Professional Documents
Culture Documents
1.1 Introduction
Writing a report on “Damages of segmental lining” is one of the on-going activities of the International
Tunnelling Association (ITA-AITES) Working Group 2 – Research, animated by Elena Chiriotti. The
International Team Leader of this activity is Jon Hurt.
Aiming to contribute, in years 2016 – 2018 the Italian Tunnels Society - Società Italiana Gallerie (SIG) Working
Group 2 - Research, under the coordination of Andrea Sciotti and animated by Enrico Maria Pizzarotti, has
prepared the present draft report and submitted it to the ITA WG2 Animateur and to the International Team
Leader, as technical core of a possible final report to be further developed.
In order to be reviewed by the ITA WG 2 members and go through the formal approval process of ITA, a
conceptual and final agreement on the document should be achieved, through further discussion and meetings
within ITA WG 2; moreover, the technical part of the report itself should be completed with the ancillary
chapters (e.g. Preface, Glossary, List of Symbols and Abbreviations, Introduction, Scope, Concluding
Remarks). The final report should also take advantage of the results of an international survey on the subject,
which will constitute its possible Annexes (e.g. Case Studies, General Tendencies).
Nevertheless, after an independent evaluation of two experts, SIG decided to publish this draft report, in order
to illustrate what done by the SIG WG 2.
The members of the SIG Working Group 2, to whom the SIG’s thanks go, are: Chiara Agostini, Monica Barbero,
Gustavo Bomben, Vincenza Floria, Federico Foria, Valeria Mainieri, Davide Merlini, Matteo Moja, Ludovica
Pizzarotti, Giovanni Plizzari, Diego Sebastiani, Giovanni Tiberti, Giuseppe Vago, Alessandra Vecchiarelli.
1.2 Scope
In the construction of underground infrastructures, the use of mechanised tunnelling faces a continuous
increase; consequently, the production of precast segmental linings has become an increasingly important
part of the tunnel industry. Therefore, guaranteeing high quality and performance of precast linings gets more
and more crucial, both from the Project Owner and the Contractor points of view; in fact, the Owner of the
infrastructure requires (and pays for) a tunnel free from defects and water-tight in the long-term, whereas the
Contractor (and his potential Subcontractors) doesn’t want to spend for replacing damaged segments,
repairing defective segments or non performing rings after the erection, performing water-tightening injections,
etc.
The aim of this draft report is providing an overview of the aspects that affect the quality of the precast
segment's production and of the complete precast tunnel lining, thus equipping the parties involved in tunnel
industry with a set of tools that can help to improve the segments’ production and the precast lining quality, in
terms of: quality control; types, causes, mitigation and repair of possible damages; appropriate design
procedure; useful tests and checks, both preliminary and on the finished product.
References to the currently applicable standards and guidelines (Chapter 3) and of the principal bibliography
(Chapter 8) on the topic are given. Specific indications on Quality Control procedures (Chapter 4), Type and
Causes of damage, Mitigation and Repair actions (Chapter 5), Calculation Methods (Chapter 6) and On-Site
and Laboratory Test and Checks (Chapter 7) are provided.
All the phases of the segment life, from factory production, transportation and delivery on site, installation, until
handover and service life are considered.
1 PREFACE ................................................................................................................................................ 1
1.1 Introduction............................................................................................................................................. 1
Causes of damage........................................................................................................................... 56
Description of damage.................................................................................................................... 59
Causes of damage........................................................................................................................... 60
Description of damage.................................................................................................................... 64
5.2.3.1.1 Splitting / bursting cracks (transversal cracks perpendicular to the thrust force) ...........................64
5.2.3.1.2 Longitudinal cracks along the tunnel and spalling cracks ............................................................... 65
Causes of damage........................................................................................................................... 65
Description of damage.................................................................................................................... 68
Causes of damage........................................................................................................................... 70
Geometrical tolerances..................................................................................................................... 78
Components....................................................................................................................................... 78
Structural verifications for the Prefabrication processing (at the prefabrication factory) ........83
The contractual management of the damaged segments is not regulated by specific standards as this aspect
is project-related and it is normally defined by the Client within the Quality Management plan or the project
specifications. In these documents the Client identifies the functional requirements which include operational,
security, durability, water tightness, repair and maintenance requirements that must be incorporated into the
design and sizing of the tunnel lining.
However most of the countries have published guidelines that suggest practical measures to avoid the
occurrence of defects in the concrete during the production, transport and installation phase as well as to
identify, interpret and repair specific types of damage or to carry out a general tunnel inspection, damage
assessment, rehabilitation and maintenance.
[1] AFTES Recommendations: Geometry, concrete, formwork and concreting of tunnel lining:
Construction defects;
[2] AFTES Guidelines: The design, sizing and construction of precast concrete segments installed at
the rear of a tunnel boring machine;
[3] AFTES Recommendation n.GT38R1A1 (2013): Design, dimensioning and execution of precast steel
fibre reinforced concrete arch segments, Tunnels et espace souterrain, n. 238, July-August 2013,
pp. 312-324
[4] U.S. Department of Transportation: Technical Manual for Design and Construction of Road tunnels
– Civil Elements;
[5] BTS (British Tunnelling Society), 2016. PAS 8810. Tunnel Design-Design of concrete segmental
tunnel lining-Code of practice;
[6] BTS and ICE: Specifications for tunnelling third edition;
[7] DAUB Deutscher Ausschuss fur unterirdisches Bauen e. V. German Tunnelling Committee (ITA-
AITES): Recommendations for the design, production and installation of segmental rings;
[8] Japan Society of Civil Engineers (JSCE), 2005. Standards on test methods of repairing materials
used for concrete structures;
[9] Japan Society of Civil Engineers (JSCE), 2006. Standard Specifications for Tunnelling: Shield
Tunnels, Tokyo;
[10] Australian Standards: AS 4825-2011, AS 3610-1995, AS 1170-SAA;
[11] BS EN 1504: Products and systems for the protection and repair of concrete structures - Definitions,
requirements, quality control and evaluation of conformity;
[12] BS 1881-208: Testing concrete. Recommendations for the determination of the initial surface
absorption of concrete.
[13] BS 1881-122: Method for determination of water absorption.
[14] BS EN 1990:2002+A1:2005, 3.2
[15] BS EN 1992-1-1.
[16] CIRIA C671 – Tunnels: inspection, assessment and maintenance;
[17] FHWA: Tunnel Operations, Maintenance, Inspection and Evaluation Manual;
[18] FHWA: Highway and Rail Transit Tunnel Maintenance and Rehabilitation Manual;
[19] ACI 318-95: Building Code Requirements for Structural Concrete;
[20] ACI 544.7R-16: Report on Design and Construction of Fiber- Reinforced Precast Concrete Tunnel
Segments;
[21] Model Code 2010 - Final draft (2012), “fib Bulletin 65”, Volume 1, pp. 350, ISBN 978-2-88394-105-
2; “fib Bulletin 66”, Volume 2, pp. 370, ISBN 978-2-88394-106-9;
[22] fib bulletin, n. 83, state-of-art report, fib WP 1.4.1, “Precast tunnel segments in fibre-reinforced
concrete”, October 2017, pp. 168, ISBN: 978-2-88394-123-6
Some references have been summarised in Table 1 with a summary of the relevant topics covered in the
documents.
4.1 Introduction
Quality control is an integral part of the whole segment journey from the precast factory to the tunnel
construction. Given that the precast elements are made under controlled conditions and closed supervision, a
high level of quality can be achieved during the manufacturing process; however critical activities such as
lifting, handling, transportation and installation may impact the quality criteria requirements for a specific
project. The quality level can be measured in terms of serviceability, aesthetic, performance in health and
safety, etc. and these requirements are normally stated within the Contract Specifications.
The following paragraphs describe the general quality control procedures for the precast elements carried out
during each phase of the segment life, from factory production (Paragraph 4.3), transportation and delivery on
site (Paragraph 4.4), the installation (Paragraph 4.5), until the handover and service (Paragraph 4.6). These
main phases are schematically shown in Figure 1.
Each phase normally involves three fundamental operations which are defined and detailed within the general
quality plan: traceability and data record, inspection, acceptance and/or repair works. Each segment
undergoes these activities at every phase of its life and cannot be moved to the next stage of the process until
all the quality criteria are fulfilled (Figure 2). A description of the most common procedures for segment
tracking, control and repair is provided as guidance for each stage of the segment journey.
• The Project Owner (Client): is generally directly involved in the construction process and is the
recipient of the inspection reports on segmental lining, mining, settlements measurements etc.
• The Main Contractor: executes the construction works. It is usually responsible for the manufacturing
and delivering of the segments on site. It is an intermediary between the Subcontractor (if any) and
the Project Owner. It is also responsible of all the communications with the Project Owner.
• The Subcontractor (if any, for the tunnel construction; otherwise the Main Contractor is the only
responsible): is usually, in charge of the tunnel excavation and lining installations and carries on a
separate quality process related to the tunnel activities.
• The Segment Manufacturer: manufactures the lining in its own facility.
• Transport Companies: oversee the segmental lining transportation.
• Project Supervision / Construction Administration
The wide number of organisations and people involved require cooperation between the parties. The
collaboration can allow easy and smooth sharing of documents among them and access to different databases.
Contractors, Subcontractors and Segment Manufacturer should have an internal Quality Assurance (QA) team
that assures the implementation of quality measures during the production, delivery and installation and it is
responsible for the fulfilment of all quality related terms. The QA Manager assures that all requirements
prescribed in the tender documents or in relevant standards are respected. He is also responsible for providing
the quality plan as well as compiling all certificates and test results.
Under the conditions stated in the Contract, an Inspection Agency shall be an independent party to ensure
quality of the precast segment production. It shall conduct on-site quality control audits and inspection on
behalf of the Project Owner.
An overview of the main aspects that a general quality plan should cover can be summarized as follows:
• Meet requirements given in the tender documents or in relevant standards for production and repairs
materials, equipment and plants.
• Supervise, sample and test all segments’ constituent materials and concrete, at the batching plant or
in lab.
• Supervise, sample and test all segments repairs materials.
• Compile certificates and test results.
• Implement quality measures on the production yard. Moulds, steel cages, assembly parts and segment
production must be in accordance with the production plans.
• Implement quality measures on the production activities (cleaning and oiling of moulds, transport and
mounting of steel cages, casting of segments, surface finishing, curing, demoulding, repair works,
applying of gaskets and transport to the storage).
• Foresee an inspection plan and segments’ repairing procedure.
Each segment is identified by a unique barcode (Figure 3) that can be scanned to keep track of its journey
from the factory to the construction site.
The Manufacturer database should contain the following information per each ring pack:
• Production date
• Production ring number
• Segments unique Identification Number ID (which the entire tracked history of the segment, from
production to service, will be related)
• Reinforcement ID and Type
• Mould ID and Type
• Start – End Date of casting
• Segments drawings
• Check list (Inspections) to compile after demoulding and for final acceptance for each segment
• General Materials Specifications and Quantities
• Weakness points or minor defects for which no action or general repairs are needed
• Hold point or major defects, known as non-conformities (NCR), for which a special concept has to be
defined or the segment is rejected
A Close Out Criteria should be defined and included in the Quality Plan as a guideline to identify the type of
damage during the inspection and the related corrective actions to adopt (see Chapter 5 for more details on
the type of damages, mitigations and repairs). These criteria can vary for each project depending on the
different Manufacturers, Design specifications, Contract requirements and local standards and regulations.
An example of how a Close Out Criteria can be structured is shown in Figure 4 and Figure 5.
Figure 6 shows the steps of the inspection and acceptance process. If the segment has been repaired after
the first inspection, a final inspection is carried out for acceptance. At this point, the segment can be stacked
with the other ring components at the storage area, ready to be transported.
• Meet requirements given in the tender documents or in relevant local regulation and standards.
• Supervise segments handling and transportation process.
• Compile transport permits, notes and inspections check lists.
• Foresee an inspection plan and segments repairing procedure.
• Implement quality measures during handling and transportation.
• Fulfil production target and meet workplace regulations.
The Main Contractor is, in most cases, responsible also to inform the transport company about the shipped
quantities and their destination.
The segments are therefore transported either from the Production Factory to the site or to a temporary storage
area and then to the site.
Together with the transportation and delivery permits and notes, it is good practice to issue and record within
the Manufacturer and Main Contractor database the following documents:
1) The Shipping request handed over to the Manufacturer by the Main Contractor.
2) The Shipping list handed over to the Main Contractor by the Manufacturer. This list is the output of
Manufacturer database and provides the list of segments to be transported and delivered, previously
inspected at the factory (usually signed by the Main Contractor QC representative for acceptance).
3) Loading Pack list handed over to the Transport Company by the Main Contractor. This document
provides the list of elements loaded on each transportation mean, including important data such as
production ring number, segment ID and type of reinforcement.
Once segments have been delivered on site, delivery notes and shipping lists are checked by the Main
Contractor Site Personnel.
Whenever a new pack of segments is planned to be delivered on site, the Main Contractor should track the
rings and notifies verbally or by e-mail the Tunnelling Subcontractor (if any) responsible personnel. The
shipping list (Ring Pack list) should be shared among all the parties involved and recorded.
In this phase, a new reference number related to the ring building sequence should be assigned to each ring
pack. The new numbering system of the segments must be correctly correlated to the segments information
recorded during the previous phases, from the factory to the site and the history of each ring/segment should
be stored in a database (Figure 7) for long-term traceability.
Each segment is inspected for damages and can be accepted, marked for repairs or rejected as per defined
Close Out Criteria (see Chapter 5 for more details on damages after the production phase). Only accepted
segments can be transported to the site.
Once the rings arrive on site, another inspection by the Main Contractor QC inspector should take place to
ensure proper unloading, handling and storage. Another checklist is issued and recorded in the system per
each segment.
The Quality Department representatives of the Tunnelling Subcontractor (if any) might perform joint inspections
with the Main Contractor personnel for the acceptance of the segments on site.
At the arrival, the segments are inspected for damages as per Close Out Criteria (see Chapter 5 for more
details) and can be:
• Accepted;
• Marked for repair;
• Rejected.
In case of rejection, if permitted, they can be re-used for temporary purposes such as sacrificial segments at
the interface with other structures (such as stations, shafts and adits that will be demolished after the passage
of the TBM). Those requiring repair, should be stored in a separate area until they are ready to be re-inspected
and eventually accepted.
The following operations are carried out during each inspection at site:
• Each ring stack (identified by an ID which is indicated on its barcode label) is scanned and registered;
• The n. segment IDs as they appear on the barcode labels in compliance with the ring numbering given
by the manufacturer are registered;
• Each segment is checked at this point for the detection of any possible spalling, cracks, surface defects
and/or damage to the gasket. The defect is registered with reference to specific ring number and
segment ID number.
The criteria to be met for the acceptance are specified in Chapter 5 and usually are:
• Gasket in good condition and fitting inside the groove (no humps) along its entire length;
• No broken edges or surface breakouts affecting the gasket groove area of the segment;
• Segments with complete absence of cracks within a certain width and broken edges or surface
breakouts within a certain depth outside gasket groove.
A “traffic light” system can be followed for the segment acceptance process:
• Accepted: the segment has no substantial defects and it is accepted. Therefore, when a ring is wholly
accepted can be supplied directly to TBM after the first inspection.
• Marked for repairs: the segment needs to undergo repairs. In case one segment from a ring stack
does not meet the acceptance, criteria but is still repairable according to relevant repairs criteria, the
whole ring is then considered in a “Stand-by Status” for repair.
In case a segment is rejected for any reason, it is possible to replace it with an accepted one if available on
site. The segments substituting other should be:
Once ring packs are accepted, they are ready to be transported and delivered on the TBM for installation.
4.5 Installation
The Quality Plan, during delivery on TBM and installation phase, should address and cover:
• Roles and responsibilities during segment handling, transportation and ring building.
• Records of information provided and exchanged between the Main Contractor, the Subcontractor (if
any) and the Tunnel Personnel.
• Segments inspections and acceptance for ring building.
• Meet requirements given in the tender documents and in relevant working procedures.
• Supervise segments handling, transportation and installation process.
• Compile TBM production reports and inspections check lists.
• Foresee an inspection plan and segments’ repairing procedure.
• Implement quality measures during handling, transportation and installation.
• Fulfil production target and meet workplace regulations.
During this last handling and transportation process, before reaching the TBM, segments should be tracked
and inspected for damages (by the Subcontractor or Main Contractor operators). All the information should be
recorded in the Subcontractor/Main Contractor system.
Once the segments reach the TBM and are in proximity of the erector, a last tracking and inspection, before
installation, should be done by the TBM responsible personnel.
Ring Building operations should be always supervised by the TBM responsible personnel. It’s fundamental to
correctly install and align the segment with each other to avoid severe damages and misalignments during the
next steps (thrust phase during TBM advancing and servicing).
Ring Erection Reports are usually compiled to keep track of TBM daily production and inspected segments
damages.
The report can collect the following data: date, TBM number, ring build number, segment ID, key position,
previous key position, invert position, strain gauges installed/monitoring ring and inspected damages.
At the end of each TBM shift, Ring Erection Reports should be delivered to the Technical and Production
Department (of the Subcontractor and/or Main Contractor) in charge of recording and updating the segments
database.
• Roles and responsibilities during tunnel handover process (from the Subcontractor and/or Main
Contractor to the Project Owner)
• Records of information provided and exchanged between the above-mentioned parties
• Segments inspections and acceptance for the final handover
• Meet requirements given in the tender documents and in relevant working procedures.
• Supervise segments’ inspections and repairs process.
• Compile inspections, repairs and handover reports.
• Foresee an inspection plan and segments’ repairing procedure.
• Implement quality measures during repairing operations.
• Fulfil production target and meet workplace regulations.
Before starting any quality inspection after the ring building, it is important to ensure that all the rings’ segments
have been recorded and the system contain all the ring life cycle data from the factory up to the tunnel
(Segments IDs, Damages Records, Inspections, Reparations, etc.).
The segment tracking is therefore finally checked segment by segment and filled in with any missing
information.
When completed, the database should be shared between the parties involved.
• First Internal Inspection before repairs carried out by Subcontractor/Main Contractor and
independently by the Project Owner Inspector (or by the Project Supervision / Construction
Administration)
1) : a Ring Condition report is filled up from each party to show the Quality-structural status of the ring
(segments at invert are generally excluded if not cleaned). The position and the type of damage are
marked on a ring scheme; remarks, descriptions, pictures, date and inspectors should be listed.
2) Joint Inspection between Subcontractor/Main Contractor and the Project Owner Inspector before
repairs: the damages recorded during the independent inspections will be discussed within the tunnel.
An agreement between parties will take place. The Ring Conditions Reports will be updated and
shared between the parties.
3) Repairs: Repairs can be done on the inspected rings. Subcontractor/Main Contractor Repairs team is
responsible to compile a special repair report for each work carried out. For example: for leaks and
cracks the number of injected points, the injection pressure, the injected volume or quantity and the
The project development, strong planning, software design, field-testing and execution (the paramount PDCA,
Plan, Do, Check, Act of the Quality Assurance Management Systems - Figure 9) can make this task more
streamlined and more efficient.
An implementation aimed for the project users and workers involved rather than fulfilling mere regulatory and
contractual requirements can boost project success and nowadays technologies make this possible. The
application of a software/service integrated to the project system and a cloud service is the optimal solution.
The process is integrated starting with two basic keywords: paperless and cloud service.
By using the cloud service all TBM reports and Inspections production is automated. The segment tracking,
including not only damage recording and repair recording, but also acceptances and signatures, happens by
handheld device, such as portable media players (smartphones or similar). All the data is stored in the cloud
to be immediately accessible for processing and or sharing among the parties. The rings library is built, and
the complete traceability target achieved having more than one point of scanning and control (Figure 10).
One of the biggest result in implementing this kind of automated process is that, once the ring package library
is archived after all the scanning process, only one segment needs to be scanned to have the direct access to
the ring pack data.
Other advantages of having an integrated tracking system is that at any given moment of the flow it is possible
to take pictures, signal different type of damage, write comments, and produce reports. At any time, it is
possible to extract statistical information to show amount and distribution of the defects which can be easily
put in relation to the alignment and the position of the TBM.
This could be used as part of the tunnel handover protocol to the Project Owner.
With regards to segments repairs, the following guidelines must be read in conjunction with the relevant
technical data sheets of the adopted materials.
Sampling, pre-testing, full-scale test and laboratory tests should be carried out prior the commencing the
repairs operations to test the material, the repair operators and the operations. These preliminary activities
(type of inspections, testing, responsibilities, frequency and acceptance criteria) should be, generally, strictly
identified by the contract requirements and developed differently for each construction phases (before and
after ring building).
Repairs operators and supervisors should be certified by the supplier for having attended the training on the
use of the relevant repairs materials. Moreover, full-scale tests on segments (usually pull-off testing and
Petrographic analysis on cores) should be carried out to certificate the operators and the company on the
repairs methods and procedures adopted. In case of fulfilment of the project specifications, the company is
certified.
• Hollow
• Exposed reinforcement
• Exposed aggregates (gravel nests or honeycombs)
• Removal of concrete skin
Depending on the position of the affected area, the importance of defects varies.
• Extrados
• Intrados
• Perimetric surfaces
• Gasket grooves and other niches, pockets, holes, etc.
5.1.1.1.1 Hollows
Generally, hollows located at extrados, intrados and perimetric surfaces are considered defects, when their
dimension exceed 5 mm.
Hollows on gaskets groove can be considered non-conformities when bigger than 1 mm [53].
To ensure gaskets and lining correct water tightness, grooves (Figure 12) should be free from this type of
defect.
Causes
Hollows are mainly due to a non-complete or non-optimal air expulsion from the surface between mould and
concrete or from the concrete itself.
In addition to the air trapped inside the mould during concrete pouring, the concrete can absorb air also during
segment casting and concrete transport.
Every time the concrete is unloaded from one recipient to another, air can be absorbed (i.e. from mixer to
hopper, from shuttle hopper to casting hopper, from concrete conveyor belt to casting hopper, from truck mixer
to mould)
Surfaces located in an undercut section in relation to demoulding direction, are more likely to be affected by
this type of defect because air can get stuck and be absorbed.
A poor or unevenly distributed vibration inside the mould, can cause segment surface hollows.
Mitigation measures that can be adopted to reduce hollows formation on segments surfaces, consist in
adjusting:
• Mix design
Enhance mix workability adding water and/or fluidifiers. This kind of correction has a limit: the concrete
final strength must always be reached and mix segregation avoided.
• Casting process
Proper pouring elevation and adequate vibration (correct intensity, duration and distribution).
Causes
Mitigations
Possible mitigation measures to reduce the risk of reinforcement exposure are described as follows:
Exposures occur at segment surface where the fine fraction (sands, cement, additives) of the mix design is
absent whereas the coarse fraction (gravels) is visible.
EXPOSED
AGGREGATES
Causes
• Washout
When a very fluid concrete is adopted and/or the water amount of the mix design is excessive,
washouts might occur. The fine fraction of the mix is washed out toward other areas or outward of the
mould, exposing the coarse fraction.
• Poor mixing
A poor mixing can lead to the formation of coarse fraction conglomerates. If conglomerates don’t break
up during the following concrete transport phases (pouring in transport buckets/hoppers, casting in the
mould), nests and combs can form inside the segment or outside at the segment-mould contact
surface.
Mitigations
• Washout
Reduce mix design water content (if possible) and build watertight moulds, avoiding the outflow of fine
and fluid fractions.
• Poor mixing
A correct management of mixing times and a proper batching of aggregates, cement, additives and
water in the mixer ensures a uniformly mixed concrete.
The batch volume must be suitable for the size of the adopted mixer. As a guideline the batch volume
should be comprised between 75-100% of the maximum volume mixable by the mixer (it’s important
to discuss this aspect with the supplier when choosing the mixer to use).
If no fibre-reinforced concrete is used, concrete layers between the segment surface and the concrete cover
are the weakest areas.
Statistically these defects affect more corner areas than circumferential edges.
Concrete removals must not be mistaken with chipping of corners, damage that will be discussed further on.
Causes
• Incorrect demoulding
If the segment is demoulded applying a force that excessively deviate from the optimal demoulding
direction, some areas of the segment can cling on the mould causing surface scratches and/or
removals.
The deviation from demoulding direction can be related to error in the mould construction or usually to
a mispositioning of the demoulding equipment (sling bar and vacuum).
When a mechanical sling bar is used, if the clamping force or the clamping pads dimension are not
well sized, the segment can slide, tilt and cling during demoulding and consequently break.
• Insufficient undercuts and draft angles
Undercut surfaces or more often insufficient draft angles can cause localized concrete surface removal
during demoulding. A correct mould design is fundamental to avoid these defects.
• Demoulding agent non-homogeneous distribution
Whenever the demoulding agent is not uniformly distributed on the whole mould surface, concrete
removals can occur.
Mitigations
• Incorrect demoulding
To avoid or minimize an incorrect demoulding, caused by the demoulding system mispositioning, the
gantry crane lifting height can be increased (in this case, the pull force deviation decreases when lifting
height increases). Heights higher than 8 m can minimize this issue.
• Insufficient undercuts and draft angles
In the design phase, it’s important to carefully evaluate draft angles and possible undercuts.
The adoption of modular inserts that can be removed from the segment after demoulding can avoid
surface scratches and/or segment breaks.
If it’s not possible to use them, surfaces with not very pronounced draft angles, should be carefully
and uniformly covered with a proper demoulding agent or grease.
As an alternative, single-use inserts can facilitate demoulding operations eliminating the necessity to
treat inserts surfaces in contact with concrete.
Repairs
For the previously described type of damages (5.1.1.1) the following repair procedures can be defined:
• If the defect (hollow, exposed aggregates, removal of concrete skin) is deeper than 5 mm at the
intrados, extrados and perimetric surface or deeper than 1 mm on the gasket groove, the repair
method plans to clean and level the surface with a fine mortar or liquid cement plaster. Up to 10 mm,
an extra bonding coat is not necessary when fine mortars are applied.
• For blowholes, honeycombs, deep voids, breakouts and broken edges depths indicatively between
10 to 50 mm, a repair mortar is poured in combination with a bonding agent primer. In the worst
cases, rheoplastic mortar is suggested and if the reinforcement is exposed it must be treated with a
passivating corrosion inhibitor before pouring the admixture.
• When the damage is deeper or excessively extended, if it’s repairable in terms of contract, repair
mortars are applied. If drill holes are made to take off the damaged part, the surface is filled with
grout.
For any information about mixing, application, finishing, overcoating and curing the instructions of the relevant
product supplier have to be followed.
• Grease, that can be wrongly applied on link-points for the assembly on the mould
• Grout, that can leak during casting
During inserts assembling, the grease is often used improperly, spread on inserts retention link-points on the
mould. This operation is not correct when these systems are not in direct contact with the concrete and don’t
need to be lubricated (there is the possibility that some surfaces of the insert application mechanical system
are in contact with the concrete and these can be covered with demoulding agents or greases but it’s obvious
that those surfaces in contact with sockets teeth or threads must be free of grease or demoulding agent to
allow the correct connection system).
At the beginning of the production or after a long stoppage, it’s possible that grease has been applied to protect
retention mechanical systems. If present, it must be removed before starting the segments production.
Causes
Mitigations
Grout leakages can be avoided by applying the correct tightening torque between the insert and the related
lodging. Personnel should be properly trained on inserts assembling.
At the same time inserts retaining systems on the mould should be adequate to avoid leaks, adopting O-ring
or other sealing systems can reduce the leak.
Repairs
Grout or grease inside inserts components must be eliminated without damaging the insert.
Grout can be removed with the use of acidulated water. Since inserts are horizontally oriented, it’s important
to foresee systems that allow to keep the water inside the insert for the time needed (or as an alternative place
the segment sidewise). Moreover, concrete around the insert to be treated must be covered to avoid water
reaches segment surfaces.
Greases can be mechanically removed or with the use of solvents that do not affect mechanical properties of
the insert.
Causes
Figure 14 Disconnection of an insert from the related mould lodging and its consequent absorption in the segment
casting
Defining and applying a correct tightening torque it’s the first thing to set to avoid disconnections and insert
absorptions.
If the tightening torque is not sufficient to ensure the connection, a dimensional check of the insert and its
lodging is required. Dimensional alterations can affect both the insert (if the production cycle parameters are
not completely controlled by the manufacturer) and the lodging (usually made of steel, after a x number of
production cycles can be affected by wear). Doublechecks on inserts and different lodgings are then advisable.
Repair
In case of insert absorption in the casting, a core must be drilled where the insert is positioned.
The core and the insert diameter must have approximately the same dimension (core diameter should be 10-
20 mm bigger than the insert one).
Core and insert replacement positions are defined by properly shaped jigs considering the position of other
installed inserts.
The insert is placed inside the drill hole and fixed with bicomponent resins injection.
Gaskets’ damages
During concrete casting, during and after demoulding operations and during segment handling operations, the
gasket can be damaged (Figure 15), ripped or deformed.
Possible gaskets damages can be decreased by reducing the number of segment handling operations.
Other gasket related damages are classified in relation to how the gasket is installed, if anchored or glued:
The gasket doesn’t come out properly from the segment contact zone, for this reason it sinks in the segment.
Gasket can sink along longitudinal and circumferential joints or/and at the corners (Figure 16).
Causes
Mitigations
Repairs
The repair work for this type of damage are the following (Figure 17):
1) Lift the gasket from its seat with a screwdriver and keep the gasket lifted at the correct height with
some thicknesses. Fill with the epoxy anchoring gel underneath the gasket to fix it in its correct
position.
ATTENTION: Avoid lacerating the gasket when lifting it with the screwdriver
2) Level the restored gasket with a straight iron or wooden edge.
Concrete damaging
This damage represents the concrete cracking or breaking (Figure 18) near the gasket groove without any
gasket damage.
Causes
For causes and mitigations see below at the Paragraph 5.1.1.4 Chipping sides and corner
Repairs
These damages, if possible in terms of contract, can be repaired as follows (Figure 19):
• Clean the part to recover and apply mortar, with a spatula, ensuring the incorporation of the gasket
base foot.
• Apply the appropriate restraint with a support to maintain the mortar in place during curing time.
• Clean the gasket.
This damage concerns concrete detachments around the gasket along quite extended areas (Figure 20).
For causes and mitigations See below at the Paragraph 5.1.1.4 Chipping sides and corner
Repairs
The remedial actions for this kind of damage are described below (Figure 21, Figure 22 and Figure 23):
1) Cut the gasket in the damage area, remove it and recover the groove with a proper mortar
2) Take a piece of gasket 5% longer than the damaged part. Cut the base foot of the gasket as shown
below in Figure 21
3) Apply a glue along the empty part of the groove and on the new piece. After few minutes insert the
gasket into the groove, ensuring the fitting. Be careful to match perfectly the two extremities. Remove
the extra glue.
After demoulding, damages affecting gaskets and concrete can occur together with cracks and concrete
detachments.
The causes and mitigations can be referred at the main cases reported at the beginning of this paragraph, also
see Paragraph 5.1.1.4 Chipping sides and corner.
Repairs
Repairs should be carry out starting from gasket repair, as described in the repair actions for “Concrete
damaging around a wide gasket area”
Corners deformations are represented by a mispositioning of the gasket at the segment corner.
The two corners (gasket and segment) are not aligned and the gasket corner is moved toward the
circumferential or longitudinal side of the segment (Figure 25).
Mitigations
Repairs
Gasket detachments
The gasket comes off the segments along quite extended longitudinal sections (Figure 26).
• Incorrect gluing
Non-homogeneous or insufficient distribution of the glue along the affected area
• Moisture on sprayed glue
When the glue for gasket installation is sprayed on the segment, moisture can form and a white layer
will cover the glue surface. This affects the characteristics of the gasket bonding, that results weakly
causing gasket detachments. Moisture formation occurs when the sprayed glue reaches the dew point
causing the condensation of the glue moist. Factors that can influence this phenomenon are:
• Environmental condition
Temperature and air moisture content can lead to the dew point of the glue
• Moisture in the compressed air
Using not completely dried compressed air can facilitate moisture formation on the glue.
• Collisions or rubbing
If during handling the gasket is hit or rubbed against other surfaces, the gasket can come off.
• Glue weakening
The exposure of the glue to unborn storage environmental conditions can weaken the gluing effect
until gasket detaches.
Mitigations
The following mitigation measures can be adopted to reduce this damage occurrence:
• Incorrect gluing
Gluing Personnel must be trained and must carry out a final inspection to verify the correct installation.
• Moisture on sprayed glue
• Environmental condition
If the air is excessively moist and cold, gluing might be performed in an environment at controlled
temperature and moisture (just moving the segment from the outside to the inside can be enough, for
example inside the manufacturing plant). Using spray guns, warming up the glue before spraying it,
avoid the moisture formation on the glue.
• Moisture in compressed air
Compressed air adopted for spraying the glue must be dried to remove the internal moisture.
Compressed air plant must be equipped with a drier and/or moisture removal device.
• Collisions or rubbing
Segments handling operator must pay attention not to hit or rub the handling equipment against
installed gasket.
• Glue weakening
Gluing the gasket few days before the segment can avoid glue weakening during storage exposure.
Repairs
1) Lift the gasket from the groove without causing new detachments.
2) Apply with a brush a new glue layer and wait for the evaporation of glue solvents (15-20 min)
3) Push the lifted part inside the groove again. Keep the gasket in place with a clamp for 5-10 min.
At corners areas, limited gasket sections can come off (< 200 mm). The gasket at the corner can bulge and
consequently come off (Figure 27).
Small detachments at corners are caused by a gasket mispositioning and excess that leads to a bulging effect
and then to detachment.
Causes
• Incorrect installation
Non-uniform distribution of gasket length or insufficient amount of glue at the corner
• Excessive gasket side length
Mitigations
• Corners deformation
• Incorrect installation
and
• Incorrect gasket length
Repairs
1) Apply a line of suitable glue along the detached side of the gasket
2) Push the gasket against the groove
• ≤ 25mm
• 25-50mm
• ≥ 50mm
Demoulding must take place following the vertical direction, the mould and the equipment must be aligned in
order to reduce the mispositioning error, main cause of chipping during demoulding. Demoulding equipment
with lasers can be adopted to facilitate the operator in the alignment operation.
Excessive concrete cover thickness is one of the parameters that can affect the segment surfaces resistance.
Mitigations
As already said, mispositioning errors can be avoided increasing the gantry crane lifting height at demoulding.
The use of hand pumps and rugs allows to reach all the surfaces in contact with concrete.
Dabbing demoulding agent stagnations with sponges is fundamental to avoid alteration of concrete mechanical
properties and consequently chipping occurrence.
The reinforcement cover thickness must be well defined, monitored and ensured with spacers or other devices
during the production phase.
In order to increase corners and edges strength, specific fiberglass or synthetic reinforcements can be adopted
at corners and fiberglass or plastic material protections at edges (especially at the extrados).
As an alternative to this punctual reinforcement, a distributed one can be adopted, for example SFRC.
A good practice is to minimize the number handling operations avoiding collisions and chippings.
If all the mitigation measures aren’t enough to avoid the damaging of the segment the advisable repair
procedures for different damages’ depths are:
• ≤ 25mm
− good surface cleaning, possibly with compressed air not to have residuals or unstable parts
− application of an epoxy adhesive on the construction joint on which a one-component
thixotropic cementitious mortar (it must harden without shrinking) will be led.
• 25-50mm
− surface cleaning until a solid, resistant and coarse base is reached
− application of an epoxy adhesive on the construction joint on which a one-component
thixotropic cementitious mortar (shrinkage-compensated, sulphate-resistant and with suitable
hardening timings) will be led.
• ≥ 50mm
− surface cleaning until a solid, resistant and coarse base is reached
− application of an epoxy adhesive on the construction joint on which will be led a ready-mixed
mortar composed by highly resistant cements, selected aggregates, special admixtures and
synthetic fibres (when mixed with water becomes a highly fluid mortar, suitable for pouring
into formwork and its workability lasts for about 1 hour).
Moreover, during ring installation, when a segment is positioned close to the one already installed, the gasket
of the segment to be installed can be expelled from the longitudinal side of the segment. In addition to the
expulsion, the gasket section is also stretched and compressed (Figure 29).
INSTALLATION INSTALLED
OF THE RING RING
Root causes during handling are mainly due to collisions and rubbing against handling equipment, inadequate
to preserve gasket integrity.
Reducing the number of handling operations or adopting proper handling system that do not damage gaskets
are the two principal actions to be taken to reduce the damage occurrence.
Mitigations
Repairs
As far as gaskets and concrete repairs are concerned, refer to Paragraph 5.1.1.3, even if, when gaskets
expulsions occur, it is better to adopt preventive measure than remedial actions (see mitigation measures
described in this paragraph). If the gasket expulsion compromises the water tightness of the segment, resin
injections should be performed to restore the sealing.
During handling operations, the segment can be damaged at corners and/or edges.
Sharp corners are more exposed to damages, for instance, during erector segment rotation phase, where the
space is narrow and the possibility of collision is high.
Minimizing the number of segment handling operations can help to reduce damages occurrence.
For damages repair procedure, considering the segment’s manufacturer quality plan for repair works, the
tunnel lining designer’s recommendation and the adjustments for the relevant works on site, please refer to
the final part of Paragraph 5.1.1.4.
During installation, if the jack plate comes over the gasket, breaks and detachments of concrete can occur
between the gasket and the edge (Figure 31).
Causes
Mitigations
For damage repairs refer to Paragraph 5.1.1.4. The repair action can be difficult if carried out in presence of
water, debris or narrow spaces.
This damage represents the formation of cracks with or without concrete detachment at intrados and/or
extrados corners areas.
• Collisions
• Concrete mechanical properties at the corner
Corner zones, as already said for edges, are segment extremities where concrete can have different
mechanical properties. Concrete is weaker in these areas, even because there is no reinforcement
out of the concrete cover zone.
• Gasket loads incompatible with concrete mechanical properties
The gasket, when compressed, transmits to the segment area a reaction that stress the concrete. If
this reaction force is higher than concrete ultimate strength, concrete breaks.
The gasket must be properly designed and manufactured in relation to its use, defining the geometry
of the section and materials to use for straight and corner areas.
• Compressibility of gasket corner
The gasket corner represents a discontinuity section for the gasket functionality itself since the
transversal section is different from the longitudinal one.
It can happen that the gasket joint at the corner is not properly designed and manufactured for its
specific use.
In this case, when gaskets are compressed during installation the loads applied on the concrete can
cause concrete breaks.
Mitigations
• Collisions
To reduce collisions occurrence the following actions can be applied:
− Foresee enough room for handling inside the TBM
Repairs
Considering the segment’s manufacturer quality plan for repair works, the tunnel lining designer’s
recommendation and the adjustments for the relevant works on site, please refer to the previous Paragraph
5.1.1.4 methods (Figure 33).
Thrust phase
Gasket compression from jacks’ plate
During thrust phase, TBM jacks’ plates compress segment gasket (Figure 34).
Loads applied by TBM jacks lead to a reduction of gaskets water tightness capacity because, after the
compression, this property can’t be completely recovered.
Causes related to this damage can be reconducted to the interaction, and its design, of TBM and Segments.
The necessity of adopting TBMs and moulds for/from different projects can be a primary cause.
Segmental rings and TBM jacks design must include considerations on the presence of segment gaskets that
should not be overcome by TBM jacks.
If these considerations are not carried out during the design phase, it’s possible to reshape jacks’ plates to
avoid the gaskets compression.
If the compression cannot be avoided with reshaping, another solution can be to use specific segments gaskets
whose water tightness capacity do not deteriorate under compression.
This damage can be repaired if punctual and accidental. Whenever it is repeated at each following thrust
phase, jacks’ plates must be reshaped.
Causes
Excessive gaps and offsets are due to the following possible causes:
• Pull-out resistance
The pull-out resistance of the connection system must counteract the tendency of the section to slide
from the connection system itself. The connection system must therefore contrast the following
forces:
− Reaction of the compressed gaskets between the segments
− Bending moment generated by the weight of the segment installed, hanging on the previous
ring
• Shear resistance
The shear strength must bear the stresses caused by:
− Segment weight
− Cross-passage openings or other discontinuities within the ring.
The pull-out resistance is closely linked to the gap values obtained on the assembled ring. In case of insufficient
pull-out resistance, excessive gaps may occur. Therefore, the connection system must offer the highest
possible pull-out resistance at minimum gap values and its design must be conceived not to allow any space
between neighbouring segments, as these would add up to the gaps due to the assembly of the ring,
contributing to increase their size.
At the same time, the stresses generated by the reaction of the compressed gaskets must be as low as
possible. The seal must therefore guarantee the maximum hydraulic sealing with the least possible
compression reaction.
Any gap higher than 5 mm and any offset (lip sealing or step) higher than 10mm should be recorded and
monitored.
Causes
The infiltration of water is due to the insufficient hydraulic seal of the gaskets which are not able to completely
waterproof the tunnel. Also, there may be leaks from fissures affecting the entire thickness of the segment.
Mitigations
When this type of infiltration occurs, it is necessary to change the type of gasket used and / or the connection
system. The waterproofing action is a direct effect of the joint action coming from the gasket and the connection
system. Laboratory tests of the connection and sealing system, also with gap and offset allowance are useful
for the selection of the latter in the tunnel design phase (see Chapter 7).
Repairs
Every type of concrete damage or ring erection imperfection that cause water seepage inside the tunnel
through the joints or from the bolts’ sockets must be repaired to guarantee the waterproofing of the lining and
comply with all the requirements defined within the contract.
Prior to any type of repairing, the surface must be cleaned and dried. It’s necessary to stop any leakage
affecting the surface to be repaired.
A local plastering with silicon and previous cement water-plug should be applied.
For small and punctual leaks or for a temporary sealing, polyurethane resins should be injected within the
affected joint behind the ring. Polyurethane resins guarantee a fast reaction with water and its expansion
ensures the filling of all the remaining voids, avoiding the resin wash out. This gives time to the following
application (if needed) of acrylic resin to be injected without running waters.
In case of leak spread over more rings is envisaged to evaluate the possibility of injecting a water/cement mix
or bi-component grouting (grout-silicate) within the primary grouting and the lining extrados to fill any
unexpected void gap. After that, acrylic or epoxy resin injections are performed.
Injections from bolts’ sockets are possible with the use of ad hoc packers that fit the bolt hole.
Furthermore, the use of HSR (High Sulphate Resistant) cements, with high resistance to sulphates, which may
be present in the substrate outside the tunnel or, in the case of a tunnel for pipelines, in the fluids that flow
inside the tunnel, allows to reduce and / or eliminate the damage to surfaces exposed to contact with
aggressive water.
If the use of such HSR cements is insufficient, then dressed concrete coatings may be used.
The accidental event of a fire is related to the common causes of fires in the tunnels.
• Vibration
Excavation activities, TBM movements, other activities can induce vibrations that generate unscrewing
of bolted joints;
• Low tightening torque
Bolted joints must be tightened with the correct tightening torque. Excessive torque can damage the
joint or reduce its ability to react to stresses that tend to open the joint. Poor tightening torque may
cause unscrewing of bolted joints.
In case of unscrewing the bolts connecting the segments, the first mitigating action to be implemented is the
redefinition of the tightening torque to be applied. If this correction is not sufficient to eliminate the defect,
washers or anti-unscrewing accessories can be used.
Table 2 Classification of segment damages during construction life cycle (modified from [8]).
• Defects due to inserts presence: through going cracks between erector gripper pockets and grout
holes;
• Defects due to demoulding: cracks due to an incorrect demoulding process;
• Defects due to handling: cracks due to an incorrect handling process;
• Defects due to overturning: cracks due to an incorrect overturning process;
• Defects due to storage: cracks due to an incorrect storage process.
It is worth to note that, before ring installation, cracked segments (or not repaired) are generally not allowed to
be delivered to the TBM for erection. Different project specifications and acceptance criteria are defined
depending on the crack width and position (extrados, intrados, joint, gasket groove and pocket) and on the
impact on the segment integrity.
Causes of damage
During this first phase, cracks are generally stress-induced during demoulding, handling, overturning and
storage operations. Defects due to inserts presence: through going cracks between erector gripper pockets
and grout holes. Cracks due to type of structural damage are identified for their width opening: less than 0.2
mm, between 0.2 and 0.3 mm, more than 0.3 mm
Mitigation actions
Demoulding, handling and overturning phase
Usually, during demoulding phase the contractor tends to prefer to demould the segment early to increase
production, but an early demoulding means low concrete strength. It’s worth considering the following
suggestions: 1) the minimum concrete strength to be specified together with the process of demoulding; 2) a
correct analysis approach requires a factor of safety of 1.5 to account for adhesion, and it considers the
segment as a simple beam subjected to bending moment (verifications performed to be below the cracking
moment).
Storage phase
Once removed from the mould, segment needs to be stacked waiting for supply to the tunnel. At this stage,
usually specifications require a tolerance associated with stacking (Figure 38). In the ideal scenario all the
segments would line up, and all the load is transferred to the ground. The worst case occurs when segments
are not aligned in the designed stack position and their self-weight is transferred onto the bottom segment. For
this reason, a good control on segment stack alignment during storage stage is an essential action to prevent
damages.
Restoring actions
5.2.1.4.1 Defects due to inserts presence
Specifications should state which damage could be repaired, planning actions and methods that could be used
at this purpose.
Reject damages effecting gaskets, cracks through the segment, or exposure of reinforcement.
Usually damages impacting the effectiveness of the gasket groove or the bearing surface should
Reject not be repaired (unless very tight tolerances can be obtained in repairs). It is worth to note that
gaskets require tight tolerances to be effective, and if the bearing surfaces have a high point that
attracts all the load, the repaired section will suffer damage.
Repair chips or edge damage not effecting bearing area, surface damage along face of segment.
Repair Indeed, superficial damage (intrados/extrados) should be repaired, provided integrity of
reinforcement (if present) is not compromised.
Useful references can be found in [2], [5], [7], [66], [32] and [68].
- Cracks at extrados, gasket groove and area between gasket groove and extrados are recorded,
measured, repaired and monitored.
· The surface must be cleaned, shaved with a proper sandpaper and cleaned again via moistening.
Once the water is absorbed, a water-repellent one-component cementitious skimming mortar (with a
fine-textured, normal hardening and high-resistance special binders) is applied.
Segments with cracks equal or higher than 0.3 mm or wide through going cracks, are often rejected to avoid
the occurrence of any impact on the segment’s structural integrity during the following phases (see for example
Table 4). If not rejected, a special concept is applied: the surface is cleaned eventually with compressed air
then is deepened to create a hollow to fill with epoxy resin. The repair must guarantee the waterproofing. If the
structural integrity is compromised, the segment is rejected.
Allowed for
installation
Damage Criteria and measures 1)
yes not
Cracks through
Not restorable X
the whole section
Surface < 200 cm2 Remove the gravel nests with a hammer, then apply ah
X
or depth < 5 cm adhesive bridge and restore 2)
Gravel nests
installation
Length of the damaged
edges < 30cm − Give the first layer of anti-rust paint (cement- X
Damage of based) to the exposed in-traction or flexed
corners and edges reinforcement
− And/or measures in order to meet the requirements
of the waterproofing substrate
Length of the damaged
Not restorable X
edges > 30 cm
yes not
− Restoration 3)
Air bubbles X
− In case of frequent passing: check and
Air bubbles
Table 4 from Galleria di base del Ceneri “Segments production – technical control”
Note:
1)
For mitigation actions, see [65].
2) Rehabilitation of damages and gravel nests:
− Remove any detached parts
− Make the reinforcements free
− Make the connection to the intact concrete
− Apply the cement-based protective paint against corrosion on the reinforcements’ surface
− Rehabilitation of the concrete system in accordance to the needs of the manufacturer
− Adhesive bridge
− Application of mortar to reprofile in thickness (maximum 20mm)
− Grouting
3) Rehabilitation of the cavities from air bubbles:
Examples of damages during ring erection are given in the Figure 40 and Figure 41.
Figure 40 Example of segments erection left and damages during ring erection right (27).
Causes of damage
Cracks can be due to incorrect handling and installation of the ring. Cracks due to type of structural damage
are identified for their width opening: less than 0.2 mm, between 0.2 and 0.3 mm, more than 0.3 mm.
Mitigation actions
Some mitigation actions aimed to reduce cracks and fissures during handling and installation of the ring are
given in terms of: corner shape, length of the ring, number of segments per ring.
Furthermore, among the mitigation actions, the check of dimensional tolerances (Limit deviation -Table 5) can
be considered:
The segment corners are always the critical point in the assembled segmental ring [7]. The risk of leaks and
of spalling is greater between the corners than at any other point. Against leakage particularly strong
compression tends to help, against spalling as little compression as possible. When designing the segment
corners, it must be considered that through the vulcanization process during insertion of the corners, material
can easily get into the cavities of the extruded profile, unintentionally making it more rigid locally. In addition,
there is usually some excess material on the segment corners created during assembly, which also increases
the restoring force generated.
- 1.50 m and 2.20 m for big rings (diameter >10 m and big radius of alignment bends);
- 1.25 m and 1.60 m for small rings (diameter ≤10 m and small radius of alignment bends).
Furthermore, the choice of the adequate length of the segment/ring is influenced by different and sometimes
opposite needs such as time of excavation, weight of the single segment, risk of damaging the segments while
handling, geometrical compatibility with the rear of the TBM while the ring is coming out in the condition of the
minimum radius of curvature.
Figure 43 Example of number of segments with the internal diameter of the ring (27).
Furthermore, to reduce the risk of damaging during the ring assembling and ring erection, some considerations
should be taken into account during these activities, as reported in Table 6.
Clear responsibility, never interfere in decisions given by The dimensions of the segment and of the
others back-up are inter-related with respect to the
movements (rotation and translation) that the
Order “STOP” at the end of each movement segment itself must undertake
The order "STOP" is obligatory and it must not be The segments can arrive to the erector both in
discussed the upper and in the lower part
Table 6 General safety considerations to prevent crack of rings during ring assembling and erection (27)).
An example of good practice in rotating the segment near the erector and sequence for ring assemblage is
given in the Figure 44.
Restoring actions
Figure 45shows an example of repair criteria for cracks and fissures.
Thrust phase
Description of damage
The concentration of stresses induced by the thrust cylinders during the TBM advancing coupled to a poor
segmental design and manufacture can lead to:
5.2.3.1.1 Splitting / bursting cracks (transversal cracks perpendicular to the thrust force)
In most cases, cracks are < 0.2 mm and are circumscribed around the contact between surface and concrete
cover zone. Sever damage can invalidate the waterproofing (Figure 46).
Figure 47 Longitudinal cracks along the tunnel and spalling cracks (27).
Consecutive segments can be affected, in curves or where the contact between the two adjacent segments is
not continuous or planar.
Causes of damage
Possible causes of these damages are:
interaction
Tail shield gap should be more than 30
between a) Tail gap around the tail and
mm all around the ring, while the axis
TBM and
of thrust cylinders (rams) should be
segmental
proximate to ring axis.
ring.
b) rams (28).
Table 8 Causes of segments’ damage during thrust phase.
Mitigation actions
Cracks of segmental linings due to the high compressive stresses developed under the jack shoes at the
contact surface due to TBM advance, are common. Experience gained in the past suggests that cracks could
be prevented by having high care in designing segment flanks in order to 1) minimize breakage at their edges
and 2) not changing the durability of the works due to water inflow, corrosion of reinforcement, etc.[1].
Damages and cracks during the TBM advance can already be mitigated during the assembly phase. Indeed,
according to [7], inaccuracies and a not perfect alignment of adjacent segments during the ring assembly
phase, can result in a tensile stress and damage to the segments during the TBM advance.
a) b)
Figure 50 a), b) Thrust of TBM jacks on segments. c) Spalling and cracking of concrete cover. d) Damage from
displacement in the ring grove. (AFTES recommendations and (26)).
At this purpose, two considerations can be done to avoid the above-mentioned problems:
• detailed geometrical design of large flanks in the contact zone must be aimed at guaranteeing the
highest possible strength;
• in the same time, stresses acting on the contact surface must remain acceptable also under
unfavourable loading configurations (eccentric loads from TBM thrust in curved alignments etc.).
According to [7] and [1], high surface pressures developed under the jack shoes due to TBM advance must
be verified by performing a difference between standard values of the jacking forces and extraordinary jacking
forces for unusual control movements (maximum allowed thrust, maximum allowed eccentricity or both) by
considering different design situations with the respective safety factors.
Restoring actions
For repair remedial actions usually taken after the ring has been built, please refer to the relevant Paragraph
5.2.4 for Grouting and Service Phases.
Small pieces of concrete, up to 20mm in size, are gradually and non-violently dislodged from the surface during
the early phase of the fire. In the case of surface spalling, the degradation of the concrete is relatively slow
and involves the dehydration of the cement matrix followed by the loss of bond between aggregate and matrix.
The sloughing off, corner break-off, occurs at edges and corners of concrete elements during the latter stages
of the fire when the concrete has cracked and weakened.
Explosive spalling is the most serious and dangerous form of spalling that occurs during the first 20–30 minutes
of a fire when the temperature in the concrete is in the range of 150-250°C. Very large pieces of concrete can
be violently ejected for several metres. As a fresh concrete face is exposed to fire, progressive explosive
spalling deep into the concrete thickness occurs, threatening the structural integrity of the construction.
Figure 52 Fire damage in Channel tunnel (left) and in Cracks in the Storebelt tunnel (26).
Causes of damage
Possible causes for this kind of damages can be due to loss of connector and bolt performance, spalling during
fire, chipping of sides and corners, leaks from cracks on segments, cracks (wet or dry), cracks on lining
Mitigation actions
Some rules in terms of concrete cover, reinforcing spacing and minimum reinforcement must be followed to
prevent cracks on lining, chipping of sides/corner and leaks from cracks on segments as given in Table 9.
Concrete with
Fibres melt at 160°C forming
polypropylene
interconnecting passages for
fibers
vapour pressure to escape.
(b)
Table 10 Mechanism and examples from fire testing on concrete sections. Note: (a) loss of section of normal concrete
exposed at fire and (b) concrete with polypropylene fibres (26).
Restoring actions
5.2.4.4.1 Loss of Connector and Bolt Performance
The performance of connectors and bolts can be fundamental for the correct tunnel alignment and structural
capacity. A loss of the inserts performance can lead to segment sliding, ring rotation and tunnel eye
deformation. To avoid this kind of induced damages, ad hoc structural reinforcements can be installed locally.
Some examples are:
Depending on the entity of the damage the following restoration products should be sequentially applied on
the surface:
- Bonding Primer and reinforcement corrosion protection (by a brush to fill all unevenness).
Deep spalling and broken edges at the crown, where steel reinforcement is visible must be repaired following
a special concept, described underneath. If the steel is not exposed repairs could not be required.
For any kind of damages where the concrete cover has been severely compromised, two solutions can be
suggested depending on the damaged area (see Table 11).
Broken corner/edge or spalling surface < Broken corner/edge or spalling surface >
Cases
0.10 m2. 0.10 m2.
Surface preparation (as previously Surface preparation (as previously
described) described)
Injection through a fixed formwork of a quick- Injection through a fixed formwork of a quick-
hardening cementitious mortar for repairs up hardening cementitious mortar for repairs up
Solutions
to 150mm of thickness, prior embedding to 150mm of thickness, prior embedding
stainless-steel rods with resin in sound stainless-steel rods with resin in sound
concrete and a stainless-steel nut with concrete and a stainless-steel mesh fixed at
washer at the free end of the rod. the rods.
Table 11 Suggested solutions depending on the damaged area
Injections of acrylic or epoxy resins are advisable. Acrylic product can successfully be used to inject cracks
and fissures since the cracks in the lining are not structural.
A first injection of acrylic or polyurethane resin is made behind the ring to fill the possible voids not completely
backfilled. Then packers will be drilled and placed in staggered spacing from each other and at a certain
distance and inclination from the crack to intercept it. It’s important to drill where the predefined lining markers
are not to catch the rebars. A preliminary water injection is made to wash the crack. This step will end once
the clean water will come out from the crack.
After this phase, the acrylic or epoxy resin will be injected through the same packers at low pressure (action
to be taken also for dry cracks with width higher than 0.2 mm).
All the packers are removed once the leak is stopped and the holes are closed with a water-plug mortar.
If the leak is not conspicuous a crack surface cleaning and a liquid mortar filling of the opening can be adopted.
An example of bending tensile cracks in the absence of correct annular grouting is shown in Figure 55 and
Figure 56.
6.1 Introduction
The segment lining design is provided with consideration of the following key elements:
a) Clearance of the tunnel to meet the project functional requirements, considering geometric tolerances;
b) Review of the tunnel construction methodology and type of lining structure considering interactions
between multiple drifts, adjacent excavations, geotechnical and hydrogeological conditions (including
hazardous substances such as gases), third party and environmental impact;
c) Estimation of the tunnel lining structural types and thickness in relation to concrete grade;
d) Feasibility study structural integrity of the tunnel lining under the expected critical loading conditions
(e.g. Under high internal pressure for water tunnel);
e) Identified project-specific technical challenges;
f) Tunnel-to-tunnel junctions, such as cross passages;
g) Connections with other underground structures such as portals, station box and shafts;
h) Development of tunnel lining design concepts.
The geometrical and structural design of the segmental lining is essential to evaluate the risk mitigation
measures. The design includes structural elements, gaskets, sealing materials and the ability of all the
materials to resist the degradation due to ground, the groundwater and the environment throughout the design
working life.
Fiber Reinforced Concrete (FRC) was adopted in several tunnel projects (5) [22]. The most important benefit
due to the inclusion of fibers is the noticeable increase of the post-cracking residual tensile properties.
Moreover, the use of fiber reinforcement enables an improvement and a boost of the industrialized production
of precast tunnel segments.
Among the current national and international standards regarding the design of FRC tunnel linings (see
Chapter 3), it is worthwhile mentioning the ITA Report n.16 (5) and fib bulletin n.83 [22]. Both documents are
based on the performance approach suggested by MC2010 [21] for considering the post-cracking residual
strengths exhibited by FRCs. The former presents general rules, principles and procedures for FRC tunnel
linings with special emphasis to the requirements and loading conditions of these elements. The latter also
provides a detailed design procedure based on on-going research or recently developed research.
Design conditions
In current Eurocode [28] design scenarios are defined as a series of circumstances or conditions that the
tunnel lining might experience during its life. These design scenarios are classified as transient, persistent,
accidental or seismic (see Table 12):
• Transient: refers to temporary conditions applicable to the structure, e.g. during construction or repair;
• Persistent: refers to the conditions of normal use;
• Accidental: refers to exceptional conditions applicable to the structure or to its exposure;
• Seismic: refers to conditions applicable to the structure when subjected to seismic events.
• The construction of a stable lining, for both the short and long term, considering all the foreseeable
load.
• Longitudinal continuity with respect to the tunnel alignment.
• Fast and safe assembling in the rear part of the TBM and under the protection of the shield.
The geometrical dimensioning includes the definition and validation of the following key elements (Figure 57):
Regarding the thickness of the lining, is mainly related to the normal ring force (hoop-force) occurring in final
stage (embedded in ground condition) and the concrete grade adopted. In this regard a kind of rule of thumb
regarding the ratio between internal diameter and thickness, around 20, was early reported in [1].
• the tunnel linings reinforced only with fibres are the 71% and the remaining 29% are a hybrid
solution (fibres and conventional rebars are used);
• the solution with fibres only has been mainly used with diameter less than 8 m, even though in three
case studies with large diameters the solution with fibres only was successfully adopted. The hybrid
solution has generally not been used for lining having very small diameter (less than 4 m);
• it seems that the hybrid solution was used with ratio internal diameter/thickness higher than 20, even
though it is worthwhile noticing that is a simplified ratio which does not provide any information on
issues such as, for instance, the TBM ram loads or the expected ground conditions.
The assembly process generally involves the construction of the ring starting from the first segment, and
finishing up with the key element, the k-segment, whose presence is always foreseen and is, of course, placed
at the opposite side of the ring that has the counter k-segment (Figure 58). The k-segment has a trapezoidal
shape with the largest side facing the front of excavation and it can be smaller than all the other elements. In
order to install the key segment, it is necessary to have two side-key segments with inclined sides to
correspond with the shape of the key segment.
The current tendency is to use the universal ring systematically in straight and curved parts of the tunnel. This
approach allows the horizontal and vertical trend of the alignment to be followed without the use of any other
special elements and to correct any deviations made by the TBM during advancement. In addition, the current
tendency is to define the key segment with similar dimensions of the other segments.
Geometrical tolerances
Due to the needs of a very accurate coupling among the various segments to compose a lining ring and of
placing the rings following a sequence compatible with the alignment to form the complete tunnel lining, the
geometrical tolerances of the pre-cast segments are a very important issue and this is especially true for
mechanized tunnels lined with universal segments. The order of magnitude of the relevant tolerances ranges
between 0.1 mm and 1 mm, depending on the specific part of each segment considered and on the dimension
of the ring.
The moulds shall be designed and manufactured with the high precision normally adopted for steel structures,
and the inner surfaces of the moulds should be finished by a machine tool.
The direct geometrical check of an assembled ring is made just at the beginning of the segment production
process, at the prefabrication plant where the first few sets of segments from the trial production are assembled
to form 2 or 3 rings, laid down on a levelled platform one above the other (see Chapter 7).
Components
The single segment is composed of different elements and particular geometries that protect from failure and
make their assemblage easier:
• The pockets should be large enough to allow the head of the bolt and the pneumatic wrench to be
easily inserted; and the minimum distance from the bolt axis to the walls of the pocket should be at
least 60 mm.
• The slot side of the pocket should have a conicity of at least 1°.
• The bolt slot in the segment that houses the nut should have a compatible conicity so that the
insertion of the bolt into the tunnel will be well guided and fast.
• The bolt axis should pass through the center of the segment.
• The distance between the end part of the nut and the extrados of the segment should be sufficient to
not interfere with the lining bars and, therefore, as a minimum, it should be 1.5–2.5 cm more than the
cover side.
The different types of connection system and guidance to their selection is given in [1] for the design, sizing
and construction of precast concrete segments installed at the rear of a tunnel boring machine.
− Select a suitable geotechnical model and choose representative constitutive law and strength
criterion for the soil or rock mass involved and hydrological parameters;
− Select a suitable method to model the structural behaviour of the tunnel;
− Select a suitable method to simulate the interaction between the geotechnical model of the soil or
rock mass and the lining model.
The main issues of the tunnel lining design model are listed below.
Numerical approaches attempt to satisfy all theoretical requirements, include realistic ground and lining
constitutive models and incorporate boundary conditions that more accurately simulate field conditions.
Approaches based on finite differences (FD) and finite elements (FE) methods are most widely used for tunnel
lining design when the continuum or equivalent continuum models can be assumed to represent the soil or
rock mass. These methods involve a computer simulation of the full stress path from green field conditions,
through to the construction, and in the long term. Other methods such as boundary elements (BE) method or
the discrete elements (DE) method can be more suitable in certain cases such as analysis of small-scale
features or extremely complex geometries, the latter being used when a discontinuous model has to be
assumed for the soil or rock mass.
Simplified methods such as bedded beam spring model can be adopted (Figure 59), since they are able to
capture the lining internal actions even though the interaction between lining and surrounding ground is
simulated by means of springs. The lining can be modelled through beam elements or plates (Figure 60). In
case of beam elements typical internal actions like bending moment, shear and normal force are retrieved,
whereas in case of plate elements (Figure 60) a more comprehensive evaluation of internal actions can be
done by considering bending moments, shear in two directions as well as torque.
When the tunnel ring has more than four radial joints, the designer can consider the reduction of the ring
stiffness. The following equation can be used as a first method of determination of the reduced ring stiffness:
Figure 61 Reduction factor for fictitiously reducing the flexural stiffness of the whole tunnel ring by indirectly considering
the effects of longitudinal joints
According to the design conditions (transient, persistent, accidental, seismic) mainly introduced in Paragraph
6.1.2, the following main structural verifications have to be provided (Table 13).
Segment
Demoulding Stacking
casting
Figure 62 Construction stage of the segmental lining and main design verifications
Extraction
handling, overturning
prefabrication factory
i t ll ti
storage
tation,
B
Overturning under to effect of dynamic action
Contact with
TBM
TBM advancement (thrust phase)
(interaction
Examine the segments in terms of contact stress results
between
from TBM thrusting force, taking into account the effect
jacks, rams
of the load eccentricity
and
Segmental
B ring)
Induced
tension from
rams of
Examine the segments in terms of induced traction
jacks (due
stresses induced by rams
to effect of
thrusting
force)
Grouting and Service life
All the structural checks must be carried out also to guarantee the durability requirements.
Beside recommendations or guidelines devoted to the design of FRC tunnel linings [20] [24] [25], it is
worthwhile noticing the principles reported in (5). In the latter the following general aspects are clearly
underlined:
- splitting stresses, which occurs as result of the diffusion of TBM high concentrated forces into tunnel
segments, are better resisted by a spread reinforcement such as fibres; of course, it must be always
checked that a spread reinforcement alone can resist the actual stresses. In fact, in the post-
cracking stage, splitting stresses can be re-distributed and diffused along the segment depth by
exploiting residual strengths provided by fibre reinforcement;
· bending stresses are generally better resisted by localized reinforcement such traditional steel
reinforcing bars (rebars). In the latter case, it is worthwhile noticing that the actual flexural demand
occurring in the segments in the final stage (embedded in ground condition) and temporary stages
(such as de-moulding, storage and positioning by the erector) as well as the FRC post-cracking
strengths have a key role in a partial or total substitution of traditional curved steel rebars. Localized
traditional reinforcement is also recommended in case of high in plane-bending stresses (in the
plane of the segment), which may occur in presence of some irregularities occurring during the TBM
thrust phase (e.g. gaps between rings);
The fibre type or content are not complete information for design purposes; the key factor is the quantification
of post-cracking strengths that a given fibre content or type of fibre can provide in a specific concrete matrix.
The verification for the extraction from the mould defines the minimum amount of concrete strength of the
segment to be extracted without cracking (Figure 63). The check consists in the comparison of the maximum
bending moment applied in the extraction with the first cracking moment Mcr. The extraction can be modelled
with standard static schemes considering the dynamic effect of adherence. The other verifications are carried
out similarly to the extraction from the mould (changing the static scheme) always checking that there isn’t
cracking during operations.
Regarding FRC elements, [22] confirms that it is desirable to avoid cracking in this stage even though fibre
reinforcement is not exploited in un-cracked state. The same approach is suggested by (5); in addition, it is
also underlined that a minimum bearing capacity must be provided to avoid collapse. In this case, the post-
cracking residual properties of FRC will be exploited but with aim to guarantee the safety of workers.
In final storing to avoid cracking phenomena, particular attention should be devoted to the position of the
segments on supports. In this regard, [20] suggests some maximum admissible eccentricities between
supports (misalignment of the supports) of about 10 cm.
(a) (b)
(c)
Figure 65 TBM thrust configurations: German (a), French (b) and Japanese (c) configurations (10)
The structural verifications of this load condition are generally developed according to two main different level
of investigation:
• local segment behaviour: generally corresponding to stress concentrations under and/or between
TBM rams;
• global segment behaviour: normally related to the distribution of the highly-concentrated applied
loads throughout the segment.
To prevent damage of precast tunnel segments the local behaviour as well as the global one should be
carefully considered. Consequently, special attention will be devoted to the former in Paragraph 6.4.4.1, while
the latter will be deeply described in Paragraph 6.4.4.2.
The local behaviour is mainly related to transverse stresses under the TBM thrust shoes and between them.
To the contrary, the global behaviour is strongly affected by the adopted TBM thrust shoes configuration and
rear supports layout (Figure 65).
In fact, with regard to local behaviour, the spreading of the thrust forces into the segments leads to a disturbed
region (D-region) that has to be carefully analysed since transverse tensile stresses (defined as splitting or
bursting stresses, Figure 66, Figure 67a) occur perpendicular to the loading direction. Consequently, splitting
cracks (due to transverse tensile stresses) can occur under the TBM rams. Moreover, spalling cracks (due to
transverse tensile stresses occurring between the TBM thrust shoes) could occur between the TBM rams.
With reference to the global segment behaviour, the possible no-perfect arrangements of TBM thrust shoes
as well as no-perfect contact with the previous assembled ring may cause damages.
With regards to FRC elements, the roles of these possible irregularities are pointed out in [22], (5) and [20].
Local verifications
− tensile transverse stresses (defined as splitting or bursting), perpendicular to the direction of the load
P, occur;
− tensile stresses in the “dead corners” near the loading area (generally defined as spalling stresses,
Figure 66). It is worthwhile noticing that these stresses in case of two adjacent high concentrated
loads, correspond to the spalling stresses occurring between two adjacent TBM rams.
The amount and direction of these stresses can be evaluated according to well-known elastic solution
proposed by Iyengar (6) and cited by Leonhardt (7); based on this solution the bursting transverse stresses
along a longitudinal axis centred with the applied force (Figure 67a).
This approach can be used for evaluating, as a first approximation, the risk of incipient cracking phenomena
at SLS since the maximum tensile bursting stress can be evaluated: this issue is very important since it is
desirable to avoid cracks when service load is applied by the jacks. It is worthwhile noticing that also the global
resultant tensile force (Z) can be calculated, which represents basically the local bearing capacity required to
fulfil equilibrium in the direction perpendicular to the applied load.
A local strut-and-tie model can be adopted in order to directly evaluate the resultant transverse tensile force
under the point load due to the jack (Z, Figure 67b, Mörsch (8) as quoted by Leonhardt (7)). It is well known
that this approach is directly focused on the bearing capacity, since it is a solution only based on equilibrium
equations. Nevertheless, this simplified approach can be also applied after cracking. Hence, it can be generally
used for designing the necessary local reinforcing bars for withstanding to these tensile stresses after cracking.
In fact, designers generally estimate the total transverse bursting force “Z” (Figure 67b), by means of the
following relationship:
a
Z = 0.25 ⋅ P ⋅ 1 −
d
In the aforementioned equation, P corresponds to the applied load by the jack and the ratio a/d basically
governs the amount of expected bursting stresses (as depicted in Figure 67a). Note that similar relationships
are reported in recommendations concerning precast tunnel segments [1] [32] and [7].
Leonhardt (7) suggested a simplified approach for estimating the resulting transverse forces in case of a 3D
D-region, basically based on the superposition of the previously mentioned 2D solutions: two transverse forces
(Zz, Zy) representing the resultants of the splitting stresses according to two orthogonal directions are
introduced (Figure 68a and b).
As a first approximation, the approach proposed by Leonhardt (7) can be used for predicting the resulting
transverse forces in tunnel segments at SLS by referring to local reference system illustrated in Figure 68b
(before cracking). Similarly, the bearing capacity can be also investigated by assuming two local strut-and-ties
models corresponding to the radial and tangential direction of the tunnel segment (as a simplified approach
after cracking).
Figure 67 a) Distribution of transverse stresses due to point load (6), b) strut-and-tie resistant mechanism (8).
Zy
Zz
a) b)
Figure 68 Scheme of the superposition of principal compressive trajectories (two-planes) in presence of a 3D D-region
(7) b) 3D D-region as the sum of two 2D contributions
To better evaluate the local splitting behaviour under the TBM rams, numerical models (FEM) can be used
(Figure 69). In fact, the analytical approaches previously mentioned, are generally probably more conservative
even though they are very useful for a preliminary evaluation and as a reference for more advanced FEMs.
The advanced modelling enables a better understanding of the phenomena leading to a better control or
avoidance of possible damages. The numerical analyses can be developed within the linear elastic behaviour
of concrete or they could be also carried out by including the actual post-cracking tensile behaviour of concrete,
especially in case of Fiber Reinforced Concrete (Non-Linear Finite Element Analyses, NLFEA).
To avoid the risk of damage in the local verification under the TBM rams, possible unfavourable scenarios are
recommended to be considered:
The latter are generally aspects which are desirable to include in the process of structural verifications to avoid
damages as much as possible.
Regarding the local behaviour under TBM thrust shoes, in (5), it is stated that, since cracks due to splitting
stresses remain relatively small, also FRCs having post-cracking properties corresponding to class “2e”
(according to the performance classification reported in [21]) can be probably satisfactory. Nevertheless,
analytical or semi-empirical well-known relationships are still not available for the precise prediction of the
bearing capacity as well as the expected splitting crack width in FRC elements. Schnütgen (11) proposed a
simplified analytical approach based on a constant distribution of post-cracking FRC strengths as is similarly
currently reported in current [20]. The issue is still under discussion in the scientific community. In fact, in recent
[22], no specific simplified analytical relationships are reported for local splitting behaviour.
Global verifications
The analysis of the global behaviour exhibited by tunnel segments when the forces exerted by TBM’s thrust
rams are applied is an important step of the design process of precast tunnel elements. It is a matter of fact
that if local damages are avoided (Paragraph 6.4.4.1) not necessarily global damaging mechanisms are
prevented.
This phase should be analysed by considering the global behaviour of segments and ring, according to the
following aspects:
• study of the possible boundary conditions that could interest the tunnel segments during this phase;
• choice of a realistic load scheme;
• choice of an opportune resistant mechanism.
Referring to traditional RC tunnel elements, this stage is generally considered by designers by assuming that
the tunnel element behaves like a 2D deep beam, which exhibits the schematic typology of expected stresses
illustrated in Figure 70 (9). Based on this assumption, the global segment behaviour during this stage can be
predicted by means of analytical approaches (e.g. strut-and-tie models, as previously described, for predicting
(a) (b)
Figure 70 Distribution of stresses in the tunnel segment loaded by the TBMs jacks: French segment configuration (a);
German segment configuration (b) (13).
Tensile forces
between the
jacks
a) b)
Figure 71 Strut-and-tie model for evaluating the global tunnel segment behavior
The numerical methods, from a design point of view, can be generally accepted if a critical analysis of relevant
factors, such as the choice of boundary conditions, is preliminary developed. Similar to the local behaviour,
simplified strut-and-tie models can be applied (11) (13) as shown in Figure 71 a, b.
The location of the introduction of the jack’s forces and the position of bearing pads (thrust jack configurations)
determine where the stress concentrations in the tunnel lining take place.
Refinement of the calculation can be done with 3D numerical models (Figure 72), where the distribution of the
stresses is studied in a segment with the jack forces applied. The boundary conditions are induced by the
transversal connections (guidance rod) with the other segments and the longitudinal connections (bolts,
dowels) with the previous installed ring. The latter issues can be included in more complicated numerical
models (Figure 73).
In order to avoid the risk of damage in the global verification under the TBM rams, the following aspects should
be probably included in the design process:
The assumption of post-cracking residual properties exhibited by FRCs can be done by means of non-linear
numerical simulations. As underlined in Appendix 3 of [22], such numerical simulations required engineers
with specific know-how, who should be aware of all issues and pitfalls related to NLFEA on cementitious
composites exhibiting softening uniaxial tensile constitutive laws. In (5) is underlined that the frequency and
entity of the possible aforementioned irregularities (eccentricity, gaps etc.) can govern the amount of localized
stresses (e.g. in-plane segment localized stresses) and consequently, the possible complete or partial
substitution of traditional rebars with fiber reinforcement. This phenomenon can be captured with advanced
non-linear numerical simulations or through full-scale experimental tests.
Analysed segment
Figure 73 3D numerical model of a tunnel segment loaded by TBM rams with evidenced the interaction with adjacent
tunnel segments.
With regards to FRC tunnel elements, the M-N diagram at ULS can be determined by using the typical
analytical sectional analysis as suggested by several standards for the design of FRC elements; among them,
the current [21] can be cited. The applications of this general approach in tunnel linings are reported in Section
5 of [22] and in [20].
For evaluating the tunnel lining behaviour at SLS to estimate the crack width (if any), the sectional response
of the tunnel segment can be analytically (by means of layer-by-layer sectional model) determined based on
the uniaxial simplified constitutive law proposed by current [21]. The application of this general approach is
reported in Appendix 2 of [22] where M-N envelopes at SLS are presented.
Fiber reinforcement generally enables a possible complete replacement of shear reinforcement occurring at
this stage. Details on the evaluation of the shear resistance capacity in presence of fiber reinforcement in case
of precast tunnel linings can be found in [22].
In (5) the advantages of monofilament polypropylene (PP) microfibers against explosive-spalling are briefly
reported, while in [22], by referring to fibres for structural purposes, a procedure is proposed for taking into
account the post-cracking strengths after exposure to high temperatures.
Seismic design
Seismic design scenarios are characterized by the probability of seismic events in the specific project location.
As indicated in the [5], the designer of segmental lining should assess and document the frequency, magnitude
and loads associated with seismic design situations with reference to (17). The study of the ITA Group No 9
The change of internal force in the segmental lining during earthquakes can be calculated following several
approaches. Relevant guidelines suggest closed form solutions (18), pseudo-static and uncoupled dynamic
analyses. However, to take into account, the influence of the existing state of stress around the tunnel and the
permanent ground deformation during dynamic actions, full dynamic analysis by numerical methods should be
performed. One of the most important input data for dynamic analysis is the time histories which should be
site-compatible. In Figure 74 a scheme of the main steps of a full dynamic analysis by numerical modelling is
provided.
6
0.5
5
0
Sa [m/s2]
0 5 10 15 20 25 30
Sa[m/s2]
4
-0.5
3
-1
2
-1.5
1
-2
0
0 0.5 1 1.5 2 2.5 3
Period [s] -2.5
Time [s]
10m
D=6.3m Control points
5D
∆l=2mx1m L=15m
40m ∆l=1mx1m
≈4D
∆l=1mx2m ∆l=2mx2m
102 m
Figure 74 Example of dynamic analysis (Finite Difference Element model) - Moment and Axial Force time history of the
control points on the segmental lining
The seismic performance of the tunnel linings is generally good because they are constrained by the ground
around them and not subjected to inertial effects like above-ground structures. In addition to that constriction,
their circular, largely symmetrical shape and ample flexibility ensure them to perform well in earthquakes. The
flexibility of the segments is achieved through steel reinforcing bars or steel fibre reinforcing and flexibility of
the overall structural system is achieved through joints between the segments that accommodate deformations
with little or no damage. In addition, joint contact areas contain packing materials which prevent high contact
stresses. An extensive literature analysis on the performance of concrete segmental lining in seismic areas
was conducted (Dean et Al. – 2006). It is concluded that since the reconnaissance reports of earthquakes
focus on the poor performance in general, there are not many published inspection reports about the
performance of linings because of their good seismic performance.
Nowadays, the recent technical requirements for the design of tunnel and underground structures include the
structural verifications related to these additional loads with definition of the maximum level of security against
collapse. Impact loads generated by derailed trains can be extremely high, especially in the case of heavy
trains running at high speeds, which usually cause significant safety issues to the rail infrastructures. The
increase in the number of terrorist attacks has shown that the effect of blast loads on buildings is a serious
matter that should be taken into consideration in the design process.
Impact and blast loads are dynamic loads that need to be calculated just like earthquake and wind loads. In
shield tunnels, such loads may cause the damage and deformation of concrete segments and the failure of
segmental joint connections. Simplified design methods may not give an accurate result for the ultimate
capacity of the structure under impact and blast loads. The design should include advanced numerical analysis
on the failure behaviour of segmental lining and dynamic response of the elements should be investigated.
The interaction of a precast structure with the surrounding soil should be considered in analysing the behaviour
of the structure under impact loads. The analysis should consider the non-linearity in material behaviour and
geometric non-linearity. Considering the probability of the event and the associated return period, it is
reasonable in some cases to include the plastic response of the structural elements (damage control zone of
the Potential Deformation Limit State).
Figure 75 Train impact analyses according to AS 5100 - No-linear analysis: maximum displacement and bending
moment
Figure 76 Blast loading analyses (10 kg equivalent TNT blast event located at a 1m distance from the internal surface of
the concrete lining) – Dynamic analysis: maximum displacement and bending moment during the time history
With regard to the possible advantages related to the adoption of FRC in preventing damages, in [22], it is
stated: “only a limited amount of studies has been carried out with respect to the influence of fibre reinforcement
on fastenings to concrete. Certain enhancement in ductility is evident in all the available literature. However,
conclusions with regard to the effects of fibres when it comes to the load-bearing capacity of bolts and dowels
vary, showing some enhancement in load bearing capacity but not in a consistent fashion. It is also important
to note that the available studies have been performed in uncracked concrete with standard steel or synthetic
fibres”.
In particular situations, the longitudinal connections could be different among the cross-passages compared
to the rest of the tunnel. The required shear forces of the connections in by-pass area can be computed (Figure
79): analytically (with static schemes that take into account the repartition of the internal forces from the cut
rings through the connections) or numerically (with 3D numerical models, Figure 80). In the latter case, special
attention should be devoted to modelling the boundary conditions through non-linear springs with force-
displacement relations coming from lab test of the manufacturer.
By the way of example, in (5) is underlined that in a case study of tunnel lining having large diameter (internal
diameter of 11.3 m) a solution with fibre reinforced only was adopted expect for high-loaded sections or cross-
passages, where a hybrid RC+SFRC was used, confirming the needed to pay attention in terms of connections
but also in terms of localized stresses which can occurs in precast tunnel elements in presence of cross-
passages.
Figure 79 Shear force in the by-pass in the hypothesis of tension rebalancing acting exclusively to the connection system
7.1 Generalities
This chapter describes experimental activities and tests that can be performed in the laboratory or in the
prefabrication plant on the lining elements to verify their characteristics.
In Chapter 4, several non-invasive controls and checks, that are usefully performed on the segments to verify
their characteristics in an expeditious way, are listed; this part of the document is dedicated to the tests to be
carried out in laboratory.
The described tests can be performed on a whole segment, to verify the strength to the state of stress which
will be subject during the installation and on the final configuration, or on specific parts such as gaskets,
reinforcements or edges. Finally, some tests will be briefly described to verify the behaviour of the segments
when they are subjected to stresses in non-optimal conditions, such as non-axial differential loads or loads
applied to incorrectly positioned segments.
The same tests are performed to verify the effectiveness of innovative technological solutions such as fiber-
reinforced concrete or fiberglass reinforcement.
The list of laboratory tests described in the following paragraphs does not claim to exhaust all the tests that
can be performed, rather to describe the most common tests whose results can be considered more reliable.
On this point, more insights can be obtained following the bibliographical references cited for each described
test.
Consequently, laboratory tests, based on the use of X-Ray Diffraction analysis (XRD), aimed at verifying the
exact chemical composition of the bars are carried out in cases where a high risk of corrosion phenomena is
expected.
Tensile test
This test is performed to determine the tensile properties of reinforcing bars. The general standard reference
is [43] and [44].
For GFRP (glass fiber reinforced polymer), the test is performed according [47].
Bend test
The bend test consists of submitting a test fraction of rebars to plastic deformation by bending, without
changing the direction of loading, until a specified angle of bend is reached. This test is conducted for
determining the ability of metallic materials to undergo plastic deformation in bending. The [48] covers bend
testing of bars primary for the evaluation of their ductility.
• Tensile test on bolts, with or without a nut [49] [58] [60] [61] [63]
• Shear test on bolts [49] [57] [58] [60] [61] [63]
• Load test on nuts [64] [62] [59] [60] [49]
In general, for this purpose, the most commonly performed tests are the non-destructive ones and only in
particular circumstances the lining elements are subjected to destructive tests.
This provides cylindrical samples representative of the entire lining element on which it is possible to perform
the most common laboratory tests such as the uniaxial compression test, the indirect tensile test (Brazilian
test) or non-destructive tests.
Figure 82 shows the apparatus necessary to perform the coring and sampling of the lining element; while in
Figure 83 there are two images of the most common tests that can be carried out on cylindrical concrete
samples.
Figure 83 Uniaxial compression test and indirect tensile test performed on concrete samples.
The same typology of tests can be usefully performed to verify the tensile strength of sockets.
The measurement equipment is composed by a couple of transducer, a pulse receiver unit and a data
acquisition/recording system.
The test system allows quick screening of structure for flaws like honeycombing, de-laminations, voids etc.
and identifies suspect areas for subsequent detailed assessment.
Impact Echo
Impulse Echo tests consists in applying a stress pulse by a mechanical impact and studying the frequency
response of the reflected waves. The dominant frequency in the frequency response is used to compute either
the depth of the member or the possible depth of the flaw.
Avantech Engineering Consortium has carried out Impact Echo tests to assess thickness of tunnel walls, crack
depths and voids in tendons ducts in bridge girders.
The principal components of the device required to perform this test are a hand-held transducer unit, a set of
spherical impactors, a notebook computer, a high-speed analogic/digital data acquisition system and a
software system.
Handling and installation of the ring. In this paragraph several laboratory tests and checks that can be
performed to verify features of the lining elements in the installation phase are listed. The main aim involves
geometric matters to verify that all the elements will adhere perfectly to each other and stay in perfect contact.
There are a series of laboratory tests and checks aimed at verifying if the elements produced are in conformity
with the project specifications; these tests are useful to simulate the assembly of one or more coating rings to
verify their correctness.
Geometrical test
This verification consists in the assembly of one or more lining rings simulating the operations that are
performed on site. Once the lining elements are assembled, several measurements are performed to verify
that the dimensions and alignment of the joints comply with the limits set by the technical specifications.
One or several jacks are used for each steel plate; the load was continuously measured by pressure
transducers. Several transducers (at the intrados and at the extrados) measure the shoes displacements, while
one LVDT transducer is applied between the load shoes, at the top, to measure the crack openings.
The tests are performed using a single jack for the application of the load or parallel jibs to study the
combination of the applied loads.
A gap of 5 mm is given at the segment base, and the point load test is performed by applying three-point loads
at the segment, by adopting the same steel plates used by the TBM machine.
Each jack, having a loading capacity of 2000 KN, is inserted in a close ring frame made with HEM 360 steel
beams and 50 mm diameter bars, see Figure 93.
Figure 93 Point load test with gap (Università degli Studi di Roma Tor Vergata)
The load was continuously measured by pressure transducers. Several transducers, located at the intrados
and at the extrados, measure the vertical displacements while others are placed close to the gap onset to
measure the crack openings (25).
These tests are not included in any standard but are performed to meet the needs of specific projects. In Figure
95 are presented two pictures of the test configuration before and after different tests. The comparison of the
results obtained performing this tests on samples specifically realized using different mix design, materials (i.e.
fiber reinforced concrete) provide useful insights on the effectiveness of each solution.
Several studies have described the formation of cracks in the lining segments in a condition of uneven support
generated by contact deficiencies between the segments. Tests similar to the one described in this paragraph
can be performed to simulate the application of the load in a non-orthogonal direction to the sample surface.
Flexural testing
Figure 96 shows the experimental apparatus for flexural testing. It is composed by a couple of reaction frames
which support the lining element and a tree loading frame, commonly used to apply a uniformly distributed
load.
Figure 96 Flexural test apparatus pictures in the Laboratory of Materials and Structures of the Università degli Studi di
Roma Tor Vergata.
One or two cycles of loading-unloading are conducted for several load steps (1.25%, 2.5%, 5%, and 10% of
Δmax) and subsequently, three cycles are applied for 20%, 40%, 60%, 80%, 100% of Δmax. This loading cycles
are continuously applied until the tested segment fails, splitting into two pieces.
A series of displacement transducers are positioned at the segment mid-span to measure vertical
displacements.
The load and displacement measures are collected simultaneously at proper time intervals using a data
acquisition system. The measurement of the crack widths can be measured using a crack width ruler.
The described test can be performed using a similar methodology which involves the same lining element
positioned in the opposite direction to the one described, namely rotated by 180 degrees.
These tests are carried out in particularly equipped laboratories and include the application of both longitudinal
and transverse loads and, at the same time, the measurement of the induced displacements. In Figure 97 are
pictures of the test set up configuration for these typologies of tests.
Figure 97 Picture and scheme of the test set-up available in the laboratories in Delft University.
Sealing tests
The test consists in verifying the behaviour of the sealing elements between the segments under the effect of
the hydrostatic pressure. The test is generally performed on two assembled and connected rings positioned
one over the other.
These tests are designed to verify the tightness of joints in water when the joints are correctly aligned but also
when they are misaligned (gap and/or offset).
The test procedure can be described by the following points (Figure 98):
Specific tests (Figure 99) are developed to verify the effectiveness of the sealing elements; the most common
tests are the tightness tests, which require the application of increasing values of water pressure in a chamber
composed of two half-boxes between which the gaskets to be tested are affixed (also with gap and / or offset).
Other more specific tests have been developed to verify the strength of the seals with respect to the risk of
being torn or removed during the handling and installation phases.
The details of these tests are generally agreed during the design phase based on the characteristics of the
work to be carried out, the hydrogeological conditions and the final use of the tunnel.
Durability tests
To verify the variation of the characteristics of the concrete over time, several tests can be performed. The
water permeability test is performed according to the standard [40]; Rapid Chloride Ion Penetration Test
according to [42]; the water absorption test according to [13] and the Initial Surface Absorption Test following
the [12]. All the cited tests can be performed according with the specific tunnel project following different
procedures.
Figure 101 Water absorption tests (left) and rapid chloride ion penetrability test (right)(24).
Creep on sockets
If the tunnel project foresees that parts incorporated in the concrete are subjected to continuous loads, it is
necessary to consider the creep phenomena, both during the validation of the project and through a validation
test campaign.
In evaluating the creep, it is appropriate to consider the presence of external agents to the embedded part,
such as humidity or water, which can significantly alter the performance of the same.
It is advisable to know the aging process of the materials used to evaluate the chemical-physical performances
over the design time.
Figure 102 shows the graph that represents the set of factors considered for a polyamide bush.
Rebars corrosion
Monitoring the corrosion activity and determining the rate of corrosion in the RCC structures is essential for
estimating the service life of the structural member.
If the project involves permanent metal connection systems, it is necessary to evaluate how the environmental
characteristics interact with the system.
The salt spray test, defined by [54], can be used in the design phase to define the corrosion resistance required.
Some standard references in which are defined the classes of corrosion of the various environments and the
annual consumption of the zinc coating are.
There is no standard that indicates the results to be obtained from the salt spray test according to the class of
corrosion of the environment, this definition must be made in the design phase based on previous experiences.
Furthermore, the aging of the material the related causes must be considered, which may alter its chemical-
physical characteristics.
Fire testing
Some tests are specifically arranged to verify the resistance of a concrete mixture to face sudden variations in
temperature, situation that occurs, for example, in the event of a tunnel fire.
To perform this test, a chamber in which it is possible to increase the temperature up to extremely high values
such as those occurring during a fire is required; the chamber is closed by the sample to be tested.
Tests are carried out progressively increasing the temperature and the exposure time of the sample, evaluating
at the end the conditions of the sample and the thickness of material which suffered from spalling or strength
reduction.
In the construction of underground infrastructures, the use of mechanised tunnelling faces a continuous
increase; consequently, the production of precast segmental linings has become an increasingly important
part of the tunnel industry. Therefore, guaranteeing high quality and performance of precast linings gets more
and more crucial, both from the Project Owner and the Contractor points of view; in fact, the Owner of the
infrastructure requires (and pays for) a tunnel free from defects and water-tight in the long-term, whereas the
Contractor (and his potential Subcontractors) doesn’t want to spend for replacing damaged segments,
repairing defective segments or non performing rings after the erection, performing water-tightening injections,
etc.
In this regard, the production processes have to be to analysed in an industrial logic, aiming to a strong
standardisation and to constantly satisfactory results. Despite that, craft approaches still resist that are not
guided by past experiences. To eliminate or, at least, statistically reduce the onset of defects in precast
segments, they should be considered as an increasingly advanced industrial product, which presupposes
complex and advanced systems and equally advanced and expert workers, which is not always the case.
In fact, as in other industrial sectors, all operators in the production chain should be trained and qualified. This
implies that a third body should certify the suitability of the workers, even after specific training courses, since
experience and training would help guaranteeing the success. On the other hand, Project Owners should
contractually require the employment of certified and specialised personnel, suited for the different roles of the
production chain.
Linings geometry (thicknesses, angles, lengths, no. of segments per ring, diameters, etc.) should also be the
subject of guidelines and standards, that could lead to a kind of quality mark, with different benefits for
Contractors, Manufacturers and Project Owner, together with certification of environmental compatibility (e.g.
LEED).
Again, specific standards should be defined for segments storage , such as how and how many segments can
be piled up, after how long they can be exposed to the external environment and put in place, how they have
to be protected them from environmental/climatic conditions (the gaskets can be particularly sensitive), also
with reference to transport and handling.
Another critical issue is that all the accessories of the segments, which significantly affect the design (gaskets,
connectors, bolts, corners’ and edges’ guards, etc.), are considerably influenced by technical and commercial
factors. Often these components are defined in the tender project, but after tender awarding the Contractor try
to modify these choices, so that the whole design and implementation process restarts, with great expenditure
of economic and time resources.
The topics discussed in sections 6.4.5.2 (Structural fire design) and 6.4.5.3 (Seismic design) are becoming
increasingly important in the design of underground works as well, and they are still the subject of in-depth
studies; thus, at present a design direction to be followed in structural checks is not identified yet. Moreover,
as far as underground works are concerned, standards and guidelines (not only the Italian ones) are not very
clear and do not fully support the designer. As a result, these two essential themes are often disregarded or
analysed differently from what suggested by recent research. Given this situation of uncertainty, the Project
Owner should provide the designer with guidelines to evaluate the loads from thermal actions and those
resulting from an earthquake. This Report illustrates (necessarily in a synthetic way) the peculiar
characteristics of the seismic verification of a tunnel compared to that of an above ground structure; a future
development of the Report itself could then briefly suggest how to verify tunnel fire resistance and deepen the
fire testing subject.
Furthermore, the reduction of defects occurrence and the improvement of segments durability could be
achieved using/experimenting new technologies, as for example:
- Surface protective layers on intrados or extrados of segments
- Steel, mineral and synthetic fiber reinforcements
- Edges’ and corners’ GFRP reinforcements
- GFRP perimetric rebar cages, combined with fiber reinforcements.
Another important subject to be developed is the study, at the design stage, of the interaction between TBM
and lining or, in other words, that of the TBM design, which should be duly analysed to allow multiple TBM’s
uses, with increased safety and reliability.
A final cause for reflection could be the use of double lining, particularly frequent in hydraulic tunnels, which
combines precast segment rings with an internal cast in situ lining. In these cases, the long-term integrity of
the first lining must not be ignored, not to compromise the integrity of the whole system.