Professional Documents
Culture Documents
1 33 19
2 27 10
3 6 6
Figure 6.1 represents the current state value stream map. It is known from the current state
VSM that 15 men are employed for a period 35 days irrespective of the demand. This leads to
unwanted inventory and overproduction. This fact is verified by the intermediate inventory
which adds a total lead time/non-value adding time of 138 hours, which amounts to 94.1% of
the total cycle time. Applying demand control to each of the three phases helps in smoothen
the workflow and in ensuring that the production is carried out in accordance to the demand.
The total cycle time for the production of a single element was calculated to be 57.93 hours
out of which the net value adding time was 3.88 hours. This gives the percentage value
adding time to be 6.70 % which is still greater than 5.9 % that is proposed by the current state
value stream map. Nonetheless, the demand for 27 columns is met in 10 days.
Phase 3 of the fabrication process required the production of 6 elements in a period of 6 days.
The demand rate in phase 3 is lesser when compared to that of phase 1 & phase 2.
Therefore, using demand control techniques the number of men required at each stage of the
fabrication process is recalculated to meet the new demand. The total number of men
employed in phase 3 is 6.
The value stream map for phase 3 of the fabrication process is shown in figure 6.4. The total
cycle time for the production of a single element was calculated to be 70.58 hours out of
which the net value adding time was 11.87 hours.
This gives the percentage value adding time to be 16.82 % which is much greater than 5.9 %
that is proposed by the current state value stream map. Moreover, the demand for 6 columns
is met in 6 days.
Table 6.3: Comparison of Man hours between Current state VSM and Proposed VSM
1 285 228
2 150 180
3 90 36
The total man hours involved in the current state value stream map is 525 man hours.
Similarly, the total man hours involved in the proposed value stream map works out to be 444
man hours. The total reduction in man hours from the current VSM to the proposed VSM is
81 man hours i.e., a percentage reduction of 15.43. This bolsters the fact that value stream
mapping streamlines workflow and reduces lead time.
= 81 man hours
= 15.43 %
= Rs 3099.54
= 22.04 %
Thus the savings in cost on applying the proposed inventory model over the present inventory
model is Rs 3099.54 ie, 22.04 % savings in cost over the present inventory model.
CHAPTER 7: Conclusions
Steel plates form a very important raw material of our project and incur large cost. In order to
control material wastage at site and reduce inventory cost, a reliable forecasting model is
required. In our research, we used exponential smoothening forecasting model to forecast the
steel plate requirements for fabrication in kg. The exponential smoothening model presented
satisfactory results with the increase in input data points. However, large deviation in the
forecasted values was seen towards the end of the fabrication phase. The site engineers were
interviewed in order to determine reasons for the deviation. It was concluded that, since
during the end of the project the setup was to be removed and hence simultaneous fabrication
were conducted and finished at an earlier stage. This lead to a sudden spike in the fabrication
data and hence the deviation.
Value stream mapping is one of the lean tools used in manufacturing to identify bottlenecks
that is, stages at which inventory is built up. These bottlenecks once identified are rectified
and workflow is streamlined so that there is a smooth flow of material from one state to
another. The present project taken up consisted of seven stages .Using value stream mapping
it was identified that a large amount of inventory was getting built up at the end of marking
and cutting. The painting phase was another bottleneck as the paint had to dry for a period of
8 hours prior to the application of the subsequent Coat. These bottlenecks when left
uncertified lead to build up of lead time which reduces the overall efficiency of the process.
This study uses value stream mapping to perform demand control. Knowing the productivity
at each stage of fabrication, the available time and the number of units to be produced to meet
the demand, workers were assigned such that the overall demand was met as well as the
inventory built up at intermediate stages was reduced to a bare minimum. But the bottleneck
identified at the painting face was not rectifiable, as the paint used in the process remained
the same. This bottleneck can be rectified by using paints having lesser drying time. Value
stream mapping effectively reduced the overall labour man hours, reduced the intermediate
inventory and help in meeting the required demand.
Economic batch quantity (EBQ) is a concept that is used to identify the optimal batch size of
a product in manufacturing industries, where the products are simultaneously produced as
well as consumed/ dispatched. As the present project involved the fabrication of Steel
elements at the site, it more or less resembled the manufacturing environment. Therefore
EBQ was decided to be the most suitable model to be applied to the present project. The
production system followed at the site involved a lot of uncertainty. Large quantities of
elements were produced at a stretch and later consumed, which lead to large inventory build
up. This fact became evident when the inventory versus time graph for the present inventory
model was plotted. As the project involved three different kinds of elements namely columns,
jack beams and rafters, economic lot
if employed if would drastically reduce the total inventory cost. As the project involved
customer financed warehouse/ site, the cost incurred towards this was neglected. The savings
in cost would have been greater is the warehouse cost was born by the Builder.