sub total of D = 0.0
Sub total of A +B + C = 493287.5 Sub total of A + B + C + D= 493287.5 Contractor's overhead expenses 15% = 73993.1 Norms Rate = 567280.6
Unit Rate = 113.46
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang

Rate Analysis
Description of Work: Bituminous Concrete / Asphalt Concrete, Providing and laying Bituminous concrete/ Asphalt concrete using crushed aggregates of specified grading, premixed with bituminous binder and filler as per Drawing and
95.5 cum
Technical Specifications, Grading - I-19 mm (Nominal Size)
Spec. cl. No: 1309
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.6 Unskilled day 15 850.0 12750.0 Bitumen tonne 12.94 89550 1158777 Batch mix HMP hour 6 14122 84732.0
Skilled day 5 520.0 2600.0 Aggregate Paver Finisher hour 6 260.00 1560.0
Grading - I-19 mm (Nominal
Generator hour 6 150.00 900.0
Size)
Smooth Wheeled
Aggregate 20 - 10 mm cum 49.48 2190.00 108361.2 hour 12 1200.00 14400.0
Roller
Aggregate 10 - 5 mm cum 32.52 2240.00 72844.8 Pneumatic Roller hour 6 1200.00 7200.0
Aggregate 5 mm and below cum 56.55 2240.00 126672
Filler [cement] tonne 2.83 12580.00 35601.4
Sub total of A = 15350.0 Sub total of B = 1502256.4 Sub total of C = 108792.0 Sub total of D = 0.0
Sub total of A +B + C = 1626398.4 Sub total of A + B + C + D= 1626398.4 Contractor's overhead expenses 15% = 243959.8 Norms Rate = 1870358.2
Unit Rate = 19584.9

Description of Work:
Providing and laying , fitting and placing un-coated Mild steel / HYSD reinforcement complete in foundation as per drawing and technical specification 1 tonne
Spec. cl. No: 2014
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Skilled
20.3 (Blacksmith day 4 850.0 3400.0 MS bars tonne 1.1 74000.00 81400
)
Unskilled day 9 520.0 4680.0 Binding Wire Kg 8 92 736
Sub total of A = 8080.0 Sub total of B = 82136.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 90216.0 Sub total of A + B + C + D= 90216.0 Contractor's overhead expenses 15% = 13532.4 Norms Rate = 103748.4
Unit Rate = 103748.4

Description of Work:
Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing and Technical Specifications., RCC Grade M 35 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.2.H Skilled day 3 850.0 2550.0 Cement tonne 6.33 12580.00 79631.4 Concrete Mixer hour 6 470.00 2820.0 @ 3 per cent on a+b+c 4618.6
Unskilled day 30 520.0 15600.0 Coarse Sand cum 6.75 2140.00 14445 Generator hour 6 150.00 900.0
Aggregate 20 mm cum 8.1 2190.00 17739
Aggregate 10 mm cum 5.4 2240.00 12096
Water KL 3 150 450
Admixture kg 25.32 305 7722.6
Sub total of A = 18150.0 Sub total of B = 132084.0 Sub total of C = 3720.0 Sub total of D = 4618.6
Sub total of A +B + C = 153954.0 Sub total of A + B + C + D= 158572.6 Contractor's overhead expenses 15% = 23785.9 Norms Rate = 182358.5
Unit Rate = 12157.23

Description of Work:
Providing, Boring and installing bored cast-in-situ RCC Pile excluding Reinforcement and Concrete in all types of Rock including Bentonite and other consumable and removal of excavated material with necessary lifts and
5 meter
lead all complete as per Drawing and Technical Specifications ., Pile diameter-1000 mm
Spec. cl. No: 1612
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang

Rate Analysis
Piling Rig with all
16.2.E Skilled day 2 850.0 1700.0 Bentonite kg 220 25.00 5500 hour 6 3500.00 21000.0
Accessories
Unskilled day 20 520.0 10400.0 Crane hour 6 3500.00 21000.0
Bentonite Pump hour 6 800 4800.0
Sub total of A = 12100.0 Sub total of B = 5500.0 Sub total of C = 46800.0 Sub total of D = 0.0
Sub total of A +B + C = 64400.0 Sub total of A + B + C + D= 64400.0 Contractor's overhead expenses 15% = 9660.0 Norms Rate = 74060.0
Unit Rate = 14812

Description of Work:
Supplying, fitting and fixing in position true to line and level POT-PTFE bearing consisting of a metal piston supported by a disc or unreinforced elastomer confined within a metal cylinder, sealing rings, dust seals, PTFE
1No
surface sliding against stainless steel mating surface, complete assembly to be of cast steel/fabricated structural steel, metal and elastomer elements as per Drawing and Technical Specifications.
Spec. cl. No: 1902
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount

Pot type bearing assembly


consisting of a metal piston
supported by a disc, PTFE
pads providing sliding
surfaces against stainless steel
mating together with cast steel
19.6 Unskilled day 2 850.0 1700.0 assemblies/fabricated nos 1 60000.00 60000
structural steel assemblies
duly painted with all
components as per clause
2006 and complete as per
drawings and Technical
Specifications.

Add 1 per cent of cost of


bearing assembly for
Skilled day 1 520.0 520.0 600.0
foundation anchorage bolts
and consumables.
Sub total of A = 2220.0 Sub total of B = 60600.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 62820.0 Sub total of A + B + C + D= 62820.0 Contractor's overhead expenses 15% = 9423.0 Norms Rate = 72243.0
Unit Rate = 72243.0

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in super-structure as per drawing and Technical Specification, PSC Grade M-45 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.F Skilled day 4 850.0 3400.0 Cement tonne 6.975 12580.00 87745.5 Concrete Mixer hour 6 470.00 2820.0
Unskilled day 33 520.0 17160.0 Coarse Sand cum 6.75 2140.00 14445 Generator hour 6 150.00 900.0
Aggregate 20 mm cum 8.1 2190.00 17739
Aggregate 10 mm cum 5.4 2240.00 12096
Admixture kg 27.9 305 8509.5
Water KL 3 150 450
Sub total of A = 20560.0 Sub total of B = 140985.0 Sub total of C = 3720.0 Sub total of D = 0.0
Sub total of A +B + C = 165265.0 Sub total of A + B + C + D= 165265.0 Contractor's overhead expenses 15% = 24789.8 Norms Rate = 190054.8
Unit Rate = 12670.32

Description of Work: Painting Two Coats on Steel Surfaces, Providing and applying two coats of ready mix paint of approved brand on steel surface after through cleaning of surface to give an even shade as per Drawing and Technical
20 sqm
Specifications.
Spec. cl. No: 1501
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang

Rate Analysis
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Skilled
15.5 day 1 850.0 850.0 Paint liter 2.5 500.00 1250
(Painter)
Add @ 1 per cent on cost of
Unskilled day 1 520.0 520.0 12.5
Material for scaffolding
Add @ 5 per cent cost of
Labour and Materials to
prepare the surface by filling
minutes roughness on the 131.0
surface and priming the
surface before laying 2 coats
of painting.
Sub total of A = 1370.0 Sub total of B = 1393.5 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 2763.5 Sub total of A + B + C + D= 2763.5 Contractor's overhead expenses 15% = 414.5 Norms Rate = 3178.0
Unit Rate = 158.9

Description of Work:
Retro-Reflectorized Traffic Signs, Providing and fixing of retro- reflectorized warning, Regulatory and informatory sign as per specification clause 1501 made of high intensity grade sheeting , fixed over aluminum sheeting,
1.5 mm thick supported on a 50 mm internal dia steel tube or mild steel angle iron post 75 mm x 40 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M 10/40 grade cement concrete 30 10 no
Spec. cl. No: 1501 cm x 30 cm , 30 cm below ground level or as per Drawing and Technical Specifications., 80 mm * 60 mm rectangular
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
15.2 Skilled day 1 850.0 850.0 Excavation for foundation cum 0.54 306.64 165.6 Tractor - Trolley hour 3 1086.27 3258.8
Unskilled day 3 520.0 1560.0 Cement concrete M 10 grade cum 0.27 7973.03 2152.7
Painting angle iron post two
sqm 8.78 154 1352.1
coats

Mild Steel Angle Iron 75 * 40


kg 204 80 16320
* 6 mm, 3 m long @ 6.8 kg/m

Aluminum sheeting fixed with


encapsulated lens type
reflective sheeting of size
including lettering and signs
as applicable

Add 2 per cent of cost of angle


iron towards cost of drilling 326.4
holes, nuts, bolts etc.

80 mm * 60 mm rectangular sqm 4.8 80 384


Sub total of A = 2410.0 Sub total of B = 20700.8 Sub total of C = 3258.8 Sub total of D = 0.0
Sub total of A +B + C = 26369.6 Sub total of A + B + C + D= 26369.6 Contractor's overhead expenses 15% = 3955.4 Norms Rate = 30325.1
Unit Rate = 3032.51

Description of Work:
Painting Two Coats on Concrete Surfaces, Providing and Painting two coats after filling the surface with synthetic enamel paint in all shades on concrete / plaster surfaces as per Drawing and Technical Specifications. 10 sqm
Spec. cl. No: 1501
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Skilled
15.4 day 3 850.0 2550.0 Paint liter 6 500.00 3000
(Painter)
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang

Rate Analysis
Add for scaffolding @ 1 per
Unskilled day 2 520.0 1040.0 cent of Labour cost where 35.9
required

Add @ 5 per cent cost of


Labour and Materials to
prepare the surface by filling
minutes roughness on the 329.5
surface and priming the
surface before laying 2 coats
of painting.
Sub total of A = 3590.0 Sub total of B = 3365.4 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 6955.4 Sub total of A + B + C + D= 6955.4 Contractor's overhead expenses 15% = 1043.3 Norms Rate = 7998.7
Unit Rate = 799.87

Description of Work:
Road Marking with Hot Applied Thermoplastic Compound with Reflectorizing Glass Beads on Bituminous Surface, On smooth surface (similar to Asphalt concrete and rigid pavement), Providing and laying of hot applied
400 sqm
thermoplastic compound at least 2 mm thick including reflectorizing glass beads as per DOR Traffic sign manual/ Specifications .The finished surface to be level, uniform and free from streaks and holes.
Spec. cl. No: 1504
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Skilled Hot applied thermoplastic Road Marking
15.9.i day 2 850.0 1700.0 liter 930 150 139500 hour 10 1003 10030.0
(Painter) compound Machine
Unskilled day 4 520.0 2080.0 Reflectorizing Glass Beads kg 100 160 16000 Tractor - Trolley hour 10 350.00 3500.0
Sub total of A = 3780.0 Sub total of B = 155500.0 Sub total of C = 13530.0 Sub total of D = 0.0
Sub total of A +B + C = 172810.0 Sub total of A + B + C + D= 172810.0 Contractor's overhead expenses 15% = 25921.5 Norms Rate = 198731.5
Unit Rate = 496.83

Description of Work:
Painting Lines, Dashes, Arrows etc. on Roads in Two Coats, Providing required material and Painting lines, dashes, arrows etc. on roads in two coats on new work with ready mixed road marking paint conforming to NS
10 sqm
408/ IS 164 on bituminous surface, including cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control as per Drawing and Technical Specifications., Up to 10 cm in width
Spec. cl. No: 1503
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Skilled
15.7.ii day 1 850.0 850.0 Road Marking Paint liter 1.48 500.00 740
(Painter)
Unskilled day 2 520.0 1040.0
Sub total of A = 1890.0 Sub total of B = 740.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 2630.0 Sub total of A + B + C + D= 2630.0 Contractor's overhead expenses 15% = 394.5 Norms Rate = 3024.5
Unit Rate = 302.45

Description of Work:
Providing and installation of project signboards with size of 1.8 x 1.2 m as per specification and instruction of engineer. 1 nos
Spec. cl. No: 110
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Project signboards with size of
1.8 x 1.2 m having details of
1.3 Skilled day 0.1 850.0 85.0 contract in the format and nos 1 1000 1000
wording as directed by the
Engineer
Unskilled day 0.5 520.0 260.0
Sub total of A = 345.0 Sub total of B = 1000.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 1345.0 Sub total of A + B + C + D= 1345.0 Contractor's overhead expenses 15% = 201.8 Norms Rate = 1546.8
Unit Rate = 1546.75
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang

Rate Analysis
Description of Work: 0.337
Providing, fitting and fixing high tensile steel wires/strands ( Tendons) including all accessories for stressing, stressing operations and grouting complete as per Drawing and Technical Specifications.
tonne
Spec. cl. No: 2100
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
i) For
making and
Stressing Jack with
21.1 fixing H.T. Strand tonne 0.39 0 0 hour 2.50 775 1937.5
Pump
cables,
anchorages
Grout pump with
Technician day 1 1064.40 1064.4 Sheathing duct ID 66 mm meter 42 330 13860 hour 1.00 800 800.0
Agitator
Skilled Tube anchorage set complete
(Blacksmith day 2 850 1700.0 with bearing plate, permanent each 2 8200 16400 Generator hour 3.50 150.00 525.0
) wedges etc.
Unskilled day 5 520 2600.0 Cement tonne 0.13 12580.00 1635.4
Add 0.50 per cent cost of
ii) For pre- material for Spacers,
1594.8
stressing Insulation tape and
miscellaneous items
Technician day 1 1064.40 1064.4
Skilled
(Pre-
stressing day 1 850 850.0
operator /
Fitter)
Unskilled day 2 520 1040.0
iii) For
grouting
Technician day 1 1064.40 1064.4
Skilled
day 1 850 850.0
(Mason)
Unskilled day 2 520 1040.0
Sub total of A = 11273.2 Sub total of B = 33490.2 Sub total of C = 3262.5 Sub total of D = 0.0
Sub total of A +B + C = 48025.9 Sub total of A + B + C + D= 48025.9 Contractor's overhead expenses 15% = 7203.9 Norms Rate = 55229.8
Unit Rate = 163886.5

Description of Work:
Providing and Laying Reinforced cement concrete NP3 Flush jointed pipe for culverts including fixing with cement mortar 1:2 as per Drawing and Technical Specifications., 900 mm internal dia. 12.5 meter
Spec. cl. No: 701
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount

Add 3 % of Labour
cost for bellies, crow
7.2.D Skilled day 1 850 850.0 Sand cum 0.12 2140.00 256.8 150.3
bars, chain pulley and
other T&P

Unskilled day 8 520 4160.0 Cement tonne 0.09 12580.00 1132.2


NP3 RCC Pipe 900 mm dia meter 12.5 10450.00 130625
Sub total of A = 5010.0 Sub total of B = 132014.0 Sub total of C = 150.3 Sub total of D = 0.0
Sub total of A +B + C = 137174.3 Sub total of A + B + C + D= 137174.3 Contractor's overhead expenses 15% = 20576.1 Norms Rate = 157750.4
Unit Rate = 12620.04
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang

Rate Analysis

Description of Work:
Road Delineators Post, Providing and installation of 150 mm * 150 mm 1. 5 m long delineators (road way indicators, hazard markers, object markers), 80-100 cm high above ground level, painted black and white in 20 cm
30 no
wide strips, buried or pressed into the ground and conforming to the drawings and Technical Specifications.
Spec. cl. No: 1507
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Skilled
15.12 day 1 850 850.0 M-15 grade of concrete cum 1.01 9392.42 9486.3 Tractor - Trolley hour 3 350.00 1050.0
(Mason)
Steel reinforcement as per
standard drawing ( 4 Nos 8
Unskilled day 7 520 3640.0 tonne 0.1128 73000.00 8234.4
mm dia and 11 Nos 6 mm dia
stirrups)
Excavation in soil for
cum 0.47 306.64 144.1
foundation
Painting two coats on concrete
sqm 14.4 799.87 11518.1
surface
Transportation and fixing
Sub total of A = 4490.0 Sub total of B = 29383.0 Sub total of C = 1050.0 Sub total of D = 0.0
Sub total of A +B + C = 34923.0 Sub total of A + B + C + D= 34923.0 Contractor's overhead expenses 15% = 5238.4 Norms Rate = 40161.4
Unit Rate = 1338.71

Description of Work:
Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing and Technical Specifications, PCC Grade M 15 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
@ 4 per cent on cost
of concrete i.e. cost of
20.2.A Skilled day 3 850 2550.0 Cement tonne 4.13 12580.00 51955.4 Concrete Mixer hour 6 470.00 2820.0 4711.9
Material, Labour and
Equipment
Unskilled day 30 520 15600.0 Coarse Sand cum 6.75 2140.00 14445 Generator hour 6 150.00 900.0
Aggregate 40 mm cum 8.1 2140.00 17334
Aggregate 20 mm cum 4.05 2190.00 8869.5
Aggregate 10 mm cum 1.35 2240.00 3024
Water KL 2 150 300
Sub total of A = 18150.0 Sub total of B = 95927.9 Sub total of C = 3720.0 Sub total of D = 4711.9
Sub total of A +B + C = 117797.9 Sub total of A + B + C + D= 122509.8 Contractor's overhead expenses 15% = 18376.5 Norms Rate = 140886.3
Unit Rate = 9392.42

Description of Work:
Providing suitable material and Back filling behind abutment, wing wall and return wall complete as per Drawing and Technical Specifications., Granular Material 10 cum
Spec. cl. No: 908
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.11.A Skilled day 0.2 850 170.0 Granular Material cum 11 1165.56 12821.16 Plate Compactor hour 2.5 290 725.0
Unskilled day 5 520 2600.0 Water KL 1 150 150
Sub total of A = 2770.0 Sub total of B = 12971.2 Sub total of C = 725.0 Sub total of D = 0.0
Sub total of A +B + C = 16466.2 Sub total of A + B + C + D= 16466.2 Contractor's overhead expenses 15% = 2469.9 Norms Rate = 18936.1
Unit Rate = 1893.61

Description of Work:
Construction of Embankment with Material obtained from Borrow pits, Providing, laying, spreading and compacting embankment with borrow material as per Drawing and Technical Specifications. 300 cum
Spec. cl. No: 909910
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang

Rate Analysis
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.8 Skilled day 1 850 850.0 Water KL 72 150 10800 Hydraulic Excavator hour 6 3597.99 21587.9
Tractor with
Unskilled day 4 520 2080.0 Borrowpit Material cum 360 300.00 108000 hour 12 1132 13584.0
Rotavator
Dozer hour 3 3000 9000.0
Mortar Grader hour 3 1500.00 4500.0
Water Tanker hour 6 1751 10506.0
Vibratory Road Roller hour 6 800.00 4800.0
Sub total of A = 2930.0 Sub total of B = 118800.0 Sub total of C = 63977.9 Sub total of D = 0.0
Sub total of A +B + C = 185707.9 Sub total of A + B + C + D= 185707.9 Contractor's overhead expenses 15% = 27856.2 Norms Rate = 213564.1
Unit Rate = 711.88

Description of Work:
Providing suitable material and Back filling behind abutment, wing wall and return wall complete as per Drawing and Technical Specifications., Granular Material 10 cum
Spec. cl. No: 908
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.11.A Skilled day 0.2 850 170.0 Granular Material cum 11 300.00 3300 Plate Compactor hour 2.5 290 725.0
Unskilled day 5 520 2600.0 Water KL 1 150 150
Sub total of A = 2770.0 Sub total of B = 3450.0 Sub total of C = 725.0 Sub total of D = 0.0
Sub total of A +B + C = 6945.0 Sub total of A + B + C + D= 6945.0 Contractor's overhead expenses 15% = 1041.8 Norms Rate = 7986.8
Unit Rate = 798.68

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, PCC Grade M 25, Height upto 5 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Basic Cost of Labour,
Material & Equipment
20.4.C.p Skilled day 3 850 2550.0 Cement tonne 5.99 12580.00 75354.2 Concrete Mixer hour 6 470.00 2820.0 0.0
(a+b+c) of item
20.2(D)
Add 10 % of cost of
Material, Labour and
Unskilled day 30 520 15600.0 Coarse Sand cum 6.75 2140.00 14445 Generator hour 6 150.00 900.0 14885.7
Equipment (a+b+c) for
Formwork
Aggregate 40 mm cum 5.4 2140.00 11556
Aggregate 20 mm cum 5.4 2190.00 11826
Aggregate 10 mm cum 2.7 2240.00 6048
Water KL 3 150.00 450
Admixture Kg 23.96 305 7307.8
Sub total of A = 18150.0 Sub total of B = 126987.0 Sub total of C = 3720.0 Sub total of D = 14885.7
Sub total of A +B + C = 148857.0 Sub total of A + B + C + D= 163742.7 Contractor's overhead expenses 15% = 24561.4 Norms Rate = 188304.1
Unit Rate = 12553.61

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in super-structure as per drawing and Technical Specification, RCC/PSC Grade M 35 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.D Skilled day 3 850 2550.0 Cement tonne 6.33 12580.00 79631.4 Concrete Mixer hour 6 470.00 2820.0
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang

Rate Analysis
Unskilled day 32 520 16640.0 Coarse Sand cum 6.75 2140.00 14445 Generator hour 6 150.00 900.0
Aggregate 20 mm cum 8.1 2190.00 17739
Aggregate 10 mm cum 5.4 2240.00 12096
Water KL 3 150.00 450
Admixture kg 25.32 305 7722.6
Sub total of A = 19190.0 Sub total of B = 132084.0 Sub total of C = 3720.0 Sub total of D = 0.0
Sub total of A +B + C = 154994.0 Sub total of A + B + C + D= 154994.0 Contractor's overhead expenses 15% = 23249.1 Norms Rate = 178243.1
Unit Rate = 11882.87

Description of Work:
Providing and fixing Drainage Spouts complete as per Drawing and Technical specifications. 10 no
Spec. cl. No: N/A
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
For Corrosion Resistant Structural
31.3 Kg 40 100 4000
fabrication Steel

Skilled
(Blacksmith day 1 850 850.0 GI Pipe 100 mm dia. meter 60 100.00 6000
/ Welder)

Unskilled day 2 520 1040.0 GI Bolt 10 mm dia. nos 60 200 12000


For fixing
Galvanized MS Flat Clamp nos 20 100 2000
in position
Add @ 5 per cent of cost of
Material and Labour for
electrodes, cutting gas,
Skilled day 1 850 850.0 1441.0
sealant, anti-corrosive
bituminous paint, mild steel
grating etc.
Unskilled day 4 520 2080.0
Sub total of A = 4820.0 Sub total of B = 25441.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 30261.0 Sub total of A + B + C + D= 30261.0 Contractor's overhead expenses 15% = 4539.2 Norms Rate = 34800.2
Unit Rate = 3480.02

Description of Work:
Tubular Steel Railing on Precast RCC Posts, 1.2 m High Above Ground Level, Providing, fencing and erecting 50 mm dia painted steel pipe railing in 3 rows on precast M 20 grade RCC vertical posts 1.8 metres high (1.2 m
100 meter
above GL) with 3 holes 50 mm dia for pipe, fixed 2 metres center to, complete as per Drawing and Technical Specifications.
Spec. cl. No: 3105
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Skilled Steel pipe 50 mm external dia
31.7 day 1 850 850.0 meter 300 100 30000 Tractor - Trolley hour 6 1086.27 6517.6
(Plumber) as per IS: 1239
Unskilled day 6 520 3120.0 Excavation for foundation cum 12.96 306.64 3974.1
Foundation concrete M - 15 cum 6.48 9424.71 61072.1
RCC M - 20 cum 3.2 10044.07 32141.0
Painting of pipe sqm 47.1 158.9 7484.2
Sub total of A = 3970.0 Sub total of B = 134671.4 Sub total of C = 6517.6 Sub total of D = 0.0
Sub total of A +B + C = 145159.0 Sub total of A + B + C + D= 145159.0 Contractor's overhead expenses 15% = 21773.9 Norms Rate = 166932.9
Unit Rate = 1669.33

Description of Work:
Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing and Technical Specifications, PCC Grade M 15 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No.
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang

Norms Rate Analysis


No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
@ 4 per cent on cost
of concrete i.e. cost of
20.2.A Skilled day 3 850 2550.0 Cement tonne 4.13 12580.00 51955.4 Concrete Mixer hour 6 470.00 2820.0 4728.1
Material, Labour and
Equipment
Unskilled day 30 520 15600.0 Coarse Sand cum 6.75 2140.00 14445 Generator hour 6 150 900.0
Aggregate 40 mm cum 8.1 2190.00 17739
Aggregate 20 mm cum 4.05 2190.00 8869.5
Aggregate 10 mm cum 1.35 2240.00 3024
Water KL 2 150.00 300
Sub total of A = 18150.0 Sub total of B = 96332.9 Sub total of C = 3720.0 Sub total of D = 4728.1
Sub total of A +B + C = 118202.9 Sub total of A + B + C + D= 122931.0 Contractor's overhead expenses 15% = 18439.7 Norms Rate = 141370.7
Unit Rate = 9424.71

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in super-structure as per drawing and Technical Specification, RCC Grade M 20 15 Cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.A Skilled day 3 850 2550.0 Cement tonne 5.12 12580.00 64409.6 Concrete Mixer hour 6 470 2820.0
Unskilled day 30 520 15600.0 Coarse Sand cum 6.75 2140.00 14445 Generator hour 6 150 900.0
Aggregate 20 mm cum 8.1 2190.00 17739
Aggregate 10 mm cum 5.4 2240.00 12096
Water KL 3 150.00 450
Sub total of A = 18150.0 Sub total of B = 109139.6 Sub total of C = 3720.0 Sub total of D = 0.0
Sub total of A +B + C = 131009.6 Sub total of A + B + C + D= 131009.6 Contractor's overhead expenses 15% = 19651.4 Norms Rate = 150661.0
Unit Rate = 10044.07

Description of Work:
Painting Two Coats on Steel Surfaces, Providing and applying two coats of ready mix paint of approved brand on steel surface after through cleaning of surface to give an even shade as per Drawing and Technical
20 sqm
Specifications.
Spec. cl. No: 1501
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Skilled
15.5 day 1 850 850.0 Paint liter 2.5 500.00 1250
(Painter)
Add @ 1 per cent on cost of
Unskilled day 1 520 520.0 12.5
Material for scaffolding
Add @ 5 per cent cost of
Labour and Materials to
prepare the surface by filling
minutes roughness on the 131.0
surface and priming the
surface before laying 2 coats
of painting.
Sub total of A = 1370.0 Sub total of B = 1393.5 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 2763.5 Sub total of A + B + C + D= 2763.5 Contractor's overhead expenses 15% = 414.5 Norms Rate = 3178.0
Unit Rate = 158.9
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang

Quantity Estimate

Length Breadth
S.N. Description of Works Unit No Height (m) Quantity Remarks
(m) (m)
1 GENERAL:
Insurance of works, plants, equipment, construction
1.1 LS 1
materials and manpower
Provide and installation of project information board of
1.2 size 1.80 mx1.2 m along with iron posts including Nos 2
excavation, concreting, backfilling etc all complete
Establish, maintain and operate labaratory at the site with
1.3 equipments furnishing required for testing specified LS 1
quality of the materials
1.4 Provisional Sum for other miscellaneous works PS 1

2 FOUNDATION AND SUB STRUCTURE:


Excavation in foundation in all types of soil including
2.1 m3
dewatering / diversion /dam / lift and haulage
Abutment Pile cap 2.00 11.40 10.50 5.50 avg 1,316.70
Pier Pile Cap 3.00 10.40 7.40 5.00 avg 1,154.40
Total 2,471.10
Providing, Boring and installing bored cast-in-situ RCC
Pile excluding Reinforcement and Concrete in all types of
Rock including Bentonite and other consumable and
2.2 Rm
removal of excavated material with necessary lifts and lead
all complete as per Drawing and Technical
Specifications ., Pile diameter-1000 mm
Abutment Pile 32.00 15.00 480.00
Pier Pile 48.00 13.00 624.00
Total 1,104.00
Providing and laying of hand pack Stone soling with 150
2.3 to 200 mm thick stones and packing with smaller stone on
prepared surface as per Drawing and Technical
Specifications.
Abutment Pile cap 2 11.4 10.5 0.15 35.91
Pier Pile Cap 3 10.4 7.4 0.15 34.63
m3 Total 70.54

Supply and place concrete M10/40 including dewatering,


2.4
mixing, laying,compacting and curing all complete (2000)

Abutment footing 2.00 11.40 10.50 0.10 23.94


Pier Foundation 3.00 10.40 7.40 0.10 23.09
m3 Total 47.03

Supply and place concrete M25/20 including dewatering,


2.5
mixing, laying,compacting and curing all complete (2000)

Abutment
Abutment stem 2.00 11.00 1.35 4.59 136.32
Abutment cap 2.00 11.00 1.90 1.00 41.80
Back walls 2.00 11.00 0.40 3.30 29.04
Return walls 4.00 3.50 0.40 2.60 14.56
Approach slab seat 2.00 11.00 0.30 0.38 2.48
Stopper block 4.00 1.50 0.60 1.11 4.01
Pier
Pier stem (circular) 3.00 Area= 3.80 3.59 40.94
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang

Quantity Estimate

Length Breadth
S.N. Description of Works Unit No Height (m) Quantity Remarks
(m) (m)
Pier Cap 3.00 Area= 12.35 4.50 166.73
Stopper block 12.00 1.50 0.60 1.11 4.01
m3 Total 439.87

Supply and place M35/20 grade concrete including


2.6
mixing, laying, compacting and curing all complete (2000)

Abutment
Abutment pile cap 2.00 11.40 10.50 1.50 359.10
Abutment pile 32.00 15.00 Area= 0.79 376.99
Bearing pad 4.00 1.00 1.00 0.30 1.20
Pier
Pier Pile Cap 3.00 10.40 7.40 1.50 346.32
Pier pile 48.00 13.00 area= 0.79 490.09
Bearing pad 12.00 1.00 1.00 0.30 3.60
Total m3 1,577.30

Supplying, cutting, bending, placing of reinforcement


2.7 (HYSD bars) in position as shown in the drawings and MT
binding by wires as specified in the specification (2014)

Abutment
Stem and back wall From BBS 2.00 13,351.60
return wall 4.00 2,377.85
abutment cap 2.00 2,882.36
bearing pad 4.00 516.63
stopper block 4.00 238.54
pile cap 2.00 31,909.60
pile 32.00 47,840.44
Pier
Stem 3.00 8,670.82
Pier cap 3.00 21,681.52
bearing pad/Pedestal 12.00 1,549.89
stopping block 12.00 715.61
pile cap 3.00 34,791.47
pile 36.00 40,459.68
Total 206,986.01 kg
206.99 ton
Providing and filling with graded gravel filter material in
2.8
layers as per drawing and specification (3110)
Abutment backfill 2.00 11.00 1.00 2.50 55.00
Total 55.00 m3
Back filling with common material including watering and
2.9
compaction (900)
Abutment backfill 2.00 11.00 3.00 4.00 264.00
Abutment frontfill 2.00 3.00 11.00 3.00 198.00
Pier Back and Front Fill 3.00 10.40 2.20 2.00 137.28
Total 599.28 m3

3 SUPERSTRUCTURE:

Supply and place M45/20 grade concrete including


3.1 m3
mixing, laying, compacting and curing all complete (2000)

Two web slab deck 4.00 916.00


Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang

Quantity Estimate

Length Breadth
S.N. Description of Works Unit No Height (m) Quantity Remarks
(m) (m)
Total 916.00 m3

Supply and place M35/20 grade concrete including


3.2 m3
mixing, laying, compacting and curing all complete (2000)

Slab,Footpath , Kerb etc 4.00 3.50 7.50 0.30 120.00


Approach slab 2.00 3.50 7.50 0.30 15.75
Total 135.75 m3

Supplying, Cutting, bending, placing of reinforcement


3.3 (HYSD bars) in position as shown in the drawings and MT
binding by wires as specified in the specification (2014)

Total 140,000.00 kg
Approach Slab 1,259.00
141.26 MT
Providing, fitting and fixing high tensile steel
wires/strands ( Tendons) including all accessories for
3.4 MT 4.00 27.60 MT
stressing, stressing operations and grouting complete as
per Drawing and Technical Specifications.
Providing mixing, laying and compaction of Asphaltic
3.5 m3 1.00 150.00 7.50 0.06 70.31
waring course.
Supplying and fixing of expansion joint as per drawing
3.6 Rm 5.00 11.00 55.00 Rm
[1900]
Supply and fix in position bearing(PoT Fix and Free) as
3.7 Nos 16.00 16.00 Nos
per drawing (1902)
Supply and fixing in position 50mm dia GI pipe (Medium
3.8 Rm 2.00 223.00 446.00 Rm
class) railings as per drawings. (3100)
Supply and fixing in position Drainage Spouts 450mm
3.9 Nos 64.00 64.00 Nos
long and 100mm diameter.
Painting Two Coats on Concrete Surfaces, Providing and
Painting two coats after filling the surface with synthetic
3.10 Sqm 149.52 0.315 47.10 Sqm
enamel paint in all shades on concrete / plaster surfaces as
per Drawing and Technical Specifications.

4 APPROACH ROAD:
4.1 Hume Pipe Works
As per
Excavation in foundation for road structures / protection
Stnadard
4.1.1 works through all types of soil including relevant lift and m3
dawing of
disposal upto 20m (900)
DOR
Hume pipe at Ch. 0+352 1.00 4.32
Hume pipe at Ch. 0+447 1.00 4.32
Total 8.64 m3
Providing and laying of hand pack Stone soling with 150 As per
to 200 mm thick stones and packing with smaller stone on Stnadard
4.1.1 m3
prepared surface as per Drawing and Technical dawing of
Specifications. DOR
Hume pipe at Ch. 0+352
hume pipe bed 1.00 5.18
vertical wall at u/s and d/s 2.00 3.50 1.20 0.15 1.26
Hume pipe at Ch. 0+447
hume pipe bed 1.00 5.18
vertical wall at u/s and d/s 2.00 3.50 1.20 0.15 1.26
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang

Quantity Estimate

Length Breadth
S.N. Description of Works Unit No Height (m) Quantity Remarks
(m) (m)
Total 12.87 m3
As per
Supply and place concrete M10/40 including dewatering, Stnadard
4.1.2
mixing, laying,compacting and curing all complete (2000) dawing of
DOR
Hume pipe at Ch. 0+352
hume pipe bed 1.00 3.46
vertical wall at u/s and d/s 2.00 3.50 1.20 0.10 0.84
Hume pipe at Ch. 0+447
hume pipe bed 1.00 3.46
vertical wall at u/s and d/s 2.00 3.50 1.20 0.10 1.26
Total 9.02 m3
Providing and laying Stone Masonry work in cement
mortar 1:3 in structure complete as per drawing and
4.1.3 m3
Technical Specifications, Random Rubble Masonry, Using
Concrete Mixer
Hume pipe at Ch. 0+352 2.00 3.50 0.85 4.00 23.80
Hume pipe at Ch. 0+447 2.00 3.50 0.85 2.50 14.88
Total 38.68 m3
Providing and Laying Reinforced cement concrete NP3
Flush jointed pipe for culverts including fixing with
4.1.3 Rm
cement mortar 1:2 as per Drawing and Technical
Specifications., 900 mm internal dia.
Hume pipe at Ch. 0+352 1.00 10.00 10.00
Hume pipe at Ch. 0+447 1.00 10.00 10.00
Total 20.00 Rm
4.2 Pavement Works
Road way excavation including disposal upto 10m and lift Quanity
4.2.1 m3 107.13
upto 1.5 m etc. all complete sheet
Formation of embankment with excavated soil including
Quanity
4.2.2 haulage, compaction in layers not exceeding 150 mm and m3 12,465.44
sheet
watering.
Preparation of capping layer in all types of materials Quanity
4.2.3 m3 1,275.00
including compaction and watering all complete. sheet
Preparation of sub-grade in all types of materials including Quanity
4.2.4 m2 382.50
compaction and watering all complete. sheet
Providing, laying, spreading, watering, levelling and Quanity
4.2.5 m3 510.00
compaction of natural gravel subbase all complete. sheet
Providing, laying, spreading, watering, levelling and Quanity
4.2.6 m3 510.00
compaction of natural gravel base all complete. sheet
Traffic safety and Road Furniture and acessories
4.3
Works
Supplying and fixing in place RCC delineator post with
4.3.1 reflective element including excavation, backfilling, nos 40.00 40.00 Nos
painting and erection etc.
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang

Quantity Estimate

Length Breadth
S.N. Description of Works Unit No Height (m) Quantity Remarks
(m) (m)

Retro-Reflectorized Traffic Signs, Providing and fixing of


retro- reflectorized warning, Regulatory and informatory
sign as per specification clause 1501 made of high
intensity grade sheeting , fixed over aluminum sheeting,
1.5 mm thick supported on a 50 mm internal dia steel tube
4.3.2 Nos 2.00 2.00 Nos
or mild steel angle iron post 75 mm x 40 mm x 6 mm
firmly fixed to the ground by means of properly designed
foundation with M 10/40 grade cement concrete 30 cm x
30 cm , 30 cm below ground level or as per Drawing and
Technical Specifications., 80 mm * 60 mm rectangular

Road Marking with Hot Applied Thermoplastic


Compound with Reflectorizing Glass Beads on
Bituminous Surface, On smooth surface (similar to
Asphalt concrete and rigid pavement), Providing and
4.3.3 m2 3.00 150.00 0.15 67.50 Sqm
laying of hot applied thermoplastic compound at least 2
mm thick including reflectorizing glass beads as per DOR
Traffic sign manual/ Specifications .The finished surface
to be level, uniform and free from streaks and holes.

5 RIVER TRAINING AND PROTECTION WORKS:


5.1 Gabion Wall for River Training Works
Excavation in foundation for road structures / protection
5.1.1 works through all types of soil including relevant lift and
disposal upto 20m (900)
Gabion protection at U/S 2.00 225.00 5.00 1 2,250.00
Gabion protection at D/S 2.00 200.00 5.00 1 2,000.00
Total 4,250.00 m3

Gabion works with heavy zinc coated GI mesh wire


(10SWG), selvedge wire (7SWG), binding wire
5.1.2
(12SWG),fabricating boxes in hexagonal mesh size
(100mmx120mm) and filling stones, all complete (2400)

Gabion protection wall (up stream) 2.00 225.00 x-sectinal area=8.00 3,600.00
Gabion protection wall (down stream) 2.00 200.00 x-sectinal area=9.00 3,600.00
Total 7,200.00 m3
Laying and fixing of Geo-Textile all complete as per
5.1.3 specification., Providing and laying and fixing of Geo- m2
membrane all complete as per specification.
For Gabion 1.00 425.00 3.50 1,487.50

5.2 Masonry Wing Wall near Abutment


Excavation in foundation for road structures / protection
5.2.1 works through all types of soil including relevant lift and m3 4.00 7.35 3.35 1.45 142.81
disposal upto 20m (900)
Providing and laying of hand pack Stone soling with 150
to 200 mm thick stones and packing with smaller stone on
5.2.2 m3 4.00 7.35 3.35 0.15 14.77
prepared surface as per Drawing and Technical
Specifications.
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang

Quantity Estimate

Length Breadth
S.N. Description of Works Unit No Height (m) Quantity Remarks
(m) (m)

Supply and place concrete M10/40 including dewatering,


5.2.3 m3 4.00 7.35 3.35 0.10 9.85
mixing, laying,compacting and curing all complete (2000)

Providing and laying random rubble stone masonry in


5.2.4 cement mortar (1:4) including scaffolding, curing, 4.00 7.35 area=9.76 286.81
preparation of mortar etc, all complete (2600)
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Abstract of Cost

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang
S.N. Description of Works Unit Quantity Rate(NRs) Amount (NRs) Remarks
1 GENERAL:
Insurance of works, plants, equipment, construction
1.1 LS 1.00 1000000.00
materials and manpower
Provide and installation of project information board of
1.2 size 1.80 mx1.2 m along with iron posts including Nos 2.00 1546.750 3093.50
excavation, concreting, backfilling etc all complete
Establish, maintain and operate labaratory at the site with
1.3 equipments furnishing required for testing specified LS 1.00 500000.00
quality of the materials
Provisional Sum for relocation of existing
1.4 PS 1.00 1000000.00
facilities,Environmental and Social Considerations etc.
2 FOUNDATION AND SUB STRUCTURE:
Excavation in foundation in all types of soil including
2.1 m3 2471.10 306.64 757738.10
dewatering / diversion /dam / lift and haulage
Providing, Boring and installing bored cast-in-situ RCC
Pile excluding Reinforcement and Concrete in all types of
Rock including Bentonite and other consumable and
2.2 Rm 1104.00 14812 16352448.00
removal of excavated material with necessary lifts and lead
all complete as per Drawing and Technical
Specifications ., Pile diameter-1000 mm

Providing and laying of hand pack Stone soling with 150


2.3 to 200 mm thick stones and packing with smaller stone on m3 70.54 5,837.40 411781.87
prepared surface as per Drawing and Technical
Specifications.

Supply and place concrete M10/40 including dewatering,


2.4 m3 47.03 7,973.03 374955.65
mixing, laying,compacting and curing all complete (2000)

Supply and place concrete M25/20 including dewatering,


2.5 m3 439.87 12,553.61 5521997.77
mixing, laying,compacting and curing all complete (2000)

Supply and place M35/20 grade concrete in foundation


2.6 including mixing, laying, compacting and curing all m3 1577.30 12,157.23 19175593.68
complete (2000)

Supplying, cutting, bending, placing of reinforcement


2.7 (HYSD bars) in position as shown in the drawings and MT 206.99 103,748.40 21474467.87
binding by wires as specified in the specification (2014)

Providing and filling with graded gravel filter material in


2.8 m3 55.00 1,893.61 104148.55
layers as per drawing and specification (3110)
Back filling with common material including watering and
2.9 m3 599.28 798.68 478632.95
compaction (900)
3 SUPERSTRUCTURE:

Supply and place M45/20 grade concrete including


3.1 m3 916.00 12,670.32 11606013.12
mixing, laying, compacting and curing all complete (2000)

Supply and place M35/20 grade in superstructure concrete


3.2 including mixing, laying, compacting and curing all m3 135.75 11,882.87 1613099.60
complete (2000)

Supplying, Cutting, bending, placing of reinforcement


3.3 (HYSD bars) in position as shown in the drawings and MT 141.26 103,748.40 14655395.24
binding by wires as specified in the specification (2014)
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Abstract of Cost

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang
S.N. Description of Works Unit Quantity Rate(NRs) Amount (NRs) Remarks

Providing, fitting and fixing high tensile steel


wires/strands ( Tendons) including all accessories for
3.4 MT 27.60 163,886.50 4523267.40
stressing, stressing operations and grouting complete as
per Drawing and Technical Specifications.
Providing mixing, laying and compaction of Asphaltic
3.5 m3 70.31 19,584.90 1377063.28
waring course.
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Abstract of Cost

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang
S.N. Description of Works Unit Quantity Rate(NRs) Amount (NRs) Remarks
Supplying and fixing of expansion joint as per drawing
3.6 Rm 55.00 17,825.00 980375.00
[1900]
Supply and fix in position bearing(PoT-PTFE Fix and
3.7 Nos 16.00 72,243.00 1155888.00
Free) as per drawing (1902)
Supply and fixing in position 50mm dia GI pipe (Medium
3.8 Rm 446.00 1,669.33 744521.18
class) railings as per drawings. (3100)
Supply and fixing in position Drainage Spouts 450mm
3.9 Nos 64.00 3,480.02 222721.28
long and 100mm diameter.
Painting Two Coats on Concrete Surfaces, Providing and
Painting two coats after filling the surface with synthetic
3.10 Sqm 47.10 799.87 37672.92
enamel paint in all shades on concrete / plaster surfaces as
per Drawing and Technical Specifications.
4 APPROACH ROAD:
4.1 Hume Pipe Works
Excavation in foundation for road structures / protection
4.1.1 works through all types of soil including relevant lift and m3 8.64 306.64 2649.37
disposal upto 20m (900)
Providing and laying of hand pack Stone soling with 150
to 200 mm thick stones and packing with smaller stone on
4.1.1 m3 12.87 5,837.40 75127.34
prepared surface as per Drawing and Technical
Specifications.

Supply and place concrete M10/40 including dewatering,


4.1.2 m3 9.02 7,973.03 71916.73
mixing, laying,compacting and curing all complete (2000)

Providing and laying Stone Masonry work in cement


mortar 1:4 in structure complete as per drawing and
4.1.3 m3 38.68 9,648.53 373156.90
Technical Specifications, Random Rubble Masonry, Using
Concrete Mixer
Providing and Laying Reinforced cement concrete NP3
Flush jointed pipe for culverts including fixing with
4.1.3 Rm 20.00 12,620.04 252400.80
cement mortar 1:2 as per Drawing and Technical
Specifications., 900 mm internal dia.
4.2 Pavement Works
Road way excavation including disposal upto 10m and lift
4.2.1 m3 107.13 76.66 8212.59
upto 1.5 m etc. all complete
Formation of embankment with excavated soil including
4.2.2 haulage, compaction in layers not exceeding 150 mm and m3 12465.44 711.88 8873899.33
watering.
Preparation of capping layer in all types of materials
4.2.3 m3 1275.00 1,406.01 1792662.75
including compaction and watering all complete.
Preparation of sub-grade in all types of materials including
4.2.4 m2 382.50 75.43 28851.98
compaction and watering all complete.
Providing, laying, spreading, watering, levelling and
4.2.5 m3 510.00 1,519.69 775041.90
compaction of natural gravel subbase all complete.
Providing, laying, spreading, watering, levelling and
4.2.6 m3 510.00 3,628.06 1850310.60
compaction of natural gravel base all complete.
Traffic safety and Road Furniture and acessories
4.3
Works
Supplying and fixing in place RCC delineator post with
4.3.1 reflective element including excavation, backfilling, m3 40.00 1,338.71 53548.40
painting and erection etc.
Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang

Abstract of Cost

Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang
S.N. Description of Works Unit Quantity Rate(NRs) Amount (NRs) Remarks

Retro-Reflectorized Traffic Signs, Providing and fixing of


retro- reflectorized warning, Regulatory and informatory
sign as per specification clause 1501 made of high
intensity grade sheeting , fixed over aluminum sheeting,
1.5 mm thick supported on a 50 mm internal dia steel tube
4.3.2 Nos 2.00 3,032.51 6065.02
or mild steel angle iron post 75 mm x 40 mm x 6 mm
firmly fixed to the ground by means of properly designed
foundation with M 10/40 grade cement concrete 30 cm x
30 cm , 30 cm below ground level or as per Drawing and
Technical Specifications., 80 mm * 60 mm rectangular

Road Marking with Hot Applied Thermoplastic


Compound with Reflectorizing Glass Beads on
Bituminous Surface, On smooth surface (similar to
Asphalt concrete and rigid pavement), Providing and
4.3.3 m2 67.50 302.45 20415.38
laying of hot applied thermoplastic compound at least 2
mm thick including reflectorizing glass beads as per DOR
Traffic sign manual/ Specifications .The finished surface
to be level, uniform and free from streaks and holes.

5 RIVER TRAINING AND PROTECTION WORKS:


5.1 Gabion Wall for River Training Works
Excavation in foundation for road structures / protection
5.1.1 works through all types of soil including relevant lift and m3 4250.00 306.64 1303220.00
disposal upto 20m (900)

Gabion works with heavy zinc coated GI mesh wire


(10SWG), selvedge wire (7SWG), binding wire
5.1.2 m3 7200.00 6,089.55 43844760.00
(12SWG),fabricating boxes in hexagonal mesh size
(100mmx120mm) and filling stones, all complete (2400)

Laying and fixing of Geo-Textile all complete as per


5.1.3 specification., Providing and laying and fixing of Geo- Sqm 1487.50 393.65 585554.38
membrane all complete as per specification.
5.2 Masonry Wing Wall near Abutment
Excavation in foundation for road structures / protection
5.2.1 works through all types of soil including relevant lift and m3 142.81 306.64 43791.41
disposal upto 20m (900)
Providing and laying of hand pack Stone soling with 150
to 200 mm thick stones and packing with smaller stone on
5.2.2 m3 14.77 5,837.40 86238.83
prepared surface as per Drawing and Technical
Specifications.

Supply and place concrete M10/40 including dewatering,


5.2.3 m3 9.85 7,973.03 78526.37
mixing, laying,compacting and curing all complete (2000)

Providing and laying random rubble stone masonry in


5.2.4 cement mortar (1:4) including scaffolding, curing, m3 286.81 9,648.53 2767275.83
preparation of mortar etc, all complete (2600)
Total without PS 165964500.86
PS 1000000.00
Total with PS 166964500.86
VAT (13%) 21575385.11
Contingency(4%) 6638580.03
Physical Contingency(10%) 16596450.09
Provivison for Price Escalation(10%) 16596450.09
Grand Total 228371366.18
Babai Bridge

Provincial Government
Ghorahi Sub-Metropoltan City
Office of Municipal Executive
Ghorahi, Dang
Name of Bridge: Babai River Bridge at Ghorahi Sub-Metropolitan City,Ward no 5 Dharna Dang
Summery Of Cost

Percentage of
S.N. Description of Works Cost Remarks
total cost
1 GENERAL ITEMS 2503093.50 1.50%
2 FOUNDATION AND SUB STRUCTURE 64651764.45 38.73%
3 SUPERSTRUCTURE 36878344.10 22.09%
4 APPROACH ROAD 14184259.07 8.50%
5 RIVER TRAINING AND PROTECTION WORKS 48709366.82 29.18%
Total Without VAT 166926827.94 100.00%
Total with VAT,Contingences,Provision for Price
228371366.18
Escalation
Cost Per Running Meter Without VAT 1,111,881.89 NRS
Cost Per Running Meter With VAT contingecies and
1,521,157.44 NRS
Provison of Price Escalation
Note : Total length of Bridge excluding approach slab
150.13 m
=(35*4+2.95*3+0.61*2+0.01+0.05)

You might also like