Professional Documents
Culture Documents
Ariba Case Solution
Ariba Case Solution
MED – X Inc. a global pharmaceutical giant that has seen a sustained growth ever since its inception. In
order to maintain its competitive advantage, the company has decided to closely monitor the
procurement process and make it more efficient. For this they have brought in Implementation
Technologies, to install its Ariba application to transform the existing set of procurement procedures
into a decentralized purchasing model having a self-service philosophy. This process will help in
streamlining the process between suppliers and MED-X while ensuring better connectivity, reducing
cycle time and cost involved.
Analysis
Which of the two components are underperforming according to the plan? How do you know this?
As per our above analysis, Technical infrastructure component of our project is not performing as per
our plan. We can see that the average CPI is 0.93 and average SPI is 0.94 the project is behind on both
the cost basis and time basis. The work is not being done on time as planned and the project is going
overbudget. This is not the case for our software customization component as the CPI and SPI values are
both above 1.
Are the components of the projects within budget? How do you know?
Technical infrastructure component is overbudget as we can see that Cost variance (CV) is negative for
the last four months of the project. The average and month wise CPI (Cost performance index) is also
below 1 for technical infrastructure. This indicates that the component is incurring additional cost than
planned.
software customization component has positive average CPI and CV for each month proving that the
component is performing while being underbudget. As their SPI is also above 1, it shows that the
component is underbudget while being ahead of schedule.
What can you conclude by looking at the combined earned value data for the project?
The combined EV analysis data shows us that overall the project is still underbudget and performing
within the schedule as the overutilization of resources is by technical infrastructure is being made-up for
by the underbudget and ahead of schedule performance by software customization component.
Although, we cannot be assured that the project will be completed within budget, neither we can say
the same for time of completion. As the technical infrastructure component still needs to be finished to
declare the project complete, its additional cost and additional time will determine the final cost and
time of the project.
Why did Terry Baker think that the project was going according to plan the entire time?
As mentioned in the case, there had been some issues in the beginning of the project regarding some
resources which martin did not report to terry. Another incident of the pulling out of MED-X staffer off
the team and the delay of sun server equipment delivery. These incidents points towards a lack of
communication between the implementing company and MED-X CIO Terry Baker.
As all the communication was going through martin, he may have been apprehensive of reporting the
shortcomings of the project to his superior. Also as there was no proper checks and control system for
the project in place, it might have been that Martin himself came to know about the delay at the end
stages of the project.
We can declare the project as complete only after the technical infrastructure component is complete.
To calculate that we will calculate estimated time at completion.
What should Martin have done earlier in the project timeline to prevent delays?
What should Martin do when managing future projects to prevent similar problems from developing?
Martin should focus on implementing the above-mentioned points in his project planning to prevent the
problems that caused the delay of this project. A project that involves various long time, resource
consuming steps to be implemented can be completed on intuition. More open communication
channels and proper guidelines are necessary for a project to succeed. It also leads to quick resolving of
any issues that might crop up.