SUMMARY.
APPROVED B.S.R FOR THE 1st HALF 0F 2020 IN VAVUNIYA

11 - PLASTERER.

NO DESCRIPTION OF WORK BSR NO UNIT RATE

1 Cement lime plastering 1:1:5, 5/8" thick. 1/89 Sqr 6,275.00


m2 675.00

2 Cement plastering 1:4, 5/8" thick. 2/89 Sqr 6,177.00


finish semi rough m2 665.00

3 Cement plastering 1:3, 5/8" thick. 3/90 Sqr 6,570.00


finish semi rough m2 707.00

4 Reveals plastering 1:3, 5/8" thick. 4/90 L.ft 58.00


not exceeding 6" wide. L.m 190.00

5 Cove moulding 2 1/2" x 2 1/2" in cement mortar 1:2 5/90 L.ft 105.00
built inexisting wall. L.m 344.00

6 Lime plastering 5/8" thick 2:5 finished smooth. 6/91 Sqr 7,122.00
m2 766.00

7 Rendering,cement floating coat,using red cement 11/92 Sqrs 1,208.00


finished smooth with carborandum stone. m2 130.00

8 Skirting in cement mortar 1:3, 1/2"x6" projected or 12/93 L.ft 127.00


flush with wall, & including forming groove. L.m 415.00

9 3/8" thick plastering to R.C.C. beams,slab soffit in 15/94 Sqrs 9,126.00


cement & sand 1:3 finished smooth m2 982.00

10 Rendering, cement 3/4", 1:2 with 5% Pudlo Cement. 16/94 Sqrs 9,855.00
m2 1,061.00

11 Skirting in cement mortar 1:3, 1/2"x4" projected or 17/95 L.ft 88.00


flush with wall, & including forming groove. L.m 290.00

12 Skirting in cement mortar 1:3, 1/2"x4" projected or 18/95 L.ft 104.00


flush with all finished with Red cement floating, L.m 342.00
including forming groove.

13 Plaster bands laid over tiles 4" to 6" wide on roof in 19/95 L.ft 68.00
cement & lime mortar.1:1:4 L.m 222.00

14 1/2" thick cement plastering 1:4 mix Sqr 5,825.00


m2 627.00

B.S.R. - 2020 1st Half Vavuniya 11. Plasterer


2

NO DESCRIPTION OF WORK BSR NO UNIT RATE


15 3/4" Thick DPC, in cement sand 1:2 finished with 2 coats
hot tar and bliended with sand Sqr 11,075.00
m2 1,192.00
16 5/8" Thick plastering to wall in lime and sand 2.5
including floating with lime putty Sqr 6,978.00
m2 751.00
17 5/8" Thick plastering to wall in cement sand 1:3 including
cement floating Sqr 6,978.00
m2 751.00
18
3/8" Thick plastering to sofit slab in cement and sand 1:3
including floating with lime putty Sqr 11,243.00
m2 1,210.00
19
3/8" Thick plastering to sides and soffit of beams in
cement sand 1:3 including floating with lime putty Sqr 9,476.00
m2 1,020.00
20 5/8" Thick to wall in lime cement and sand 1:1:5 finished
semi rough with wooden float Sqr 6,311.00
m2 679.00
21 5/8' Thick plastering to wall in lime cement and sand
1;1:5 finished smooth with lime putty floating Sqr 7,932.00
m2 854.00
22 1/2" Thick rendering in cement and sand 1:3 finished
smooth Sqr 6,287.00
m2 677.00
23 1/2" Thick rendering in cement and sand 1:2 in floors,
finished smooth Sqr 7,423.00
m2 799.00
24 3/4" Thick rendering in cement and sand 1;3 finished
smooth Sqr 9,178.00
m2 988.00

25 3/4" Thick rendering in cement and sand 1:2 in floors


finished smooth Sqr 9,791.00
m2 1,054.00

26 3/4" Thick rendering in cement sand 1:2 in coloured


cement floors finished smooth Sqr 10,772.00
m2 1,159.00

27 1/2" x 6" skirting in cement and sand 1;3 projected or


flush to walls finished with floating including forming
groove L.ft 152.00
Lm 499.00

B.S.R. - 2020 1st Half Vavuniya 11. Plasterer


3

****

B.S.R. - 2020 1st Half Vavuniya 11. Plasterer


1

RATE ANALYSIS 1st HALF OF 2020 IN VAVUNIYA


'11 - PLASTERER.
No Qty Unit Description Unit Rate Rate Amount
1 Cement lime plastering 1:1:5, 5/8" thick.
finish semi rough with lime putty
Per Sqrs.
0.80 Cwts Cement 1,075.00 860.00
20 K.g Lime 18.00 360.00
0.07 Cube Sand 10,188.00 713.16
3/4 Day Mason 1,650.00 1,237.50
Allow for scaffolding 108.75 108.75
Allow for water 50.00 50.00
1 1/2 Day Labourer 1,450.00 2,175.00 5,504.41
Over heads 14% 770.62
Per square 6,275.03
Say per sqrs 6,275.00
Per m2 675.46
Say per m2 675.00

2 Cement plastering 1:4, 5/8" thick.


finish semi rough
Per Sqrs.
1.15 Cwts Cement 1,075.00 1,236.25
0.06 Cube Sand 10,188.00 611.28
3/4 Day Mason 1,650.00 1,237.50
Allow for scaffolding 108.75 108.75
Allow for water 50.00 50.00
1 1/2 Day Labourer 1,450.00 2,175.00 5,418.78
Over heads 14% 758.63
Per square 6,177.41
Say per sqrs 6,177.00
Per m2 664.95
Say per m2 665.00

3 Cement plastering 1:3, 5/8" thick. finish semi rough


Per Sqrs.
1.47 Cwts Cement 1,075.00 1,580.25
0.06 Cube Sand 10,188.00 611.28
3/4 Day Mason 1,650.00 1,237.50
Allow for scaffolding 108.75 108.75
Allow for water 50.00 50.00
1 1/2 Day Labourer 1,450.00 2,175.00 5,762.78
Over heads 14% 806.79
Per square 6,569.57
Say per sqrs 6,570.00
Per m2 707.17
Say per m2 707.00
4 Reveals plastering 1:3, 5/8" thick.not exceeding 6" wide.

Per 200.0 L.ft


1.47 Cwts Cement 1,075.00 1,580.25
0.06 Cube Sand 10,188.00 611.28
2 1/2 Day Mason 1,650.00 4,125.00

B.S.R. - 20201st Half Vavuniya 11. Plasterer


2

Allow for water 50.00 50.00


Allow for scaffolding 150.00 150.00
2 1/2 Day Labourer 1,450.00 3,625.00 10,141.53
Over heads 14% 1,419.81
Per 200.0 L.ft 11,561.34
Say per L.ft 58.00
Per L.m 190.24
Say per L.m 190.00

5 Cove moulding 2 1/2" x 2 1/2" in cement mortar 1:2 built in existing wall.
Per 100.0 L.ft.
1.10 Cwt Cement 1,075.00 1,182.50
0.03 Cube Sand 10,188.00 305.64
2 1/2 day Mason 1,650.00 4,125.00
2 1/2 day Labourer 1,450.00 3,625.00 9,238.14
Overheads 14% 1,293.34
Per 100 L.ft 10,531.48
Per L.ft 105.31
Say per L.ft. 105.00
Per L.m. 344.40
Say per L.m 344.00

6 Lime plastering 5/8" thick 2:5 finished smooth.


Per Sqrs.
0.07 Cube Sand 10,188.00 713.16
65 K.g Slaked lime 18.00 1,170.00
1 Day Mason 1,650.00 1,650.00
Allow for scaffolding 126.88 126.88
Allow for water 50.00 50.00
1 3/4 Day Labourer 1,450.00 2,537.50 6,247.54
Over heads 14% 874.65
Per square 7,122.19
Say per sqrs. 7,122.00
Per m2 765.66
Say per m2 766.00

7 Rendering, cement, floating coat, using Red cement finished smooth.


Per Sqrs.
8 Kg Grey cement 1,075.00 172.00
1 Kg Red cement 500.00 500.00
1 Hour Mason 1,650.00 206.25
1 Hour Labourer 1,450.00 181.25 1,059.50
Over heads 14% 148.33
Per Square 1,207.83
Say per sqrs. 1,208.00
Per m2 130.01
Say per m2 130.00

8 Skirting in cement mortar 1:3, 1/2"x6" projected or flush with wall, &
including forming groove.

B.S.R. - 20201st Half Vavuniya 11. Plasterer


3

1/3 Cu.ft Sand 10,188.00 33.96


0.1 Cwts Cement 1,075.00 107.50
2 1/2 Hour Mason 1,650.00 515.63
2 1/2 Hour Labourer 1,450.00 453.13 1,110.21
Over heads 155.43
Per 10 L.ft 1,265.64
Per L.ft 126.56
Say per L.ft. 127.00
Per L.m. 415.13
Say per L.m. 415.00

9 3/8" thick plastering to R.C.C. beams,slab soffit in cement & sand 1:3
finished smooth
Per Sqrs.
0.8 Cwts Cement 1,075.00 860.00
.05 Cub. Sand 10,188.00 509.40
1 3/4 Day Mason 1,650.00 2,887.50
2 Day Labourer 1,450.00 2,900.00
Allow for scaffolding 5% of labour 289.38 289.38
Allow for water 50.00 50.00
0.05 Cube Sand 10,188.00 509.40 8,005.68
Over heads 14% 1,120.79
Per square 9,126.47
Say per sqrs 9,126.00
Per m2 982.40
Say per m2 982.00

10 Rendering, cement 3/4", 1:2 with 5% Pudlo Cement.


Per Sqrs.
2.25 Cwts Cement 1,075.00 2,418.75
0.0725 Cube Sand 10,188.00 738.63
1.00 Day Mason 1,650.00 1,650.00
10 Gls. Allow for water 1.50 15.00
2.25 Day Labourer 1,450.00 3,262.50
5.600 Kg Pudlo Cement 5% 100.00 560.00 8,644.88
Over heads 1,210.28
Per Square 9,855.16
Say per sqrs 9,855.00
Per m2 1,060.84
Say per m2 1,061.00

11 Skirting in cement mortar 1:3, 1/2"x4" projected or flush with wall, &
including forming groove.
Per 10.0 L.ft.
0.22 Cu.ft Sand 10,188.00 22.41
0.07 Cwts Cement 1,075.00 75.25
1.75 Hour Mason 1,650.00 360.94
1.75 Hour Labourer 1,450.00 317.19 775.79
Over heads 108.61
Per 10 L.ft 884.40
Per L.ft 88.44
Say per L.ft. 88.00
Per L.m. 289.97

B.S.R. - 20201st Half Vavuniya 11. Plasterer


4

Say per L.m. 290.00

12 Skirting in cement mortar 1:3, 1/2"x4" projected or flush with all finished
with Red cement floating, including forming groove.
Per 10.0 L.ft.
As in Item 14 775.79 775.79
0.07 Kg Add for Red cement 500.00 35.00
1/2 Hour Mason 1,650.00 103.13 913.91
Over heads 127.95
Per 10 L.ft 1,041.86
Per L.ft 104.19
Say per L.ft. 104.00
Per L.m. 341.59
Say per L.m. 342.00

13 Plaster bands laid over tiles 4" to 6" wide on roof in


cement & lime mortar.1:1:4
Per 20.0 L.ft.
0.01 Cube Sand 10,188.00 101.88
0.16 Cwt Cement 1,075.00 172.00
3.33 Kg Lime 18.00 59.94
1.50 Hrs Mason 1,650.00 309.38
3.00 Hrs Labourer 1,450.00 543.75 1,186.95
Over heads 166.17
Per 20 L.ft 1,353.12
Per L.ft 67.66
Say per L.ft. 68.00
Per L.m. 221.82
Say per L.m. 222.00

14 1/2" thick cement plastering 1:4 mix


Per Sqr
0.90 Cwt Cement 1,075.00 967.50
5.00 C.ft Sand 101.88 509.40
0.75 Day Mason 1,650.00 1,237.50

B.S.R. - 20201st Half Vavuniya 11. Plasterer


5

1.50 Day Labourer 1,450.00 2,175.00


Scaffolding 170.63 170.63
Allow for water 50.00 5,110.03
Overheads 14% 715.4035
Per Sqr 5,825.43
Say per Sqr 5,825.00
Per m2 627.06
Say per m2 627.00

15 3/4" Thick DPC, in cement sand 1:2 finished with 2 coats ho


nd bliended with sand
Per squares
materials
2.25 Cwt. Cement 1,075.00 2,418.75
0.11 Cube sand 10,188.00 1,120.68
1 1/2 Gals. Bitumen 272.00 408.00
firewood (10 lbs) 50.00 50.00
Water 10 gls. 3.00 30.00
Labour
1 1/4 Days Mason 1,650.00 2,062.50
2 1/2 Days U/sk Labourer 1,450.00 3,625.00
9,714.93
14 % Over head s 1,360.09
Rate per Square 11,075.02
Say Sqr. 11,075.00
Rate per m2 1,192.14
Say m2 1,192.00

16 5/8" Thick plastering to wall in lime and sand 2.5 including floating
with lime putty
Per Square
Materials
1.30 Cwt slaked lime 800.00 1,040.00
0.07 cubes sand 10,188.00 713.16
water 10 glas. 3.00 30.00
Labour
1 Day Mason 1,650.00 1,650.00
1 3/4 Days U/Sk Labourer 1,450.00 2,537.50
Scaffolding;-
1 set 50% use 300.00 150.00
6,120.66
Add 14% Overhead 856.89
Rate per Square 6,977.55
Say Sqr. 6,978.00
Rate per m2 751.08
Say m2 751.00
17 5/8" Thick plastering to wall in cement sand 1:3 including cement
floating

Per Square
Materials
1.40 cwt cement (50 kg. bags) 1,075.00 1,505.00
0.06 Cube sand 10,188.00 611.28
Water 10 glas 3.00 30.00
Labour

B.S.R. - 20201st Half Vavuniya 11. Plasterer


6

1 Day Mason 1,650.00 1,650.00


1 1/2 Days U/Sk Labourer 1,450.00 2,175.00
Scaffolding:-
1 Set 50% use 300.00 150.00
6,121.28
Add 14% Overhead 856.98
Rate per Square 6,978.26
Say Sqr. 6,978.00
Rate per m2 751.16
Say m2 751.00

18 3/8" Thick plastering to sofit slab in cement and sand 1:3 including
floating with lime putty

Per Square
Materials
0.80 Cwt. Cement (50 Kg Bags) 1,075.00 860.00
0.16 Cwt slaked lime 800.00 128.00
0.05 cubes sand 10,188.00 509.40
Water 5 gls. 3.00 15.00
Labour
2 1/2 Days Mason 1,650.00 4,125.00
2 1/2 Days u/Sk Labourer 1,450.00 3,625.00

Scaffolding:-
2 Set- 100% use 300.00 600.00
9,862.40
Add 14% Overhead 1,380.74
Rate per Square 11,243.14
Say Sqr. 11,243.00
Rate per m2 1,210.24
Say m2 1,210.00

19 3/8" Thick plastering to sides and soffit of beams in cement sand 1:3
including floating with lime putty

Per square
Materials
0.80 Cwt Cement (50 Kg bags) 1,075.00 860.00
0.16 Cwt slaked lime 800.00 128.00
0.05 Cubes sand 10,188.00 509.40
Water 5 Gls. 3.00 15.00
Labour
2 Days Mason 1,650.00 3,300.00
2 Days U/Sk Labourer 1,450.00 2,900.00

B.S.R. - 20201st Half Vavuniya 11. Plasterer


7

Scaffolding:-
2 sets - 100% use 300.00 600.00
8,312.40
Add 14% Overhead 1,163.74
Rate per Square 9,476.14
Say Sqr. 9,476.00
Rate per m2 1,020.04
Say m2 1,020.00

20 5/8" Thick to wall in lime cement and sand 1:1:5 finished semi
rough with wooden float
Per square
Materials
0.80 Cwt Cement (50 Kg bags) 1,075.00 860.00
0.40 Cwt slaked lime 800.00 320.00
0.07 Cubes sand 10,188.00 713.16
water 10 gls. 3.00 30.00
Labour
1 Day Mason 1,650.00 1,650.00
1 1/4 days u/sk Labourer 1,450.00 1,812.50

scaffolding;-
1 set - 50% use 300.00 150.00
5,535.66
Add 14% Overhead 774.99
Rate per Square 6,310.65
Say Sqr. 6,311.00
Rate per m2 679.30
Say m2 679.00

21 5/8' Thick plastering to wall in lime cement and sand 1;1:5 finished
smooth with lime putty floating

Per square
Materials
0.80 Cwt cement (50 Kg. bags) 1,075.00 860.00
0.60 Cwt slacked lime 800.00 480.00
0.07 Cubes sand 10,188.00 713.16
Water (10 Glas.) 3.00 30.00
Labour
1 1/2 Days Mason 1,650.00 2,475.00
1 1/2 Days U/Sk Labourer 1,450.00 2,175.00
scaffolding;- 300.00 225.00
1 set - 75% use 6,958.16
Add 14% Overhead 974.14
Rate per Square 7,932.30
Say Sqr. 7,932.00
Rate per m2 853.85
Say m2 854.00

22 1/2" Thick rendering in cement and sand 1:3 finished smooth

B.S.R. - 20201st Half Vavuniya 11. Plasterer


8

Per square
Materials
1.07 Cwt cement (50 kg. bags) 1,075.00 1,150.25
0.05 Cube sand 10,188.00 509.40
water 10 gls 3.00 30.00

Labour
1 Day Mason 1,650.00 1,650.00
1 1/2 Day u/sk Labourer 1,450.00 2,175.00
1/4 Day u/sk Labourer (curing) 1,450.00 362.50
5,514.65
Add 14% Overhead 772.05
Rate per Square 6,286.70
Say Sqr. 6,287.00
Rate per m2 676.72
Say m2 677.00

23 1/2' Thick rendering in cement and sand 1:2 in floors, finished smooth

Per square
Materials
1.66 Cwt cement (50 Kg. bags) 1,075.00 1,784.50
0.05 Cubes sand 10,188.00 509.40
Water 10 Gls. 3.00 30.00
Labour
1 Day Mason 1,650.00 1,650.00
1 1/2 Days u/sk Labourer 1,450.00 2,175.00
1/4 Day U/Sk Labourer (curing) 1,450.00 362.50
6,511.40
Add 14% Overhead 911.60
Rate per Square 7,423.00
Say Sqr. 7,423.00
Rate per m2 799.03
Say m2 799.00

24 3/4" Thick rendering in cement and sand 1;3 finished smooth

Per square
Materials
1.75 Cwt Cement (50 kg. bags) 1,075.00 1,881.25
0.08 Cube sand 10,188.00 815.04
Water 10 gls. 3.00 30.00
Labour
1 1/4 Days Mason 1,650.00 2,062.50
2 Days U/Sk Labourer 1,450.00 2,900.00
1/4 Days u/Sk Labourer (curing) 1,450.00 362.50
8,051.29
Add 14% Overhead 1,127.18
Rate per Square 9,178.47
Say Sqr. 9,178.00
Rate per m2 987.99
Say m2 988.00

B.S.R. - 20201st Half Vavuniya 11. Plasterer


9

25 3/4" Thick rendering in cement and sand 1:2 in floors finished smooth

Per square
Materials
2.25 Cwt Cement (50 Kg bags) 1,075.00 2,418.75
0.08 Cubes sand 10,188.00 815.04
Water 10 Gls. 3.00 30.00
Labour
1 1/4 Day Mason 1,650.00 2,062.50
2 Days U/sk Labourer 1,450.00 2,900.00
1/4 Day U/sk Labourer (curing) 1,450.00 362.50
8,588.79
Add 14% Overhead 1,202.43
Rate per Square 9,791.22
Say Sqr. 9,791.00
Rate per m2 1,053.95
Say m2 1,054.00

26 3/4" Thick rendering in cement sand 1:2 in coloured cement floors


finished smooth

Per square
Materials
2.25 Cwt Cement (50 Kg bags) 1,075.00 2,418.75
0.08 Cubes sand 10,188.00 815.04
5 lbs powdered pigment 172.00 860.00
Water 10 Gls. 3.00 30.00

Labour
1 1/4 Day Mason 1,650.00 2,062.50
2 Days U/sk Labourer 1,450.00 2,900.00
1/4 Day U/sk Labourer (curing) 1,450.00 362.50
9,448.79
Add 14% Overhead 1,322.83
Rate per Square 10,771.62
Say Sqr. 10,772.00
Rate per m2 1,159.49
Say m2 1,159.00

27 1/2" x 6" skirting in cement and sand 1;3 projected or flush


with floating including forming groove

Per 10 L.ft
Materials
0.10 Cwt Cement (50 kg bags) 1,075.00 107.50
0.003 cube sand 10,188.00 30.56
0.1 kg red cement 500.00 125.00

Labour
3/8 Days mason 1,650.00 618.75
5/16 Day U/Sk labourer 1,450.00 453.13
1,334.94

B.S.R. - 20201st Half Vavuniya 11. Plasterer


10

Add 14% Overhead 186.89


Rate per 10 L.ft 1,521.83
Rate per l.ft 152.18
Say L.ft 152.00
Rate per Lm 499.16
Say Lm. 499.00

B.S.R. - 20201st Half Vavuniya 11. Plasterer


11

252

229,320.00

62,500.00

B.S.R. - 20201st Half Vavuniya 11. Plasterer


1

APPROVED B.S.R FOR THE 1st HALF 0F 2020 IN VAVUNIYA


11 - PLASTERER.

Code No Description Unit Rate

1 Cement Cwt 1,075.00


2 Fine Sand Cube 10,188.00
3 Mason Day 1,650.00
4 Red cement Kg 500.00
5 Slacked lime K.g 18.00
6 Tar gls 110.00
7 Unskilled labour Day 1,450.00
8 Pudlo Cement K.g 100.00
9 Water Gls. 3.00
10 Bittumum Gls. 272.00
11 Scaffolding Set 300.00
12 Slack lime Cwt 800.00
13 Powder pigment Kg 370.00
14 Powder pigment Lb 172.00