Professional Documents
Culture Documents
A PAVEMENT WORK
1
BASE COURSE OR RED ASH SPREADING
Suppply ,spread to level and compact 5 to 9 cm base course,fine
crushed aggregate from stone crusher site keeping the design slope
so as to enable cobblestone paving following the slope
1.1 M3 260.62 873.80
3 filling voids and lay by crushed fine aggregate ,finishing and under
red ash
4.2 supply and fix 20*25cm shaped curvedstone side drains to drain ml 247.50 130.50
rain water where necessary, the curved part is 5cm deep out of 10
cm thick. the length of the stone pcs is 30 to 50cm and to be laid on
a compacted base and c-15 concerte and joint filled with cement
mortar 1:3.
Total carried to summary……………
5.Concrete work
5cm lean concrete ( Hand mix ) with ratio of 1:2:6 after compaction
5.1 M2 15.84 161.7
price include Compaction of the Bed.
5.2 C-25 concrete with ratio of 1:2:3 for beams at the edge of greenery M3 4.75 3743.7
the cobble stone road
2. Concrete work
2.1 5cm thick lean concrete quality C-5, 150 kg of cement/m3 M2 198.00 161.70
2.2 10cm concrete bedding grade c-20 above grouted stone bedding. M2 148.50 374.37
3.1 40cm thick stone masonry wall jointed with (1:3)cement sand mortar M3 178.20 1,775.40
2. Concrete work
2.1 5cm thick lean concrete quality C-5, 150 kg of cement/m3 M2 148.50 161.70
Averege 50cm thick stone masonry wall jointed with (1:3)cement sand
3.1 M3 154.69 1,775.40
mortar
5cm thick cement sand mortar(Copping) (1:3) at the top of masonry
3.2 M2 99.00 184.20
wall
Total carried to summary……………
D.FOR STEPS
SUB-STRUCTIRE
1.Excavation&Earth work
2. Concrete work
2.1 5cm thick lean concrete quality C-5, 150 kg of cement/m3 M2 13.20 161.70
Averege 80cm thick stone masonry wall jointed with (1:3)cement sand
3.1 M3 10.56 1,775.40
mortar
Prepared by Approved by
Amount (Birr)
227,729.76
227,729.76
1,026,543.38
1,026,543.38
384,555.60
384,555.60
66,577.50
32,298.75
98,876.25
2,561.33
17,782.58
15,954.20
36,298.10
21,542.40
4,573.78
59,126.76
10,630.62
56,192.40
121,710.60
273,776.56
32,016.60
55,593.95
87,610.55
316,376.28
36,471.60
352,847.88
10,137.60
4,573.78
35,194.50
5,694.98
32,353.20
54,093.60
142,047.65
24,012.45
24,012.45
274,636.63
18,235.80
292,872.43
1,013.76
2,028.72
573.72
1,878.24
5,890.19
11,384.63
2,134.44
2,134.44
18,748.22
4,823.09
23,571.32
SUMMERY OF BILL QUANTITY AND SPECIFICATION FOR COBBLE STONE ROAD
GRAND SUMMARY
D.STEPS WORK
filling voids and lay by crushed fine aggregate ,finishing and under red
ash
supply, fill lay 4-6 cm and compact the 10mm spaces or voids between
the cobblestones with fine crushed aggregate to prevent the movement
of stone due traffic and make the pavement stiff. The surface should
be cleaned
4 .Curbstone & Storm Water Drainage
supply and fix 20*25cm shaped curvedstone side drains to drain rain
water where necessary, the curved part is 5cm deep out of 10 cm thick.
the length of the stone pcs is 30 to 50cm and to be laid on a
compacted base and c-15 concerte and joint filled with cement mortar
1:3.
.Concrete work
5cm lean concrete ( Hand mix ) with ratio of 1:2:6 after compaction
price include Compaction of the Bed.
C-25 concrete with ratio of 1:2:3 for beams at the edge of greenery
the cobble stone road
. Masonry work
40cm thick stone masonry wall jointed with (1:3)cement sand mortar
. Masonry work
Averege 50cm thick stone masonry wall jointed with (1:3)cement sand
mortar
. Masonry work
Averege 80cm thick stone masonry wall jointed with (1:3)cement sand
mortar
T D S Unit DESCRIPTION
BASE COURSE OR RED ASH SPREADING
Suppply ,spread to level and compact 5 to 9 cm base course,fine crushed
1 150 aggregate from stone crusher site keeping the design slope so as to enable
cobblestone paving following the slope
10.89
0.09 147.02 m3
COBBLE STONE PAVING
Supply and lay to the required level 10*10*10 cm and 8*8*8cm shaped cobble
stone made of hard rock as per the layout,design and slope for the main body of
the road and 10*10*10 cm shaped edge cobblestones following the design
1 150 pattern of the cobblestone of the cobblestones road pavement
0 0 m2
filling voids and lay by crushed fine aggregate ,finishing and under red ash
1 150
supply, fill lay 4-6 cm and compact the 10mm spaces or voids between the
cobblestones with fine crushed aggregate to prevent the movement of stone due
traffic and make the pavement stiff. The surface should be cleaned
0 0 m2
Curbstone & Storm Water Drainage
1 0 0 ml Supply and fix 15*25cm shaped curbstone, 30 to 50cm long each, between
pavement and side walk, along both sides of the road, storm water way, with a
cement mortar base of 1:3 mix and backed with c-15 concrete on the external
side of the road, for support, as shown in the design and fill joints with cement
mortar of 1:3 mix. Additional hand tools for the activity are measuring box (for
sand and crushed aggregate)etc.
1 0 0 ml supply and fix 20*25cm shaped curvedstone side drains to drain rain water
where necessary, the curved part is 5cm deep out of 10 cm thick. the length of
the stone pcs is 30 to 50cm and to be laid on a compacted base and c-15 concerte
and joint filled with cement mortar 1:3.
.Concrete work
5cm lean concrete ( Hand mix ) with ratio of 1:2:6 after compaction price include
1 0 Compaction of the Bed.
0 0 m2
1 0
C-25 concrete with ratio of 1:2:3 for beams at the Expantion joint of the cobble
0 0 m2 stone road
1 0
Formwork For concrete of the expantion joints
0 0 m2
B.Maintenance of Box Masonary Ditch Work
SUB STRUCTURE
2 150
Cleaninig & chisseling the existing masonary ditch
0.33
99 m2
CONCRETE WORK
1 150 10cm concrete bedding grade c-20 above grouted stone bedding
0.66
99.00 m2 Total area of concrete
MASONARY WORK
1 9
0.4 40cm thick hard trachytic stone masonary ditch
0.22 0.79 m3
Total volume of stone masonary
Copping
2 150 Cement sand mortar ( 1:2) Copping on top of masonary
0.44
132 m2
132 m2 Total area of copping
2 150 pointing to existing masonary wall
0.55 165
1.Excavation&Earth work
1 150
Site clearing to a depth not exceeding 20cm
2.86 429 m2
2 150
0.98 Cart away surplus excavated material
0.8 235.2 M3
1 150
20cm thick basaltic stone hardcore well rolled, consolidated and blinded with
0.66 99 M2 crushed stone .
3. Masonry work
Averege 50cm thick stone masonry wall jointed with (1:3)cement sand mortar
1 150
0.55
0.9 74.25 m3
1 150
0.44
5cm thick cement sand mortar(Copping) (1:3) at the top of masonry wall
66 M2
BILL OF QUANTITY AND SPECIFICATION FOR COBBLE STONE ROAD
A PAVEMENT WORK
1.BASE COURSE OR RED ASH SPREADING
Suppply ,spread to level and compact 5 to 9 cm base course,fine
crushed aggregate from stone crusher site keeping the design
slope so as to enable cobblestone paving following the slope
1.1 M3 147.02 0.00 1,480.40
3.1 supply, fill lay 4-6 cm and compact the 10mm spaces or voids M2 1,633.50 0.00 199.50
between the cobblestones with fine crushed aggregate to
prevent the movement of stone due traffic and make the
pavement stiff. The surface should be cleaned
Total carried to summary……………
4 .Curbstone & Storm Water Drainage
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
27,155.70
27,155.70
54,821.25
54,821.25
2,165.09
31,360.56
39,484.50 27,155.70
73,010.15
12,655.50
13,829.40
5,997.60
32,692.80
44,550.00
109,725.30
24,047.10
24,047.10
202,977.23
15,680.28
218,657.51
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
BILL OF QUANTITY AND SPECIFICATION FOR COBBLE STONE ROAD
TOTAL SUMMERY
A PAVEMENT WORK
BASE COURSE OR RED ASH SPREADING 0.00
COBBLE STONE PAVING 0
filling voids and lay by crushed fine aggregate ,finishing and
under red ash 0
Curbstone & Storm Water Drainage 0
TOTAL CARRIED 0.00
C RETAINING WALL
Excavation&Earth work 109,725.30
Concrete work 24,047.10
Masonry work 218,657.51
TOTAL CARRIED 352,429.91
D .Slab ditch work 4pcs 0
TOTAL CARRIED 0
PR.BY APPR.BY
PAYMENT CERTIFICATE SHEET
We Certify that the contractor is now entitled to the sum of Birr 639,422.03 ETB
T D S Unit DESCRIPTION
BASE COURSE OR RED ASH SPREADING
Suppply ,spread to level and compact 5 to 9 cm base course,fine crushed aggregate
from stone crusher site keeping the design slope so as to enable cobblestone paving
1 150 following the slope
0
0 0 m3
COBBLE STONE PAVING
Supply and lay to the required level 10*10*10 cm and 8*8*8cm shaped cobble stone
made of hard rock as per the layout,design and slope for the main body of the road and
10*10*10 cm shaped edge cobblestones following the design pattern of the
cobblestone of the cobblestones road pavement
1 150
0 0 m2
filling voids and lay by crushed fine aggregate ,finishing and under red ash
1 150
supply, fill lay 4-6 cm and compact the 10mm spaces or voids between the
cobblestones with fine crushed aggregate to prevent the movement of stone due traffic
and make the pavement stiff. The surface should be cleaned
0 0 m2
Curbstone & Storm Water Drainage
1 0 0 ml Supply and fix 15*25cm shaped curbstone, 30 to 50cm long each, between pavement
and side walk, along both sides of the road, storm water way, with a cement mortar
base of 1:3 mix and backed with c-15 concrete on the external side of the road, for
support, as shown in the design and fill joints with cement mortar of 1:3 mix.
Additional hand tools for the activity are measuring box (for sand and crushed
aggregate)etc.
1 0 0 ml supply and fix 20*25cm shaped curvedstone side drains to drain rain water where
necessary, the curved part is 5cm deep out of 10 cm thick. the length of the stone pcs
is 30 to 50cm and to be laid on a compacted base and c-15 concerte and joint filled
with cement mortar 1:3.
.Concrete work
5cm lean concrete ( Hand mix ) with ratio of 1:2:6 after compaction price include
1 0
Compaction of the Bed.
0 0 m2
1 0 C-25 concrete with ratio of 1:2:3 for beams at the Expantion joint of the cobble stone
0 0 m2 road
1 0
Formwork For concrete of the expantion joints
0 0 m2
STONE PAVEMENT
1 400 grouted stone pavement jointed with treanch RHS & LHS
1.75 Trench wall (1:3)cement sand mortar
700.00 m2 Total area of grouted stone pavement
CONCRETE WORK
LEAN CONCRETE
2 320 lean concrete in c-5 with minimum cement content 150 kg/m3
0.44
281.60 m2 Total area of lean concrete
C-20 concrete
1 320 mass concrete in concrete class of c-20
0.65
208.00 m2 Total area C-20 bedding
MASONARY WORK
2 320
0.41 hard trachytic stone masonary ditch
1.09
286.02 m3 Total volume of stone masonary
Copping
2 320 Cement sand mortar ( 1:2) Copping on top of masonary
0.44
281.6 m2
281.6 m2 Total area of copping
T D S Unit DESCRIPTION
1.BASE COURSE OR RED ASH SPREADING
Suppply ,spread to level and compact 5 to 9 cm base course,fine crushed aggregate from
1 224 stone crusher site keeping the design slope so as to enable cobblestone paving following the
slope
8
0.09 161.28 m3
2.COBBLE STONE PAVING
Supply and lay to the required level 10*10*10 cm and 8*8*8cm shaped cobble stone made of
hard rock as per the layout,design and slope for the main body of the road and 10*10*10 cm
1 224 shaped edge cobblestones following the design pattern of the cobblestone of the
cobblestones road pavement
8 1792 m2
3.filling voids and lay by crushed fine aggregate ,finishing and under red ash
1 224
supply, fill lay 4-6 cm and compact the 10mm spaces or voids between the cobblestones
with fine crushed aggregate to prevent the movement of stone due traffic and make the
8 1792 m2 pavement stiff. The surface should be cleaned
4.Curbstone & Side Drainage
1 224 ml
Supply and fix 15*25cm shaped curbstone, 30 to 50cm long each, between pavement and
side walk, along both sides of the road, storm water way, with a cement mortar base of 1:3
mix and backed with c-15 concrete on the external side of the road, for support, as shown in
the design and fill joints with cement mortar of 1:3 mix. Additional hand tools for the
1 224 ml activity are measuring box (for sand and crushed aggregate)etc.
5. Big Stons
supply and fix 20*25cm shaped curvedstone side drains to drain rain water where
1 224 ml necessary, the curved part is 5cm deep out of 10 cm thick. the length of the stone pcs is 30 to
50cm and to be laid on a compacted base and c-15 concerte and joint filled with cement
mortar 1:3.
1 224
6.Concrete work
1 30
C-25 concrete with ratio of 1:2:3 for beams at the Expantion joint of the cobble stone road
0.4
0.3 3.6 m3
1 90
.Formwork For concrete of the expantion joints
0.4 36 m2
B. RETAINING WALL
SUB STRUCTURE
1.Excavation&Earth work
1 100 25cm thick basaltic stone hardcore well rolled, consolidated and blinded with crushed stone .
0.686 68.6 m2
CONCRETE WORK
1 100 5cm thick lean concrete quality C-5, 150 kg of cement/m3
0.686 68.6 m 2
Masonry work
1 100 40cm thick stone masonry wall jointed with (1:3)cement sand mortar
0.6
0.98 58.80 m3
5cm thick cement sand mortar(Copping) (1:3) at the top of masonry wall
1 100
0.392 39.20 m2
C. TYPE-1 OPEN MASONARY DITCH WORK
1.Excavation&Earth work
1 154 20cm thick basaltic stone hardcore well rolled, consolidated and blinded with crushed stone .
1.4605 224.917 m2
Concrete work
2 154 5cm thick lean concrete quality C-5, 150 kg of cement/m3
0.487 150.00
1 154 10cm thick mass concrete in C-20
0.584 89.936 m2
Masonry work
2 154 Construct 40cm thick hard trachytic stone masonary ditch
0.778
0.4
95.85 m3 Total volume of stone masonary
Copping
2 154 40cm width and5cm Cement sand mortar ( 1:2) Copping on top of masonary
0.389
119.812 m2
119.812 m2 Total area of copping
1 120 20cm thick basaltic stone hardcore well rolled, consolidated and blinded with crushed stone .
1.437 172.44 m 3
Concrete work
2 120 5cm thick lean concrete quality C-5, 150 kg of cement/m3
0.479 114.96 m2
1 120 10cm thick mass concrete in C-20
0.575 69 m2
Masonry work
2 120 Construct 40cm thick hard trachytic stone masonary ditch
0.958
0.4
91.97 m3 `
Copping
2 120 40cm width and5cm Cement sand mortar ( 1:2) Copping on top of masonary
0.383
91.92 m2 109
91.92 m2 Total area of copping
A PAVEMENT WORK
1 BASE COURSE OR RED ASH SPREADING
Suppply ,spread to level and compact 5 to 9 cm base course,fine
crushed aggregate from stone crusher site keeping the design slope
so as to enable cobblestone paving following the slope
1.1 M3 260.62 873.80 227,729.76
3 filling voids and lay by crushed fine aggregate ,finishing and under
red ash
3.1 supply, fill lay 4-6 cm and compact the 10mm spaces or voids M2 2,895.75 132.80 384,555.60
between the cobblestones with fine crushed aggregate to prevent the
movement of stone due traffic and make the pavement stiff. The
surface should be cleaned
Total carried to summary…………… 384,555.60
4 .Curbstone & Storm Water Drainage
4.1 Supply and fix 15*25cm shaped curbstone, 30 to 50cm long each, ml 247.50 269.00 66,577.50
between pavement and side walk, along both sides of the road,
storm water way, with a cement mortar base of 1:3 mix and backed
with c-15 concrete on the external side of the road, for support, as
shown in the design and fill joints with cement mortar of 1:3 mix.
Additional hand tools for the activity are measuring box (for sand
and crushed aggregate)etc.
4.2 supply and fix 20*25cm shaped curvedstone side drains to drain ml 247.50 130.50 32,298.75
rain water where necessary, the curved part is 5cm deep out of 10
cm thick. the length of the stone pcs is 30 to 50cm and to be laid on
a compacted base and c-15 concerte and joint filled with cement
mortar 1:3.
Total carried to summary…………… 98,876.25
5.Concrete work
5cm lean concrete ( Hand mix ) with ratio of 1:2:6 after compaction
5.1 M2 15.84 161.7 2,561.33
price include Compaction of the Bed.
5.2 C-25 concrete with ratio of 1:2:3 for beams at the edge of greenery M3 4.75 3743.7 17,782.58
the cobble stone road
5.3 Formwork For concrete edge of greenery beams M2 57.02 279.8 15,954.20
1.3 Trench excavation depth of not exceeding 150cm M3 623.70 94.80 59,126.76
2.1 5cm thick lean concrete quality C-5, 150 kg of cement/m3 M2 198.00 161.70 32,016.60
2.2 10cm concrete bedding grade c-20 above grouted stone bedding. M2 148.50 374.37 55,593.95
3.1 40cm thick stone masonry wall jointed with (1:3)cement sand mortar M3 178.20 1,775.40 316,376.28
1.3 Trench excavation depth of not exceeding 150cm M3 371.25 94.8 35,194.50
1.4 Back fill around to Retaining masonry wall M3 74.25 76.7 5,694.98
1.5 Cart away surplus excavated material M3 376.20 86 32,353.20
2.1 5cm thick lean concrete quality C-5, 150 kg of cement/m3 M2 148.50 161.70 24,012.45
2.1 5cm thick lean concrete quality C-5, 150 kg of cement/m3 M2 13.20 161.70 2,134.44
We Certify that the contractor is now entitled to the sum of Birr 1,197,034.59 ETB (One million one hundred
ninty seven thounsand thirty four and 59/100 cents)
TOTAL SUMMERY
A PAVEMENT WORK
BASE COURSE OR RED ASH SPREADING 238,758.91
COBBLE STONE PAVING 655,513.60
filling voids and lay by crushed fine aggregate ,finishing and
under red ash 357,504.00
Curbstone & Storm Water Drainage 51,318.40
Concrete work for Expantion Joint 40,001.40
TOTAL CARRIED 1,343,096.31
B RETAINING WALL
8.Excavation&Earth work 0.00
9. Concrete work 0.00
10. Masonry work 0.00
TOTAL CARRIED 0.00
Type.1 Box Masonary Ditch Work
C 11.Excavation & Earth work 0.00
12. Concrete work 0.00
13. Masonry work 0.00
TOTAL CARRIED 0.00
Type.2 Box Masonary Ditch Work
14.Excavation & Earth work 0.00
15. Concrete work 0.00
16. Masonry work 0.00
TOTAL CARRIED 0.00
D SLAB DITCH COVER WORK FOR JUNCTION1 12Pcs
17.Form Work 0.00
18. Concrete work 0.00
19. Reinforcement 0.00
TOTAL CARRIED 0.00
PR.BY APPR.BY
BILL OF QUANTITY AND SPECIFICATION FOR COBBLE STONE ROAD
8.2 Trench excavation depth of not exceeding 150cm M3 64.68 64.56 0 118.20 0.00
11.2 Trench excavation depth of not exceeding 150cm M3 342.00 341.94 0.00 118.20 0.00
11.3 Back fill around to masonry wall M3 90.00 89.81 0.00 117.60 0.00
11.4 Cart away surplus excavated material M3 354.00 353.85 0.00 139.00 0.00
20cm thick basaltic stone hardcore well rolled,
11.5 M2 225.00 224.92 0.00 450.00 0.00
consolidated and blinded with crushed stone .
Total carried to summary…………… 0.00
12. Concrete work
5cm thick lean concrete quality C-5, 150 kg of
12.1 M2 150.00 150.00 0.00 242.90 0.00
cement/m3
10cm concrete bedding grade c-20 above grouted
12.2 M2 90.00 89.94 0.00 553.75 0.00
stone bedding.
Total carried to summary…………… 0.00
13. Masonry work
40cm thick stone masonry wall jointed with
13.1 M3 96.00 95.85 0.00 2,733.70 0.00
(1:3)cement sand mortar
5cm thick cement sand mortar(Copping) (1:3) at
13.2 M2 120.00 119.81 0.00 237.58 0.00
the top of masonry wall
Total carried to summary…………… 0.00
Type.2 Box Masonary Ditch Work
SUB-STRUCTIRE
14.Excavation & Earth work
14.1 Site clearing to a depth not exceeding 20cm M2 391.00 390.96 0.00 29.50 0.00
14.2 Trench excavation depth of not exceeding 150cm M3 327.75 327.60 0.00 118.20 0.00
Prepared by Approved by
BILL OF QUANTITY AND SPECIFICATION FOR COBBLE STONE ROAD
Prepared by Approved by
S/N Name of Project Unit
1 Movement Network
1.1 Cobble
From Community police Office to Amare arega
1.1.1 m2
residence
Sub Total
2 Environmental Service
2.2 Drainage Network Qtty(ml)/No
3.3 Bus Station fence right and left side with retaining wall ml
1463 117.04
1897.5 172.5
2055 236.21
1125 150
2095.5 165
8636 0.84 1.23
Qtty(ml)/No
250
167
150
395
86
1,048.00
18
60
27
3,660
184
233
1200
1
1
1
1000
3600
Unit.Rate Total Amount
1,553.75 2,273,141.59
1,383.18 2,624,599.71
1,827.34 3,755,187.96
1,807.64 2,052,364.22
1,874.44 3,927,901.95
1.23371428571429 14,633,195.43
2,603,300.75 2,603,300.75
3,698,510.12 3,698,510.12
6,301,810.87
6,781.74 1,695,435.39
6,619.92 1,105,527.24
6,557.40 983,610.26
6,349.31 2,507,977.60
8,920.12 767,130.27
23,381.52 420,867.40
13,841.46 830,487.72
16,727.79 451,650.47
8,762,686.35
677.813 3,351,083.57
9,930.74 1,827,256.77
21,117.19 4,920,305.63
5,833.33 7,000,000.00
1,199,808.90 1,199,808.90
1,053,143.66 1,053,143.66
678,985.15 678,985.15
20,030,583.68
-
-
1,884,916 1,884,916.00
459,100 459,100.00
814 813,700.00
120 432,648.00
3,590,364.00
53,318,640.33
Asset type Material Actual length/km
1
0.9
0.8
0.7
0.6
0.5
0.4
0.3 Series1
0.2 0 0 0 0 0 0 0
0.1
0
0 0 0 0 0 0 0
Length of Road in km
Acttual Area/m2 Coverage %
converted to 7m width
Series1
Owner
ERA
Adolla
Adolla
Adolla
Adolla
Adolla
Adolla
50
45
40
35
30
25
20
Coverage %
15 Actual length/km
10
5
0
l sh l
ER
A
oa
d le ve ed ra
bb a A ss t u
ad
alt
R
Co Gr Re
d
Pr
e
Na
Ro ph h t h
la t s rt r
ph
A Ea Ea
As
Coverage %
Actual length/km
al
Length of
Actual Actual Acttual Drainage in km
Asset type Material Coverage %
length/m length/km Area/m2 converted to
1.5m width
Masonry Drain
14,541.61 14.54161 20,358.25 13.57 96%
Open