You are on page 1of 6

188 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 21, NO.

1, FEBRUARY 2006

Bulk Electric System Well-Being Analysis


Using Sequential Monte Carlo Simulation
Wijarn Wangdee, Student Member, IEEE, and Roy Billinton, Fellow, IEEE

Abstract—There is growing interest in combining deterministic assessment consists of determining if the system oscillations
considerations with probabilistic assessment in order to evaluate following an outage or a fault will cause loss of synchronism
the “system well-being” of a composite generation and transmis- between generators. The objective of static security analysis
sion system and to evaluate the likelihood not only of entering a
complete failure state but also the likelihood of being very close
is to determine whether, following the occurrence of a contin-
to trouble. This paper presents bulk electric system well-being gency, there exists a new steady-state secure operating point
analysis using sequential Monte Carlo simulation. This approach where the perturbed power system will settle after the dynamic
provides accurate frequency and duration assessments and the oscillations have damped out. The system well-being approach
index probability distributions associated with the mean values. [10], [11] provides the ability to incorporate the deterministic
The basic N-1 security criterion is used as the deterministic criteria used in static security assessment into the probabilistic
requirement for incorporating a deterministic consideration in a
probabilistic assessment to monitor system well-being. The results framework utilized in conventional adequacy evaluation.
shown in this paper indicate that the system well-being concept Most electric power utilities use deterministic techniques,
can provide comprehensive knowledge on what the degree of such as the traditional N-1 security criterion, to assess system
system vulnerability might be under a particular system condi- reliability in transmission system planning. These deterministic
tion. The basic concepts and their application in composite power techniques do not provide an assessment of the actual system
system well-being analysis are illustrated by application to a small
reliability as they do not incorporate the probabilistic or sto-
practical test system.
chastic nature of the system behavior and component failures.
Index Terms—Bulk electric system (BES), sequential simulation, These approaches, therefore, are not consistent [12] and do not
system well-being analysis.
provide an accurate basis for comparing alternate equipment
configurations and performing economic analyzes. In contrast,
I. INTRODUCTION probabilistic methods can respond to the significant factors
that affect the reliability of a system. These techniques provide
B ULK electric system (BES) reliability assessment can
be divided into two basic aspects designated as system
adequacy and system security. BES adequacy assessment is fo-
quantitative indexes, which can be used to decide if the system
performance is acceptable or if changes need to be made.
Most of the published papers on reliability assessment of bulk
cused on the existence of sufficient facilities within the system
electric systems are based on probabilistic approaches [1]–[4].
to satisfy the consumer load demand within the basic system
There is, however, considerable reluctance to use probabilistic
operational constraints. A BES includes the facilities necessary
techniques in many areas due to the difficulty in interpreting
to generate sufficient energy and the associated transmission
the resulting numerical indexes. Although deterministic criteria
required to transport the energy to the actual bulk supply points
do not consider the stochastic behavior of system components,
(distribution delivery points). Adequacy assessment of BES
they are easier for regulators, managers, system planners. and
has been generally conducted using probabilistic techniques
operators to appreciate than numerical risk indexes determined
[1]–[4]. Security considerations in BES are generally consid-
using probabilistic techniques. This difficulty can be alleviated
ered by focusing on the operation of the system in different
by incorporating the accepted deterministic criteria in a prob-
operating states designated as normal, alert, emergency, and
abilistic framework to assess the well-being of the BES. The
extreme emergency states [5]–[7]. A BES security assessment
concept of quantifying the different operating states of a power
normally utilizes the traditional deterministic criterion known
system described in [5] and [6] was introduced in [7] using an
as the N-1 security criterion [8], [9] in which the loss of any
analytical approach. This was extended in [13] using a Monte
BES component (a contingency) will not result in system
Carlo state sampling technique. The concepts were further
failure. In this approach, a system is able to withstand distur-
extended to large system analysis in [14]. The well-being
bances, i.e., due to BES equipment failures, without violating
structure shown in Fig. 1 is a simplification of the operating
any system constraints when the system is initially operating
state framework [5]–[7] and was proposed in [10]. System
in its normal state. There are two types of security analysis:
well-being can be categorized into the three states of healthy,
transient (dynamic) and steady-state (static). Transient stability
marginal, and at risk, as shown in Fig. 1. In the healthy state,
all equipment and operating constraints are within limits, and
Manuscript received August 8, 2005. Paper no. TPWRS-00497-2005. there is sufficient margin to serve the total load demand, even
The authors are with the Power System Research Group, University of with the loss of any element, i.e., generator or transmission line.
Saskatchewan, Saskatoon, SK S7N 5A9, Canada (e-mail: wijarn.w@usask.ca;
roy.billinton@usask.ca). In the marginal state, the system is still operating within limits,
Digital Object Identifier 10.1109/TPWRS.2005.862000 but there is no longer sufficient margin to satisfy the acceptable
0885-8950/$20.00 © 2006 IEEE
WANGDEE AND BILLINTON: BES WELL-BEING ANALYSIS USING SEQUENTIAL MONTE CARLO SIMULATION 189

Fig. 1. Well-being framework.

deterministic criterion. In the risk state, equipment or system


constraints are violated, and load may be curtailed.
The system well-being concept shown in Fig. 1 is a prob-
abilistic framework incorporating the simplified operating
states associated with the accepted deterministic N-1 security
criterion. Well-being analysis, therefore, provides a combined
framework that incorporates both the deterministic and prob-
abilistic perspectives. It provides system engineers and risk
managers with a quantitative interpretation of the degree of
system security (N-1, healthy) and insecurity (marginal) in a
bulk electric power system. Reliability indexes calculated with Fig. 2. A single-line diagram of the reinforced RBTS (R-RBTS).
the inclusion of appropriate deterministic criteria provide power
system planners, designers, engineers, and operators with addi-
III. SEQUENTIAL SIMULATION PROCESS FOR
tional system information. The degree of system well-being can
SYSTEM WELL-BEING ANALYSIS
be quantified in terms of the probabilities and frequencies of
the healthy and marginal states in addition to the traditional risk A. Basic Procedure of Bulk Electric System
indexes. This paper is focused on system well-being analysis Reliability Evaluation
using sequential Monte Carlo simulation. The advantage when The procedure for well-being analysis of a composite power
utilizing a sequential simulation technique, besides providing system is similar to the basic process used in bulk electric
accurate frequency and duration assessments, is the ability to system reliability evaluation, as briefly illustrated in the fol-
create well-being index probability distributions. It is important lowing steps. More detailed descriptions of the sequential
to appreciate the inherent variability in the reliability indexes technique can be found in references [2], [16], and [17].
and the likelihood of specific values being exceeded. This
1) Specify the initial state of each component (all generating
knowledge can be assessed from the probability distributions
units and transmission links). Normally, it is assumed that
associated with the expected values. At the present time,
all components are initially in the normal state (up state).
sequential simulation is the only realistic option available to
2) Simulate the duration of each component residing in its
investigate the distributional aspects associated with system
present state using the inverse transform method [18] and
index mean values.
the distribution functions of the component failure and re-
pair rates. For example, given an exponential distribution
II. STUDY SYSTEM
function, i.e., , then the sampled value of the
The bulk electric system utilized in this paper is designated as state duration (T) is , where is a uni-
the RBTS [15]. The original RBTS is an educational test system formly distributed random number [0,1] corresponding to
developed by the Power System Research Group at the Univer- the th component. is a failure rate or repair rate, de-
sity of Saskatchewan. The RBTS is a six-bus system composed pending on the current state of the th component.
of two generator buses, five load buses (delivery points), nine 3) Repeat step 2) in a given time span, normally a year.
transmission lines, and eleven generating units. The system peak A chronological up and down state for each component
load is 185 MW, and the total generation is 240 MW. The peak is then constructed in a given time span. Chronological
demands occurring at each individual delivery point may not be hourly load models for individual delivery points are con-
coincident when using chronological load models. The system structed and incorporated in the analysis.
peak demand, therefore, is lower than that of a load model in 4) The simulated operation is assessed for each hour during
which all the delivery points reach their peak loads at the same a given time span. If constraints occur, corrective actions
time. In this case, the system peak is 179 MW rather than 185 may be required to alleviate the constraints and load cur-
MW. In this paper, the original RBTS described above has been tailed if necessary.
reinforced by adding a transmission line (Line #10) between 5) At the end of each simulated year, the delivery point and
Bus 5 and Bus 6 in order to support the original single circuit system reliability indexes are calculated and updated.
delivery point at Bus 6. The reinforced RBTS is designated as Steps 2)–4) are repeated until the coefficient of variation
the R-RBTS and is shown in Fig. 2. is less than the specified tolerance error.
190 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 21, NO. 1, FEBRUARY 2006

The fast decoupled ac power flow technique [19] and linear pro-
gramming methods [7], [20] are implemented in the sequential
software. Corrective actions such as generation rescheduling,
line overload alleviation, operating constraint corrections (i.e.,
real and reactive power, voltage violations), and load curtail-
ment solutions are considered. Approximate techniques are ap-
plied when split network and system ill-conditioning problems
occur. Fig. 3. Bounded network.

B. System Well-Being Analysis Consideration


is curtailed if necessary. If load is curtailed, update the
The procedure described in the previous section is generally marginal indexes, and then skip the rest of components
the overall process for bulk electric system reliability evaluation in the contingency list and proceed to the next simu-
using sequential simulation. The well-being analysis process lated hour. If all the components in the contingency list
can be implemented and extended as a subprocedure in Step 4). do not cause any load curtailment, update the healthy
The following procedures are the extension of Step 4) to include state and proceed to the next simulated hour.
system well-being considerations.
4a) In each simulation hour, the simulation results can be C. Contingency Selection
put in the following three categories. The deterministic N-1 criterion is utilized for security assess-
Category: 1. There is no system contingency; go to ment in the well-being framework analysis. The purpose of a
Step 4b). contingency selection process is to reduce and limit the set of
Category: 2. There exists system contingency(s) but no outaged components (contingencies) to be considered. This dra-
load curtailed; go to Step 4c). matically speeds up the simulation process of security assess-
Category: 3. There exists system contingency(s) and ment. For generation facilities, the largest generating units at
load curtailed. If the system is in this category, it im- different locations in the system are considered, i.e., at two or
plies that the system is in a risk state. The risk indexes more different generator buses. For transmission facilities, the
are updated, and then directly proceed to the next sim- process for transmission contingency selection is as follows.
ulated hour. Step 1) Transmission contingency ranking is used to eval-
4b) If there is no system contingency, the critical gener- uate a scalar performance index (PI) that measures
ating unit, such as a largest unit, is assumed to be how much a particular component outage might
out of service. The system is then assessed whether affect the system [20]. The PI can be measured
or not there is a generation constraint at that simu- in terms of line flows, bus voltage changes, or a
lated hour. If there exists a generation constraint, up- combination of both. This step (transmission con-
date the marginal indexes since this simulated hour tingency ranking) is calculated only once before
does not meet the N-1 criterion. Otherwise, update the starting the simulation process, and the ranking re-
healthy indexes and then proceed to the next simu- sults are stored for future use.
lated hour. If the system tends to be a transmission-de- Step 2) In each simulation hour, when there is transmission
ficient system, the most critical transmission facility contingency(s) but no load curtailment [Step 4c)],
should be also considered in a similar process, as de- the concept of a bounding technique [20], [21] is
scribed above for a generation constraint. If the system used in order to select the critical components to
contains single circuit delivery points, i.e., radial load add to the contingency list. The basic concept of a
buses, these delivery points should be excluded in the bounded network is that a transmission outage tends
system well-being analysis as single circuit delivery to have a localized effect. The loss of a next trans-
points are normally categorized as “N-1 acceptable” in mission facility (N-1) that is located far away from
an actual system. Components, i.e., radial lines, con- the original outaged transmission facility tends to
nected to these delivery points therefore should not have less effect than the loss of one that is close to
be included in the contingency selection process of the original outage. Only transmission facilities that
system well-being analysis when determining the mar- are closest to the original outaged one are added into
ginal and healthy states. The at-risk state indexes for a contingency list. An example of the bounded net-
these delivery points can, however, still be quantified work technique is illustrated in Fig. 3.
under Category 3 in Step 4a) In Fig. 3, if a line outage occurs between buses
4c) If there is a system contingency(s) but no load cur- and , lines # 1–4 are added into the contin-
tailment, contingency selection is investigated and a gency list. Lines # 5–8, which are two lines away
contingency list is built (contingency selection is ad- from the original outaged line, are not considered.
dressed in the next section). Components in the con- After that, transmission lines that are in a contin-
tingency list are tested one at the time. If any selected gency list (lines # 1–4) will be ranked using the
component leads to system violations, corrective ac- PI obtained from Step 1). The reason in ranking
tions are required to alleviate the constraints, and load these selected lines is that the computational time
WANGDEE AND BILLINTON: BES WELL-BEING ANALYSIS USING SEQUENTIAL MONTE CARLO SIMULATION 191

can be reduced when the top-ranked components in TABLE I


the list tend to cause system problems more than DELIVERY POINT AND OVERALL SYSTEM WELL-BEING INDEXES
OF THE R-RBTS (BASE CASE)
the bottom-ranked components in the list. The mis-
ranking of PI will not affect the result accuracy but
will only relatively affect the computation time of
the simulation.
Step 3) The next step is to add the most critical transmis-
sion line based on the PI into the list [if this critical
component is not yet included in Step 2)]. Finally,
the generation contingencies (the largest generating
units at different locations selected prior) are added
to the list to obtain the complete contingency selec-
tion list for a particular simulation hour.
TABLE II
IV. SIMULATION RESULTS DELIVERY POINT AND OVERALL SYSTEM WELL-BEING INDEXES
OF THE R-RBTS (FUTURE CASE)
System well-being results obtained using the developed se-
quential software are presented in this section using two study
scenarios. The first scenario is designated as the base case and
presents the results obtained using the reinforced RBTS config-
uration and the conditions described in Section II. In the second
scenario, the reinforced RBTS described in Section II is modi-
fied to simulate a future system condition in which 2 20 MW
generating units are added to Bus 1, and the load growth is 13%.
A simulation period of 4000 years was used in these studies.
The coefficient of variation of the expected energy not supplied
(EENS) based on 4000 simulated years is less than 2.5%.
point well-being indexes. The main focus in system well-being
A. System Base Case analysis is on the security of the system as a whole rather than
The well-being indexes are the probabilities, frequencies, and on individual delivery points as violations of a delivery point
durations of the healthy, marginal, and risk states and are listed are considered to be a system security operation problem. The
as follows: delivery point well-being indexes, however, provide supple-
Prob Probability of the healthy state (per year). mentary information to the overall system well-being indexes.
Prob Probability of the marginal state (per year). The Prob and Freq , respectively, shown in Table I
Prob Probability of the at-risk state (per year). are identical to the probability of load curtailment (PLC) and
Freq Frequency of the healthy state (occurrences per expected frequency of load curtailment (EFLC) used in conven-
year). tional bulk electric system reliability evaluation [1], [2]. The
Freq Frequency of the marginal state (occurrences per system reliability in the base case shown in Table I is rela-
year). tively high (low system risk Prob ). The de-
Freq Frequency of the at risk state (occurrences per year). gree of system well-being can be appreciated using Prob . In
Dur Average residence duration in the healthy state this scenario, the degree of system well-being is relatively high
(hours per occurrence). Prob . This indicates that the probability of
Dur Average residence duration in the marginal state the system residing in a state in which the loss of any single com-
(hours per occurrence). ponent following random system contingencies would not result
Dur Average residence duration in the at-risk state (hours in a load curtailment condition is 93.1%. Freq indicates that
per occurrence). there are 91.59 times on average when the system leaves the
The residence duration of each state can be roughly calcu- healthy state, and Dur indicates that the system resides in
lated using the ratio of the state probability to the state frequency the healthy state for 92.01 hours on average before departure to
based on the overall simulation years. The accurate residence another state.
duration, however, should be calculated by considering it on an
individual simulation year basis. The average residence dura- B. System Future Case
tion of each state shown in this paper is based on the individual In this scenario, the R-RBTS environment described in Sec-
simulation year approach. tion II has been modified to consider a situation in which 2
Table I presents the base case well-being indexes for the 20 MW generating units are added to Bus 1, and the load has
delivery points and for the overall R-RBTS. It is important to grown by 13%. This scenario creates an increased utilization
note that the delivery point indexes are directly affected by the of the existing transmission networks, which is a common sit-
load curtailment philosophy used in the analysis. This effect uation under the transmission open access paradigm. Table II
is relatively minor for the overall system indexes [22]. The shows the future case well-being indexes for the delivery points
contingency selection process also directly affects the delivery and for the overall R-RBTS.
192 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 21, NO. 1, FEBRUARY 2006

Fig. 4. System well-being index probability distributions for the base case and future scenarios.

Table II shows the system well-being indexes for the future maintained (even lower risk compared to the base case) but with
case where the system conditions have created increased trans- an increased system stress level (high marginal probability) as
mission utilization compared to the base case. The R-RBTS more of the contingencies that resided in the healthy state for the
shown in Fig. 2 has a generation center located in the northern base case move to the marginal state for the future scenario. A
part of the system, while most of the system loads are located in knowledge of contingency movements, particularly when they
the southern area. There are, therefore, significant power trans- move from healthy to marginal, is very important, and they are not
fers from the north to the south through the two double circuits identified using traditional probabilistic reliability assessment
(lines # 1 and 6, and lines # 2 and 7). The transmission utiliza- (risk indexes) until they actually move into the at-risk region
tion on lines # 1 and 6 in this scenario is approximately 80% of when they suddenly begin to have a severe effect. The outcome
the line ratings, while that of lines # 2 and 7 experiences approx- is not easily identified if only at-risk states are considered since
imately 50% of the line ratings during the system peak demand. the at-risk probabilities do not change to any significant degree
The power flow on lines # 2 and 7 is less than those on lines # 1 [11]. The well-being approach, therefore, attempts to bridge the
and 6 as they are long transmission circuits with relatively high gap between the deterministic and probabilistic approaches by
impedances. The loss of any one transmission line in the critical addressing the need to determine the likelihood of encountering
path (lines # 1 and 6) during a high demand period could result marginal system states as well as that of encountering system
in an overload on the remaining line. at-risk states. The system well-being concept provides a com-
Table II indicates that even though the system risk under prehensive knowledge of specific system conditions as well
the future scenario Prob is lower than that as additional information on what the degree of the system
of the base case shown in Table I Prob , vulnerability might be under a particular system condition.
the Prob for the future scenario is, however, considerably
higher, which indicates the potential of the system moving C. System Well-Being Index Probability Distributions
from the marginal state to the at-risk state in the near future. The The results shown in Sections IV-A and IV-B are based on
Prob is, therefore, relatively low under the future system con- the average or expected values of the well-being indexes. One
dition. The acceptable healthy state probability level is dependent advantage when utilizing sequential Monte Carlo simulation
on management philosophy, which can vary from one system to in system well-being analysis is the ability to provide system
another. The results shown in Table II illustrate the example of well-being index probability distributions associated with their
a system with a future scenario in which the system reliability is expected values. The system well-being index probability
WANGDEE AND BILLINTON: BES WELL-BEING ANALYSIS USING SEQUENTIAL MONTE CARLO SIMULATION 193

distributions, which provide a pictorial representation of the [3] IEEE Task Force, Reliability assessment of composite generation and
annual variability of the indexes, are illustrated in this section. transmission systems, in IEEE Tutorial Course 90EHO311-1-PWR, Feb.
1990.
The overall system well-being indexes obtained using the two [4] M. V. F. Pereira and N. J. Balu, “Composite generation/transmission reli-
scenarios presented in Tables I and II are graphically presented ability evaluation,” Proc. IEEE, vol. 80, no. 4, pp. 470–490, Apr. 1992.
[5] L. H. Fink and K. Carlsen, “Operating under stress and strain,” IEEE
in Fig. 4, accompanied by the expected or average (avg.) values Spectr., vol. 15, no. 3, pp. 48–53, Mar. 1978.
and the standard deviations (S.D.). Reliability index probability [6] EPRI Final Report, “Composite-System Reliability Evaluation: Phase
distributions are normally created as frequency histograms 1—Scoping Study,”, Tech. Rep. EPRI EL-5290, Dec. 1987.
[7] R. Billinton and E. Khan, “A security based approach to composite
using discrete intervals (bins). The probability distributions power system reliability evaluation,” IEEE Trans. Power Syst., vol. 7,
shown in this paper are, however, presented using approximate no. 1, pp. 65–71, Feb. 1992.
continuous distributions for illustration purposes rather than [8] North American Electric Reliability Council Planning Standards. [On-
line]http://www.nerc.com.
histograms. The use of smooth curves in representing the [9] Union for the Co-ordination of Transmission of Electricity (UCTE).
probability distributions facilitates comparisons of the various Policy 3: Operational Security (Final Policy 1.3 E, 20.07.2004), Asso-
scenario results on the same axis. ciation of Transmission System Operators in Continental Europe. [On-
line]http://www.ucte.org.
Fig. 4 shows that the distributions of the healthy and marginal [10] R. Billinton and G. Lian, “Composite power system health analysis
state indexes (probability, frequency, and duration) tend to have using a security constrained adequacy evaluation procedure,” IEEE
Trans. Power Syst., vol. 9, no. 2, pp. 936–941, May 1994.
normal distribution characteristics for both the base case and fu- [11] R. N. Allan and R. Billinton, “Probabilistic assessment of power sys-
ture scenarios. The distributions of the at-risk indexes, however, tems,” Proc. IEEE, vol. 88, no. 2, pp. 140–162, Feb. 2000.
have exponential trends due to the fact that the system reliability [12] R. Billinton and R. Mo, “Deterministic/probabilistic contingency
evaluation in composite generation and transmission systems,” in Proc.
under these two scenarios is relatively high (low system risk). IEEE Power Engineering Society General Meeting, vol. 2, Jun. 2004,
Fig. 4 also shows that the well-being index probability distri- pp. 2232–2237.
butions (probability and frequency) of the less healthy system [13] E. Khan and R. Billinton, “A hybrid model for quantifying different op-
erating states of composite systems,” IEEE Trans. Power Syst., vol. 7,
condition (future scenario) have more dispersion and, therefore, no. 1, pp. 187–193, Feb. 1992.
more uncertainty with lower predicted probability of occurrence [14] A. M. L. da Silva, L. C. de Resende, L. A. F. Manso, and R. Billinton,
compared to those of the base case. The probability distribution “Well-being analysis for composite generation and transmission sys-
tems,” IEEE Trans. Power Syst., vol. 19, no. 4, pp. 1763–1770, Nov. 2004.
of the residence duration in the healthy state for the less healthy [15] R. Billinton et al., “A reliability test system for educational pur-
system (future scenario) is, however, less dispersed with shorter poses—basic data,” IEEE Trans. Power Syst., vol. 3, no. 4, pp.
1238–1244, Aug. 1989.
residence times than that for the base case. Operating a system in [16] R. Ubeda and R. N. Allan, “Sequential simulation applied to composite
such an environment (less healthy) will, therefore, make it more system reliability evaluation,” Proc. Inst. Elect. Eng., Gener., Transm.,
difficult for system engineers to manage the potential system Distrib., vol. 139, no. 2, pp. 81–86, Mar. 1992.
[17] A. Sankarakrishnan and R. Billinton, “Sequential Monte Carlo simula-
risk with a high degree of confidence. tion for composite power system reliability analysis with time varying
loads,” IEEE Trans. Power Syst., vol. 10, no. 3, pp. 1540–1545, Aug.
1995.
V. CONCLUSION [18] R. Y. Rubinstein, Simulation and the Monte Carlo Methods Wiley,
New York, 1981.
The system well-being concept provides a probabilistic frame- [19] B. Stott and O. Alsac, “Fast decoupled load flow,” IEEE Trans. Power
work that incorporates a practical simplification of the traditional App. Syst., vol. PAS-93, pp. 859–869, May/Jun. 1974.
operating states associated with the accepted deterministic N-1 [20] A. J. Wood and B. F. Wollenberg, Power System Generation, Operation
and Control, 2nd ed. Wiley, New York, 1996.
security criterion. Well-being analysis, therefore, provides a [21] V. Brandwajn, “Efficient bounding method for linear contingency anal-
combined framework that incorporates both deterministic and ysis,” IEEE Trans. Power Syst., vol. 3, no. 1, pp. 38–43, Feb. 1988.
[22] W. Wangdee and R. Billinton, “Impact of load shedding philosophies on
probabilistic perspectives. System well-being analysis for a bulk electric system reliability analysis using sequential Monte Carlo
bulk electric system using a sequential Monte Carlo simula- simulation,” Elect. Power Compon. Syst., vol. 34, no. 3, pp. 355–368,
tion technique is presented in this paper. One advantage when Mar. 2006.
utilizing a sequential simulation technique, besides providing
accurate frequency and duration assessments, is the ability to
create well-being index probability distributions. The results Wijarn Wangdee (S’03) received the B.Eng. degree in electrical engineering
shown in the paper indicate that different system conditions that from Chulalongkorn University, Bangkok, Thailand, in 1999. He received the
M.Sc. degree in electrical engineering in 2002 and is currently working toward
result in a similar degree of system risk may not necessarily carry the Ph.D. degree from the University of Saskatchewan, Saskatoon, SK, Canada.
the same degree of system stress (marginal state). The system He joined the Power System Research Group at the University of
well-being concept provides system engineers and risk managers Saskatchewan in September 2000.
with a quantitative interpretation of the degree of system security
(N-1, healthy) and insecurity (marginal) in a bulk electric power
system. The basic concepts and their application in composite Roy Billinton (S’59–M’64–SM’73–F’78) came to Canada from England in
system well-being analysis are illustrated by application to a 1952. He obtained the B.Sc. and M.Sc. degrees from University of Manitoba,
Winnipeg, MB, Canada, and the Ph.D. and D.Sc. degrees in electrical engi-
small practical test system using two different system conditions. neering from the University of Saskatchewan, Saskatoon, SK, Canada.
He was with the System Planning and Production Divisions of Manitoba
Hydro. He joined the University of Saskatchewan in 1964. He is the author and
REFERENCES coauthor of eight books on reliability evaluation and over 775 papers on power
[1] R. Billinton and R. N. Allan, Reliability Evaluation of Power Systems, system reliability evaluation, economic system operation, and power system
2nd ed. New York: Plenum, 1996. analysis.
[2] R. Billinton and W. Li, Reliability Assessment of Electrical Power Sys- Dr. Billinton is a Fellow of the EIC and the Royal Society of Canada and a
tems Using Monte Carlo Methods. New York: Plenum, 1994. Registered Professional Engineer in the Province of Saskatchewan, Canada.

You might also like