COST ESTIMATE FOR RE-CONDITIONING AND RENOVATION OF CATTLE SHED LOCATED NEAR ROSE VALLEY

Rate Per Unit


Quantit
Quantity As Per
Length Width in Height y in
S.No Item of Work Nos AJK CSR 1st Amount in RS.
in Feet Feet in feet Cubic
Semi Annual
Feet
2019-20
Superstructure in 8" thick hollow block
masonary Cement sand mortar 1 : 6 Long
1 wall 2.00 100.00 0.67 10.00 1333.33 193.00 257,333.3

Superstructure in 8" thick hollow block


masonary Cement sand mortar 1 : 6 short
2 wall 2.00 42.00 0.67 10.00 560.00 193.00 108,080.0

3/8 inch (9.5mm) thick cement plaster using


Lawrencepur sand 1:6
on walls and columns in basement, plinth
and ground floor
3 including making edges, corners and 2.00 100.00 - 10.00 2000.00 22.75 45,500.0
curing.

3/8 inch (9.5mm) thick cement plaster using


Lawrencepur sand 1:6
on walls and columns in basement, plinth
and ground floor
4 including making edges, corners and 2.00 42.00 - 10.00 840.00 22.75 19,110.0
curing.

Providing and laying 1:2:4 cement concrete


floor using using
Margalla crushed aggrgate 1/2" (19mm)
and down gauge in
5
ground floor laid in panels including - 100.00 42.00 - 4200.00 98.20 412,440.0
formwork, consolidation,

6 Total 842,463.33