Lebanon Water Project LWP

Lebanon Water Project


A3-CQC DAILY REPORT  

Project: Date: 23-5-2019


Upgrade of potable water facilities in el
Ayoun,Rachaaine and Rahbeh villages
Project No: CQM:
Construction Subcontractor: Arison Safety Meeting (Y/N): Incident (Y/N):
Weather Conditions: Sunny Avg Temp:
Equipment on Site:
Equipment on Site: Subcontractor Labor on Site
Type Qty Idle Position No Idle
Excavator 1 Project Manager 1
Truck 1 Foreman 1
Bobcat 1 Excavator operator 1
Labor 2
Bobcat operator 1
Truck operator 1

ONGOING ACTIVITIES
BOQ Div Area Description
Rahaaine village Pouring concrete cover protection above the drainage pipe

Rahaaine village Preparing the route to the site

QC INSPECTIONS PERFORMED
BOQ Div Area Type: Definable Scope of Work and Inspection type Approved QC Issues/ Name of
Prelim/ / Not inspector
Initial/ Approved
Final

CQC Daily Report


1 Appendix A-3
Lebanon Water Project LWP
Lebanon Water Project
A3-CQC DAILY REPORT  

OPEN DEFICIENCIES
BOQ Div Area Type* QC Issue Description Anticipate Comment
d Resolve
Date

*QC Issue Type: Def= Deficiency, NC= Non-Compliance, S=Saftey, EN= Environmental, Other
ACTIVE NON COMPLIANCE ISSUES(if any)
BOQ Div Area NCN No. NCN Description and Remedial Activities Anticipate Comment
d Resolve
Date

SUBMITTALS, RFI or OTHER CORRESPONDENCE RECEIVED TODAY


Description Type Control Number Stamped Storage

SAFETY MEETING TOPIC:


SITE SECURITY: ( document any issues)
List of visitors:
Name Title Organization Time

CQC Daily Report


2 Appendix A-3
Lebanon Water Project LWP
Lebanon Water Project
A3-CQC DAILY REPORT  

Materials Delivered:

QCM Comments

Signatures Date

QCM

Subcontractor Representative
Khodor Elwan 23-5-2019

CQC Daily Report


3 Appendix A-3