Professional Documents
Culture Documents
On
ARTIFICIAL INTELLIGENCE
IN
POWER STATION
Submitted by
CONTENTS
1. INTRODUCTION………………………………………………
…………………… 6
2. SUBSTATION…………………………………………………
………………………. 7
2.1. TRANSMISSION
SUBSTATION…………………………………………… 8
2.2. DISTRIBUTION
SUBSTATION……………………………………………. 8
3. INTELLIGENT
SUBSTATION……………………………………………….
10
TO AN INTELLIGENT
SUBSTATION………………………….… 14
SYSTEM……………..… 16
……………………. 31
8. REFERENCE……………………………………………………
……………………. 32
1. INTRODUCTION
The upgradation of our 500-kV trunk transmission system has almost been
completed, and the electricity system has been considerably improved. Yet, cost
reductions are required to cope with the entry of IPP (Independent Power
Producer) and the introduction of power source distributors caused by the
deregulation of electric utilities. To achieve this, each electricity supply company
is decreasing expenditure by efficiently using equipment, improving operations,
and effectively controlling plant-and-equipment investment. In addition, power
systems will become more complex, requiring operation in an uncertain and less
structured environment. Consequently, secure and economic operation of power
systems requires improved and innovative methods of control. The power
distribution system also requires reductions in initial investments, such as the unit
price of apparatus and miniaturization, and reduced costs for the whole life cycle,
including the operation/maintenance costs of the substation system. The
construction of a new power distribution system has been considered to meet
these requirements. It will adopt “digital technology” and “IT-related
technology,” which has made rapid advances in recent years.
This system aims at minimizing the total cost, not only reducing of the
unit price but also the cost of installation, construction, operation, and
maintenance. This article discusses the construction of intelligent substations in
the power distribution system, as well as protection/control-unified equipment as
examples of the new technology.
2. SUBSTATION
in the network. Earth faults at a substation can cause a ground potential rise.
Currents flowing in the Earth's surface during a fault can cause metal objects to
have a significantly different voltage than the ground under a person's feet; this
touch potential presents a hazard of electrocution.
3. INTELLIGENT SUBSTATION
For convenience, power system higher level controls are classified here as:
The functions of the operation unit, which is the central component of the
equipment, can be improved and shared, reducing the number of sections. As the
dimensions of the whole unit are reduced by 50%, both the protection and control
units can be configured into a single unit. The characteristics of this single unit
are discussed below:
(1) Operation unit
The protection and control units need to be separated in the operation unit,
which is equivalent to the center of the unit.
Therefore, the CPU (central processing unit) was separate and the use of a
high-performance 32-bit RISC (reduced instruction set computer) processor
enabled us to reduce the total number of boards to 70%.
(4) Interface
By mounting the Ethernet* LAN port in the operation unit, it can now
respond to a flexible network configuration. Ethernet LAN is based on the TCP
(transmission control protocol)/IP (Internet protocol), which is a general-purpose
standard network interface. This is a high performance all-in-one operation unit.
We slimmed down the system by mounting the protection and control equipment,
which until now had been independent, into a single 350-mm width panel (see
Fig. 4). The advantages of this equipment are as follows:
(a) Perfect isolation between protection and control unit from input to
output
(b) Large reduction in installation space (Half the conventional space)
(c) Direct coupling between protection and control unit by an isolated
interface
Fig. 4: Compact Type Operation Unit and Single Protection/ Control Equipment.
In order to narrow the broad range of topics that may be included under
the topics in the TF scope, some general guidelines were established with the
intention of helping the TF members on focusing their work on aspects of the
problem considered more relevant. These guidelines are:
BACKGROUND
Scope of applications :
Limiting to power system operations
Power system planning outside scope
Scope considered for intelligent system methods :
Rule-based methods/Logic programming
Model-based reasoning
Artificial neural nets
Evolutionary programming
Approximate reasoning (fuzzy sets, certainty factors, etc.)
Sumary of report conclusions
POWER SYSTEM OPERATION
Control functions and time frames :
Open and closed loop
Time frames of interest
Decision requirements in operations :
Operator responsibilities
Centralized vs. decentralized
Limitations of existing tools :
Response to changing and unforeseen conditions
Usefulness of infrequently used applications
Complexity of system prevents possibility of all situations being fully
analyzed
Inability to improve with experience or easily incorporate experience
Trends in operations :
State of the art
Recent computational advancements
Developments in static and dynamic security methodologies
Survey (or discussion) of operator needs
Movement towards real-time controls
Challenges arising from the new utility environment :
New operator responsibilities
Increasingly stressed systems
Possibility of broader fluctuations in system operating conditions arising
from power sales and contracts
Data limitations; concerns of proprietary data
Regulatory requirements/restrictions on centralized decisions
Variations in regulations from region to region
APPLICATION OF INTELLIGENT CONTROL METHODS FOR
OPERATIONS
IMPLEMENTATION
Guidelines/requirements :
Hardware
Software
Control center integration
Operator training/user interface
Evaluation/testing methodologies :
Logical verification methods
Simulation approaches
Software maintenance and updates :
Regular improvements in knowledge base