04 - BRICKLAYER
Per Cube
Materials
1450 Bricks 10.80 15,660.00
3.70 Cwt cement (50 Kg. Bags) 1,075.00 3,977.50
0.23 Cubes sand 9,905.00 2,278.15
Water (150 Gls.) -
Labour
3 Days Mason 1,650.00 4,950.00
5 Days U/Sk Labourer 1,450.00 7,250.00
34,115.65
Add 14% Overhead 4,776.19
Rate per Cube 38,891.84
Say cube. 38,892.00
Rate per m3 13,742.70
Say m3 13,743.00
Per Cube
Materials
1450 Bricks 10.80 15,660.00
2 1/3 Cwt cement (50 Kg. Bags) 1,075.00 2,508.33
3/8 Cubes sand 9,905.00 3,714.38
Water (150 Gls.) 3.00 450.00
Labour
3 Days Mason 1,650.00 4,950.00
4 Days U/Sk Labourer 1,450.00 5,800.00
33,082.71
Add 14% Overhead 4,631.58
Rate per Cube 37,714.29
Say Cube 37,714.00
Rate per m3 13,326.60
Say m3 13,327.00
3
Brick work in cement and sand 1:5 in 4 1/2" thick walls in gound floor
Per square
Materials
550 Bricks 10.80 5,940.00
1.30 cwt cement (50 Kg bags) 1,075.00 1,397.50
0.10 Cubes sand 9,905.00 990.50
water (150 Gals.) 3.00 450.00
Labour
1 1/2 Day Mason 1,650.00 2,475.00
2 Days U/Sk Labourer 1,450.00 2,900.00
Scaffolding
2 sets 50% usage 300.00 300.00
14,453.00
Add 14% Overhead 2,023.42
Rate per square 16,476.42
Say per sqr. 16,476.00
Rate per m2 1,771.28
Say m2 1,771.00
Per Sqr
Materials
1090 Bricks 10.80 11,772.00
3 Cwt cement (50 Kg bags) 1,075.00 3,225.00
0.20Cubes sand 9,905.00 1,981.00
water (115 Gals.) 3.00 345.00
Labour
2 1/4 Day Mason 1,650.00 3,712.50
3 3/4 Days U/Sk Labourer 1,450.00 5,437.50
Scaffolding
2 sets 50% usage 300.00 300.00
26,773.00
Add 14% Overhead 3,748.22
Rate per Sqr 30,521.22
Say Sqr 30,521.00
Rate per m2 3,281.85
B.S.R 2020 1st half Vavuniya 04_Brick Layer
3
5 Brick work 13 1/2" thick in Ct. sand 1:5 in superstructure in ground floor
Labour
3 1/2 Days Mason 1,650.00 5,775.00
5 1/2 Days u/Sk Labourer 1,450.00 7,975.00
Scaffolding
2 sets 50% use 300.00 300.00
39,973.00
Add 14% Overhead 5,596.22
Rate per square 45,569.22
Say Sqr. 45,569.00
Rate per m2 4,898.86
Say m2 4,899.00
6 9" Thick brick wall cement sand 1:8 in superstructure in ground floor
Labour
2 1/4 Day Mason 1,650.00 3,712.50
3 Days U/Sk Labourer 1,450.00 4,350.00
Scaffolding
2 sets 50% usage 300.00 300.00
25,332.25
Add 14% Overhead 3,546.52
Rate per square 28,878.77
Say Sqr. 28,879.00
Rate per m2 3,104.58
B.S.R 2020 1st half Vavuniya 04_Brick Layer
4
Per Square
Materials
350 Bricks 10.80 3,780.00
1.20 Cwt slaked lime 750.00 900.00
0.11 Cubes sand 9,905.00 1,089.55
Water (45 Glas.) 3.00 135.00
Labour
1 1/4 Days Mason 1,650.00 2,062.50
21/2 Days U/Sk Labourer 1,450.00 3,625.00
11,592.05
Add 14% Overhead 1,622.89
Rate per square 13,214.94
Say Sqr. 13,215.00
Rate per m2 1,420.66
Say m2 1,421.00
8 Steps 1'-1 1/2" x 0'-6" in brick in cement and sand 1:5 with 1/2"
Per 10.L.ft
Materials
120 Bricks 10.80 1,296.00
0.50 Cwt cement (50 Kg. bags) 1,075.00 537.50
0.05 Cubes sand 9,905.00 495.25
Water (15 Gals.) 3.00 45.00
Labour
1/2 Days Mason 1,650.00 825.00
1/2 Days U/Sk Labourer 1,450.00 725.00
3,923.75
Add 14% Overhead 549.33
Rate per 10.0 L.ft 4,473.08
Rate per L.ft 447.31
Say L.ft 447.00
Rate per Lm 1,467.17
9 Brick drains in cement and sand 1:5 9" wide and 6'-9" average depth
including cement rendering 1/2" thick 1:2 to exposed faces with 1'-6"
ramp including necessary excavation
Labour
1 1/4 Days Mason 1,650.00 2,062.50
1 1/4 Days U/sk Labourer 1,450.00 1,812.50
6,802.25
Add 14% Overhead 952.32
Rate per 10.0 L.ft 7,754.57
Rate per L.ft 775.46
Say L.ft 775.00
Rate per Lm 2,543.50
Say Lm 2,543.00
10
Brick drains in cement and sand 1:5 9" wide and 6'-9" average depth
including cement rendering 1/2" thick 1:2 to exposed faces without
ramp including necessary excavation
Labour
1 Day Mason 1,650.00 1,650.00
1 1/4 Days U/sk Labourer 1,450.00 1,812.50
Err:522
Per Cube
Materials
1450 Bricks 10.80 15,660.00
3.70 Cwt cement (50 Kg bags) 1,075.00 3,977.50
0.23 Cubes sand 9,905.00 2,278.15
water (150 Gals.) 3.00 450.00
Labour
3 Day Mason 1,650.00 4,950.00
5 Days U/Sk Labourer 1,450.00 7,250.00
Scaffolding
2 sets 50% usage 300.00 300.00
34,865.65
Add 14% Overhead 4,881.19
Rate per Cube 39,746.84
Say Cube 39,747.00
Rate per m3 14,044.82
Say m3 14,045.00
**************
end
PRICE LIST
04 - BRICK LAYER
8500
SUMMARY
RATE
RATEANALYSIS
ANALYSIS11st
st
HALF
HALFOF
OF 2014
2020 IN
IN VAVUNIYA
04 - BRICK LAYER
01 Brick work in cement sand 1:5 in foundation upto D.P.C Cube 38,892.00
m3 13,743.00
02 Brick work in cement sand 1:8 in foundation upto D.P.C Cube 37,714.00
m3 13,327.00
03
Brick work in cement and sand 1:5 in 4 1/2" thick walls in gound floor Sqr. 16,476.00
m2 1,771.00
04 9" Thick brick wall cement sand 1:5 in ground floor Sqr. 30,521.00
m2 3,282.00
06
9" Thick brick wall cement sand 1:8 in superstructure in ground floor Sqr. 28,879.00
m2 3,105.00
07 3' Thick floor paved in lime mortar 2.5 in ground floor Sqr. 13,215.00
m2 1,421.00
08 Steps 1'-1 1/2" x 0'-6" in brick in cement and sand 1:5 with 1/2" L.ft 447.00
Lm 1,467.00
09 Brick drains in cement and sand 1:5 9" wide and 6'-9" average depth
including cement rendering 1/2" thick 1:2 to exposed faces with 1'-6"
ramp including necessary excavation L.ft 775.00
Lm 2,543.00
10 Brick drains in cement and sand 1:5 9" wide and 6'-9" average depth
including cement rendering 1/2" thick 1:2 to exposed faces without
ramp including necessary excavation L.ft 666.00
Lm 2,185.00
11 9" Thick brick wall cement sand 1:5 in ground floor Cube 39,747.00
m3 14,045.00