GOVERNMENT OFTHE REPUBLIC OF THE UNION OF MYANMAR

MINISTRY OF CONSTRUCTION

PUBLIC WORKS

ANALYSIS OF RATES

FOR

BRIDGE WORKS

SECOND EDITION JUNE 2013


CONTENTS

SH-NO NAME OF SUB-HEAD PAGE NO

BRIDGES

SUB-HEADS

1O
. Foundation Work

2.0 P.C Girder

3.0 Steel Truss

4.0 Steel Plate Girder

5.0 Suspension and Cablestayed Bridge

6.0 Survey

Miscellaneous Notes
1
Standard Data for Working Out Rates Per Unit Quantity ofltems of Work.

Sr
Particulars of Materials and Labour Unit Quantity Remarks
No.
X IX. BRIDGES
Foundation Works
1 Labour For Driving (250 mm) Diameter Timber
Piles inordinary Soil(With 500 kg drop hammer
from pulley winch and local trestle and manually
operated). Penetration average 6 m.
Labour
Foreman Man-Day 0.3 - Cost of Timber piles
Carpenter (1st Grade) Man-Day 0.5 according to varying dia;
Carpenter (2nd Grade) Man-Day 0.5 with all necessary fittings
Worker Man-Day 3 is to be included in the
Plants main estimate.
Pile driving frame (1)No Hour 4
Sundries L.S -

2. Labour For Driving (250 mm)Diameter Timber


Piles inordinary Soil (With pile driving machine).
Penetration average 6 m.
Labour - Cost of Timber piles
Operator Man-Day 0.3 according to varying dia;
Foreman Man-Day 0.3 with all necessary fittings
Carpenter (I st Grade) Man-Day 0.5 is to be included in the
Carpenter (2nd Grade) Man-Day 0.5 main estimate.
Worker Man-Day 3
For Operation
H.S.D litre 3
Grease kg 0.1
Plants
Pile driving frame (1)No Hour 2.7
Sundries L.S -

3. Labour for Pile Driving reinforced cement con-


crete pile (350 mm x 350 mm x 12000 mm) in
ordinary soil (with 12m dieselhammer).
Penetration average 12 m.
Labour
Foreman Man-Day 0.3
Pile driving machine operator Man-Day 0.3
Pile driving machine Asst Man-Day 0.3
Crane operator Man-Day 0.3
Worker Man-Day 6 A
2
StandardData for Working Out Rates Per Unit Quantity of Items of Work-contd.

Particulars of Materials and Labour Unit Remarks

'001s Required Cost for R.C Piles to be


12m)rail line trollies for transport of precast calculated according to
bile. the reqd.Size and inclu-
One crane for loading unloading erecting ded in the main estimate.
and pitching of precast pile. Hour
Pile driving machine (1) No Hour
;or Operation
H.S.D for Pile Driving Machine
H.S.D for Crane
Engine Oil
Sundries

.abour for Pile Driving reinforced cement con-


rete pile (350 mm x 350 mm x 12000 mm) in
~rdinarysoil ( Using drop hammer with winch
~peratedby machine).Penetration Average 12m.
.abour
Foreman
Operator
Worker
dachine Cost for R.C Piles to be
Pile driving machine (1)No Hour calculated according to
:or Operation the reqd.Size and inclu-
Diesel Oil ded in the main estimate.
Grease Oil
Sundries

Making of Stand Pipe 8 rnrn thk; 12mm thk;


(800 mm 0 to 1650 mm 0 ) (For 1 Sqm)
Steel fixer Man-Da:
Worker Man-Da:

Driving Stand Pipe


Driving of Stand Pipe1350mm 0,1650mm 0
with Vibro Hammer for 1200mm 0 ,
1500mm 0 Bored Pile. ( For 1 m )
Stand pipe
Steel fixer Man-Dti
Head Worker
Worker
3
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.

Sr
Particulars of Materials and Labour Unit Quantity Remarks
No.
Electric Helper Man-Day 0.5
Operator /Machine Driver Man-Day 0.7
Sundries L.S -
H.S.D litre -

(b) Driving of Stand Pipel950rnrn 0,2650mm 0


with Vibro Hammer for1800mm 0,2500mm0
Bored Pile. ( For 1 m )
Stand Pipe No
Steel Fixer Man-Day 1
Head Worker Man-Day 1
Worker Man-Day 3.2
Electric Helper Man-Day 0.5
Operator /Machine Driver Man-Day 0.7
Sundries L.S -
H.S.D litre -

7. Removing Stand Pipe


(a) Removing of Stand Pipe 1350mm 0,1650mm0
with Vibro Hammer for 1200 mm 0 ,
1500mm 0 Bored Pile. ( For 1 m )
Stand Pipe No -
Steel Fixer Man-Day 0.7
Head Worker Man-Day 0.5
Worker Man-Day 2
Electric Helper Man-Day 0.5
Operator Machine Driver Man-Day 0.5
Sundries L.S -

(b) Removing of Stand Pipe 1950mm 0 ,


2650 mm0 with Vibro Hammer for 1800mm 0,
2500mm 0 Bored Pile. ( For 1 m )
Stand Pipe No -
Steel Fixer Man-Day 0.7
Head Worker Man-Day 0.7
Worker Man-Day 2.5
Electric Helper Man-Day 0.5
Operator /Machine Driver Man-Day 0.5
Sundries L.S -
H.S.D litre -
4
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd

Sr
Particulars of Materials and Labour Unit Quantity Remarks
No.
8. Fitting of Drilling Equipment to dig Bored Pile.
1200rnm 0 , 1500rnm 0 ,1800mm 0,
2500rnm 0. ( For 1 time )
Head Worker Man-Day 2
Worker Man-Day 7
Operator /Machine Driver Man-Day 0.8
Sundries L.S -
H.S.D litre -

9. Dismantling of Drilling Equipment.


( For 1 time )
Head Worker Man-Day 2
Worker Man-Day 7
Operator Machine Driver Man-Day 0.8
Sundries L.S -
H.S.D litre -

10. Drilling of 800mm 0 mini Bored Pile.


(Ground, Ordinary Soil) ( For 1 m )
Head Worker Man-Day 0.7
Foreman Man-Day 0.5
Worker Man-Day 2
Operator Machine Driver Man-Day 0.3
Water Pump Helper Man-Day 0.3
Sundries L.S -
H.S.D litre -
Machinary hair Charges L.S -

1 1. Drilling of 800 mm @miniBored Pile.


(Ground ,Weathered Soft Rock ) ( For 1 m )
Head Worker Man-Day 1.3
Foreman Man-Day 1
Worker Man-Day 4
Operator Machine Driver Man-Day 0.7
Water Pump Helper Man-Day 0.7
Sundries L.S -
H.S.D litre -
Machinary hair Charges L.S -
-
5
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.

Sr
Particulars of Materials and Labour Unit Quantity Remarks
No.
12. Drilling of 800 rnm 0 mini Bored Pile.
(Water, Ordinary Soil) ( For 1 m )
Head Worker Man-Day 0.8
Foreman Man-Day 0.6
Worker Man-Day 2.5
Operator /Machine Driver Man-Day 0.4
Water Pump Helper Man-Day 0.4
Sundries L. S -
H.S.D litre -

13. Drilling of 800mm 0 mini Bored Pile.


(Water ,Weathered Soft Rock) ( For 1 m )
Head Worker Man-Day 1.5
Foreman Man-Day 1.2
Worker Man-Day 5
Operator /Machine Driver Man-Day 0.8
Water Pump Helper Man-Day 0.8
Sundries L.S -
H.S.D litre -

14. Drilling of 1200mm 0 Bored Pile


( Ordinary Soil ) ( For 1 m )
Head Worker Man-Day 1
Foreman Man-Day 0.5
Worker Man-Day 3
Operator /Machine Driver Man-Day 0.5
Water Pump Helper Man-Day 0.3
Sundries L.S -
H.S.D litre -

15. Drilling of 1500mm 0 Bored Pile


( Ordinary Soil ) ( For 1 m )
Head Worker Man-Day 1.2
Foreman Man-Day 0.5
Worker Man-Day 3.5
Operator Machine Driver Man-Day 0.5
Water Pump Helper Man-Day 0.4
Sundries L.S -
H.S.D litre -
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.

Sr Unit Quantity Remarks


Particulars of Materials and Labour
No.
16. Drilling of 1500mm 0 R.C.D Bored Pile
( Ordinary Soil ) ( For 1 m )
Head Worker Man-Day 1.4
Foreman Man-Day 0.8
Worker Man-Day 4.3
Operator Machine Driver Man-Day 0.7
Water Pump Helper Man-Day 0.5
Sundries L.S -
H.S.D litre -

17. Drilling of 1800mm 0 , Bored Pile


( Ordinary Soil ) ( For 1 m )
Head Worker Man-Day 1.5
Foreman Man-Day 0.8
Worker Man-Day 4.5
Operator /Machine Driver Man-Day 0.8
Water Pump Helper Man-Day 0.5
Sundries L.S -
H.S.D litre -

18. Drilling of 2500rnm 0 , Bored Pile


( Ordinary Soil ) ( For 1 m )
Head Worker Man-Day 1.5
Foreman Man-Day 0.8
Worker Man-Day 4.8
Operator /Machine Driver Man-Day 0.8
Water Pump Helper Man-Day 0.5
Sundries L.S -
H.S.D litre -

19. Drilling of 1200mm 0 Bored Pile.


( Weathered Soft Rock Layer Only, Based on Soil
Test Result ) ( For 1 m )
Head Worker Man-Day 1.3
Foreman Man-Day 0.5
Worker Man-Day 3.5
Operator /Machine Driver Man-Day 0.5
Water Pump Helper Man-Day 0.4
Sundries L.S -
H.S.D litre -
I

Standard Data for Working Out Rates Per Unit Quantiry of Items of Work-contd.

Particulars of Materials and Labour Unit Remarks

lrilling of 1500mm 0 Bored Pile


:Weathered Soft Rock Layer Only) Based on Soil
rest Result ) ( For 1 m )
Head Worker
Foreman
Worker
Operator Machine Driver
Water Pump Helper
Sundries
H.S.D

lrilling of 1500rnrn 0 R.C.D Bored Pile


Weathered soft rock Layer only Based on soil
Testresult) ( For 1 m )
Head Worker
Foreman
Worker
Operator Machine Driver
Water Pump Helper
Sundries
H.S.D

lrilling of 1800mm 0 Bored Pile


:Weathered Soft Rock Layer Only Based on
Soil Test Result ) ( For 1 m )
Head Worker Man-Da:
Foreman Man-Da:
Worker Man-Da:
Operator /Machine Driver Man-Da:
Water Pump Helper Man-Da:
Sundries L.S
H.S.D litre

Drilling of 2500mm 0 Bored Pile


( Weathered Soft Rock Layer Only based on
Soil Test Result ) ( For 1 m )
Head Worker Man-D?
Foreman Man-D?
Worker Man-D?
Operator Machine Driver Man-Da:
8
Standard Data for Working Out Rates Per Unit Quantity of hems of Work-contd.

Sr
Particulars of Materials and Labour Unit Quantity Remarks
No.
Water Pump Helper Man-Day 0.7
Sundries L.S -
H.S.D litre -

24. Mixing of Betonite Solution. (For 1 cum)


Worker Man-Day 0.8
Sundries L.S -
H.S.D litre -

25. After drilling Bored Pile and fitting tremie pipe to


pour concrete ,Proving of Slime Wash with
Compressor, for cleaning to Bored hole.
(For 1 hole)
Worker Man-Day 3
Sundries L.S -
H.S.D litre -

26. Hanging of Steel Cage for 800mm0,1000rnrn 0 ,


1200 mm 0 to Bored Hole with Crane.
(For 12m length )
Welding Rod kg -
Steel Fixer Man-Day 2
Worker Man-Day 6
Sundries L.S -

27. Hanging of Steel Cage for 1500 mrn 0 ,


1800 mm 0,2500 mm 0 to Bored Hole with
Crane. (For 12m length )
Welding Rod kg -
Steel Fixer Man-Day 3
Worker Man-Day 8
Sundries L.S -
H.S.D litre -

28. Pouring (1 :1?4:3) Cement concrete by Tremie


Method. (1 cum)
Head Worker Man-Day 0.5
Worker Man-Day 0.8
Operator /Machine Driver Man-Day 0.1
Sundries L.S -
H.S.D litre -
9
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.

Particulars of Materials and Labour Unit Remarks


oining, Dismantling, Cleaning, Painting of
:arth oil & Grease of Tremie Pipe to be ready.
For 1 m )
Steel Fixer
Helper
Sundries

3reaking of Bored Pile Head. ( 1cum )


Head Worker
Sundries

Well Foundation
Iigging and sinking of 1200mrn0 spun pipe
o get specified depth including removing soil
md water pumping. (Ground, Ordinary soil)
For 1 m)
Worker
Carpenter
Head Worker
Operator
Steel Fixer
Sundries

Iigging and sinking of 1200mm0 spun pipe


o get specified depth including removing soil
md water pumping. (Ground, Sand) (For 1 m)
Worker vim-Daj
Carpenter vim-Daj
Head Worker Man-Da:
Operator Man-Dq
Steel Fixer Man-Dq
Sundries L.S

Digging and sinking of 1200mm0 spun pipe


to get specified depth including removing soil
md water pumping. (Ground, Weathered soft
rock) (For 1 m)
Worker Man-Dq
Carpenter Man-Da,
Head Worker Man-Da
10
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.

Sr
Particulars of Materials and Labour Unit Quantity Remarks
No.
Operator Man-Day 1.6
Steel Fixer Man-Day 1.2
Sundries L.S -

34. Digging and sinking of 1200mrn0 spun pipe


to get specified depth including removing soil
and water pumping. (Water, Ordinary soil)
(For 1 m)
Worker Man-Day 15.6
Carpenter Man-Day 1.2
Head Worker Man-Day 1.2
Operator Man-Day 1
Steel Fixer Man-Day 0.7
Sundries L.S -

35. Digging and sinking of 1200mm0 spun pipe


to get specified depth including removing soil
and water pumping. (Water, Sand) (For 1 m)
Worker Man-Day 19.6
Carpenter Man-Day 1.6
Head Worker Man-Day 1.2
Operator Man-Day 1.2
Steel Fixer Man-Day 1
Sundries L.S -

36. Digging and sinking of 1200mm0 spun pipe


to get specified depth including removing soil
and water pumping. (Water, Weathered soft
rock) (For 1 m)
Worker Man-Day 31.2
Carpenter Man-Day 2.4
Head Worker Man-Day 2.2
Operator Man-Day 1.9
Steel Fixer Man-Day 1.4
Sundries L,S -

37. Digging and sinking of 2750mm0 cassion well


to get specified depth including removing soil
and water pumping. (Ground , Ordinary soil)
(For 1 m)
-1 -1

Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.

Sr Unit Quantity Remarks


Particulars of Materials and Labour
No.
Head Worker Man-Day 2
Worker Man-Day 63
Welder Man-Day 0.5
Operator Man-Day 10
Steel Fixer Man-Day 3
Foreman Man-Day 6
Diver Man-Day 6.5
Helper Man-Day 9
Rigger Man-Day 10.5
Carpenter Man-Day 3
Sundries L.S -

38. Digging and sinking of 2750mm0 cassion well


to get specified depth including removing soil
and water pumping. (Ground ,Sand)
(For 1 m)
Head Worker Man-Day 2.5
Worker Man-Day 78.8
Welder Man-Day 0.6
Operator Man-Day 12.5
Steel Fixer Man-Day 3.8
Foreman Man-Day 7.5
Diver Man-Day 8.1
Helper Man-Day 11.3
Rigger Man-Day 13.1
Carpenter Man-Day 3.8
Sundries L.S -

39. Digging and sinking of 2750rnm0 cassion well


to get specified depth including removing soil
and water pumping. (Ground, Weathered soft
rock) (For 1 m)
Head Worker Man-Day 4
Worker Man-Day 126
Welder Man-Day 1
Operator Man-Day 20
Steel Fixer Man-Day 6
Foreman Man-Day 12
Diver Man-Day 13
Helper Man-Day 18
12
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.

Sr
Particulars of Materials and Labour Unit Quantity Remarks
No.
Rigger Man-Day 21
Carpenter Man-Day 6
Sundries L.S -

40. Digging and sinking of 2750rnm0 cassion well


to get specified depth including removing soil
and water pumping. (Water ,Ordinary soil)
(For 1 m)
Head Worker Man-Day 2.4
Worker Man-Day 75.6
Welder Man-Day 0.6
Operator Man-Day 12
Steel Fixer Man-Day 3.6
Foreman Man-Day 7.2
Diver Man-Day 7.8
Helper Man-Day 10.8
Rigger Man-Day 12.6
Carpenter Man-Day 3.6
Sundries L.S -

41. Digging and sinking of 2750rnrn0 cassion well


to get specified depth including removing soil
and water pumping. (Water, Sand) (For 1m)
Head Worker Man-Day 3
Worker Man-Day 94.6
Welder Man-Day 0.7
Operator Man-Day 15
Steel Fixer Man-Day 4.6
Foreman Man-Day 9
Diver Man-Day 9.7
Helper Man-Day 13.6
Rigger Man-Day 15.7
Carpenter Man-Day 4.6
Sundries L.S -

42. Digging and sinking of 2750mm0 cassion well


to get specified depth including removing soil
and water pumping. (Water, Weathered soft
rock) (For 1 m)
Head Worker Man-Day 4.8
13

Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.

Mechanic
Worker
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
15

Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.

Sr
No.
- I Particulars of Materials and Labour

54. Stressing for Post tension HT Wire to get


Unit Quantii Remarks

complete strength . (1 Tendon)


Erector Man-Day 1
Steel Fixer Man-Day 0.3
Operator Machine Driver Man-Day 0.7
Machine Helper Man-Day 0.3
Electric Helper Man-Day 0.3
Worker Man-Day 11
Sundries L.S -

55. Plugging (1:1:1)Cement Concrete into the


Concrete cavity of the end-block. (Girder 1 No)
Mason Man-Day 1
Worker Man-Day 2
Sundries L.S -

56. Grouting high strength cement motor with Gro-


uting machine to sheating pipe. (Girder 1 No)
Mechanic Man-Day 3
Electric Helper Man-Day 1
Operator Machine Driver Man-Day 1
Worker Man-Day 30
Sundries L.S -

57. Fixing cycle trolley, launching arm and accesso-


ries on the bailey girder. (with crane and man)
Including fixing break wedge and sway braces.
(1 pair)
Erector Man-Day 8
Worker Man-Day 40
Sundries L.S -

1 58. 1~ i x i lowering
n~ bar, jacking beam, hanger jack

Erector Man-Day 5
Worker Man-Day 35
Sundries L.S -
16

Standard Data for Working Out Rates Per Unit Quantity ofItems of Work-contd.

Sr
Particulars of Materials and Labour Unit Quantity Remarks
No.
59. Side shifting P.C Girder from casting position
to Launghing position distance l m . (1 time)
Erector Man-Day 5
Worker Man-Day 20
Sundries L.S -

60. Making Jack up P.C Girder, timber crib.


Tighting in hanging beam with steel cable,
removing crib, fixing to get right alignment
between two Launching Arm. (1 time)
Erector Man-Day 4
Carpenter Man-Day 2
Worker Man-Day 15
Sundries L.S -

61. Pulling Steel cable from electric winch and


fixing them top of the launching Arm. (1 time)
Erector Man-Day 2
Electric Helper Man-Day 1
Worker Man-Day 3

62. Launching P.C Girder by electric winch.


Launching (1 time)
Mechanic Man-Day 4
Electric Helper Man-Day 1
Erector Man-Day 2
Worker Man-Day 20

63. Making Jack Down Launched P.C Girder


bracing strut not to fall down. (1 time)
Erector Man-Day 4
Carpenter Man-Day 4
Worker Man-Day 4
Sundries L.S -

64. After making jack down dismantling launching


equipment from P.C Girder,Pushing Launching
arm to the casting stagging. (1 time)
Erector Man-Day 2
Machine operator driver Man-Day 1
Worker Man-Day 6
17
Slandard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.

-
Sr
Particulars of Materials and Labour Unit Remarks
Jo.
-
55. Levelling and carving on the Cross Beam for
fitting P.C Girder,carving 1200mm 0 x 254mm
grouting hole, fitting bearing plate. (1 sheet)
Mason Aan-Daj
Erector Aan-Daj
Worker Am-Daj
Sundries L.S

i6. Fixing pretension frame with anchor bolt on the


concrete pretension bench according to the
required design. (10 Nos)
Erector Aan-Daj
Worker Aan-Daj

i7. Putting H.T wire coil (3MT)to the Dispencer


with crane using man,fixing bolt & nut.
(1 coil-3 ton)
Erector
Worker
Sundries

58. Pulling H.T wire to Dispencer for required


length,cutting then with griding machine.
(60 Nos)
Erector
Mechanic
Head Worker
Worker
Skill (Electric)
Sundries

69 Fixing repaired wires in pretension bench,


anchorage frame systematically.
(26m - 38 Nos)
Erector Man-Da
Head Worker Man-Da
Worker Man-Da
Sundries L.S
(18m - 38 Nos)
Erector Man-Da
Standard Data for Working Out Rates Per Unit Quantig of Items of Work-contd.

Sr Unit Quantity Remarks


Particulars of Materials and Labour
No.
Head Worker Man-Day 3
Worker Man-Day 25
Sandries L.S -

70. Fixing end plate each end of the P.C Girder


systematically whille arranging H.T wire.
(Girder 1 No)
Erector Man-Day 2

71. Stressing for pretension H.t wire to get stressing


force3.45 MPa. ( wire 1 No)
Mechanic Man-Day 0.1
Erector Man-Day 0.1
Machine operator driver Man-Day 0.1
Worker Man-Day 0.1
Skill (electric) Man-Day 0.1
Sundries L. S -

72. Stressing of 12mm 0 or 13 rnm 0 7 strand wire


(For 1 No)
Foreman Man-Day 0.1
Steel Fixer Man-Day 0.1
Worker Man-Day 0.3
Sundries L.S -

73. After fixing and checking P.C wire and rein-


forcement due to design, stressing H.T wire to
get required design force and elongation.
(Wire 38 Nos)
Erector Man-Day 3
Worker Man-Day 8
Skill (electric) Man-Day 3
Hard Worker Man-Day 2
Operator (Jack operator) Man-Day 1
Operator (Hydraulic pump) Man-Day 1
Sundries L.S -
74. Fixing accessories on the P.C Girder as per
design.
(a)Making and fixing hook (2 points)
19

Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd

Sr Quantity Remarks
Particulars of Materials and Labour Unit
No,
Erector Man-Day 2
Sundries L.S -

@)Making and fixing shoe plate (1 0 Points)


Welder Man-Day 7

(c)fixing througt bolt & nut (10 Nos)


Erector Man-Day 3
Sundries L.S -

75. Fixing of R.S.T Beam, H Beam, Angle,


M.S Flat & Channel for casting bed only.
(For 10 kg)
Head Worker Man-Day 0.4
Sundries L.S -

76. Dismantling of R.S.T Beam, H Beam, Angle,


M.S Plate, M.S Flat & Channel for casting bed
only. (For 10 kg)
Head Worker Man-Day 0.1
Sundries L.S -

77. Fixing of L.S.T Part, Bailey Part & C.H Parts


system. ( (For 10 kg)
Head Worker Man-Day 0.8
Sundries L.S -

78. Dismantling of L.S.T Part ,Bailey Part & C.H


Parts system. ( (For 10 kg)
Head Worker Man-Day 0.2
Sundries L.S -

Steel Truss
79. Labour for Launching of R.S.JS. over bridge
sup ports (Using two pulleys and winch from
the other side) (5No x 13000rnrn x 610mrn x
190mm) at (43.l)kg per RFT.
(Total Weight = 9.3 MTons)
Labour
Bridge Foreman Man-Day 3
20
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.

Total Kit one


One hammer
Coir rope (25mm 0 61m)
25000 Kg Jacks (2)No

Bridge Foreman
Worker
Sundries
21
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd

Sr Unit Quantity Remarks


Particulars of Materials and Labour
No.
Tools Required
Total Kit one - -
One hammer - -
Coir rope (25mrn 0 61m) - -
4000 Kg Hand Winch (2)No - -
Bailey Roller (6)No - -
Jumper (10)No - -
Wire Rope (16mm 0 228m) - -
One local JIB - -
Double pulley (2)No - -
Single pulley (1)No - -
50000 kg Jacks (2)No - -
Sundries L.S -

(b) Labour for assembling and launching C.H.


bridge (6.5m Road way)bolts and nuts for all
steel works complete (48m) span double depth.
(Total Weight = 150 MTons) (By Crane)
Labour
Bridge Foreman Man-Day 20
Skilled Worker Man-Day 150
Unskilled Worker Man-Day 1150
Tools Required
Total Kit one - -
One hammer - -
Coir rope (25mm 0 61m) - -
4000 Kg Hand Winch (2)No - -
Bailey Roller (6)No - -
Jumper (10)No - -
Wire Rope (16mm 0 228m) - -
One local JIB - -
Double pulley (2)No - -
Single pulley (1)No - -
50000 kg Jacks (2)No - -
Sundries L.S -

83. Labour for assembling and German bridge


(3.35m Road way) on scaffolding and lowering
down on supports or launching (18m)span.
(Total Weight = 17.87 MTons)
22
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.

Sr
Particulars of Materials and Labour Unit Quantity Remarks
No.
Labour
Bridge Foreman Man-Day 8
Worker Man-Day 80
Tools Required
Bailey Jacks = 2 No - -
Bailey rollers = 7 No - -
One spanner - -
One hammer - -
Sundries L.S -

84. Labour for assembling of R.P.T bridge on


scaffolding including rivetting and lowering
down on supports complete (30m).Span and
(5m) road way.
(Total Weight = 64.2 MTons)
Labour
Bridge Foreman Man-Day 30
Skilled workers Man-Day 100
Unskilled workers Man-Day 420
Tools Required
4000 Kg hand winch - -
Wire rope (12rnm 0 457m) - -
Wire rope (16mm 0 457m) - -
Coir rope (25mm 0 152m) - -
Service bolts - -
Double pulley (2)No - -
Single pulley (1)No - -
One Bellow - -
Dollys (2)No - -
Rivetting guns (2)No - -
One compressor with (2)No. Hose pipe (1 52m) - -
Local JIB one No. - -
One hammer - -
75000 Kg Jacks (2)No - -
Sundries L.S -

85. Labour for assembling and launching of R.P.T


bridge after rivetting complete for all steel
works (3Om)span (5m) road way.
(Total Weight = 64.2 MTons)
23
Standard Datafor Working Out Rates Per Unit Quantity of Items of Work-contd.

Sr
Particulars of Materials and Labour Unit Quantity Remarks
No.
Labour
Bridge Foreman Man-Day 35
Skilled workers Man-Day 120
Unskilled workers Man-Day 400
Tools Required
4000 Kg hand winch - -
Wire rope (12rnm 0 457m) - -
Wire rope (16rnm 0 457m) - -
Coir rope (25mm 0 152m) - -
Service bolts - -
Double pulley (2)No - -
Single pulley (1)No - -
One Bellow - -
Dollys (2)No - -

Rivetting guns (2)No - -


One compressor with (2)No. Hose pipe (500') - -
Local JIB one No. - -
Bailey rollers (6)No - -
Jumpers (10)No - -
75000 Kg Jacks (2)No - -
Sundries L.S -

86. Shifting Steel Truss and Bailey by Crane from


one place to another (Including hooking,
removing, handling with man) (10 MTons)
Foreman Man-Day 1
Head Worker Man-Day 1
Worker Man-Day 5
Sundries L.S -

87. Sorting & arranging the steel truss systemati-


cally, Laying out them for preassambling works
systematically. (10 MTons)
Foreman Man-Day 1
Head Worker Man-Day 1
Worker Man-Day 4
Sundries L.S -
Standard Data for Working Out Rates Per Unit Quantity ofltems of Work-contd.

Sr Unit Quantity Remarks


Particulars of Materials and Labour
No.
88. Checking the steel truss according to the design
for preassembling works on the ground.
(1000 kg)
Steel Fixer Man-Day 2
Head Worker Man-Day 1
Worker Man-Day 2
Operator /Machine Driver Man-Day 0.5
Electric Helper Man-Day 0.5
Sundries L.S -
89. (a) Erecting the preassembled steel truss from
pier to pier with erection crane according to
the design. (1000 kg)
Steel Fixer Man-Day 4
Head Worker Man-Day 2
Worker Man-Day 4
Operator /Machine Driver Man-Day 1
Electric Helper Man-Day 1
Sundries L.S -
(b) Allowing 50% of the above expenditure
for dismentling.

90. (a) Installing Bolts & Nuts, Drift Pins & Tigh-
tenning according to the design while erecting
steel truss. (1000 Nos)
Steel Fixer Man-Day 1
Worker Man-Day 4
- Tightening them with & Electric Guns again
before transfering the target place. (1000 Nos)
Steel Fixer Man-Day 1
Head Worker Man-Day 0.5
Worker Man-Day 4
Electric Helper Man-Day 0.5

(b) Removing Bolt & Nuts (1000 Nos)


Steel Fixer Man-Day 0.8
Head Worker Man-Day 0.5
Worker Man-Day 3
Electric Helper Man-Day 0.5
25
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.

Sr
Particulars of Materials and Labour Unit Quantity Remarks
No.
91. Final Tightenning the ready installed Bolts &
Nuts according to theTightenning sequence
( including with checking them whether
standard or not ) (1000 Nos)
Steel Fixer Man-Day 2
Head Worker Man-Day 1
Worker Man-Day 6
Electric Helper Man-Day 1.5
Sundries L. S -

92. Checking high tension Bolts & Nuts with check


Wrench whether standard or not. (1000 Nos)
Steel fixer Man-Day 1.5
Worker Man-Day 5
Sundries L.S -

93. (a)Fixing the safety Net to the upper & lower


steel truss systematically. (100 m)
Carpenter Man-Day 4
Head Worker Man-Day 6
Worker Man-Day 50
Sundries L.S -

(b) Removing Safety nets from Steel truss


Systemtically. (100 m)
Carpenter Man-Day 2
Head Worker Man-Day 3
Worker Man-Day 25
Sundries L.S -

94. Fixing Sleeper on the top & bottom Chord of


the Steel truss. (200 mm x 200 rnm)
(a) Carving sleepers fixing on Top Chord.
(100 Nos)
Carpenter Man-Day 4.5
Sundries L.S -

(b) Drilling holes on the sleepers for hooking.


(100 Nos)
Carpenter Man-Day 2.4
Sundries L.S -
Standard Dafafor Working Out Rates Per Unit Quantity of Items of Work-contd.

r
Particulars of Materials and Labour Unit Quantity Remarks
0.
(c) Shifting the sleepers within 30m with man
and arranging them Systemtically (not more
than one time. ) (100 Nos)
Carpenter Man-Day 4
Sundries L.S -

(d) Fixing the railway on the sleeper firmly on


the Top Chord of Installed steel truss.
- fixing with the required G.Bolt, U.Bolt along
the rail length for UIS & DIS. (10 m)
Steel Fixer Man-Day 2
Carpenter Man-Day 2
Head Worker Man-Day 1
Worker Man-Day 9
Operator /Machine Driver Man-Day 1
Electric Helper Man-Day 0.5
Sundries L.S -

(e) Fixing the railway on the the sleeper firmly


on the strainger of installed steel truss.
- fixing with the J.Bolt or Dog Spike for Up
Stream and Down Stream. (10 m)
Steel Fixer Man-Day 1
Carpenter Man-Day 1
Head Worker Man-Day 1
Worker Man-Day 4.5
Sundries L.S -

(f) Dismantling the railway (50 % of fixing)

95. Installing Erection Tower, Mast Crane & Multi-


purpose Crane on the Top Chord of the Steel
Truss. (1000 kg)
(a) With universal member
Steel Fixer Man-Day 5
Head Worker Man-Day 2
Worker Man-Day 13
Sundries L.S -
27
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Standard Data for Working Out Rates Per Unit Quantiv of Items of Work-contd.

Sr Unit Quantity Remarks


Particulars of Materials and Labour
No.
Steel Fixer Man-Day 0.5
Worker Man-Day 1
Operator /Machine Driver Man-Day 1
Electric Helper Man-Day 1
Sundries L.S -

99. Shifting Erection Tower on the Top Chord fiom


one span to another with winch, Pretension the
Steel Cables Final tension with 500 MT Jack
and Checking Erection Tower. (1 Time)
Foreman Man-Day 20
Steel Fixer Man-Day 20
Head Worker Man-Day 10
Worker Man-Day 100
Operator /Machine Driver Man-Day 20
Electric Helper Man-Day 20
Sundries L.S -

100. While erecting steel truss fiom one Pier to


another for the required level, fixing with 100 M
Ton jack, 3001350 MTon jack,500 MTon jack,
on the bearing of the piers.
- After that, making jack up & Jackdown
- Shifting horizontally & longitudinally
- Other components Work
(a) 100 MTon Jack
(10 Nos per 1 Time)
Foreman Man-Day 4
Steel Fixer Man-Day 8
Head Worker Man-Day 2
Worker Man-Day 7
Operator /Machine Driver Man-Day 7
Electric Helper Man-Day 7
Sundries L.S -

(b) 3001350 MTon Jack


(10 Nos per 1 Time)
Foreman Man-Day 5
Steel Fixer Man-Day 9
Head Worker Man-Day 2
29
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.

Sr
Particulars of Materials and Labour Unit Quantity Remarks
No.
Worker Man-Day 8
Operator /Machine Driver Man-Day 8
Electric Helper Man-Day 8
Sundries L.S -

(c) 500 MTon Jack


(10 Nos per 1 Time)
Foreman Man-Day 6
Steel Fixer Man-Day 11
Head Worker Man-Day 3
Worker Man-Day 8.5
Operator /Machine Driver Man-Day 10
Electric Helper Man-Day 10
Sundries L.S -
101. Fixing of Bearing. (1000 kg)
Steel Fixer Man-Day 2
Head Worker Man-Day 2
Worker Man-Day 9
Sundries L.S -

102. Cutting steel plate to get required size (With gas)


(a) 12mm thk: (for 2500 mm)
Welder Man-Day 1
Oxygen gas kg 4.5
Propane gas kg 1.5

(b) 16 mm to 20 rnm thk: (for 2500 rnrn)


Welder Man-Day 1.5
Oxygen gas kg 5
Propane gas kg 1.5

(c) 25 mm to 30 rnrn thk: (for 2500mm)


Welder Man-Day 2
Oxygen gas kg 6
Propane gas kg 1.5

103. Welding work. (one ply:)


(for 2500mm)
welding rod (5kglpkt) Pkt 0.2
Welder Man-Day 1
Standard Data for Working Out Rates Per Unit Quanlily of Items of Work-contd.

;r Unit Quantio Remarks


Particulars of Materials and Labour
Jo.
Steel Plate Girder
04. Preassembling of steel plate girder according
to design on the ground. (1000 kg)
Skilled Worker Man-Day 2.5 Including Loading,
Worker Man-Day 3.3 Unloadtig and shifting
Sundries L.S -

05. Fixing ,Initial & final tightenning of bolt &


nuts and drip pins according to the design while
assembling steel plate girder .(I000 Nos)
Skilled Worker Man-Day 2
Worker Man-Day 1.5
Sundries L. S -

06. Installation of preassembled steel plate girder


by crane as per drawing from pier to pier.
(1 000 kg)
Skilled Worker Man-Day 2
Worker Man-Day 2
Sundries L.S -

07. Checking to final tightenned bolt nuts with


checking spanner whether standard or not.
(1 000 Nos)
Skilled Worker Man-Day 0.8
Sundries L.S -

,08. Placing bearing plate and fixing bolt & nut.

Skilled Worker Man-Day 1


Sundries L.S -

Suspension and Cablestayed Bridge


109. Cutting and cleaning main cable (For 10 m) - Moving main cable coin
Skilled Man Man-Day 1 to cutting place by cran
Head Worker Man-Day 1 - Cleaning main cable
Worker Man-Day 1 - Levelling ground and
Machine Driver / Operator Man-Day 0.1 setting turn table for
Sundries L.S - cutting main cable with
wheel cutter & chain
block to get specified
length.
- Transferring cutted mai
cable
3I
Standard Data for Working Out Rates Per Unit Quantity ofllems of Work-confd.

Sr
Particulars of Materials and Labour Unit Quantity Remarks
No.
110. Taking out and cleaning running cable from
Cable Drum and placing them on timber crib
(For 10 m)
Skilled Man Man-Day 0.1
Head Worker Man-Day 0.1
Worker Man-Day 0.1
Sundries L.S -

111. Fixing running cable on Winch Drum at


Up stream and Down stream (For one winch)
Skilled Man Man-Day 3
Head Worker Man-Day 4.5
Sundries L.S -

112. Taking out and cleaning Pilot Cable from Cable


Drum and placing them on
timber Crib (For 10 m)
Skilled Man Man-Day 0.3
Head Worker Man-Day 0.2
Worker Man-Day 0.4
Sundries L.S -

113. Fixing step by step steel wire rope Pilot Cable


on each side of Anchor on high Level.
(For lm)
Skilled Man Man-Day 0.3
Head Worker Man-Day 0.2
Worker Man-Day 0.1
Sundries L.S -

114. Fixing Travelling Cage by safety belt on high - Including installation of


level of Tower with Pulley Travelly. lock, Bull Dog Grip
(For 1 Cage)
Skilled Man Man-Day 13.5
Helper for Skilled Man Man-Day 7.5
Head Worker Man-Day 1.5
Electrician Man-Day 0.8
Sundries L.S -
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-confd.

3r Unit Quantit Remarks


Particulars of Materials and Labour
qo. - - ~

15. Fixing 5 Mton winch According Tower Anchor Including timber support

Alignment (For one winch) and wedging according


Skilled Man Man-Day 3 inline of Anchor slab

Helper for Skilled Man Man-Day 4.5


Sundries L.S -

Fixing Supporting Frame Anchor Plate system- Including temporary

tically according cable alignment behind welding work

Anchorage. (For 1 Anchor Supporting Frame)


Skilled Man Man-Day 3
Welder Man-Day 1.5
Worker Man-Day 6
Sundries L.S -

After installation main cable, dismantling


and cutting supporting Anchor Frame, extra
Anchor Plate ( For 1 Anchor Supporting
Frame.)
Skilled Man Man-Day 1
Welder Man-Day 0.5
Worker Man-Day 1.8
Sundries

118. Fixing roller by welding on high level of Tower


with safety belt. (For 1 No)
Skilled Man Man-Day 0.5
Welder Man-Day 0.3
Operator of welding M/C Man-Day 1.3
Worker Man-Day 1.8
Sundries L.S -

119. Making for Cable clamp systemmatically and


making hole for Bolt & Nut For Tower Tilting
work. (For Cable clamp 1 set)
Welder Man-Day
Helper For Welder Man-Day
Sundries L.S

120. Fixing firmly Over lapping at least 5MTon Chain


Iblock, Steel Wire rope with Bull Dog Grip at
33
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.

Particulars of Materials and Labour Unit Remarks


nall Anchor For Tower Tilting.(For small
achor (Dead men) 1 No)
Skilled Man
Sundries

king Over Lapping and chainging way of chain


)r 10 MTon Chain Block at 10 MTon pulley
tee1 Wire with Bull Dog Grip at Anchor Canopy
or Tower Tilting.
:or Anchor 1 Point)
Skilled Man tan-Day
Worker Ian-Day
Sundries L.S

urning back Tower According specific


besign For TowerTiting.
For One Tower (2)Nos)
Skilled Man tan-Day
Worker Ian-Day
Sundries L.S

'ransfering cable from stockyard to Anchorage


by men and placing one on another (8)shape
In timber crib. (For 10 m)
Skilled Man
Head Worker
Sundries

nstallation of Main Cable for Bridge (For1Om)


Skilled Man Inserting Main Cable to
Head Worker Anchor Plate
Electrician a Putting on place upon
Mechanic temporary rope
Welder . holding upon Main Cab1
Sundries at saddle at each Tower
with B.D Grip by safety
belt and layer with Filler
stand
. Transfering cable from
one Tower to another
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.

Sr Unit Quantity Remarks


Particulars of Materials and Labour
No.
- Taking out cable from
Anchor Plate of Ancho-
rage
- Checking Cable of Back
stay between Tower and
Anchorage
- Numbering cable by
layer and layer
- Installation of Main
Cable on high level over
water by life jacket and
safety belt
125. Installation of Cable Top Clamp.
(a) (For Cable Clamp 1 set)
Skilled Man Man-Day 14 - Joining heavy Cable
lamp to
Head Worker Man-Day 3 Travelly by pulley and
Electrician Man-Day 4 chain block
Sundries L.S - - Specified cable marking
on main cable

(b) Tightening Bolt & Nut for one time


(For 10 Nos of Bolt)
Skilled Man Man-Day 0.3 - Doing difficulty on high
Electrician Man-Day 0.1 level of Main Cable
Sundries L.S -

(c) Painting Enamel paint for cable Top Clamp on


high level (For 1 no of Top Clamp)
Skilled Man Man-Day 0.4
Sundries L.S -

126. Installation Suspender Rod


(a) (For Suspender Rod 1 No)
Skilled Man Man-Day 7 - Fixing Suspender Rod
on main cable with Hing
Head Worker Man-Day 2 shaft and safety pin
Worker Man-Day 0.5 - Transfering suspender
Sundries L.S - rod to working area
by Manpower
35
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.

Sr Unit Quantity Remarks


Particulars of Materials and Labour
No.
(b) Threading Suspender U bolt ,painting grease,
Checking Bolt & Nut washer and Specifing
U Bolt marking
Skilled Man Man-Day 0.1
Head Worker Man-Day 0.1
Sundries L. S -

(c) Painting Enamel paint for Suspender rod by


safety belt on high level
Skilled Man Man-Day 0.1
Head Worker Man-Day 0.1
Sundries L.S -

127. Adjusting Back stayed (for 1Om)


Skilled Man Man-Day 0.2
Head Worker Man-Day 0.1
Sundries L.S -

128. Stressing Main Cable and Specifing Elongation


within Anchor according specified tension.
(For 1Om)
Skilled Man Man-Day 1
Head Worker Man-Day 0.1
Sundries L.S -

129. Grouting Cement motor for Cable Guide Tube


within Anchor after stressing Main cable.
(For 1Om)
Skilled Man Man-Day 3.5
Mechanic for Grout pump Man-Day 0.5
Electrician Man-Day 0.5
Head Worker Man-Day 5
Sundries L.S -

130. Releasing binding cable Working length position


of Main Cable For Enclosing Blockafter
stressing.
( For 1 No of cable )
Skilled Man Man-Day 0.5
Sundries L.S -
36
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.

Sr
Particulars of Materials and Labour Unit Quantity Remarks
No.
131. Adjusting and cutting layer of cable to
install Anchor Plate For Stressing.
(For 1 No of cable)
Skilled Man Man-Day 0.1
Sundries L.S -

132. Shifting bailey (or) Steel truss on ground for


PreAssembling work. (For 1000 Kg)
Skilled Man Man-Day 1.5
Head Worker Man-Day 1.5
Sundries L.S -

133. Preassembling work for bailey (or) steel truss.


(For 1000 Kg)
Skilled Man Man-Day 5
Head Worker Man-Day 0.5
Sundries L. S -

134. Shifting heavy bailey (or) Steel Truss from


Preassembled Yard to join cable car by Crane
(For 1000 Kg)
Skilled Man Man-Day 0.8
Head Worker Man-Day 1
Sundries L.S -

135. Fixing preassembled bailey (or)Steel Truss on


Suspender Rod of Main Cable.
(For 1000 Kg)
Skilled Man Man-Day 7.5
Head Worker Man-Day 10
Sundries L.S -

136. Fixing Safety Net (For 1m)


Skilled Man Man-Day 0.5
Sundries L.S -

137. Removing safety Net (For 1m)


Skilled Man Man-Day 0.2
Sundries L.S -
37
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.

Sr
Particulars of Materials and Labour Unit Quantity Remarks
No.
138. Laying systematically small Transon walk way
and Checking, Laying Decking Beam
(For 1000 Kg)
Skilled Man Man-Day 9.5
Sundries L.S -

139. Canying Decking Beam and small Transon


difficulty by man power on temporary walkway
at high level of main bridge. (For 1000 Kg)
Skilled Man Man-Day 2
Sundries L.S -

140. Putting heavy Decking slab on main bridge


by crane (For 1000 Kg)
Skilled Man Man-Day 0.8
Head Worker Man-Day 1.3
Sundries L.S -

141. Adjusting bailey (or)Steel truss of main bridge


to get specified camber by wing temporary
cable and Cushion Block. (For Suspender
Hanger 1 Point)
Skilled Man Man-Day 3.5
Sundries L. S -

142. Jacking Down bailey (or)Steel truss with right


alignment to get final R.L by using 30 MTon
Jack Cushion Block and M.S Plate.(For one Pier)
Skilled Man Man-Day 13.5
Sundries L.S -

143. Fixing Bearing Bolt to Bearing Mat and Bailey - Include adjusting bottom
(or)Steel truss Pin to Bearing Mat & Bailey surface of Bearing Mat
(or)Steel truss. (For one Pier) to get specified R.L.
Skilled Man Man-Day 12
Sundries L. S -

144. Pouring High Strength Concrete to get required - Including cushion.


Bearing Level (For 1 Bearing)
Skilled Man Man-Day 5
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
39
Standard Datafor Working Out Rates Per Unit Quantity of Items of Work-contd.

Sr Quantity Remarks
Particulars of Materials and Labour Unit
No.
152. Reading and specifying the centre of the Bored
pile when driving stand pipe from control point
by using theodolite.(l Time)
Surveyor Man-Day 0.5
Helper Man-Day 0.5

153. Surveying and specifying concrete top level to


pour bored concrete.(l Time)
Surveyor Man-Day 0.5
Helper Man-Day 0.5

154. Checking Bored Pile position after pouring


concrete. (1 Time)
Surveyor Man-Day 0.5
Helper Man-Day 0.5

155. Surveying and Checking Bored Pile after pouring


concrete to know stable or unstable. (1 Time)
Surveyor Man-Day 0.3
Helper Man-Day 1

156. Surveying and specifying Cap position of


Abutment or Pier.(l Time)
Surveyor Man-Day 1

157. Surveying and Checking settlement of pier cap in


water. (1 Time)
Surveyor Man-Day 1

158. Surveying and specifying Shaft position of Abutment


or Pier.(l Time)
Surveyor Man-Day 1

159. Surveying and specifling Bearing position of


Abutment or Pier. (1 Time)
Surveyor Man-Day 1

160. Specifling and Checking Level to fix M.S Rod in


Pile Cap, Shaft ,Cross-beam. (1 Time)
Surveyor Man-Day 0.5
Helper Man-Day 0.5
Standard Data for Working Out Rates Per Unit Quantity ofltems of Work-contd.

Particulars of Materials and Labour

Levelling Cap (or) Shaft (or) Cross Beam in their


form works before pouring concrete. (1 Time)
Surveyor
4
Unit

Man-Day
Quantity

0.3
Remarks

Helper Man-Day 1
I
162. Rechecking position of Pile (or)Cap (or) Shaft (or)
Cross Beam after concreting. (1 Time)
Surveyor Man-Day 0.5
Helper Man-Day 0.5

163. Surveying bearing hole depth to get right depth


before pouring concrete for one pier. (1 Time)
Surveyor Man-Day 0.5
Helper Man-Day 0.5

Surveying ,Checking and specifying centre of


Abutment (or) pier systematically. (1 Time)
Surveyor Man-Day 0.3
Helper Man-Day 0.5

Surveying and Checking bottom ground of Pier in


water. (1 Time)
Surveyor Man-Day
Helper Man-Day

Transfering and rechecking level Mark for specifiec


place from one bench Mark to another.(100 m)
Surveyor Man-Day 0.3
Helper Man-Day 0.3
I
Surveying Echo Sounding Pier in water and water
level daily. (1 Time)
Surveyor Man-Day 0.5

Fixing bearing for one pier of main bridge (or) 1


Approach bridge (Position or Grouting to fix bearing
hole position Bearing.) (1 Time)
Surveying Position
Surveyor Man-Daj
Helper Man-Daj
41

Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.

Sr Remarks
Particulars of Materials and Labour Unit Quantity
No.
(b) Rechecking position.
Surveyor Man-Day 3
Helper Man-Day 3

169. Fixing bearing for one pier of main bridge (or)


Approach bridge(Position or Grouting to fix bearing
hole position Bearing.) (1 Time)
(a) Levelling
Surveyor Man-Day 0.5
Helper Man-Day 0.5
(b) Rechecking level
Surveyor Man-Day 0.5
Helper Man-Day 0.5

170. Surveying and Rechecking 18m(or)21m(or)24m(or)


27m(or)30m Girder for pouring concrete. (1 No)
Surveyor Man-Day 0.3
Helper Man-Day 1

171. Surveying for erection of main truss to get specified


(a) level. (1 Time)
Surveyor Man-Day 0.3
Helper Man-Day 1

(b) Surveying ,Leveling and checking for erection of


main truss to get specified level. (1 Time)
Surveyor Man-Day 0.3
Helper Man-Day 1

172. Surveying and Checking Level for Laying Precast


slab and finished level. (1 Time)
Surveyor Man-Day 0.5
Helper Man-Day 0.5

173. Surveying and specifjing Center line for installation


of Road Curb and Hand Rail. (1 Time)
Surveyor Man-Day 0.5
Helper Man-Day 0.5
Standard Data for Working Out Rates Per Unit Quantity ofItems of Work-contd.

Sr
Particulars of Materials and Labour Unit Quantitj Remarks
No.
174. Surveying and specifLing level for installation of
Road Curb and Hand Rail. (1 Time)
Surveyor Man-Day 0.5
Helper Man-Day 0.5

175. Surveying and specifling level for laying AC.(l Time)


Surveyor Man-Day 0.5
Helper Man-Day 0.5

176. Surveying Overlay, Road Curb, Hand Rail and AC


to get right alignment. (1 Time)
Surveyor Man-Day 0.3
Helper Man-Day 1
177. Surveying Precast Slab, Overlay, Road Curb,
Hand Rail level. (1 Time)
Surveyor Man-Day 0.3
Helper Man-Day 1

178. Surveying position of anywork before starting work


(a) (Excavation or Fixing Reinforcement and forrnwork
or Pouring concrete or embedded plate or Hand Rail
or Road Curb or P.C Girder or Collosion Barrier or
Decking slab or Girder Overlay or AC or Anchor
Box or Bored Pile or Stand Pipe or Keyline or Cap
Skirting or Road or Drain or Box Culvert or Steel
Truss or Pier Cap or shaft Cross-beam or Abutment
or Retaining Wall or Rail Road or Vertical devia -
tion.) (1 Time)
Surveyor Man-Day 0.5
Helper Man-Day 0.5

@) Rechecking position of anywork after working.(l Time)


Surveyor Man-Day 0.5
Helper Man-Day 0.5

179. Surveying alignment (Center Line)of anywork before


(a) working. (1 Time)
Surveyor Man-Day 0.5
Helper Man-Day 0.5
43

Srandard Data for Working Out Rates Per Unit Quantity ofltems of Work-contd

Sr
Particulars of Materials and Labour Unit Quantity Remarks
No.
(b) Rechecking alignment (Center Line)of anywork after
working. (1 Time)
Surveyor Man-Day 0.5
Helper Man-Day 0.5

180. Surveying and levelling anywork before working.


(a) (1 Time)
Surveyor Man-Day 0.5
Helper Man-Day 0.5

(b) Rechecking level of anywork before working.(l Time)


Surveyor Man-Day 0.5
Helper Man-Day 0.5

181. Surveying and checking settlement (Main Bridge or


Approach Bridge or Highway or Railway.)(l Time)
Surveyor Man-Day 0.5
Helper Man-Day 0.5

182 Checking for theodolite level and E.D.M instrument


which are used for surveying in bridge construction.
(a) Theodolite Calibration. (1 Time)
Surveyor Man-Day 0.5
Helper Man-Day 0.3

(b) Level Calibration. (1 Time)


Surveyor Man-Day 0.5
Helper Man-Day 0.3

(c) E.D.M Calibration. (1 Time)


Surveyor Man-Day 0.5
Helper Man-Day 0.5

183. Determination of Pier Position by E.D.M including


finding distance between piers etc; other relevant
or equivalent works.(l Time)
Surveyor Man-Day 0.5
Helper Man-Day 1.5

184. Level Net Survey Calculation & Drawing.(l Time)


Surveyor Man-Day 2
Helper Man-Day 4
44
Standard Datafor Working Out Rates Per Unit Quantity of Items of Work-contd.

Sr
Particulars of Materials and Labour Unit Quantity Remarks
No.
185. Triangulation Net Survey
(a) Basic Line Measurement (1 Time)
Surveyor Man-Day 3
Helper Man-Day 4.5

(b) Calculation & Drawing.(l Time)


Surveyor Man-Day 2
Helper Man-Day 4

(c) Check Base & Distance Measurement(1 Time)


Surveyor Man-Day 0.5
Helper Man-Day 0.5
45
Standard Data for Working Oui Rates Per Unit Quantity of Items of Work-contd.

Sr
Particulars of Materials and Labour Unit Quantity Remarks
No.
MISCELLANEOUS NOTES

1 For contractor's profit and overheads


(Taxes ,safety charges ,management & etc.) L.S -

2 For Bridge Machinery Work


(Use according to rate of analysis of Machanical
Department.) L. S -