RATE ANALYSIS 1st .HALF OF 2020 IN VAVUNIYA

04 - BRICKLAYER

Item Description Rate Amount

1 Brick work in cement sand 1:5 in foundation upto D.P.C

Per Cube
Materials
1450 Bricks 10.80 15,660.00
3.70 Cwt cement (50 Kg. Bags) 1,075.00 3,977.50
0.23 Cubes sand 9,905.00 2,278.15
Water (150 Gls.) -

Labour
3 Days Mason 1,650.00 4,950.00
5 Days U/Sk Labourer 1,450.00 7,250.00
34,115.65
Add 14% Overhead 4,776.19
Rate per Cube 38,891.84
Say cube. 38,892.00
Rate per m3 13,742.70
Say m3 13,743.00

2 Brick work in cement sand 1:8 in foundation upto D.P.C

Per Cube
Materials
1450 Bricks 10.80 15,660.00
2 1/3 Cwt cement (50 Kg. Bags) 1,075.00 2,508.33
3/8 Cubes sand 9,905.00 3,714.38
Water (150 Gls.) 3.00 450.00

Labour
3 Days Mason 1,650.00 4,950.00
4 Days U/Sk Labourer 1,450.00 5,800.00
33,082.71
Add 14% Overhead 4,631.58
Rate per Cube 37,714.29
Say Cube 37,714.00
Rate per m3 13,326.60
Say m3 13,327.00

B.S.R 2020 1st half Vavuniya 04_Brick Layer


2

Item Description Rate Amount

3
Brick work in cement and sand 1:5 in 4 1/2" thick walls in gound floor

Per square
Materials
550 Bricks 10.80 5,940.00
1.30 cwt cement (50 Kg bags) 1,075.00 1,397.50
0.10 Cubes sand 9,905.00 990.50
water (150 Gals.) 3.00 450.00

Labour
1 1/2 Day Mason 1,650.00 2,475.00
2 Days U/Sk Labourer 1,450.00 2,900.00

Scaffolding
2 sets 50% usage 300.00 300.00
14,453.00
Add 14% Overhead 2,023.42
Rate per square 16,476.42
Say per sqr. 16,476.00
Rate per m2 1,771.28
Say m2 1,771.00

4 9" Thick brick wall cement sand 1:5 in ground floor

Per Sqr
Materials
1090 Bricks 10.80 11,772.00
3 Cwt cement (50 Kg bags) 1,075.00 3,225.00
0.20Cubes sand 9,905.00 1,981.00
water (115 Gals.) 3.00 345.00

Labour
2 1/4 Day Mason 1,650.00 3,712.50
3 3/4 Days U/Sk Labourer 1,450.00 5,437.50

Scaffolding
2 sets 50% usage 300.00 300.00
26,773.00
Add 14% Overhead 3,748.22
Rate per Sqr 30,521.22
Say Sqr 30,521.00
Rate per m2 3,281.85
B.S.R 2020 1st half Vavuniya 04_Brick Layer
3

Item Description Rate Amount


Say m2 3,282.00

5 Brick work 13 1/2" thick in Ct. sand 1:5 in superstructure in ground floor

Per Square (I.e 1.125 cubes)


Materials
1630 Bricks 10.80 17,604.00
4.50 Cwt. Cement (50 Kg. bags) 1,075.00 4,837.50
0.30 cubes sand 9,905.00 2,971.50
Water (170 Gals) 3.00 510.00

Labour
3 1/2 Days Mason 1,650.00 5,775.00
5 1/2 Days u/Sk Labourer 1,450.00 7,975.00

Scaffolding
2 sets 50% use 300.00 300.00
39,973.00
Add 14% Overhead 5,596.22
Rate per square 45,569.22
Say Sqr. 45,569.00
Rate per m2 4,898.86
Say m2 4,899.00

6 9" Thick brick wall cement sand 1:8 in superstructure in ground floor

Per square (I.e 0.75 cubes)


Materials
1090 Bricks 10.80 11,772.00
1.75 Cwt cement (50 Kg bags) 1,075.00 1,881.25
0.30 Cubes sand 9,905.00 2,971.50
water (115 Gals.) 3.00 345.00

Labour
2 1/4 Day Mason 1,650.00 3,712.50
3 Days U/Sk Labourer 1,450.00 4,350.00

Scaffolding
2 sets 50% usage 300.00 300.00
25,332.25
Add 14% Overhead 3,546.52
Rate per square 28,878.77
Say Sqr. 28,879.00
Rate per m2 3,104.58
B.S.R 2020 1st half Vavuniya 04_Brick Layer
4

Item Description Rate Amount


Say m2 3,105.00

7 3' Thick floor paved in lime mortar 2.5 in ground floor

Per Square
Materials
350 Bricks 10.80 3,780.00
1.20 Cwt slaked lime 750.00 900.00
0.11 Cubes sand 9,905.00 1,089.55
Water (45 Glas.) 3.00 135.00

Labour
1 1/4 Days Mason 1,650.00 2,062.50
21/2 Days U/Sk Labourer 1,450.00 3,625.00
11,592.05
Add 14% Overhead 1,622.89
Rate per square 13,214.94
Say Sqr. 13,215.00
Rate per m2 1,420.66
Say m2 1,421.00

8 Steps 1'-1 1/2" x 0'-6" in brick in cement and sand 1:5 with 1/2"

Thick Cement and sand 1:2 rendering including necessary excavation

Per 10.L.ft
Materials
120 Bricks 10.80 1,296.00
0.50 Cwt cement (50 Kg. bags) 1,075.00 537.50
0.05 Cubes sand 9,905.00 495.25
Water (15 Gals.) 3.00 45.00

Labour
1/2 Days Mason 1,650.00 825.00
1/2 Days U/Sk Labourer 1,450.00 725.00
3,923.75
Add 14% Overhead 549.33
Rate per 10.0 L.ft 4,473.08
Rate per L.ft 447.31
Say L.ft 447.00
Rate per Lm 1,467.17

B.S.R 2020 1st half Vavuniya 04_Brick Layer


5

Item Description Rate Amount


Say Lm 1,467.00

9 Brick drains in cement and sand 1:5 9" wide and 6'-9" average depth
including cement rendering 1/2" thick 1:2 to exposed faces with 1'-6"
ramp including necessary excavation

Per 10.0 L.ft


Materials
140 Bricks 10.80 1,512.00
0.80 Cwt Cement (50 Kg. bags) 1,075.00 860.00
0.05 Cubes sand 9,905.00 495.25
Water (20 Gals) 3.00 60.00

Labour
1 1/4 Days Mason 1,650.00 2,062.50
1 1/4 Days U/sk Labourer 1,450.00 1,812.50
6,802.25
Add 14% Overhead 952.32
Rate per 10.0 L.ft 7,754.57
Rate per L.ft 775.46
Say L.ft 775.00
Rate per Lm 2,543.50
Say Lm 2,543.00

10
Brick drains in cement and sand 1:5 9" wide and 6'-9" average depth
including cement rendering 1/2" thick 1:2 to exposed faces without
ramp including necessary excavation

Per 10.0 L.ft


Materials
110 Bricks 10.80 1,188.00
0.70 Cwt Cement (50 Kg. bags) 1,075.00 752.50
0.04Cubes sand 9,905.00 396.20
Water (15 Gals) 3.00 45.00

Labour
1 Day Mason 1,650.00 1,650.00
1 1/4 Days U/sk Labourer 1,450.00 1,812.50

B.S.R 2020 1st half Vavuniya 04_Brick Layer


6

Item Description Rate Amount


5,844.20
Add 14% Overhead 818.19
Rate per 10.0 L.ft 6,662.39
Rate per L.ft 666.24
Say L.ft 666.00
Rate per Lm 2,185.26
Say Lm 2,185.00

Err:522

11 9" Thick brick wall cement sand 1:5 in ground floor

Per Cube
Materials
1450 Bricks 10.80 15,660.00
3.70 Cwt cement (50 Kg bags) 1,075.00 3,977.50
0.23 Cubes sand 9,905.00 2,278.15
water (150 Gals.) 3.00 450.00

Labour
3 Day Mason 1,650.00 4,950.00
5 Days U/Sk Labourer 1,450.00 7,250.00

Scaffolding
2 sets 50% usage 300.00 300.00
34,865.65
Add 14% Overhead 4,881.19
Rate per Cube 39,746.84
Say Cube 39,747.00
Rate per m3 14,044.82

Say m3 14,045.00

B.S.R 2020 1st half Vavuniya 04_Brick Layer


7

Item Description Rate Amount

B.S.R 2020 1st half Vavuniya 04_Brick Layer


8

B.S.R 2020 1st half Vavuniya 04_Brick Layer


9

B.S.R 2020 1st half Vavuniya 04_Brick Layer


10

B.S.R 2020 1st half Vavuniya 04_Brick Layer


11

**************

B.S.R 2020 1st half Vavuniya 04_Brick Layer


12

B.S.R 2020 1st half Vavuniya 04_Brick Layer


13

end

B.S.R 2020 1st half Vavuniya 04_Brick Layer


14

B.S.R 2020 1st half Vavuniya 04_Brick Layer


15

B.S.R 2020 1st half Vavuniya 04_Brick Layer


16

B.S.R 2020 1st half Vavuniya 04_Brick Layer


17

B.S.R 2020 1st half Vavuniya 04_Brick Layer


18

B.S.R 2020 1st half Vavuniya 04_Brick Layer


19

B.S.R 2020 1st half Vavuniya 04_Brick Layer


20

B.S.R 2020 1st half Vavuniya 04_Brick Layer


21

B.S.R 2020 1st half Vavuniya 04_Brick Layer


22

B.S.R 2020 1st half Vavuniya 04_Brick Layer


23

B.S.R 2020 1st half Vavuniya 04_Brick Layer


24

B.S.R 2020 1st half Vavuniya 04_Brick Layer


25

B.S.R 2020 1st half Vavuniya 04_Brick Layer


26

B.S.R 2020 1st half Vavuniya 04_Brick Layer


27

B.S.R 2020 1st half Vavuniya 04_Brick Layer


28

B.S.R 2020 1st half Vavuniya 04_Brick Layer


Page 29

PRICE LIST

RATE ANALYSIS 1st . HALF OF 2020 IN VAVUNIYA

04 - BRICK LAYER

No. Description Unit Rate


01 Bricks No. 10.80
02 Cement Cwt. 1,075.00
03 Sand Cub. 9,905.00
04 Water Gls. 3.00
05 Mason Day 1,650.00
06 Labourer Day 1,450.00
07 Slacked lime Cwt 750.00
08 Scaffolding Set 300.00

4. Brick Layer 2020 1st Half Vavuniya


Page 30

8500

4. Brick Layer 2020 1st Half Vavuniya


31

SUMMARY

RATE
RATEANALYSIS
ANALYSIS11st
st
HALF
HALFOF
OF 2014
2020 IN
IN VAVUNIYA

04 - BRICK LAYER

No. Description Unit Rate

01 Brick work in cement sand 1:5 in foundation upto D.P.C Cube 38,892.00
m3 13,743.00

02 Brick work in cement sand 1:8 in foundation upto D.P.C Cube 37,714.00
m3 13,327.00

03
Brick work in cement and sand 1:5 in 4 1/2" thick walls in gound floor Sqr. 16,476.00
m2 1,771.00

04 9" Thick brick wall cement sand 1:5 in ground floor Sqr. 30,521.00
m2 3,282.00

05 Brick work 13 1/2" thick in Ct. sand 1:5 in superstructure in ground


floor Sqr. 45,569.00
m2 4,899.00

06
9" Thick brick wall cement sand 1:8 in superstructure in ground floor Sqr. 28,879.00
m2 3,105.00

07 3' Thick floor paved in lime mortar 2.5 in ground floor Sqr. 13,215.00
m2 1,421.00

08 Steps 1'-1 1/2" x 0'-6" in brick in cement and sand 1:5 with 1/2" L.ft 447.00
Lm 1,467.00

09 Brick drains in cement and sand 1:5 9" wide and 6'-9" average depth
including cement rendering 1/2" thick 1:2 to exposed faces with 1'-6"
ramp including necessary excavation L.ft 775.00
Lm 2,543.00

10 Brick drains in cement and sand 1:5 9" wide and 6'-9" average depth
including cement rendering 1/2" thick 1:2 to exposed faces without
ramp including necessary excavation L.ft 666.00
Lm 2,185.00

11 9" Thick brick wall cement sand 1:5 in ground floor Cube 39,747.00