You are on page 1of 10

Impact of Skilled Labor Availability on

Construction Project Cost Performance


Hossein Karimi, Ph.D., A.M.ASCE 1; Timothy R. B. Taylor, Ph.D., P.E., M.ASCE 2;
Gabriel B. Dadi, Ph.D., P.E., M.ASCE 3; Paul M. Goodrum, Ph.D., P.E., M.ASCE 4;
and Cidambi Srinivasan, Ph.D. 5
Downloaded from ascelibrary.org by La Trobe University on 05/03/18. Copyright ASCE. For personal use only; all rights reserved.

Abstract: The North American construction industry began to experience a shortage of skilled labor in the 1980s, which has continued as a
repetitive cyclic trend over the last three decades. Although this issue has received significant attention from researchers, less attention has
been given to quantifying the impact of skilled labor availability on project performance. This study contributes to the body of knowledge by
filling a gap in the existing literature by quantitatively modeling and elucidating the influence of skilled labor availability on construction
project cost performance. Data from 97 construction projects completed in the United States and Canada were collected from two industry
databases. The primary analysis shows that projects that experienced craft shortages underwent significantly higher growth in cost overruns
compared with projects that did not. Further analysis on both databases returned two robust multiple regression models that demonstrate
similar patterns of the risk that a skilled labor shortage poses to cost performance. By using data-combining techniques, two data sets were
combined to obtain more reliable informative models. The primary benefit of this risk estimation is to enable project management teams to
determine whether mitigation strategies are warranted to prevent potential shortfalls in project cost performance. Understanding the level
of impact that craft shortages have on project performance can serve as a primary step in developing motivation for industry leaders,
communities, and construction stakeholders to address the challenge of skilled labor shortage in construction industry. DOI: 10.1061/
(ASCE)CO.1943-7862.0001512. © 2018 American Society of Civil Engineers.
Author keywords: Craft labor; Cost; Skills shortage; Risk assessment; Data combining.

Introduction and Background with a repetitive cyclic trend over the last three decades. The inevi-
table consequences of this shortage are difficulties in recruiting
Construction is a labor-intensive industry. Labor costs account for and retaining skilled labor for projects, which puts the financial
30–50% of the total cost of a project (McTague and Jergeas 2002; success of projects in a precarious situation. The evidence of this
Hanna 2001). It is considered an element that contains the most shortage between the 1980s and 2008 Great Recession has been
risks in a project cost. The other major elements of a project costs discussed frequently in previous literature (Business Roundtable
(materials and equipment) are significantly influenced by market 1983, 1997; Construction Industry Institute 1990; Abdol et al.
price and often beyond the control of a project manager. Consid- 1999; Rosenbaum 2001; Goodrum 2004; Sawyer and Rubin 2007).
ering the 2–3% profit margin of many construction projects, a con- The slowdown in construction work during the 2008 Great Reces-
tractor’s management of labor cost and productivity is critical to sion in the United States began to temporarily ameliorate the craft
the financial success of a construction project (Hanna et al. 2005; shortage for a period of time. However, the postrecession rapid eco-
Ernzen and Schexnayder 2000). nomic recovery again initiated a craft shortage in some segments
The North American construction industry began to experi- of the industry. The Construction Industry Institute (CII) (2015)
ence a shortage of skilled labor in the 1980s, which has continued revealed that the severe shortages among key craft trades, including
welders, pipefitters, and electricians, appeared, particularly in the
1
Postdoctoral Associate, School of Civil Engineering, College of US southeast and southwest regions. Taylor et al. (2016) conducted
Engineering, Univ. of Tehran, 16 Azar Ave., P.O. BOX 14395-477, Tehran, a survey among the North American construction companies and
Iran (corresponding author). ORCID: https://orcid.org/0000-0001-7290- revealed that 52% of surveyed projects were impacted by skilled
7822. Email: karimi.hossein@ut.ac.ir; hossein.karimi@uky.edu
2 labor shortage.
Associate Professor and Terrell-McDowell Chair of Construction
Engineering and Project Management, Dept. of Civil Engineering, Univ. Projects encountering craft labor shortages endure difficulties
of Kentucky, Lexington, KY 40506-0281. in recruiting and retaining a required level of skills and/or quantity
3
Assistant Professor, Dept. of Civil Engineering, Univ. of Kentucky, of craft labors. When the required quality level of skills cannot
Lexington, KY 40506-0281. be met, a project will be executed with less-skilled workers. When
4
Nicholas R. Petry Professor in Construction Engineering and Manage- a craft labor quantity issue arises, a project cannot meet its basic
ment, Dept. of Civil, Environmental, and Architectural Engineering, Univ. labor demand. A project executed under either of these two con-
of Colorado, Boulder, CO 80309. ditions is highly likely to experience cost escalation. Previous
5
Professor, Dept. of Statistics, Univ. of Kentucky, Lexington, KY
works provide a wealth of information on how a shortage of skills
40506-0281.
Note. This manuscript was submitted on July 24, 2017; approved on
can affect project cost performance. To propose testable hypoth-
January 15, 2018; published online on May 3, 2018. Discussion period eses and models built on previous research findings, the authors
open until October 3, 2018; separate discussions must be submitted for reviewed and examined the body of literature that discusses the
individual papers. This paper is part of the Journal of Construction En- impact of skilled labor availability on construction projects’ cost
gineering and Management, © ASCE, ISSN 0733-9364. performance.

© ASCE 04018057-1 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 2018, 144(7): 04018057


Impact of Skilled Labor Availability on Cost increases in hourly wage, escalation in safety incidents, increases in
Performance: Evidence from Previous Researches amount of rework, and escalation of schedule overruns are major
processes that ultimately result in further cost overruns in a project
Cost performance of a construction project is a complex function of encountering a skilled labor shortage.
many factors. Over the last two decades, there have been numerous
studies about predicting the accuracy of construction project actual
Impact through Loss of Productivity
costs. Doloi (2013) summarized the highlighted key factors in the
past research into seven groups as follows: Project productivity can be significantly affected by a shortage
• project-related factors (such as scope, size, and type of project); of skilled labor. Dai et al. (2009) identified 10 groups of factors
• contract-related factors (such as contract management and form that represent the underlying structure of productivity. Among
of procurement); these groups, four factors were related to labor issues, namely train-
• project management factors (capability of construction team); ing, craft worker qualification, superintendent competency, and
• quality-related factors (such as inspection and testing of work, foreperson competency. They also found that the qualification of
method, and techniques); workers is an area that has the greatest possibility for project pro-
Downloaded from ascelibrary.org by La Trobe University on 05/03/18. Copyright ASCE. For personal use only; all rights reserved.

• planning-related factors (such as effective monitoring process ductivity improvement. Wang et al. (2008) showed that the effec-
and construction control); tiveness of craft training on project productivity is significant. They
• market-related factors (such as availability of labors and short- also showed that higher percent of certified workers in a project
age of material); and was statistically associated with higher project productivity. Heravi
• contractor-related factors (such as experience and communica- and Eslamdoost (2015) developed a predictive model for estimating
tion between client and contractor). construction labor productivity and found that by improving “labor
Doloi (2013) also conducted a survey on 160 Australian con- competence,” labor productivity could be increased by 13–18.7%,
struction clients, consultants, and contractors. The contractors and which makes it one of the top five influential factors that can highly
clients ranked “availability and supplies of labor and material” as improve labor productivity. Karimi et al. (2017) analyzed 97 con-
the 21st and 15th important factors (total of 48 factors) contributing struction projects completed in the United States and Canada and
to the cost performance, respectively. Akintoye (2000) conducted a found a significant decline in productivity of projects that experi-
comparative study on 84 British contractors ranging from very enced a craft shortage compared with those that did not. By con-
small to large firms about factors influencing contractor cost esti- ducting a regression analysis, they also demonstrated that there is a
mating practices. Overall, “availability and supply of labor and significant relationship between increased skilled labor recruiting
material” was ranked 10th among 24 identified factors. In addition, difficulty and the decline in project productivity.
by performing factor analysis, this variable was also recognized as
one of the significant contributors to project cost performance. Impact through Use of Overtime and Growth in
Gharaibeh (2014) conducted a Delphi study on project manage- Hourly Wage
ment teams of two megaprojects in Canada. “Lack of contingency
Projects experiencing a shortage of skilled craft workers usually
and escalation for material and craft labor costs in the initial esti-
have a tight schedule to meet a project deadline. Hanna et al. (2005)
mate” was identified as one of the top 10 most important problems
argued that overtime scheduling has become the prevalent option in
in managing project cost. In addition, “applying quantity-tracking
this situation because it accelerates a project schedule. They ex-
concept to monitor changes of material and craft labor quantities”
plained that an associated premium pay with overtime can attract
was mentioned as one of the top 10 most important lessons learned
the required workforce as well. Karimi et al. (2017) demonstrated
in managing project cost performance.
that there is a significant relationship between an increased craft
In a quantitative analysis and to establish a model for early cost
recruiting difficulty and increased use of overtime hours in con-
estimation, Trost and Oberlender (2003) performed a factor analy-
struction projects. The extended overtime can significantly dimin-
sis and multivariate regression on 45 identified cost drivers on 67
ish a project’s productivity (Li et al. 2017; Lyneis and Ford 2007;
completed construction projects across the world. The Bidding and
Hanna et al. 2005), which ultimately results in growth of total craft
Labor Climate factor, recognized as one of the five variables that
workhours and final cost of a project.
significantly impacts cost estimate accuracy, accounted for 14.5%
This strategy is usually associated with premium pay, which,
of the prediction in the model. This factor includes the effects of along with other approaches such as bonuses, loyalty rewards, and
bidding climate, labor productivity, contract type, project schedule, promotions, is a common short-term solution that project managers
and logistics for engineering and construction. RSMeans (2016) use for attracting and retaining a workforce (Abdol et al. 1999;
suggested a cost allowance of 10% of the total construction cost Hanna et al. 2005). Therefore, the shortage of skilled labor often
for building projects encountering a shortage of skilled labor. This encompasses increases in craft labor’s hourly wage. CII (2015)
allowance rises to 11% for heavy industrial projects. reported that trades with the highest level of shortage in the
These previous works emphasize the significance of the direct United States also had the highest wage growth in recently com-
impact of skilled labor availability on cost performance. Further pleted projects. The top three trades with the highest level of shortage
exploration of previous literature indicates that mechanism of the were pipe welders, pipefitters, and structural welders, with average
impact of skilled labor availability on project cost is complex and actual wage growth of 6.0, 5.4, and 3.1% in a project, respectively.
can be through various processes. For instance, cost escalation can
result from increasing total craftwork hours due to the reduction of
labor productivity in a project that has experienced a skills short- Impact through More Frequent Safety Incidents
age. Another example is the increase in safety incidents due to the Karimi et al. (2016) analyzed the influence of a skilled labor short-
lack of experienced/skilled craft labor (Karimi et al. 2016), which age on project safety performance and demonstrated that there is
results in imposing additional direct costs (i.e., clean up and repair a strong relationship between increased skilled labor staffing diffi-
or equipment damage) and indirect costs (i.e., disrupted schedules) culty and increased total recordable incident rate (TRIR). The
on a project (Improving Construction Safety Performance 1982). impact of construction injuries on project cost performance with
In summary, loss of productivity, increases in extended overtime, regard to the indirect cost of injuries is substantial. Hinze and

© ASCE 04018057-2 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 2018, 144(7): 04018057


Appelgate (1991) demonstrated that indirect costs, which are sub- the impact on hourly wages and quality performance. This study
stantially greater than direct costs, make the cost of even a minor also examines the influence of time overruns on cost overruns
injury considerable. Indirect costs are but not limited to the loss of as a part of the process of a craft shortage’s influence on cost per-
productivity, disrupted schedules, administrative time for investiga- formance through impacts on time overruns. The importance of
tions and reports, training of replacement personnel, wages paid to addressing these knowledge gaps lies in the fact that doing so will
the injured workers and other workers for time not worked, clean explicate and clarify the significance of skilled labor availability as
up and repair, adverse publicity, third-party liability claims against one of the main causes of cost overruns in construction projects.
the owner, and equipment damage (Improving Construction Safety To accomplish the previously mentioned aims, the following re-
Performance 1982). Everett and Frank (1996) found that injuries search objectives were defined:
account for 7.9–15% of the cost of nonresidential new construction • Examine whether there is a significant relationship between
projects. That indicates the significant contribution of safety acci- craft staffing difficulty and hourly wage as well as quality per-
dents to cost overruns, particularly when projects experience a craft formance. In addition, it will be examined if there is a significant
labor shortage. influence of time overrun on cost overrun. Fulfilling this objec-
tive, along with results of recent aforementioned studies men-
Downloaded from ascelibrary.org by La Trobe University on 05/03/18. Copyright ASCE. For personal use only; all rights reserved.

Impact through Increasing Schedule Overrun tioned, will complete the quantitative support for all processes
of influence of skilled labor shortage on cost performance.
Karimi et al. (2017) presented a series of quantitative analyses on a • Identify whether there is a significant difference in cost overrun
total of 97 construction project completed in the United States and of projects that experienced a craft labor shortage versus the
Canada and demonstrated that there was a significant difference be- ones that did not.
tween the average time overrun of projects that experienced a craft • Develop a model that quantifiably links skilled labor variability
shortage and ones that did not. The study also showed that there is a to project actual cost overrun.
statistically significant relationship between craft recruiting difficul-
ties and time overruns in construction projects. Delays in a project
cause direct and indirect costs. Direct costs are costs related to Data Collection
additional labor, equipment, and material to complete the job, and
indirect costs are often, but not limited to, site and home office over- The data used in this research were obtained from two different sour-
heads (Chester and Hendrickson 2005). The evidence of the impact ces to enhance the validity and reliability of the study. The first
of project duration variation on cost performance has been demon- source was a primary data collection effort through a CII Research
strated in previous studies (Akintoye 2000; Flyvbjerg et al. 2004). Team 318 (RT-318) survey (Taylor et al. 2016). This survey collected
project performance and workforce demographic data on completed
construction projects in the United States and Canada. The survey
Impact through Decline in Quality Performance
was developed, pilot-tested, and distributed to CII and non-CII
Shortages of skills on a project causes construction field rework. member construction organizations. There were 29 total responses
Fayek et al. (2003) quantified the cost of each cause of rework to the survey (30% response rate), with 26 projects from the United
in a mining expansion venture project. The root-cause analysis States and three from Canada. Most of the survey responses were
on 125 field rework incidents (accounting for 0.87% of the total industrial projects (25 out of 29), whereas the remaining projects
cost of construction) showed that inadequate technical knowledge were a building (one project), light industrial (one project), and infra-
of supervisors, lack of training and experience of supervisors, inad- structure (two projects). The projects were distributed across North
equate supervisor/foreperson/tradesperson ratios, lack of adherence America covering 18 states in the United States and three Canadian
to procedure, and shortage of skilled labor and supervision ac- provinces. Except for two projects performed between 2009 and
counted for a total of 13.12% of total construction field rework 2011, all of the other 27 projects were performed and completed
costs. With much research effort focusing on the impact of rework between 2011 and 2014. The results of this survey were used to con-
on the cost of projects, it is now well-known that rework is one of struct a database of project characteristics. Additional details of the
the key contributors to a project’s cost overrun. Researchers found survey effort were described by Taylor et al. (2016).
rework could account for 2.4–12.4% of the total cost of a project The second data source was obtained through the CII Bench-
(Hwang et al. 2009; Love and Li 2000). marking and Metrics (CII BM&M) database. The CII BM&M data-
base was designed to get comprehensive data of construction
Departure Point projects performed by CII member companies. For this research,
all projects in this database that reported data of availability of
The body of literature provides strong quantitative and qualitative skilled labor were selected. This subset consisted of 68 completed
support for various processes of the impacts of skilled labor short- projects, of which 59 were performed in the United States and nine
age on cost performance. In addition, it provides strong qualitative in Canada. Of these 68 projects, 31 projects (45%) were heavy
support for the influence of skilled labor availability on project cost industrial, 24 projects (35%) were commercial building, seven
performance. However, no studies have yet examined an empirical projects (10%) were light industrial, and six projects (9%) were in-
overall impact of craft labor shortage on project cost performance. frastructure projects. All projects in this database were executed be-
This study contributes to the body of knowledge by collecting and tween 2001 and 2013. Additional details of the CII BM&M survey
analyzing empirical data of projects recently completed in the and the subset of data used in this study can be found in Taylor et al.
United States and Canada to quantitatively model and elucidate the (2016) and Karimi (2017). Table 1 provides the average, median,
influence of skilled labor availability on construction project cost and range of the size of these projects in terms of actual cost, actual
performance. time, and actual craft direct work hours in both databases.
Besides regarding empirical evidence provided by the previous
studies for various influential processes of the impacts of skilled
Skilled Labor Availability Measurement
labor shortage on cost performance, remaining processes that have
not been proved quantitatively will be examined. These processes In both databases, an estimate of the level of craft shortages in proj-
include the impact of craft shortages on cost performance through ects relied on subjective evaluations by project management teams.

© ASCE 04018057-3 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 2018, 144(7): 04018057


Table 1. Summary of projects size in RT-318 survey and CII BM&M Cost overrunð%Þ
database
Actual construction cost − Budgeted construction cost
Average Minimum ¼ × 100
Database Project size (median) and maximum
Budgeted construction cost
RT-318 survey Actual cost ($ millions) 455.2 (45) 3.6 and 8,549 Schedule overrunð%Þ
(29 projects) Actual schedule (days) 554.7 (533) 134 and 1,648
Craft work hours 610.6 (321) 13.3 and 3,777.9 Actual construction schedule − Planned construction schedule
¼
(1,000 h) Planned construction schedule
CII BM&M Actual cost ($ millions) 142.5 (40.1) 0.5 and 1,799.3 × 100
(68 projects) Actual schedule (days) 1,054.5 (678) 46 and 3,131
Craft work hour 732.5 (110) 2.5 and 8,870.6
(1,000 h) Quality Performance
The quality performance in CII BM&M projects was measured
Downloaded from ascelibrary.org by La Trobe University on 05/03/18. Copyright ASCE. For personal use only; all rights reserved.

and obtained by a subjective evaluation of project management


Table 2. Levels of craft staffing difficulties in the RT-318 survey team. The respondents of the CII BM&M questionnaire were asked
Level Definition Score to indicate the level of success of their project’s quality perfor-
mance on the scale of 1 as Not At All Successful to 7 as Extremely
No Difficulty There was no shortage. Able to staff the 0 Successful. The RT-318 survey did not collect any data related to
project with no delay on construction
quality performance.
Slight Recruiting difficulties led to consumption of 1
schedule float and/or contingency
Moderate Recruiting difficulties led to delay of 2 Hourly Wage Change
completing project activities on time
Severe Recruiting difficulties led to delay of 3 The RT-318 survey asked respondents to provide an estimated and
completing project milestones actual raw hourly wage for each of the aforementioned 13 trades in
Very Severe Recruiting difficulties led to project delay 4 their projects. Therefore, an hourly wage change in a project for
each trade was measured by a percentage of change in wage relative
to the estimated one as follows:
That is because collecting quantitative data on labor availability (sup-
ply and demand) over the whole period of a project and for different Hourly wage changeð%Þ
trades is a complex task. It requires collecting the number of required Actual hourly wages − Estimated hourly wages
craft labor (demand) as well as actual hired craft labor (supply) in ¼ × 100
Estimated hourly wages
each week or month. In addition, the level of skills of the hired craft
workers needs to be taken into consideration, which increases the The CII BM&M database had no data related to the hourly wage
complexity of this measurement. Therefore, it is justified to choose of craft labor in projects.
subjective measurements by the project management team as an ap-
propriate way to measure skilled labor availability in a project.
In the RT-318 survey, respondents were asked to indicate the Data Analysis
level of craft staffing difficulty they experienced on their project
for 13 craft labor trades, which included carpenters, pipefitters,
electricians, boilermakers, sheet-metal workers, ironworkers, pipe Preliminary Hypothesis Testing
welders, structural welders, equipment operators, crane operators, The purpose of preliminary hypothesis testing is to examine the
millwright workers, instrument fitters, and supervisors. There were influential processes of the impact of craft shortage on cost perfor-
five levels of staffing difficulty defined in the survey, ranging from mance that have not yet been examined empirically in previous
No Difficulty to Very Severe (Table 2). To provide an overall level works. These processes include the impact of craft labor shortages
of craft staffing difficulty for each project, the authors calculated an on quality performance decrease as well as craft hourly wage in-
aggregate average of craft staffing difficulty across these 13 trades creases. In addition, the impact of time overruns on cost overruns
for each project as follows: will be examined as a part of the impact process of a craft shortage
Craft staffing difficulty score of a project on cost performance through time overruns.
Simple linear regression analysis was selected to examine the
ð0 × AÞ þ ð1 × BÞ þ ð2 × CÞ þ ð3 × DÞ þ ð4 × EÞ
¼ hypotheses. The null hypothesis for each analysis is that no rela-
13 tionship exists between the two variables. The alternative hypoth-
in which A, B, C, D, and E = numbers of trades in each level of esis is that there is a significant relationship between the two
staffing difficulty from No Difficulty to Very Severe. variables, which was determined by obtaining a p-value of less than
In the CII BM&M database, respondents indicated the level of 0.05. For all regression analyses, outliers were detected and re-
availability of skilled labor across all trades compared with what moved from the analysis using the Cook’s distance as suggested by
had been specified during the planning stage of their projects. Agresti (2015). The two variables used in the regression analyses to
These levels ranged from Extremely Negative (−5) to Extremely assess the level of craft labor availability were the craft staffing dif-
Positive (þ5), with zero representing the as-planned situation. ficulty (RT-318 survey) and skilled labor availability (CII BM&M).
Both variables are categorical with natural ordering; hence, they can
be referred to as ordinal variables. To use more powerful methods
Cost and Schedule Performance
available for quantitative variables such as regression, it is possible
The cost and schedule performances in both databases were mea- to assign numerical scores to categories of ordinal variables and treat
sured by the percentage of cost and schedule overrun relative to the them as an interval variable (Agresti and Finlay 2009). Both vari-
planned ones as follows: ables had been assigned numerical scores and were suitable to be

© ASCE 04018057-4 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 2018, 144(7): 04018057


Table 3. Summary of preliminary hypothesis development
Hypothesis Database (unit) Dependent variable Independent variable Null hypothesis Alternative hypothesis
H1 RT-318 survey (trade) Hourly wage change Craft staffing difficulty There is no relationship There is a relationship between
between variables hourly wage change and craft
staffing difficulty
H2 RT-318 survey & Cost overrun Time overrun There is no relationship There is a relationship between
CII BM&M (project) between variables cost overrun and time overrun
H3 CII BM&M (project) Meeting quality Skilled labor availability There is no relationship There is a relationship between
performance between variables meeting quality performance
expectation expectation and skilled labor
availability
Downloaded from ascelibrary.org by La Trobe University on 05/03/18. Copyright ASCE. For personal use only; all rights reserved.

Table 4. Summary of the results of preliminary hypothesis testing Hinze & Appelgate (1991)
Karimi et al. (2016) Safety Everett & Frank (1996)
Number of Performance
Model data points Equationa R2 P-value
H1 96 trades Y ¼ −1.03 þ 1.83X 0.24 <0.0001 Karimi et al. (2017)
Overtime
H2 72 projects Y ¼ −5.38 þ 0.45X 0.32 <0.0001 Hanna et al.
H3 55 projects Y ¼ 5.86 þ 0.16X 0.13 0.0076 Karimi et al. (2017) (2005)
Heravi & Eslamdoost (2015) Labor
a
X = independent variable; and Y = dependent variable as defined in Table 3. Productivity Project Cost
Skilled Labor
Availability H1 Performance
Hourly Wage

used in regression analysis. In addition, the Meeting Quality Expect- Hwang et al. (2009)
Fayek et al. (2003) Quality Love & Li (2000)
ation variable in BM&M database also has a similar status as skilled H3 Performance
labor availability variable. All hypotheses are described in detail in
Table 3. Karimi et al. (2017) Schedule Flyvbjerg et al. (2004)

The regression analysis for Hypothesis 1 (H1) shows that there Performance H2

is a significant relationship between increased craft staffing diffi-


culty and increased hourly wages in construction projects. The Fig. 1. Processes of the impact of skilled labor availability on project
p-value of less than 0.0001 resulted in rejection of the null hypoth- cost performance. The studies are those that quantitatively demonstrate
esis and acceptance of the alternative hypothesis. In Hypothesis 2, the significance of the impact. H1–H3 are the hypotheses tested in this
because the type and method of measuring the two variables were study and show the significance of the impact.
the same in both data sets, two databases were combined. The
analysis shows that the impact of time overruns, which can be par-
tially due to a shortage of skilled labor (Karimi et al. 2017), on cost subsequently, this also helps to have comparable regression models
overruns is considerable. The p-values of less than 0.0001 indicates derived from each of these data sets.
the significance of the relationships. The scale in the RT-318 survey has no measure for the condition
The last analysis examines the influence of skilled labor avail- of surplus of craft labor like the CII BM&M scale (þ1 to þ5);
ability on quality performance. The p-value of the model was therefore, the only option was to convert the CII BM&M’s scale
0.0076, which supports a conclusion that there is a significant to the RT-318’s scale. Each number between zero (As Planned)
relationship between these two variables. Table 4 presents the de- to þ5 (Extremely Positive) in the CII BM&M database was con-
tailed results of all hypothesis testing. Fig. 1 illustrates the proc- verted to the No Difficulty level (0) in the RT-318 survey. The CII
esses of the influence of skilled labor shortage on cost performance. BM&M questionnaire defined the zero score as a situation where
It also lists studies that demonstrated the significance of the impact actual skilled labor availability was similar to what was expected
empirically. during project planning (i.e., skilled labor availability did not pos-
The analyses of the preliminary hypotheses testing along with itively or negatively affect project performance when compared
various quantitative studies explained previously explicate the proc- with the project plan) and scores greater than zero as the condition
esses of impact of a skilled labor shortage on projects cost perfor- where the availability of craft workers had a positive impact on
mance. The next analysis examines the significance of the overall project performance. Therefore, it can be reasonably assumed that
influence of a skilled labor shortage on projects cost performance. when a project in this database has a score of equal or greater than
zero, the project experienced no craft shortage whereas projects
with scores between −1 and −5 experienced some level of skilled
Main Hypothesis Testing
labor shortage. There were 17 projects among the total of 68 proj-
The purpose of the main hypothesis testing is to examine the overall ects in this database that had a score greater than zero. The scores
impact of skilled labor shortages on project cost performance. between −5 (Extremely Negative) to −1 in the CII BM&M were
To conduct more reliable hypothesis testing, the authors decided scaled proportionally to the number between 1 (Slight) to 4 (Very
to define a single hypothesis for all projects in both databases. Severe), as defined in the RT-318 survey. This can be done by
Because the two databases used in this study had different scales multiplying any score between −1 and −5 by −4=5. The final
to measure skilled labor availability, it was required to convert one skilled labor availability score for projects in both databases can
database’s scale to that of the other and create a single unified meas- be any number between 0 and 4. Fig. 2 illustrates this scale con-
urement across all projects in the two data sets. As will be explained version process.

© ASCE 04018057-5 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 2018, 144(7): 04018057


CII BM&M Survey Tool
Extremely Extremely
Table 6. Hypothesis testing result of cost overrun comparison between
Negative As Planned projects that experienced a skilled labor shortage and projects that did not
Positive
-5 -4 -3 -2 -1 0 +1 +2 +3 +4 +5
Availability of Skilled Hypothesis analysis Parameter Value
Labor
Projects not impacted by Mean cost overrun −6.7%
(-4/5)
craft shortage (score ¼ 0) N 48
W 0.96a
Projects impacted by Mean cost overrun 6.3%
Craft Staffing
Difficulty
Very Severe (4) Severe (3) Moderate (2) Slight (1) No Difficulty (0) craft shortage (0 < score ≤ 4) N 35
W 0.89b
RT-318 Survey Tool
Levene’s F-value 1.43a
T-value — 3.14
Fig. 2. Process of converting the BM&M scale of availability of craft Degree of freedom — 81
workers to RT-318 survey’s scale. P-value — 0.001
Note: N = Number; and W = Shapiro-Wilk statistics.
Downloaded from ascelibrary.org by La Trobe University on 05/03/18. Copyright ASCE. For personal use only; all rights reserved.

a
Not significant at 0.05 level.
b
Table 5. Summary of main hypothesis development Significant at 0.01 level.

Hypothesis section Description


Projects classification Projects impacted by craft shortage performance. The results justify a deeper exploration of these in-
(0 < score ≤ 4) versus not impacted
fluential relationships in construction projects.
(score ¼ 0)
Database RT-318 survey and CII BM&M
Null hypothesis (Ho ) There is no difference in mean cost overrun Regression Analysis
Alternative hypothesis (Ha ) The mean cost overrun is higher in projects
impacted by a craft shortage Multiple linear regression analysis was performed to further exam-
ine the relationship between a craft labor staffing difficulty and
project cost overruns. Two predictor variables of the analysis were
actual construction cost and craft staffing difficulty scores. In de-
After scale conversion, all projects in both databases were di- veloping a predictive labor demand model for construction proj-
vided into two groups: (1) projects with craft staffing difficulty ects, Wong et al. (2008) found that construction cost is the most
score equal to zero (score ¼ 0), which were classified as projects significant determinant of labor demand. Although the craft staffing
that experienced no shortage of skilled labor; and (2) projects with difficulty variable inherently includes both demand and supply of
a craft staffing difficulty score greater than zero (0 < score ≤ 4), craft labor in a project, it is reasonable to examine its influence on
which were classified as projects that experienced some level of cost overrun with consideration of actual cost of a project. It is ex-
shortage of skilled labor. Table 5 provides details of this hypothesis pected that a labor shortage on a larger project results in a higher
testing. cost overrun because the execution of a project relies on more num-
A t-test was conducted to determine if the difference in average ber of craft workers. The other important and independent predic-
cost overrun between two groups of projects was statistically sig- tors related to the analysis, such as project type, actual project
nificant. The underlying assumption of the test is to have a nor- schedule, project complexity, and total site work hours, were also
mally distributed population. This assumption was assessed using examined and found to have no statistically significant impact on
Shapiro-Wilk test. The test returned a p-value greater than 0.05 project cost overrun when considering the impact of craft staffing
for the first group (score ¼ 0), suggesting that the assumption of difficulties.
normality is justifiable for this group. The test in second group
(0 < score ≤ 4) returned a p-value less than 0.05, indicating the Analysis of CII BM&M Database
deviation from normality in this data set.
Agresti and Finlay (2009) stated that the t-test is robust to the A total of 64 data points were available for this analysis. The analy-
sis returned the regression model containing both aforementioned
violation of the normal population assumption, particularly when
variables. The p-value of the model was less than 0.0001, which
the data points exceed 30 according to Central Limit Theorem.
indicates the adequacy of the model. The R2 value of the model is
They, however, stated that caution needs to be exercised if there
0.59 with an adjusted R2 of 0.58. Table 7 presents the details of the
is an extreme outlier or extreme skew in the data points. Because
statistical analysis of the model.
there are more than 30 data points in the second group (n ¼ 35) and
they do not contain any extreme outliers and have no extreme
deviation from normality, the t-test can be adopted to test the differ- Analysis of RT-318 Survey Database
ence in average cost overrun between the two groups. Levene’s test The total available data points for this analysis were 17. The analy-
was performed to examine the assumption of equality of variances. sis again returned the regression model containing both variables.
The test returned a p-value greater than 0.05, suggesting that the The p-value of the model was 0.0019, which indicates the signifi-
assumption of equality of variances is justifiable. As indicated in cance of the model. The R2 value of the model is 0.59 with an ad-
Table 6, the average cost overrun in projects affected by a skilled justed R2 of 0.53. The details of the statistical analysis of model are
labor shortage was 6.3% compared with −6.7% for projects not given in Table 7.
affected by a skilled labor shortage. This difference is significant
at the 0.001 level, which allows the null hypothesis (Ho ) to be re-
Analysis of the Combined Data Set
jected and supports a conclusion that cost performance in projects
is substantially affected by shortages of skilled labor. Because the models derived from two available databases with
The analyses of main hypothesis testing demonstrate the sub- different temporal contexts [BM&M projects (2001–2013) and
stantial influence of a skilled labor staffing difficulty on project cost RT-318 survey (2011–2014)] showed a similar pattern of the

© ASCE 04018057-6 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 2018, 144(7): 04018057


Table 7. Regression model of the impact of craft staffing difficulty on construction cost overrun
Number projects Actual Craft staffing Adjusted
(database) Dependent variable Constant construction cost difficulty F-value P-value R2 R2
64 (BM&M) Construction cost overrun −15.84a (−5.79) 0.077a (6.54) 10.699b (3.80) 43.91 <0.0001 0.59 0.58
17 (RT-318) Construction cost overrun −9.167c (−1.63) 0.0058d (3.25) 11.132e (2.61) 10.08 0.0019 0.59 0.53
81 (combined) Construction cost overrun −10.74b (−3.76) 0.008d (3.06) 15.04b (5.56) 23.89 <0.0001 0.38 0.36
Note: t-values shown in parentheses.
a
t-statistics significant at 0.0001 level.
b
t-statistics significant at 0.001 level.
c
t-statistics significant at 0.15 level.
d
t-statistics significant at 0.01 level.
e
t-statistics significant at 0.05 level.
Downloaded from ascelibrary.org by La Trobe University on 05/03/18. Copyright ASCE. For personal use only; all rights reserved.

impact of skilled labor availability on cost performance, it was de- transfer estimator (CTE). Introduced by Atherton and Ben-Akiva
cided to examine this impact across all available data. The most (1976), the Bayesian updating method is based on classical
common method of data combining used in past literature is the Bayesian analysis and estimates updated parameters of model with
joint context estimation. This method combines two databases and combining the parameters of models derived from two data sources.
uses them simultaneously in determining the parameters of a new Based on a normality assumption, the method is expressed math-
model. The basic theory of the method was discussed by Bradley ematically as follows (Karasmaa 2007):
and Daly (1991) and Ben-Akiva and Morikawa (1990). The under- !−1 !
X−1 X−1 X−1 −1
X
lying idea of this method is to adjust the random variation in the
βd
BU ¼ þ βbi þ βbj
utility function of the different data sets to be equal (Karasmaa
i j i j
2007). Under the assumption of equality of parameter vectors of
models from two databases, the least-square estimator of combined in which βBU = updated vector of parameters of the final model;
model is calculated as follows: βi and βj = estimated
P P vectors of parameters of the first and second
β ¼ ð½XT ½XÞ½XT ½Y models; and i and j = covariance matrixes of the first and sec-
  ond
P models.
P−1 The covariance of final model can be calculated as
Y1 ð −1i þ
−1
j Þ .
in which ½Y ¼ = vector of response variable form two
Y2 The combined transfer estimator method is a generalization
 
X1 of the Bayesian updating method because it explicitly takes into con-
databases; and ½X ¼ = explanatory variables from two
X2 sideration of the bias transfer (Shyr 1993). This procedure calculates
databases. In order to make the variance of error in two models the weighted average of models’ parameters and assigns the weight
equal, the second model needs to be multiplied by correction factor to each parameter in such a way that the mean square error (MSE) of
(μ), which is defined as μ2 ¼ Varðε1 Þ=Varðε2 Þ (Karasmaa 2007), the updated parameters is minimized (Ben-Akiva and Bolduc 1987).
in which ε1 and ε2 are the errors of Models 1 and 2, respectively. In The model can be expressed as follows (Karasmaa 2007):
this analysis, the correction factor (μ) can be reasonably assumed to !−1 !−1
X−1 X−1
equal to 1 because the test shows no significant difference between βd
CTE ¼ þΔΔ T
þ
Var (ε1 ) and Var (ε2 ) (F ¼ 1.53 < Fα¼0.05 ¼ 2.22). The null hy- i j
pothesis in the test is Ho ∶Varðε1 Þ ¼ Varðε2 Þ, and the alternative −1
!−1
−1
!
hypothesis is Ha ∶Varðε1 Þ ≠ Varðε2 Þ. The details of test are pro- X X
þ þΔΔ T
βbi þ βbj
vided in Table 8. i j
The regression analysis on total available data points (81 proj-
ects) returned the model containing both variables. The p-value of in which βCTE = updated vector parameter of the final model;Pβi and
the model was less than 0.0001, which indicates the significance β
P j = estimated parameters of the first and second models; i and
of the model. The R2 value of the model is 0.38 with an adjusted j = covariance matrixes of the first and second models; Δ ¼ ðβi−
R2 of 0.36. The details of the statistical analysis of the model are βj Þ is the transfer bias; and ΔT = transpose of the matrix Δ. The
given in Table 7. covariance matrix of final model can be calculated as
P2
P 0 −1
i P
CTE ¼ 2 . Table 9 shows the final models derived
Other Methods of Data Combining 0 j

The two other common data-combining procedures used in pre- from all of the data (both databases) with three different common
vious literature are the Bayesian updating method and combined methods of data combining. All three models demonstrate similar
patterns of the impact of skilled labor availability, which enhance
the reliability of the result.
Table 8. Comparison of variance of error in two models
Database Parameter Value
Discussion
CII BM&M MSE 330.26
Degree of freedom 61 Cost performance of a construction project is a complex function of
RT-318 MSE 216.26 many factors. The models presented in Table 9 should be regarded
Degree of freedom 14 as informative models that illustrate the pattern of the risk that a
— F-value 1.53 skilled labor shortage poses to cost performance. The primary ben-
— F-value (α ¼ 0.05) 2.22
efit of this risk estimation is to enable project management teams to

© ASCE 04018057-7 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 2018, 144(7): 04018057


Table 9. Regression model of the impact of craft staffing difficulty on construction cost overruns using common data-combining methods (CII BM&M and
RT-318 survey)
Data-combining method Final model
Joint context estimation Construction cost overrun ¼ −10.74 þ 0.008 × actual construction cost þ 15.04 × craft staffing difficulty
Bayesian updating method Construction cost overrun ¼ −10.64 þ 0.007 × actual construction cost þ 14.62 × craft staffing difficulty
Combined transfer estimator Construction cost overrun ¼ −10.63 þ 0.006 × actual construction cost þ 11.06 × craft staffing difficulty

determine whether mitigation strategies are warranted to prevent two databases that demonstrated similar patterns of the significant
potential shortfalls in project cost performance. impact of skilled labor staffing difficulties on project cost perfor-
The strength of these informative risk models lies in the fact that mance. Finally, by using the three main valid methods of data com-
two primary models derived from two databases with two different bining, the two data sets were combined to obtain more reliable
temporal contexts show similar patterns within the two robust re- models. The final models are presented as risk informative models
Downloaded from ascelibrary.org by La Trobe University on 05/03/18. Copyright ASCE. For personal use only; all rights reserved.

gression models. This affirms the reliability and consistency of the that illustrate the pattern of skilled labor shortage risk on project
results because they externally validate each other. To take the most cost overruns with regard to the size of a project.
of these two available data sets and enhance the model reliability, The main contribution of this work to the body of knowledge is
the two models were combined using three major data-combining to fill the gap in the existing literature by quantitatively modeling
methods. The first model was obtained by performing a regression and elucidating the influence of craft labor availability on construc-
analysis on the combined data set. The other two models were cal- tion project cost performance. This study supports and validates
culated by two statistical methods of combining the models derived previous qualitative studies that used opinion-based data to anec-
from two data sets. dotally link a craft labor shortage to a project’s cost growth.
Because the final model is intended to be used as an informative The theoretical implications of this study will be on construction
model not predictive one and all three final models show similar industry workforce development system as one of the major US
patterns, the available tests used for assessing the performance industry sectors. Considering the results of this study, which shows
of models (predictability) were not conducted. All models provide the adverse impact of a skilled labor shortage on project perfor-
a proper risk perception of a shortage of skilled labor with regard to mance, and on the other hand, studies that evidenced the recent
the size of the project. structural change in the US construction industry workforce, makes
the risk of a skilled labor shortage alarming. Taylor et al. (2016)
showed that the US construction workforce is aging faster than that
Limitations of the Study of all other private industries. They also revealed that there is a sig-
nificant shift in craft workers’ preferences from work satisfaction to
Although the presented models provide beneficial and statistically
higher income and job security while there are shrinking real wage
valid results, it is recognized that they are subject to the following
gaps between construction craft labor and all other private indus-
limitations:
tries. CII (2015) cautioned that there are national shortages in key
• The analysis was based heavily on industrial projects (90% of
industrial trades (e.g., welders, pipefitters, and electricians). These
projects in RT-318 survey and 56% in CII BM&M database
challenges represent substantial changes in the construction industry
were industrial projects).
workforce, which makes the problem of skilled labor availability
• Although regression models are statistically significance with
critical. This fundamental problem cannot be expected to be amelio-
adequate R2 value for prediction purpose, because they contain
rated unless these challenges are addressed not only within the con-
only two influential variables of cost performance, they can only
struction industry but also in K–12 education and societal
be used as an informative risk model instead of predictive tool.
perceptions toward construction. However, understanding the level
of impact that craft shortages have on project performance through
Conclusions and Recommendations robust statistical analyses can serve as a primary step in developing
motivation for industry leaders, communities, and construction
The main purpose of this research was to quantitatively model stakeholders to address this challenge.
the empirical influence of skilled labor availability on construction The practical implications of this study lie in identifying,
project cost performance. Data from 97 construction projects com- through a quantitative approach, the shortage of skilled labor as
pleted in the United States and Canada between 2001 and 2014 one of the main root causes of cost overruns in construction proj-
were collected from two data sources. Preliminary hypothesis test- ects. The study provides a new realization for practitioners that
ing evidenced the processes of the impact of craft shortage on cost the impact of craft shortages on cost performance is significant
performance that have not yet been examined quantitatively. These and can arise through various indirect influential processes. These
processes include the effects of skilled labor shortage on increasing processes include impacts through loss of productivity, higher
craft hourly wages and decreasing the quality performance. In ad- safety incidents, lower quality performance, higher schedule over-
dition, the impact of time overruns on cost overruns was examined runs, and increases in hourly wage and overtime usage. Therefore,
and shown to be significant as a part of influence of skilled labor addressing the availability of skilled labor in a project can be re-
shortages on cost performance through schedule performance. The garded as a multipurpose mitigation strategy with substantial ben-
impact of skilled labor shortages on time overruns has been evi- efits and gains for a project. In addition to controlling the overall
denced in the recent quantitative study. The main hypothesis testing cost of a project, project managers can improve productivity, safety,
examined the overall impact of a skilled labor shortage on cost per- quality, and schedule performance by investing in hiring, training,
formance and demonstrated that projects experiencing a labor and retaining of skilled labors.
shortage experienced a higher cost overrun compared with projects The presented risk models can be used by project management
that experienced no shortages. Further analysis by means of multi- teams at the planning stage of projects to estimate the risk of ex-
ple regression analysis resulted in two robust models derived from pected level of skilled labor availability to the cost of a project with

© ASCE 04018057-8 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 2018, 144(7): 04018057


regard to its size. This risk estimation will enable them to determine Dai, J., P. M. Goodrum, and W. F. Maloney. 2009. “Construction craft
the best possible mitigation strategies to address a skilled labor workers’ perceptions of the factors affecting their productivity.” J.
shortage in a project. Constr. Eng. Manage. 135 (3): 217–226. https://doi.org/10.1061
/(ASCE)0733-9364(2009)135:3(217).
Doloi, H. 2013. “Cost overruns and failure in project management:
Understanding the roles of key stakeholders in construction projects.”
Data Availability Statement J. Constr. Eng. Manage. 139 (3): 267–279. https://doi.org/10.1061
/(ASCE)CO.1943-7862.0000621.
Data generated or analyzed during the study (RT-318 Survey) are Ernzen, J., and C. Schexnayder. 2000. “One company’s experience with
available at http://uknowledge.uky.edu/cgi/viewcontent.cgi?article= design/build: Labor cost risk and profit potential.” J. Constr. Eng.
1059&context=ce_etds. Other data analyzed during the study were Manage. 126 (1): 10–14. https://doi.org/10.1061/(ASCE)0733-9364
provided by a third party. Requests for data should be directed (2000)126:1(10).
to the provider indicated in the Acknowledgements (CII BM&M). Everett, J. G., and P. B. Frank, Jr. 1996. “Costs of accidents and injuries to
Information about the Journal’s data sharing policy can be found the construction industry.” J. Constr. Eng. Manage. 122 (2): 158–164.
here: http://ascelibrary.org/doi/10.1061/%28ASCE%29CO.1943 https://doi.org/10.1061/(ASCE)0733-9364(1996)122:2(158).
Downloaded from ascelibrary.org by La Trobe University on 05/03/18. Copyright ASCE. For personal use only; all rights reserved.

-7862.0001263. Fayek, A. R., M. Dissanayake, and O. Campero. 2003. Measuring and clas-
sifying construction field rework: A pilot study. Edmonton, AB, Canada:
Dept. of Civil and Environmental Engineering, Univ. of Alberta.
Flyvbjerg, B., M. K. Skamris Holm, and S. L. Buhl. 2004. “What causes
Acknowledgments cost overrun in transport infrastructure projects?” Transp. Rev. 24 (1):
3–18. https://doi.org/10.1080/0144164032000080494a.
The authors would like to thank the Construction Industry Institute Gharaibeh, H. M. 2014. “Cost control in mega projects using the Delphi
for its support of this research through Research Team (RT) 318. method.” J. Constr. Eng. Manage. 30 (5): 04014024. https://doi.org/10
In addition, the authors thank the members of CII RT 318 and 335 .1061/(ASCE)ME.1943-5479.0000218.
for their substantial contributions to this research. The views and Goodrum, P. M. 2004. “Hispanic and non-Hispanic wage differentials:
opinions expressed herein are of the authors and do not necessarily Implications for United States construction industry.” J. Constr.
represent the views and opinions of the Construction Industry Eng. Manage. 130 (4): 552–559. https://doi.org/10.1061/(ASCE)0733
Institute or the industry team members of RT-318 and RT-335. -9364(2004)130:4(552).
Hanna, A. S. 2001. Quantifying the impact of change orders on electrical
and mechanical labor productivity. Research Rep. No. 158-11. Austin,
TX: Construction Industry Institute.
References Hanna, A. S., C. S. Taylor, and K. T. Sullivan. 2005. “Impact of extended
Abdol, R. C., H. B. Brisbane, and G. D. Eric. 1999. “Causes of the overtime on construction labor productivity.” J. Constr. Eng. Manage.
construction skilled labor shortage and proposed solutions.” In Proc., 131 (6): 734–739. https://doi.org/10.1061/(ASCE)0733-9364(2005)
ASC 35th Annual Conf., 187–196. San Luis Obispo, CA: California 131:6(734).
Polytechnic State Univ. Heravi, G., and E. Eslamdoost. 2015. “Applying artificial neural networks
Agresti, A. 2015. Foundations of linear and generalized linear models. for measuring and predicting construction-labor productivity.” J.
East Orange, NJ: Wiley. Constr. Eng. Manage. 141 (10): 04015032. https://doi.org/10.1061
Agresti, A., and B. Finlay. 2009. Statistical methods for the social sciences. /(ASCE)CO.1943-7862.0001006.
4th ed. Upper Saddle River, NJ: Pearson Prentice Hall. Hinze, J., and L. L. Appelgate. 1991. “Costs of construction injuries.”
Akintoye, A. 2000. “Analysis of factors influencing project cost estimating J. Constr. Eng. Manage. 117 (3): 537–550. https://doi.org/10.1061
practice.” Constr. Manage. Econ. 18 (1): 77–89. https://doi.org/10.1080 /(ASCE)0733-9364(1991)117:3(537).
/014461900370979. Hwang, B. G., S. R. Thomas, C. T. Haas, and C. H. Caldas. 2009. “Meas-
Atherton, T., and M. E. Ben-Akiva. 1976. “Transferability and updating of uring the impact of rework on construction cost performance.” J.
disaggregate travel demand models.” Transp. Res. Rec. 610: 12–18. Constr. Eng. Manage. 135 (3): 187–198. https://doi.org/10.1061
Ben-Akiva, M., and D. Bolduc. 1987. “Approaches to model transferability /(ASCE)0733-9364(2009)135:3(187).
and updating: The combined transfer estimator.” Transp. Res. Rec. Improving Construction Safety Performance. 1982. Construction industry
1139: 1–7. cost effectiveness (CICE) project. Rep. A-3. New York: Business
Ben-Akiva, M. E., and T. Morikawa 1990. “Estimation of travel demand Roundtable.
models from multiple data sources.” In Proc., 11th Int. Symp. on Trans- Karasmaa, N. 2007. “Evaluation of transfer methods for spatial travel de-
portation and Traffic Theory, Yokohama, Japan. mand models.” J. Transp. Res. Part A 41 (5): 411–427. https://doi.org
Bradley, M., and A. Daly. 1991. “Estimation of logit choice models using /10.1016/j.tra.2006.09.009.
mixed stated preference and revealed preference information.” In Proc., Karimi, H. 2017. “Quantitative analysis of the impact of craft labor avail-
6th Int. Conf. on Travel Behaviour, edited by P. Stopher and M. Lee- ability on construction project performance.” Theses and Dissertations–
Gosselin, 209–232. New York: Elsevier. Civil Engineering, University of Kentucky. https://uknowledge.uky.edu
Business Roundtable. 1983. More construction for the money, construction /ce_etds/56.
industry cost effectiveness project. Summary Rep. Washington, DC: Karimi, H., T. R. Taylor, and P. M. Goodrum. 2017. “Analysis of the impact
Business Roundtable. of craft labour availability on North American construction project pro-
Business Roundtable. 1997. Confronting the skilled construction workforce ductivity and schedule performance.” Constr. Manage. Econ. 35 (6):
shortage. Washington, DC: Business Roundtable. 368–380. https://doi.org/10.1080/01446193.2017.1294257.
Chester, M., and C. Hendrickson. 2005. “Cost impacts, scheduling impacts, Karimi, H., T. R. Taylor, P. M. Goodrum, and C. Srinivasan. 2016. “Quan-
and the claims process during construction.” J. Constr. Eng. Manage. titative analysis of the impact of craft worker availability on construc-
131 (1): 102–107. https://doi.org/10.1061/(ASCE)0733-9364(2005) tion project safety performance.” J. Constr. Innovation 16 (3): 307–322.
131:1(102). https://doi.org/10.1108/CI-10-2015-0050.
Construction Industry Institute. 1990. An assessment of education and train- Li, Y., L. Jiang, T. R. B. Taylor, and D. N. Ford. 2017. “Impact of labor
ing needs among construction personnel. Research Rep. 158-11. Austin, controls on tipping point dynamics in large complex projects.” Syst.
TX: Univ. of Texas at Austin. Res. Behav. Sci. in press.
Construction Industry Institute. 2015. Is there a demographic craft labor Love, P. E., and H. Li. 2000. “Quantifying the causes and costs of rework in
cliff that will affect project performance? Research Summary 318-1. construction.” Constr. Manage. Econ. 18 (4): 479–490. https://doi.org
Austin, TX: Univ. of Texas at Austin. /10.1080/01446190050024897.

© ASCE 04018057-9 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 2018, 144(7): 04018057


Lyneis, J. M., and D. N. Ford. 2007. “System dynamics applied to project Taylor, T. R. B., H. Karimi, P. M. Goodrum, and M. Albattah. 2016. Is there
management: A survey, assessment, and directions for future research.” a demographic craft labor cliff that will affect project performance?
Syst. Dyn. Rev. 23 (2/3): 157–189. https://doi.org/10.1002/sdr.377. Construction Industry Institute Research Rep. 318-2. Austin, TX: Univ.
McTague, B., and G. Jergeas. 2002. Productivity improvement on Alberta of Texas-Austin.
major construction projects. Construction Productivity Improvement Trost, S. M., and G. D. Oberlender. 2003. “Predicting accuracy of early cost
Rep. Edmonton, AB, Canada: Alberta Economic Development. estimates using factor analysis and multivariate regression.” J. Constr.
Rosenbaum, D. 2001. “Craft labor shortage provokes more studies of pay Eng. Manage. 129 (2): 198–204. https://doi.org/10.1061/(ASCE)0733
and safety.” Engineering news record, 11. New York: McGraw-Hill. -9364(2003)129:2(198).
RSMeans. 2016. Building construction cost data. Norwell, MA: Construc- Wang, Y., P. M. Goodrum, C. T. Haas, and R. W. Glover. 2008. “Craft
training issues in American industrial and commercial construction.”
tion Publishers & Consultants.
J. Constr. Eng. Manage. 134 (10): 795–803. https://doi.org/10.1061
Sawyer, T., and D. Rubin. 2007. “Leaders probe new solutions for indus-
/(ASCE)0733-9364(2008)134:10(795).
try’s labor shortfall.” Engineering News Record, 15. New York:
Wong, J. M. W., A. P. C. Chan, and Y. H. Chiang. 2008. “Modeling
McGraw-Hill. and forecasting construction labor demand: Multivariate analysis.”
Shyr, F.-Y. 1993. “Combining laboratory and field data in rain fatigue J. Constr. Eng. Manage. 134 (9): 664–672. https://doi.org/10.1061
analysis.” Ph.D. dissertation, Massachusetts Institute of Technology.
Downloaded from ascelibrary.org by La Trobe University on 05/03/18. Copyright ASCE. For personal use only; all rights reserved.

/(ASCE)0733-9364(2008)134:9(664).

© ASCE 04018057-10 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 2018, 144(7): 04018057

You might also like