You are on page 1of 7

SMS ENERPRISE

LABOUR RATE FOR ELECTRICAL WORKS -2020

Work Description of Works Unit Rate, Tk SMS Rate, Tk Basis of Measurement Above/
No. ENTERPRISE Remarks
Rate, Tk

1 Fixing of PVC conduit of following sizes The linear length in ft. along Including
through brick-wall, RCC slab, column, the mid section of pipe shall supply of G.I
including circular, Junction boxes, bends, be measured for payment. All wire & Nitto
the fitting such as junction/ tape
sockets, 14 swg G.I. pull wire & including
pull box shall be included in
all other accessories and supply of binding the length of pipe.
wire as per drawing and instruction of the
Engineer-in-charge

a) ½" dia Rft. 2.20 5.50


b) ¾" dia Rft. 2.30 5.75
c) 1" dia Rft. 2.40 6.00
d) 1.25" dia Rft. 2.50 6.25
e) 1.5" dia Rft. 3.50 8.75
f) 2" dia Rft. 4.00 10.00
g) 3"dia & above Rft. 5.00 12.50
2 Drawing of PVC insulated or PVC sheathed - The linear length in ft. of Including
copper conductor through PVC conduit in cable shall be measured for supply of G.I
wall, roof, slab, column, beam, under payment. wire & Nitto
tape
ground, surface etc. and there of including
all consumable such as cable lugs with
supply of GI wire & Nitto tape as per
drawing and instruction of Engineer-in-
Charge

I. SINGLE-CORE -
a) 1 x 3/029/1.00mm2 Rft. 1.75 4.38
b) 1 x 3/036/1.50mm2 Rft. 1.75 4.38
c) 1 x 7/029/2.50mm2 Rft. 1.90 4.75
d) 1 x 7/036/4.00mm2 Rft. 1.90 4.75
e) 1 x 7/044/6.00mm2 Rft. 2.10 5.25
f) 1 x 7/064/10.00mm2 Rft. 2.10 5.25
g) 1 x 16 rm Rft. 2.75 6.88
h) 1x 25rm to 1x 35 rm Rft. 2.75 6.88
i) 1x 50rm to 1x 70rm Rft. 3.85 9.63
j) 1x 95rm to 1x 120rm Rft. 3.85 9.63
k) 1X150 rm & above Rft. 4.40 11.00
II. MULTI-CORE - The linear length in ft. of
cable shall be measured for
a) 2C-1.50mm2 Rft. 2.00 5.00 payment.
b) 2C-2.50mm2 Rft. 2.50 6.25
c) 2C-4.0mm2 & above Rft. 3.50 8.75
-
3 Drawing of PVC insulated or PVC sheathed - The linear length in ft. of Including
copper conductor for telephone and TV. pipe and cable shall be supply of G.I
antenna, Intercom etc. through PVC conduit measured for payment. wire & Nitto
tape
in wall, roof, slab, column, beam, under
ground, surface etc. and thereof including
all consumable with supply of G.I wire &
Nitto tape as per drag. and inst. of
Engineer-in-Charge

a) Drop wire 0.6mm to .9mm Rft 1.65 4.13


b) Co-axial cable for antenna Rft. 2.00 5.00
c) 1 to 2 pair telephone cable Rft. 1.75 4.38
d) 3 to 4 pair telephone cable Rft 1.90 4.75
e) 5 to 10 pair telephone cable Rft 2.00 5.00
f) 11 to 20 pair telephone cable Rft 2.10 5.25
g) 21 to 60 pair telephone cable Rft 2.75 6.88
h) 61 to 100 pair telephone cable Rft 3.85 9.63
i) Internet cable cat- 5/6 Rft 2.25 5.63
4 Drawing of bare annealed, earth continuity - The linear length in ft. of
copper conductor through PVC conduit cable shall be measured for
along-with current carrying conductor as payment.
routing shown on the drawing and as per
direction of Engineer-in-charge.

a) 16 SWG Rft. 1.15 2.88


b) 14 to 10 SWG Rft. 1.40 3.50
c) 8 to 6 Rft. 2.10 5.25
d) 4 SWG Rft. 2.35 5.88
e) 2 SWG Rft. 2.75 6.88
5 Installation with PVC pipe, steel saddle, - The linear length in ft. of
earthing wiring, fitting fixing complete as cable shall be measured for
per direction of Engineer-in-charge. payment.

a) 4X1C-10 rm to 4X1C-16 rm NYY cable Rft 14.00 35.00

b) 4X1C-25 rm to 4X1C- 35 rm NYY cable Rft 17.00 42.50

5 c) 4X1C- 50 rm to 4X1C- 70 rm NYY Rft 22.00 55.00


cable
d) 4X1C- 95 rm to 4X1C- 120 rm NYY Rft 25.00 62.50
cable
e) 4X1C- 150 rm NYY cable & above Rft 30.00 75.00
f) HT cable laying any size (Under Grd.) Rft 55.00 137.50

g) HT cable laying any size (Over head) Rft 55.00 137.50


6 Groove cutting work in Brick wall and in - The linear length of the
RCC wall, filling the gap with cement groove cutting will be the
mortar/ CC and mending good all basis for measurement
damages , keep the work place clean & tidy
during and after his work every day etc.
complete as per direction of Engineer-in-
Charge

1 no. pipe in groove Rft 4.50 11.25


7 Trench (Earth) cutting for under ground Rft. 9.00 22.50 The linear length in ft. of the
cable piping along with sand filling brick earth cutting will be the basis
laying as per instruction of Engineer-in- for measurement
charge.
8 Fitting and fixing of steel boxes (concealed) - The Fixture installed
for MK switch, Junction boxes, plug point, Complete in all respect
spot light box, regulator box in/c sand including consumable
materials shall be considered
cement plastering, curing the plaster for 07 as one unit.
days, keep the work place clean & tidy
during and after his work every day etc
complete as per direction of Engineer-in-
Charge

a)      Single box Each 17.00 42.50


b)      Double box Each 18.00 45.00
c)      Triple box Each 22.00 55.00
d) Joint Box : Any Size Each 15.00 37.50
e) Circular Box supply & fitting (for wall Each 10.00 25.00
9 a) Fixing of fan hook box for ceiling fan Each 18.00 45.00 The Fixture installed
etc. as per instruction of Engineer-in- Complete in all respect
charge. including consumable
materials shall be considered
as one unit.

b) Fixing of fan hook box for ceiling fan Each 60.00 150.00
etc. as per instruction of Engineer-in-charge
( After slab casting by making hole in
RCC slab)

c) Steel Box fitting in RCC slab for Spot Each 18.00 45.00
light
10 Fitting fixing Ceiling fan with necessary Nos. 50.00 125.00 The Fixture installed
box as per drawing or instruction of the Complete in all respect
Engineer-in-charge. including consumable
materials shall be considered
as one unit.

11 Installation of 10”-16” on different - The Fixture installed


mounted Exhaust fan with necessary works Complete in all respect
including scaffolding, resin water louver including consumable
materials shall be considered
barrier etc. complete as per direction of
as one unit.
Engineer-in-Charge

a) With whole cutting and side finish Each 130.00 325.00


with sand-cement mortar
b) Without whole cutting but side Each 65.00 162.50
finish with sand-cement mortar
12 Fitting fixing of concealed type switches on - The Fixture installed
boards at the location shown on the drawing Complete in all respect
or as per instruction of Engineer-in-charge. including consumable
materials shall be considered
as one unit.

a) Piano switch and socket Nos. 5.00 12.50


b) MK Switch -
i. 1 Gang Switch Nos. 15.00 37.50
ii. 2 Gang Switch Nos. 16.50 41.25
iii. 3 Gang Switch Nos. 18.00 45.00
iv. 4 Gang Switch Nos. 20.00 50.00
12 v. 5 Gang Switch Nos. 22.00 55.00
c) MK Socket (5A to 20A) Nos. 15.00 37.50
d) MK Dimmer Nos. 15.00 37.50
e) Telephone socket Nos. 16.50 41.25
f) Antenna socket Nos. 16.50 41.25
g) 20ADP switch Nos. 18.00 45.00
h) 5A to 15A Tumbler switch Nos. 7.00 17.50
I) 5A to 15A Tumbler socket Nos. 7.00 17.50
m) Bell push Nos. 15.00 37.50
n) Computer Socket Nos. 18.00 45.00
13 Fitting fixing of calling bell at the location Nos. 15.00 37.50 The Fixture installed
shown in the drawing. Complete in all respect
including consumable
materials shall be considered
as one unit.

14 Installation of Ckt Breaker on sub- - The Fixture installed


distribution Board (Concealed Type) Complete in all respect
insulators, copper Bus bar, copper neutral including consumable
materials shall be considered
bar, Main switches, internal connections
as one unit.
and mounting accessories etc. complete as
per direction of Engineer-in-charge.

a) 5A to 100A SP MCB Each 20.00 50.00


b) 5A to 100A Cut Out Each 10.00 25.00
c) 6A to 100A DP MCB Each 22.00 55.00
d) 10A to 100A TP MCB Each 30.00 75.00
e) 16A to 100A TP MCCB Each 40.00 100.00
f) 125A to 400A TP MCCB Each 40.00 100.00
g) 500 A TP MCCB Each 55.00 137.50
15 Fitting, fixing of Ebonite Sheet cover, Nos. 9.00 22.50 The Fixture installed
Plastic Sheet cover for switch board, Complete in all respect
Junction Boxes etc. including leveling as including consumable
materials shall be considered
per direction of Engineer-in-charge.
as one unit.

16 Fitting fixing and installation of Set 500.00 1,250.00 The actual top surface area of
SDB/EDB boxes of 18 SWG sheet metal the boxes shall be the basis of
enclosed hammer painted with hinged measurement
front cover with required nuts, bolts etc.
having knockout for conduits / cables
entry and exit (bottom / Top as required
for 415/240 Volts TP & N/SP & N
operations. The box should have solid
natural link. Each box should have one
copper earthling block of required
numbers of required dia. Drilled holes for
accommodating the terminal of ECC
with copper 1ug (where applicable).
Including required numbers of brass nuts
bolts etc. complete as per direction of
Engineer-in-Charge

17 Main earthing of building with G.I. Pipe Rft. 22.00 55.00 The Fixture installed
including boring up to max. 100'-0" laying Complete in all respect
of copper wire, making inspection pit etc. including consumable
materials shall be considered
all complete as per direction Engineer-in- as one unit.
charge.

Inspection pit construction ('-0''X1'- Each 300.00 750.00


0''X1'-0'') with brick & CC works
plastering the pit and making RCC slab
for covering the inspection Pit all
complete as per direction Engineer-in-
charge.
18 Fitting fixing of incandescent light, spot Nos. 35.00 87.50 The Fixture installed
light fittings on different mountings Complete in all respect
including lamp, holder etc. all complete including consumable
materials shall be considered
similar to crescent/showash model, wall as one unit.
bracket, soccer and fancy light shade,
security light as per direction of the
Engineer-in-Charge

Chandelier light Nos. 100.00 250.00


19 Tube light of any size fitting fixing - The Fixture installed
including necessary connections with wire, Complete in all respect
ballast, starter etc. all complete as per including consumable
materials shall be considered
direction of Engineer-in-Charge as one unit.

a) Single Set 40.00 100.00


b) Double Set 50.00 125.00
20 Parking light, Round Tube light fitting Set 40.00 100.00 The Fixture installed
fixing including necessary connections with Complete in all respect
wire, ballast, starter etc. all complete as per including consumable
materials shall be considered
Engineer-in-Charge as one unit.

21 Gate light, Logo light, Garden Light fitting Set 85.00 212.50 The Fixture installed
with necessary connection & work as per Complete in all respect
direction of Engineer-in-Charge including consumable
materials shall be considered
as one unit.

22 3-Phase meter fitting, fixing including Nos. 140.00 350.00 The Fixture installed
necessary connection & work as per Complete in all respect
direction of Engineer-in-Charge including consumable
materials shall be considered
as one unit.

23 Single Phase meter fitting, fixing including 100.00 250.00 The Fixture installed
necessary connection & work as per Complete in all respect
Engineer-in-Charge including consumable
materials shall be considered
as one unit.

24 Lighting arrestor with base plate fitting, Set 100.00 250.00 The Fixture installed
fixing with necessary connection complete Complete in all respect
as per Engineer-in-Charge including consumable
materials shall be considered
as one unit.

25 Wooden board fitting of any size, all Nos. 25.00 62.50 The Fixture installed
complete Complete in all respect
including consumable
materials shall be considered
as one unit.

26 Fitting fixing of Fire Extinguisher of any Nos. 45.00 112.50 The Fixture installed
capacity etc complete Complete in all respect
including consumable
materials shall be considered
as one unit.

27 Ceiling rose fitting Nos. 8.00 20.00 The Fixture installed


Complete in all respect
Batten holder fitting Nos. 8.00 20.00 including consumable
materials
linear shall beofconsidered
28 Fitting fixing of PVC channel in surface of - The length the
following size through brick wall, RCC Channel will be the basis of
slab, column including circular box, measurement for payment
junction boxes including all other acce. as
per Engineer-in-Charge

a) 1/2" dia PVC Channel Rft. 1.40 3.50


b) 3/4" dia PVC Channel Rft. 1.80 4.50
c) 1" dia PVC Channel Rft. 1.90 4.75
28 d) 1.25" dia PVC Channel Rft. 2.00 5.00
e) 1.5" dia PVC Channel Rft. 2.10 5.25
f) 2" dia PVC Channel Rft. 2.40 6.00
29 Hole cutting of any size for fitting any - For Each hole cutting
sanitary fittings including mending good Complete in all respect shall
the damages etc. complete as per direction be considered as one unit
of the Engineer. All cutting equipment and
accessories supplied by the labor-
contractor.

a) Below 4'' thick RCC slab Each 30.00 75.00


b)    4” to 7.5” thick RCC slab Each 40.00 100.00
c)      7.5” above to 10” thick RCC slab Each 60.00 150.00
d)      5” Brick wall Each 20.00 50.00
e)      10” Brick wall Each 35.00 87.50
f)      15” Brick wall Each 45.00 112.50
30 MK Box removing Each 5.00 12.50 Actual number should be Only for
counted Modification
works
31 PVC Cable removing Rft 0.50 1.25 Actual length should be
measured
32 PVC pipe removing Rft 0.65 1.63 Actual length should be
measured
33 Fitting, fixing of Expanded metal with Sft 8.00 20.00 Actual Area should be
supply of nails, GI wire etc. including measured
mending good the damages etc. complete as
per direction of Engineer-in-charge.

34 Fitting, fixing of cable lugs with PIB tape in - Actual number should be
proper position etc. all complete as per counted
drawing & direction of Engineer-in-charge

i) 2.5 rm to 16 rm Each 6.00 15.00


ii) 25 rm to 150 rm Each 35.00 87.50
iii) 185 rm to 300 rm Each 60.00 150.00
35 Fitting and fixing of Changeover Each 800.00 2,000.00 Actual number should be New
counted
switch Panel board with all connections
as per direction of Engineer-in-charge.

36 Supply of Electrician Each 250.00 700.00 The actual no. of persons


shall be counted
37 Supply of Helper Each 150.00 500.00 The actual no. of persons
shall be counted

Note 1) This Rate is Applicable only for 10 Storied Building. For 11- 15th floor the rate will
increase 10% and above 16th floor the rate will increase 20 % on the Labour Rate -
: Present 2020
and the rate of Main line for SDB, TV, Telephone, Internet , Intercom & for Lightning
arrestor of any floor will be applicable of the rate of the floor from which it will be
drawn to the bottom
2)You will pay current market rate if exclude worklist.

3)You will pay 1.5 x times more than as per worklist rate If you make us rework.

4)You will pay 27 taka per square feet as per in-voice or roof Area if you choose out of
working list rate.

5)You Have to pay us daily 600 taka per labour and after 7 days you will give
us full payment with labour charge as much as work has done.
6) This Rate schedule will be applicable for Bashundhara and all up coming project.
Prepared by Forwarded by Approved by
Md. Alamin Head of EME Chief Engineer
Coordinaton, Construction

You might also like