Professional Documents
Culture Documents
Date: 19th February 2012
Report Ref: R439/01 Rev. C
Asia
GCG (Asia) Ltd Sha Lo Tung Development
Drainage Assessment and Mitigation Measures
TABLE OF CONTENTS
1. INTRODUCTION.................................................................................................... 1
2. PROPOSED DEVELOPMENT............................................................................... 1
2.1 Design Concepts for Land Use in the Development Site ................................. 1
2.2 Components of Development Site................................................................... 3
6. CONCLUDING REMARKS.................................................................................. 13
FIGURES
APPENDICES
GCG (Asia) Ltd Sha Lo Tung Development
Drainage Assessment and Mitigation Measures
1. INTRODUCTION
This report presents the results of the assessment of the changes the proposed
development will have on the existing drainage features and summarizes the
mitigation measures that will accommodate the various requirements from
Government departments such as DSD and WSD in order to demonstrate that the
proposed development is acceptable in terms of drainage characteristics. This report
will contain the following elements:
2. PROPOSED DEVELOPMENT
The Development Site comprises a total area of approximately 4.1ha and the location
is illustrated in Figure 2.1. It is located in the present “Greenbelt” zone just south of
the Ecological Reserve. In all previous ecological studies undertaken by the SLTDC,
this area was recorded as being of low ecological value, although its northern
boundary edge is contiguous with the Conservation Area. The Development Site is
also located outside of the Country Park and Conservation Area.
The Landscape Master Plan for the development is shown in Figure 2.2. Due to the
sensitivity of the Sha Lo Tung Valley and the need to minimize potential construction
impact on the stream and existing trees, the master plan for the Development Site
has adopted the following design considerations which have been taken into account
when carrying out the drainage impact assessment.
GCG (Asia) Ltd Sha Lo Tung Development
Drainage Assessment and Mitigation Measures
GCG (Asia) Ltd Sha Lo Tung Development
Drainage Assessment and Mitigation Measures
helps maintain existing natural flow paths in the hinterland around the
development, thus minimising the overall drainage impact caused by the
specific changes due to the development.
The main buildings in the Development Site are shown in Figure 2.2. These are the
Nature Interpretation Centre, the Multi-Cultural Education Retreat (MCER) and the
Columbarium structures which together occupy approximately 1.27 ha. This area
includes the car park and major paths connecting all buildings, but does not include
the landscaped areas (ie pavilion and gathering area which may comprise up to
approximately 0.36 ha)
The Site comprises two groups of uses, namely the Nature Interpretation Centre and
public parking areas which are integral parts of the Conservation Area and the Multi-
Cultural Educational Retreat cum Columbarium which comprise the development
concession that generate the funds for the Conservation Area.
• Public parking and private parking area at the end of Sha Lo Tung Road;
Figure 3.1 presents the location of the Sha Lo Tung development site within the
context of the water gathering grounds that form the drainage environment for the
entire area that’s services the Hok Tau Irrigation Reservoir. This includes the Sha Lo
Tung stream system that is potentially impacted by the proposed development. The
total land area draining into the Sha Lo Tung stream system upstream of the Hok
Tau Reservoir is in the region of 555ha.
GCG (Asia) Ltd Sha Lo Tung Development
Drainage Assessment and Mitigation Measures
The area of water catchment land draining into the Sha Lo Tung valley stream
system upstream of, and including, the development site area is approximately
39.9ha. Figure 3.1 also shows the location and extent of the development area
associated with the Sha Lo Tung PPP. Section 3.4.3 of the EIA identifies the principal
components of the development. This states that the main buildings in the
Development Site are the Nature Interpretation Centre, Multi-Cultural Education
Retreat and Columbarium structures which together occupy approximately 1.27 ha
(including the car park and major paths connecting all buildings). In addition to this
land take, the cut slopes, formed platforms, pavilion and gathering area amount to an
additional 0.36 ha. This means that when one examines the land classification for the
proposed development, less than 1.625ha of surface area represents flow through
areas of proposed development, paved surfaces and/or buildings with rooftop
gardens (ie land area that is not naturally vegetated, abandoned agricultural land
and/or landscaped slopes). This represents only 4.07% of the area contributing flow
into the Sha Lo Tung stream at the location of the development and only 0.29% of
the land area upstream of the Hok Tau Reservoir.
It should also be noted that the upgraded access road into the development site
represents an area of around 0.33ha. As explained later in this document the surface
run-off flow from this area (together with the car park) will be collected and pumped
off site with no discharge into the Sha Lo Tung stream.
4.1 Area A1
GCG (Asia) Ltd Sha Lo Tung Development
Drainage Assessment and Mitigation Measures
existing access road. The proposed development will not impact on this sub-
catchment area and the run-off will flow naturally into the Sha Lo Tung Stream.
4.2 Area A2
This sub-catchment has a surface area of 1.69ha and at present comprises 1.58ha of
naturally vegetated land and 0.11ha of single carriageway access road which has no
engineered drainage for surface run-off. It is intended that after the development is
complete Area A2 will comprise three separate and distinct drainage regimes. These
are as follows:
4.3 Area B1
4.4 Area B2
The structures will be cut into the western ridgeline and extend as cantilever
structures over the true valley which will be retained. Paved access between the
columbarium blocks will be provided along the valley floor, which is also proposed to
feature a cascade waterfall. The run-off area for B2 will be increased by the run-off
GCG (Asia) Ltd Sha Lo Tung Development
Drainage Assessment and Mitigation Measures
from the Interpretation Centre and associated car park from Area A2 (see above).
The total area of the development within the 4.0ha of Area B2 is 1.3ha.
4.5 Area B3
This sub-catchment has a surface area of 2.96ha and at present comprises naturally
vegetated land that is located outside of the proposed development area and is
unaffected by the development but naturally drains towards it. During construction it
is proposed that the run-off flows from this area are intercepted and conveyed to the
Sha Lo Tung Stream this avoiding any interaction with either the development site or
any area subject to vehicular traffic.
4.6 Area B4
4.7 Area C
4.8 Area D
This sub-catchment area is to the east of the development, drains away from the
development and discharges into the Sha Lo Tung stream downstream of the
development. The proposed development will not impact on this sub-catchment area
and the run-off will continue to flow naturally into the Sha Lo Tung Stream.
GCG (Asia) Ltd Sha Lo Tung Development
Drainage Assessment and Mitigation Measures
5.1 Introduction
Having identified the sub-divisions in the natural topography based on their drainage
characteristics it is possible to develop mitigation measures to minimise the impact of
the development on the existing drainage system and in particular the discharge into
Sha Lo Tung Stream. The approach to drainage impact mitigation measures has as
an overriding objective to retain and maintain the existing quality and quantity of
water flow into the natural stream systems downstream of the Sha Lo Tung
development area. In doing so it is intended to draw clear distinctions between the
following run-off and drainage circumstances:
The approach and measures proposed to mitigate the impact on the existing
hydrology regime are illustrated in Figure 5.1 and summarised in Section 5 below.
As described above Areas A1, B1, C and D are all naturally vegetated land (non-
development zones) and the drainage characteristics of all of these areas will be
unaffected by the proposed development. The surface run-off will be maintained as
general hinterland flow draining naturally into the Sha Lo Tung stream system. As an
added precaution a 20m buffer zone will be maintained at the border of these areas
where they interface with areas of construction.
Both of the Areas B3 and B4 are naturally vegetated land (non-development zones)
and will not be changed to either development vehicular zones or development non-
vehicular zones. This means the drainage characteristics will be unaffected by the
development. However, surface run-off from this area drains towards and at present
GCG (Asia) Ltd Sha Lo Tung Development
Drainage Assessment and Mitigation Measures
passes through the area designated for development and eventually discharges into
the Sha Lo Tung stream. It is intended therefore to intercept the run-off from Areas
B3 and B4 before it enters the development site and either by-pass the development
site in order to retain and maintain existing water quality or incorporate it within the
development water management plan. These two options which provide the same
product (i.e. minimal change to the existing run-off characteristics) will be evaluated
during detailed design and are described below.
5.4 Area A2
As discussed above the sub-catchment area A2 will have three distinct areas of
drainage characteristics after the development has been constructed. The proposed
mitigation measures for each of these areas are discussed below:
GCG (Asia) Ltd Sha Lo Tung Development
Drainage Assessment and Mitigation Measures
features including self sustaining plants and herring bone filter drains as
required to encourage groundwater recharge. There will be no chemicals
used for the landscaping in this area. Surface run-off will be routed to
non-developed naturally vegetated “buffer” zone before discharge to Sha
Lo Tung stream.
The pumping station pumps and wet well will be sized to control the rate
of discharge from the development vehicular zone such that the highway
drainage system will not be overloaded. Preliminary calculations to
estimate the additional run-off volume generated by the upgraded access
road and proposed car park are presented in Appendix I. These
calculations indicate that for a 200 Year return storm event the additional
volume of run-off would be in the region of 70m3.
GCG (Asia) Ltd Sha Lo Tung Development
Drainage Assessment and Mitigation Measures
It is noted that the quality of surface run-off from highways can contain
some degree of contaminants. Key pollutants have been identified as
PHAs derived from partially combusted hydrocarbon fuel, leakage from
internal combustion engines and degradation of rubber tyres. These are
typically fine particles that accumulate like dust on highways. They
coalesce into larger masses or stick to grit and other highway debris.
These pollutants can be reduced significantly by removing the solids
transported in highway surface runoff. In most highways this can be
achieved through trapped gullys and catchpits that have a depressed
sump that collects heavier material such as grits. Research has also
shown that the first rainfall after a dry period has a significantly higher
proportion of pollutants as it washes down the accumulated “highway
dust”, leading to the concept of “first flush”. The volume of flow associated
with the “first flush” arising form the development vehicular zone is
calculated in Appendix II.
5.5 Area B2
GCG (Asia) Ltd Sha Lo Tung Development
Drainage Assessment and Mitigation Measures
The vortex grit separation system typically consists of a hollow, cylindrical vessel with
a sloping base and a flat cover. The geometry of the interior and the shape and
placing of the entry nozzle are such that the flow must follow a prescribed path
through the vessel.
The stormwater runoff is introduced tangentially into the side of the cylindrical vessel
causing the contents to rotate slowly about the vertical axis. The flow spirals
gradually down the perimeter allowing any grit and sand particles to settle out by
gravity. This process is aided by the drag forces at the boundary layer on the wall
and base of the vessel.
An inverted cone, attached to the centre shaft, is often mounted at the bottom of the
vessel so that its edge is clear of the sloping base. A grit pot for the separated grit is
located under the cone.
The internal components direct the main water flow away from the perimeter and
back up the middle of the vessel as a broad spiralling column, rotating at a slower
velocity than the outer downward flow. In addition, a dip plate is suspended from the
underside of a component support frame. This dip plate locates the shear zone, the
interface between the outer downward circulation and the inner upward circulation
where a marked difference in velocity encourages further grit separation. By the time
the flow reaches the top of the vessel, it is free of grit and can be discharged to the
outlet channel.
The accumulated solid particles removed from the storm water flow are collected
within the grit pot of the separator and transferred either by pumping or by gravity
through an Archimedean screw to a grit skip for disposal. If a range of solid particles
is expected an intermediate filter system can be incorporated to serrate and classify
material by their particle size.
The grit separators are not sized based on flow volume but on flow rates. The
supplier uses a design flow rate to physically size the vortex chambers to suit the
flow rates in combination with the physical constraints on site.
As stated above “first flush” is a term used to define the initial stormwater discharge
from a rainfall event. First flush has been shown to exhibit peak pollutant
concentrations particularly from highway pavements with the pollutants attached to
grit and sediments concentrated in the initial runoff. Similarly, in regions that exhibit
dry/wet seasonal variations such as the sub-tropical patterns experienced in Hong
Kong, treating the first few storms has been shown to be more effective than treating
a constant volume throughout the wet season. The calculation for first flush volumes
is only really appropriate for uniform highway surfaces and cannot be calculated with
GCG (Asia) Ltd Sha Lo Tung Development
Drainage Assessment and Mitigation Measures
The grit separators are sized on rates of flow and not flow volumes. The physical size
of the grit separators is normally determined by the manufacturer based on the flow
rates calculated in Appendix III together with a consideration of the physical
constraints appropriate to the particular site location.
During the dry season the outlet from the storage/holding tank will provide an
opportunity for run-off to be re-used in the development site for toilet flushing, or
other suitable uses as identified in the development water management plan. This
will only be done after the contents of the holding tank have been tested and checked
for compliance with water in the Table 3 of Water Pollution Control Ordinance
(WPCO) Technical Memorandum and the views from Department of Health will be
sought to address any hygienic concerns. This reflects a sustainable and socially
responsible approach to stormwater management. If compliance cannot be
demonstrated by the proposed mitigation measures the grit interceptors can be
linked to the pumping station to isolate the discharge from water gathering grounds
and the runoff volume can be pumped in its entirety to a public stormwater system in
GCG (Asia) Ltd Sha Lo Tung Development
Drainage Assessment and Mitigation Measures
a controlled and regulated manner to minimize impact (ie not concurrent with a storm
event) via a rising main or, in the case of unacceptable contamination, into a tanker
for off-site removal.
6. CONCLUDING REMARKS
The principal impacts on the existing drainage that require mitigation are as follows:
The increase in water quantity has been addressed by minimising the creation of
impermeable surfaces, encouraging natural ground water recharge through
soakaways/filter drains and transferring all highway runoff into the adjacent urban
catchment. The increase in peak intensity has been addressed by controlled run-off
attenuation using swales, naturally lined channels, catchpits, and grit separators with
outlet control and undeveloped buffer zones. The risk of pollution has been
addressed by transferring runoff from high risk area to the adjacent urban catchment,
and the use of catchpits, filter drains and grit separators in the traffic free, low risk
development site. The ability to discharge all stormwater flow off site without
interaction with the Sha Lo Tung stream has also been reviewed for emergency
scenarios.
GCG (Asia) Ltd Sha Lo Tung Development
Drainage Assessment and Mitigation Measures
FIGURES
3.1 Total Catchment Area for Water Gathering Grounds between Sha Lo
Tung and Hok Tau Reservoir
D
0099337l6
GCG (Asia) Ltd Sha Lo Tung Development
Drainage Assessment and Mitigation Measures
APPENDIX I
Calculation for Surface Run-off from
Vehicular Development Areas
Appendix I
Vehicular Area
Hong Kong HyD Road Note 6 states mean 200 Year Storm Intensity = 280 mm/hour
Stormwater Drainage Manual (Section 7.5.2) recommends Rational Method for calculation of
run-off ie.
= 0.081 m3/s
= 81 litres/second
= 35.5 m3
2. Proposed Vehicular Development :
Upgraded Access Road and Car Park Area – Total Surface Area = 0.33 ha
= 3,300m2
Q = 0.278.c.i.A
Table 2 of Stormwater Design Manual : 200 Year Return Storm has duration of 7.3 mins.
= 107 m3
Additional Run-off due to proposed Vehicular Development for 200 Year Storm Event
= (107 – 36) m3
= 71 m3
GCG (Asia) Ltd Sha Lo Tung Development
Drainage Assessment and Mitigation Measures
APPENDIX II
Calculation of First Flush for Vehicular
Development Zone
Appendix II
1. Introduction
A significant proportion of the potential pollutants from the vehicular development zone will
conveyed in the “first flush” with up to 85% of pollutants found as, or adsorbed on/by
sedimentary particles (Ref. CIRIA Report # 142 : Control of Pollution from Hignway Drainage
Discharges (1997)). The level of potential concentration will be dependent upon the antecedent
conditions ie. when the road was last washed down by rainfall. The most extreme conditions
are likely to occur following the first rainfall of the wet season after a prolonged dry season
duration, typically of around 4 months.
There are two alternative methods for calculation of first flush volumes. The first is based on
extensive studies carried out in the USA (Oberts, 1994) which demonstrated that up to 90% of
pollutants were carried by the initial 12 mm of rainfall. Using this approach and applying an
adjustment factor of 1.5 for the Hong Kong climatic conditions this would mean the first flush
volume for the upgraded access road and car park would be in the order of 60m3.
The second approach would be to intercept the run-off volume associated with the first 5
minutes of the rising limb of hydrograph modelling a 1 in 2 year rainstorm event stormwater.
The DSD Stormwater Drainage Manual (Table 2) indicates the rainfall intensity to be
145 mm/hour.
= 26 m3
3. Conclusion
Based on two alternative methods for calculating the first flush run-off volume the drainage
impact mitigation measures shall be based on the most onerous method which is a volume of
60m3.
GCG (Asia) Ltd Sha Lo Tung Development
Drainage Assessment and Mitigation Measures
APPENDIX III
Calculation of Run-off for
Non-Vehicular Development Area (Area B2)
Appendix III
1. Introduction
Sub-catchment Area B2 hosts the significant majority of the proposed development which will
comprise four columbarium blocks, the administration centre and the Multi-Cultural Education
Retreat (MCER) with paved access between them. No vehicular traffic will be permitted in this
area. In order to mitigate the increased run-off from the paved surfaces, rooftop gardens are
proposed for the columbarium structures and the lower part of the MCER, thereby reducing the
run-off co-efficient. Grit separators will be installed beneath the development car park and
designed to capture all flow from regular rainstorm events generating run-off through the non-
vehicular development area. To prevent the grit-separators from being overloaded a high level
overflow will bypass the grit intercepts during peak flows and discharge into a storage tank.
The following sections present the calculations to determine the change in run-off volumes as a
result of the non-vehicular development and it is the product of these calculations that determine
the size of the storage tank.
It is necessary to calculate the time of concentration (tc) for the non-vehicular development zone
catchment area. As stated in the DSD Stormwater Manual (Section 4.4.3), this is the time taken
for rainfall to travel from the most remote point in the catchment area to the point under
consideration, which in this case is the point of discharge into the Sha Lo Tung Stream system
downstream of the proposed development. When this element of rainfall is contributing to the
discharge then the entire area of the catchment is contributing and is therefore the critical (or
design) storm duration.
In accordance with the DSD Stormwater Drainage Manual (SDM) Section 7.5.2 the time of
concentration can be calculated using the Brandsby Williams formula as follows:
0.14465L
t =
H0.2.A0.1
where :
t = time of concentration (minutes)
L = distance (m) measured on the line of natural flow
H = average fall (m per 100m) from the summit of the
catchment to the point under consideration
A = Catchment Area (m2)
In addition to the above, it is good practice to check the calculation for the time of concentration
for a number of different flow lines as the time of concentration depends on the average slope
gradient as well as the length of the lines of flow. The drainage design for the development site
will calculate the time of concentration for each element/flow length within the stormwater
system and size it accordingly to cater for a storm of duration equal to the time of concentration.
In order to assess the impact of the non-vehicular development on the Sha Lo Tung stream, the
time of concentration is that time for all areas of the natural catchment extending up to Kau
Lung Hang Shan to reach the outfall point from the development. The plan of the hinterland
catchment that influences the surface run-off at the development site and the longitudinal
topographical profile from Kau Lung Hang Shan to the development site are shown in Figures
III.1 and III.2.
Figure III.1 : The Hinterland Catchment
440mPD
200mPD
172mPD
178mPD
Figure III.2: Longitudinal Profile of the Hinterland Catchment
The information presented in Figure III.2 shows clearly that the hinterland catchment comprises at
least two distinct zones; the upper catchment with predominantly overland flow in poorly defined
channels that are frequently dry in the winter months, and the lower regions designated by the Sha
Lo Tung Valley characterized at present by abandoned agricultural land and irrigation channels We
believe that applying the Brandsby–Williams approach to the total upland catchment between the
peak elevation of the catchment and the development outfall is clearly not representative. This is
demonstrated in Table III.1 below. The Brandsby–Williams method has been used for the entire
streamlength extending from the peak point at the top of Kau Lung Hang Shan to the outfall at Point
4 (see Figures III.1 and III.2). This results in a Time of Concentration (tc) of 37 minutes. An
alternative (and in our view more representative) approach is to use the Brandsby-Williams method
to calculate the Time of Concentration only for the upland portion; the initial approximately one
kilometre between the peak point at the top of Kau Lung Hang Shan and Point 2 (see Figures III.1
and III.2). Thereafter a time of flow approach has been adopted. This assumes that as the run-off
crosses the valley floor between Points 2 and 4 the stream water is moving at 1m/s and so will cover
60m in 1 minute, or between Points 2 and 3 it will cover 415m in 6.92 minutes, and the 155m
between Points 3 and 4 in 2.52 minutes. Adding these together we get a Time of Concentration (tc)
equal to 32.86 or 33 minutes. This represents a reduction in tc of over 10% when compared to the
Brandsby Williams method.
3.1 Introduction
The calculation for run-off will be based on the Soil Conservation Service (SCS) method. This
method assumes a time varying rainfall - run-off relationship that is non-linear and comprises an
initial phase of losses due to infiltration followed by a time-dependent infiltration curve.
Due to the particular (and complex) characteristics of the Sha Lo Tung development site and the
surrounding hinterland it is considered that the SCS method is the most appropriate method to
calculate the existing and post development run-off volumes to estimate (and to mitigate against)
the effects of the developments site.
The volume and rate of run-off depends on both meteorological and catchment characteristics
and the estimation of run-off requires an index to represent these two factors. The precipitation
volume is probably the single most important meteorological characteristic in estimating the
volume of run-off. The soil type, land use and the hydrological condition of the soil are the
catchment characteristics that will have the most significant impact in estimating the volume of
run-off. The antecedent soil moisture will also be an important determinant of run-off volume.
The SCS method involves an index, which is called the run-off curve number (CN), to represent
the combined hydrological effect of soil, land use, agricultural land treatment class,
hydrological condition and antecedent soil moisture, all of which can be assessed. The values
used in the Sha Lo Tung drainage impact assessment are presented in Table III.2 below and
have been derived from a comprehensive schedule of published data.
This approach results in the following expressions for nett rainfall (mm) is expressed as:
(P – 0.2)2
R = for R > 0.2S
P + 0.8S
R = 0 for P ≤ 0.2S
where :
R = nett rainfall after infiltration losses
P = total gross rainfall (mm)
S = potential maximum retention of catchment
Land Use CN
Upland Slopes & Natural Vegetation 70
Lowland Abandoned Agricultural Land 60
Rooftop Garden 77
Structure / Paved Road 98
Stream Course 100
Table III.2: SCS Method Curve Numbers for Different Land Use
(Ref. USDA TR-55 Urban Hychology for Small Watershed)
1000
S ={ -10} x 25.4 (mm)
CN
It should be noted that whilst the CN number may look similar to the more simplistic run-off
coefficients used in the Rational Method, they are not the same.
Because the catchment area servicing the non-vehicular development zone has different land
uses and is therefore non-homogeneous in terms of infiltration it is necessary to calculate a
“weighted” SCS Curve Number. This has been done for the conditions which are representative
of both pre and post-development and this work is summarised in Tables III.3 and III.4.
Land Use CN Area % Age of Weighted
(m2) Total Area CN
Upland Slopes & 70 36,280 85% 59.5
Natural Vegetation
Lowland Abandoned 60 6,360 14.9% 8.9
Agricultural Land
Stream Course 100 64 0.1% 0.15
Weighted CN Value 68.6
Taking the 1 in 50 year storm of 33 minutes duration from Table 5 of the DSD Stormwater
Drainage Manual we can determine the nett rainfall hyetograph. Table III.5 summarizes the
solution for nett rainfall after infiltration losses for the existing land use condition.
Time Rainfall Rainfall Cumulative Solving for R Nett rainfall SCS nett rain
(min) Intensity increment Rain CN=68.6 SCS Loss expressed as a
(mm/hr) (mm) (mm) S =116 model percentage *
Ia = 23.2 hyetograph
0 0 0 0
1 91 1.60 1.60
2 93 1.63 3.23
3 96 1.68 4.83
4 98 1.75 6.47
5 101 1.82 8.15
6 105 1.88 9.90
7 109 1.97 11.72
8 113 2.05 13.60
9 118 2.17 15.57
10 123 2.30 17.62
11 130 2.45 19.78
12 138 2.65 22.08
13 147 2.90 24.53 0.02 0.02 0.7
14 159 3.25 27.18 0.13 0.12 3.7
15 174 3.78 30.08 0.39 0.25 6.6
16 195 4.63 33.33 0.81 0.43 9.3
17 227 5.73 37.12 1.49 0.68 11.9
18 278 4.63 41.75 2.56 1.07 23.1
19 344 3.78 47.48 4.20 1.65 43.7
20 278 3.25 52.11 5.77 1.57 48.3
21 227 2.90 55.89 7.19 1.42 49.0
22 195 2.65 59.14 8.50 1.31 49.4
23 174 2.45 62.04 9.74 1.24 50.6
24 159 2.30 64.69 10.93 1.19 51.7
25 147 2.17 67.14 12.07 1.14 52.5
26 138 2.05 69.44 13.18 1.11 54.1
27 130 1.97 71.61 14.26 1.08 54.8
28 123 1.88 73.66 15.30 1.04 55.3
29 118 1.82 75.63 16.32 1.02 56.0
30 113 1.75 77.51 17.32 1.00 57.1
31 109 1.68 79.33 18.31 0.98 58.3
32 105 1.63 81.08 19.27 0.96 58.8
33 101 1.60 82.76 20.21 0.94 58.9
Note *: Rational Method recommends Run‐off Coefficient of 0.13 – 0.35 for grassland (SDM 7.5.2 refers)
Table III.5: Calculation of 50 year Nett Rainfall for Run-off at Area B2 – Existing Condition
It is noted that the total nett rainfall (R) is 20.21mm for the 33 minute storm.
The Parameters, CN, S, P and R change for the post-development scenario and hence the SCS
nett rainfall hyetograph changes too. This is summarized in Table III.6 below and the total nett
rainfall for the post-development condition with a 33 minute storm increases to 28.7 mm
(50 year event).
Time Rainfall Rainfall Cumulative Solving for R DEVELOPMENT EXISTING
(min) Intensity increment Rain CN=75 Nett rainfall SCS Nett rainfall
(mm/hr) (mm) (mm) S =85 Loss model SCS Loss
Ia = 17.0 hyetograph model
hyetograph
0 0 0 0
1 91 1.60 1.60
2 93 1.63 3.23
3 96 1.68 4.83
4 98 1.75 6.47
5 101 1.82 8.15
6 105 1.88 9.90
7 109 1.97 11.72
8 113 2.05 13.60
9 118 2.17 15.57
10 123 2.30 17.62 0 0
11 130 2.45 19.78 0.09 0.08
12 138 2.65 22.08 0.29 0.20
13 147 2.90 24.53 0.61 0.33 0.02
14 159 3.25 27.18 1.09 0.48 0.12
15 174 3.78 30.08 1.75 0.66 0.25
16 195 4.63 33.33 2.63 0.89 0.43
17 227 5.73 37.12 3.85 1.22 0.68
18 278 4.63 41.75 5.58 1.73 1.07
19 344 3.78 47.48 8.05 2.47 1.65
20 278 3.25 52.11 10.26 2.22 1.57
21 227 2.90 55.89 12.21 1.94 1.42
22 195 2.65 59.14 13.97 1.76 1.31
23 174 2.45 62.04 15.60 1.63 1.24
24 159 2.30 64.69 17.14 1.54 1.19
25 147 2.17 67.14 18.61 1.46 1.14
26 138 2.05 69.44 20.01 1.41 1.11
27 130 1.97 71.61 21.36 1.35 1.08
28 123 1.88 73.66 22.66 1.30 1.04
29 118 1.82 75.63 23.94 1.27 1.02
30 113 1.75 77.51 25.17 1.23 1.00
31 109 1.68 79.33 26.37 1.21 0.98
32 105 1.63 81.08 27.55 1.17 0.96
33 101 1.60 82.76 28.69 1.14 0.94
Table III.6: Calculation of 50 year Nett Rainfall for Run-off at Area B2 – Proposed Development
3.4.1 Introduction
In order to calculate the change in run-off volume due to the development and consequently the
size of the storage tank, we need to construct a run-off hydrograph for both the existing and
post-development conditions in Area B2. Hydrographs describe the whole time history of the
changing rate of flow from a catchment due to a rainfall event rather than just the peak flow
derived when using the Rational Method. Again, we would emphasize that the particular
conditions that exist at Sha Lo Tung make it necessary to adopt this approach to get the most
accurate and representative estimate of the impact due to the change in land use.
A major step forward in hydrological analysis is the concept of a unit hydrograph, defined as the
hydrograph resulting from effective rainfall falling in a unit of time produced uniformly in
space and time over the total catchment area. Each catchment will have its own unique shaped
site specific hydrograph. An important element in constructing the site specific hydrograph is
understanding the concept of the Lag Time. Lag Time is the period of time from the centroid of
the effective rainfall distribution to the time of peak flow for a catchment area for a particular
storm event. This is illustrated in Figure III.3.
The Lag Time for the unit hydrograph can be defined by a range of empirical expressions. In
this assessment the WSD lag time equation has been used ie:
The existing catchment for Area B2 covers 42,700m2 equivalent to 10.55 acres. The developed
site will cover an area of 44,480 m2 equivalent to 10.99 acres. The lag time for catchment B2 is
therefore 0.09 hours or 5.25 minutes.
For the Sha Lo Tung Drainage Impact Assessment the SCS unit hydrograph has been used. The
unit hydrograph is triangular with a base length in time of 2.67 times the time to peak (tp) as
shown in Figure III.4.
The principles of unit hydrographs which make them such a versatile tool are:
These principles may be applied in developing a run-off for a time variable effective rainstorm as
shown above in Figure III.4.
For the analysis illustrated in Figure III.4 a one minute time step (ie D=1) (unit hydrograph) has
been adopted a time to peak flow (minutes) tp = Lag + D/2 which equates to 5.75 minutes or, more
simply for the purposes of calculation, tp = 6 minutes. The time element for the falling leg of the
hydrograph is 1.67 tp or 10 minutes. The area under the triangular hydrograph is (Qp*6/2) +
(Qp*10/2) = 8Qp and is equivalent to effective rainfall (i) x Area. This results in Qp defined as A.i/8.
For the existing condition in Catchment B2 this is 42,700 x i/8 or Qp = 5.34 i (m3/min) or
0.089i m3/s.
The ordinates of the SCS unit hydrograph can therefore be defined as follows:
Time (min) Q
0 0
1 0.167Qp
2 0.33Qp
3 0.5Qp
4 0.66Qp
5 0.833Qp
6 0.089
7 0.9Qp
8 0.8Qp
9 0.7Qp
10 0.6Qp
11 0.5Qp
12 0.4Qp
13 0.3Qp
14 0.2Qp
15 0.1Qp
16 0
3.4.2 Calculation of Run-off Volume (50 Year Storm Event)
Using the method of construction described above in Section 3.4.1, the run-off hydrographs for both
existing and proposed development conditions at B2 for a 50 year storm event may thus be
determined using the data generated from Table III.7 (Existing Condition) and Table III.8 (proposed
Development Condition) and result in the graphical form presented in Figure III.5. The peak run-off
is highlighted in both Table III.7 and III.8 – this is the value used to calculate the Extra Over
Volume of Run-off caused by the development in Area B2, as highlighted in Figure III.5. It is this
Extra Over Volume of Run-off that is used to determine the size of the Storage Tank.
Extra-Over Volume
Proposed Development
Existing Condition
Table III.9: Calculation of Extra Over Volume at Area B2 for 50 Year Storm Event
The run-off volume that exceeds the existing run-off at a value of 0.85 m3/s, referred to as “Extra
Over Volume”, is termed stored volume and may be calculated as the mean rate of flow x time step.
For example:
(0.85 - 0.80) x 60 = 3 m3
(0.85 – 0.71) x 60 = 8.4 m3
At t= 46 minutes the mean inflow is (0.16+0.10)/2 = 0.13m3/s representing an inflow volume of 0.13
x 60 = 7.8 m3 that combines with the 14.0m3 remaining in storage to give a volume of 21.8 m3 that
discharges at a rate of 21.8/60 = 0.36m3/s. Thereafter the inflow balances the outflow as illustrated
below in Figure III.6.
The overall summary of the information provided in Table III.9 is that for a 50 year storm event of
33 minute duration the additional volume created by the post development run off is 201m3.
Proposed Development
Extra-Over Volume
Existing Condition
The process and calculations described above for the 50 year event can then be repeated for the same
33 minute duration 200 year event.
This is summarised in Tables III.10, III.11 and III.12 below which generate peak run-off for both the
existing and post-development condition and the data required for the unit hydrographs to calculate
the Extra Over Volume for the 200 year event.
Table III.10: Calculation of 200 year Nett Rainfall for Run-off at Area B2 (existing and proposed)
Table III.11: Calculation of Run-off Hydrograph for existing B2 Catchment (200 year return period)
Table III.12: Calculation of Run-off Hydrograph for B2 Catchment with development (200 yr return period)
As is highlighted in Table III.11the 200 year storm event of 33 minutes duration produces a peak
run-off from the existing condition of the B2 site of 1.24 m3/s. With the outfall from the site
controlled at this level the “Extra-Over Volume generated by the post-development condition can be
simply calculated as shown below in Table III.13 and illustrated graphically in Figure III.7.
Table III.13: Calculation of Extra Over Volume at Area B2 for 200 Year Storm Event
The overall summary of the information provided in Table III.13 is that for a 200 year storm event
of 33 minute duration the additional volume created by the post-development run-off is 172 m3.
It is noted that the stored volume is less for the 200 year event is less than for the 50 year storm
event of the same duration. This is because the threshold level based on the existing run-off for the
200 year event is higher than the threshold for the 50 year event.
It should be noted that this is a hypothetical situation as it will be impossible to determine the
statistical return period of any storm event in real time and therefore set the outlet control
accordingly. What is required is for the governing bodies to accept the general principles described
above and to determine an acceptable outflow rate which shall not be exceeded to allow on-site
storage facilities to be designed accordingly as part of the detailed design.
It is proposed as part of the drainage impact mitigation measures that all run-off from paved and
rooftop areas will discharge directly into grit separators with a storage facility to accommodate
overload. As this run-off will dominate the Extra Over Volume created by the non-vehicular
development zone the remaining contribution from the development zone will be extremely small,
the Extra Over Volume will reduce and the size of the storage tank will also reduce.
The run-off from the remainder of the non-vehicular development site is comparable to the pre-
existing run-off hydrograph for the full undeveloped B2 catchment. The B2 developed area of
44,482 m2 can be split into 6,624m2 of structure and paved surfaces and the remainder comprising
more conservative development (green roofs and landscaping) of 37,858 m2.
The calculation for weighted CN value as provided in Table III.4 can be reworked for this land use
as illustrated in Table III.14 below.
Land Use CN Area (m2) %age of Total Area Weighted CN
37,858 m2 portion of catchment B2
Upland Slopes &
70 31,820 84.0 58.8
natural vegetation
Lowland abandoned
60 1280 3.4 2.0
agricultural land
Rooftop garden 77 3,995 10.6 8.1
Stream course water feature 100 763 2.0 2.0
71
6,624 m2 portion of catchment B2
Structure/Paved surfaces 98 6,624 100% 98
The nett rainfall hyetograph will change due to the reduction in the weighted CN from 75 down to
71. This is demonstrated in Table III.15 below.
Table III.15: Calculation of 50 Year Nett Rainfall for Run-off at Area B2 (37,858 m2 without paved surfaces)
The run-off hydrograph for the 37,858 m2 portion of catchment B2 can then be calculated using the
same principles as outlined previously, with Qp= A.i/8 equivalent to 0.0789i m3/s. This is shown in
Table III.16 below. The peak 50 year run-off shown in Table III.16 is now reduced to 0.86 m3/s
from the 1.25 m3/s in Table III.8 for the run-off model for the complete post-development scenario.
This reduced peak run-off is comparable to the run-off calculated for the existing condition for the
entire B2 catchment (0.85 m3/s) calculated above in Table III.7. This means that there is no
significant Extra Over Volume to be accommodated for the 50 year storm event.
The run-off from the paved areas will pass through the grit separators and may be either combined
with the highway run-off for discharge to Tai Po or discharged into Sha Lo Tung streamcourse.
The calculations presented in Tables III.15 and III.16 can be repeated for the 200 year storm of 33
mins duration on an area of 37.858 m2 with a weighted CN value of 71.This is summarized in
Tables III.17 and III.18 below.
Table III.16: Calculation of Run-off Hydrograph for B2 Catchment with development and
roof top run-off to grit separators (50 year return period)
Time Rainfall Rainfall Cumulative Solving for R DEVELOPMENT
(min) Intensity increment Rain CN=71 Nett rainfall SCS
(mm/hr) (mm) (mm) S =103.7 Loss model
Ia= 20.7 hyetograph
0 0 0 0
1 118 1.97 1.97
2 121 2.02 3.98
3 125 2.08 5.95
4 128 2.13 7.97
5 133 2.22 10.05
6 138 2.30 12.18
7 143 2.38 14.40
8 150 2.50 16.70
9 157 2.62 19.08
10 166 2.77 21.58 0.01 0.01
11 177 2.95 24.20 0.11 0.10
12 191 3.18 26.97 0.35 0.24
13 208 3.47 29.92 0.75 0.39
14 232 3.87 33.10 1.32 0.57
15 267 4.45 36.57 2.10 0.78
16 325 5.42 40.43 3.14 1.05
17 399 6.65 44.88 4.56 1.42
18 325 5.42 50.30 6.56 2.00
19 267 4.45 56.95 9.37 2.81
20 232 3.87 62.37 11.92 2.55
21 208 3.47 66.82 14.17 2.25
22 191 3.18 70.68 16.23 2.06
23 177 2.95 74.15 18.16 1.92
24 166 2.77 77.33 19.98 1.82
25 157 2.62 80.28 21.72 1.74
26 150 2.50 83.05 23.39 1.67
27 143 2.38 85.67 25.00 1.61
28 138 2.30 88.17 26.57 1.57
29 133 2.22 90.55 28.09 1.52
30 128 2.13 92.85 29.58 1.49
31 125 2.08 95.07 31.03 1.46
32 121 2.02 97.20 32.45 1.42
33 118 1.97 99.28 33.85 1.40
Table III.17: Calculation of 200 Year Nett Rainfall for Run-off at Area B2
(37,858 m2 without paved surfaces)
Repeating the run-off calculations using the reduced area of 37.858m2 with a weighted CN value of
71 and 200 year return event results in post-development peak run-off equal to 1.22 m3/s. This is a
significant reduction from the peak run-off for the full area of development area in B2 (44,482 m2)
of 1.61 m3/s (Table III.12) based on a CN value of 75 and is comparable with (but less than) the
existing scenario of 1.24 m3/s.
This may be simply explained by demonstrating that the run-off volume from the structures
calculated as the gross rainfall (87.3mm for the 50 year event and 99.3mm for 200 year event)
falling on a rooftop and paved area of 6,624 m2 with a (Rational method) run-off coefficient of 0.9
will be 520 m3 and 592 m3 respectively.
Table III.18: Calculation of Run-off Hydrograph for B2 Catchment with development and
roof top run-off to grit separators (200 year return period)
3.4.5 Summary of Run-off Volume Calculations
The calculations presented in Section 3.4.4 can be summarised in Table III.19 where the Extra
Over Volume created by the non-vehicular development zone is recalculated but this time
omitting the flow volume passing through the grit separators. This shows that for a range of
storm return events the maximum requirement for a storage/holding facility to prevent
additional flow into the Sha Lo Tung Stream system is around 30 m3. This can be
accommodated beneath the proposed car park.