1. Describe, with the help of suitable figure(s), the components and working of mine power
center.

2. Describe the method of symmetrical components and how it is used to calculate fault
current in case of a single line-to-ground fault.

3. Describe, with the help of suitable figures, the distribution of electric power in surface
mines.

4. Describe with the help of suitable figure(s), the components and working of single-ended
mine substation with circuit breaker protected transformer.

5. Describe the relaying schemes for phase-to-phase fault, over-load and ground fault
protection.