SUMMARY.
APPROVED B.S.R FOR THE 1st HALF 0F 2020 IN VAVUNIYA
11 - PLASTERER.
5 Cove moulding 2 1/2" x 2 1/2" in cement mortar 1:2 5/90 L.ft 105.00
built inexisting wall. L.m 344.00
6 Lime plastering 5/8" thick 2:5 finished smooth. 6/91 Sqr 7,122.00
m2 766.00
10 Rendering, cement 3/4", 1:2 with 5% Pudlo Cement. 16/94 Sqrs 9,855.00
m2 1,061.00
13 Plaster bands laid over tiles 4" to 6" wide on roof in 19/95 L.ft 68.00
cement & lime mortar.1:1:4 L.m 222.00
****
5 Cove moulding 2 1/2" x 2 1/2" in cement mortar 1:2 built in existing wall.
Per 100.0 L.ft.
1.10 Cwt Cement 1,075.00 1,182.50
0.03 Cube Sand 10,188.00 305.64
2 1/2 day Mason 1,650.00 4,125.00
2 1/2 day Labourer 1,450.00 3,625.00 9,238.14
Overheads 14% 1,293.34
Per 100 L.ft 10,531.48
Per L.ft 105.31
Say per L.ft. 105.00
Per L.m. 344.40
Say per L.m 344.00
8 Skirting in cement mortar 1:3, 1/2"x6" projected or flush with wall, &
including forming groove.
9 3/8" thick plastering to R.C.C. beams,slab soffit in cement & sand 1:3
finished smooth
Per Sqrs.
0.8 Cwts Cement 1,075.00 860.00
.05 Cub. Sand 10,188.00 509.40
1 3/4 Day Mason 1,650.00 2,887.50
2 Day Labourer 1,450.00 2,900.00
Allow for scaffolding 5% of labour 289.38 289.38
Allow for water 50.00 50.00
0.05 Cube Sand 10,188.00 509.40 8,005.68
Over heads 14% 1,120.79
Per square 9,126.47
Say per sqrs 9,126.00
Per m2 982.40
Say per m2 982.00
11 Skirting in cement mortar 1:3, 1/2"x4" projected or flush with wall, &
including forming groove.
Per 10.0 L.ft.
0.22 Cu.ft Sand 10,188.00 22.41
0.07 Cwts Cement 1,075.00 75.25
1.75 Hour Mason 1,650.00 360.94
1.75 Hour Labourer 1,450.00 317.19 775.79
Over heads 108.61
Per 10 L.ft 884.40
Per L.ft 88.44
Say per L.ft. 88.00
Per L.m. 289.97
12 Skirting in cement mortar 1:3, 1/2"x4" projected or flush with all finished
with Red cement floating, including forming groove.
Per 10.0 L.ft.
As in Item 14 775.79 775.79
0.07 Kg Add for Red cement 500.00 35.00
1/2 Hour Mason 1,650.00 103.13 913.91
Over heads 127.95
Per 10 L.ft 1,041.86
Per L.ft 104.19
Say per L.ft. 104.00
Per L.m. 341.59
Say per L.m. 342.00
16 5/8" Thick plastering to wall in lime and sand 2.5 including floating
with lime putty
Per Square
Materials
1.30 Cwt slaked lime 800.00 1,040.00
0.07 cubes sand 10,188.00 713.16
water 10 glas. 3.00 30.00
Labour
1 Day Mason 1,650.00 1,650.00
1 3/4 Days U/Sk Labourer 1,450.00 2,537.50
Scaffolding;-
1 set 50% use 300.00 150.00
6,120.66
Add 14% Overhead 856.89
Rate per Square 6,977.55
Say Sqr. 6,978.00
Rate per m2 751.08
Say m2 751.00
17 5/8" Thick plastering to wall in cement sand 1:3 including cement
floating
Per Square
Materials
1.40 cwt cement (50 kg. bags) 1,075.00 1,505.00
0.06 Cube sand 10,188.00 611.28
Water 10 glas 3.00 30.00
Labour
18 3/8" Thick plastering to sofit slab in cement and sand 1:3 including
floating with lime putty
Per Square
Materials
0.80 Cwt. Cement (50 Kg Bags) 1,075.00 860.00
0.16 Cwt slaked lime 800.00 128.00
0.05 cubes sand 10,188.00 509.40
Water 5 gls. 3.00 15.00
Labour
2 1/2 Days Mason 1,650.00 4,125.00
2 1/2 Days u/Sk Labourer 1,450.00 3,625.00
Scaffolding:-
2 Set- 100% use 300.00 600.00
9,862.40
Add 14% Overhead 1,380.74
Rate per Square 11,243.14
Say Sqr. 11,243.00
Rate per m2 1,210.24
Say m2 1,210.00
19 3/8" Thick plastering to sides and soffit of beams in cement sand 1:3
including floating with lime putty
Per square
Materials
0.80 Cwt Cement (50 Kg bags) 1,075.00 860.00
0.16 Cwt slaked lime 800.00 128.00
0.05 Cubes sand 10,188.00 509.40
Water 5 Gls. 3.00 15.00
Labour
2 Days Mason 1,650.00 3,300.00
2 Days U/Sk Labourer 1,450.00 2,900.00
Scaffolding:-
2 sets - 100% use 300.00 600.00
8,312.40
Add 14% Overhead 1,163.74
Rate per Square 9,476.14
Say Sqr. 9,476.00
Rate per m2 1,020.04
Say m2 1,020.00
20 5/8" Thick to wall in lime cement and sand 1:1:5 finished semi
rough with wooden float
Per square
Materials
0.80 Cwt Cement (50 Kg bags) 1,075.00 860.00
0.40 Cwt slaked lime 800.00 320.00
0.07 Cubes sand 10,188.00 713.16
water 10 gls. 3.00 30.00
Labour
1 Day Mason 1,650.00 1,650.00
1 1/4 days u/sk Labourer 1,450.00 1,812.50
scaffolding;-
1 set - 50% use 300.00 150.00
5,535.66
Add 14% Overhead 774.99
Rate per Square 6,310.65
Say Sqr. 6,311.00
Rate per m2 679.30
Say m2 679.00
21 5/8' Thick plastering to wall in lime cement and sand 1;1:5 finished
smooth with lime putty floating
Per square
Materials
0.80 Cwt cement (50 Kg. bags) 1,075.00 860.00
0.60 Cwt slacked lime 800.00 480.00
0.07 Cubes sand 10,188.00 713.16
Water (10 Glas.) 3.00 30.00
Labour
1 1/2 Days Mason 1,650.00 2,475.00
1 1/2 Days U/Sk Labourer 1,450.00 2,175.00
scaffolding;- 300.00 225.00
1 set - 75% use 6,958.16
Add 14% Overhead 974.14
Rate per Square 7,932.30
Say Sqr. 7,932.00
Rate per m2 853.85
Say m2 854.00
Per square
Materials
1.07 Cwt cement (50 kg. bags) 1,075.00 1,150.25
0.05 Cube sand 10,188.00 509.40
water 10 gls 3.00 30.00
Labour
1 Day Mason 1,650.00 1,650.00
1 1/2 Day u/sk Labourer 1,450.00 2,175.00
1/4 Day u/sk Labourer (curing) 1,450.00 362.50
5,514.65
Add 14% Overhead 772.05
Rate per Square 6,286.70
Say Sqr. 6,287.00
Rate per m2 676.72
Say m2 677.00
23 1/2' Thick rendering in cement and sand 1:2 in floors, finished smooth
Per square
Materials
1.66 Cwt cement (50 Kg. bags) 1,075.00 1,784.50
0.05 Cubes sand 10,188.00 509.40
Water 10 Gls. 3.00 30.00
Labour
1 Day Mason 1,650.00 1,650.00
1 1/2 Days u/sk Labourer 1,450.00 2,175.00
1/4 Day U/Sk Labourer (curing) 1,450.00 362.50
6,511.40
Add 14% Overhead 911.60
Rate per Square 7,423.00
Say Sqr. 7,423.00
Rate per m2 799.03
Say m2 799.00
Per square
Materials
1.75 Cwt Cement (50 kg. bags) 1,075.00 1,881.25
0.08 Cube sand 10,188.00 815.04
Water 10 gls. 3.00 30.00
Labour
1 1/4 Days Mason 1,650.00 2,062.50
2 Days U/Sk Labourer 1,450.00 2,900.00
1/4 Days u/Sk Labourer (curing) 1,450.00 362.50
8,051.29
Add 14% Overhead 1,127.18
Rate per Square 9,178.47
Say Sqr. 9,178.00
Rate per m2 987.99
Say m2 988.00
25 3/4" Thick rendering in cement and sand 1:2 in floors finished smooth
Per square
Materials
2.25 Cwt Cement (50 Kg bags) 1,075.00 2,418.75
0.08 Cubes sand 10,188.00 815.04
Water 10 Gls. 3.00 30.00
Labour
1 1/4 Day Mason 1,650.00 2,062.50
2 Days U/sk Labourer 1,450.00 2,900.00
1/4 Day U/sk Labourer (curing) 1,450.00 362.50
8,588.79
Add 14% Overhead 1,202.43
Rate per Square 9,791.22
Say Sqr. 9,791.00
Rate per m2 1,053.95
Say m2 1,054.00
Per square
Materials
2.25 Cwt Cement (50 Kg bags) 1,075.00 2,418.75
0.08 Cubes sand 10,188.00 815.04
5 lbs powdered pigment 172.00 860.00
Water 10 Gls. 3.00 30.00
Labour
1 1/4 Day Mason 1,650.00 2,062.50
2 Days U/sk Labourer 1,450.00 2,900.00
1/4 Day U/sk Labourer (curing) 1,450.00 362.50
9,448.79
Add 14% Overhead 1,322.83
Rate per Square 10,771.62
Say Sqr. 10,772.00
Rate per m2 1,159.49
Say m2 1,159.00
Per 10 L.ft
Materials
0.10 Cwt Cement (50 kg bags) 1,075.00 107.50
0.003 cube sand 10,188.00 30.56
0.1 kg red cement 500.00 125.00
Labour
3/8 Days mason 1,650.00 618.75
5/16 Day U/Sk labourer 1,450.00 453.13
1,334.94
252
229,320.00
62,500.00
20 IN VAVUNIYA
750