Government of Nepal

National Reconstruction Authority


Central Level Project Implementation Unit (Education)
District Level Project Implementation Unit (Education),Gorkha
Emergency School Reconstruction Project (ESRP), JICA Loan No. : NE-P11
Contract Bills
FINAL INTERIM PAYMENT CERTIFICATE
Period: 15th November 2018 to 14th January 2020
Name of School: Shree Basuki L. S. School Payment Voucher no:
Name of Contractor:Sharma-A.M Joint Venture Date of payment:
Contract Number:ESRP/MOE/CLPIU/074/075-GORKHA-15 Page no of measurement book:
Serial no. of previous payment bills: 7
Voucher no.of previous payment bills:
Date of order for commencement of work: 15th November, 2018
Date of work to be completed: 14th January, 2020
Date of completion of work:
Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Pay
Item Description Unit Quantity % completion Remarks
No. As per Rate Amount Quantity Amount Quantity Amount Quantity Amount
Contract
BILL NO.1 PRELIMINARIES/TEMPORARY WORKS
MOBILIZATION AND DEMOBILIZATION
1 L.S. 1.00 500,000.00 500,000.00 1.00 500,000.00 1.00 500,000.00 0.00 - 100.00%
Mobilization of the construction by constructing temporaty
acomodation
SITE OFFICE forESTABLISHMENT
labours and site staff with required suitable Per
2 facilities and 14.00 25,000.00 350,000.00 14.00 350,000.00 14.00 350,000.00 0.00 - 100.00%
Providing andkeeping
Maintaining the same Site inOffice
good of hygenic
two Roomscondition havingfor Month
entire project completion
total Area INFORMATION
20 sq.m for the time.use Demolition
of Clientofand the Consultant
same and
PROJECT BOARD
3 cleaning the
including office site after completion of the construction activities nos. 1.00 10,000.00 10,000.00 1.00 10,000.00 1.00 10,000.00 0.00 - 100.00%
Providing and chair,
FixingTable, Lockable
of Project file cabinet,board
Information Stationery
with
all complete.
Items (Ink,Text
Paper, [Note: 50% payment shall be made after
approved
SAFETY SIGN in Pen, Pencils
appropriate etc.),
location 1 Computer
including and all 1required
Printer
4 completion
with all of BOARD
necessary mobilization
set up. all and remaining
complete as per 50% after
instruction of nos. 1.00 10,000.00 10,000.00 1.00 10,000.00 1.00 10,000.00 0.00 - 100.00%
fixing accessories
Providing and Fixingas perof perdrawingSign
Safety all complete.
Board with approved Text
completionThe
engineer. of works as
Specification contract]
of computer shall not be less than
and Sinage including
BARRICADING WORKS required fixing accessories as per
5 (19.5" led monitor with Core i5, 7th Generation, 500 gb Hdd, R.m 75.00 2,000.00 150,000.00 70.00 140,000.00 70.00 140,000.00 0.00 - 93.33%
drawing all complete.
Barricading between
8gb ddr 4 ram), Printer the should School
function Academic
at least ofarea and
Printing,
Construction
Scanning andarea
DISMANTLING withOF
Photocopy 1.8ofmCOMPLETELY
A4highsizeCGI Sheet fixed
documents. to Bamboo
DAMAGED
Providing and
6 support frameallallabove
complete sq.m 153.36 5,000.00 766,800.00 144.00 720,000.00 144.00 720,000.00 0.00 - 93.90%
BUILDING
Maintaining itemsason perRental
instruction
Basisoffor Engineer.
entire project
Demolition of existing damaged
completionMATERIALS
SAFETY time. & SITEbuilding SAFETY safely and handover
7 of the reusable L.S. 1.00 100,000.00 100,000.00 1.00 100,000.00 0.99 98,571.43 0.01 1,428.57 100.00%
Providing and materials
Maintaining to the school authority,
Construction Safety storing
Measures themin
to the location
Construction Siteshown
with by theSafety
proper schoolmeasures
and disposing
to person debris
and
RELOCATING OF EXISTING TLC
8 including
work area of transportation
(Helmet, of debris ,cleaning site etc. as per sq.m 85.47 3,000.00 256,410.00 73.08 219,225.00 73.08 219,225.00 0.00 - 85.50%
Relocating ExistingShoes, Temporary First Learning
Aid Kit,Centre Clothing,
(TLC), Glove,
specification
Guardconstruction
Rail for andedge
instruction
protection, of Engineer.
Safety Net, Safety rope, Fall
from
CONSTRUCTION siteOF to other
NEWplace TLCby Demolition and using
8 Protection etc.)
existing materials as required
obtained by the Contract
from demolition Clause GCC 24 and sq.m 36.58 5,000.00 182,900.00 12.95 64,750.00 12.95 64,750.00 0.00 - 35.40%
Construction of new Temporary Learning of TLC to the with
Centre(TLC),
Specification
place decided bydivision
SMC. 1 "GENERAL REQUIREMENT
Locally Available
LAB TEST(WATER materials (CGI Sheet and Bamboo etc.), rate
9 CLAUSE 8(C)". The TEST) number of Safety Materials Personal job 1.00 7,500.00 7,500.00 1.00 7,500.00 1.00 7,500.00 0.00 - 100.00%
shall include
Testing all Materials
andEquipments
Providing Lab with
Test fixing
Report charge.
for Quality
Protecting (PPE) shall be minimum butof notWater
limited in
Water
TEMPORARY Stream
to 35 sets. Payment (Up
TOILET shall beDown
and made streem)
in ProratalocatedBasis for near by
entire
10 Construction site before Starting and after completion of nos. 2 150,000.00 300,000.00 2.00 300,000.00 2.00 300,000.00 0.00 - 100.00%
Construction
duration of project. of temporary toilet with CGI Sheet fixed to
construction
Bamboo work.
support This Testallhas
frame to be done itemstoincluding
mark the Septic
affect
ROAD REPAIR AND and MAINTENANCE necesary
11 pit,
of construction
Pipeline, workPan in water stream. project completion time Km 47.00 50,000.00 2,350,000.00 47.00 2,350,000.00 47.00 2,350,000.00 0.00 - 100.00%
Providing andToilet
Maintaining etc. for
the entire
roads as necessary to avoid
all complete
blockage as per Instruction
by Landslides and Rockfallof Engineer. Rate shall
for regular include
transport of
all Material materials
construction cost withand fixing,
site construction
inspection during charges and
overall
BILL NO. 2&CIVIL
demolition cleaning WORKS- of the BUILDING
same after completion of the
construction period. Rate shall include all Material cost with
SITE CLEARANCE & MOBILIZATION:
1.1 construction activities
demolition charges, all
cleaning,complete.
fixing & construction charges of sq.m 397.77 100.00 39,777.00 390.11 39,011.35 428.77 42,877.00 -38.66 (3,865.65) 98.08%
Clearing and grubbing the site for construction by removing
the samethick
150mm aftertop completion
soil including of bushes,
the construction activities all
EARTHWORK IN EXCAVATION
complete. : small trees, leveling of
1.2 undulated ground, shorting and stacking/storing selected top cu.m 214.70 400.00 85,880.00 217.52 87,009.29 204.53 81,811.89 12.99 5,197.40 101.31%
Excavation in foundations in all type of soils for foundation,
soil for reuse
trenches, footing, in pits
landscaping
etc. to works, disposing unsuitable
EARTH BACK FILLING : the required depth including
materials from
1.3 dewatering site, etc., or all complete means as peretc.drawings, cu.m 121.53 300.00 36,459.00 172.96 51,887.53 109.25 32,775.60 63.71 19,111.93 142.32%
Back fillingbyin manual foundation mechanical
and sides of foundationas with per
specifications and
specifications with instructions
allfrom of the Engineer.
contractor’s ownat machinery and
approved
BOULDER soilSOLING
obtained : the excavation site and stacked
1.4 atequipment's,
site or brought providing
from crossinginoflayer
outside track,not shoring,
exceeding strutting, cu.m 58.84 6,000.00 353,040.00 60.46 362,772.57 52.47 314,818.95 7.99 47,953.62 102.76%
Providing and laying uncoursed hand packed Dry Rubble15 cm
Stone
timbering
thick and buttressing with appropriate materials andsoil, all
soling (compacted
in foundation, thickness)
under floor including
plinthtransportation
with out any of special
such measures
spreading of necessary
in required to retain
line and level, in position the sides of the
dressing stone including fillingsprinkling
interstices water,
withramming,
suitable
foundation
compacting pit and including refilling the excavated material
quarry wastewith mechanical
or stone chips rammers,
or quarry testing, etc., all
sand, watering,
with watering,
complete perramming,
as using drawing, leveling the siteand
specification andinstructions
disposing off of the
the
compacting appropriate mechanical compaction means
surplus/unusable earth to outside the construction premises, etc.
Engineer.
with all contractors materials, handling, placing etc. all
all complete as per drawings, specifications and instructions of
complete as per drawings,
Prepared by contractor Checked specifications
by Consultant, and instruction
DSC of the Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
the Engineer.
Engineer. The complete item including all lead & lift.
Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Pay
Item Description Unit Quantity % completion Remarks
No. As per Rate Amount Quantity Amount Quantity Amount Quantity Amount
Contract
SAND FILLING :
1.5 cu.m 2.49 6,000.00 14,940.00 2.16 12,960.00 2.16 12,960.00 0.00 - 86.75%
Providing and filling sand in soak pit. all complete as per
drawings,
CONCRETE specifications
WORKS and instruction of the Engineer.
2.1.1 cu.m 8.91 14,000.00 124,740.00 9.81 137,352.25 9.81 137,352.25 0.00 - 110.11%
P.C.C (1:3:6)
Providing
P.C.C (1:2:4) and WORKS
laying machine mixed Plain Cement Concrete of
2.1.2 nominal mix cu.m 15.09 16,000.00 241,440.00 13.64 218,240.00 14.46 231,360.00 -0.82 (13,120.00) 90.39%
Providing and1:3:6
laying (1 machine
cement : mixed3 sandPlain: 6 coarse
Cement aggregate
Concrete ) for
of
leveling course
nominal mix 1:2:4 in foundations
cement : and
(1 WORKS 2: sandunder floor ofaggregate
: 4 coarse building,)etc. for
P.C.C. FOR R.C.C.
2.2 in all level
leveling withinbroken
course stone aggregate
foundations under of
andmachine sizeofnot
floor more than
building, etc. cu.m 153.80 18,000.00 2,768,400.00 153.50 2,762,994.11 171.08 3,079,447.11 -17.58 (316,452.99) 99.80%
Providing and laying in position mixed and machine
25 mm
in all of with
level approved
brokenqualitystone including offormwork
aggregate size not more wherever
than
vibrated
SILICA cement
CEMENT concrete of mix
ADMIXTURE 1:1.5:3 (1 cement:1.5 sand: 3
2.3 necessary,
25 mmaggregate)dewatering,
of approved batching,
quality mixing,
including transporting,
formwork placing,
wherever kg 1,538.00 300.00 461,400.00 1,535.00 460,499.02 1710.78 513,234.36 -175.78 (52,735.34) 99.80%
coarse
Providing andcuring,
mixing M20 grade
Silica for
Cement reinforced cement concrete
compacting,
necessary, dewatering, including
batching, leadAdmixture
all mixing, of all
andtransporting,
lift, etc. in structural
complete
placing,
work using
concrete approved
at the rate ofcement
2.50% with byand 20 mmof graded
weight the cement machine
for
STEEL
compacting, REINFORCEMENT
as per drawings, curing, specifications
including allapproved
lead andthe lift,
instructions
etc. all of the
complete
2.4 crushed stone
promoting aggregate of quality inachieving
various Mt. 24.62 115,000.00 2,831,300.00 26.95 3,099,103.06 28.65 3,294,534.85 -1.70 (195,431.79) 109.46%
Providing
Engineer.
as andworkability,
per drawings, fixing in position
specifications
improving
Fe strength,
and500thesteel reinforcement
instructions of
of the
locations
waterproofing and heights
properties,including transportation of concrete to
various
FORM
Engineer. diameter
WORKS confirmingbleeding to relevant prevention,
IS code etc. Silica
in R.C.C.
2.5 site
Cementof placing,
Admixture compaction,
shall befinished
the to required
product line and
of Silica level,
Japan or sq.m 1,089.63 800.00 871,704.00 1,075.98 860,785.12 1070.68 856,541.32 5.30 4,243.80 98.75%
works
Supplying including
and straightening,
laying centering, cutting,
shutteringbending, binding with
protection
superior andandshallcuring,
meet etc. all complete of as various
as per
pattern
drawings,
20 SWG annealed
formworks withand wire
19/12 for the
tying requirements
thick the reinforcement mentioned
bars & in
at steel
each
BRICK
specifications
specification MASONRY themminstructions
of materials WORKSBRICK water
and Workmanship,
proof
of theplyEngineer,
wood
MASONRY
Division – but
4:
junctions (binding
adjustable props for wire
all shall
kinds of not
RCC be works
measured for separately)
foundations,
3.1 WORKS
excludingWorks,
Concrete ( 1 :cost
the 4 c/s of) ONE
Article centering,
2.4 SIDEshuttering,
FAIRFACE and reinforcement, cu.m 53.42 20,000.00 1,068,400.00 - - 0.00 - 0.00
including shear
columns, all waste
walls, and
beams,cutslab,pieces, provision
staircase, lintel, for
sill,adequate
pergola,
Providing
all complete andaslaying first class
per drawings, selected
specifications factory
and pressed
instructions wire
of
numbers
including of spacers,
nails, propping chairs, providing
scaffolding, and supporting
staging, placing cement and
cut Fair Face
the Engineer. brick (machine made brick) one or more brick
7.2.3 mortar
bracing
CLEAR (1:1)
in cover
proper
SILICON blocks
lines to
WATER-REPELENT keep
and level, the bars
sealing in intended
the: joints
COATING with position
heavy sq.m - - - 0.00 - 0.00
thick wall in cement mortar 1:4 (1 cement 4coarse sand) in
at
dutyall brown
levels WORK
all
self complete astape,
per drawings, specifications and
8.1.1 POINTING
,superstructure andadhesive
IN
otherBRICK aligning
MASONARY
specified places to in line and levels
all heights and sq.m - - - 0.00 - 0.00
instructions Ties,
including of the PVCEngineer. Spacer,(Authorized
Providing lapopenings/
length andcutouts/for the
level
BOQ including
Totalexceedingthe cost
of items 3.1.,of7.2.3
single or multi stage self standing
& length
8.1.1: - - - 0.00 - 0.00
bar length
pockets, applying 10 meter
De-shuttering in chemical,shallDe-shuttering
be measured for as
scaffolding,
Replaced soaking
items 3.1, tobricks,and
7.2.3 curing,
8.1.1raking joints, provision
with following items for for
the payment,
approved by except
the Engineer column).etc., complete at all
recesses, openings,
3-6C(S) and Ts(F) toothing etc., all complete as levels as per
per drawing, - - -
0.00
- 0.00
drawing, specifications
specifications and instructions
and instructions of the Engineer.
of the Engineer.
Brick Masonry Works (1:4 c/s) cu.m 18,000.00 - - - 0.00 - 0.00
Cement Plaster Works on Outer Wall (1:6) sq.m 600.00 - - - 0.00 - 0.00
Exterior Weather Coat Paint sq.m 350.00 - - - 0.00 - 0.00
- - - 0.00 - 0.00
BRICK MASONRY WORKS ( 1 : 4 c/s )
3.2 cu.m 53.31 18,000.00 959,580.00 97.07 1,747,335.15 1,727,019.00 1.13 20,316.15 182.09%
Providing and laying first class chimney fired brick one or 95.95
3.3 more
HALFbrick thick WORKS
BRICK wall in cement
( 1 : 4mortar
c/s ) 1:4 (1 cement : 4 coarse sq.m 57.75 1,500.00 86,625.00 21.65 32,481.60 15.20 22,803.75 6.45 9,677.85 37.50%
3.4 sand)
HONEY in COMB
foundation
BRICK up WORKS
to plinth,
(1:3superstructure
c/s) and other cu.m 0.24 9,000.00 2,160.00 0.24 2,160.00 0.24 2,160.00 0.00 - 100.00%
specified places in all heights and level including the cost of
4 DOORS & WINDOWS WORKS
single or multi stage scaffolding, soaking bricks, curing, raking
METAL
4.1 joints, FRAME for recesses, openings, toothing etc., all
provision
4.1.1 complete
Door Frameas per drawing, specifications and instructions of the r.m 89.94 1,100.00 98,934.00 89.94 98,934.00 89.94 98,934.00 0.00 - 100.00%
Engineer.
4.1.2 Window Frame r.m 244.40 1,100.00 268,840.00 223.80 246,180.00 223.80 246,180.00 0.00 - 91.57%
4.2 METAL SHUTTER
4.2.1 WINDOW SHUTTER sq.m 47.66 7,500.00 357,450.00 39.21 294,075.00 47.66 357,450.00 -8.45 (63,375.00) 82.27%
4.3 WOODEN SHUTTER
4.3.1 FLUSH DOOR SHUTTER (32MM) sq.m 34.25 8,000.00 274,000.00 31.03 248,240.00 34.25 274,000.00 -3.22 (25,760.00) 90.60%
4.4 UPVC DOOR
4.4.1 Shutter/Frame sq.m 7.14 9,000.00 64,260.00 7.14 64,260.00 7.14 64,260.00 0.00 - 100.00%
4.5 WINDOW GRILL sq.m 28.73 2,500.00 71,825.00 46.00 115,000.00 25.61 64,025.00 20.39 50,975.00 160.11%
4.6 COLLAPSIBLE GATE sq.m 7.55 10,000.00 75,500.00 7.55 75,500.00 7.55 75,500.00 0.00 - 100.00%
5 FLOORING WORKS
5.1 HARDENED CEMENT CONCRETE FLOOR sq.m 476.26 900.00 428,634.00 475.47 427,923.00 424.79 382,308.75 50.68 45,614.25 99.83%
5.2 NEAT CEMENT SKIRTING r.m 226.89 100.00 22,689.00 239.96 23,996.00 227.96 22,796.00 12.00 1,200.00 105.76%
5.3 TERRAZZO CAST-IN SITU DADO sq.m 35.43 1,500.00 53,145.00 35.28 52,920.00 35.28 52,920.00 0.00 - 99.58%
6 ROOFING/TERRACING WORK
6.1 METAL WORKS (TRUSS) kg 3613.44 220.00 794,956.80 4,244.94 933,886.80 4142.34 911,314.80 102.60 22,572.00 117.48%
6.2 CGI SHEET ROOFING sq.m 235.89 2,000.00 471,780.00 239.04 478,080.00 235.89 471,780.00 3.15 6,300.00 101.34%
6.3 CGI SHEET ROOFING RIDGE r.m 24.7 1,200.00 29,640.00 24.85 29,820.00 24.70 29,640.00 0.15 180.00 100.61%
6.4 GI FACIA (EAVES) kg 220.63 250.00 55,157.50 151.97 37,993.75 215.78 53,945.00 -63.81 (15,951.25) 68.88%
6.5 CEMENT BOARD FALSE CEILING sq.m 192.40 1,600.00 307,840.00 198.65 317,846.40 192.39 307,826.24 6.26 10,020.16 103.25%
7 PLASTERING/WALL FINISHING WORK

Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Pay
Item Description Unit Quantity % completion Remarks
No. As per Rate Amount Quantity Amount Quantity Amount Quantity Amount
Contract
7.1 CEMENT PLASTER WORK
7.1.1 ON INNER WALL sq.m 579.24 600.00 347,544.00 586.85 352,108.22 579.23 347,540.93 7.61 4,567.29 101.31%
7.1.2 ON CEILING (1:4) sq.m 176.98 500.00 88,490.00 312.00 156,000.96 176.97 88,486.21 135.03 67,514.75 176.29%
7.1.3 ON OUTER WALL (1:6)
7.1.3.1 EXTERNAL PLASTER sq.m 216.55 600.00 129,930.00 441.40 264,837.99 360.53 216,318.00 80.87 48,519.99 203.83%
7.1.4 EXTERNAL PLASTER WITH CEMENT PUNNING sq.m 35.21 700.00 24,647.00 35.66 24,962.00 35.66 24,962.00 0.00 - 101.28%
7 PAINTING WORKS
7.2.1 DISTEMPER PAINT sq.m 920.30 200.00 184,060.00 1,097.51 219,502.00 986.79 197,358.00 110.72 22,144.00 119.26%
7.2.2 EXTERIOR WEATHER COAT PAINT sq.m 236.95 350.00 82,932.50 441.40 154,490.00 429.46 150,311.00 11.94 4,179.00 186.28%
7.2.3 CLEAR SILICON WATER-REPELLANT COATNG sq.m 253.40 550.00 139,370.00 - - 0.00 - 0.00
7.2.4 ENAMEL PAINT sq.m 230.49 400.00 92,196.00 224.90 89,960.00 221.65 88,660.00 3.25 1,300.00 97.57%
8 MISCELLANEOUS
8.2 CEMENT BOARD WALL sq.m 18.77 6,500.00 122,005.00 18.77 122,005.00 18.76 121,950.07 0.01 54.93 100.00%
8.3 RAILING kg 982.18 220.00 216,079.60 992.98 218,455.60 972.25 213,895.00 20.73 4,560.60 101.10%
8.4 PUMP SHED nos. 1.00 80,000.00 80,000.00 1.00 80,000.00 1.00 80,000.00 0.00 - 100.00%

3 ELECTRICAL WORKS
A. Common Installation
1.1 Stand Alone 40 A DP MCB with Enclosure no. 1.00 12,000.00 12,000.00 1.00 12,000.00 1.00 12,000.00 0.00 - 100.00%
1.2 Stand Alone 6 A DP MCB with Enclosure no. 1.00 8,500.00 8,500.00 1.00 8,500.00 1.00 8,500.00 0.00 - 100.00%
2 CABLES & WIRES
2.1 2 Nos 10 Sq.mm + 1 No 6 Sq.mm mutistranded copper rm 50.00 800.00 40,000.00 52.00 41,600.00 52.00 41,600.00 0.00 - 104.00%
2.2 conductor wires mutistranded copper conductor wires + 1
2 Nos 2.5 Sq.mm rm 50.00 250.00 12,500.00 50.00 12,500.00 12,500.00 0.00 - 100.00%
50.00
B Nos. 1.5sq
School mm multistranded Cu wire
Blocks
1 DISTRIBUTION BOARDS nos.
1.1 Ground Floor nos. 1.00 30,000.00 30,000.00 1.00 30,000.00 1.00 30,000.00 0.00 - 100.00%
1.2 First Floor nos. 1.00 22,000.00 22,000.00 1.00 22,000.00 1.00 22,000.00 0.00 - 100.00%
1.3 Second Floor nos. 1.00 22,000.00 22,000.00 1.00 22,000.00 1.00 22,000.00 0.00 - 100.00%
1.4 Stand Alone 6 A DP MCB with Enclosure nos. 1.00 8,500.00 8,500.00 1.00 8,500.00 1.00 8,500.00 0.00 - 100.00%
2 CABLES & WIRES
2.1 2 Nos 6 Sq mm Multistranded Cu Wire + 1 No 4 Sq mm rm 10.00 600.00 6,000.00 10.00 6,000.00 10.00 6,000.00 0.00 - 100.00%
3 Multistranded Cu wire
General Service Light Point Wiring
3.1 One Way Light Point pts. 46.00 700.00 32,200.00 46.00 32,200.00 46.00 32,200.00 0.00 - 100.00%
3.2 Two Way Light Point pts. 2.00 900.00 1,800.00 2.00 1,800.00 2.00 1,800.00 0.00 - 100.00%
3.3 Ceiling Fan Point pts. 2.00 900.00 1,800.00 2.00 1,800.00 2.00 1,800.00 0.00 - 100.00%
4 6A Universal Pin Light Power Socket Wiring pts. 28.00 700.00 19,600.00 28.00 19,600.00 28.00 19,600.00 0.00 - 100.00%
5 Switch Socket Outlets
5.1 6A Universal Power Switch Socket nos. 28.00 900.00 25,200.00 28.00 25,200.00 28.00 25,200.00 0.00 - 100.00%
6 Sweep Ceiling/Exhaust Fans/ Wall Fan
6.1 225mm dia M/D Exhaust Fan nos. 2.00 6,000.00 12,000.00 2.00 12,000.00 2.00 12,000.00 0.00 - 100.00%
7 Light Fixtures/Luminaires & Accessories
7.1 18 W LED Surface Mounted Square type nos. 16.00 2,700.00 43,200.00 16.00 43,200.00 16.00 43,200.00 0.00 - 100.00%
7.2 18 W LED Recessed Mounted Square type nos. 8.00 2,700.00 21,600.00 8.00 21,600.00 8.00 21,600.00 0.00 - 100.00%
7.3 12 W LED Surface Mounted Cylindrical type nos. 9.00 2,400.00 21,600.00 9.00 21,600.00 9.00 21,600.00 0.00 - 100.00%
7.4 12 W LED Recessed Mounted Circular type nos. 5.00 2,400.00 12,000.00 5.00 12,000.00 5.00 12,000.00 0.00 - 100.00%
7.5 7W LED Wall Light nos. 2.00 1,800.00 3,600.00 2.00 3,600.00 2.00 3,600.00 0.00 - 100.00%
7.6 9W LED Surface Mounted Cylindrical type nos. 1.00 2,000.00 2,000.00 1.00 2,000.00 1.00 2,000.00 0.00 - 100.00%
7.7 6W LED Recessed Mounted Circular type nos. 3.00 1,800.00 5,400.00 3.00 5,400.00 3.00 5,400.00 0.00 - 100.00%
7.8 7W LED T5 Slim Mirror Light nos. 1.00 2,000.00 2,000.00 1.00 2,000.00 1.00 2,000.00 0.00 - 100.00%

Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Pay
Item Description Unit Quantity % completion Remarks
No. As per Rate Amount Quantity Amount Quantity Amount Quantity Amount
Contract
8 Pull Box nos. 3.00 700.00 2,100.00 3.00 2,100.00 3.00 2,100.00 0.00 - 100.00%
9 External Post Top Light Pole nos. 3.00 7,500.00 22,500.00 3.00 22,500.00 3.00 22,500.00 0.00 - 100.00%
10 Post Top External Light Fixtures nos. 3.00 9,800.00 29,400.00 3.00 29,400.00 3.00 29,400.00 0.00 - 100.00%
11 Earthing & Lighting Protection
11.1 Chemical Earthing nos. 3.00 45,000.00 135,000.00 3.00 135,000.00 3.00 135,000.00 0.00 - 100.00%
11.2 Earthing Bar nos. 3.00 2,200.00 6,600.00 3.00 6,600.00 3.00 6,600.00 0.00 - 100.00%
12 Earthing Strip/Wires
12.1 25 x 3 mm GI strip mtr. 65.00 300.00 19,500.00 67.00 20,100.00 65.00 19,500.00 2.00 600.00 103.08%
12.2 12 SWG Cu wire mtr. 15.00 200.00 3,000.00 16.00 3,200.00 15.00 3,000.00 1.00 200.00 106.67%
13 Earth Test link nos. 1.00 1,500.00 1,500.00 1.00 1,500.00 1.00 1,500.00 0.00 - 100.00%
C Solar PV System
1 Solar PV Panel nos. 4.00 26,000.00 104,000.00 4.00 104,000.00 4.00 104,000.00 0.00 - 100.00%
2 Tubular Deep Cycle Battery nos. 2.00 30,000.00 60,000.00 2.00 60,000.00 2.00 60,000.00 0.00 - 100.00%
3 Hybrid Inverter nos. 1.00 100,000.00 100,000.00 1.00 100,000.00 1.00 100,000.00 0.00 - 100.00%

D SANITARY WORKS
1 WATER SUPPLY INSTALLATION
a CPVC pipes SDR-11
40 mm r.m 64.00 1,600.00 102,400.00 55.00 88,000.00 55.00 88,000.00 0.00 - 85.94%
25mm r.m 10.00 1,000.00 10,000.00 9.00 9,000.00 9.00 9,000.00 0.00 - 90.00%
20mm r.m 11.00 700.00 7,700.00 10.00 7,000.00 10.00 7,000.00 0.00 - 90.91%
15mm r.m 5.00 500.00 2,500.00 3.00 1,500.00 3.00 1,500.00 0.00 - 60.00%
c CPVC Ball Valve
40 mm nos. 2.00 2,000.00 4,000.00 2.00 4,000.00 2.00 4,000.00 0.00 - 100.00%
25 mm nos. 3.00 900.00 2,700.00 3.00 2,700.00 3.00 2,700.00 0.00 - 100.00%
20 mm nos. 2.00 400.00 800.00 2.00 800.00 2.00 800.00 0.00 - 100.00%
d 40mm dia Gun Metal Check Valve nos. 1.00 4,500.00 4,500.00 1.00 4,500.00 1.00 4,500.00 0.00 - 100.00%
e Electrical Centrifugal Water Pump nos. 1.00 12,500.00 12,500.00 1.00 12,500.00 1.00 12,500.00 0.00 - 100.00%
f 1000 litres Capacity Water Storage Tank nos. 1.00 34,000.00 34,000.00 1.00 34,000.00 1.00 34,000.00 0.00 - 100.00%
2 Sewer, Rain and Waste Water Installation
110 mm r.m 46.00 1,400.00 64,400.00 32.00 44,800.00 32.00 44,800.00 0.00 - 69.57%
75mm r.m 27.00 1,200.00 32,400.00 25.00 30,000.00 25.00 30,000.00 0.00 - 92.59%
50mm r.m 7.00 350.00 2,450.00 2.00 700.00 2.00 700.00 0.00 - 28.57%
B School Blocks
1 Sanitary Installation
a Water Closet Set set 1.00 34,000.00 34,000.00 1.00 34,000.00 1.00 34,000.00 0.00 - 100.00%
b Orissa Pan set 2.00 3,100.00 6,200.00 2.00 6,200.00 2.00 6,200.00 0.00 - 100.00%
c Hand Wash Basin set 1.00 8,000.00 8,000.00 1.00 8,000.00 1.00 8,000.00 0.00 - 100.00%
d Ladies Urinal set 2.00 11,000.00 22,000.00 2.00 22,000.00 2.00 22,000.00 0.00 - 100.00%
e Self Closing Bib Cock nos. 6.00 4,000.00 24,000.00 6.00 24,000.00 6.00 24,000.00 0.00 - 100.00%
f CP Spreader in Urinal set 2.00 2,500.00 5,000.00 2.00 5,000.00 2.00 5,000.00 0.00 - 100.00%
g Toilet Paper Holder nos. 1.00 2,600.00 2,600.00 1.00 2,600.00 1.00 2,600.00 0.00 - 100.00%
h Commode Spray nos. 1.00 2,000.00 2,000.00 1.00 2,000.00 1.00 2,000.00 0.00 - 100.00%
i PVC Multi Floor Trap nos. 5.00 600.00 3,000.00 5.00 3,000.00 5.00 3,000.00 0.00 - 100.00%
j Waste Coupling and PVC Bottle Trap nos. 2.00 1,500.00 3,000.00 2.00 3,000.00 2.00 3,000.00 0.00 - 100.00%
k 40mm SS Grab Bar-Side nos. 1.00 4,500.00 4,500.00 1.00 4,500.00 1.00 4,500.00 0.00 - 100.00%
l 40mm SS Grab Bar-Rear nos. 1.00 4,500.00 4,500.00 1.00 4,500.00 1.00 4,500.00 0.00 - 100.00%
m CP Foldable Hinge nos. 2.00 5,500.00 11,000.00 2.00 11,000.00 2.00 11,000.00 0.00 - 100.00%

Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Pay
Item Description Unit Quantity % completion Remarks
No. As per Rate Amount Quantity Amount Quantity Amount Quantity Amount
Contract
B CIVIL WORKS : SITE DEVELOPMENT
1 EARTHWORKS
1.1 SITE CLEARANCE AND MOBILIZATION Sq.m 189.83 100.00 18,983.00 175.08 17,507.50 175.08 17,507.50 0.00 - 92.23%
1.2 EARTHWORK IN EXCAVATION Cu.m 109.16 400.00 43,664.00 34.22 13,688.00 34.15 13,660.00 0.07 28.00 31.35%
1.3 EARTHBACK FILLING Cu.m 7.46 300.00 2,238.00 4.60 1,379.85 - 4.60 1,379.85 61.66%
1.4 BOULDER SOLING Cu.m 18.42 6,000.00 110,520.00 18.22 109,320.00 18.16 108,960.00 0.06 360.00 98.91%
2 CONCRETE WORKS
2.1 P.C.C
2.1.1 P.C.C (1:3:6) Cu.m 0.54 14,000.00 7,560.00 0.55 7,700.00 0.55 7,700.00 0.00 - 101.85%
2.1.2 P.C.C (1:2:4) Cu.m 10.35 16,000.00 165,600.00 14.25 228,000.00 14.25 228,000.00 0.00 - 137.68%
2.2 P.C.C FOR R.C.C WORK Cu.m 0.99 20,000.00 19,800.00 0.99 19,800.00 0.99 19,800.00 0.00 - 100.00%
2.3 SILICA CEMENT ADMIXTURE Kg 9.90 300.00 2,970.00 9.90 2,970.00 9.90 2,970.00 0.00 - 100.00%
2.4 STEEL REINFORCEMENT Mt. 0.10 130,000.00 13,000.00 0.11 13,897.00 0.10 12,902.51 0.01 994.49 106.90%
2.5 FORM WORKS Sq.m 9.12 800.00 7,296.00 11.33 9,064.00 9.12 7,296.00 2.21 1,768.00 124.23%
3 BRICKS MASONRY WORKS
3.2 BRICKS MASONRY WORKS (1:4 c/s) Cu.m 0.22 18,000.00 3,960.00 0.53 9,540.00 0.53 9,540.00 0.00 - 240.91%
4 FLOORING WORKS
4.1 NEAT CEMENT SKIRTING r.m 4.72 100.00 472.00 4.72 472.00 4.72 472.00 0.00 - 100.00%
5 METAL WORKS
5.1 METAL WORKS FOR FENCE k.g 1788.66 220.00 393,505.20 1,101.74 242,382.80 884.12 194,506.40 217.62 47,876.40 61.60%
5.2 METAL WORKS FOR GATE k.g 130.78 220.00 28,771.60 123.31 27,128.20 118.89 26,155.80 4.42 972.40 94.29%
5.3 CHAIN LINK FENCE Sq.m 167.21 1,000.00 167,210.00 145.20 145,200.00 138.00 138,000.00 7.20 7,200.00 86.84%
6 PLASTERING WORKS
6.1 PLASTER ON OUTER WALL Sq.m 7.92 600.00 4,752.00 7.80 4,680.00 7.80 4,680.00 0.00 - 98.48%
7 EXTERIOR WEATHER COAT PAINT Sq.m 8.87 350.00 3,104.50 8.28 2,898.00 8.28 2,898.00 0.00 - 93.35%
8 FLAG POLE nos. 2.00 25,000.00 50,000.00 2.00 50,000.00 2.00 50,000.00 0.00 - 100.00%

CIVIL WORKS-RESERVOIR TANK


1 EARTH WORK
1.1 SITE CLEARANCE AND MOBILIZATION sq.m 22.31 100.00 2,231.00 22.31 2,231.00 22.31 2,231.00 0.00 - 100.00%
1.2 EARTHWORK IN EXCAVATION cu.m 24.58 400.00 9,832.00 24.57 9,828.72 24.57 9,828.72 0.00 - 99.97%
1.3 EARTH BACK FILLING cu.m 4.02 300.00 1,206.00 4.01 1,202.85 4.01 1,202.85 0.00 - 99.74%
1.4 BOULDER SOLING cu.m 2.08 6,000.00 12,480.00 2.08 12,462.00 2.08 12,462.00 0.00 - 99.86%
2 CONCRETE WORKS
2.1 P.C.C (1:3:6) cu.m 0.78 14,000.00 10,920.00 0.78 10,904.25 0.78 10,904.25 0.00 - 99.86%
2.2 P.C.C FOR R.C.C WORKS cu.m 7.42 20,000.00 148,400.00 7.41 148,295.00 7.41 148,295.00 0.00 - 99.93%
2.3 SILICA CEMENT ADMIXTURE kg 74.2 300.00 22,260.00 74.15 22,244.25 74.15 22,244.25 0.00 - 99.93%
2.4 STEEL REINFORCEMENT Mt 1.46 130,000.00 189,800.00 1.58 204,902.61 1.56 203,018.63 0.01 1,883.98 107.96%
2.5 FORMWORKS sq.m 54.93 800.00 43,944.00 56.46 45,170.80 56.46 45,170.80 0.00 - 102.79%
3 PLASTERING/WALL FINISHING WORKS
3.1.1 INTERNAL PLASTER ON WALL (1:4) WITH CEMENT PU sq.m 33.66 700.00 23,562.00 35.46 24,824.45 32.56 22,792.00 2.90 2,032.45 105.36%
4 WATERPROOFING WORKS sq.m 33.66 550.00 18,513.00 35.46 19,504.93 32.56 17,908.00 2.90 1,596.93 105.36%

FURNITURE WORKS lot 1 3,000,000.00 3,000,000.00 1.00 3,000,000.00 1.00 3,000,000.00 0.00 - 100.00%
Total 25,597,164.70 25,401,040.97 25,623,209.21 - 222,168.24

Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block, 3-6C(S)-B, T(S)F
School Name : Shree Basuki Lower Secondary School
Location : Aruarbang, Gorkha
Abstract of Cost
Pay Type Design
Quantity in
Item Description of Works Unit Rate (NRs.) Total Qty Amount (NRs) Remarks
BOQ Site
No. 3-6C(S) Ts(F) Water Tank
Development
BILL NO.1 PRELIMINARIES/TEMPORARY WORKS
1 MOBILIZATION AND DEMOBILIZATION L.S. 1.00 500,000.00 1.00 500,000.00
2 SITE OFFICE ESTABLISHMENT Per Month 14.00 25,000.00 14.00 350,000.00
3 PROJECT INFORMATION BOARD nos. 1.00 10,000.00 1.00 10,000.00
4 SAFETY SIGN BOARD nos. 1.00 10,000.00 1.00 10,000.00
5 BARRICADING WORKS R.m 75.00 2,000.00 70.00 140,000.00
6 DISMANTLING OF COMPLETELY DAMAGED BUILDING sq.m 153.36 5,000.00 144.00 720,000.00
7 SAFETY MATERIALS & SITE SAFETY L.S. 1.00 100,000.00 1.00 100,000.00
8 RELOCATING OF EXISTING TLC sq.m 85.47 3,000.00 73.08 219,225.00
8 CONSTRUCTION OF NEW TLC sq.m 36.58 5,000.00 12.95 64,750.00
9 LAB TEST(WATER TEST) job 1.00 7,500.00 1.00 7,500.00
10 TEMPORARY TOILET nos. 2 150,000.00 2.00 300,000.00
11 ROAD REPAIR AND MAINTENANCE Km 47.00 50,000.00 47.00 2,350,000.00

BILL NO. 2 CIVIL WORKS- BUILDING


1.1 SITE CLEARANCE & MOBILIZATION: sq.m 397.77 100.00 306.20 83.91 390.11 39,011.35
1.2 EARTHWORK IN EXCAVATION : cu.m 214.70 400.00 146.33 71.19 217.52 87,009.29
1.3 EARTH BACK FILLING : cu.m 121.53 300.00 109.75 63.21 172.96 51,887.53
1.4 BOULDER SOLING : cu.m 58.84 6,000.00 45.99 14.48 60.46 362,772.57
1.5 SAND FILLING : cu.m 2.49 6,000.00 2.16 2.16 12,960.00
CONCRETE WORKS
2.1.1 P.C.C (1:3:6) cu.m 8.91 14,000.00 7.32 2.49 9.81 137,352.25
2.1.2 P.C.C (1:2:4) WORKS cu.m 15.09 16,000.00 13.08 0.56 13.64 218,240.00
2.2 P.C.C. FOR R.C.C. WORKS : cu.m 153.80 18,000.00 137.04 16.46 153.50 2,762,994.11
2.3 SILICA CEMENT ADMIXTURE kg 1,538.00 300.00 1,370.37 164.63 1,535.00 460,499.02
2.4 STEEL REINFORCEMENT Mt. 24.62 115,000.00 24.82 2.13 26.95 3,099,103.06
2.5 FORM WORKS sq.m 1,089.63 800.00 947.85 128.13 1,075.98 860,785.12
3.1 BRICK MASONRY WORKSBRICK MASONRY WORKS ( 1 : 4 c/s ) ONE SIDE cu.m 53.42 20,000.00
7.2.3 FAIRFACE
CLEAR SILICON WATER-REPELENT COATING sq.m
8.1.1 POINTING WORK IN BRICK MASONARY sq.m
BOQ Total of items 3.1., 7.2.3 & 8.1.1:
Replaced items 3.1, 7.2.3 and 8.1.1 with following items for 3-6C(S) and Ts(F)
Brick Masonry Works (1:4 c/s) cu.m 18,000.00
Cement Plaster Works on Outer Wall (1:6) sq.m 600.00
Exterior Weather Coat Paint sq.m 350.00

3.2 BRICK MASONRY WORKS ( 1 : 4 c/s ) cu.m 53.31 18,000.00 72.19 24.88 97.07 1,747,335.15
3.3 HALF BRICK WORKS ( 1 : 4 c/s ) sq.m 57.75 1,500.00 11.04 10.61 21.65 32,481.60
3.4 HONEY COMB BRICK WORKS (1:3 c/s) cu.m 0.24 9,000.00 0.24 0.24 2,160.00
4 DOORS & WINDOWS WORKS
4.1 METAL FRAME
4.1.1 Door Frame r.m 89.94 1,100.00 89.94 89.94 98,934.00
4.1.2 Window Frame r.m 244.40 1,100.00 223.80 223.80 246,180.00
4.2 METAL SHUTTER
4.2.1 WINDOW SHUTTER sq.m 47.66 7,500.00 39.21 39.21 294,075.00
4.3 WOODEN SHUTTER
4.3.1 FLUSH DOOR SHUTTER (32MM) sq.m 34.25 8,000.00 31.03 31.03 248,240.00
4.4 UPVC DOOR
4.4.1 Shutter/Frame sq.m 7.14 9,000.00 7.14 7.14 64,260.00
4.5 WINDOW GRILL sq.m 28.73 2,500.00 39.77 6.23 46.00 115,000.00
4.6 COLLAPSIBLE GATE sq.m 7.55 10,000.00 7.55 7.55 75,500.00
5 FLOORING WORKS
5.1 HARDENED CEMENT CONCRETE FLOOR sq.m 476.26 900.00 433.94 41.53 475.47 427,923.00
5.2 NEAT CEMENT SKIRTING r.m 226.89 100.00 228.46 11.50 239.96 23,996.00
5.3 TERRAZZO CAST-IN SITU DADO sq.m 35.43 1,500.00 2.40 32.88 35.28 52,920.00
6 ROOFING/TERRACING WORK
6.1 METAL WORKS (TRUSS) kg 3613.44 220.00 3,545.29 699.65 4,244.94 933,886.80
6.2 CGI SHEET ROOFING sq.m 235.89 2,000.00 205.50 33.54 239.04 478,080.00
6.3 CGI SHEET ROOFING RIDGE r.m 24.7 1,200.00 17.90 6.95 24.85 29,820.00
6.4 GI FACIA (EAVES) kg 220.63 250.00 143.91 8.06 151.97 37,993.75
6.5 CEMENT BOARD FALSE CEILING sq.m 192.40 1,600.00 174.90 23.75 198.65 317,846.40
7 PLASTERING/WALL FINISHING WORK
7.1 CEMENT PLASTER WORK
7.1.1 ON INNER WALL sq.m 579.24 600.00 534.33 52.52 586.85 352,108.22
7.1.2 ON CEILING (1:4) sq.m 176.98 500.00 288.40 23.60 312.00 156,000.96
7.1.3 ON OUTER WALL (1:6)
7.1.3.1 EXTERNAL PLASTER sq.m 216.55 600.00 372.47 68.93 441.40 264,837.99
7.1.4 EXTERNAL PLASTER WITH CEMENT PUNNING sq.m 35.21 700.00 35.66 35.66 24,962.00
7 PAINTING WORKS
7.2.1 DISTEMPER PAINT sq.m 920.30 200.00 997.64 99.87 1,097.51 219,502.00
7.2.2 EXTERIOR WEATHER COAT PAINT sq.m 236.95 350.00 372.47 68.93 441.40 154,490.00
7.2.3 CLEAR SILICON WATER-REPELLANT COATNG sq.m 253.40 550.00
7.2.4 ENAMEL PAINT sq.m 230.49 400.00 218.67 6.23 224.90 89,960.00
8 MISCELLANEOUS
8.2 CEMENT BOARD WALL sq.m 18.77 6,500.00 15.39 3.38 18.77 122,005.00
8.3 RAILING kg 982.18 220.00 992.98 992.98 218,455.60
8.4 PUMP SHED nos. 1.00 80,000.00 1.00 1.00 80,000.00

3 ELECTRICAL WORKS
A. Common Installation
1.1 Stand Alone 40 A DP MCB with Enclosure no. 1.00 12,000.00 1.00 1.00 12,000.00
1.2 Stand Alone 6 A DP MCB with Enclosure no. 1.00 8,500.00 1.00 1.00 8,500.00
2 CABLES & WIRES - -
2.1 2 Nos 10 Sq.mm + 1 No 6 Sq.mm mutistranded copper conductor wires rm 50.00 800.00 52.00 52.00 41,600.00
2 Nos 2.5 Sq.mm mutistranded copper conductor wires + 1 Nos. 1.5sq mm multistranded
2.2 Cu wire rm 50.00 250.00 50.00 50.00 12,500.00
B School Blocks
1 DISTRIBUTION BOARDS nos.
1.1 Ground Floor nos. 1.00 30,000.00 1.00 1.00 30,000.00
1.2 First Floor nos. 1.00 22,000.00 1.00 1.00 22,000.00
1.3 Second Floor nos. 1.00 22,000.00 1.00 1.00 22,000.00
1.4 Stand Alone 6 A DP MCB with Enclosure nos. 1.00 8,500.00 1.00 1.00 8,500.00
2 CABLES & WIRES
2.1 2 Nos 6 Sq mm Multistranded Cu Wire + 1 No 4 Sq mm Multistranded Cu wire rm 10.00 600.00 10.00 10.00 6,000.00
3 General Service Light Point Wiring
3.1 One Way Light Point pts. 46.00 700.00 41.00 5.00 46.00 32,200.00
3.2 Two Way Light Point pts. 2.00 900.00 2.00 2.00 1,800.00
3.3 Ceiling Fan Point pts. 2.00 900.00 2.00 2.00 1,800.00
4 6A Universal Pin Light Power Socket Wiring pts. 28.00 700.00 28.00 28.00 19,600.00
5 Switch Socket Outlets
5.1 6A Universal Power Switch Socket nos. 28.00 900.00 28.00 28.00 25,200.00
6 Sweep Ceiling/Exhaust Fans/ Wall Fan
6.1 225mm dia M/D Exhaust Fan nos. 2.00 6,000.00 2.00 2.00 12,000.00
7 Light Fixtures/Luminaires & Accessories
7.1 18 W LED Surface Mounted Square type nos. 16.00 2,700.00 16.00 16.00 43,200.00
7.2 18 W LED Recessed Mounted Square type nos. 8.00 2,700.00 8.00 8.00 21,600.00
7.3 12 W LED Surface Mounted Cylindrical type nos. 9.00 2,400.00 9.00 9.00 21,600.00
7.4 12 W LED Recessed Mounted Circular type nos. 5.00 2,400.00 5.00 5.00 12,000.00
7.5 7W LED Wall Light nos. 2.00 1,800.00 1.00 1.00 2.00 3,600.00
7.6 9W LED Surface Mounted Cylindrical type nos. 1.00 2,000.00 1.00 1.00 2,000.00

Prepared and Submitted By: Checked By: Approved By:


DLPIU Engineer
Sharma-AM J/V Consultant Engineer
Pay Type Design
Quantity in
Item Description of Works Unit Rate (NRs.) Total Qty Amount (NRs) Remarks
BOQ Site
No. 3-6C(S) Ts(F) Water Tank
Development
7.7 6W LED Recessed Mounted Circular type nos. 3.00 1,800.00 3.00 3.00 5,400.00
7.8 7W LED T5 Slim Mirror Light nos. 1.00 2,000.00 1.00 1.00 2,000.00
8 Pull Box nos. 3.00 700.00 3.00 3.00 2,100.00
9 External Post Top Light Pole nos. 3.00 7,500.00 3.00 3.00 22,500.00
10 Post Top External Light Fixtures nos. 3.00 9,800.00 3.00 3.00 29,400.00
11 Earthing & Lighting Protection
11.1 Chemical Earthing nos. 3.00 45,000.00 3.00 3.00 135,000.00
11.2 Earthing Bar nos. 3.00 2,200.00 3.00 3.00 6,600.00
12 Earthing Strip/Wires
12.1 25 x 3 mm GI strip mtr. 65.00 300.00 67.00 67.00 20,100.00
12.2 12 SWG Cu wire mtr. 15.00 200.00 16.00 16.00 3,200.00
13 Earth Test link nos. 1.00 1,500.00 1.00 1.00 1,500.00
C Solar PV System
1 Solar PV Panel nos. 4.00 26,000.00 4.00 4.00 104,000.00
2 Tubular Deep Cycle Battery nos. 2.00 30,000.00 2.00 2.00 60,000.00
3 Hybrid Inverter 1.00 100,000.00 1.00 1.00 100,000.00

D SANITARY WORKS
1 WATER SUPPLY INSTALLATION
a CPVC pipes SDR-11
40 mm r.m 64.00 1,600.00 55.00 55.00 88,000.00
25mm r.m 10.00 1,000.00 9.00 9.00 9,000.00
20mm r.m 11.00 700.00 10.00 10.00 7,000.00
15mm r.m 5.00 500.00 3.00 3.00 1,500.00
c CPVC Ball Valve
40 mm nos. 2.00 2,000.00 2.00 2.00 4,000.00
25 mm nos. 3.00 900.00 3.00 3.00 2,700.00
20 mm nos. 2.00 400.00 2.00 2.00 800.00
d 40mm dia Gun Metal Check Valve nos. 1.00 4,500.00 1.00 1.00 4,500.00
e Electrical Centrifugal Water Pump nos. 1.00 12,500.00 1.00 1.00 12,500.00
f 1000 litres Capacity Water Storage Tank nos. 1.00 34,000.00 1.00 1.00 34,000.00
2 Sewer, Rain and Waste Water Installation
110 mm r.m 46.00 1,400.00 32.00 32.00 44,800.00
75mm r.m 27.00 1,200.00 25.00 25.00 30,000.00
50mm r.m 7.00 350.00 2.00 2.00 700.00
B School Blocks
1 Sanitary Installation
a Water Closet Set set 1.00 34,000.00 1.00 1.00 34,000.00
b Orissa Pan set 2.00 3,100.00 2.00 2.00 6,200.00
c Hand Wash Basin set 1.00 8,000.00 1.00 1.00 8,000.00
d Ladies Urinal set 2.00 11,000.00 2.00 2.00 22,000.00
e Self Closing Bib Cock nos. 6.00 4,000.00 6.00 6.00 24,000.00
f CP Spreader in Urinal set 2.00 2,500.00 2.00 2.00 5,000.00
g Toilet Paper Holder nos. 1.00 2,600.00 1.00 1.00 2,600.00
h Commode Spray nos. 1.00 2,000.00 1.00 1.00 2,000.00
i PVC Multi Floor Trap nos. 5.00 600.00 5.00 5.00 3,000.00
j Waste Coupling and PVC Bottle Trap nos. 2.00 1,500.00 2.00 2.00 3,000.00
k 40mm SS Grab Bar-Side nos. 1.00 4,500.00 1.00 1.00 4,500.00
l 40mm SS Grab Bar-Rear nos. 1.00 4,500.00 1.00 1.00 4,500.00
m CP Foldable Hinge nos. 2.00 5,500.00 2.00 2.00 11,000.00

B CIVIL WORKS : SITE DEVELOPMENT


1 EARTHWORKS
1.1 SITE CLEARANCE AND MOBILIZATION Sq.m 189.83 100.00 175.08 175.08 17,507.50
1.2 EARTHWORK IN EXCAVATION Cu.m 109.16 400.00 34.22 34.22 13,688.00
1.3 EARTHBACK FILLING Cu.m 7.46 300.00 4.60 4.60 1,379.85
1.4 BOULDER SOLING Cu.m 18.42 6,000.00 18.22 18.22 109,320.00
2 CONCRETE WORKS
2.1 P.C.C
2.1.1 P.C.C (1:3:6) Cu.m 0.54 14,000.00 0.55 0.55 7,700.00
2.1.2 P.C.C (1:2:4) Cu.m 10.35 16,000.00 14.25 14.25 228,000.00
2.2 P.C.C FOR R.C.C WORK Cu.m 0.99 20,000.00 0.99 0.99 19,800.00
2.3 SILICA CEMENT ADMIXTURE Kg 9.90 300.00 9.90 9.90 2,970.00
2.4 STEEL REINFORCEMENT Mt. 0.10 130,000.00 0.11 0.11 13,897.00
2.5 FORM WORKS Sq.m 9.12 800.00 11.33 11.33 9,064.00
3 BRICKS MASONRY WORKS
3.2 BRICKS MASONRY WORKS (1:4 c/s) Cu.m 0.22 18,000.00 0.53 0.53 9,540.00
4 FLOORING WORKS
4.1 NEAT CEMENT SKIRTING r.m 4.72 100.00 4.72 4.72 472.00
5 METAL WORKS
5.1 METAL WORKS FOR FENCE k.g 1788.66 220.00 1,101.74 1,101.74 242,382.80
5.2 METAL WORKS FOR GATE k.g 130.78 220.00 123.31 123.31 27,128.20
5.3 CHAIN LINK FENCE Sq.m 167.21 1,000.00 145.20 145.20 145,200.00
6 PLASTERING WORKS
6.1 PLASTER ON OUTER WALL Sq.m 7.92 600.00 7.80 7.80 4,680.00
7 EXTERIOR WEATHER COAT PAINT Sq.m 8.87 350.00 8.28 8.28 2,898.00
8 FLAG POLE nos. 2.00 25,000.00 2.00 2.00 50,000.00

CIVIL WORKS-RESERVOIR TANK


1 EARTH WORK
1.1 SITE CLEARANCE AND MOBILIZATION sq.m 22.31 100.00 22.31 22.31 2,231.00
1.2 EARTHWORK IN EXCAVATION cu.m 24.58 400.00 24.57 24.57 9,828.72
1.3 EARTH BACK FILLING cu.m 4.02 300.00 4.01 4.01 1,202.85
1.4 BOULDER SOLING cu.m 2.08 6,000.00 2.08 2.08 12,462.00
2 CONCRETE WORKS
2.1 P.C.C (1:3:6) cu.m 0.78 14,000.00 0.78 0.78 10,904.25
2.2 P.C.C FOR R.C.C WORKS cu.m 7.42 20,000.00 7.41 7.41 148,295.00
2.3 SILICA CEMENT ADMIXTURE kg 74.2 300.00 74.15 74.15 22,244.25
2.4 STEEL REINFORCEMENT Mt 1.46 130,000.00 1.58 1.58 204,902.61
2.5 FORMWORKS sq.m 54.93 800.00 56.46 56.46 45,170.80
3 PLASTERING/WALL FINISHING WORKS
3.1.1 INTERNAL PLASTER ON WALL (1:4) WITH CEMENT PUNNING sq.m 33.66 700.00 35.46 35.46 24,824.45
4 WATERPROOFING WORKS sq.m 33.66 550.00 35.46 35.46 19,504.93

FURNITURE WORKS lot 1 3,000,000.00 1.00 1.00 3,000,000.00


Total 25,401,040.97

Prepared and Submitted By: Checked By: Approved By:


DLPIU Engineer
Sharma-AM J/V Consultant Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
School Name : Shree Basuki Lower Secondary School
Location : Aaruarbang, Gorkha

Length Breadth Height


S.No Description No. Qty. Unit Remarks
(m) (m) (m)
1 Mobilization and Demobilization 1 1 L.S.

2 Site Office Establishment 14 14 Per month

3 Project Information Board 1 1 No.

4 Safety Sign Board 1 1 No.

5 Barricading Works 1 70 70 Rm

Dismantling of completely damaged


6
building
Building 1 1 144.00 sq.m

7 Safety materials and site safety L.S

8 Relocating of existing TLC 1 73.08 sq.m

9 Construction of new TLC


Building 1 ( 5 Class room) 1 12.95 sq.m

11 Construction of Temporary Toilet 2 2 Nos.

12 Road Repair and maintenance 1 47 47 km

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-6C(S)-B
School Name : Shree Basuki Lower Secondary School
Location : Aaruarbang, Gorkha

Breadth Height
S.No Description No. Length (m) Qty. Unit Remarks
(m) (m)
1 Earthworks
1.1 Site Clearance and Mobilization 1 21.95 13.95 306.20
Total 306.20 Sq.m

1.2 Earthwork in excavation


For Footing
Grid 1
Footing (F2) 2 2.50 2.50 1.50 18.75
Footing (F3) 2 2.80 2.80 1.50 23.52
Grid 2
Footing (F3) 2 2.80 2.80 1.50 23.52
Footing (F4) 2 3.10 3.10 1.50 28.83
Grid 3
Footing (F1) 4 1.80 1.80 1.50 19.44
Excavation for lower tie beam
Grid 1 1 7.40 0.60 0.90 4.00
Grid 2 1 6.50 0.50 0.90 2.93
Grid 3 1 10.10 0.60 0.90 5.45
Grid A & Grid D 2 3.55 0.60 0.90 3.83
Grid B 1 3.10 0.60 0.90 1.67
Grid C 1 3.10 0.50 0.90 1.40
Front Steps/Drain 1 10.03 1.50 0.15 2.26
1 10.03 0.60 0.05 0.30
Back Drain 1 15.95 0.98 0.15 2.33
1 15.95 0.60 0.05 0.48
Side Drain 2 6.45 0.98 0.15 1.89
2 6.45 0.60 0.05 0.39
Side Steps 1 2.43 0.75 0.15 0.27
1 2.50 0.75 1.15 2.16
Ramp
For Slope 1 3.50 1.03 0.28 0.99
For Front wall 3-AB 1 6.50 0.55 0.45 1.61
For Side wall -3B 1 1.33 0.55 0.45 0.33
Total 146.33 Cu.m

1.3 Earth Back filling


Excavated earthwork 146.33
Boulder soling -14.65
PCC -7.32
RCC -28.76

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Brick masonry work below plinth tie beam -6.28
Class room 2 5.70 5.70 0.18 11.37
Staircase 1 3.20 5.70 0.18 3.19
Corridoor 1 14.60 2.20 0.18 5.62
Below Ramp 1 1.40 1.30 0.14 0.25
Total 109.75 Cu.m

1.4 Boulder Soling


For Footing
Grid 1
Footing (F2) 2 2.20 2.20 0.20 1.94
Footing (F3) 2 2.50 2.50 0.20 2.50
Grid 2
Footing (F3) 2 2.50 2.50 0.20 2.50
Footing (F4) 2 2.80 2.80 0.20 3.14
Grid 3
Footing (F1) 4 1.50 1.50 0.20 1.80

For Lower Tie Beam


Grid 1,3 2 12.95 0.45 0.10 1.17
Grid 2 1 12.95 0.35 0.10 0.45
Grid A,B,D 3 6.80 0.45 0.10 0.92
Grid C 1 6.80 0.35 0.10 0.24

Building Floors
Classroom
Class Room 2 5.75 5.75 0.20 13.23
Corridor 2 5.75 2.25 0.20 5.18
1 3.25 2.25 0.20 1.46
Below Staircase 1 3.25 5.75 0.20 3.74

Front Steps/Drain 1 10.03 1.50 0.10 1.50


1 10.03 0.60 0.05 0.30
Back Drain 1 15.95 0.98 0.10 1.56
1 15.95 0.60 0.05 0.48
Side Drain 2 6.45 0.98 0.10 1.26
2 6.45 0.60 0.05 0.39
Side Steps 1 2.43 0.60 0.10 0.15
1 2.50 0.60 0.10 0.15

Below ramp
For Slope 1 6.82 1.18 0.20 1.61
For Front wall 3-AB 1 6.50 0.45 0.10 0.29
For Side wall -3B 1 1.33 0.45 0.10 0.06
Total 45.99 Cu.m

2 Concrete Works

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
2.1 PCC
2.1.1 PCC work (1:3:6)
For Footing
Grid 1
Footing (F2) 2 2.20 2.20 0.10 0.97
Footing (F3) 2 2.50 2.50 0.10 1.25
Grid 2
Footing (F3) 2 2.50 2.50 0.10 1.25
Footing (F4) 2 2.80 2.80 0.10 1.57
Grid 3
Footing (F1) 4 1.50 1.50 0.10 0.90

For Lower Tie Beam


Grid 1,3 2 12.95 0.45 0.05 0.58
Grid 2 1 12.95 0.35 0.05 0.23
Grid A,B,D 3 6.80 0.45 0.05 0.46
Grid C 1 6.80 0.35 0.05 0.12
Total 7.32 Cu.m

2.1.2 P.C.C.(1:2:4) Works


Floor Area
Room 2 5.7 5.7 0.075 4.88
Staircase Portion 1 3.2 5.7 0.075 1.37
Verandah 1 14.6 2.2 0.075 2.41
Side Drain
Around Building-Foundation PCC 1 33 0.575 0.075 1.43
Around Building-Top PCC 1 33.4 0.125 0.05 0.21
Apron
Around Building 1 30.4 0.95 0.05 1.45
Steps
Front 1 10.025 0.6 0.05 0.31
Sides 2 1.925 0.6 0.05 0.12
Ramp
Wall- Foundation
1 6.75 0.45 0.05 0.16
1 1.4 0.45 0.05 0.04
Wall-Top
1 6.75 0.125 0.05 0.05
1 1.4 0.25 0.05 0.02
Ramp-Floor 1 6.525 1.275 0.075 0.63
Total 13.08 Cu.m

2.2 PCC for RCC Work 1:1.5:3


For Footing
Footing F1 4.00
Square portion 1.50 1.50 0.20 1.80
Trapezoid portion Area 1.49 0.25 1.49

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Footing F2 2.00
Square portion 2.20 2.20 0.20 1.94
Trapezoid portion Area 2.78 0.25 1.39
Footing F3 4.00
Square portion 2.50 2.50 0.20 5.00
Trapezoid portion Area 3.49 0.25 3.49
Footing F4 2.00
Square portion 2.80 2.80 0.20 3.14
Trapezoid portion Area 4.28 0.25 2.14
Lower Tie Beam
Grid 1,2,3 3.00 14.15 0.25 0.30 3.18
Grid A,B,C,D 4.00 7.60 0.25 0.30 2.28

Column
From lower to plinth tie beam 12.00 0.45 0.45 1.20 2.92
Plinth tie beam
Grid 1,2,3 3.00 14.15 0.30 0.53 6.69
Grid A,B,C,D 4.00 7.60 0.30 0.53 4.79
Ground Floor
For column 12 0.45 0.45 3.00 7.29
G.F Staircase
Landing beam 1 3.05 0.25 0.38 0.29
Landing 1 1 3.20 1.50 0.15 0.72
Landing 2 1 3.20 1.85 0.15 0.89
First flight
Waist Slab 1 3.35 1.50 0.15 0.75
Riser 9 Area 0.02 1.50 0.30
Second Flight
Waist Slab 1 3.40 1.50 0.15 0.77
Riser 10 Area 0.02 1.50 0.34
Staircase gap
Waist Slab 1 1.30 0.20 0.15 0.04
Riser 3 Area 0.02 0.45 0.03
First floor beam
Primary Beam
Grid 1-2-3 3 14.15 0.30 0.53 6.69
Grid A-B-C_D 4 7.60 0.30 0.53 4.79
Secondary Beam
Grid A1-C1 2 7.90 0.25 0.43 1.68
Grid 1a 2 5.45 0.25 0.43 1.16
Grid 1b 1 3.20 0.25 0.43 0.34
F.F. Slab
Class room 8 2.73 2.73 0.13 7.43
Corridoor 4 2.73 2.20 0.13 3.00
1 3.20 2.20 0.13 0.88
Slab between beam 1b & 2B-2C 1 0.49 3.20 0.13 0.20
Staircase top slab 1 0.39 3.20 0.15 0.18

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Lintel Bands, Ground floor level
Along grid A,B,C,D 4 5.55 0.23 0.13 0.64
Along grid 1 1 11.10 0.23 0.13 0.32
Along grid 2 1 11.10 0.23 0.13 0.32
Sill Bands, Ground floor level
Along grid A,B,C,D 4 5.55 0.23 0.08 0.38
Along grid 1 1 11.10 0.23 0.08 0.19
Along grid 2 1 11.10 0.23 0.08 0.19
At store 1 1.30 0.12 0.08 0.01
Vetical Band 4.00 2.48 0.25 0.08 0.19

First Floor
For column 12 0.45 0.45 3.00 7.29
F.F Staircase
Landing beam 1 3.05 0.25 0.38 0.29
Landing 2 1 3.2 1.85 0.15 0.89
First flight
Waist Slab 1 3.35 1.5 0.15 0.75
Riser 9 Area 0.02 1.50 0.30
Second Flight
Waist Slab 1 3.40 1.50 0.15 0.77
Riser 10 Area 0.02 1.50 0.34
Second Floor Beam
Primary Beam
Grid 1-2-3 3 14.15 0.30 0.53 6.69
Grid A-B-C_D 4 7.60 0.30 0.53 4.79
Secondary Beam
Grid A1-C1 2 7.90 0.25 0.43 1.68
Grid 1a 2 5.45 0.25 0.43 1.16
Grid 1b 1 3.20 0.25 0.43 0.34
S.F. Slab
Class room 8 2.73 2.73 0.13 7.43
Corridoor 4 2.73 2.20 0.13 3.00
1 3.20 2.20 0.13 0.88
Slab between beam 1b & 2B-2C 1 0.49 3.20 0.13 0.20
Staircase top slab 1 0.39 3.20 0.15 0.18
Lintel Bands, First floor level
Along grid A,B,C,D 4 5.55 0.23 0.13 0.64
Along grid 1 1 11.10 0.23 0.13 0.32
Along grid 2 1 11.10 0.23 0.13 0.32
Sill Bands, First floor level
Along grid A,B,C,D 4 5.55 0.23 0.08 0.38
Along grid 1 1 11.10 0.23 0.08 0.19
Along grid 2 1 11.10 0.23 0.08 0.19
Vetical Band 4.00 2.48 0.25 0.08 0.19

Second Floor

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
For column 12 0.45 0.45 2.60 6.32
Second Floor Truss Beam
Primary Beam
Grid 1-2-3 3 14.15 0.30 0.40 5.09
Grid A-B-C-D 4 7.60 0.30 0.40 3.65
Lintel Bands, Second floor level
Along grid A,B,C,D 4 5.55 0.23 0.13 0.64
Along grid 1 1 11.10 0.23 0.13 0.32
Along grid 2 1 14.15 0.23 0.13 0.41
Sill Bands, Second floor level
Along grid A,B,C,D 4 5.55 0.23 0.08 0.38
Along grid 1 1 11.10 0.23 0.08 0.19
Along grid 2 1 11.10 0.23 0.08 0.19
Vetical Band 4.00 2.48 0.25 0.08 0.19

Deduction of Doors For Sill


Ground floor level
D1 -4 1.10 0.230 0.08 -0.08
First floor level
D1 -4 1.10 0.230 0.08 -0.08
Second floor level
D1 -4 1.10 0.230 0.08 -0.08

Pedestal in corridor 8 0.50 0.25 0.25 0.25


Bench Slab 2 2.50 0.60 0.08 0.23
Total 137.04 Cu.m

2.3 Silica Admixture


10 Kg per cu.m. of R.C.C. M20 10 137.04 1,370.37
Total 1370.37 kg
2.5 Form Works
For Footing
Footing F1 4 6.00 0.20 4.80
Footing F2 2 8.80 0.20 3.52
Footing F3 4 10.00 0.20 8.00
Footing F4 2 11.20 0.20 4.48
Lower tie beam
Grid 1,2,3 3 14.15 0.60 25.47
Grid A,B,C,D 4 7.60 0.60 18.24
For Column
From lower to plinth tie beam 12 1.80 1.20 25.92
Deduction1 at beam and column junction at -34 0.25 0.30 -2.55
LTB
Deduction1 at beam and column junction at -34 0.30 0.53 -5.36
UTB
For Plinth Tie Beam
Grid 1,2 & 3 3 14.15 1.05 44.57

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Grid A,B,C &D 4 7.60 1.05 31.92
Landing Beam 1 3.20 1.01 3.23
Ground floor
For column 12 1.80 3.00 64.80
Deduction for Beam opening part -34 0.30 0.53 -5.36
Staircase Area
First flight
Waist slab 1 3.35 1.50 5.03
Landing 1 1.94 1.50 2.90
1 1.47 1.70 2.49
Riser 10 1.50 0.15 2.25
Side 2 3.35 0.30 2.01
1 4.00 0.15 0.60
Second flight
Waist slab 1 3.40 1.50 5.10
Riser 10 1.50 0.15 2.25
Side 2 3.40 0.30 2.04
First floor beam
Main beam
Grid 1 (A-B & C-D) 2 5.55 1.23 13.60
Grid 1 (B-C) 1 3.05 1.35 4.12
Grid 2 1 14.15 1.10 15.57
Grid 3 1 14.15 1.23 17.33
Grid A & D 2 7.60 1.23 18.62
Grid B & C (1-2) 2 5.55 1.23 13.60
Grid B & C (2-3) 2 2.05 1.10 4.51
Secondary beam
Grid A1-C1 2 7.65 0.85 13.01
Grid 1a 2 5.70 0.85 9.69
Grid 1b 1 3.20 0.85 2.72
Deduction on main beam and secondary beam
-14 0.30 0.25 -1.05
junction
Slab
Class room 8 2.73 2.73 59.41
Corridoor 4 2.73 2.20 23.98
1 3.20 2.19 7.01
Stair case area 1 3.20 0.49 1.57
1 3.20 0.39 1.23
First Floor
For column 12 1.80 3.00 64.80
Deduction on beam and column junction -34 0.30 0.53 -5.36
F.F.Staircase Area
First flight
Waist slab 1 3.35 1.50 5.03
Landing 1 1.94 1.50 2.90
1 1.47 1.70 2.49
Riser 10 1.50 0.15 2.25

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Side 2 3.35 0.30 2.01
1 1.47 0.15 0.22
1 1.94 0.15 0.29
1 1.25 0.15 0.19
Second flight
Waist slab 1 3.40 1.50 5.10
Riser 10 1.50 0.15 2.25
Side 2 3.40 0.30 2.04

Second Floor Beam


Main beam
Grid 1 (A-B & C-D) 2 5.55 1.23 13.60
Grid 1 (B-C) 1 3.05 1.35 4.12
Grid 2 1 14.15 1.10 15.57
Grid 3 1 14.15 1.23 17.33
Grid A & D 2 7.60 1.23 18.62
Grid B & C (1-2) 2 5.55 1.23 13.60
Grid B & C (2-3) 2 2.05 1.10 4.51
Secondary beam
Grid A1-C1 2 7.65 0.85 13.01
Grid 1a 2 5.70 0.85 9.69
Grid 1b 1 3.20 0.85 2.72
Deduction on main beam and secondary beam
-14 0.30 0.25 -1.05
junction
Slab
Class room 8 2.73 2.73 59.41
Corridoor 4 2.73 2.20 23.98
1 3.20 2.19 7.01
Stair case area 1 3.20 0.49 1.57
1 3.20 0.39 1.23
Second Floor
For column 12 1.80 3.00 64.80
Deduction on beam and column junction -34 0.30 0.53 -5.36
Second Floor Beam
Truss beam
Grid 1-2-3 3 14.15 1.10 46.70
Grid A-B-C-D 4 7.60 1.10 33.44
Lintel Bands
Ground floor level
Along grid A,B,C,D 8 5.55 0.13 5.55
Along grid 1 2 11.10 0.13 2.78
Along grid 2 2 11.10 0.13 2.78
First floor level
Along grid A,B,C,D 8 5.55 0.13 5.55
Along grid 1 2 11.10 0.13 2.78
Along grid 2 2 11.10 0.13 2.78
Second floor level

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Along grid A,B,C,D 8 5.55 0.13 5.55
Along grid 1 2 11.10 0.13 2.78
Along grid 2 2 11.10 0.13 2.78
Sill Bands
Ground floor level
Along grid A,B,C,D 8 5.55 0.08 3.33
Along grid 1 2 11.10 0.08 1.67
Along grid 2 2 11.10 0.08 1.67
At store 2 1.30 0.08 0.20
First floor level
Along grid A,B,C,D 8 5.55 0.08 3.33
Along grid 1 2 11.10 0.08 1.67
Along grid 2 2 11.10 0.08 1.67
Second floor level
Along grid A,B,C,D 8 5.55 0.08 3.33
Along grid 1 2 11.10 0.08 1.67
Along grid 2 2 11.10 0.08 1.67
Vetical Band
Ground Floor 4.00 2.48 0.38 3.76
First Floor 4.00 2.48 0.38 3.76
First Floor 4.00 2.60 0.38 3.95

Deduction of Doors For Sill


Ground floor level
D1 -8 1.10 0.08 -0.66
First floor level
D1 -8 1.10 0.08 -0.66
Second floor level
D1 -8 1.10 0.08 -0.66
Pedestal in corridor 8 1.25 0.25 2.50
Bench
Bench Top Slab 2 5.80 0.125 1.45
Bottom 2 1.90 0.25 0.95
Total 947.85 sq.m

3 Brick Masonary Works


3.2 Brick Masonary Works (1:4 c/s)
Foundation upto plinth
Grid 1,2,3 3 14.15 0.23 0.38 3.66
Grid A,B,C,D,E 4 7.60 0.23 0.38 2.62

Ground floor
Along grid A,B,C,D/(1-2) 4 5.55 0.23 2.33 11.87
Along grid 1 1 11.10 0.23 2.33 5.94
1 3.05 0.23 2.02 1.42
Along grid 2 1 10.80 0.23 2.33 5.78

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Deduction for doors and windows
Ground floor plan
W1 -8 1.10 0.23 1.13 -2.28
V1 -8 1.10 0.23 0.53 -1.06
W3 -1 1.50 0.23 0.37 -0.13
D1 -4 1.10 0.23 2.33 -2.35

First floor level


Along grid A,B,C,D 4 5.55 0.23 2.33 11.87
Along grid 1 1 11.10 0.23 2.33 5.94
1 3.05 0.23 2.05 1.43
Along grid 2 1 10.80 0.23 2.33 5.78

Deduction for doors and windows


First floor plan
W1 -8 1.10 0.23 1.13 -2.28
V1 -8 1.10 0.23 0.53 -1.06
W2 -1 1.50 0.23 1.00 -0.35
D1 -4 1.10 0.23 2.33 -2.35

Second floor level


Along grid A,B,C,D 4 5.55 0.23 2.45 12.51
Along grid 1 1 11.10 0.23 2.45 6.25
1 3.05 0.23 2.53 1.77
Along grid 2 1 10.80 0.23 2.45 6.09

Deduction for doors and windows


Second floor plan
W1 -8 1.10 0.23 1.13 -2.28
V2 -8 1.10 0.23 0.65 -1.32
W2 -1 1.50 0.23 1.00 -0.35
D2 -4 1.10 0.23 2.45 -2.48

Drain 1 33.40 0.23 0.15 1.15


Below ramp
For Front wall 3-AB 1 6.50 0.35 0.30 0.68
For Side wall -3B 1 1.33 0.35 0.30 0.14
Above ramp
For Front wall 3-AB 1 1.40 0.23 0.38 0.12
1 4.25 0.23 0.19 0.18
For Side wall -3B 1 1.33 0.23 0.59 0.18

External Steps 1 13.50 0.48 0.10 1.35


1 13.50 0.18 0.15 2.03
1 13.50 0.08 0.10 1.35
Grid 2A 1 0.60 0.50 0.45 0.14

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Grid 3A 1 0.53 0.40 0.45 0.09
Grid 2D 1 0.60 0.50 0.45 0.14
Total 72.19 Cu.m

3.2 Half brick work (1:4 c/s)


Storeroom below staircase 1 3.00 1.35 2.03
1 0.20 1.35 0.27
1 0.90 1.50 1.35
1 1.50 1.65 2.48
Deductions D3 -1 1.00 1.55 -1.55
Ramp
Grid 3AB
1 1.40 0.22 0.31
1 5.12 0.22 1.13
Bench
4 2.15 0.53 4.52
4 0.25 0.53 0.53
Total 11.04 Sq.m

4 Doors and Windows


4.1 Metal Frame
4.1.1 Door Frame
D1 8 7.07 56.56
D2 4 7.32 29.28
D3 1 4.10 4.10
Total 89.94 R.m

4.1.2 Window Frame


W1 24 5.58 133.80
W2 2 5.00 10.00
V1 16 3.25 52.00
V2 8 3.50 28.00
Total 223.80 R.m

4.2 Metal Shutter


4.2.1 Window Shutter
W1 24 1.01 1.04 25.09
W2 2 1.41 0.91 2.57
V1 16 1.01 0.44 7.03
V2 8 1.01 0.56 4.52
Total 39.21 Sq.m

4.3.1 Flush Door Shutter


D1 8 1.01 2.46 19.84
D2 4 1.01 2.56 10.32
D3 1 0.91 0.96 0.87
Total 31.03 Sq.m

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
4.5 Window Grill
W1 24 1.01 1.04 25.09
W2 2 1.41 0.91 2.57
W3 1 1.50 0.37 0.56
V1 16 1.01 0.44 7.03
V2 8 1.01 0.56 4.52
Total 39.77 Sq.m

4.6 Collapsible Gate


1 3.05 2.475 7.55
Total 7.55 sq.m

5 FLOORING WORKS
5.1 Hardened Cement Concrete Flooring (40mm) With Neat Cement Punning
Ground floor plan
Class Room 2 5.78 5.75 66.41
Corridor 1 15.80 2.50 39.50
1 3.20 1.50 4.80
Below Staircase 1 4.50 3.20 14.40
Staircase Tread 18 0.3 1.50 8.10
Riser 20 0.15 1.50 4.50
Staircase landing 1 1.80 3.20 5.76

First floor plan


Class Room 2 5.78 5.75 66.41
Corridor 1 15.80 2.50 39.50
1 3.20 1.50 4.80
Staircase Tread 18 0.3 1.50 8.10
Riser 20 0.15 1.50 4.50
Staircase landing 1 1.80 3.20 5.76

Second floor plan


Class Room 2 5.78 5.75 66.41
Corridor 1 15.80 2.50 39.50
1 3.20 1.50 4.80

Ramp 1 6.52 1.30 8.48


Exterior Steps (Front) 1 13.50 0.90 12.15
Drain
Back of Building 1 15.95 0.95 15.15
Side of bulding 1 6.45 0.95 6.13
Side Steps 1 10.03 0.875 8.77
Total 433.94 sq.m

5.2 Neat Cement Skirting works


Ground floor plan

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Room 2 21.35 42.70
Staircase Lobby 1 15.75 15.75
Waist Slab 2 3.00 6.00
Store Below Landing 1 4.85 4.85
Staircase/Landing 1 12.94 12.94
Column 4 2.25 9.00
Corridor 2 3.85 7.70

First floor plan


Room 2 21.35 42.70
Staircase Lobby 2 1.77 3.54
Waist Slab 2 3.00 6.00
Staircase/Landing 1 12.94 12.94
Corridor 2 4.53 9.05

Second Floor Plan 0.00


Room 2 21.35 42.70
Staircase Lobby 2 1.77 3.54
Corridor 2 4.53 9.05
Total 228.46 rm

5.3 25mm Terrazo Finishing


For In-built Furniture
Bench 2 2.40 0.50 2.40
Total 2.40 sq.m

6 Roofing/ Terracing Works


6.1 Metal Works
Truss 1 3,545.29
Total of Truss Total 3,545.29 k.g

6.2 CGI Sheet Roofing


Total Area 2 17.90 5.74 205.49
Total 205.50 sq.m

6.3 CGI Ridge


Top 1 17.90 17.90
Total 17.90 r.m

6.4 GI Facia(Eaves) Length (WxT) Density


Grid 1,3/AC 2 17.90 0.00031 7850 87.68
Grid A,D/1-3 4 5.74 0.00031 7850 56.23
Total 143.91 kgs.

6.5 Cement Board For False Ceiling


Backward and front slope of roof 2.00 15.95 1.18 37.64

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Side Slope of Roof 4.00 5.65 0.97 21.92
Classroom 2.00 5.70 5.70 64.98
Staircase 1.00 5.70 3.20 18.24
Corridor 2.00 5.70 2.20 25.08
1.00 3.20 2.20 7.04
Total 174.90 Sq.m

7 PLASTER/PAINTING WORKS
7.1 Internal Plaster
7.1.1 Internal Plaster on Wall (1:6)
Ground Floor
Classroom 2.00 23.15 2.91 134.73
Staircase 1.00 14.67 2.91 42.69
Store Below Landing 1.00 2.50 1.25 3.11
2.00 0.31 1.25 0.78
2.00 0.69 1.44 1.98
2.00 1.44 1.63 4.69
Pedestal 4.00 1.25 0.25 1.25
4.00 0.50 0.25 0.50
Column
Grid 2A,2D 2.00 0.35 0.68 0.47
Grid 2B,2C 2.00 0.98 0.68 1.32

Grid 2A,2D 2.00 0.45 2.20 1.98


Grid 2B,2C 2.00 1.08 2.20 4.73
Deductions
W1 -8 1.10 1.13 -4.95
V1 -8 1.10 0.53 -2.31
W3 -1 1.50 0.37 -0.28
D1 -4 1.10 2.48 -5.45
D3 -2 1.00 1.55 -1.55

First Floor
Classroom 2.00 23.15 2.91 134.73
Staircase 1.00 14.67 2.91 42.69
Column
Grid 2A,2D 2.00 0.45 2.91 2.62
Grid 2B,2C 2.00 1.08 2.91 6.26

Deductions
W1 -8 1.10 1.13 -4.95
V1 -8 1.10 0.53 -2.31
W2 -1 1.50 1.00 -0.75
D1 -4 1.10 2.48 -5.45

Second Floor
Classroom 2.00 23.15 3.00 138.90

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Staircase 1.00 14.67 3.00 44.01
Column
Grid 2A,2D 2.00 0.45 3.00 2.70
Grid 2B,2C 2.00 1.08 3.00 6.45
Deductions
W1 -8 1.10 1.13 -4.95
W2 -1 1.50 1.00 -0.75
V2 -8 1.10 0.65 -2.86
D2 -4 1.10 2.60 -5.72
Total 534.33 sq.m

7.1.2 Internal Plaster on Ceiling (1:4)


Ground floor
Classroom 1 4 2.73 2.73 29.70
Classroom 2 4 2.73 2.73 29.70
Corridor 4 2.73 2.20 23.98
1 3.20 2.20 7.04
Staircase Area 1 3.20 0.88 2.80
Secondary Beam
Along Grid A1-C1 2 7.65 0.60 9.18
Along Grid 1a 2 5.77 0.60 6.92
Along Grid 1b 1 3.20 0.60 1.92
Below staircase
Waist slab 1 3.35 1.50 5.03
Landing 1 1.94 1.50 2.90
1 1.47 1.70 2.49
First floor
Classroom 3 4 2.73 2.73 29.70
Classroom 4 4 2.73 2.73 29.70
Corridor 4 2.73 2.20 23.98
1 3.20 2.20 7.04
Staircase Area 1 3.20 0.88 2.80

Secondary Beam
Along Grid A1-C1 2 7.65 0.60 9.18
Along Grid 1a 2 5.70 0.60 6.84
Along Grid 1b 1 3.20 0.60 1.92

Below staircase
Waist slab 1 3.35 1.50 5.03
Landing 1 1.94 1.50 2.90
1 1.47 1.70 2.49
Second floor
Truss Beam
Classroom 4 4 5.55 0.40 8.88
Classroom 5 4 5.55 0.40 8.88
Corridor; Along grid 2 , ( A-B) and (C-D) 2 5.55 0.40 4.44

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Corridor; Along grid 2 , ( B-C) 1 3.05 1.10 3.36
Corridor; Along grid 3 , ( A-B), (B-C) and (C-
D) 1 14.15 0.70 9.91
Corridor; Along grid A, B, C and D; (2-3) 4 2.20 1.10 9.68
Total 288.40 sq.m

7.1.3 External Plaster


Outer Plaster
Beam Plaster
Plinth Beam
Along grid 1 1 14.15 0.45 6.37
Along grid A & D 1 5.55 0.45 2.50

First Floor Level


Main Beam(300 x 525)
Along grid 1 1.00 11.10 0.53 5.83
Grid 1-BC 1.00 3.05 0.65 1.97
Landing Beam 1.00 3.05 0.56 1.71
Along grid 3 1.00 14.15 0.83 11.67
Along grid A and D 2.00 7.60 0.53 7.98

Second Floor Level


Main Beam(300 x 525)
Along grid 1 1.00 14.15 0.53 7.43
Landing Beam 1.00 3.05 0.38 1.16
Along grid 3 1.00 14.15 0.83 11.67
Along grid A and D 2.00 7.60 0.53 7.98

Truss Level
Main Beam(300 x 400)
Along grid 1 1.00 14.15 0.40 5.66
Along grid 3 1.00 14.15 0.40 5.66
Along grid A and D 2.00 7.60 0.40 6.08

Column Plaster
Upto Plinth Level
Along grid 1
Grid 1A,1D 2.00 1.10 0.45 0.99
Grid 1B,1C 2.00 0.65 0.45 0.59
Along grid 2
Grid 2A,2D 2.00 0.55 0.45 0.50
Along grid 3
Along grid 3A 1.00 0.08 0.38 0.03
1.00 0.45 0.40 0.18
Grid 3B 1.00 0.08 0.15 0.01
Grid 3C 1.00 0.60 0.15 0.09
Grid 3D 1.00 1.05 0.15 0.16

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Upto Sill Level
Along grid 1
Grid 1A,1D 2.00 0.90 0.68 1.22
Grid 1B,1C 2.00 0.45 0.68 0.61
Along grid 2
Grid 2A,2D 2.00 0.55 0.68 0.74
Ground Floor
Along grid 1
Grid 1A,1D 2.00 1.10 2.33 5.12
Grid 1B,1C 2.00 0.65 2.33 3.02
Along grid 2
Grid 2A,2D 2.00 0.65 2.33 3.02
Along grid 3
Grid 3A,3D 2.00 1.05 3.00 6.30
2.00 0.75 2.88 4.31
Grid 3B,3C 2.00 1.20 2.88 6.90
2.00 0.60 3.00 3.60
First Floor
Along grid 1
Grid 1A,1D 2.00 1.10 2.33 5.12
Grid 1B,1C 2.00 0.65 2.33 3.02
Along grid 2
Grid 2A,2D 2.00 0.65 2.33 3.02
Along grid 3
Grid 3A,3D 2.00 1.05 3.00 6.30
2.00 0.75 2.88 4.31
Grid 3B,3C 2.00 1.20 2.88 6.90
2.00 0.60 3.00 3.60
Second Floor
Along grid 1
Grid 1A,1D 2.00 1.10 2.33 5.12
Grid 1B,1C 2.00 0.65 2.33 3.02
Along grid 2
Grid 2A,2D 2.00 0.65 2.33 3.02
Along grid 3
Grid 3A,3D 2.00 1.05 3.00 6.30
2.00 0.75 2.88 4.31
Grid 3B,3C 2.00 1.20 2.88 6.90
2.00 0.60 3.00 3.60

Plaster in Outer Wall


Ground floor
Along grid A,D/(1-2) 2 5.55 2.33 25.81
Along grid 1 1 11.10 2.33 25.81
1 3.05 2.02 6.16
Along grid 2 1 10.80 2.33 25.11

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
First floor level
Along grid A,D 2 5.55 2.33 25.81
Along grid 1 1 11.10 2.33 25.81
1 3.05 2.05 6.24
Along grid 2 1 10.80 2.33 25.11

Second floor level


Along grid A,D 2 5.55 2.45 27.20
Along grid 1 1 11.10 2.45 27.20
1 3.05 2.53 7.70
Along grid 2 1 10.80 2.45 26.46
Deduction for doors and windows
Ground floor plan
W1 -8 1.10 1.13 -9.90
V1 -8 1.10 0.53 -4.62
W3 -1 1.50 0.37 -0.56
D1 -4 1.10 2.33 -10.23
First floor plan
W1 -8 1.10 1.13 -9.90
V1 -8 1.10 0.53 -4.62
W2 -1 1.50 1.00 -1.50
D1 -4 1.10 2.33 -10.23
Second floor plan
W1 -8 1.10 1.13 -9.90
V2 -8 1.10 0.65 -5.72
W2 -1 1.50 1.00 -1.50
D2 -4 1.10 2.45 -10.78

Outer Steps
Grid 2A,2D 2.00 1.03 0.45 0.92
Grid 3A 1.00 0.93 0.45 0.42
Steps Edge 3.00 0.60 0.45 0.81
For Ramp
Top-3B 1.00 1.33 0.25 0.33
Top 3AB 1.00 6.47 0.13 0.81
Front 3-AB 1.00 1.60 0.60 0.96
1.00 5.10 0.38 1.91
Inner 1.00 7.52 0.15 1.13
Side-3B 1.00 1.33 0.60 0.80
For Bench
Top 2.00 2.40 0.50 2.40
Edge 2.00 5.80 0.13 1.45
Total 372.47 sqm

7.2 Painting Works


7.2.1 Distemper Painting Works
As per Internal plaster on wall 1.00 534.33 Area 534.33

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
As per internal plaster on ceiling 1.00 288.40 Area 288.40
False Ceiling 1.00 174.90 Area 174.90
Total 997.64 sq.m

7.2.2 Exterior Weather Coat Paint


Beam,Column and Walls Paint 1.00 372.47 Area 372.47
Total 372.47 sq.m

7.2.4 Enamel Painting


Doors Factor
D1 8 1.10 2.44 2.00 42.86
D2 4 1.10 2.56 2.00 22.53
D3 1 1.00 1.55 2.00 3.10
Collapsible Gate 1 3.05 2.48 2.00 15.10
Window 2.00
W1 24 1.10 1.13 2.00 59.40
W2 2 1.50 1.00 2.00 6.00
V1 16 1.10 0.53 2.00 18.48
V2 8 1.10 0.65 2.00 11.44
Window Grill
W1 24 1.01 1.04 25.09
W2 2 1.41 0.91 2.57
W3 1 1.50 0.37 0.56
V1 16 1.01 0.44 7.03
V2 8 1.01 0.56 4.52
Total 218.67 sq.m

8 MISCELLANOUS
8.2 Cement Board
Partition
Above Side Walls 1.00 9.73 1.58 15.38
Total 15.39 sq.m

8.3 Railing
Total
Staircase Railing Kg/m Total
No. Length (m) Length
Horizontal ISNB 40 M 1 18.40 18.40 3.61 66.42
Vertical 38 mm Square Pipe 14 0.86 12.04 3.14 37.81
Horizontal 25mm Square Pipe 4 17.35 69.40 0.85 58.99
Balcony Railing
Horizontal ISNB 40 M 2 18.25 36.50 3.61 131.77
Horizontal ISNB 32 M 4 16.40 65.60 3.14 205.98
Vertical ISNB 40 M 34 1.08 36.72 3.61 132.56
Vertical 25mm Square Pipe 236 0.82 193.52 0.85 164.49
Pedestal
ISNB 40M 8 1.70 13.60 3.61 49.10
ISNB 40M 8 2.05 16.40 3.61 59.20

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Base plate 69 0.00009375 0.01 7850 50.78
12 mm dia. Anchor Bolt, Nut 276 0.13 35.88
Total 992.98 k.gs

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-6C(S)-B
School Name : Shree Basuki Lower Secondary School
Location : Aaruarbang, Gorkha
BAR BENDING SCHEDULE
Cut Total
Dia. of No. of
S. No. Description No. Length Length Wt/m (Kg) Weight (Kg) Bar Shape
Bar (mm) Bars
(m) (m)
A Foundation for footing
1.1 Footing (F1,1500 X1500) 4
X- direction 12 10 1.56 62.40 0.89 55.54 0.08 0.08
Y- direction 12 10 1.56 62.40 0.89 55.54 1.4
1.2 Footing (F2,2200 X 2200) 2
X- direction 12 15 2.26 67.80 0.89 60.34 0.08 0.08
Y- direction 12 15 2.26 67.80 0.89 60.34 2.1
1.3 Footing (F3, 2500 X 2500) 4
X- direction 12 17 2.56 174.08 0.89 154.93 0.08 0.08
Y- direction 12 17 2.56 174.08 0.89 154.93 2.4
1.4 Footing (F4, 2800 X 2800) 4
X- direction 12 19 2.86 217.36 0.89 193.45 0.08 0.08
Y- direction 12 19 2.86 217.36 0.89 193.45 2.7

B Column
1 Grid 1 (A & D) 2 20mm ɸ 20mm ɸ
Main Bar 20 6 4.22 50.63 2.47 125.04
20 6 7.26 87.08 2.47 8.00
3.40 6.44

0.125 0.125
0.699 0.699
2 Grid 1(B & C) 2 25mm ɸ 25mm ɸ
Main Bar 25 6 4.82 57.83 3.86 223.20
25 6 7.82 93.83 3.86 362.16
3.70 6.70

0.125 0.125
0.999 0.999

3 Grid 2 (A) 1 20mm ɸ 20mm ɸ


Main Bar 20 6 4.22 25.31 2.47 62.52
20 6 7.26 43.54 2.47 107.54
3.40 6.44

0.125 0.125

4 Grid 2(B,C & D) 3


Main Bar 25 4 7.82 93.83 3.86 362.16 25mm ɸ 20mm ɸ
20 2 7.22 43.31 2.47 106.98
20 6 4.22 75.94 2.47 187.57
6.70 6.4

0.125 0.125
0.999 0.699
5 Grid 3 (A,B,C & D) 4
Main Bar 20 6 4.22 101.25 2.47 250.09 20mm ɸ 20mm ɸ
20 6 7.26 174.15 2.47 430.15

3.40 6.44

0.125 0.125
0.699 0.699
6 Stiruups 0.37
For 12 column 12 8 18 1.64 344.40 0.40 137.76 0.08 0.37
8 18 1.18 247.80 0.40 99.12 0.37 0.14 0.08
8 18 1.18 247.80 0.40 99.12

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
7 For Lower Tie Beam 8.13
7.1 Grid 1,2 & 3 3 0.44 8.42 0.44
Top Bar 12 2 8.86 53.16 0.89 47.31
12 2 8.57 51.42 0.89 45.76
12 1 11.35 34.05 0.89 30.30 2.97 2.97
12 2 3.41 20.46 0.89 18.21
Bottom Bar 12 3 12.00 108.00 0.89 96.12 0.44 11.35 0.44
12 3 5.45 49.05 0.89 43.65
Stirrups
Grid 1,2 & 3 3 8 125 1.06 397.39 0.40 158.96 0.44 11.56 5.01 0.44
0.72
7.2 Grid A,B,C & D 4
Top Bar 12 3 9.73 116.76 0.89 103.92
Bottom Bar 12 3 9.73 116.76 0.89 103.92
Stirrups 0.44 8.85 0.44
Grid A,B,C & D 4 8 71 1.06 300.33 0.40 120.13
0.44 8.85 0.44
0.2
0.08

0.25

8 Plinth tie beam


8.1 Grid 1,2 & 3 3 3.64 3.64
Top Bar 16 1 10.51 31.53 1.59 50.13
16 2 4.36 26.16 1.59 41.59 0.72 10.51 0.72
16 2 9.15 54.91 1.59 87.31
16 2 9.12 54.72 1.59 87.00
Bottom Bar 16 2 8.89 53.34 1.59 84.81 8.43 8.4
16 4 5.17 62.04 1.59 98.64 0.72 0.72
20 2 12.00 72.00 2.47 177.84
20 2 4.15 24.90 2.47 61.50
20 2 4.15 24.90 2.47 61.50 0.72 4.45 8.89 4.45 0.72

Stirrups 3 12 143 1.69 722.48 0.89 643.00


Torsion bar 16 2 16.67 100.02 1.59 159.03 3.15 3.15
1 1
8.2 Grid A,B,C,D 4 12
Top bar 16 3 10.31 123.72 1.59 196.71 0.72 8.87 0.72
Bottom bar 20 4 10.87 173.92 2.47 429.58 8.87
Stirrups 4 12 77 1.69 520.52 0.89 463.26 1 0.25 1
Torsion bar 16 2 8.71 69.68 1.59 110.79 0.12
0.475

8.3 Extra Bar


Grid 1 & Grid 2 2 1.9
Grid A 1 20 2 2.98 11.90 2.47 29.39 1 0.075

Grid B,C 2 20 2 7.10 56.80 2.47 140.30 6.95


0.075 0.075
Grid D 1 25 2 3.55 14.20 3.86 54.81
2.1
1.35 0.1
Grid 3 1
Grid A 1 16 2 2.70 5.39 1.59 8.57 1.9
0.72 0.075
Grid B,C 2 16 2 3.20 12.80 1.59 20.35
3.05
0.075 0.075
Gird D 1 16 2 2.70 5.39 1.59 8.57
1.9
0.72 0.075
Grid A,B,C,D, 4
Grid 1 1 25 2 3.55 28.40 3.86 109.62 2.1

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
1.35 0.1
Grid 2,3 2 25 2 6.05 96.80 3.86 373.65
4.6
1.35 0.1

0.37
9 Ground floor column 0.08 0.37
Grid 1,(A &D) 2 20 6 7.20 86.40 2.47 213.41 0.37 0.14 0.08
Grid 1 (B &C) 2 25 6 7.50 90.00 3.86 347.40
Grid 2 (A,B,C,D) 4 20 2 7.20 57.60 2.47 142.27
25 4 7.50 120.00 3.86 463.20
Grid 3 (A) 1 20 6 7.20 43.20 3.86 166.75
Grid 3 (B,C,D) 3 20 6 5.72 103.01 2.47 254.42

Stiruups
For 12 column 12 8 30 1.64 590.40 0.40 236.16 20mmɸ 25mmɸ
8 30 1.18 424.80 0.40 169.92
8 30 1.18 424.80 0.40 169.92

7.2 7.5
10 Stair Case GF
10.1 First Flight 3.35 1.46
Top Main Bar 12 12 7.26 87.11 0.89 77.53 1.67 0.31
Bottom Main Bar 12 12 2.74 32.89 0.89 29.27 0.45
Top Distribution Bar 10 16 1.46 23.36 0.62 14.48 1.2
Bottom Distribution Bar 10 42 1.46 61.32 0.62 38.02 0.3 1.24
Extra Bar 12 12 2.00 24.00 0.89 21.36
10.2 Landing 1
Bottom bar in first flight 12 12 2.90 34.80 0.89 30.97 1
Top Distribution Bar 10 8 1.46 11.68 0.62 7.24
Bottom Distribution Bar 10 12 3.16 37.92 0.62 23.51 3.16
Top Distribution Bar 10 12 3.16 37.92 0.62 23.51 1.69
Extra Bar 12 12 2.00 24.00 0.89 21.36 1 0.21
10.3 Second Flight
Top Main Bar 12 12 7.31 87.74 0.89 78.09 0.82 3.402
Bottom main Bar 12 12 3.30 39.60 0.89 35.24 0.45
Bottom Distribution Bar 10 23 1.46 33.09 0.62 20.52 2.32 0.31
Top Distribution Bar 10 13 1.46 19.47 0.62 12.07 1.2
Top main bar in forst floor level 12 12 2.38 28.55 0.89 25.41 1.89 0.21
Extra Bar 12 22 2.00 44.00 0.89 39.16
1.46
10.4 Nosing Bar 10 20 1.46 29.20 0.62 18.10
10.5 Nosing ties 0.26
18 8 5 0.67 60.66 0.40 24.26 0.22
0.15

11 Ground floor beam


11.1 Grid 1,2 & 3 ( Main Beam) 3 3.64 3.64
Top Bar 16 1 10.51 0.00 1.59 0.00
16 4 4.36 0.00 1.59 0.00 0.72 10.51 0.72
16 2 9.15 0.00 1.59 0.00
16 2 9.12 0.00 1.59 0.00
Bottom Bar 16 2 12.00 0.00 1.59 0.00 0.72 8.43 8.4 0.72
16 4 3.61 0.00 1.59 0.00
20 2 10.87 0.00 2.47 0.00
20 4 4.20 0.00 2.47 0.00
0.72 2.89 2.89 0.72
Stirrups 12
Grid 1,2 & 3 3 10 142 1.65 700.43 0.62 434.26
Torsion bar 3 16 2 16.67 100.02 1.59 159.03 1 3.2 10.87 3.2 1

16.67
11.2 Grid A,B,C,D ( Main Beam) 4 0.25
Top bar 16 3 10.29 123.48 1.59 196.33 0.1

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Bottom bar 20 4 10.87 173.92 2.47 429.58 0.475
Stirrups
Grid A,B,C & D 4 10 76 1.65 501.60 0.62 310.99
Torsion bar 4 16 2 8.87 70.96 1.59 112.83
0.71 0.71
8.87

1 1
8.87

8.87
11.3 Grid 1a (Secondary Beam) 2
Top bar 16 3 7.94 0.00 1.59 0.00 0.2
Bottom bar 16 3 7.94 0.00 1.59 0.00 0.8
Stirupps 8 49 1.31 0.00 0.40 0.00 0.375

0.87 6.2 0.87


11.4 Grid 1A &1C (Secondary Beam) 2
Top bar 16 3 10.44 0.00 1.59 0.00
Bottom bar 16 3 10.44 0.00 1.59 0.00 0.87 8.7 0.87
Stirupps 8 70 1.31 0.00 0.40 0.00

11.5 Grid 1b (Secondary Beam) 1 0.6 3.53 0.6


Top bar 12 3 4.73 0.00 0.89 0.00
Bottom bar 12 4 4.73 0.00 0.89 0.00
Stirupps 8 27 1.31 0.00 0.40 0.00
11.6 Extra Bar
11.6.1 Grid 1 & Grid 2 2 1.9
Grid A 1 20 2 2.98 11.90 2.47 29.39 1 0.075

Grid B,C 2 20 2 7.10 56.80 2.47 140.30 6.95


0.075 0.075
Grid D 1 25 2 3.55 14.20 3.86 54.81
2.1
1.35 0.1
11.6.2 Grid 3 1
Grid A 1 16 2 2.70 5.39 1.59 8.57 1.9
0.72 0.075
Grid B,C 2 16 2 3.20 12.80 1.59 20.35
3.05
0.075 0.075
Gird D 1 16 2 2.70 5.39 1.59 8.57
1.9
0.72 0.075
11.6.3 Grid A,B,C,D, 4
Grid 1 1 25 2 3.55 28.40 3.86 109.62 2.1
1.35 0.1
Grid2,3 2 25 2 6.05 96.80 3.86 373.65
4.6
1.35 0.1

0.96 0.96

11.7 Bent up bar in primary and


secondary beam junction 16 24 3.01 72.24 1.59 114.86 0.42

0.25
12 Landing Beam 3.87
Top bar 16 3 4.02 12.06 1.59 19.18 0.075 0.075
Bottom bar 16 3 4.02 12.06 1.59 19.18 0.2
Stirrups 1 8 31 1.22 37.82 0.40 15.13 0.8
0.33

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
13 GF Slab Rebar 0.475 Type A 0.55
Grid A-B and C-D 2 0.085 0.085
Short Span 8.7
Type A 8 20 9.90 395.80 0.40 158.32
Type B 8 20 10.03 401.08 0.40 160.43 Type B

0.475 0.55
0.085 0.33 0.085
Long Span(upto 1b) 2
Type A 8 19 7.47 0.00 0.40 0.00 0.55 Type A 0.55
Type B 8 19 7.54 0.00 0.40 0.00 0.085 0.085
6.2
Grid 1b-3 1 Type B
Main bar 0.55 1.35 0.55
Type A 8 12 17.45 209.40 0.40 83.76 0.085 0.33
Type B 8 12 17.71 212.57 0.40 85.03
0.55 Type A 0.55
Grid B-C 1 0.085 0.48
Main bar 0.55 Type B
Type A 8 11 4.30 47.25 0.40 18.90 0.085 0.33
Type B 8 11 4.63 50.88 0.40 20.35

Distribution Bar 6
Along Grid 1 2 8 2 6.00 24.00 0.40 9.60
Along Grid 1a 2 8 13 6.00 156.00 0.40 62.40 15.98
Along Grid 2 2 8 12 15.98 383.52 0.40 153.41
Along Grid 3 1 8 2 15.98 31.96 0.40 12.78
Along Grid A1- C1 2 8 13 8.50 221.00 0.40 88.40
Along Grid B and C 2 8 5 8.50 85.00 0.40 34.00 8.5
Along Grid between B and C 2 8 7 3.75 52.50 0.40 21.00
3.75
Negative bar
Along Grid A1-C1 2 8 14 2.16 60.48 0.40 24.19 0.055 2.05 0.055
Along Grid 1a( A-B and C-D) 2 8 11 2.16 47.52 0.40 19.01
Along Grid 2( A-B and C-D) 2 8 11 2.06 45.32 0.40 18.13 0.055 1.95 0.055
along Grid 2 (B-C) 1 8 4 2.17 8.69 0.40 3.48
0.055 2.06 0.055

1 First Floor Column


Grid 1,(A &D) 2 16 6 6.50 78.015 2.47 192.70
Grid 1 (B &C) 2 20 6 6.78 81.375 2.47 201.00
Grid 2 (A,B,C,D) 4 20 6 6.78 162.75 2.47 401.99
Grid 3 (A) 1 20 6 6.78 40.68 2.47 100.48
Grid 3 (B,C,D) 3 16 6 6.50 117.0225 2.47 289.05 16mmɸ 20mmɸ
Stiruups
For 12 column 12 8 30 1.64 590.4 0.4 236.16
8 30 1.18 424.8 0.4 169.92
8 30 1.18 424.8 0.4 169.92 6.5 6.78

2 Stair Case FF
2.1 First Flight 3.35 1.46
Top Main Bar 12 12 7.26 87.108 0.89 77.53 1.67 0.31
Bottom Main Bar 12 12 2.74 32.892 0.89 29.27 0.45
Top Distribution Bar 10 16 1.46 23.36 0.62 14.48 1.2
Bottom Distribution Bar 10 42 1.46 61.32 0.62 38.02 0.3 1.24
Extra Bar 12 12 2 24 0.89 21.36
2.2 Landing 1
Bottom bar in first flight 12 12 2.90 34.8 0.89 30.97 1
Top Distribution Bar 10 8 1.46 11.68 0.62 7.24
Bottom Distribution Bar 10 12 3.16 37.92 0.62 23.51 3.16
Top Distribution Bar 10 12 3.16 37.92 0.62 23.51 1.69
Extra Bar 12 12 2 24 0.89 21.36 1 0.21
2.3 Second Flight
Top Main Bar 12 12 7.31 87.744 0.89 78.09 0.82 3.402
Bottom main Bar 12 12 3.3 39.6 0.89 35.24 0.45

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Bottom Distribution Bar 10 23 1.46 33 0.62 20.52 2.32 0.31
Top Distribution Bar 10 13 1.46 19.47 0.62 12.07 1.2
Top main bar in forst floor level 12 12 2.38 28.548 0.89 25.41 1.89 0.21
Extra Bar 12 22 2 44 0.89 39.16
1.46
2.4 Nosing Bar 10 20 1.46 29.2 0.62 18.10
2.5 Nosing ties 0.26
18 8 5 0.674 60.66 0.4 24.26 0.22
0.15

3 Second Floor beam


3.1 Grid 1,2 & 3 ( Main Beam) 3 3.64 3.64
Top Bar 16 1 10.51 31.53 1.59 50.13
16 4 4.36 52.32 1.59 83.19 0.72 10.51 0.72
16 2 9.15 54.9 1.59 87.29
16 2 9.12 54.72 1.59 87.00
Bottom Bar 16 2 12 72 1.59 114.48 0.72 8.43 8.4 0.72
16 4 3.61 43.26 1.59 68.78
20 2 10.87 65.22 2.47 161.09
20 4 4.2 50.4 2.47 124.49
0.72 2.89 2.89 0.72
Stirrups 12
Grid 1,2 & 3 3 10 142 1.65 700.43 0.62 434.26
Torsion bar 3 16 2 16.67 100.02 1.59 159.03 1 3.2 10.87 3.2 1

16.67
3.2 Grid A,B,C,D (Main Beam) 4 0.25
Top bar 16 3 10.29 123.48 1.59 196.33 0.1
Bottom bar 20 2 10.87 86.96 2.47 214.79 0.475
16 2 10.29 82.32 1.59 130.89
Stirrups
Grid A,B,C & D 4 10 76 1.65 501.60 0.62 310.99
Torsion bar 4 16 2 8.87 70.96 1.59 112.83
0.71 0.71
8.87

1 1
8.87

8.87
3.3 Grid 1a (Secondary Beam) 2
Top bar 16 3 7.94 47.64 1.59 75.75 0.2
Bottom bar 16 3 7.94 47.64 1.59 75.75 0.8
Stirupps 8 49 1.31 128.38 0.4 51.35 0.375

0.87 6.2 0.87


3.4 Grid 1A &1C (Secondary Beam 2
Top bar 16 3 10.44 62.64 1.59 99.60
Bottom bar 16 3 10.44 62.64 1.59 99.60 0.87 8.7 0.87
Stirupps 8 70 1.31 182.09 0.4 72.84

3.5 Grid 1b (Secondary Beam) 1 0.6 3.53 0.6


Top bar 12 3 4.73 14.19 0.89 12.63
Bottom bar 12 4 4.73 18.92 0.89 16.84
Stirupps 8 27 1.31 35.59 0.4 14.24

3.6 Extra Bar


Grid 1 & Grid 2 2 1.9
Grid A & D 2 20 2 2.98 23.8 2.47 58.79 1 0.075

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Grid B,C 2 20 2 7.10 56.8 2.47 140.30 6.95
0.075 0.075
Grid 3 1
Grid A 1 16 2 2.70 5.39 1.59 8.57 1.9
0.72 0.075
Grid B,C 2 16 2 3.20 12.8 1.59 20.35
3.05
0.075 0.075
Grid D 1 16 2 2.70 5.39 1.59 8.57
1.9
0.72 0.075
Grid A,B,C,D, 4

Grid 1 1 20 2 3.00 24 2.47 59.28 1.9


1 0.1
Grid2,3 2 16 2 5.22 83.52 1.59 132.80
4.4
0.72 0.1

0.96 0.96
Bent up bar in primary and 16 24 3.01 72.24 1.59 114.86
3.7 secondary beam junction 0.42

0.25
4 Landing Beam 3.87
Top bar 16 3 4.02 12.06 1.59 19.18 0.075 0.075
Bottom bar 16 3 4.02 12.06 1.59 19.18 0.2
Stirrups 1 8 31 1.22 37.82 0.4 15.13 0.8
0.33

5 FF Slab Rebar 0.475 Type A 0.55


5.1 Grid A-B and C-D 2 0.085 0.085
Short Span 8.7
Type A 8 20 9.90 395.80 0.4 158.32
Type B 8 20 10.03 401.08 0.4 160.43 Type B

0.475 0.55
0.085 0.33 0.085
Long Span(upto 1b) 2
Type A 8 19 7.47 283.86 0.4 113.54 0.55 Type A 0.55
Type B 8 19 7.54 286.37 0.4 114.55 0.085 0.085
6.2
5.2 Grid 1b-3 1 Type B
Main bar 0.55 1.35 0.55
Type A 8 12 17.45 209.40 0.4 83.76 0.085 0.33
Type B 8 12 17.71 212.57 0.4 85.03
0.55 Type A 0.55
5.3 Grid B-C 1 0.085 0.48
Main bar 0.55 Type B
Type A 8 11 4.295 47.25 0.4 18.90 0.085 0.33
Type B 8 11 4.625 50.88 0.4 20.35

Distribution Bar 6
Along Grid 1 2 8 2 6 24.00 0.4 9.60
Along Grid 1a 2 8 13 6 156.00 0.4 62.40 15.98
Along Grid 2 2 8 12 15.98 383.52 0.4 153.41
Along Grid 3 1 8 2 15.98 31.96 0.4 12.78
Along Grid A1- C1 2 8 13 8.5 221.00 0.4 88.40
Along Grid B and C 2 8 5 8.5 85.00 0.4 34.00 8.5
Along Grid between B and C 2 8 7 3.75 52.50 0.4 21.00
3.75
Negative bar
Along Grid A1-C1 2 8 14 2.16 60.48 0.4 24.19 0.055 2.05 0.055
Along Grid 1a( A-B and C-D) 2 8 11 2.16 47.52 0.4 19.01

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Along Grid 2( A-B and C-D) 2 8 11 2.06 45.32 0.4 18.13 0.055 1.95 0.055
Along Grid 2 (B-C) 1 8 4 2.17 8.69 0.4 3.48
0.055 2.06 0.055
6 Second Floor Column
Grid 1,(A &D) 2 16 6 3.47 41.64 2.47 102.85
Grid 1 (B &C) 2 20 6 3.75 45 2.47 111.15
Grid 2 (A) 1 16 6 3.47 20.82 2.47 51.43
Grid 2 (A,B,C,D) 3 20 6 3.75 67.5 2.47 166.73
Grid 3 (A) 1 16 6 3.47 20.82 2.47 51.43 16mmɸ 20mmɸ
Grid 3 (B,C,D) 3 20 6 3.75 67.5 2.47 166.73
Stiruups
For 12 column 12 8 31 1.64 610.08 0.4 244.03
8 31 1.18 438.96 0.4 175.58 6.5 6.78
8 31 1.18 438.96 0.4 175.58

7 Second Floor Truss beam


7.1 Grid 1,2 & 3 ( Main Beam) 3 3.64 3.64
Top Bar 16 1 10.51 31.53 1.59 50.13
16 2 4.36 26.16 1.59 41.59 0.72 10.51 0.72
16 2 9.15 54.9 1.59 87.29
16 2 9.12 54.72 1.59 87.00
Bottom Bar 16 2 12 72 1.59 114.48 0.72 8.43 8.4 0.72
16 4 3.61 43.26 1.59 68.78
12 2 9.73 58.38 0.89 51.96
12 4 4.2 50.4 0.89 44.86
0.72 2.89 2.89 0.72
Stirrups 12
Grid 1,2 & 3 3 8 143 1.36 581.40 0.40 232.56 0.25
0.1
7.2 Grid A,B,C,D ( Main Beam) 4 0.475
Top bar 16 3 10.29 123.48 1.59 196.33
Bottom bar 12 2 9.73 77.84 0.89 69.28
16 2 10.29 82.32 1.59 130.89 0.71 0.71
Stirrups 8.87
Grid A,B,C & D 4 8 77 1.36 418.88 0.40 167.55 1 1
8.87
8 Lintel Bands
8.1 Ground floor level
Main Bar
Along grid A,B,C,D 8 10 2 5.85 93.60 0.62 58.03
Along grid 1 2 10 2 5.85 23.40 0.62 14.51
Along grid 2 2 10 2 5.85 23.40 0.62 14.51 0.075 0.075
At store 2 10 2 5.85 23.40 0.62 14.51 5.7
Tie Bar 0.075 0.075
Along grid A,B,C,D 8 8 38 0.40 121.60 0.40 48.64 0.25
Along grid 1 2 8 38 0.40 30.40 0.40 12.16
Along grid 2 2 8 38 0.40 30.40 0.40 12.16
At store 2 8 38 0.40 30.40 0.40 12.16

8.2 First floor level


Main Bar
Along grid A,B,C,D 8 10 2 5.85 93.60 0.62 58.03
Along grid 1 2 10 2 5.85 23.40 0.62 14.51
Along grid 2 2 10 2 5.85 23.40 0.62 14.51
Tie Bar
Along grid A,B,C,D 8 8 38 0.40 121.60 0.40 48.64
Along grid 1 2 8 38 0.40 30.40 0.40 12.16
Along grid 2 2 8 38 0.40 30.40 0.40 12.16

8.3 Second floor level


Main Bar
Along grid A,B,C,D 8 10 2 5.85 93.60 0.62 58.03
Along grid 1 2 10 2 5.85 23.40 0.62 14.51
Along grid 2 2 10 2 5.85 23.40 0.62 14.51
Tie Bar

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Along grid A,B,C,D 8 8 38 0.40 121.60 0.40 48.64
Along grid 1 2 8 38 0.40 30.40 0.40 12.16 0.075 0.075
Along grid 2 2 8 38 0.40 30.40 0.40 12.16 5.7

9 Sill Bands
9.1 Ground floor level
Main Bar
Along grid A,B,C,D 8 10 2 5.85 93.60 0.62 58.03
Along grid 1 2 10 2 5.85 23.40 0.62 14.51
Along grid 2 2 10 2 5.85 23.40 0.62 14.51 0.075 0.075
At store 2 10 2 5.85 23.40 0.62 14.51 5.7
Tie Bar 0.075 0.075
Along grid A,B,C,D 8 8 38 0.40 121.60 0.40 48.64 0.25
Along grid 1 2 8 38 0.40 30.40 0.40 12.16
Along grid 2 2 8 38 0.40 30.40 0.40 12.16
At store 2 8 38 0.40 30.40 0.40 12.16

9.2 First floor level


Main Bar
Along grid A,B,C,D 8 10 2 5.85 93.60 0.62 58.03
Along grid 1 2 10 2 5.85 23.40 0.62 14.51
Along grid 2 2 10 2 5.85 23.40 0.62 14.51
Tie Bar
Along grid A,B,C,D 8 8 38 0.40 121.60 0.40 48.64
Along grid 1 2 8 38 0.40 30.40 0.40 12.16
Along grid 2 2 8 38 0.40 30.40 0.40 12.16

9.3 Second floor level


Main Bar
Along grid A,B,C,D 8 10 2 5.85 93.60 0.62 58.03
Along grid 1 2 10 2 5.85 23.40 0.62 14.51
Along grid 2 2 10 2 5.85 23.40 0.62 14.51
Tie Bar
Along grid A,B,C,D 8 8 38 0.40 121.60 0.40 48.64
Along grid 1 2 8 38 0.40 30.40 0.40 12.16 0.075 0.075
Along grid 2 2 8 38 0.40 30.40 0.40 12.16 5.7

10 Vertical Bands
10.1 Ground Floor 4
Main Bar 10 2 2.50 20.00 0.62 12.40
Tie Bar 8 17 0.40 27.20 0.40 10.88

10.2 First Floor 4


Main Bar 10 2 2.50 20.00 0.62 12.40
Tie Bar 8 17 0.40 27.20 0.40 10.88

10.3 Second Floor 4


Main Bar 10 2 2.50 20.00 0.62 12.40
Tie Bar 8 17 8.00 544.00 0.40 217.60

Total 24821.53
24.82 Mt.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-6C(S)-B
School Name : Shree Basuki Lower Secondary School
Location : Aaruarbang, Gorkha

Weight Length Total


S.N. Particulars Size Thickness Qty Total wt. Remarks
Per Metre (m) Length
1 TOP CHORD PIPE 50MM MID 5.03 5.641 12 67.69 340.49
2 BOTTOM CHORD PIPE 40MM MID 3.56 4.378 12 52.54 187.03
3 VERTICAL BRACING.1 40MM MID 3.56 1.351 12 16.21 57.71
4 VERTICAL BRACING.2 40MM MID 3.56 1.088 12 13.05 46.47
5 VERTICAL BRACING.3 40MM MID 3.56 0.825 12 9.90 35.24
6 VERTICAL BRACING.4 40MM MID 3.56 0.419 12 5.03 17.90
7 DIGONAL BRACING.1 32 MM MID 3.1 1.328 12 15.94 49.40
8 DIGONAL BRACING.2 32MM MID 3.1 1.123 12 13.48 41.78
9 DIGONAL BRACING.3 32MM MID 3.1 1.272 12 15.26 47.32
10 PURLIN 1 65MM MID 6.42 3.000 48 144.00 924.48
11 PURLIN 2 65MM MID 6.42 3.500 12 42.00 269.64
12 RUNNER 1 40MM MID 3.56 3.000 24 72.00 256.32
13 RUNNER2 40MM MID 3.56 3.500 8 28.00 99.68
15 END PURLIN 65MM MID 6.42 1.125 24 27.00 173.34
16 CROSS BRACING 40MM MID 3.56 1.380 32 44.16 157.21
17 BASE PLATE 250X250 10MM 4.9 18 88.20
18 BASE PLATE STIFFNER(L) 127X250 10MM 2.49 24 59.76
19 BASE PLATE STIFFNER(S) 50X75 10MM 0.29 24 6.96
20 PURLIN CLITE 200X90 10MM 1.41 144 203.04
21 TRUSS CLITE 200X90 10MM 1.41 72 101.52
22 RUNNER CLITE 175X70 10MM 0.96 40 38.40
23 R.CONNECTION BOX PLATE 175X160 10MM 2.19 12 26.28
24 TRUSS JOINT CLITE(C) 175X175 10MM 2.4 16 38.40
25 TRUSS JOINT CLITE(O) 175X175 10MM 2.4 8 19.20
26 STIPNER1. 100X63 10MM 0.49 16 7.84
27 STIPNER2. 63X63 10MM 0.31 64 19.84
28 WIND TIE PLATE 380X80 6MM 1.43 16 22.88
29 BRACING TIE STEPER 100X100 6MM 0.47 16 7.52
30 CROSS BRACING PIPE CLITE 165X80 6MM 0.62 64 39.68
31 TEMP PLATE 250X250 10MM 4.9 18 88.20
32 ANCHOR BOLT 16MM 1.58 0.45 72 32.40 51.19
33 NUT BOLT(16X60) 16MM 1.58 0.06 148 14.03
34 NUT BOLT(16X50) 16MM 1.58 0.05 48 3.79
35 NUT BOLT(16X40) 16MM 1.58 0.04 72 4.55
Total 3545.29 Kgs.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Block : 3-6CS
School Name : Shree Chandrodaya S.S
Location : Shreenathkot, Gorkha

Site
S. No. Description G.F F.F S.F Quantity Unit Remarks
Development
A. Common Installation
1.1 Stand Alone 40 A DP MCB with Enclosure 1.00 1.00 nos.
2 CABLES & WIRES
2 Nos 10 Sq.mm + 1 No 6 Sq.mm mutistranded
2.1 52.00 r.m
copper conductor wires

2.2 2 Nos 2.5 Sq.mm mutistranded copper conductor 50.00 r.m


wires + 1 Nos. 1.5sq mm multistranded Cu wire
B School Blocks
1 DISTRIBUTION BOARDS 1.00 1.00 1.00 3.00 nos.
2 CABLES & WIRES
2 Nos 6 Sq mm Multistranded Cu Wire + 1 No 4
2.1 10.00 r.m
Sq mm Multistranded Cu wire
3 General Service Light Point Wiring
3.1 One Way Light Point 3.00 13.00 12.00 13.00 41.00 pts.
3.2 Two Way Light Point 1.00 1.00 2.00 pts.
3.3 Ceiling Fan Point 2.00 2.00 pts.
4 6A Universal Pin Light Power Socket Wiring 12.00 12.00 4.00 28.00 pts.
5 Switch Socket Outlets
5.1 6A Universal Power Switch Socket 12.00 12.00 4.00 28.00 no.
7 Light Fixtures/Luminaires & Accessories
7.1 18 W LED Surface Mounted Square type 8.00 8.00 16.00 no.
7.2 18 W LED Recessed Mounted Square type 8.00 8.00 no.
7.3 12 W LED Surface Mounted Cylindrical type 4.00 5.00 9.00 no.
7.4 12 W LED Recessed Mounted Circular type 5.00 5.00 no.
7.5 7W LED Wall Light 1.00 1.00 no.
8 Pull Box 3.00 3.00 no.
9 External Post Top Light Pole 3.00 3.00 no.
10 Post Top External Light Fixtures 3.00 3.00 no.
11 Earthing & Lighting Protection
11.1 Chemical Earthing 3.00 3.00 no.
11.2 Earthing Bar 3.00 3.00 no.
12 Earthing Strip/Wires
12.1 25 x 3 mm GI strip 65.00 67.00 r.m
12.2 12 SWG Cu wire 15.00 16.00 r.m
13 Earth Test link 1.00 1.00 no.
C Solar PV System
1 Solar PV Panel 4.00 4.00 nos.
2 Tubular Deep Cycle Battery 2.00 2.00 nos.
3 Hybrid Inverter 1.00 1.00 nos.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-6C(S)-B
School Name : Shree Basuki Lower Secondary School
Location : Aaruarbang, Gorkha

S.N Furniture Description Symbol Qty Unit Remarks


1 Student Desk 6-12 (2 Seater) D-01C 30 nos.
2 Student Bench 6-12 (2 Seater) B-01C 30 nos.
3 Student Bench G6-12 (3 Seater) B-02C 8 nos.
4 Teacher's Table T-01 4 nos.
5 Teacher's Chair C-01 4 nos.
6 White Board F-03 2 nos.
7 Library Table T-02 4 nos.
8 Library Shelf F-04 3 nos.
9 Computer Chair C-02 24 nos.
10 Computer Table T-04 12 nos.
11 White Board with Stand F-05 1 nos.
12 Cabinet F-06 3 nos.
13 Office Table T-07 12 nos.
14 Office Chair C-03 12 nos.
15 Office Chair (Visitor) C-05 12 nos.
16 Dining Table T-09 2 nos.
17 Equipment Cabinet F-09 2 nos.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Toilet Block,T(S)F
School Name : Shree Basuki Lower Secondary School
Location : Aaruarbang, Gorkha

Length Breadth Height


S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
1 Earthworks
1.1 Site Clearance
Toilets ( Female)
Toilet block 1 8.34 6.35 52.91
Septic tank 1 5.00 3.95 19.75
Soak Pit 1 1.50 1.50 2.25
Sewer Manhole 1 1.00 1.00 1.00
Waste water Chamber 2 2.00 2.00 8.00
Total 83.91 Sq.m

1.2 Earth Work Excavation


For Footing
Footing F1 6 1.30 1.30 1.20 12.17

For Lower Tie Beam


Along grid 1 1 3.70 0.60 0.70 1.55
Along grid 2 1 3.70 0.50 0.70 1.30
Along grid 3 1 3.70 0.60 0.70 1.55
Along grid A 1 3.40 0.60 0.70 1.43
Along grid B/1-2 1 2.20 0.60 0.70 0.92
Along grid B/2-3 1 1.20 0.50 0.70 0.42
Between Grid AB & 2-3 1 4.50 0.60 0.45 1.20

Along the incinerator 1 1.90 1.15 0.15 0.33


For ramp 1 0.50 Area 1.03 0.51
From exterior wall to drain 1 3.00 1.30 0.05 0.20
1 2.80 0.60 0.05 0.08
Drain 1 6.50 0.60 0.05 0.20
External Steps 1 1.20 0.60 0.15 0.11
For Septic Tank 1 5.80 2.55 2.60 38.45
1 1.10 1.85 1.20 2.44
Soak Pit 1 4.15 Area 1.50 6.23
For Sewer Manhole 1 1.00 Area 0.70 0.70
Waste Water Chamber 2 1.00 1.00 0.70 1.40
Total 71.19 Cu.m

1.3 Earth Back filling


Excavated earthwork 71.19
Boulder soling -2.40
PCC -1.20
RCC -5.49

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)

-3.62
Brick masonry work below plinth tie beam
Room 1 5.00 3.20 0.18 2.80
Corridoor 1 5.00 2.20 0.18 1.93
Total 63.21 Cu.m

1.4 Boulder Soling


For Footing
Along the isolated foundation 6 1.00 1.00 0.20 1.20

Along the plinth beam


Along grid 1 1 4.50 0.45 0.10 0.20
Along grid 2 1 4.50 0.35 0.10 0.16
Along grid 3 1 4.50 0.45 0.10 0.20
Along grid A 1 5.00 0.45 0.10 0.23
Along grid B/1-2 1 3.00 0.45 0.10 0.14
Along grid B/2-3 1 2.00 0.35 0.10 0.07
Between Grid AB & 2-3 1 4.50 0.45 0.10 0.20

Below the ground floor.


1 2.00 3.23 0.20 1.29
1 2.50 3.25 0.20 1.63
Below the corridor. 1 5.00 2.25 0.20 2.25

Along the incinerator 1 1.90 1.15 0.90 1.97


For the ramp 1 6.00 1.00 0.20 1.20
From exterior wall to drain 1 3.00 1.33 0.05 0.00
1 2.70 0.60 0.05 0.00

Septic Tank 1 5.50 2.25 0.06 0.68


1 0.80 1.55 0.06 0.07
Inside of soak Pit 1 1.20 2.00 2.40
Sewer Manhole 1 1.00 1.00 0.20 0.20
Waste Water Chamber 2 1.00 1.00 0.20 0.40
Total 14.48 Cu.m

1.5 Sand Filling


Periphery ot Soak pit 1 1.80 Area 1.20 2.16
Total 2.16 cu.m

2 Concrete Works
2.1 PCC
2.1.1 P.C.C.(1:3:6) Works
For Footing 1
P.C.C. for isolated footing(F1) 6 1.00 1.00 0.10 0.60

For Tie Beam

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
Along grid 1 1 4.50 0.45 0.05 0.10
Along grid 2 1 4.50 0.35 0.05 0.08
Along grid 3 1 4.50 0.45 0.05 0.10
Along grid A 1 5.00 0.45 0.05 0.11
Along grid B/1-2 1 3.00 0.45 0.05 0.07
Along grid B/2-3 1 2.00 0.35 0.05 0.04
Between Grid AB & 2-3 1 4.50 0.45 0.05 0.10

Septic Tank
1 5.50 2.25 0.08 0.99
Sewer Manhole
Bottom 1 1.00 Area 0.10 0.10
Waste water Chamber 0.00
Bottom 2 1.00 1.00 0.10 0.20
Total 2.49 Cu.m

2.1.2 P.C.C.(1:2:4) Works


Toilets ( Female) 1
For the ramp 1 6.00 1.00 0.08 0.45
Bellow the ground floor.
1 2.00 3.23 0.08 0.00
1 2.50 3.25 0.08 0.00
Bellow the corridor. 1 5.00 2.25 0.08 0.00
Along the incinerator 1 1.90 1.15 0.05 0.11
From exterior wall to drain 1 3.00 1.20 0.05 0.00
1 2.70 0.60 0.05 0.00
Total 0.56 cu.m

2.2 P.C.C For R.C.C. Works (1:1.5:3)


Foundation
Inclined Part 6 Area 0.63 0.15 0.56
Rectangular Base 6 1.00 1.00 0.20 1.20

Beam
Foundation Beam
Along grid 1 1 4.70 0.25 0.30 0.35
Along grid 2 1 4.70 0.25 0.30 0.35
Along grid 3 1 4.70 0.25 0.30 0.35
Along grid A 1 5.40 0.25 0.30 0.41
Along grid B/(1,2) 1 3.20 0.25 0.30 0.24

Tie Beam
Along grid 1 1 4.70 0.25 0.30 0.35
Along grid 2 1 4.70 0.25 0.30 0.35
Along grid 3 1 4.70 0.25 0.30 0.35
Along grid A 1 5.40 0.25 0.30 0.41
Along grid B(1,2) 1 3.20 0.25 0.30 0.24

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
Along grid B/(2,3) 1 2.20 0.25 0.59 0.32

For first floor Beam


Main beam
Along grid 1 1 4.70 0.25 0.40 0.47
Along grid 2 1 4.70 0.25 0.45 0.53
Along grid 3 1 4.70 0.25 0.45 0.53
Along grid A/1-2 1 3.20 0.25 0.40 0.32
Along grid A/2-3 1 2.20 0.25 0.45 0.25
Along grid B/1-2 1 3.20 0.25 0.40 0.32
Along grid B/2-3 1 2.20 0.25 0.45 0.25

Column
Column up to plinth level 6 0.30 0.30 1.00 0.54
Column from plinth to top 6 0.30 0.30 3.00 1.62

Slab
Slab of first floor 1 4.75 2.25 0.15 1.60

Lintel Bands
For first floor
Along grid 1 1 4.70 0.125 0.25 0.15
Along grid 2 1 4.70 0.125 0.25 0.15
Along grid 3 1 4.70 0.125 0.25 0.15
Along grid A 1 5.40 0.125 0.25 0.17
Along grid B 1 3.20 0.125 0.25 0.10
Along the partition wall 1 3.25 0.125 0.25 0.10
For the partition wall 1 2.77 0.125 0.13 0.04

Sill Bands 0.00


For first floor 0.00
Along grid 1 1 4.70 0.075 0.43 0.15
Along grid 2 1 4.70 0.075 0.43 0.15
Along grid 3 1 4.70 0.075 0.43 0.15
Along grid A 1 5.40 0.075 0.43 0.17
Along grid B 1 3.20 0.075 0.43 0.10
Along the partition wall 1 3.25 0.075 0.25 0.06
For the partition wall 1 2.77 0.075 0.13 0.03
Deduction 0.00
D1 -1 1.00 0.075 0.43 -0.03
D2 -1 0.90 0.075 0.43 -0.03

Along the Slab of incinirator 1 0.80 1.000 0.08 0.06


Along the water trough
1 1.80 0.500 0.100 0.00
1 1.80 0.500 0.100 0.00
3 0.58 0.300 0.100 0.00

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
Septic Tank
At Bottom 1 5.20 1.95 0.12 1.22
Conceal Beam 1 1.20 0.25 0.15 0.05
Top Cover 1 5.20 1.95 0.12 1.22
Deduction Cap -2 0.30 0.30 0.12 -0.02
-1 0.30 0.30 0.12 -0.01

Soak Pit
RCC slab 1 1.13 Area 0.12 0.14
Sewer Manhole
Top Cover 1 1.00 1.00 0.10 0.10
Waste Water Chamber
Top Cover 2 1.00 1.00 0.10 0.20
Total 16.46 Cu.m

2.3 Silica Cement Admixture


10 Kg per cu.m. of R.C.C. M20 10 16.46 164.63
Total 164.63 Kg.

2.5 Formworks
Foundation
Isolated footing (F1) 6 4.00 0.20 4.80

Beam
Foundation Beam
Along grid 1 1 4.70 0.50 2.35
Along grid 2 1 4.70 0.50 2.35
Along grid 3 1 4.70 0.50 2.35
Along grid A 1 5.40 0.50 2.70
Along grid B/(1,2) 1 3.20 0.50 1.60

Tie Beam
Along grid 1 1 4.70 0.60 2.82
Along grid 2 1 4.70 0.60 2.82
Along grid 3 1 4.70 0.60 2.82
Along grid A 1 5.40 0.60 3.24
Along grid B/(2,3) 1 2.20 1.18 2.60

Truss level Beam


Main beam
Along grid 1 1 4.70 1.05 4.94
Along grid 2 1 4.70 1.15 5.41
Along grid 3 1 4.70 1.15 5.41
Along grid A/1-2 1 3.20 1.05 3.36
Along grid A/2-3 1 2.20 1.15 2.53
Along grid B/1-2 1 3.20 1.05 3.36
Along grid B/2-3 1 2.20 1.15 2.53

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)

Column
Column up to plinth level 6 1.00 1.20 7.20
Column from plinth to top 6 3.00 1.20 21.60

Slab
Along corridor 1 4.75 2.25 10.69

Lintel Bands
Along grid 1 2 4.70 0.125 1.18
Along grid 2 2 4.70 0.125 1.18
Along grid 3 2 4.70 0.125 1.18
Along grid A 2 5.40 0.125 1.35
Along grid B 2 3.20 0.125 0.80
Along partition walls 1 2.77 0.125 0.35

Sill Bands 0.00


Along grid 1 1 4.70 0.150 0.71
Along grid 2 1 4.70 0.150 0.71
Along grid 3 1 4.70 0.150 0.71
Along grid A 1 5.40 0.150 0.81
Along grid B 1 3.20 0.150 0.48

For the partition wall 1 2.77 0.150 0.42


subtraction 0.00
D1 -1 1.00 0.150 -0.15
D2 -1 0.90 0.150 -0.14

Along the water trough 2 3.75 0.875 6.56


6 0.50 0.300 0.90
For Septic Tank
For cover Slab 1 5.20 1.95 10.14
Conceal Beam 1 0.55 Perimeter 1.20 0.66

For Soak Pit


RCC slab
Base Area 1 1.13 1.13

Sewer Manhole
Top Cover 1 0.60 Area 0.60

Waste Water Chamber


Top Cover 2 0.75 0.75 1.13
Total 128.13 Sq.m

3 Brick Masonary Works


3.2 Full Brick (230 mm) Works (1:4c/s)

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
Brick Works under Plinth beam
Along grid 1 1 4.70 0.23 0.45 0.49
Along grid 2 1 4.70 0.23 0.45 0.49
Between Grid 2 and 3 1 4.50 0.23 0.68 0.70
Along grid 3 1 4.70 0.23 0.45 0.49
Along grid A 1 5.40 0.23 0.45 0.56
Along grid B 1 3.20 0.23 0.45 0.33

Internal Partition Walls


Along grid 1 1 4.70 0.23 2.03 2.19
1 0.25 0.23 0.38 0.02
Along grid 2 1 4.70 0.23 2.03 2.19
1 0.25 0.23 0.38 0.02
Deduction -1 1.00 0.23 2.03 -0.47
-1 0.90 0.23 2.03 -0.42
Along grid 3 1 4.70 0.23 1.00 1.08
Along grid B 1 3.20 0.23 1.78 1.31
Along grid A 1 3.20 0.23 2.40 1.77
1 2.20 0.23 2.40 1.21
Middle Wall 1 3.25 2.80 0.25 2.28

Below Water Trough 1 0.58 0.23 0.30 0.04


1 0.58 0.23 0.45 0.06
At outside Drain 1 0.93 area 1.20 1.11
For Septic Tank
Inlet wall (250 mm ) 1 1.20 0.23 0.60 0.17
1 1.20 0.23 0.20 0.06
Outer Wall (375 mm) 2 4.20 0.38 2.25 7.09
2 1.20 0.38 2.25 2.03

Soak Pit Brick work 1 0.20 0.50 0.10


Total 24.88 cu.m

3.3 Half Brick (125 mm) Works (1:4c/s)


Long wall 1 1.72 2.80 4.82
Short wall 1 0.43 2.80 1.19

Sewer Man Hole


Outer Wall 1 3.20 0.45 1.44
Waste Water Chamber
Outer Wall 2 3.50 0.45 3.15
Total 10.61 sq.m

3.4 Honey Comb Brick (350 mm) Works (1:3c/s)


Soak Pit Brick work 1 0.20 1.20 0.24
Total 0.24 cu.m

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)

4 DOORS & WINDOWS


4.4 UPVC Door
4.4.1 UPVC Door Shutter
Toilets (Female) 1
D1 1 1.00 2.10 2.10
D2 1 0.90 2.10 1.89
D3 2 0.75 2.10 3.15
Total 7.14 sq.m

4.5 Window Grill


Toilets ( Female) 1
Ventilation FrameV1 1 2.48 0.38 1.86
V2 1 2.48 0.33 1.61
V3 1 1.98 0.38 1.48
V4 1 1.98 0.33 1.28
Total 6.23 sq.m

5 FLOORING WORKS
5.1 Cement Concrete Flooring (40mm) With Neat Cement Punning
Toilets ( Female) 1
At corridor 1 5.30 1.20 6.36
At Ramp 1 5.60 1.20 6.72
Along the terrace 1 4.75 2.25 10.69
step 1 0.30 1.20 0.36
Inside the room 1 3.23 2.00 6.45
1 3.23 2.50 8.06
At Doors 1 1.90 0.25 0.48
Along the water trough 1 3.45 0.7 2.42
Total 41.53 sq.m

5.2 Neat cement Skirting


1 11.5 11.50
Total 11.50 r.m

5.3 Terrazo Cast In-Situ Dado


Toilets (Male & Female) 1
Along grid A & B 2 3.20 1.20 7.68
Along grid 1 1 4.50 1.20 5.40
Along grid 2 1 2.60 1.20 3.12
Along the water trough 1 3.45 0.80 2.76
Along the partition wall 1 5.10 1.20 6.12
2 3.25 1.20 7.80
Total 32.88 sq.m

6 Roofing/ Terracing Works

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
6.1 Metal Works
Total
Description Nos length Kg/m Total
Length
Truss 597.05
Total 597.05 kg

6.2 CGI Sheet Roofing


Toilets (Female) 1
1.00 6.95 2.71 area 18.82
1.00 6.95 2.12 area 14.71
Total 33.54 sq.m

6.3 CGI Ridge


Toilets (Female) 1
1.00 6.95 6.95
Total 6.95 r.m
6.4 Eves Board
Toilets (Female) 1
23.32 0.288 1.20 7.85 8.06
Total 8.06 k.g

6.5 Cement Board For False Ceiling


Inside the room 1 1.00 2.00 3.25 6.50
Inside the room 2 1.00 2.50 3.25 8.13
Slopped Roof 1.00 6.95 0.64 4.42
1.00 4.82 0.98 4.70
Total 23.75 sq.m

7 PLASTER/PAINTING WORKS
7.1 Internal Plaster
7.1.1 Internal Plaster on Wall (1:6)
Toilets ( Female) 1
Along grid A & B 2 3.20 1.80 11.52
Along A 1 2.20 3.00 6.60
Along grid 1 1 4.70 1.80 8.46
Along grid 2 1 2.55 1.80 4.59
On partition wall 2 3.25 1.80 11.70
Long wall 1 1.63 1.80 2.93
1 1.88 1.80 3.38
Short wall 2 0.43 1.80 1.53
Deduction
V1 -1 3.48 0.38 -0.65
V2 -1 3.48 0.33 -0.56
V3 -1 1.98 0.38 -0.37
V4 -1 1.98 0.33 -0.32
D1 -1 1.00 0.90 -0.45
D2 -1 0.90 0.90 -0.41

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
Along grid 3 1 4.70 1.95 4.57
Total 52.52 sq.m

7.1.2 Internal Plaster on Ceiling (1:4)


Toilets ( Female) 1
slab
Along corridor 1 2.24 2.24
Beam Along 1 1 4.45 0.40 1.78
Beam Along 2 1 4.45 0.90 4.01
Beam Along A 1 3.2 0.40 1.28
1 2.2 0.45 0.99
Beam Along B 1 3.2 0.40 1.28
1 2.2 0.45 0.99
Along Corridor 1 5.03 2.20 11.04
Total 23.60 sq.m

7.1.3 External Plaster


External Plaster on Beam/Column
Toilets (Female) 1
Along grid 1 1 4.70 0.40 1.88
Along grid 3 1 4.70 0.45 2.12
Along grid A 1 3.20 0.40 1.28
2.20 0.45 0.99
Along grid B 1 3.20 0.40 1.28
1 2.20 0.45 0.99
slab
Along side edge of the slab 2 2.25 0.15 0.68
Along the column 6 3.00 0.60 10.80
0.00
External Plaster on Walls
Along Grid 1 1 4.70 2.23 10.46
Along Grid 2 1 4.70 2.23 10.46
Along Grid 3 1 4.70 1.20 5.64
Along Grid A 1 5.40 2.60 14.04
Along Grid B 1 3.20 2.60 8.32
Total 68.93 sq.m

7.1.4 Internal Plaster on Wall (1:4) with Cement Punning


Inside Septic Tank Wall
Long Wall 2.00 5.20 2.25 23.40
Short Wall 2.00 1.95 2.25 8.78
Baffle wall 2.00 1.20 1.45 3.48
35.66 Sq.m

7.2 Painting works


7.2.1 Distemper painting Works
As Per Internal Plaster on Ceilings 1 23.60 23.60

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
As per internal plaster on wall 1 52.52 52.52
False Ceiling Works 1 23.75 23.75
99.87 sq.m

7.2.2 Exterior Weather Coat Paint


AS per External Plaster 1 68.93 68.93
68.93 sq.m

7.2.4 Enamel Paint


Window grill
Ventilation FrameV1 1 2.48 0.38 2.00 1.86
V2 1 2.48 0.33 2.00 1.61
V3 1 1.98 0.38 2.00 1.48
V4 1 1.98 0.33 2.00 1.28
6.23 sq.m

8 MISCELLANOUS
8.2 Cement Board
For Partition
2.00 1.69 Area 3.37
Total 3.38 sq.m

8.4 Pump Shed


1 1 1.00
Total 1.00 Nos.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Toilet Block,T(S)F
School Name : Shree Basuki Lower Secondary School
Location : Aaruarbang, Gorkha
BAR BENDING SCHEDULE
Spacing c/c Structure Length/pc. Total Weight Per Total
SN Description Shape Size (mm) Rebar Nos Remarks
(mm) Nos (mm) Length (m) Meter (Kg) Weight (Kg)
A. Foundation Mesh
Footing F1

900
a. Along Y-axis 100 12 150 6 7 1100 46.2 0.889 41.07
100

900
b. Along X-axis 100 12 150 6 7 1100 46.2 0.889 41.07
100

B. Column-MAIN BAR
465

4251
a. Longitudinal bar upto full height 12 - 6 8 5160 247.68 0.889 220.16

100 344
STIRRUPS FOR COLUMN SIZE 300 x 300 upto Plinth Height-

220
80

b Stirrups 220 8 100 6 9 1040 56.16 0.395 22.19

1
160 6
80 0
c Stirrups 8 100 6 11 800 52.8 0.395 20.86
1
6 160
0

C Column (300*300)

220
80
a Stirrups for Column upto floor Height 220 8 125 6 25 1040 156 0.395 61.63

1
160 6
80 0
b " 8 125 6 25 800 120 0.395 47.41
1
6 160
0

D BEAM
1 Foundation Beam (250*250)

5000
a Along Grid-1,2 & 3- Top Bar 720 720 12 3 3 6440 57.96 0.889 51.52

b Along Grid--1,2 & 3-Bottom Bar 720 12 3 3 6440 57.96 0.889 51.52
5000 720

6000
c Along Grid-A & B-Top Bar 720 12 3 3 7440 66.96 0.889 59.52
720

d Along Grid-Bottom Bar 12 3 3 7440 66.96 0.889 59.52


720 720
6000

200
80
e Stirrups Along Grid 1, 2 & 3 8 150 3 34 960 97.92 0.395 38.69
200

200
80
f Stirrups Along A & B 8 150 2 40 960 76.8 0.395 30.35
200

2 Plinth Beam (250*300)

Approved By:
Prepared and Submitted By: Checked By: DLPIU Engineer
Sharma-AM J/V Consultant Engineer
Spacing c/c Structure Length/pc. Total Weight Per Total
SN Description Shape Size (mm) Rebar Nos Remarks
(mm) Nos (mm) Length (m) Meter (Kg) Weight (Kg)

5000
a. Along Grid-1 -Top Bar 960 16 1 2 6920 13.84 1.580 21.88
960

5000
b 720 12 1 1 6440 6.44 0.889 5.73
720

5000
c Along Grid-1 -Bottom Bar 960 16 1 2 6920 13.84 1.580 21.88
960

5000
d 720 12 1 1 6440 6.44 0.889 5.73
720

e Along Grid-2 & 3-Top Bar 960 16 2 2 6920 27.68 1.580 43.75
5000 960

f 720 12 2 1 6920 13.84 0.889 12.31


5000 720

g Along Grid-2 & 3-Bottom Bar 960 16 2 2 6920 27.68 1.580 43.75
5000 960

h 720 12 2 1 6920 13.84 0.889 12.31


5000 720

6000
i Along Grid-A & B-Top Bar 12 2 3 7440 44.64 0.889 39.68
720 720

j Along Grid-A & B-Bottom Bar 720 12 2 4 7440 59.52 0.889 52.91
6000 720

200
80

k Stirrups Along Grid 1, 2 & 3 8 150 3 42 1360 171.36 0.395 67.70


400

200
80

l Stirrups Along Grid A & B 8 150 2 35 1360 95.2 0.395 37.61


400

3 FLOOR BEAM
LONGITUDINAL BARS
Along Grid 1,2&3

5200
a Top Bars 870 16 3 2 6940 41.64 1.580 65.81
870

5200
b Top Bars 12 3 1 6380 19.14 0.889 17.02
590 590

c Bottom Bars 350 16 3 2 5900 35.4 1.580 55.95


5200 350

d Bottom Bars 350 350 12 3 2 5900 35.4 0.889 31.47


5200

Along Grid A&B

6200
e Top Bars 12 2 3 7380 44.28 0.889 39.36
590 590

f Bottom Bars 350 12 2 4 6900 55.2 0.889 49.07


6200 350

STIRRUPS

Approved By:
Prepared and Submitted By: Checked By: DLPIU Engineer
Sharma-AM J/V Consultant Engineer
Spacing c/c Structure Length/pc. Total Weight Per Total
SN Description Shape Size (mm) Rebar Nos Remarks
(mm) Nos (mm) Length (m) Meter (Kg) Weight (Kg)

200
8
0
g Stirrups for Beam Size 250*400 350 8 125 1 93 1260 117.18 0.395 46.30

200
80

h Stirrups for Beam Size 250*450 400 8 125 1 124 1360 168.64 0.395 66.63

E SLAB

Approved By:
Prepared and Submitted By: Checked By: DLPIU Engineer
Sharma-AM J/V Consultant Engineer
Spacing c/c Structure Length/pc. Total Weight Per Total
SN Description Shape Size (mm) Rebar Nos Remarks
(mm) Nos (mm) Length (m) Meter (Kg) Weight (Kg)

850 850
a Main Bars Short Span 100 10 150 1 33 4600 151.8 0.617 93.71
100 2700

1475 1475
b Main Bars Long Span 100 10 150 1 16 8350 133.6 0.617 82.47
5200 100

c Distribution Bars Short Span 8 150 1 18 2700 48.6 0.395 19.20


2700

d Distribution Bars Long Span 8 150 1 10 5200 52 0.395 20.55


5200
F STIRRUPS FOR COLUMN SIZE 300 x 300 ( From Plinth Level to Beam Bottom Level)

220
80

a Stirrups 220 8 125 6 21 1040 131.04 0.395 51.77

1
160 6
80 0
b Stirrups 8 125 6 21 800 100.8 0.395 39.83
1
6 160
0

G SOAKPIT

d=1850+Ld

a Middle Ring 8 200 1 1 6289 6.289 0.395 2.49 L=Pi*d

d=1450+Ld

b Inner Ring 8 200 1 1 5033 5.033 0.395 1.99 L=Pi*d

c Main Bar Along both Direction 8 200 1 2 1650 3.3 0.395 1.31
1650

d " 8 200 1 4 1600 6.4 0.395 2.53


1600
e " 8 200 1 4 1440 5.76 0.395 2.28
1440

f " 8 200 1 4 1130 4.52 0.395 1.79


1130

g " 8 200 1 4 400 1.6 0.395 0.64


400

h Top Bar Along Radial Direction 8 200 1 8 425 3.4 0.395 1.35
425
H SEPTIC TANK

200
6
a Stirrups for Concealed Beam 5 8 150 1 13 670 8.71 0.395 3.45
70

1850
b 10Ø Longitudional Bar for CB-Top Bar 10 1 2 1970 3.94 0.617 2.44

60
60

c 10Ø Longitudional Bar for CB-Bottom Bar 10 1 2 1970 3.94 0.617 2.44
60 1850
60
Bed RCC Bars

d Bottom Mesh Bar-Along Length Wise 8 200 1 12 5550 66.6 0.395 26.32
50 5450
50

e Bottom Mesh Bar-Along WIdth Wise 8 200 1 28 2300 64.4 0.395 25.45
50 2200 50
f Septic Tank Slab Cover

Approved By:
Prepared and Submitted By: Checked By: DLPIU Engineer
Sharma-AM J/V Consultant Engineer
Spacing c/c Structure Length/pc. Total Weight Per Total
SN Description Shape Size (mm) Rebar Nos Remarks
(mm) Nos (mm) Length (m) Meter (Kg) Weight (Kg)

g 8Ø Bottom bar along Width wise 8 1 23 1970 45.31 0.395 17.91


60 1850 60

h 8 1 8 1050 8.4 0.395 3.32


60 930 60

i 8 1 8 450 3.6 0.395 1.43


60 330 60

1215 1475
j 8Ø Bottom bar along Length wise 8 1 9 7650 68.85 0.395 27.20
60 4840 60

1215
k 8 1 4 3780 15.12 0.395 5.98
60 2445 60

l 8 1 4 920 3.68 0.395 1.46


60 800 60

m 8 1 4 445 1.78 0.395 0.71


60 325 60

1
n Top Bars-Along Width Wise 0 8 1 8 620 4.96 0.395 1.96
0 520

o 100 8 1 8 620 4.96 0.395 1.96


520

p Top Bars-Along Length Wise 7 8 1 9 1250 11.25 0.395 4.45


5 1175

q 75 8 1 9 1250 11.25 0.395 4.45


1175

r Corner Bars 500 10 1 30 500 15 0.617 9.26

I SILL BAND
Longitudinal Bars

3400 75
800
800
a Grid 1/A-B ,Grid 3/A-B 10 75 2 2 6350 25.4 0.617 15.68
75 600 600

1175 75
1700
b Grid 2/A-B 10 1 2 2950 5.9 0.617 3.65
75

2650 75
425
425
c Grid A/1-2, B/1-2 10 2 2 4950 19.8 0.617 12.23
75
75 600 600

2150 75
175
175
d Grid A/2-3 10 1 2 3850 7.7 0.617 4.76
75
75 600 600

e Partition Wall between Grid A & Grid B 10 1 2 3600 7.2 0.617 4.45
3600

f Partition Wall between Incinerator Holes 10 1 2 1400 2.8 0.617 1.73


1400

g Partition Wall between along D3 10 1 2 900 1.8 0.617 1.12


525 375

h Partion Wall for Urinal 10 1 2 700 1.4 0.617 0.87


700

Ties

65 65
i Grid 1/A-B ,Grid 3/A-B 8 150 2 33 320 21.12 0.395 8.35
190

65 65
j Grid 2/A-B 8 150 1 20 320 6.4 0.395 2.53
190

Approved By:
Prepared and Submitted By: Checked By: DLPIU Engineer
Sharma-AM J/V Consultant Engineer
Spacing c/c Structure Length/pc. Total Weight Per Total
SN Description Shape Size (mm) Rebar Nos Remarks
(mm) Nos (mm) Length (m) Meter (Kg) Weight (Kg)

65 65
k Grid A/1-2, B/1-2 8 150 2 23 320 14.72 0.395 5.82
190

65 65
l Grid A/2-3 8 150 1 16 320 5.12 0.395 2.03
190

65 65
m Partition Wall between Grid A & Grid B 8 150 1 23 320 7.36 0.395 2.91
190

50 50
n Partition Wall between Incinerator Holes 8 150 1 9 170 1.53 0.395 0.61
70

50 50
o Partition Wall between along D3 8 150 1 7 170 1.19 0.395 0.48
70

50 50
p Partion Wall for Urinal 8 150 1 5 170 0.85 0.395 0.34
70

J Lintel Band
Longitudinal Bars

3400 75
800
800

a Grid 1/A-B ,Grid 3/A-B 10 75 2 2 6350 25.4 0.617 15.68


75 600 600

3400 75
800
800

b Grid 2/A-B 10 75 1 2 6350 12.7 0.617 7.84


75 600 600

2650 75
425
425

c Grid A/1-2, B/1-2 10 75 2 2 4950 19.8 0.617 12.23


75 600 600

2150 75
175
175

d Grid A/2-3 10 75 1 2 3850 7.7 0.617 4.76


75 600 600

e Partition Wall between Grid A & Grid B 10 1 2 3700 7.4 0.617 4.57
3600

f Partition Wall between Incinerator Holes 1400 10 1 2 1500 3 0.617 1.86

g Partition Wall between along D3 10 1 2 2950 5.9 0.617 3.65


2950

h Partion Wall for Urinal 10 1 2 700 1.4 0.617 0.87


700
Ties

65 65
i Grid 1/A-B ,Grid 3/A-B 8 150 2 33 320 21.12 0.395 8.35
190

65 65
j Grid 2/A-B 8 150 1 33 320 10.56 0.395 4.18
190

65 65
k Grid A/1-2, B/1-2 8 150 2 23 320 14.72 0.395 5.82
190

65 65
l Grid A/2-3 8 150 1 16 320 5.12 0.395 2.03
190

65 65
m Partition Wall between Grid A & Grid B 8 150 1 23 320 7.36 0.395 2.91
190

50 50
n Partition Wall between Incinerator Holes 8 150 1 10 170 1.7 0.395 0.68
70

50 50
o Partition Wall between along D3 8 150 1 21 170 3.57 0.395 1.42
70

50 50
p Partion Wall for Urinal 8 150 1 5 170 0.85 0.395 0.34
70

Approved By:
Prepared and Submitted By: Checked By: DLPIU Engineer
Sharma-AM J/V Consultant Engineer
Spacing c/c Structure Length/pc. Total Weight Per Total
SN Description Shape Size (mm) Rebar Nos Remarks
(mm) Nos (mm) Length (m) Meter (Kg) Weight (Kg)
K Wash Basin Slab
Left Portion

a At Long Side 250 8 150 1 5 2175 10.875 0.395 4.3


1825 100

b At Short Side 8 150 1 13 775 10.075 0.395 3.99


540 235

Right Side Portion

c At Long Side 8 150 1 5 2325 11.625 0.395 4.6


250 1825 250

d At Short Side 8 150 1 13 775 10.075 0.395 3.99


540 235

L Manhole Cover Slab- Septic Tank ( 2 Nos )

a Along Long and Short Direction 8 150 2 10 750 15 0.395 5.93


50 650 50

M INCINERATOR
a 630*505 Grill Mesh

b 8 mm dia bar of length 630 8 25 1 21 630 13.23 0.395 5.23


630

c 8 mm dia bar of length 505 8 25 1 26 505 13.13 0.395 5.19


505

d Precast Cover Slab-Long Bar 8 150 1 5 1000 5 0.395 1.98


1000

e Precast Cover Slab-Short Bar 700 8 150 1 7 1000 7 0.395 2.77

Total of Reinforcement Work 2127.19 Kg


2.12719 Mt.

Approved By:
Prepared and Submitted By: Checked By: DLPIU Engineer
Sharma-AM J/V Consultant Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Toilet Block,T(S)F
School Name : Shree Basuki Lower Secondary School
Location : Aaruarbang, Gorkha

Truss Calculation Details-T(S)-F


Total Total Wt.
S.N Description Notation Nos Length Breadth Thickness Wt/m Wt/m3
Length (Kg)
1 Top Chord TP dia 40 M 3 4.665 13.995 5.03 70.4
2 Bottom Chord BC dia 40 M 3 3.75 11.25 3.56 40.05
3 Vertical Strut VS dia 40 M 3 0.561 1.683 3.56 6.00
4 Diagonal Strut DS dia 32 M 6 0.912 5.472 3.1 16.97
5 Purlin P dia 50 1 47.6 47.6 5.06 240.86
6 Truss Base Plate TBP 10 mm 12 0.25 3 0.25 0.01 7850 58.88
7 Truss Cleat for Purlin TCP 10 mm 140 0.2 28 0.09 0.01 7850 197.82
8 Purlin Eves Plate PEP 3 mm 12 0.125 1.5 0.075 0.003 7850 2.65
9 Truss Eves Plate TEP 3 mm 6 0.125 0.75 0.06 0.003 7850 1.06
10 Anchor Bolt AB 16 dia 16 0.45 7.2 1.58 11.38
11 Truss Base Plate Support SC 10 mm 12 0.114 1.368 0.025 0.01 7850 2.69
12 Runner Purlin Cleat RPC 10 mm 4 0.175 0.7 0.07 0.01 7850 3.85
13 Purlin Cleat 10 mm 16 0.175 2.8 0.075 0.01 7850 16.49
14 Truss Support Cleat 10 mm 32 0.063 2.016 0.04 0.01 7850 6.34
15 Runner Pipe NB 40 1 6.8 6.8 3.56 7850 24.21
Total of Truss Work 699.65

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Toilet Block,T(S)F
School Name : Shree Sarbodaya Lower Secondary School
Location : Choprak,Gorkha

Toilet
S. No. Description Quantity Unit Remarks
Block
A. Common Installation
1.2 Stand Alone 6 A DP MCB with Enclosure 1 1.00 nos.
B School Blocks
1 DISTRIBUTION BOARDS nos.
1.4 Stand Alone 6 A DP MCB with Enclosure 1.00 1.00 nos.
3.1 One Way Light Point 5.00 5.00 pts.
6 Sweep Ceiling/Exhaust Fans/ Wall Fan
6.1 225mm dia M/D Exhaust Fan 2 2.00 no.
7 Light Fixtures/Luminaires & Accessories
7.5 7W LED Wall Light 1.00 1.00 no.
7.6 9W LED Surface Mounted Cylindrical type 1.00 1.00 no.
7.7 6W LED Recessed Mounted Circular type 3.00 3.00 no.
7.8 7W LED T5 Slim Mirror Light 1.00 1.00 no.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: T(S)F
School Name : Shree Basuki Lower Secondary School
Location : Aruarbang, Gorkha
Length
S. No. Description No. Quantity Unit Remarks
(m)
1 WATER SUPPLY INSTALLATION
a CPVC pipes SDR-11
40 mm 1 55 55.00 r.m
25mm 1 9 9.00 r.m
20mm 1 10 10.00 r.m
15mm 1 3 3.00 r.m
c CPVC Ball Valve
40 mm 2 2.00 nos.
25 mm 3 3.00 nos.
20mm 2 2.00 nos.
d 40mm dia Gun Metal Check Valve 1 1.00 nos.
e Electrical Centrifugal Water Pump 1 1.00 nos.
f 2000 litres Capacity Water Storage Tank 1 1.00 nos.
2 Sewer, Rain and Waste Water Installation
110 mm 1 32 32.00 r.m
75mm 1 25 25.00 r.m
50mm 1 2 2.00 r.m
B School Blocks
1 Sanitary Installation
a Water Closet Set 1 1.00 set
b Orissa Pan 2 2.00 set
c Hand Wash Basin 1 1.00 set
d Ladies Urinal 2 2.00 set
e Self Closing Bib Cock 6 6.00 nos.
f CP Spreader in Urinal 2 2.00 set
g Toilet Paper Holder 1 1.00 nos.
h Commode Spray 1 1.00 nos.
i PVC Multi Floor Trap 5 5.00 nos.
j Waste Coupling and PVC Bottle Trap 2 2.00 nos.
k 40mm SS Grab Bar-Side 1 1.00 nos.
l 40mm SS Grab Bar-Rear 1 1.00 nos.
m CP Foldable Hinge 2 2.00 nos.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Site Development
School Name : Shree Basuki Lower Secondary School
Location : Aaruarbang, Gorkha

Length Breadth Height


S.No Description No. Qty. Unit Remarks
(m) (m) (m)
1 Earthworks
1.1 Site Clearance
Infront of Bldg 1 105.08 Area 105.08
Way to Toilet Block 1 70.00 Area 70.00
Total 175.08 sq.m
1.2 Earth Work Excavation
Infront of Bldg 1 105.08 Area 0.15 15.76
Way to Toilet Block 1 70.00 Area 0.15 10.50
Around Gate Column 1 12.70 Area 0.15 1.91

Excavation For Boundary Wall


Chain Link Fence 51 0.15 0.15 0.60 0.69
Excavation For Gate Column
Column 2 1.20 1.20 1.50 4.32
Excavation For Flag Pole
Flag Pole 2 0.60 0.60 1.00 0.72
2 1.10 0.50 0.15 0.17
2 1.60 0.25 0.15 0.12
1 0.60 0.40 0.15 0.04
Total 34.22 cu.m

1.3 Earth Back Filling


Total Excavation Work 1 6.05 6.05
Deduction
Soling -1 0.32 -0.32
PCC -1 0.55 -0.55
RCC -2 0.90 0.90 0.25 -0.41
-2 0.30 0.30 0.95 -0.17
4.60 cu.m

1.4 Boulder Soling


Infront of Bldg 1 21.35 3 0.15 9.61
Way to Toilet Block 1 33.25 1.5 0.15 7.48

Gravel Sand packing


Chain Link Fence 51 0.15 0.15 0.53 0.60
Soling For Gate Column
Column 2 0.90 0.90 0.20 0.32
Stone Soling for Flag Pole 1 0.70 0.80 0.35 0.20
Total 18.22 cu.m
2 Concrete Works
2.1 PCC
2.1.1 P.C.C.(1:3:6) Works
PCC For Gate Column
Column 2 0.90 0.90 0.08 0.12
PCC For Flag Pole
Flag Pole 2 0.30 0.30 1.20 0.22
1 2.40 0.80 0.10 0.19
2 0.30 0.30 0.08 0.01

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S.No Description No. Qty. Unit Remarks
(m) (m) (m)
Total 0.55 cu.m
2.1.2 P.C.C.(1:2:4) Works
Infront of Bldg 1 21.35 3 0.13 8.01
Way to Toilet Block 1 33.25 1.5 0.13 6.23
Total 14.25 cu.m
2.2 P.C.C For R.C.C. Works
R.C.C. Works M20
A Foundation
Gate Column Footing
Footing 2 0.90 0.90 0.25 0.41

B Column
Gate Column 2 0.30 0.30 2.95 0.53
Top RCC Coping 2 0.60 0.60 0.05 0.04
2 0.175 0.05 0.02
Total 0.99 cu.m

2.3 Silica Cement Admixture


10 Kg per cu.m. of R.C.C. M20 10.00 0.99 9.90
Total 9.90 Kg

2.4 Steel Reinforcement 1 106.90 106.9


Total 106.90 Kg
0.11 Tons
2.5 Formworks
Entrance Gate-Foundation 2 3.60 0.35 2.52
Gate Column 2 1.20 3.15 7.56
Flag Pole Steps 2 0.25 0.80 0.4
Flag Pole Masonry Top Surface 1 1.70 0.50 0.85
Total 11.33 sq.m

3 Brick Masonary Works


3.2 Full Brick (230 mm) Works (1:4c/s)
Gate Column 2 0.54 0.23 1.85 0.46
2 0.3 0.23 0.45 0.06
Flag Pole Base 2 0.8 0.23 0.55 0.20
Total 0.53 cu.m

4 Flooring Works
4.1 Neat Cement Skirting works
Gate Column 2 2.36 4.72
Total 4.72 r.m

5 Metal Works
5.1 Metal Works (Fence)
Total
Description Nos length Kg/m Total
Length
Chain Link Fence
ISA 40x40x4mm 2 115 230.00 2.40 552.00
ISA 50x50x5mm 51 1.90 96.90 3.80 368.22
Bracings 19 2.5 47.50 2.40 114.00
Sub Entrance Gate
ISA 40x40x4mm 3 1.5 4.50 2.40 10.80
ISA 50x50x5mm 2 1.90 3.80 3.80 14.44

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S.No Description No. Qty. Unit Remarks
(m) (m) (m)
Incinerator Vent Pipe 1 2.416 17.5 42.28 M=17.5 Kg/m
Total 1,101.74 k.g

5.2 Metal work (Entrance Gate)


Metal Gate
50mm Dia MS Pipe 2 7.13 14.26 3.61 51.48
25mm Dia MS Pipe 56 0.7 39.2 1.58 61.94
Middle sheet 1 0.74 0.0012 7850 6.97
Hole Fast 4 0.45 1.8 3.61 2.92
Total 123.31 k.g

5.3 Chain Link Fence(50x50 Mesh)


Fencing 1.00 121 1.20 145.20
Total 145.20 sq.m

6.1 External Plaster


Column Inside face 4 0.54 1.64 3.54
Column Outside face 2 1.2 0.20 0.48
4 0.54 1.70 3.67
Deduct -2 0.3 1.40 -0.84
Top Coping 2 2.36 0.05 0.24
4 0.59 0.30 0.71
Total 7.80 sq.m

7 Exterior Weather Coat Paint


As per Outside Plaster 1 7.8 7.80
Gate Column Skirting 2 2.36 0.10 0.47
Total 8.28 sq.m

8 Flag Pole
75 Dia GI Pipe 2.00 1 2.00
Total 2.00 nos

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Site Development
School Name : Shree Basuki Lower Secondary School
Location : Aaruarbang, Gorkha
Total
Size Spacing Structure Rebar Length/pc. Total Weight Per
SN Description Shape Weight Remarks
(mm) c/c (mm) Nos Nos (mm) Length (m) Meter (Kg)
(Kg)
1 Entrance Gate-Column
75 75
a 900*900 Foundation Mesh 850 10 150 2 12 1000 24 0.62 14.82

8-12 dia Column


b 12 2 8 3770 60.32 0.89 53.62
Reinforcement 3050+Ld

220
8 mm dia at 150 c/c for
c 7
8 150 2 26 1030 53.56 0.40 21.16
column stirrups-Outer 5 220

1
7
7 3
8 mm dia at 150 c/c for 5
d 8 150 2 26 842 43.784 0.40 17.3
column stirrups-Outer

Total of Reinforcement Work 106.90 Kg


0.11 Mt.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Job : Reservoir Water Tank
School Name : Shree Basuki Lower Secondary School
Location : Aaruarbang, Gorkha

Length Breadth Height


S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
1 Earthworks
1.1 Site Clearance & Mobilization
For Water Tank 1 4.85 4.6 22.31
Total 22.31 sq.m

1.2 Earthwork in excavation


For Water Tank 1 3.65 3.40 1.98 24.57
Total 24.57 Cu.m.

1.3 Earthback Filling


Total Earthwork Excavated 24.57
Water Tank Volume -1 3.35 3.1 1.98 -20.56
Total 4.01 Cu.m.

1.4 Boulder soling


Below Water Tank 1 3.35 3.1 0.2 2.077
Total 2.08 Cu.m.

2 Concrete Works
2.1 PCC
2.1.1 PCC Work (1:3:6)
Below Water Tank 1 3.35 3.1 0.075 0.78
Total 0.78 Cu.m.

2.2 PCC for RCC Work 1:1.5:3


For Base Slab 1 3.35 3.10 0.18 1.82
For Water Tank Wall
Long Wall 2 3.35 0.18 1.68 1.96
Short Wall 2 2.75 0.18 1.68 1.61
Trianagle Portion
Long Wall 2 3.00 0.05 Area 0.27
Short Wall 2 2.75 0.05 Area 0.25
Slab 1 3.35 3.1 0.15 1.56
Manhole openings -1 0.6 0.6 0.15 -0.05
Total 7.41 Cu.m.

2.3 Silica Admixture


10 Kg per cu.m. of R.C.C. M20 10 7.41 74.15
Total 74.15 kg

2.5 Form works


For Base Slab 1 12.9 0.18 2.26
For Water Tank Wall
Outer Side
Long Wall 2 3.35 1.83 12.23
Short Wall 2 3.10 1.83 11.32
Inside wall

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Length Breadth Height
S. No. Description No. Quantity Unit Remarks
(m) (m) (m)
Long Wall 2 3.00 1.53 9.15
Short Wall 2 2.75 1.53 8.39
Trianagle Portion
Long Wall 2 3.00 0.42 2.54
Short Wall 2 2.75 0.42 2.33
Slab 1 3 2.75 8.25
Side for Manhole openings 1 2.4 0.15 0.36
Deduct Manhole openings -1 0.6 0.60 -0.36
Total 56.46 Sq.m.

3 PLASTERING WALL FINISHING WORKS


3.1.1 CEMENT PLASTER WORKS WITH
PUNNING
Base Slab 1 2.40 2.15 5.16
For Water Tank Wall
Long Wall 2 3.00 1.53 9.15
Short Wall 2 2.75 1.53 8.39
Triangle Portion
Long Wall 2 3.00 0.42 2.54
Short Wall 2 2.75 0.42 2.33
Top Slab 1 3.00 2.75 8.25
Deduct Manhole openings -1 0.6 0.60 -0.36
Total 35.46 Sq.m.

4 Water Proof Coating


Inside Water tank 1 35.46
Total 35.46 sq.m

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Job : Reservoir Water Tank
School Name : Shree Basuki Lower Secondary School
Location : Aaruarbang, Gorkha
Bar Bending Schedule
Cut Total
Dia. of No. of Wt/m Weight
S. No. Description No. Length Length Bar Shape
Bar (mm) Bars (Kg) (Kg)
(m) (m)
A Outer Vertical Bars 1
1 Shorter Span 10 35 7.01 245.35 0.62 152.12 0.083 0.083

1.915 1.915

3.02

2 Longer span 10 32 7.286 233.152 0.62 144.55


0.083 0.083

1.915 1.915

3.29

B Inner Vertical Bars 2


1 Shorter Span 10 35 2.503 175.21 0.62 108.6302 0.079 0.079

1.884 1.884

0.05
0.49 0.49

2 Longer Span 10 32 2.503 170.204 0.62 105.5265 0.079 0.079

1.884 1.884

0.05
0.49 0.49

C. Extra Bars 2 10 67 1.79 239.86 0.62 148.71 0.6 0.6

0.592
0.592 0.6 0.6

D. Horizontal Bars(outer 4
0.3 0.3
1 Shorter Span 10 21 3.62 304.08 0.62 188.5296

3.02 3.02

0.3 0.3

2 Longer Span 10 21 3.87 325.08 0.62 201.5496 0.3 0.3

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Cut Total
Dia. of No. of Wt/m Weight
S. No. Description No. Length Length Bar Shape
Bar (mm) Bars (Kg) (Kg)
(m) (m)
3.27 3.27

0.3 0.3
E. Base Slab bar 4
1 Shorter Span 10 35 3.14 439.6 0.62 272.55 3.045
0.05 0.05

2 Longer Span 10 31 3.42 424.08 0.62 262.93 3.32


0.05 0.05
F Man Hole Rebar
1 horizontal Rebar -2 10 6 1.2 -14.4 0.62 -8.93 0.9 0.3
Total 1576.17 Kg
1.58 Mt.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer