1. What type of gas is used in accumulator bottles. (1 Point)
a. Air
b. Oxygen
c. Hydrogen
d. Nitrogen
2. Select the correct pressure that accumulator bottles are normally pre-charged
to. (1 Point)
a. 1000 psi
b. 2000 psi
c. 3000 psi
d. 1500 psi
e. 1200 psi
3. Hose bundles contain pilot lines to operate SPM valves. What does SPM refer
to. (1 Point)
4. What is the function of the High – Low bypass valve on a Driller’s surface
remote panel. (1 Point)
5. On a master subsea BOP panel, what is the correct colour that the panel lights
should be in to indicate the correct drilling line up according to API. RP16E.
(1 Point)
a. All Red
b. All Green
c. Some Red Some Green
6. Select the TWO correct statements with regards to pilot signals (2 Points).
Training to be First
2
7. Which pressure is used to operate failsafe valves. (1 Point)
a. Manifold Pressure
b. Accumulator Pressure
c. Annular Pressure
d. Rig Air Pressure
8. Select from the list of locking systems below the one that locks in one position
only. (1 Point)
a. Ultra-Lock
b. MPL
c. Poslock
d. Wedgelock
e. Manual Lock
9. From the following list select the components that are not found in Annular
Preventers. (3 points)
10. What 2 types of preventers will close and seal around various sizes of
tubulars. (2 Points)