Back To Back Promising - Fusion Gop Supply Planning PDF
Back To Back Promising - Fusion Gop Supply Planning PDF
Table of Contents
This whitepaper covers the functional flow, setup and change management scenarios for the Back
to Back promising and planning in Fusion Supply Chain Planning modules GOP and Planning
Central.
Back to Back promising is a supply to order scenario where fulfillment lines are promised by
purchasing from suppliers - the supplier ships to the ship from warehouse rather than shipping to
the customer directly.
• A purchase order equivalent to the fulfillment line is created against the supplier and
supply is reserved against the fulfillment line
• Another variant of Back to Back called Internal Material Transfer Back to Back (IMT Back
to Back) involves transferring supply from an internal org to the ship from warehouse; in
this case a transfer order is created and is reserved against the fulfillment line.
• A fulfillment line is sent for promising from Distributed Order Orchestration (DOO)
• GOP recognizes the item as back to back based on the PIM attribute ‘BacktoBack’
• GOP identifies the eligible ship from warehouses and the upstream sources based on the
sourcing rules. GOP performs availability calculations and provides response.
Note: The sourcing rule definitions override the item attribute. For example, for an item that is
indicated as back-to-back, if a “Make At” sourcing rule is defined as rank1 source, GOP will
promise using Make CTP if required and provide the relevant supply recommendation.
• Upon scheduling, GOP will provide supply recommendations. SCO then orchestrates the
creation of supplies. SCO also maintains association of supplies with demands and the
association information can be communicated to GOP in real-time using the net change
capabilities.
• GOP honors the associated supply that is reserved, during rescheduling.
GOP provides the suggested supply to SCO, which creates the inventory reservation if the source is
ship from X or SCO creates the purchase order or transfer order with the reservations if X does not
have on hand supply.
Note: Use Document Reference DropshipAndBackToBackProcessManual when creating
SalesOrder in DOO.
• GOP will return the same scheduled date back to DOO. GOP will export the supply pegging
which will be identical to the original pegging that was associated with this demand. SCO
compares the Requested Quantity on the fulfillment line and the pegged PO quantity and
determine whether the PO quantity must be reduced.
• GOP will look for additional supply from suppliers that deliver to this ship-from warehouse
since the Ship-From warehouse is already present on the line.
• GOP can determine a date from the supplier currently on the PO, or choose a new supplier, or
even split the fulfillment for the incremental quantity across suppliers. This will depend on
supplier capacity, lead times and transportation lead times. GOP could split the fulfillment line
due to the shipment dates from the Ship-From warehouse being different.
• GOP will send the existing scheduled date back since the PO date is still the same – thus, this
could result in a delay, since the Requested Date has moved in, but the Scheduled Date is the
same as earlier.
Note: If the PO date has been pulled in and is already reflected within GOP before the
scheduling call with the earlier requested date, GOP will schedule the pulled-in requested date
on time.
• GOP will schedule the line on the same date as the requested date, or schedule the line earlier
depending on the Earliest Acceptable date on the line.
Demand Cancelled
• SCO will cancel this supply out which can be received by collections and GOP in real-time
based on the net change rules.
• When DOO calls GOP to reschedule the line, GOP will first schedule a part of the line by using
the pegged PO supply. For the remainder, GOP will look for sources of supply.
• Results will be restricted to the Ship-From warehouse on the line. Using sourcing rules, GOP
will look at suppliers for the remaining demand, and choose the best supplier source. GOP
updates DOO with the new Scheduled dates, and publishes updated supply recommendations.
These recommendations will consist of the existing PO, and the new purchase
recommendation created by GOP.
• DOO will initiate a reschedule call to GOP of the fulfillment line to update the scheduled dates
on the fulfillment line.
• When GOP is called for rescheduling the line, GOP will recognize the updated PO dates, and
change the scheduled dates on the fulfillment line.
• DOO will call GOP to reschedule the line – GOP will determine the updated scheduled dates
after looking at the updated PO date, and update DOO.
PO gets Cancelled
Vision Corporation needs to promise a back to back fulfillment line for 1000 units of AS66315
from Hilman associates. Vision Corporation sources this item from Allied Manufacturing and does
not hold inventory at any of the internal locations.
Supplier
(Allied Manufacturing)
Receive Shipment
Customer
from Supplier (Hilman Associates)
Transit Lead
Time 4 days
1. When the fulfillment line is sent for availability, GOP looks at the sourcing rules to determine
the eligible ship-from warehouses to ship to the customer/region based on sourcing rules.
GOP looks at inventory at these locations and performs availability check at upstream sources
as indicated by sourcing rules (if required).
2. In this case, GOP sees that sufficient capacity exists at the upstream supplier location. The
fulfillment line is promised on day 7 by considering supplier to OEM transit lead time of 4 days
and OEM to customer transit lead time of 3 days
3. GOP pegging details indicate that the PO from the supplier is shipped to the internal
warehouse and is shipped from the internal shipping warehouse to the customer location
4. Upon scheduling, the “Ship-from Warehouse” field of the fulfillment line is populated internal
shipping warehouse OEM (Vision). The scheduled ship date is set as day 4 and scheduled
arrive date is set on day 7.
5. Since supplier capacity is based on dock date, the supplier capacity on day 4 is consumed.
6. Since the PIM attribute indicates that the line is back to back, GOP provides supply
recommendations for the purchase order to be created to SCO.
7. A purchase order is created by SCO in the source systems. A purchase order is created against
Allied Manufacturing with ship to location as the internal shipping warehouse for 1000 units
with the due date as day 4.
10. Once the purchase order is received, it is converted in on-hand inventory, a reservation needs
to be explicitly created to reserve on-hand inventory against this fulfillment line
Back-to-back ordering matches each supply order with each sales order on a one-for-one basis.
The organization using “Back-to-Back order” or “Supply to Order” flow whereby that organization
purchases the product from a supplier, have the supplier ship it to the organization and then
combine that product with other goods that organization may have purchased or stocked to create
one shipment to the customer. This is a common scenario especially for the wholesale distributors
who typically use this business flow.
This process enables companies to optimize order fulfillment to customers, reduce overall
fulfillment cost, and maintain a competitive advantage with greater reliance on contract
manufacturers and suppliers to supply some or all of their products to their customers.
Planning Central collections process collects back-to-back sales orders, supplies and
reservations as created in above cycle.
Supply Planning respects reservation between sales orders and supplies as created above and
pegs these reserved supplies to sales orders for back-to-back items.
Planners analyze supply shortages and capacity overloads using any of the standard planning
tools.
Planning Central creates back-to-back supplies using associated sourcing rules when a back-
to-back sales order does not have a reserved supply and the item is marked as “Back-to-back
Enabled”.
The planned orders for back-to-back enabled items cannot be released from Planning Central.
SCO cannot accept releases from planning for back-to-back items. Planners can notify order
management to check the order line, use GOP to promise the line, and send the supply
recommendation to Supply Chain Orchestration.
By definition, the planned order quantity equals the demand quantity. Order modifiers can be
violated. Planned order quantities can be less than the demand quantity when existing
supplies are suggested for the sales order.
If the back to back supply is late for the sales order, then a late replenishment exception
message is generated. A back to back supply can be late because it is firm. Planning Central
does not cancel reserved back-to-back supplies.
When an item is marked as “Back-to-back Enabled” for the item-organization, then planning
central does not calculate or consider safety stock levels.