19. Mixing concrete 1:3:6 (1 1/2") -G15


per Cube
Materials
(50 kg bags) cement Cwt 13.00 485.00 6,305.00
sand Cubes 0.53 5,300.00 2,809.00
1 1/2" Metal Cubes 0.92 3,200.00 2,944.00
hire of mixer Days 0.33 3,250.00 1,083.33
Water (110 gals) Gals 110.00 1.00 110.00
Labour:
SK labourer Day 1.00 600.00 600.00
U/SK labourer Days 6.00 400.00 2,400.00
16,251.33
O.H & proffit 0.00 0.00
Rate per Cube 16,251.33
NOTE : 5,742.52
a) Water available at site. 5,742.52
b) If, water is not available
allowances should be made for
transport of water.
c) Sand - includes 15% for bulking
5,742.52
20. Mixing concrete 1 : 2 1/2 : 5 (1")
per Cube
Materials
(50 kg bags) cement Cwt 14.00 485.00 6,790.00
sand Cubes 0.60 5,300.00 3,180.00
1" Metal Cubes 0.90 3,400.00 3,060.00
hire of mixer Day 0.33 3,250.00 1,083.33
Water (100 gals) Gal 100.00 1.00 100.00
Labour:
SK labourer Days 1.00 600.00 600.00
U/SK labourer Days 6.00 400.00 2,400.00
17,213.33
O.H & proffit 0.00 0.00
Rate per Cube 17,213.33
NOTE : 6,082.45
a) Water available at site.
b) If, water is not available
allowances should be made for
transport of water.
c) Sand - includes 15% for bulking

21. Mixing concrete 1 : 2 : 4 (3/4") -G20


per Cube
Materials
(50 kg bags) cement Cwt 18.00 485.00 8,730.00
Sand Cubes 0.50 5,300.00 2,650.00
3/4" Metal Cubes 0.88 3,600.00 3,168.00
hire of mixer Day 0.33 3,250.00 1,083.33
Water (120 gals) Gals 120.00 1.00 120.00
Labour:
SK labourer Day 1.00 600.00 600.00
U/SK labourer Days 6.00 400.00 2,400.00

Page 1
Conc-Fm-Rf Work

18,751.33
O.H & proffit 0.00 0.00

Page 2
Conc-Fm-Rf Work

Rate per Cube 18,751.33


NOTE : 6,625.91
a) Water available at site.
b) If, water is not available
allowances must be made for
transport of water.
c) Sand - includes 15% for bulking

22. Mixing concrete 1:1 1/2:3 (3/4") -G25


per Cube
Materials
(50 kg bags) cement Cwt 23.00 485.00 11,155.00
sand Cubes 0.42 5,000.00 2,100.00
3/4" Metal Cubes 0.82 3,600.00 2,952.00
hire of mixer Day 0.33 3,250.00 1,083.33
Water (15 gals) Gals 15.00 1.00 15.00
Labour:
SK labourer Day 1.00 600.00 600.00
U/SK labourer Days 6.00 400.00 2,400.00
20,305.33
O.H & proffit 0.00 0.00
Rate per Cube 20,305.33
NOTE : 7,175.03
a) Water available at site.
b) If, water is not available
allowances must be made for
transport of water.
c) Sand - includes 15% for bulking

23. Mixing concrete 1 : 1 : 2 (3/4") G-35


per Cube
Materials
(50 kg bags) cement Cwt 31.00 485.00 15,035.00
sand Cubes 0.44 5,000.00 2,200.00
3/4" Metal Cubes 0.96 3,600.00 3,456.00
hire of mixer Day 0.33 3,250.00 1,083.33
Water (200 gals) Gals 200.00 1.00 200.00
Labour:
SK labourer Day 1.00 600.00 600.00
U/SK labourer Days 6.00 400.00 2,400.00
24,974.33
O/H & Proffits 0.00 0.00
Rate per Cube 24,974.33
NOTE : 8,824.85
a) Water available at site.
b) If, water is not available
allowances must be made for
transport of water.
c) Sand - includes 15% for bulking

24. 2" thk. cement concrete screed in


foundation at depths not exceeding 5' 0"
Per Square
Materials
concrete Cubes 0.17 19,739.25 3,289.88

Page 3
Conc-Fm-Rf Work

add 10% for wastage 328.99


Labour:
SK labourer Day 0.13 600.00 75.00
U/SK labourer Day 0.50 400.00 200.00
3893.86
O.H & proffit 0.00 0.00
Rate per Square 3893.86
NOTE :
For laying concrete at depths more
than 5' 0" add 1/6 day unskilled
labourer for each additional 5' 0" or
part thereof per squre.

25. 3" thk. cement concrete screed in


foundation at depths not exceeding 5' 0"
Per Square
Materials
concrete Cubes 0.25 19,739.25 4,934.81
add 10% for wastage 493.48
Labour:
SK labourer Day 0.13 600.00 75.00
U/SK labourer Day 0.75 400.00 300.00
5,803.29
O.H & proffit 0.00 0.00
Rate per Square 5,803.29
624.68
For laying concrete at depths more than 5' 0"
add 1/4 day unskilled labourer for each
additional 5' 0" or part thereof per square.

26. 6" thk. cement concrete floor (Mass conc.)


Per Square
Materials
concrete Cubes 0.50 19,739.25 9,869.63
add 5% for wastage 493.48
Water Gals 200.00 1.00 200.00
Labour:
SK labourer Day 0.50 600.00 300.00
Day U/SK labourer Day 1.25 400.00 500.00
11,363.11
O.H & proffit 0.00 0.00
Rate per Square 11,363.11
NOTE :
a) Water available at site.
b) If, water is not available
allowances must be made for
transport of water.

27. Cement concrete in 4 1/2" x 6" columns


in ground floor.
Consider 24 No.columns each 4 1/2"x 6"x10'
ie. 0.45 cubes.
Per 0.45 cube
Materials

Page 4
Conc-Fm-Rf Work

concrete Cubes 0.45 19,739.25 8,882.66


add 10% for wastage 888.27
hire of vibrator Day 0.13 1,500.00 187.50
Labour:
Mason Day 0.38 650.00 247.00
Carpenter Day 1.00 650.00 650.00
U/SK labourer Days 0.63 400.00 250.00
SK labourer(Vibrator) Day 0.13 600.00 78.00
Curing
Jute Hessian Sq.ft 10.00 1.00 10.00
Water Gals 170.00 1.00 170.00
U/Sk labourer Day 0.38 400.00 152.00
11,515.43
O.H & proffit 0.00 0.00
Total for 0.45 cubes or 240 l.ft of column 11,515.43
Rate per cube of column 25,589.84
9,042.35
NOTE :
1) For columns in 1st floor add
3% to ground floor rate
2) For columns in 2nd floor add
5% to ground floor rate
3) For columns in 3rd floor add
7% to ground floor rate
4) Water available at site.
5) If, water is not available
allowances must be made for
transport of water.

28. Cement concrete in 6" x 6" columns in


ground floor.
Consider 18 No. columns 6"x 6" each 10' 0"
ie. 0.45 cubes.
Per 0.45 cube
Materials
concrete Cubes 0.45 18,751.33 8,438.10
add 10% for wastage 843.81
hire of vibrator Day 1.00 1,500.00 1,500.00
Labour:
Mason Day 1.00 650.00 650.00
Carpenter Day 1.00 650.00 650.00
U/SK labourer Days 3.00 400.00 1,200.00
SK labourer(Vibrator) Day 1.00 600.00 600.00
Curing
Jute Hessian Sq.ft 80.00 1.00 80.00
Water Gals 140.00 1.00 140.00
U/Sk labourer Day 1.50 400.00 600.00
14,701.91
O.H & proffit 0.00 0.00
Total for 0.45 cubes or 180 l.ft of column 14,701.91
Rate per cube of column 32670.91
11,544.49
NOTE :
1) For columns in 1st floor add

Page 5
Conc-Fm-Rf Work

3% to ground floor rate


2) For columns in 2nd floor add
5% to ground floor rate
3) For columns in 3rd floor add
7% to ground floor rate
4) Water available at site.
5) If, water is not available
allowances must be made for
transport of water.

29. Cement concrete in 9" x 9" columns in


ground floor.
Consider 8 Nos. 9"x 9" columns each 10' 0"
ie. 0.45 cubes.
Per 0.45 cube
Materials
concrete Cubes 0.45 18,751.33 8,438.10
add 10% for wastage 843.81
hire of vibrator Day 1.00 1,500.00 1,500.00
Labour:
Mason Day 1.00 650.00 650.00
Carpenter Day 1.00 650.00 650.00
U/SK labourer Days 3.00 400.00 1,200.00
Sk/labourer(Vibrator) Day 1.00 600.00 600.00
Curing
Jute Hessian Sq.ft 60.00 1.00 60.00
Water Gals 100.00 1.00 100.00
U/Sk labourer Day 0.50 400.00 200.00
14,241.91
O.H & proffit 0.00 0.00
Total for 0.45 cubes or 80 Lft of Column 14,241.91
Rate per cube of Column 31648.69
11183.28
NOTE :
1) For columns in 1st floor add
3% to ground floor rate
2) For columns in 2nd floor add
5% to ground floor rate
3) For columns in 3rd floor add
7% to ground floor rate
4) Water available at site.
5) If, water is not available
allowances must be made for
transport of water.

30. Cement concrete in 12" x 12" columns in


ground floor.
Consider 5 Nos. 12"x 12" columns
each 10' 0" high
Per 0.5 cube
Materials
0.5 cube concrete Cube 0.50 18,751.33 9,375.67
add 5% for wastage 468.78
Jute Hessian - 40 Sq.ft Sq.ft 40.00 1.00 40.00

Page 6
Conc-Fm-Rf Work

hire of vibrator Day 1.00 1,500.00 1,500.00


Water Gals 100.00 1.00 100.00
Labour:
Mason Day 1.00 650.00 650.00
Carpenter Day 1.00 650.00 650.00
U/SK labourer Days 3.00 400.00 1,200.00
SK labourer(Vibrator) Day 1.00 600.00 600.00
U/SK labourer (curing) Day 1.50 400.00 600.00
15,184.45
O.H & proffit 0.00 0.00
Total for 0.5 cubes or 50 l.ft of column 15,184.45
Rate per cube of column 30,368.90
NOTE : 10,731.06
1) For columns in 1st floor add
3% to ground floor rate
2) For columns in 2nd floor add
5% to ground floor rate
3) For columns in 3rd floor add
7% to ground floor rate
4) Water available at site.
5) If, water is not available
allowances must be made for
transport of water.

31. Cement concrete in 13 1/2" x 13 1/2"


columns in ground floor.
Consider 4 Nos. 13 1/2"x 13 1/2" columns
each 10' 0" high. i.e. 0.51 cubes
Per 0.51 cubes
Materials
Concrete Cube 0.51 18,751.33 9,563.18
add 5% for wastage 478.16
hire of vibrator Day 1.00 1,500.00 1,500.00
Labour:
Mason Day 1.00 650.00 650.00
Carpenter Day 1.00 650.00 650.00
U/SK labourer Days 3.00 400.00 1,200.00
SK labourer(Vibrator) Day 1.00 600.00 600.00
Curing
Jute Hessian Sq.ft 45.00 1.00 45.00
Water Gals 100.00 1.00 100.00
U/Sk labourer Day 1.50 400.00 600.00
15,386.34
O.H & proffit 0.00 0.00
Total for 0.51 cubes or 40 l.ft of column 15,386.34
Rate per cube of column 30,169.29
NOTE :
1) Water available at site.
2) If, water is not available
allowances must be made for
transport of water.
10,660.53
32. Cement concrete in 6" x 6" beam up to
1st floor level.

Page 7
Conc-Fm-Rf Work

Consider 180 l.ft of beam 6" x 6" i.e 0.45cbs


Per 0.45 cubes
Materials
concrete Cube 0.45 18,751.33 8,438.10
add 10% for wastage 843.81
hire of vibrator Day 1.00 1,500.00 1,500.00
Labour:
Mason Day 1.00 650.00 650.00
Carpenter Day 1.00 650.00 650.00
U/SK labourer Days 4.00 400.00 1,600.00
SK labourer(Vibrator) Day 1.00 600.00 600.00
Curing
Jute Hessian Sq.ft 90.00 1.00 90.00
Water Gals 180.00 1.00 180.00
U/Sk labourer Day 1.50 400.00 600.00
15,151.91
O.H & proffit 0.00 0.00
Total for 0.45 cubes or 180 l.ft of column 15,151.91
Rate per cube of column 33,670.91
NOTE :
1) Water available at site.
2) If, water is not available
allowances must be made for
transport of water.
11,897.85
33. Cement concrete in 9" x 6" beam up to
1st floor level.
Consider 120 l.ft of beam 9" x 6" i.e 0.45 cbs
Per 0.45 cubes
Materials
concrete Cube 0.45 18,751.33 8,438.10
add 10% for wastage 843.81
hire of vibrator Day 1.00 1,500.00 1,500.00
Labour:
Mason Day 1.00 650.00 650.00
Carpenter Day 1.00 650.00 650.00
U/SK labourer Days 4.00 400.00 1,600.00
SK labourer(Vibrator) Day 1.00 600.00 600.00
Curing
Jute Hessian Sq.ft 75.00 1.00 75.00
Water Gals 150.00 1.00 150.00
U/Sk labourer Day 1.50 400.00 600.00
15,106.91
O.H & proffit 0.00 0.00
Total for 0.45 cubes or 120 l.ft of beam 15,106.91
Rate per cube of beam 33,570.91
NOTE :
1) Water available at site.
2) If, water is not available
allowances must be made for
transport of water.
11,862.51
34. Cement concrete in 9" x 9" beam up to
1st Floor

Page 8
Conc-Fm-Rf Work

Consider 80 l.ft of beam 9" x 9" i.e 0.45 cbs


Per 0.45 cubes
Materials
concrete Cube 0.45 18,751.33 8,438.10
add 10% for wastage 843.81
hire of vibrator Day 1.00 1,500.00 1,500.00
Labour:
Mason Day 1.00 650.00 650.00
Carpenter Day 1.00 650.00 650.00
U/SK labourer Days 4.00 400.00 1,600.00
SK labourer(Vibrator) Day 1.00 600.00 600.00
Curing
Jute Hessian Sq.ft 60.00 1.00 60.00
Water Gals 120.00 1.00 120.00
U/Sk labourer Day 1.50 400.00 600.00
15,061.91
O.H & proffit 0.00 0.00
Total for 0.45 cubes or 80 l.ft of beam 15,061.91
Rate per cube of beam 33,470.91
NOTE :
1) Water available at site.
2) If, water is not available
allowances must be made for
transport of water.
11,827.18
35. 5" thick R.C.C floor slab in 1st floor
Consider 5" thick slab 10' 0" x 12' 0"
volume of concrete 50.00 cu.ft
Per 50.00 cu.ft
Materials
concrete cube 0.50 18,751.33 9,375.67
add 10% for wastage 937.57
hire of vibrator Day 1.00 1,500.00 1,500.00
Labour:
Mason Day 1.00 650.00 650.00
Carpenter Day 1.00 650.00 650.00
U/SK labourer Days 4.00 400.00 1,600.00
SK labourer(Vibrator) Day 1.00 600.00 600.00
Curing
Jute Hessian Sq.ft 30.00 1.00 30.00
Water Gals 90.00 1.00 90.00
U/Sk labourer Day 1.50 400.00 600.00
16,033.23
O.H & proffit 0.00 0.00
Total for 50.0 cu.ft or 120 sq.ft 16,033.23
Rate per cube 32,066.47
11,330.91
NOTE :
1) Water available at site.
2) If, water is not available
allowances must be made for
transport of water.

36. 6" thick R.C.C floor slab in 1st floor

Page 9
Conc-Fm-Rf Work

Consider 10' 0" x 10' 0" panel = 50cu.ft


Materials
concrete cube 0.50 18,751.33 9,375.67
add 10% for wastage 937.57
hire of vibrator Day 1.00 1,500.00 1,500.00
Labour:
Mason Day 1.00 650.00 650.00
Carpenter Day 1.00 650.00 650.00
U/SK labourer Days 4.00 400.00 1,600.00
SK labourer(Vibrator) Day 1.00 600.00 600.00
Curing
Jute Hessian Sq.ft 25.00 1.00 25.00
Water Gals 90.00 1.00 90.00
U/Sk labourer Day 1.50 400.00 600.00
16028.23
O.H & proffit 0.00 0.00
Total for 50.0 cu.ft or 100 sq.ft 16,028.23
Rate per cube 32,056.47
11,327.37
NOTE :
1) Water available at site.
2) If, water is not available
allowances must be made for
transport of water.

37. Cement Concrete in 4-1/2" x 6" lintols in


ground floor
Consider 240 L.ft i.e 45 cu.ft
Materials
concrete cube 0.45 18,751.33 8,438.10
add 10% for wastage 843.81
hire of vibrator Day 1.00 1,500.00 1,500.00
Labour:
Mason Day 1.00 650.00 650.00
Carpenter Day 1.00 650.00 650.00
U/SK labourer Days 4.00 400.00 1,600.00
SK labourer(Vibrator) Day 1.00 600.00 600.00
Curing
Jute Hessian Sq.ft 10.00 1.00 10.00
Water Gals 90.00 1.00 90.00
Day U/Sk labourer Day 1.50 400.00 600.00
14,981.91
O/H & Proffits 0.00 0.00
Total for 0.45 cube or 240 l.ft oflintol 14,981.91
Rate per cube of lintol 33,293.13
11,764.36
NOTE :
1) Water available at site.
2) If, water is not available
allowances must be made for
transport of water.
62.42
38. Cement concrete in 9"x 9" lintols in
ground floor.

Page 10
Conc-Fm-Rf Work

Consider 80 L.ft of lintol i.e 45cu.ft.


Materials
concrete cube 0.45 18,751.33 8,438.10
add 10% for wastage 843.81
hire of vibrator Day 1.00 1,500.00 1,500.00
Labour:
Mason Day 1.00 650.00 650.00
Carpenter Day 1.00 650.00 650.00
U/SK labourer Days 4.00 400.00 1,600.00
SK labourer(Vibrator) Day 1.00 600.00 600.00
Curing
Jute Hessian Sq.ft 60.00 1.00 60.00
Water Gals 90.00 1.00 90.00
U/Sk labourer Day 1.50 400.00 600.00
15,031.91
O.H & proffit 0.00 0.00
Total per 0.45 cube or 80 l.ft of lintol 15,031.91
Rate per cube of lintol 33,404.24
187.90
NOTE :
1) Water available at site.
2) If, water is not available
allowances must be made for
transport of water.

39. Cement concrete in 9"x 12" lintols in


ground floor.
Consider length 60' 0" of lintol = 45cu.ft
Materials
concrete cube 0.45 18,751.33 8,438.10
add 10% for wastage 843.81
hire of vibrator Day 1.00 1,500.00 1,500.00
Labour:
Mason Day 1.00 650.00 650.00
Carpenter Day 1.00 650.00 650.00
U/SK labourer Days 4.00 400.00 1,600.00
SK labourer(Vibrator) Day 1.00 600.00 600.00
Curing
Jute Hessian Sq.ft 55.00 1.00 55.00
Water Gals 90.00 1.00 90.00
U/Sk labourer Day 1.50 400.00 600.00
15,026.91
O.H & proffit 0.00 0.00
Total for 0.45 cube or 60 l.ft of lintol 15,026.91
Rate per cube of lintol 33393.13
250.45
NOTE :
1) Water available at site.
2) If, water is not available
allowances must be made for
transport of water.

40. Cement concrete in 12"x 15" lintols in


ground floor.

Page 11
Conc-Fm-Rf Work

Consider length 36' 0" of lintol i.e 45cu.ft


Materials
concrete cube 0.45 18,751.33 8,438.10
add 10% for wastage 843.81
hire of vibrator Day 1.00 1,500.00 1,500.00
Labour:
Mason Day 1.00 650.00 650.00
Carpenter Day 1.00 650.00 650.00
U/SK labourer Days 4.00 400.00 1,600.00
SK labourer (Vibrator) Day 1.00 600.00 600.00
Curing
Jute Hessian Sq.ft 40.00 1.00 40.00
Water Gals 90.00 1.00 90.00
U/Sk labourer Day 1.50 400.00 600.00
15,011.91
O.H & proffit 0.00 0.00
Total for 0.45 cube or 36 l.ft of lintol 15,011.91
Rate per cube of lintol 33,359.80
417.00
NOTE :
1) Water available at site.
2) If, water is not available
allowances must be made for
transport of water.

41. Sawn timber or work to 9" x9" cement


concrete column in ground floor.
Consider column length of 5' 0"
concrete area. - 15.0 sq.ft
MAKING MOULD
Materials
1" thick class II timber Sq.ft 18.15 312.50 5,671.88
2"x 2" class II timber in yokes L.ft 17.10 18.00 307.80
2"x 1" class II timber battens L.ft 16.12 8.00 128.96
wire nails. Lb 1.50 43.13 64.70
2) Fabricating
carpenter Day 0.50 650.00 325.00
U/SK labourer Day 0.50 400.00 200.00
Total Cost 6,698.33
Allowing 4 uses cost of mould per use 1,674.58
b) Assembling (per use)
Materials
16mm 18" long bolts (20 uses) Nos 12.00 75.00 45.00
mould oil Ltrs 0.50 75.00 37.50
4"x 2" props (10 uses) L.ft 35.00 10.00 35.00
Labour :
Carpenter Day 0.25 650.00 162.50
U/SK labourer Day 0.25 400.00 100.00
Cost of Assembling per use 380.00
c) Dismantling cleaning & repairing
(per use)
Labour :
Carpenter Day 0.25 650.00 162.50
U/SK labourer Day 0.25 400.00 100.00

Page 12
Conc-Fm-Rf Work

Cost of dismantling per use 262.50


Total Cost per use (for 15.0 sq.ft)(a+b+c) 2,317.08
O/H & Proffits 0.00 0.00
Rate per Square 15,447.22
1,662.78
42. Sawn timber formwork for concrete
beams in ground floor.
Consider 9"x 12" beam of 20' 0" long.
Contact area 55 sq.ft
a) Making the mould
a) 1"thk timber planks Sq.ft 60.00 312.50 18,750.00
b) 2"x 1" battens L.ft 24.00 8.00 192.00
c) 2"x 2" ledges L.ft 45.00 18.00 810.00
d) 4"x 2" bearers at bottom of mould L.ft 30.00 60.00 1,800.00
e) 2 lbs wire nails lbs 2.00 43.13 86.26
Labour :
Carpenter Day 1.50 650.00 975.00
U/SK labourer Day 2.00 400.00 800.00
Total cost of mould 23,413.26
Assuming 4 uses cost per use 5,853.32
Add 10% for repairs 585.33
Cost per use 6,438.65
B) Assumbling
Materials
a) 4" x 2" vertical props. L.ft 110.00 10.00 1,100.00
b) 2" X 2" bracing to mould and props ft 80.00 18.00 1,440.00
c) 2"x 2" bracing to a set of props L.ft 50.00 18.00 900.00
d) 1" timber base plate to props Sq.ft 6.00 312.50 1,875.00
e) wedges Nos 22.00 8.00 176.00
Cost of materials for assembling. 5,491.00
Assuming as average of 6 uses.
Cost of materials per uses. 915.17
Add 10% of cost of materials for repairs 91.52
Total cost of materials per use 1,006.68
c) Labour & Sundries
Labour:
a) carpenter Day 1.00 650.00 650.00
b) U/Sk labourer Day 2.00 400.00 800.00
c) mould oil ltr 2.27 75.00 170.25
d) nails Lbs 0.50 43.13 21.57
Cost per use 1,641.82
d) Dismantling and cleaning
Labour:
a) carpenter Day 0.50 650.00 325.00
b) U/Sk labourer Day 2.00 400.00 800.00
Cost of labour for dismantling per use 1,125.00
Total cost for making the mould
assembling alinging dismantling and
cleaning for 55 sq.ft per use.(a+b+c+d) 10,212.14
O/H & Proffits 0.00 0.00
Rate of form work per square 18,567.54
1,998.66
43. Sawn timber formwork for under side
of first floor slab.

Page 13
Conc-Fm-Rf Work

Consider a slab of 20' 0" x 10' 0"


Contact area = 2.0 sqrs.
a) Making panels
1) Materials
a) 1" thk. tongue and grooved timber planks Sq.ft 220.00 312.50 68,750.00
b) 4"x 2" runners at 2' 0"centres L.ft 121.00 60.00 7,260.00
c) wire nails. Lbs 4.00 43.13 172.52
2) Labour
a) carpenter Day 1.00 650.00 650.00
b) U/Sk labourer Day 1.00 400.00 400.00
Total cost of making panels 77,232.52
Assuming 4 uses cost per use 19,308.13
Add 20% for repairs 3,861.63
Total cost of panels per use 23,169.76
B) Assumbling
Materials
a) 4" x 2" vertical props. L.ft 690.00 10.00 6,900.00
b) 2" X 2" bracing for props L.ft 66.00 11.00 726.00
c) wedges Nos 122.00 3.00 366.00
d) 1" base plates for props Sq.ft 333.00 15.00 4,995.00
Cost of materials for assembling. 12,987.00
Assuming as average of 6 uses.
Cost of materials per use. 2,164.50
Add 20% of cost of materials for repairs 432.90
Total cost of materials per use 2,597.40
c) Labour & Sundries
Assembling
a) carpenter Day 1.00 650.00 650.00
b) U/Sk labourer Day 4.00 400.00 1,600.00
c) mould oil for assembling ltr 4.54 75.00 340.50
d) nails Lbs 2.00 43.13 86.26
Cost per use for assembling 2,676.76
d) Dismantling and cleaning
Labour:
a) carpenter Day 0.50 650.00 325.00
b) U/Sk labourer Day 2.00 400.00 800.00
cost per use for dismantling & cleaning 1,125.00
use for 200 sq.ft (A + B + C + D) 29,568.92
O/H & Proffits 0.00 0.00
Cost of form work per square 14,784.46

44. Tor steel for steel reinforcement to 1,590.57


lintols slab beams for column bent to
shape laid in position and tied with
G.I wire as directed.
Materials
Tor steel rods Cwt 1.00 3,228.48 3,228.48
(Including transport to site)
Allow for wastage 15% 484.27
16 BWG binding wire Lbs 1.50 24.19 36.29
Add 1.5% of steel cost for spacers or
chairs. 55.69
Labour:
a) blacksmith Day 1.00 625.00 625.00

Page 14
Conc-Fm-Rf Work

b) U/Sk labourer Day 1.00 400.00 400.00


4,829.73
O/H & Proffits 0.00 0.00
Rate per Cwt 4,829.73

44a. Mild steel for steel reinforcement to 96.59


lintols slab beams for column bent to
shape laid in position and tied with
G.I wire as directed.
Materials
Mild steel rods Cwt 1.00 3,185.00 3,185.00
(Including transport to site)
Allow for wastage 15% 477.75
16 BWG binding wire Lbs 1.50 24.19 36.29
Labour:
a) blacksmith Day 1.00 625.00 625.00
b) U/Sk labourer Day 1.00 400.00 400.00
4,724.04
O/H & proffits 0.00 0.00
Rate per Cwt 4,724.04

94.48

41. Sawn timber or work to 9" x9" cement


concrete column in ground floor.
Consider contact area of 1.40 m2

MAKING MOULD
Materials
1" thick class II timber m2 0.45 540.00 243.00
2"x 2" class II timber in yokes m 1.30 51.00 66.30
2"x 1" class II timber battens m 1.25 20.00 25.00
wire nails. kg 0.40 45.00 18.00
2) Fabricating
carpenter Day 0.13 500.00 62.50
U/SK labourer Day 0.13 300.00 37.50
Add 5% for tools 5.00
Total Cost 457.30
Allowing 4 uses cost of mould per use 114.33
b) Assembling (per use)
Materials
16mm 18" long bolts (20 uses) Nos 0.60 75.00 2.25
mould oil Ltrs 0.50 75.00 37.50
4"x 2" props (10 uses) m 1.10 80.00 8.80
Labour :
Carpenter Day 0.25 500.00 125.00
U/SK labourer Day 0.25 300.00 75.00
Add 5% for tools 10.00
Cost of Assembling per use 258.55
c) Dismantling cleaning & repairing
(per use)

Page 15
Conc-Fm-Rf Work

Labour :
Carpenter Day 0.25 500.00 125.00
U/SK labourer Day 0.25 300.00 75.00
Add 5% for tools 10.00
Cost of dismantling per use 210.00

Total Cost per use (for 1.4m2t)(a+b+c) 582.88


O/H & Proffits 0.30
Rate per m2 416.34

42. Sawn timber formwork for concrete


beams in ground floor.
Contact area 5 m2

a) Making the mould


a) 1"thk timber planks m2 0.30 447.00 134.10
b) 2"x 1" battens m 2.00 15.00 30.00
c) 2"x 2" ledges m 3.75 38.00 142.50
d) 4"x 2" bearers at bottom of mould m 2.50 80.00 200.00
e) 2 lbs wire nails kg 0.25 45.00 11.25
Labour :
Carpenter Day 0.35 650.00 227.50
U/SK labourer Day 0.60 400.00 240.00
Add 5% for tools 23.38
Total cost 1,008.72
Total cost per use 252.18

B) Assembling
Materials
a) 4" x 2" vertical props. m 6.20 80.00 496.00
b) 2" X 2" bracing to mould and props m 7.30 38.00 277.40
d) 1" timber base plate to props m 0.10 447.00 44.70
e) mould oil ltr 4.31 75.00 323.25
f) nails kg 0.25 45.00 11.25
g) wedges 81.81

c) Labour & Sundries


Labour:
a) carpenter Day 1.00 650.00 650.00
b) U/Sk labourer Day 2.00 400.00 800.00
Add 5% for tools 72.50

Cost per use 2,756.91


d) Dismantling and cleaning
Labour:
a) carpenter Day 0.50 650.00 325.00
b) U/Sk labourer Day 2.00 400.00 800.00
Add 5% for tools 56.25
Cost of labour for dismantling per use 1,181.25

Total cost 4,190.34


O/H & Proffits 0.30 1,257.10
Rate of form work per m2 1,089.49

Page 16
Conc-Fm-Rf Work

43. Sawn timber formwork for under side


of first floor slab.

Contact area 20m2.


a) Making panels
1) Materials
a) 1" thk. tongue and grooved timber planks m2 6.70 504.00 3,376.80
b) 4"x 2" runners at 2' 0"centres m 10.00 80.00 800.00
c) wire nails. kg 0.50 45.00 22.50
2) Labour
a) carpenter Day 1.00 650.00 650.00
b) U/Sk labourer Day 1.00 400.00 400.00
Add 5% for tools 52.50

Total cost of making panels 5,301.80


Assuming 4 uses cost per use 1,325.45
Add 20% for repairs 265.09
Total cost of panels per use 1,590.54
B) Assumbling
Materials
a) 4" x 2" vertical props. m 45.50 80.00 3,640.00
b) 2" X 2" bracing for props m 4.50 38.00 171.00
c) mould oil for assembling ltr 5.00 75.00 375.00
d) nails kg 1.00 45.00 45.00

c) Labour & Sundries


Assembling
a) carpenter Day 1.10 650.00 715.00
b) U/Sk labourer Day 4.40 400.00 1,760.00
Add 5% for tools 123.75
Cost per use for assembling 6,829.75

d) Dismantling and cleaning


Labour:
a) carpenter Day 0.60 650.00 390.00
b) U/Sk labourer Day 2.20 400.00 880.00
Add 5% for tools 63.50
cost per use for dismantling & cleaning 1,333.50

total cost for 20 m2 (A + B + C + D) 9,753.79


O/H & Proffits 0.30 2,926.14

Cost of form work per m2 634.00

Page 17
excavation

BUILDING SCHEDULE OF RATES - EXCAVATION & EARTH WORKS,PLANKING

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


Rs. Cts. Rs. Cts.
PRELIMINARIES
01 Removing top soil to a depth not exceeding
6" & depositing as derected within the site
Per Square:
Consider as area of 10.00 sqrs ie
5.00 cubes of excavation.
U/SK Labourer Days 9.00 400.00 3,600.00
Add for tools (2%) 9.00 8.00 72.00
Total for 10.00 square 3,672.00
O.H & proffit 0.00 0.00
Rate per Square 3,672.00
395.26
02 Excavation over site to reduce level,in any
meterial except rock requiring blasting
including depositing and levelling as
derected up to distance not exceeding 30ft.
Per Cube:
U/SK Labourer Days 1.38 400.00 550.00
550.00
O.H & proffit 0.00 0.00
Rate per Cube 550.00

03 Excavation in trenches for wall/column pits 194.35


in soft/loose soil from 0 ft. to 5 ft. deep and
depositing excavated material to a distance
not exceeding 30' 0" ( Earth work supports
to be paid seperately where necessary)
Per Cube:
U/SK Labourer Days 1.00 400.00 400.00
400.00
O.H & proffit 0% 0.00
Rate per Cube 400.00
141.34
04. Excavation in trenches for wall/column pits
in ordinary soil from 0' 0" to 5' 0" deep and
depositing excavated material not
exceeding 30' 0"
Per Cube:
U/SK Labourer Days 2.25 400.00 900.00
900.00
O.H & proffit 0% 0.00
Rate per Cube 900.00

05. Excavation in trenches for wall/column pits 318.02


in hard/dense soil up to a depth of 5' 0" and
depositing excavated material up to a

Page 18
excavation

distance not exceeding 30' 0"


Per Cube:
U/SK Labourer Days 3.50 400.00 1,400.00
1,400.00
O.H & proffit 0.00 0.00
Rate per Cube 1,400.00
494.70
06. Excavation in trenches for wall/column pits
in mud/wet soil up to a depth of 5' 0" and
depositing excavated material up to a
distance not exceeding 30' 0"
(Earth work & de-watering paid for
seperatly)
Per Cube:
U/SK Labourer Days 3.00 400.00 1,200.00
1,200.00
O.H & proffit 0.00 0.00
Rate per Cube 1,200.00
424.03
07. Excavation in trenches for wall/column pits
in soft distintegrated rock (not requiring
blasting) up to a depth of 5' and deposting
excavated material to a distance not
exceeding 30' 0"
Per Cube:
U/SK Labourer Days 2.50 400.00 1,000.00
1,000.00
O.H & proffit 0.00 0.00
Rate per Cube 1,000.00
353.36
08. Excavation in trenches for wall/column pits
in hard rock requiring blasting up to a
depth of 5' 0" and deposting excavated
material to a distance not exceeding 30' 0"
Per Cube: (Materials)
blasting powder lbs 0.75 0.00 0.00
fuse wire L.ft 10.00 0.00 0.00
jumper steel lb 1.00 0.00 0.00
Fuel & forge - 20% of material cost 0.00
Labour:
SK Labourer Day 1.00 600.00 600.00
U/SK Labourer Day 2.50 400.00 1,000.00
1,600.00
O.H & proffit 0.00 0.00
Rate per Cube 1,600.00

DISPOSAL=100 PER M3
565.37
09. Benching rock in foundation in 3"- 6" steps
(Blasting Prohibited)

Page 19
excavation

Per 10 square feet:


Drilling, Chipping & Wedging
SK Labourer Days 1.50 600.00 900.00
Steel, Fuel & forge - 25% of labour cost 225.00
collecting & disposing
U/SK Labourer Days 1.50 400.00 600.00
1,725.00
O.H & proffit 0.00 0.00
Total per 10 squre feet: 1,725.00
Rate per Sq.ft 172.50
1,854.84
Anti-Termite Treatment : 1 sq.ft =72.00(without markup)
10 Anti-Termite Treatment on excavated
foundation and compacted soil under floors
Per Square:
DDT powder ( 8% in 20 gal water) Lbs 16.00 0.00 0.00
water Gals 20.00 1.00 20.00
Labour:
U/SK Labourer Days 0.50 400.00 200.00
220.00
O.H & proffit 0.00 0.00
Rate per Square. 220.00
NOTE:
Alternative Mixes :
a) Copper Naphthenate ( 05% in 04 to 08 gals.
of fuel oil)
b) Sodium arsenate (10 % in 12 to 20 gals of
water)
c) Dieldrine ( 0.3% in 19 gals of water)

Earth work - backfilling & compacting

11 Backfilling to trenches with selected earth


available at site
Per Cube
U/sk Labour Day 1.50 400.00 600.00
600.00
O/H & Proffits 0.00 0.00
Rate per cube 600.00

12. Back filling to trenches with imported 212.01


materials
Per Cube:
earth delivered at site. Cube 1.00 400.00 400.00
Allow 15% compaction 60.00
Filling & compacting
U/SK Labourer Days 1.50 400.00 600.00
1,060.00
O.H & proffit 0.00 0.00
Rate per Cube 1,060.00

Page 20
excavation

13. Filling under floors including levelling, 374.56


watering & compacting in 3" layers with
available and selected earth at site
Per Cube:
U/SK Labourer Days 2.00 400.00 800.00
800.00
O.H & proffit 0.00 0.00
Rate per Cube 800.00
282.69
14. Filling under floors including levelling,
watering & compacting in 3" layers with
imported selected earth.
Per Cube:
earth delivered at site Cube 1.00 1,000.00 1,000.00
Allow for 15% compaction 150.00
U/SK Labourer Days 2.00 400.00 800.00
1,950.00
O.H & proffit 0.00 0.00
Rate per Cube 1,950.00
689.05
15. Cutting turf sods, loading to hand carts and
transporting up to 30 yards, laying and
watering for 30 days ( Royalty for turf,
pegging and transport beyond 30 yards
paid seperately)
Per Square:
Cutting turf sods, loading and transporting to
site and unloading.
U/SK Labourer Days 2.50 400.00 1,000.00
Laying turf sods at site
U/SK Labourer Day 0.50 400.00 200.00
Watering for 30 Days
U/SK Labourer Days 1.50 400.00 600.00
Water Gal 60.00 1.00 60.00
1,860.00
O.H & proffit 0.00 0.00
Rate per Square 1,860.00

Page 21
Plastering

BUILDING SCHEDULE OF RATES - PLASTER & PAVIOUR

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


Rs. Cts. Rs. Cts.

98. 3/4" thick D.P.C in cement sand 1:2


finished with 2 coats hot tar and
blinded with sand.

Per square
Materials:
cement Cwt 2.25 485.00 1,091.25
sand Cube 0.11 5,000.00 550.00
bitumen Gals 1.50 76.27 114.41
Fire wood lbs 10.00 1.79 17.86
Water Gals 10.00 1.00 10.00

Labour
mason Days 1.25 650.00 812.50
U/Sk labourer Days 2.50 400.00 1,000.00
3,596.02
O/H & Proffits 0.00 0.00
Rate per square 3,596.02
386.93
99. 5/8" thick plastering to wall in lime
and sand 2:5 including floating with
lime putty.

Per Square
Materials:
slaked lime Cwt 1.30 425.00 552.50
sand Cubes 0.07 5,000.00 350.00
Water Gals 10.00 1.00 10.00

Labour
mason Days 1.00 650.00 650.00
U/SK labourer Days 1.75 400.00 700.00
Scaffolding - Add 3% 40.50
2,303.00
O/H & Proffits 0.00 0.00
Rate per square 2,303.00
247.80
100. 5/8" thick plastering to wall in
cement sand 1:3 including cement
floating

Per square
Materials:
cement ( 50 kg bags) Cwt 1.40 485.00 679.00
sand Cubes 0.06 5,000.00 300.00
Water Gals 10.00 1.00 10.00

Labour
mason Days 1.00 650.00 650.00
U/SK labourer Days 1.25 400.00 500.00
Scaffolding - Add 3% 34.50
2,173.50
O/H & proffits 0.00 0.00
Rate per square 2,173.50
233.87
101. 3/8" thick plastering to soffit slab
in cement sand 1:3 including floating
with lime putty

Per square
Materials:
cement ( 50 kg bags) Cwt 0.08 485.00 38.80
slaked lime Cwt 0.16 425.00 68.00
sand Cubes 0.05 5,000.00 250.00
Water Gals 5.00 1.00 5.00

Labour
mason Days 2.50 650.00 1,625.00
U/SK labourer Days 2.50 400.00 1,000.00
Scaffolding - Add 3% 78.75
3,065.55
O/H & Proffits 0.00 0.00
Rate per square 3,065.55
329.85
102. 3/8" thick plastering to sides and
soffit of beams in cement sand 1:3
including floating with lime putty.

Materials:
cement ( 50 kg bags) Cwt 0.08 485.00 38.80
slaked lime Cwt 0.16 425.00 68.00
sand Cubes 0.05 5,000.00 250.00
Water Gals 5.00 1.00 5.00

Labour
mason Days 2.00 650.00 1,300.00
U/SK labourer Days 2.00 400.00 800.00
Scaffolding - Add 3% 63.00

Page 22
Plastering

2,524.80
O/H & Proffits 0.00 0.00
Rate per square 2,524.80
271.67
103. 5/8" thick to wall in lime cement and
sand 1:1:5 finished semi - rough with
wooden float.

Per square
Materials:
cement ( 50 kg bags) Cwt 0.80 485.00 388.00
slaked lime Cwt 0.40 425.00 170.00
sand Cubes 0.07 5,000.00 350.00
Water Gals 10.00 1.00 10.00

Labour
mason Days 1.00 650.00 650.00
U/SK labourer Days 1.25 400.00 500.00
Scaffolding - Add 3% 34.50
2,102.50
O/H & Proffits 0.00 0.00
Rate per square 2,102.50
226.23
104. 5/8" thick plastering to wall in lime
cement and sand 1:1:5 finished smooth
with lime putty floating.

Materials:
cement ( 50 kg bags) Cwt 0.80 485.00 388.00
slaked lime Cwt 0.60 425.00 255.00
sand Cubes 0.07 5,000.00 350.00
Water Gals 10.00 1.00 10.00

Labour
mason Days 1.50 650.00 975.00
U/SK labourer Days 1.50 400.00 600.00
Scaffolding - Add 3% 47.25
2,625.25
O/H & Proffits 0.00 0.00
Rate per square 2,625.25
282.48
105. 1/2" thick rendering in cement and
sand 1:3 finished smooth

Per Square
Materials:
cement ( 50 kg bags) Cwt 1.07 485.00 518.95
sand Cubes 0.05 5,000.00 250.00
Water Gals 10.00 1.00 10.00

Labour
mason Days 1.00 650.00 650.00
U/SK labourer (curing) Days 1.50 400.00 600.00
2,028.95
O/H & Proffits 0.00 0.00
Rate per square 2,028.95
218.40
106. 1/2" thick rendering in cement and
sand 1:2 in floors, finished smooth

Per square
Materials:
cement ( 50 kg bags) Cwt 1.50 485.00 727.50
sand Cubes 0.05 5,000.00 250.00
Water Gals 10.00 1.00 10.00

Labour
mason Days 1.00 650.00 650.00
U/SK labourer Days 1.50 400.00 600.00
U/SK labourer (curing) Days 0.25 400.00 100.00
2,337.50
O/H & Proffits 0.00 0.00
Rate per square 2,337.50
251.52
107. 3/4" thick rendering in cement and
sand 1:3 finished smooth

Per square
Materials:
cement ( 50 kg bags) Cwt 1.75 485.00 848.75
sand Cubes 0.08 5,000.00 400.00
Water Gals 10.00 1.00 10.00

Labour
mason Days 1.25 650.00 812.50
U/SK labourer Days 2.00 400.00 800.00
U/SK labourer (curing) Days 0.25 400.00 100.00
2,971.25
O/H & Proffits 0.00 0.00
Rate per square 2,971.25
319.71
108. 3/4" thick rendering in cement and
sand 1:2 in floors finished smooth.

Page 23
Plastering

Per square
Materials:
cement ( 50 kg bags) Cwt 2.25 485.00 1,091.25
sand Cubes 0.08 5,000.00 400.00
Water Gals 10.00 1.00 10.00

Labour
mason Days 1.25 650.00 812.50
U/SK labourer Days 2.00 400.00 800.00
U/SK labourer (curing) Days 0.25 400.00 100.00
3,213.75
O/H & Proffits 0.00 0.00
Rate per square 3,213.75
345.80
109. 3/4" thick rendering in cement and
sand 1:2 in coloured cement floors
Finished smooth

Per square
Materials:
2.25 cwt cement ( 50 kg bags) Cwt 2.25 485.00 1,091.25
0.08 cubes sand cubes 0.08 5,000.00 400.00
5 lbs powered pigment lbs 5.00 54.00 270.00
Water 10 gals Gals 10.00 1.00 10.00

Labour
mason Days 1.25 650.00 812.50
U/SK labourer Days 2.00 400.00 800.00
U/SK labourer (curing) Days 0.25 400.00 100.00
3,483.75
O/H & Proffits 0.00 0.00
Rate per square 3,483.75
374.85
110. 1/2"x 6" skirting in cement and sand
1:3 projected or flush to walls finished
with floating including forming grove.

Per 10. L.ft


Materials
cement (50 kg bags) Cwt 0.10 485.00 48.50
sand Cubes 0.003 5,000.00 15.00
powered pigment lbs 0.25 54.00 13.50

Labour
mason Days 0.38 650.00 243.75
U/SK labourer Days 0.31 400.00 125.00
Total per 10 L.ft 445.75
O/H & Proffits 0.00 0.00
Rate per L.ft 44.58
146.21
Note:
Where coloured skirting is not required,
delete provision for powered pigment

Page 24
Plastering

3/4" thick D.P.C in


98. cement sand 1:2
finished with 2
coats hot tar and

blinded with sand.

99. 5/8" thick plastering to wall in lime


and sand 2:5 includin
lime putty.

100. 5/8" thick plastering to wall in cement


sand 1:3 including

101. 3/8" thick plastering to soffit slab


in cement sand 1:3 i
with lime putty

102. 3/8" thick plastering to sides and


soffit of beams in c
including floating with lime putty.

103. 5/8" thick to wall in lime cement and


sand 1:1:5 finished
wooden float.

104. 5/8" thick plastering to wall in lime


cement and sand 1:1
with lime putty floating.

105. 1/2" thick rendering in cement and


sand 1:3 finished sm

106. 1/2" thick rendering in cement and


sand 1:2 in floors,

107. 3/4" thick rendering in cement and


sand 1:3 finished s

108. 3/4" thick rendering in cement and


sand 1:2 in floors fi

109. 3/4" thick rendering in cement and


sand 1:2 in coloured
Finished smooth

110. 1/2"x 6" skirting in cement and sand


1:3 projected or flus
with floating including forming grove.

Page 25
Plastering

98

1.75 257

99

100

1.4
15.875
1.25984

1 440
4734.4
473.44
16.909

15.625
9.375
101

102

Page 26
Plastering

103
15.625

15.875
19.05
1.2

104

30

47.36276
1420.883
71.04413

105

106

107 18.75

1631.9
489.57
2121.4
228.36

3107.3 334.478 278.73


334.48

108

Page 27
Plastering

109

110

0.01

0.05

Page 28
Plastering

SCAFFOLDING
U/SK LABOUR
SLAKED LIME

FIRE WOOD
BITUMEN

AMOUNT
CEMENT

MASON
WATER
SAND

O/H
### 550.00 114.41 17.86 10.00 750.00 ### 1,060.05 4,593.57

/8" thick plastering to wall in lime


630.50 350.00 10.00 600.00 700.00 687.15 2,977.65

/8" thick plastering to wall in cement


679.00 300.00 10.00 600.00 500.00 626.70 2,715.70

/8" thick plastering to soffit slab


38.80 250.00 5.00 ### ### 838.14 3,631.94

/8" thick plastering to sides and


38.80 250.00 5.00 ### 800.00 688.14 2,981.94
ncluding floating with lime putty.

/8" thick to wall in lime cement and


38.80 170.00 350.00 10.00 600.00 500.00 449.64 2,118.44

/8" thick plastering to wall in lime


38.80 255.00 350.00 10.00 900.00 600.00 569.64 2,723.44
with lime putty floating.

/2" thick rendering in cement and


518.95 250.00 10.00 600.00 600.00 593.69 2,572.64

/2" thick rendering in cement and


727.50 250.00 10.00 600.00 700.00 686.25 2,973.75

/4" thick rendering in cement and


848.75 400.00 10.00 750.00 900.00 872.63 3,781.38

/4" thick rendering in cement and


1091.3 400 10 750 900 945.38 4096.63

/4" thick rendering in cement and


1091.3 400 10 750 900 945.38 4096.63

/2"x 6" skirting in cement and sand


48.5 15 10 228 124 127.65 553.15
with floating including forming grove.

Page 29
Painter

BUILDING SCHEDULE OF RATES - PAINTER & DECORATOR

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


Rs. Cts. Rs. Cts.

111. Prepare and apply one coat of


preservative (oil type) to structural
timber including touching up cut ends
etc. after fixing

Per square
Materials
wood preservative (oil type) Ltr. 2.75 125.00 343.75
3" brush (1/10 use) No 0.10 335.00 33.50

Labour
painter Days 0.75 600.00 450.00
U/Sk labourer Days 0.50 400.00 200.00
1,027.25
O/H & Proffits 0.00 0.00
Rate per square 1,027.25
110.58
112. Prepare surface of steel truss and
apply two coats of anti-corrosive
primer.

Consider one square


Materials
anti-corrosive primer Ltrs 2.25 600.00 1,350.00
mineral turpentine or thinner Ltrs 0.15 155.00 23.25
wire brush Nos 1.00 60.00 60.00
2" brush (1/3 use) Nos 0.33 225.00 75.00

Labour
painter Days 1.50 600.00 900.00
U/Sk labourer Days 1.50 400.00 600.00
3,008.25
O/H & Proffits 0.00 0.00
Rate per square 3,008.25

113. Apply one coat of anti - corrosive


primer and two coats enamel paint on
already shop primed and erected
steel roof truss.

Consider one square


Materials
anti-corrosive primer Ltrs 0.20 600.00 120.00
enamal paint Ltrs 1.33 610.00 813.33

Page 30
Painter

mineral turpentine or thinner Ltrs 0.20 155.00 31.00


2" brush (1/5 use) No 0.20 225.00 45.00

Labour
Painter Days 2.50 600.00 1,500.00
U/Sk labourer Days 1.00 400.00 400.00
Scaffolding - Add 3% 57.00
2,966.33
O/H & Proffits 0.00 0.00
Rate per square 2,966.33

114. Prepare and apply two cats of primer


and finishing coat of enamal paint to
mild steel( angle/flat) gate.

Consider 50 sq.ft
Materials
anti-corrosive primer Ltrs 1.50 600.00 900.00
enamal paint Ltrs 0.67 610.00 406.67
mineral turpentine or thinner Ltrs 0.20 155.00 31.00
wire brush No 0.50 60.00 30.00
2" brush (1/5 use) No 0.20 165.00 33.00

Labour
Painter Days 0.50 600.00 300.00
U/Sk labourer Days 0.75 400.00 300.00
Total per 50 sq.ft 2,000.67
O/H & Proffits 0.00 0.00
Rate per squre 2,000.67

115. Painting steel on new work with 2


coats of anti-corrosive paint

Per square
Materials
anti-corrosive paint Ltrs 1.50 440.00 660.00
2" brush (1/5 use) No 0.20 165.00 33.00

Labour
Painter Days 1.50 600.00 900.00
1,593.00
O/H & proffits 0.00 0.00
Rate per square 1,593.00

116. Painting new timber work with two


coats wood preservative

Per square
Materials
wood preservative ltr 2.27 125.00 283.75

Page 31
Painter

2" brush (1/5 use) No 0.20 165.00 33.00

Labour
Painter Days 0.50 600.00 300.00
616.75
O/H & Proffits 0.00 0.00
Rate per square 616.75
66.39
117. Preparing and painting wood work
with primer and 2 coats of enamal

Per square
Materials
Primer Ltrs 0.75 455.00 341.25
Enamel paint (2 coats) Ltrs 1.50 630.00 945.00
Sand papers Nos 2.00 30.00 60.00
3" brush ( 1/8 use) No 0.13 335.00 41.88
Labour
Painter Days 1.50 600.00 900.00
U/Sk labourer Days 0.50 400.00 200.00
2,488.13
O/H & Proffits 0.00 0.00
Rate per square 2,488.13
267.83
118. White or colour washing two coats in
single storey

Per 10 square
Materials
boiled lime Cwt 0.50 350.00 175.00
salt Lbs 2.00 5.00 10.00
yellow ochre Lbs 0.50 60.00 30.00
blue ozs 2.00 2,000.00 4,000.00
8" brush (1/3 use) No 0.33 675.00 225.00
Water Gals 10.00 1.00 10.00

Labour
Painter Days 2.50 600.00 1,500.00
U/sk Labour Days 2.50 400.00 1,000.00
Scaffolding - Add 3% 75.00
7,025.00
O/H & Proffits 0.30 2,107.50
Rate per square 913.25

119. White or colour washing in two


storeyed building

Per 10 sqrs.
(as per above) 7,025.00
Add.

Page 32
Painter

Painter Days 0.50 600.00 300.00


U/Sk labourer Days 0.50 400.00 200.00
Scaffolding - Add 3% 15.00
Total per 10 sqrs 7,540.00
O/H & proffits 0.00 0.00
Rate per square 754.00

120 prepare and apply one coat of alkali


resistant primer and two coarts of
emulision paint to walls.

Per square
Materials
primer Ltrs 0.90 345.00 310.50
emulision paint Ltrs 1.40 485.00 679.00
Water Gals 0.10 1.00 0.10
6" brush (1/10 use) Nos 0.10 530.00 53.00
sand papers Nos 2.00 30.00 60.00

Labour
painter Days 1.25 600.00 750.00
Scaffolding - Add 3% 22.50
1,875.10
O/H & Proffits 0.00 0.00
Rate per square 1,875.10
201.76
prepare and apply one coat of alkali
resistant primer and two coarts of
W/shield emulision paint to walls.

Per square
Materials
primer Ltrs 0.90 345.00 310.50
W/shield emulision paint Ltrs 1.40 585.00 819.00
Water Gals 0.10 1.00 0.10
6" brush (1/10 use) Nos 0.10 530.00 53.00
sand papers Nos 2.00 30.00 60.00

Labour
painter Days 1.25 600.00 750.00
Scaffolding - Add 3% 22.50
2,015.10
O/H & Proffits 0.00 0.00
Rate per square 2,015.10
216.82
121. Cement washing to walls of single
storeyed building 2 coats

Per 10 square
Materials

Page 33
Painter

cement Cwt 0.625 485.00 303.13


6" coir brush Nos 1.00 250.00 250.00
Water Gals 5.00 1.00 5.00

Labour
painter Days 2.00 600.00 1,200.00
U/Sk labourer Days 2.00 400.00 800.00
Scaffolding - Add 3% 60.00
Total 2,618.13
O/H & Proffits 0.00 0.00
Rate per square 261.81

122. Painting walls with emulsion paint


(2 coats)

Per square
1st coat - emulsion paint ltr 0.76 410.00 310.23
2nd coat - emulsion paint ltr 0.65 410.00 265.91
6" brush - (1/10 use) No 0.10 530.00 53.00
0.10 gals water Gal 0.10 1.00 0.10

Labour
Painter Days 0.75 600.00 450.00
Scaffolding - Add 3% 13.50
1,092.75
O/H & Proffits 0.00 0.00
Rate per square 1,092.75
117.63
123. Prepare and apply one coat alkali
resistant primer and two coats of
emulsion paint to soffit of slabs.

Consider 1.00 sqrs


Materials
primer Ltrs 0.90 345.00 310.50
emulsion paint Ltrs 1.50 410.00 615.00
6" brush ( 1/10 use) No 0.10 530.00 53.00

Labour
painter Days 1.75 600.00 1,050.00
Scaffolding - Add 3% 31.50
2,060.00
O/H & Proffits 0.00 0.00
Rate per square 2,060.00
221.74
124. Varnishing two coats with copal
varnish after sand papering.

Per square
varnish ltr 1.82 540.00 980.64

Page 34
Painter

3" brush ( 1/8 use) No 0.13 335.00 41.88

Labour
painter Days 1.25 600.00 750.00
U/Sk labourer Days 0.75 400.00 300.00
2,072.52
O/H & Proffits 0.00 0.00
Rate per square 2,072.52
223.09
125. Wax polishing to timber in panels &
floors

Per square
Materials
wax polish Lb 0.75 370.00 277.50
sand papers No 6.00 30.00 180.00
1/10 floor brush No 0.10 225.00 22.50
flannel cloth Yards 0.50 55.00 27.50

Labour
U/Sk labourer Days 0.38 400.00 150.00
657.50
O/H & Proffits 0.00 0.00
Rate per square 657.50

Page 35
Painter

323.815931

Page 36
Painter

319.303911

215.357015

Page 37
Painter

216.677419

Page 38
Painter

893.14

311.89

Page 39
Painter

0.5
0.5

112.5

10
150.00
272.5
354.25

Page 40
Door Window

BUILDING SCHEDULE OF RATES - DOORS, WINDOWS & FITTINGS

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


Rs. Cts. Rs. Cts.
81. Door single hung 3' 3"x 7' 0" high
overall with frame having 1 1/4" thick
sash and 3-3/4"x 2-3/4" timber frame
(glazing, iron mongary & painting
measured seperatly)
Per 22.75 sq.ft ( 3' 3"x 7' 0")
Materials:
a) Frame :
4"x 3" timber Cu.ft 1.50 85.00 127.50
spur stones Nos 2.00 0.00 0.00
fibre/ plastic plugs with 4" brass screws Nos 6.00 0.00 0.00
5/8" mild steel dowels 4" long Nos 2.00 0.00 0.00
b) Sash -
1 1/2" planks Sq.ft 14.00 175.00 2,450.00
1" planks Sq.ft 5.00 97.14 485.71
Labour
carpenter Days 5.00 650.00 3,250.00
U/SK labourer Days 1.50 400.00 600.00
Total per 22.75 sq.ft 6,913.21
O/H & Proffits 0.00 0.00
6,913.21
Rate per sq.ft 303.88

82. Door glazed and panelled double hung


4' 0"x 7' 0" high overall with frame
including 1 1/4" thick sash and
3-3/4"x 2- 3/4" frame.(glazing, iron
mongary and painting measured
seperatly.)
Per 28.0 square feet( 4' 0"x 7' 0")
Materials:
a) Frame -
4"x 3" timber Cu.ft 1.67 85.00 141.67
spur stones Nos 2.00 0.00 0.00
fiber/plastic piug with 4" long screws Nos 6.00 0.00 0.00
5/8" dia mild steel dowel 4" long Nos 2.00 0.00 0.00
b) Sashes -
1 1/2" planks Sq.ft 16.00 175.00 2,800.00
1" planks Sq.ft 7.00 97.14 680.00
Labour
carpenter Days 6.00 650.00 3,900.00
U/SK labourer Days 2.00 400.00 800.00
Total per 28.00 sq.ft 8,321.67
O/H & Proffits 0.00 0.00
8,321.67
Rate per sq.ft 297.20

Page 41
Door Window

83. Plywood door single hung 3' 1- 1/2" x


6' 11- 1/2" overall with frame having
1-1/4" thk. sash and 3 1/4"x 2 1/4" frame
( Iron mongary and painting measured
seperatly)
Per 21.75 square feet (3' 1 1/2"x 6' 11 1/2")
Materials:
a) Frame -
4"x 3" timber Cu.ft 1.80 85.00 153.00
spur stones Nos 2.00 0.00 0.00
fiber/plastic plug with 4" long screws Nos 6.00 0.00 0.00
b) Sashes -
6' 9"x 2' 9" plywood sash Nos 1.00 0.00 0.00
Labour
carpenter Days 0.75 650.00 487.50
U/SK labourer Days 0.38 400.00 150.00
mason (fixing frame) Days 0.25 650.00 162.50
U/SK labourer (- do -) Days 0.25 400.00 100.00
1,053.00
O/H & Proffits 0.00 0.00
Total per 21.75 sq.ft 1,053.00
Rate per sq.ft 48.41

84. Door ledged, braced and battened


single hung 2' 6" x 6' 6" overall, with
frame having 7/8" thick tongued &
grooved planks and 3 3/4"x 2 1/4"
frame (Iron mongery and painting
measured seperatly.)
Per 16.25 sq.ft (2' 6"x 6' 6")
Materials:
a) Frame -
4"x 3" timber Cu.ft 1.70 85.00 144.50
spur stones Nos 2.00 0.00 0.00
fiber/plastic plug with 4" brass screws Nos 6.00 0.00 0.00
5/8 mild steel dowels 4" long Nos 2.00 0.00 0.00
b) Sash -
1" thick planks Sq.ft 21.00 97.14 2,040.00
1 1/4" long brass screws. Nos 36.00 3.25 117.00
Labour
carpenter Days 2.25 650.00 1,462.50
U/SK labourer Days 1.00 400.00 400.00
mason (fixing frame) Days 0.25 650.00 162.50
U/SK labourer (- do -) Days 0.25 400.00 100.00
4,426.50
O/H & Proffits 0.00 0.00
Total per 16.25 sq.ft 4,426.50
Rate per sq.ft 272.40

Page 42
Door Window

85. Window, glazed 7' 0"x 4' 0" high


overall with frame comprising 3 Nos
openable sashes and 3 3/4"x 2 3/4"
frame and mullions.
(Glazing, iron mongary and painting
measured seperatly)
Per Window 7' 0"x 4' 0" (sashes)
ie. per 28.00 sq.ft
Materials:
a) Frame -
4"x 3" timber Cu.ft 3.20 85.00 272.00
fiber/plastic piug with 4" brass screws Nos 4.00 15.00 60.00
b) Sashes -
3"x 1 1/2" timber Sq.ft 9.25 175.00 1,618.75
Labour
carpenter Days 6.00 650.00 3,900.00
U/SK labourer Days 2.50 400.00 1,000.00
mason (fixing frame) Days 0.50 650.00 325.00
U/SK labourer (- do -) Days 0.50 400.00 200.00
7,375.75
O/H & Proffits 0.00 0.00
Total per 28.00 sq.ft 7,375.75
Rate per sq.ft 263.42

86. 1/8" clear sheet glass panes


exceeding 1' 0" but not exceeding 4
square feet cut and fixed with timber
beading to doors and windows.
Consider sash 3' 0"x 4' 0" high with
3"x 1-1/4" style and 4 Nos glass panes
Per 9.00 sq.ft
Materials:
glass panes Sq.ft 9.00 37.77 339.93
1/2"x 1/2" beading L.ft 30.00 1.00 30.00
brass panel pins Doz 4.00 0.25 1.00
Labour
glazier Days 0.50 600.00 300.00
U/SK labourer Days 0.50 400.00 200.00
870.93
O/H & proffits 0.00 0.00
Total Per 9.00 sq.ft 870.93
Rate per sq.ft 9.68

IRON MONGARY

87. But hinges 4"x 3"


Materials:
butt hinges Pair 1.50 110.00 165.00
3/4" brass screws Nos 24.00 2.00 48.00
Labour

Page 43
Door Window

carpenter Days 0.25 650.00 162.50


U/SK labourer Days 0.25 400.00 100.00
475.50
O/H & proffits 0.00 0.00
Total per 1 1/2 pair 475.50
Rate per pair 317.00

88. Tee hinges 6"x 12"


Materials:
Tee hinges Pair 1.00 0.00 0.00
3/4" Brass screws Nos 18.00 2.00 36.00
Labour
carpenter Day 0.25 650.00 162.50
U/SK labourer Day 0.25 400.00 100.00
298.50
O/H & Proffits 0.00 0.00
Rate per pair 298.50

89. Rim Lock


Materials:
rim lock with screws Nos 1.00 575.00 575.00
Labour
carpenter Day 0.25 650.00 162.50
U/SK labourer Day 0.25 400.00 100.00
837.50
O/H & Proffits 0.30 251.25
Rate per No 1,088.75

90. Mortice lock


Materials:
1 mortice lock with screws No. 1.00 1,400.00 1,400.00
Labour
carpenter Days 0.50 650.00 325.00
U/SK labourer Days 0.50 400.00 200.00
1,925.00
O/H & proffits 0.00 0.00
Rate per No 1,925.00

91. Casement stays


Materials:
casement stays Nos 4.00 150.75 603.00
1/2" brass screws Nos 16.00 1.75 28.00
Labour
carpenter Day 0.25 650.00 162.50
U/SK labourer Day 0.25 400.00 100.00
893.50
O/H & Proffits 0.00 0.00
Total per 4 Nos 893.50
Rate per No 223.38

Page 44
Door Window

92 Door closer (Hydraulic)


Materials:
Door closer Nos 1.00 1,000.00 1,000.00
3/4" brass screws Nos 8.00 2.00 16.00
Labour
carpenter Days 0.25 650.00 162.50
U/SK labourer Days 0.25 400.00 100.00
1,278.50
O/H & Proffits 0.00 0.00
Rate per No 1,278.50

93. Tower/Skeleton brass bolts.


Materials:
Tower/Skeleton bolts. Nos 1.00 0.00 0.00
1/2" brass screws Nos 10.00 1.75 17.50
Labour
carpenter Day 0.06 650.00 40.63
U/SK labourer Day 0.06 400.00 25.00
83.13
O/H & Proffits 0.00 0.00
Rate per No 83.13

94. Barrel bolt 4"


Materials:
Barrel bolt Nos 1.00 60.00 60.00
1/2" brass screws Nos 8.00 1.75 14.00
Labour
carpenter Days 0.06 650.00 40.63
U/SK labourer Days 0.06 400.00 25.00
139.63
O/H & Proffits 0.00 0.00
Rate per No 139.63

95. Casement fasteners


Materials:
Casement fasteners Nos 6.00 184.50 1,107.00
1/2" brass screws Nos 24.00 1.75 42.00
Labour
carpenter Days 0.50 650.00 325.00
U/SK labourer Days 0.50 400.00 200.00
1,674.00
O/H & Proffits 0.00 0.00
Total per 6 Nos 1,674.00
Rate per No 279.00

96. Spring loaded fanlight catches.


Materials:
brass fanlight catches. Nos 6.00 0.00 0.00
1/2" brass screws Nos 24.00 1.75 42.00
Labour

Page 45
Door Window

carpenter Days 0.50 650.00 325.00


U/SK labourer Days 0.50 400.00 200.00
Total per 6 Nos 567.00
1,134.00
O/H & Proffits 0.00 0.00
Tatal per 6 Nos 1,134.00
Rate per No 189.00

97. Draw rings


Materials:
draw rings Nos 6.00 15.00 90.00
1/2" brass screws Nos 12.00 1.75 21.00
Labour
carpenter Day 0.13 650.00 81.25
U/SK labourer Day 0.13 400.00 50.00
242.25
O/H & proffits 0.00 0.00
Total per 6 Nos 242.25
Rate per No 40.38

Page 46
Door Window

WOOD HOUSE DOORS- 240.09 PER 1 SQ.FT


WOOD HOUSE DOORS- 260.10 PER 1 SQ.FT

Page 47
Door Window

Page 48
Door Window

90,000.00
22,200.00
67,800.00

1422.4 1.22
0 1.815848 2

Page 49
Roof Plumb

BUILDING SCHEDULE OF RATES - ROOF PLUMBER

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


Rs. Cts. Rs. Cts.

163. 6" dia half round PVC eaves gutter


fixed to timber valance board
including gutter joiner and brackets
fixed at 18" centres.( Other specials
paid seperatly)

Consider 24.00 L.ft


Materials
6" dia eaves gutter lengths lft 24.00 - 0.00
joiner Nos 1.00 0.00 0.00
gutter brackets Nos 17.00 0.00 0.00
3/4" brass screws Nos 34.00 2.00 68.00
solvent cement Grms 20.00 0.86 17.12

Labour
plumber Days 0.50 650.00 325.00
U/Sk labourer Days 0.50 400.00 200.00
Scaffolding - Add 5% 26.25
Total 636.37
O/H & Proffits 0.00 0.00
Rate per L.ft 26.52

164. 6" dia PVC gutter head


Consider 1 No Gutter head

Materials
PVC gutter head Nos 1.00 0.00 0.00
gutter joiners Nos 2.00 0.00 0.00
gutter brackets Nos 2.00 0.00 0.00
solvent cement Grms 12.00 0.86 10.27
3/4" brass screws Nos 4.00 2.00 8.00

Labour
plumber Days 0.13 650.00 81.25
U/Sk labourer Days 0.13 400.00 50.00
Scaffolding - Add 5% 6.56
156.09
O/H & Proffits 0.00 0.00
Rate per No 156.09

165. 6" dia PVC mitres


Consider 1 No mitre

Materials

Page 50
Roof Plumb

mitre bend Nos 1.00 0.00 0.00


gutter joiners Nos 2.00 0.00 0.00
brackes Nos 2.00 0.00 0.00
solvent cement Grms 12.00 0.86 10.27
3/4" brass screws Nos 4.00 2.00 8.00

Labour
plumber Days 0.13 650.00 81.25
U/Sk labourer Days 0.13 400.00 50.00
Scaffolding - Add 5% 6.56
156.09
O/H & Proffits 0.00 0.00
Rate per No 156.09

166. 6" dia PVC end caps


Consider 1 No end cap

Materials
1 No end cap No 1.00 0.00 0.00
solvent cement Grms 12.00 0.86 10.27

Labour
plumber Days 0.06 650.00 40.63
U/Sk labourer Days 0.06 400.00 25.00
Scaffolding - Add 5% 3.28
79.18
O/H & Proffits 0.00 0.00
Rate per No 79.18

167. 3 1/2" dia PVC rain water down pipes


fixed to brick wall with wooden plugs
buried in wall. (Specials measured
seperatly)

Consider 24.0 L.ft pipe length

Materials
3 1/2" dia pipe length lft 24.00 0.00 0.00
3 1/2 joiner Nos 1.00 0.00 0.00
PVC straps Nos 4.00 0.00 0.00
brass screws 1" long Nos 1.00 2.50 2.50
solvent cement Grms 30.00 0.86 25.69

Labour
plumber Days 0.33 650.00 216.67
U/Sk labourer Days 0.33 400.00 133.33
Scaffolding - Add 5% 17.50
Total per 24.0 L.ft 395.69
O/H & Proffits 0.00 0.00
Rate per L.ft 16.49

Page 51
Roof Plumb

Page 52
Roof Plumb

86.9711133 /m

Page 53
Roof Plumb

54.0770867 /m

Page 54
Tiler

BUILDING SCHEDULE OF RATES - TILER

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


Rs. Cts. Rs. Cts.

63. Pressed floor tiles bedded in 1/2"


cement mortar 1:2 and pointing in
neat cement in ground floor

Per square
Materials
Pressed tiles 8" x 8" Nos 225.00 40.00 9,000.00
Add 5% for wastage 450.00
Cement (50 kg bags) Cwt 1.25 485.00 606.25
Sand Cubes 0.07 5,000.00 350.00
Wax polish Lb 0.25 140.00 35.00
Coloured pigment Lb 0.25 270.00 67.50
Cotton waste Lb 2.00 8.00 16.00

Labour
Mason Days 4.00 650.00 2,600.00
U/SK labourer Days 4.00 400.00 1,600.00
U/SK labourer for polishing Days 0.50 400.00 200.00
14,924.75
O/H & Proffits 0.00 0.00
Rate per square 14,924.75
1605.90
64. Glazed tiles fixed to walls including
bedding in cement mortar 1:2 and
raking in ground floor.
(Specials measured seperatly)

Per square
Materials
glazed tiles 4"x 4" Nos 900.00 35.00 31,500.00
Add 10% for wastage on cutting 3,150.00
cement sand (50 Kg bags) Cwt 2.50 485.00 1,212.50
sand Cubes 0.11 5,000.00 550.00
white cement Lb 1.00 9.92 9.92

Labour
mason Days 4.00 650.00 2,600.00
U/SK labourer Days 4.00 400.00 1,600.00
U/SK labourer for cleaning Days 0.25 400.00 100.00
40,722.42
O/H & Proffits 0.00 0.00
Rate per square 40722.42
4381.73

Page 55
Tiler

GRANITE-5900 PER M2
64. Glazed tiles fixed to walls including
bedding in cement mortar 1:2 and
raking in ground floor.
(Specials measured seperatly)

Per square
Materials
glazed tiles 6"x 6" ft 100.00 2,016.00 201,600.00
Add 10% for wastage on cutting 20,160.00
cement sand (50 Kg bags) Cwt 2.50 750.00 1,875.00
sand Cubes 0.11 8,000.00 880.00
white cement Lb 1.00 9.92 9.92

Labour
mason Days 4.00 1,100.00 4,400.00
U/SK labourer Days 4.00 850.00 3,400.00
U/SK labourer for cleaning Days 0.25 850.00 212.50
232,537.42
O/H & Proffits 16% 37205.99
Rate per square 269743.41
29024.39
65. Terrazzo floor tiles on 1/2" thick
cement and sand 1:2 in ground floor

Per square
Materials
12"x 12" terrazzo tiles Nos 100.00 0.00 0.00
Add 5% for wastage 0.00
cement (50 kg bags) Cwt 1.25 485.00 606.25
sand Cubes 0.07 5,000.00 350.00
Coloured pigment Lb 2.00 270.00 540.00
wax polish Lb 0.50 140.00 70.00
cotton waste Lb 2.00 8.00 16.00

Labour
mason Days 3.00 650.00 1,950.00
U/SK labourer Days 3.00 400.00 1,200.00
U/SK labourer for polishing Days 0.50 400.00 200.00
4,932.25
O/H & Proffits 0.00 0.00
Rate per square 4,932.25
530.71
65a. Ceramic floor tiles on 1/2" thick
cement and sand 1:2 in ground floor

Per square
Materials
12"x 12" Ceramic tiles Nos 100.00 95.00 9,500.00
Add 5% for wastage 0.00

Page 56
Tiler

cement (50 kg bags) Cwt 1.25 485.00 606.25


sand Cubes 0.07 5,000.00 350.00
Coloured pigment Lb 2.00 270.00 540.00
wax polish Lb 0.50 140.00 70.00
cotton waste Lb 2.00 8.00 16.00

Labour
mason Days 3.00 650.00 1,950.00
U/SK labourer Days 3.00 400.00 1,200.00
U/SK labourer for Cleaning Days 0.50 400.00 200.00
14,432.25
O/H & Proffits 0.00 0.00
Rate per square 14,432.25
1552.91
65b. Ceramic floor tiles bedded in 1/2"
cement mortar 1:2 and pointing in
neat cement in ground floor

Per square
Materials
Ceramic tiles 8" x 8" Nos 225.00 30.00 6,750.00
Add 10% for wastage 675.00
Cement (50 kg bags) Cwt 1.25 485.00 606.25
Sand Cubes 0.07 5,000.00 350.00
Wax polish Lb 0.25 140.00 35.00
Coloured pigment Lb 0.25 270.00 67.50
Cotton waste Lb 2.00 8.00 16.00

Labour
Mason Days 4.00 650.00 2,600.00
U/SK labourer Days 4.00 400.00 1,600.00
U/SK labourer for cleaning Days 0.50 400.00 200.00
12,899.75
O/H & Proffits 0.00 0.00
Rate per square 12,899.75
1388.01
INSITU TERRAZO WORK
Note:-
Our sub contractors current labour rate
per sq.ft is Rs.14/=

65c. Laying in situ Terrazo Grey colour.


(Levelling floor with concrete measured
seperately)

Per square
Materials
Cement Cwt 2.00 485.00 970.00
Dolomite Cwt 2.00 0.00 0.00
Milk White chips kg 25.00 0.00 0.00

Page 57
Tiler

Black chips kg 25.00 0.00 0.00


3/4"x 4' 0" long aluminium strips No 20.00 0.00 0.00
Add 5% wastage 48.50
Wax lbs 0.88 140.00 123.48
Thinner ltr 1.82 73.58 133.62
Cutting stone (medium) No 1.00 0.00 0.00
Cutting stone (rough) No 1.00 0.00 0.00
Cutting stone (fine) No 1.00 0.00 0.00
Hire of terrazo cutting machine Day 1.00 0.00 0.00

Labour
Sk/Labour Day 4.00 600.00 2,400.00
U/sk Labour Day 3.20 400.00 1,280.00
4,955.60
O/H & Proffits 0.00 0.00
Rate per square 4,955.60
533.43
65d. Laying in situ Terrazo White colour.
(Levelling floor with concrete measured
seperately)

Per square
Materials
White Cement Cwt 2.00 0.00 0.00
Dolomite Cwt 2.00 0.00 0.00
Milk White chips kg 25.00 0.00 0.00
Black chips kg 25.00 0.00 0.00
3/4"x 4' 0" long aluminium strips No 20.00 0.00 0.00
Add 5% wastage 0.00
Wax lbs 0.88 140.00 123.48
Thinner ltr 1.82 73.58 133.62
Cutting stone (medium) No 1.00 0.00 0.00
Cutting stone (rough) No 1.00 0.00 0.00
Cutting stone (fine) No 1.00 0.00 0.00
Hire of terrazo cutting machine Day 1.00 0.00 0.00

Labour
Sk/Labour Day 4.00 600.00 2,400.00
U/sk Labour Day 3.20 400.00 1,280.00
3,937.10
O/H & Proffits 0.00 0.00
Rate per square 3,937.10
423.80
65e. Laying in situ Terrazo Red colour.
(Levelling floor with concrete measured
seperately)

Per square
Materials
Cement Cwt 2.00 485.00 970.00

Page 58
Tiler

Red Cement kg 4.00 0.00 0.00


Dolomite Cwt 2.00 0.00 0.00
Milk White chips kg 25.00 0.00 0.00
Black chips kg 25.00 0.00 0.00
3/4"x 4' 0" long aluminium strips No 20.00 0.00 0.00
Add 5% wastage 48.50
Wax lbs 0.88 140.00 123.48
Thinner ltr 1.82 73.58 133.62
Cutting stone (medium) No 1.00 0.00 0.00
Cutting stone (rough) No 1.00 0.00 0.00
Cutting stone (fine) No 1.00 0.00 0.00
Hire of terrazo cutting machine Day 1.00 0.00 0.00

Labour
Sk/Labour Day 4.00 600.00 2,400.00
U/sk Labour Day 3.20 400.00 1,280.00
4,955.60
O/H & Proffits 0.00 0.00
Rate per square 4,955.60
533.43

Page 59
Tiler

2697.43408

Page 60
Plumbing

BUILDING SCHEDULE OF RATES - PLUMBING & SANITORY INSTALLATION

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


Rs. Cts. Rs. Cts.

PLUMBING - PVC PIPES

126. 1/2" DIA pvc pipes fixed to walls


(special paid seperately)

Per 10 L.ft
Materials
1/2" dia. pipes L.ft 13.00 4.96 64.45
Clips & nails Nos 3.00 4.40 13.21
Solvent cement Grams 2.00 0.86 1.71

Labour
Plumber Day 0.13 650.00 81.25
U/Sk labourer Day 0.13 400.00 50.00
Total per 10 L.ft 210.62
O/H & Proffits 0.00 0.00
Rate per L.ft 21.06

127. 3/4" dia PVC pipes fixed to walls ( special paid seperatly)

per 10 l.ft
3/4" dia. pipes L.ft 13.00 9.48 123.27
Clips & nails Nos 3.00 4.40 13.21
Solvant cement Grams 3.00 0.86 2.57

Labour
Plumber Day 0.13 650.00 81.25
U/Sk labourer Day 0.13 400.00 50.00
Total per 10 L.ft 270.30
O/H & Proffits 0.00 0.00
Rate per L.ft 27.03
88.66
128. 1" dia PVC pipes fixed to walls.
(specials paid seperatly)

Per 100 L.ft


1" dia. pipes L.ft 100.00 14.23 1,422.71
Add 5% for wastage 71.14
1" dia sockets Nos 8.00 10.43 83.46
Solvant cement Grams 32.00 0.86 27.40
Clips and nails Nos 35.00 4.40 154.09

Labour

Page 61
Plumbing

1/2 day plumber Days 0.50 650.00 325.00


1/2 day U/Sk labourer Days 0.50 400.00 200.00
Total per 100 l.ft 2,283.79
O/H & Proffits 0.00 0.00
Rate per L.ft 22.84
74.91
129. 1 1/4" dia PVC fixed to walls
(specials paid seperatly)

Per 100 L.ft


1-1/4" dia. pipes L.ft 100.00 21.93 2,193.29
Add 5% for wastage 109.66
1-1/4" dia sockets Nos 8.00 16.13 129.06
Solvant cement Grams 48.00 0.86 41.10
Clips and nails Nos 35.00 5.29 185.06

Labour
3/4 day plumber Days 0.75 650.00 487.50
3/4 day U/Sk labourer Days 0.75 400.00 300.00
Total per 100 l.ft 3,445.68
O/H & Proffits 0.00 0.00
Rate per L.ft 34.46

130. 1 1/2" dia PVC pipes fixed to walls


(specials paid seperatly)

Per 100 L.ft


1-1/2" dia. pipes L.ft 100.00 32.49 3,248.55
Add 5% for wastage 162.43
1-1/2" dia sockets Nos 8.00 30.80 246.36
Solvant cement Grams 64.00 0.86 54.80
Clips and nails Nos 35.00 6.17 215.78

Labour
3/4 day plumber Days 0.75 650.00 487.50
3/4 day U/Sk labourer Days 0.75 400.00 300.00
Total per 100 l.ft 4,715.41
O/H & Proffits 0.00 0.00
Rate per L.ft 47.15

131. 2" dia meter PVC pipes fixed to walls


(specials paid seperatly)

Per 100 L.ft


2" dia. pipes L.ft 100.00 54.42 5,441.84
Add 5% for wastage 272.09
2" dia sockets Nos 8.00 52.54 420.30
Clips and nails Nos 35.00 6.46 226.01
Solvant cement grms 112.00 0.86 95.89

Page 62
Plumbing

Labour
3/4 day plumber Days 0.75 650.00 487.50
3/4 day U/Sk labourer Days 0.75 400.00 300.00
Total per 100 l.ft 7,243.64
O/H & Proffits 0.00 0.00
Rate per L.ft 72.44

132. 3" dia PVC pipes fixed to walls


(specials paid seperatly)

Per 100 L.ft


3" dia. pipes L.ft 100.00 107.19 10,718.60
Add 5% for wastage 535.93
3" dia sockets Nos 8.00 141.08 1,128.66
Solvant cement Grams 200.00 0.86 171.24
Clips and nails Nos 35.00 31.95 1,118.25

Labour
1 day plumber Days 1.00 650.00 650.00
1 day U/Sk labourer Days 1.00 400.00 400.00
Total per 100 l.ft 14,722.68
O/H & Proffits 0.00 0.00
Rate per L.ft 147.23

133. Excavation for laying 1/2" to 3" dia


PVC pipes in ground not less than
1' 6" deep, back filling & compacting

Per 100 L.ft


Labour
2 1/2 days U/Sk labourer Days 2.50 400.00 1,000.00
Total per 100 l.ft 1,000.00
O/H & Proffits 0.00 0.00
Rate per L.ft 10.00

134. Chasing brickwork for laying 1/2" to


1 1/2" dia PVC pipes and making good
average depth 2" (pipes and specials
paid seperatly)

Per 100 L.ft


Materials
Cement Cwt 0.10 485.00 48.50
Sand Cubes 0.01 5,000.00 50.00

Labour
Mason Days 3.00 650.00 1,950.00
U/Sk labour Days 3.00 400.00 1,200.00
Total per 100 l.ft 3,248.50
O/H & Proffits 0.00 0.00

Page 63
Plumbing

Rate per L.ft 32.49

135. Chasing brick work for laying 1 1/2"


to 3" dia PVC pipes in ground or
floor and making good. Average depth
3" (pipes & specials measured
seperatly)

Per 100 L.f


Materials
Cement Cwt 0.20 485.00 97.00
Sand Cubes 0.03 5,000.00 150.00

Labour
Mason Days 3.50 650.00 2,275.00
U/Sk labourer Days 3.50 400.00 1,400.00
Total per 100 l.ft 3,922.00
O/H & Proffits 0.00 0.00
Rate per L.ft 39.22

136. 1/2" dia PVC specials viz -


elbows/bends sockets.

Per 10. specials


Materials
1/2" elbows/bends/sockets Nos 10.00 8.69 86.92
Solvent cement Grms 20.00 0.86 17.12

Labour
Plumber Day 0.25 650.00 162.50
Total per 10 nos 266.55
O/H & Proffits 0.00 0.00
Rate per No 26.65

137. 3/4" dia PVC specials viz -


elbows/bends sockets.

Per 10. specials


Materials
3/4" elbows/bends/sockets Nos 10.00 14.79 147.90
Solvent cement Grms 30.00 0.86 25.69

Labour
Plumber Day 0.25 650.00 162.50
Total per 10 Nos 336.09
O/H & Proffits 0.00 0.00
Rate per No 33.61

138. 1" dia PVC specials viz -


elbows/bends sockets.

Page 64
Plumbing

Per 10. specials


Materials
1" elbows/bends/sockets Nos 10.00 23.30 233.03
Solvent cement Grms 40.00 0.86 34.25

Labour
Plumber Day 0.25 650.00 162.50
Total per 10 Nos 429.77
O/H & Proffits 0.00 0.00
Rate per No 42.98

139. 1 1/4" dia PVC specials viz -


elbows/bends sockets.

Per 10. specials


Materials
1-1/4" dia elbows/bends/sockets Nos 10.00 0.00 0.00
Solvent cement Grms 60.00 0.86 51.37

Labour
Plumber Day 0.25 650.00 162.50
Total per 10 Nos 213.87
O/H & Proffits 0.00 0.00
Rate per No 21.39

140. 1 1/2" dia PVC specials viz -


elbows/bends sockets.

Per 10. specials


Materials
1-1/2" dia elbows/bends/sockets Nos 10.00 0.00 0.00
Solvent cement Grms 60.00 0.86 51.37

Labour
Plumber Day 0.50 650.00 325.00
Total per 10 Nos specials 376.37
O/H & Proffits 0.00 0.00
Rate per No 37.64

141. 2" dia PVC specials viz -


elbows/bends sockets.

Per 10. specials


Materials
2" dia elbows/bends/sockets Nos 10.00 0.00 0.00
Solvent cement Grms 140.00 0.86 119.87

Labour
Plumber Day 0.50 650.00 325.00

Page 65
Plumbing

Total per 10 Nos specials 444.87


O/H & Proffits 0.00 0.00
Rate per No 44.49

142. 2 1/2" dia PVC specials viz -


elbows/bends sockets.

Per 10. specials


Materials
2-1/2" dia elbows/bends/sockets Nos 10.00 0.00 0.00
Solvent cement Grms 200.00 0.86 171.24

Labour
Plumber Day 0.50 650.00 325.00
Total per 10 Nos specials 496.24
O/H & Proffits 0.00 0.00
Rate per No 49.62

143. 3" dia PVC specials viz -


elbows/bends sockets.

Per 10. specials


Materials
3" dia elbows/bends/sockets Nos 10.00 0.00 0.00
Solvent cement Grms 240.00 0.86 205.49

Labour
Plumber Day 0.50 650.00 325.00
Total per 10 Nos specials 530.49
O/H & Proffits 0.00 0.00
Rate per No 53.05

144. 1/2" dia PVC specials viz. tees.

Per 10. Tees


Materials
1/2" dia. tees Nos 10.00 0.00 0.00
Solvent cement Grms 30.00 0.86 25.69

Labour
Plumber Day 0.50 650.00 325.00
Total per 10 Nos Tees 350.69
0.00 0.00
Rate per No 35.07

145. 3/4" dia PVC specials viz. Tees

Per 10. Tees


Materials
3/4" Dia tees Nos 10.00 0.00 0.00

Page 66
Plumbing

Solvent cement Grms 45.00 0.86 38.53

Labour
Plumber Day 0.50 650.00 325.00
Total per 10 Nos Tees 363.53
O/H & Proffits 0.00 0.00
Rate per No 36.35

146. 1" dia PVC specials viz. Tees

Per 10. Tees


Materials
1" Dia tees Nos 10.00 0.00 0.00
Solvent cement Grms 60.00 0.86 51.37

Labour
1/2 day Plumber Day 0.50 650.00 325.00
Total per 10 Nos Tees 376.37
O/H & Proffits 0.00 0.00
Rate per No 37.64

147. 1 1/4" dia PVC specials viz Tees

Per 10 Tees
Materials
1-1/4" Dia tees Nos 10.00 0.00 0.00
Solvent cement Grms 90.00 0.86 77.06

Labour
Plumber Day 0.50 650.00 325.00
Total per 10 Nos Tees 402.06
O/H & Proffits 0.00 0.00
Rate per No 40.21

148. 1 1/2" dia PVC specials viz Tees

Per 10 Tees
Materials
1-1/2" Dia tees Nos 10.00 0.00 0.00
Solvent cement Grms 120.00 0.86 102.74

Labour
Plumber Days 1.00 650.00 650.00
Total per 10 Nos Tees 752.74
O/H & Proffits 0.00 0.00
Rate per No 75.27

149 2" dia PVC specials viz Tees

Per 10 Tees

Page 67
Plumbing

Materials
2" Dia tees Nos 10.00 0.00 0.00
Solvent cement Grms 210.00 0.86 179.80

Labour
Plumber Days 1.00 650.00 650.00
Total per 10 Nos Tees 829.80
O/H & Proffits 0.00 0.00
Rate per No 82.98

150. 2 1/2" dia PVC specials viz Tees

Per 10 Tees
Materials
2-1/2" Dia tees Nos 10.00 0.00 0.00
Solvent cement Grms 300.00 0.86 256.86

Labour
Plumber Days 1.50 650.00 975.00
Total per 10 Nos Tees 1,231.86
O/H & Proffits 0.00 0.00
Rate per No 123.19

151. 3" dia PVC specials viz Tees

Per 10 Tees
Materials
3" Dia tees Nos 10.00 0.00 0.00
Solvent cement Grms 360.00 0.86 308.23

Labour
Plumber Days 1.50 650.00 975.00
Total per 10 Nos Tees 1,283.23
O/H & Proffits 0.00 0.00
Rate per No 128.32

157 22" x 16" glazed fireclay wash basin


with 1/2" dia chromium plated piller
tap, waste plug, chromium plated
waste chain and stay, including
fixing wash basin on brackets.( Water
supply and waste water connection
measured seperatly.)

Per No.
Materials
wash basin complete with brackets Nos 1.00 0.00 0.00
1/2" tap Nos 1.00 0.00 0.00
Waste plug and chain Nos 1.00 0.00 0.00
wooden plugs Nos 4.00 0.00 0.00

Page 68
Plumbing

1-1/2" brass screws Nos 6.00 3.50 21.00


Cement cwt 0.02 485.00 8.80

Labour
mason Days 0.50 650.00 325.00
U/Sk labour Days 1.00 400.00 400.00
754.80
O/H & Proffits 0.00 0.00
Rate per No 754.80

157a 22" x 16" Ceramic wash basin Pedestal


with 1/2" dia chromium plated piller
tap, waste plug, chromium plated
waste chain and stay (Water supply &
waste water connection measured
seperatly.)

Per No.
Materials
wash basin pedestal, tap & waste Nos 1.00 0.00 0.00
wooden plugs Nos 4.00 0.00 0.00
1-1/2" brass screws Nos 6.00 3.50 21.00
Cement cwt 0.02 485.00 8.80

Labour
mason Days 0.50 650.00 325.00
U/Sk labour Days 1.00 400.00 400.00
754.80
O/H & Proffits 0.00 0.00
Rate per No 754.80

158. Sink 24"x15"x 7" overall vitreous China


with rubber plug and chromium plated
chain waste carried on iron brackets
painted and fixed to walls( water
supply and waste water connection
measured seperatly)

Per No.
Materials
sink 24"x 15"x 7" Nos 1.00 0.00 0.00
L iron brackets Nos 2.00 0.00 0.00
cement cwt 0.02 485.00 8.80
tapered wooden block 2" thick Nos 2.00 0.00 0.00
1-1/2" dia brass screws Nos 8.00 3.50 28.00

Labour
mason Days 0.50 650.00 325.00

Page 69
Plumbing

U/Sk labour Days 0.50 400.00 200.00


561.80
O/H & Proffits 0.00 0.00
Rate per No 561.80

159. Closet padestal type with L/L


flushing cistern, flush pipe double
plastic seat cover, 1/2" dia stop
cock, trap supplied & fixed complete
to working order.

Per No:
Materials
Low level suite complete Nos 1.00 0.00 0.00
1/2" dia stop cock Nos 1.00 0.00 0.00
Cement cwt 0.02 485.00 8.80
Sand Cu.ft 0.25 5,000.00 1,250.00
1-1/2" brass screws Nos 2.00 3.50 7.00

Labour
Mason Days 0.25 650.00 162.50
Plumber Days 1.00 650.00 650.00
U/Sk labourer Days 1.00 400.00 400.00
2,478.30
O/H & Proffits 0.00 0.00
Rate per No 2,478.30

160. Closet squatting type with trap including


high level cistern fixed complete
with flush pipe and 1/2" dia stop
cock, all complete to working order.

Per No:
Materials
Squatting pan with trap Nos 1.00 0.00 0.00
C.I cistern with 1 1/4" flush pipe, chain and
overflow pipe Nos 1.00 0.00 0.00
Clip Nos 2.00 5.29 10.58
Wooden plugs Nos 5.00 0.00 0.00
1-1/2" brass screws Nos 12.00 3.50 42.00
1/2" stop cock Nos 1.00 0.00 0.00
Cement Cwt 0.25 485.00 121.25
3/4" Metal Cube 0.01 3,600.00 18.00
Sand Cu.ft 0.25 5,000.00 1,250.00

Labour
Mason Days 0.50 650.00 325.00
Plumber Days 1.00 650.00 650.00
U/Sk labourer Days 1.00 400.00 400.00
2,816.83

Page 70
Plumbing

O/H & Proffits 0.00 0.00


Rate per No 2,816.83

161. Vitreous China bidet suite fixed


complete to working order

Per No:
Materials
Bidet Nos 1.00 0.00 0.00

Labour
Plumber Days 1.00 650.00 650.00
U/Sk labourer Days 1.00 400.00 400.00
1,050.00
O/H & Proffits 0.00 0.00
Rate per No 1,050.00

162. 4 No. Bowl type urinal with trap and


2 gals capacity automatic flushing
cistern and spreaders complete to
working orders.

Materials
Urinal Bowls Nos 4.00 0.00 0.00
2 gal. cistern Nos 1.00 0.00 0.00
Rawl plug Nos 8.00 0.00 0.00
Spreador Nos 1.00 0.00 0.00
Wooden plugs (for cistern) Nos 4.00 0.00 0.00
1-1/2" brass screws Nos 4.00 3.50 14.00
Cement cwt 0.04 485.00 17.60
Sand Cu.ft 0.13 5,000.00 625.00

Labour
Mason Days 0.25 650.00 162.50
Plumber Days 1.00 650.00 650.00
U/Sk labourer Days 1.00 400.00 400.00
Total per 4 Nos 1,869.10
O/H & Proffits 0.00 0.00
Rate per No 467.27

Page 71
Roof & Ceiling

BUILDING SCHEDULE OF RATES - ROOF & CEILING WORK

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

66. Timber frame work for calicut pattern


tile hip roof in single storey building
consisting of wall plate, beam, ridge
plate, rafters etc. ( preservative
treatment to be measured seperately)

Per 6.00 squares


Materials
Timber Cu.ft 34.00 1030.30 35,030.30
Add 10% for wastage 3,503.03
2"x 1" reepers L.ft 660.00 11.00 7,260.00
Add 05% for wastage 363.00
wire nails 6" long Lbs 8.00 43.13 345.04
wire nails 2" long Lbs 2.00 43.13 86.26

Labour
Carpentor Days 7.00 600.00 4,200.00
U/SK labourer Days 8.00 400.00 3,200.00
53,987.63
O/H & Proffits 0.00 -
Total per 6.00 squares. 53,987.63

Rate per square 8,997.94

67. Roof covering with calicut pattern


clay tiles in single storeyed building.
(Timber frame work & ridge covering
measured seperatly)

Per 6.00 squares


Materials
tiles Nos 750.00 25.00 18,750.00

Labour
carpenter Days 3.00 600.00 1,800.00
U/SK labourer Days 3.00 400.00 1,200.00
21,750.00
O/H & Proffits 0.00 -
Total per 6.00 squares. 21,750.00

Rate per square 3,625.00

68. Timber frame work for corrugated


asbestos sheet roof in single storeyed

Page 72
Roof & Ceiling

building

Per 3.60 sqrs.


Materials
timber purlins Cu.ft 13.25 1030.30 13,651.52
Add 10% for wastage 1,365.15

Labour
carpenter Days 2.50 600.00 1,500.00
U/SK labourer Days 3.00 400.00 1,200.00
17,716.67
O/H & Proffits 0.00 -
Total per 3.60 squares. 17,716.67

Rate per square 4,921.30


529.53
69. Roof covering with corrugated asbestos
sheets (Timber frame work and ridge
covering measured seperatly)

Per 3.60 sqrs.


Materials
Asbestos corrugated sheets. Sq.ft 420.00 260.00 109,200.00
Roofing screws and washers. Nos 72.00 101.00 7,272.00

Labour
carpenter Days 1.00 650.00 650.00
U/SK labourer Days 2.00 400.00 800.00
117,922.00
Mark Up 30% 0.00 -
Total per 3.60 squares. 117,922.00

Rate per square 32,756.11


3,524.56
70. One layer half round clay tiles over
corrugated asbestos roof covering.

Per square
Materials
half round clay tiles Nos 650.00 14.00 9,100.00

Labour
U/SK labourer Days 2.00 400.00 800.00
9,900.00
O/H & Proffits 0.00 -
Rate per square 9,900.00
1,065.24
71. Asbestos close fittings ridging fixed

Page 73
Roof & Ceiling

complete with roofing screws of bolts


(Hook)

Per 13' 1" Length


Materials
ridges 3' 8" long Pairs 4.00 217.71 870.84
roofing screws or bolts. Nos 16.00 43.13 690.08

Labour
carpenter Days 0.25 650.00 162.50
U/SK labourer Days 0.25 400.00 100.00
1,823.42
O/H & Proffits 0.00 -
Per 13' 1" ridging 1,823.42

Rate per L.ft 139.41


457.25
72 Ridging covering with calicut pattern
ridge tiles bedded in cement lime
mortar 1:1:4

Per 12 L.ft ridging


Materials
ridge tiles Nos 9.00 16.50 148.50
cement (50 kg bags) Cwt 1.30 485.00 630.50
sand Cubes 0.02 5000.00 100.00
slaked lime Lb 15.00 4.25 63.75
colouring powder Lb 0.50 270.00 135.00

Labour
carpenter Days 0.25 650.00 162.50
U/SK labourer Days 0.25 400.00 100.00
1,340.25
O/H & Proffits 0.00 -
Per 12 L.ft ridging 1,340.25

Rate per L.ft 111.69


366.34
73. 3/4"x 9" high valance board fixed
with brass screws to ends of rafters
( for tile roofing)

Per 100 L.ft


Materials
1" planks Sq.ft 75.00 97.14 7,285.71
Add 05% for wastage 3,642.86
1 1/2" brass screws Nos 70.00 3.50 245.00

Labour
Carpenter Days 3.00 650.00 1,950.00

Page 74
Roof & Ceiling

Un Skilled Labour Days 3.00 400.00 1,200.00


Scaffolding - Add 5% 157.50
14,481.07
O/H & Proffits 0.00 -
Total per 100 L.ft 14,481.07

Rate Per L.ft 144.81


474.98
74. 3/4"x 9" high barge board fixed with
brass screws at 2' 0" centres to sided
of rafters.

Per 100 L.ft


Materials
1" thick planks Sq.ft 75.00 97.14 7,285.71
Add 05% for wastage 3,642.86
1 1/2" brass screws Nos 50.00 3.50 175.00

Labour
carpenter Days 3.00 650.00 1,950.00
U/SK labourer Days 3.00 400.00 1,200.00
Scaffolding - Add 5% 157.50
14,411.07
O/H & Proffits 0.00 -
Total per 100 L.ft 14,411.07

Per L.ft 144.11

75. 18 B.W.C (1.2mm) galvanised iron


sheet valley gutter 3' 0" girth over
all once bent with end laps not less
than 9" width including 3/4" tongued
and grooved planks laid to slope and
profile on timber members.

Consider 15' 0"


Materials
G.I sheet ( 8'x 4' ) Nos 2.00 1750.00 3,500.00
wood preservative Gal 0.25 125.00 31.25
cement (50 Kg bags) Cwt 0.10 485.00 48.50
slaked lime Cwt 0.05 425.00 21.25
sand Cube 0.01 5000.00 50.00
1" thk. planks Sq.ft 50.00 97.14 4,857.14
1 1/2" wire nails Lbs 2.00 43.13 86.26

Labour:
a) Fixing boarding and applying woood
preservative
carpenter Days 1.00 650.00 650.00
U/Sk labourer Days 1.00 400.00 400.00

Page 75
Roof & Ceiling

b) Making and fixing G.I sheets


Tinker Days 0.50 625.00 312.50
U/Sk labourer Days 0.50 400.00 200.00

c) Building Sides
Mason Days 0.25 650.00 162.50
U/Sk labourer Days 0.50 400.00 200.00
10,519.40
O/H & Proffits 0.00 -
Total Per 15.00 L.ft 10,519.40

Rate per L.ft 701.29


2,300.24

76. 18 B.W.G (1.2mm) galvanised iron


flashing 1' 6" girth overall 3 times
bent with end laps not less than 6",
lead soldered, turned and tucked up
to not less than 6" in to chase out
in wall and pointed in cement mortar
1:2 lower end dressed over roof
covering not less than 1' 0" wide.

Consider 15' 0" L.ft


Materials
G.I sheet 8' 0" x 4' 0" Nos 1.00 1750.00 1,750.00
cement (50 Kg bags) Cwt 0.05 485.00 24.25
sand Cubes 0.01 5000.00 50.00
soldering lead lbs 1.00 -

Labour
Cutting bending, soldering & fixing
tinker Days 0.50 625.00 312.50
mason (caulking) Days 0.13 650.00 81.25
U/SK labourer Days 0.75 400.00 300.00
2,518.00
O/H & Proffits 0.00 -
Total per 15.00 L.ft 2,518.00

Rate per L.ft 167.87

77. Timber frame work for 4' 0" x 4' 0" flat
asbestos ceiling ( sheet measured
seperatly) Comprising of 4" x 2" joists
and 2" x 2" bearers in class 1 timber

Per 1.95 square


Materials
timber class 1 Cu.ft 8.00 1030.30 8,242.42

Page 76
Roof & Ceiling

2" nails Lb. 1.00 43.13 43.13


fibre/plastic plugs Nos 26.00 1.50 39.00
cement cwt 0.23 485.00 109.98
sand Cube 0.02 5000.00 100.00
2" brush - 1/4 use Nos 0.25 165.00 41.25
tarnap gal 0.33 -

Labour
carpenter Days 2.50 650.00 1,625.00
mason Days 0.50 650.00 325.00
U/SK labourer Days 1.50 400.00 600.00
Add 3% for scaffolding 76.50
11,202.28
O/H & Proffits 0.00 -
Total per 1.95 sqrs 11,202.28

Rate per square 5,744.76


618.14
78. Horizontal ceiling lining using 4' 0"
x 4' 0" flat asbestos cement sheets
fixed with and including beading and
cove moulding on timber frame work.
(Timber frame work & painting
measured seperatly)

Per 1.95 square


Materials
flat asbestos sheets Sq.ft 210.00 175.00 36,750.00
2" x 2" Halmilla cove moulding L.ft 60.00 9.50 570.00
1 1/2" x 1 1/2" Halmilla beading L.ft 125.00 5.50 687.50
1/4" clout nails Lb 0.25 43.13 10.78
1 1/2" brass screws Doz 8.00 42.00 336.00

Labour
1 1/2 days carpenter Days 1.50 650.00 975.00
2 day U/SK labourer Days 2.00 400.00 800.00
Add 3% for scaffolding 53.25
40,182.53
O/H & Proffits 0.00 -
Total for 1.95 squares 40,182.53

Rate per square 20,606.43


2,217.25
79. 3/4" thick toungued and grooved
lunumidella ceiling boards fixed
horizontal on 4"x 2" class 1 timber
joists at 2' 0" centres with 1 1/2"
brass nails.

Consider room 15' 0" x 13' 0" i.e. 1.95 sqrs

Page 77
Roof & Ceiling

Materials
4"x 2" timber joists L.ft 115.00 55.00 6,325.00
6"x 3/4" Lunumidella ceiling planks Sq.ft 215.00 45.00 9,675.00
cement cwt 0.03 485.00 13.20
sand Cube 0.04 5000.00 200.00
1 1/2" brass nails Kg 4.00 425.00 1,700.00

Labour
Making holes, fixing joists & making good
mason Days 1.00 650.00 650.00
carpenter Days 1.00 650.00 650.00
U/SK labourer Days 3.00 400.00 1,200.00

Fixing ceiling boards


carpenters Days 3.00 650.00 1,950.00
U/Sk labourers Days 4.00 400.00 1,600.00
Scaffolding - Add 3% 181.50
24,144.70
O/H & Proffits 0.00 -
Total for 1.95 squares 24,144.70

Rate per square 12,381.90


1,332.82
80. 3/4" x 6" wide tongued and grooved
Lunumidella ceiling boards fixed to
underside of roof rafters.(existing) with
1 1/2" brass nails including levelling
with timber strips where necessary.

Consider room 15' 0" x 12' 0" = 1.80 sqrs


Materials
ceiling planks Sq.ft 220.00 -
2"x 1/4" timber strips L.ft 40.00 -
3/4" nails Kg 2.00 -
1 1/2" brass nails Kg 4.00 -

Labour
carpenter Days 3.00 650.00 1,950.00
U/SK labourer Days 6.00 400.00 2,400.00
Scaffolding - Add 3% 130.50
4,480.50
O/H & Proffits 0.00 -
Total for 1.95 squares 4,480.50

Rate per sqr. 2,297.69

Page 78
Roof & Ceiling

15016.67
448.53

2700.00
80.65

Page 79
Roof & Ceiling

1560.92
393.83

262.50
66.23

1077.75
271.92

262.50
66.23

Page 80
Roof & Ceiling

8594.40
1879.31

Page 81
Roof & Ceiling

1925.00
420.93

Page 82
Roof & Ceiling

8575.78

2626.50

2835.39

38354.28 19668.86 2114.93

1775.00 910.26 97.88

26351.19

Page 83
Rate of pvc&plywood door

Description Unit Qty m2 ft2 Amount Rate per 1ft2


PVC DOOR
Door Teak Finish
N1 Door 700x2050 1.43 15.44 3390.00
Frame 700x2051 1344.00
4734.00
Lock & Hinges 690.00
5424.00 351.28

N2 Door 700x2050 1.43 15.44 3504.00


Frame 700x2051 1344.00
4848.00
Lock & Hinges 690.00
5538.00 358.66

P1 Door 900x2050 1.85 19.85 4134.00


Frame 900x2051 1398.00
5532.00
Lock & Hinges 690.00
6222.00 313.42

P2 Door 900x2050 1.85 19.85 4248.00


Frame 900x2051 1398.00
5646.00
Lock & Hinges 690.00
6336.00 319.16

P3 Door 700x2050 1.43 15.44 3738.00


Frame 700x2051 1344.00
5082.00
Lock & Hinges 690.00
5772.00 373.82

P4/P5 Door 700x2050 1.43 15.44 3858.00


Frame 700x2051 1344.00
5202.00
Lock & Hinges 690.00
5892.00 381.59

FIBER GLASS DOOR

D2 Door 1000x2100 2.10 22.60 14700.00


Frame with all fitting
14700.00
14700.00 650.56

D3 Door 750x1900 1.42 15.33 9750.00


Frame with all fitting
9750.00
9750.00 635.88

PLY WOOD DOOR

D6 Door 975x2175 2.12 22.82 4730.00


Frame with out
4730.00
4730.00 207.29

D7 Door 900x2175 1.96 21.06 4730.00


Fixing 500.00
Lock & Hinges 690.00
Frame with out 2091.00
8011.00
8011.00 380.34

Page 84
Rate of pvc&plywood door

D7 Door 800x2100 1.68 18.08 3800.00


Frame with
Fixing 500.00
Lock & Hinges 690.00
4990.00
4990.00 276.04

Page 85
Brick Works

BUILDING SCHEDULE OF RATES - BRICK,BLOCK & RUBBLE WORK

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


45. Brick work in cement sand 1:5 in
foundation up to D.P.C
Per cube
Materials
bricks Nos 1,450.00 5.60 8,120.00
Add 5% wastage 406.00
cement (50 kg bags) Cwt 4.00 485.00 1,940.00
sand Cubes 0.25 5,000.00 1,250.00
Water Gals 150.00 1.00 150.00
Labour
Mason Day 3.00 650.00 1,950.00
U/Sk labourer Day 4.00 400.00 1,600.00
15,416.00
O/H & Proffits 0.00 0.00
Rate per cube 15,416.00
5,447.35
46. Brick work cement & sand 1:8 in
foundation up to D.P.C
Per Cube
Materials
bricks Nos 1,450.00 5.60 8,120.00
Add 5% wastage 406.00
cement (50 kg bags) Cwt 2.33 485.00 1,131.67
sand Cubes 0.38 5,000.00 1,875.00
Water Gals 150.00 1.00 150.00
Labour
Mason Day 3.00 650.00 1,950.00
U/Sk labourer Day 4.00 400.00 1,600.00
15,232.67
O/H & Proffits 0.00 0.00
Rate per cube 15,232.67
5,382.57

47. Brick work in cement and sand 1:5


in 4 1/2" thk. walls in ground floor.
Per square
Materials
bricks Nos 550.00 6.50 3,575.00
Add 17% wastage 178.75
cement (50 kg bags) Cwt 1.30 672.00 873.60
sand Cubes 0.10 6,160.00 616.00
Water Gals 50.00 2.24 112.00
Labour
Mason Days 1.50 675.00 1,012.50
U/Sk labourer Days 2.00 500.00 1,000.00
Scafolding - add 5% 100.63
7,468.48
O/H & Proffits 0.35 2,613.97

Page 86
Brick Works

BUILDING SCHEDULE OF RATES - BRICK,BLOCK & RUBBLE WORK

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


Rate per square 10,082.44
1,084.71
48. 9" thk. brick wall cement, sand 1:5
in ground floor
Per Square
Materials
bricks Nos 1,090.00 5.60 6,104.00
Add 5% wastage 305.20
cement (50 kg bags) Cwt 3.00 485.00 1,455.00
sand Cubes 0.20 5,000.00 1,000.00
Water Gals 115.00 1.00 115.00
Labour
Mason Days 2.00 650.00 1,300.00
U/Sk labourer Days 3.00 400.00 1,200.00
Scafolding - add 3% 75.00
11,554.20
O/H & Proffits 0.00 0.00
Rate per square 11,554.20
1,243.05
49. Brick work 13 1/2" thk. in cement
sand 1:5 in super structure in
ground floor.
Per Square
Materials
bricks Nos 1,630.00 5.60 9,128.00
Add 5% wastage 456.40
cement (50 kg bags) Cwt 4.50 485.00 2,182.50
cubes sand Cubes 0.30 5,000.00 1,500.00
Water Gals 170.00 1.00 170.00
Labour
Mason Days 3.50 650.00 2,275.00
U/Sk labourer Days 5.50 400.00 2,200.00
Scafolding - add 2% 89.50
18,001.40
O/H & Proffits 0.00 0.00
Rate per square 18,001.40
1,937.72
50. 9" thk. brick walls in cement, sand
1:8 in super structure in ground
floor.
Per Square (ie 0.75 cubes)
Materials
bricks Nos 1,090.00 5.90 6,431.00
Add 5% wastage 321.55
cement (50 kg bags) Cwt 1.75 425.00 743.75
sand Cubes 0.30 5,000.00 1,500.00
Water Gals 115.00 1.00 115.00
Labour
Mason Days 2.25 650.00 1,462.50
U/Sk labourer Days 3.00 400.00 1,200.00

Page 87
Brick Works

BUILDING SCHEDULE OF RATES - BRICK,BLOCK & RUBBLE WORK

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


Scafolding - add 3% 79.88
11,853.68
O/H & Proffits 0.00 0.00
Rate per square 11,853.68
1,275.96

51. 4 1/2" thick brick wall (wire cut) in


cement and sand 1:5 in ground flr.
(Facing to brick work measured
seperately)
Per Square
Materials
Wirecut bricks Nos 550.00 20.00 11,000.00
Add 2% wastage 220.00
cement (50 kg bags) Cwt 1.20 485.00 582.00
sand Cubes 0.08 5,000.00 400.00
Water Gals 30.00 1.00 30.00
Labour
Mason Days 1.50 650.00 975.00
U/Sk labourer Days 2.00 400.00 800.00
Scafolding - add 5% 88.75
14,095.75
O/H & Proffits 0.00 0.00
Rate per square 14,095.75
1,515.67

52. 9" thk. brick walls in cement, sand


1:5 with wire cut bricks
(Facing to brick work measured
seperately)
Per Square
Materials
Wirecut bricks Nos 1,080.00 20.00 21,600.00
Add 4% wastage 864.00
cement (50 kg bags) Cwt 2.50 485.00 1,212.50
sand Cubes 0.13 5,000.00 650.00
Water Gals 100.00 1.00 100.00
Labour
Mason Days 2.25 650.00 1,462.50
U/Sk labourer Days 3.75 400.00 1,500.00
Scafolding - add 3% 88.88
27,477.88
O/H & Proffits 0.00 0.00
Rate per square 27,477.88

Page 88
Brick Works

BUILDING SCHEDULE OF RATES - BRICK,BLOCK & RUBBLE WORK

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

53. 13 1/2" thick brick wall (wire cut)


in cement and sand 1:5 in ground
floor.( Facing to brick work
measured seperatly)
Per square
Materials
Wirecut bricks Nos 1,630.00 20.00 32,600.00
Add 2% wastage 652.00
cement (50 kg bags) Cwt 4.50 485.00
sand Cubes 0.30 5,000.00 1,500.00
Water Gals 50.00 1.00 50.00
Labour
Mason Days 3.75 650.00 2,437.50
U/Sk labourer Days 5.50 400.00 2,200.00
Scafolding - add 2% 92.75
39,532.25
O/H & Proffits 0.00 0.00
Rate per square 39,532.25

54. Extra over for facing including


raised pointing 1/8" thk. in cement
and sand 1:1 mixture in ground flr.
Per square
Materials
cement (50 kg bags) Cwt 0.50 485.00 242.50
sand Cubes 0.01 5,000.00 50.00
acid Gals 0.10 350.00 35.00
Water Gals 10.00 1.00 10.00
Labour
Mason Days 5.00 650.00 3,250.00
U/Sk labourer Days 3.50 400.00 1,400.00
4,987.50
O/H & Proffits 0.00 0.00
Rate per square 4,987.50

55. 3" thk. floor paved in lime mortar


2:5 in ground floor.
Per square
Materials
bricks Nos 350.00 5.60 1,960.00
slaked lime Cwt 1.20 425.00 510.00
sand Cubes 0.11 5,000.00 550.00

Page 89
Brick Works

BUILDING SCHEDULE OF RATES - BRICK,BLOCK & RUBBLE WORK

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


Water Gals 45.00 1.00 45.00
Labour
Mason Days 1.25 650.00 812.50
U/Sk labourer Days 2.50 400.00 1,000.00
4,877.50
O/H & Proffits 0.00 0.00
Rate per square 4,877.50
525.03

56. Steps 1' - 1 1/2 " x 0' 6" in brick in


cement and sand 1:5 with 1/2" cmt.
and sand 1:2 rendering including
necessary excavation
Per 10 L.ft
Materials
bricks Nos 120.00 5.60 672.00
cement (50 Kg bags) Cwt 0.50 485.00 242.50
sand Cubes 0.05 5,000.00 250.00
Water Gals 15.00 1.00 15.00
Labour
Mason Days 0.50 650.00 325.00
U/Sk labourer Days 0.50 400.00 200.00
1,704.50
O/H & Proffits 0.00 0.00
Rate per 10.0 L.ft 1,704.50
Rate per L.ft 170.45

57. Brick drains in cement & sand 1:5,


9" wide and 6" - 9" average depth
including cement rendering 1/2" tk.
1:2 to exposed faces with 1' 6" ramp
including necessary excavation.
Per 10 L.ft
Materials
bricks Nos 140.00 5.60 784.00
cement (50 Kg bags) Cwt 0.80 485.00 388.00
sand Cubes 0.05 5,000.00 250.00
Water Gals 20.00 1.00 20.00
Labour
Mason Days 1.25 650.00 812.50
U/Sk labourer Days 1.25 400.00 500.00
2,754.50
O/H & Proffits 0.00 0.00
Rate per 10.0 L.ft 2,754.50
Rate per L.ft 275.45

58. Brick drains in cement & sand 1:5,


9" wide and 6"-9" average depth
including cement rendering 1/2" tk.
1:2 to exposed faces without ramp
including necessary excavation.
Per 10 L.ft
Materials

Page 90
Brick Works

BUILDING SCHEDULE OF RATES - BRICK,BLOCK & RUBBLE WORK

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


bricks Nos 110.00 0.00
cement (50 Kg bags) Cwt 0.70 0.00
sand Cubes 0.04 0.00
Water Gals 15.00 0.00
Labour
Mason Days 1.00 0.00
U/Sk labourer Days 1.25 0.00
0.00
O/H & Proffits 0.00
Rate per 10.0 L.ft 0.00
Rate per L.ft 0.00

59. 8" tk. hollow block work in cement


sand and mortat 1:5 in ground floor
(cavities unfilled)
Per Square:
10' 0" x 10' 0" area (Size of each
block 16"x 8"x 8")
Materials
Hollow cement blocks Nos 112.00 0.00
Allow 5% for wastage 0.00
cement (50 kg bags) Cwt 0.75 0.00
sand Cubes 0.06 0.00
Labour
Mason Days 1.50 0.00
U/Sk labourer Days 2.50 0.00
Scaffolding - add 3% 0.00
0.00
O/H & Proffits 0.00
Rate per square 0.00

59a. 6" tk. hollow block work in cement


sand and mortat 1:5 in ground floor
(cavities unfilled)
Per Square:
10' 0" x 10' 0" area (Size of each
block 16"x 8"x 6")
Materials
Hollow cement blocks Nos 112.00 0.00
Allow 5% for wastage 0.00
cement (50 kg bags) Cwt 0.75 0.00
sand Cubes 0.06 0.00
Labour
Mason Days 1.50 0.00
U/Sk labourer Days 2.50 0.00
Scaffolding - add 3% 0.00
0.00
O/H & Proffits 0.00
Rate per square 0.00

60. 4" tk. hollow block work in cement


sand and mortat 1:5 in ground floor
(cavities unfilled)
Per Square:

Page 91
Brick Works

BUILDING SCHEDULE OF RATES - BRICK,BLOCK & RUBBLE WORK

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


10' 0" x 10' 0" area (Size of each
block 16"x 8"x 4")
Materials
Hollow cement blocks Nos 112.00 0.00
Allow 5% for wastage 0.00
cement (50 kg bags) Cwt 0.40 0.00
sand Cubes 0.03 0.00
Labour
Mason Days 1.00 0.00
U/Sk labourer Days 2.00 0.00
Scaffolding - add 5% 0.00
0.00
O/H & Proffits 0.00
Rate per square 0.00

61. Random rubble masonry in cement 0.00


mortar 1:5 in foundation.
Per cube (14" thk)
Materials
6"-9" rubble Cubes 1.30 2,800.00 3,640.00
cement (50 kg bags) Cwt 5.00 485.00 2,425.00
sand Cubes 0.30 5,000.00 1,500.00
Water Gals 100.00 1.00 100.00
Labour
mason Days 2.50 650.00 1,625.00
U/SK labourer Days 3.50 400.00 1,400.00
10,690.00
O/H & Proffits 0.00 0.00
Rate per cube 10,690.00

62. Random rubble masonry in cement 3,777.39


mortar 1:5 in superstructure
Per cube (14" thick)
Materials
6"-9" rubble Cubes 1.30 2,800.00 3,640.00
cement (50 kg bags) Cwt 5.00 485.00 2,425.00
sand Cubes 0.30 5,000.00 1,500.00
Water Gals 100.00 1.00 100.00
Labour
mason Days 4.50 650.00 2,925.00
U/SK labourer Days 7.00 400.00 2,800.00
Scaffolding - add 3% 171.75
13,561.75
O/H & Proffits 0.00 0.00
Rate per cube 13,561.75
4,792.14

Page 92
Brick Works

1659.41873

1225.65371

5382.56773

803.926265 /m2

Page 93
Brick Works

1,083.86

3780.91547

1243.72443 /m2

1937.71798 /m2

Page 94
Brick Works

1275.96071 /m2

1517.30355 /m2

2957.79064 /m2

2957.79064 /m2

Page 95
Brick Works

4255.35522 /m2

536.8676 /m2

Page 96
Brick Works

525.026911 /m2

5590.76 /m

9034.76 /m

Page 97
Brick Works

0 /m

0 /m2

0 /m2

Page 98
Brick Works

0 /m2

3777.38516 /m3

2850

4792.13781 /m2

Page 99
CONCRETE WORK

HIRE OF MIXER
3/4" METAL
CEMENT

WATER
SAND
PRICE Rs. 485.00 5,000.00 3,600.00 3,250.00 1.00

1 Mixing concrete 1 : 3 : 6 ( 3/4") -G15 13.00 0.53 0.92 0.33 110.00


2 Mixing concrete 1 : 2 1/2 : 5 ( 3/4") 14.00 0.60 0.90 0.33 100.00
3 Mixing concrete 1 : 2 : 4 (3/4") -G20 18.00 0.50 0.88 0.33 120.00
4 Mixing concrete 1:1 1/2:3 (3/4") -G25 23.00 0.42 0.82 0.33 15.00
5 Mixing concrete 1 : 1 : 2 (3/4") G-35 31.00 0.44 0.96 0.33 200.00

Page 100
U/SK LABOUR

SCAFFOLDING
S/K LABOUR

SUB TOTAL

RATE
O/H
600.00 400.00 -

1.00 6.00 16,449.50 - 5,812.54


1.00 6.00 17,202.50 - 6,078.62
1.00 6.00 18,590.50 0.00 6,569.08
1.00 6.00 20,294.50 0.00 7,171.20
1.00 6.00 24,963.50 0.00 8,821.02

Page 101
Data

BUILDING SCHEDULE OF RATES

PRICES OF MATERIALS AND LABOUR AS AT 26.03.2004

ITEM DESCRIPTION UNIT RATE


Rs. Cts.
O/H & PROFFITS -
G.S.T 0.15
U/SK Labourer Day 400.00
SK Labourer Day 600.00
Mason Day 650.00
Carpenter Day 650.00
Painter Day 600.00
Plumber Day 650.00
Welder Day 625.00
Blacksmith Day 625.00
Tinker Day 625.00
Electrician Day 650.00

Blasting Powder lbs -


Fuse Wire L.ft -
Jumper Steel lbs -
DDT powder lbs

Water Gal 1.00

Earth delivered at site. Cube 1,000.00

Cement (50kg) Cwt 485.00


Sand Cube 5,000.00
1 1/2" Metal Cube 3,200.00
1" Metal Cube 3,400.00
3/4" Metal Cube 3,600.00 36
Jute Hessian Sq.ft 1.00
Hire of vibrator Day 1,500.00
Hire of mixer Day 3,250.00

Class II timber Cu.ft 622.84


1" thick class II timber Sq.ft 312.50
2"x 2" class II timber L.ft 18.00
2"x 1" class II timber L.ft 8.00
4"x 2" bearers class 11 L.ft 60.00
Timber Props class 11 L.ft 10.00
Wedges Nos 8.00
Timber Class 1 Cu.ft 1,030.30
1" planks class 1 Sq.ft 97.14
2"x 1" reepers Class 1 L.ft 11.00
4"x 2" timber class 1 L.ft 55.00
4"x 3" timber class 1 L.ft 85.00
1 1/2" planks class 1 Sq.ft 175.00
1" planks class 1 Sq.ft 97.14
6"x 3/4" Lunumidella ceiling planks Sq.ft 45.00
40.0 l.ft 2"x 1/4" timber strips L.ft
2" x 2" Halmilla cove moulding L.ft 9.50
1 1/2" x 1 1/2" Halmilla beading L.ft 5.50

Page 102
Data

Page 103
Data

3/4" brass screws Nos 2.00


1/2" brass screws Nos 1.75
1 " brass screws Nos 2.50
1 1/2" brass screws Nos 3.50
1 1/2" brass nails Kg 425.00
1 1/4" brass screws Nos 3.25
3/4" nails Kg 90.00
Wire nails. Lb 43.13
16mm 18" long bolts No 75.00
Mould oil Ltr 75.00

Tor steel rods incldg.transport Cwt 3,228.48


M.S steel rods incldg.transport Cwt 3,185.00
G18 Binding wire lbs 24.19

Bricks Nos 5.60


Wirecut bricks Nos 20.00
Acid gal 350.00
Slaked lime Cwt 425.00
Boiled Lime(Painting) Cwt 350.00
Hollow Block 16"x 8"x 8" Nos 56.00
Hollow Block 16"x 8"x 6" Nos 45.00
Hollow Block 16"x 8"x 4" Nos 38.00
6"-9" Rubble Cube 2,800.00 1300
Pressed foor tiles 8" x 8" Nos 40.00
Wax Lb 140.00
Coloured pigment Lb 270.00
Cotton waste Lb 8.00
Glazed wall tiles 4"x 4" Nos 35.00 1420
Glazed wall tiles 6"x 6" Nos 50.00 0.01
Glazed floor tiles 8"x 8" Nos 55.00 100
White cement Lb 9.92 586
12"x 12" Terrazzo tiles Nos
12"x 12" Ceramic floor tiles Nos 95.00

Calicut pattern tiles Nos 25.00


Asbestos corrugated sheets. Sq.ft 260.00
Flat asbestos sheets Sq.ft 175.00
Roofing screws and washers. Nos 101.00
Half round clay tiles Nos 14.00
Ridges 3' 8" long Pairs 217.71
Calicut pattern ridge tiles Nos 16.50
Colouring powder Lb 126.98

G.I sheet ( 8' x 4' )G.22 Nos 1,750.00

Wood preservative ltr 125.00

Soldering lead lbs


Fibre/plastic plugs Nos 1.50

Page 104
Data

Spur stones Nos


fibre/ plastic plugs with 4" long brass screws Nos
5/8" mild steel dowels Nos
6' 9"x 2' 9" plywood sash Nos
Glass panes 5mm Sq.ft 37.77
1/2"x 1/2" beading L.ft
Brass panel pins Doz

But hinges 4"x 3" Pair 110.00


Tee hinges 6"x 12" Pair
Rim lock with screws Nos 575.00
Mortice lock with screws No. 1,400.00
Casement stays Nos 150.75
Door closer Nos 1,000.00
Tower/Skeleton bolts. Nos
4" Barrel bolt Nos 60.00
Casement fasteners Nos 184.50
Brass fanlight catches. Nos
Draw rings Nos 15.00

Bitumen Gals 76.27


Fire wood lbs 1.79

Colour cement lbs 181.41

Page 105
Data

Wood preservative Ltr. 85.00


Anti-corrosive primer Ltrs 227.04
Mineral turpentine or thinner Ltrs 73.58
Enamal paint Ltrs 498.00
Wood Primer Ltrs 455.00
Wall Primer Ltrs 166.65
Emulision paint Ltrs 268.32
W/shield Emulsion Paint Ltrs 312.66
Varnish Ltrs 311.89
Salt Lbs
Yellow ochre Lbs
Blue ozs

Sand papers Nos 15.00


Wire brush Nos 40.00
2" brush No 165.00
3" brush No 245.00

6" brush No 395.00


8" brush No 675.00
6" Coir brush Nos 185.00
Floor Brush Nos 225.00
Wax + Floor polish lbs 370.00

flannel cloth Yards

solvant cement grm 0.86


1/2" DIA pvc pipes lft 4.96
1/2" DIA pvc clips & nails Nos 4.40
3/4" dia PVC pipes Lft 9.48
3 clips and nails Nos 4.40
1" dia PVC pipes Lft 14.23
1" dia sockets Nos 10.43
1" dia clips and nails Nos 4.40
1 1/4" dia meter PVC pipes Lft 21.93
1 1/4" dia sockets Nos 16.13
1 1/4" dia clips and nails Nos 5.29
1 1/2" dia PVC pipes Lft 32.49
1 1/2" dia sockets Nos 30.80
1 1/2" dia clips and nails Nos 6.17
2" dia meter PVC pipes lft 54.42
2" dia sockets Nos 52.54
2" dia clips and nails Nos 6.46
3" dia PVC pipes Lft 107.19
3" dia sockets Nos 141.08
3" dia clips and nails Nos 31.95

Page 106
Data

1/2" elbows/bends/sockets Nos 8.69


3/4" elbows/bends/sockets Nos 14.79
1" elbows/bends/sockets Nos 23.30
1 1/4" dia elbows/bends/sockets Nos
1 1/2" dia elbows/bends/sockets Nos
2" dia elbows/bends/sockets Nos
2 1/2" dia elbows/bends/sockets Nos
3" dia elbows/bends/sockets Nos
1/2" tees Nos
3/4" Dia tees Nos
1" Dia tees Nos
1 1/4" Dia tees Nos
1 1/2" Dia tees Nos
2" Dia tees Nos
2 1/2" Dia tees Nos
3" Dia tees Nos
4" dia EW pipes lft
4" dia C.I pipes lft
lead Lbs
yarn Lbs
wood plug 6"x 6"x 2" Nos
3" iron screws Nos
firewood Cwt
4" S W gulley Nos
4" G.I grating. Nos

Page 107
Data

wash basin complete with brackets Nos


1/2" tap Nos
Waste plug and chain Nos
wooden plugs Nos
Wash basin with pedestal,tap,waste Nos
Ceramic sink 24"x 15"x 7" Nos
L iron brackets Nos
Low level suite complete Nos
1/2" dia stop cock Nos
Squatting pan with trap Nos
2 gals C.I cistern with 1 1/4" flush
pipe, chain and pverflow pipe Nos
clip Nos 5.29
wooden plugs Nos
bidet complete waste & mixer Nos
Urinal Bowls with waste Nos
2 gal. Automatic cistern Nos
rawl plug Nos
spreador Nos
6" dia eaves gutter lengths lft -
joiner Nos
gutter brackets Nos
PVC gutter head Nos
mitre bend Nos
end cap No
3 1/2" dia down pipe lft
3 1/2 down pipe joiner Nos
PVC straps Nos

Dolomite Cwt
Milk White chips kg
Black chips kg
White Cement Cwt -
Red Cement kg
3/4"x 4' 0" long aluminium strips No
Cutting stone (medium) No
Cutting stone (rough) No
Cutting stone (fine) No
Hire of terrazo cutting machine Day

Page 108
Preliminaries

***Money allocation for Tender security bond *Labour overtime rates

Contract sumx1/100x0.1 *O/T Rate


= Daily RateX1.5/8
***Money allocation for Performance bond
*After10.00 p.m
Contract sumx10/100x0.1 .= Daily RateX1.5X1.1/8

Page 109

You might also like