Professional Documents
Culture Documents
Demolition Method Statement PDF
Demolition Method Statement PDF
STATEMENT
FOR
AT
This h&s plan & method statement has been prepared to demonstrate the safe working
method for the soft-strip of internal fixtures/fixings and identified items, asbestos
removal and demolition of the existing FLYING HIGH ACADEMY,TOWNROE DRIVE,
MANSFIELD, NG19 6JN.
This method statement is intended to be a live document in accordance with the CDM
Regualtions 2015. Any amendments to this method statement due to unforeseen circumstances
will be agreed in writing by the Project Director, Safety Adviser, Project Supervisor & forwarded
to the Principal Designer/Clients Representative as appropriate.
3. PROGRAMME OF WORKS
4. EXISTING SERVICES
5. SAFETY PROCEDURES
7. SAFETY ARRANGEMENTS
11. ACCESS
15. ARISINGS
19. METHOD
The works are located at Flying High Academy, Townroe Drive, Mansfield. This is a heavily
populated residential area of Mansfield.
The works, in summary, involves the strip out, including asbestos removal and demolition of the
part single storey, part two storey existing Flying High Academy which is to be replaced by a
new school, currently under construction on the adjacent site.
RETAINING ITEMS
• Areas of hard landscaping retained by the school as per the appended landscape plan
• Any other TBA;
Any items for retention by the Client/CA will be documented, marked and relayed to all site
operatives.
Demolition works which fall outside the development boundary covered by Planning
Application Ref. 2/2014/0531/ST are to be carried out to slab level only, with the
slab/footings and associated hardstandings remaining.
3. PROGRAMME OF WORKS
Demolition – Soft strip of internal fixtures/fittings items & removal from site;
Removal of ACM’s;
Structural demolition by mechanical means of remaining structure/s;
Sifting of materials for removal from site;
Breaking up concrete slab;
Grub up footings;
Clearance of site to suitable standards.
4. EXISTING SERVICES
All service items which are to be retained will be suitably marked and brought to the attention
of all operatives through on site tool box talks to ensure all persons are aware of the exact
location of same. All work carried out to or which affects new or existing services will be in
accordance with the bye laws or regulations of the relevant statutory authority.
Internal temporary electricity will be supplied by use of generators. These will be sited to
prevent disturbance to neighbouring properties through noise/fumes etc. and will be effectively
earthed. All cables off will be suitably marked and placed so as to prevent tripping and
damage.
Portable & hand held electric tools shall not exceed 110v and shall be inspected as per the
established maintenance system:-
User Check - Weekly
Visual Inspection - Monthly
Combined inspection and test before use and thereafter 3 monthly.
Central & task lighting will be installed as appropriate and conform to BS & IEE standards.
5. SAFETY PROCEDURES
All operatives will be made aware of the extent and location of the works, informed of any
restricted areas and possible areas where interaction with operatives or others is liable to be
hazardous.
DANGER DEMOLITION signs and exclusion zone barriers will be erected to all areas as required.
Any additional signage will be erected as required.
Edge protection, installed by a specialist contractor, will be erected to all areas where there is a
risk of falls. Signage will be affixed to each barrier advising ‘remove this = lose your job’.
All areas referred to in the Location and Description of the works are closely surrounded by a
residential environment. Extreme caution will be implemented when access and egress to the
site is required. Exclusion zone fencing is to be erected to encompass all site boundaries and
internal exclusion fencing is to be erected where needed to prohibit access by site operatives
into danger zones i.e. within the working radi of the excavator / drop zones etc;
All employees will ensure that the site is maintained in a clean and tidy manner. Removing
scrap metals and debris from the work area progressively. (Good housekeeping).
Kier Issue 03 Dated 14.10.2015 Job No. N2038
Flying High Academy, Townroe Drive, Mansfield
7
NOTE: No fires are to be set on site, and no burning of any arisings will be carried out at any
point.
Special Care will be taken to eliminate the risk of FIRE where hot cutting works are required.
All `hot works` will be under Kiers Permit to Work Systems to be implemented by the Site
Manager. Fire extinguishers of a suitable type will be on hand, as will a banksman assigned to
fire watch. NB Cold cutting to be employed where highly flammable materials are present or
there is a risk of lead coatings.
Access/Egress:-
The main entry point will be Via the entrance off Townroe Drive. This will be the point of entry
to site for deliveries and disposal. Restrictions apply to the timing of vehicular access. No
demolition traffic will arrive or leave site between 08.00 and 09.15 and 14.30-15.45.
The following controls will be initiated at the access/egress point to the carpark.
• This route will be manned THROUGHOUT THE WORKS to control traffic flow and aid
others accessing the surrounding areas;
• The banksman will oversee all movement of plant/vehicles requiring access to the site;
• Signage will be erected to advise all persons accessing the site to ‘sign in’ at the site
office;
• Signage will be erected depicting the internal designated transit / parking route and site
office with site contact telephone number;
• Signage will be erected at suitable points warning of site access point;
• The insitu gate will be locked at ‘quiet’ times.
Particular care is to be afforded by all operatives and operators of plant when accessing /
leaving site due to the continuity of the footpath which crosses this cross-over point.
Due to the nature of demolition and the waste produced, vehicles removing the waste will be of
large nature - 20T tipper wagons, skip wagons or roll-on-roll-off cointainer transports. The
frequency of these will vary throughout the demolition, but at the peak may reach 6 wagons
per hour loading excavated debris. These will be co-ordinated to avoid queing on the highway.
A copy of the access / egress route and site contact telephone number will be held within the
main office of Kier Construction and faxed to any contractor engaged for the removal of
materials or the supply of plant and machinery prior to movement taking place. This will ensure
suitable warning is given to site and enable traffic movements to be pre-planned.
A banksman will be employed for movements of construction plant / vehicles across any cross
over point and all drivers of construction traffic will adhere to the existing applicable speed
restrictions.
These access gates will be kept closed with an operative assigned to oversee all movements.
All other access gates will be locked and secured against trespass.
7. SAFETY ARRANGEMENTS
Safety, health & environmental advice and auditing is carried out by Kier’s in-house SHE
department. Their role is to make periodic site visits to advise on Health & Safety matters, to
assess hazards and risks, ensure adequate controls are implemented and monitored and to
assist in the on-going training of company operatives.
2. Noise and Dust are environmental hazards affecting both operatives and people in the
immediate vicinity during demolition and loading procedures.
3. The nature of intended work at height creates an on going hazard during the removal
process.
4. Falls from height, falling materials and tools, slips, trips, cuts and scrapes.
6. Asbestos – ensure all works are carried out as per the written method
There will be one fully trained NFDC/NDTG site supervisor involved in the project.
All operatives to be employed on site will have completed the Safety Awareness Course for
Demolition Operatives. All operatives are bona-fied 'CSCS – CCDO Ticket' holders or have
applied under the scheme and awaiting their cards (evidence of this will be held on site within
the main site file). All personnel will adhere strictly to the Codes of Practice for Demolition BS
6187:2011.
All site operatives are to attend Kier Site Induction prior to commencement of the project. The
Project Supervisor/s will ensure Tool box talks are given on assignment of work tasks and
additional talks given on a weekly basis.
All further training deemed necessary to carry out the safe conclusion of the works will be
appropriated. Specialist training courses e.g.; MEWP, Abrasive Wheels, will be carried out to
suit requirements.
The following items of Personal Protective Equipment will be worn on site by all operatives.
ii HOT-CUTTING OPERATIVES
As i above, gauntlets, flame retardant overalls, tinted visor
All PPE will be issued to operatives as and when conditions of work and or when deterioration
of existing issue is noted. Each operative is responsible for ensuring the good condition of his
PPE. (Regulation 11. PPE Regs’ 1992 ) The Site Supervisor will monitor all PPE on a daily basis
as part of the on going Health & Safety programme. A register of all PPE issued is kept on site.
11. ACCESS
Access to any above ground work areas will be achieved using one or more of the following
safe means of access, as appropriate.
All work covered by this Method Statement will be undertaken with due regard for the Control
of Substances Hazardous to Health Regulations 2002.
Additional assessments will be prepared for any residual materials contained within the building
and encountered during the works.
Risk Assessments have been carried out as required by the Management of Health & Safety at
Work Regulations 1999 to document all perceived risks in respect of operations carried out on
site.
These will be conveyed to all operatives during site induction and made available for the
duration of the works. Further assessments will be carried out as the works progress and the
necessary controls implemented.
• Site accommodation with sufficient space and seating arrangements for the number of
operatives employed on site, to allow them to take meal breaks with the facility for hot
water and food warming.
• Drinking water
• Washing facilities with a supply of hot running water, including a supply of soap and
towels.
• Suitable and sufficient plumbed in toilet facilities.
• Clothes drying facilities.
Arrangements will be made for all toilets and welfare facilities to be cleaned and restocked on a
regular basis.
Should the number of operatives on site increase, additional sufficient welfare facilities will be, if
required, placed on site.
15. ARISINGS
All arisings from these works will fall into four main categories;
1) Clean Material of Commercial Value. e.g.; Scrap metals, reclaimed building materials.
These will be handled with the necessary care and transported from site by road
transport for commercial disposal/recycling in full conformance with the Waste (England
& Wales) Regulations 2011. Duty of care ticket to be produced for each consignment off
site.
2) Concrete and Brick Rubble:- This will be handled by mechanical methods and removed
from site in full conformance with the Waste (England & Wales) Regulations 2011.
3) Paper, Wood and other:- Will be removed from site via road transport and where
applicable will be in full conformance with the Waste (England & Wales) Regulations
2011. Duty of care ticket to be produced for each consignment off site.
4) Asbestos & Hazardous Waste Materials :- Care to be taken that all ACMs are sealed
within the confines of hazardous areas, and kept segregated from other waste streams.
This and any other hazardous waste discovered in the course of the demolition is to be
disposed of via licenced carriers to a licenced tip in a manner appropriate to the waste
material encountered.
The safety of the General Public is of paramount importance to the operation in particular to
those accessing the public footpaths and surrounding town centre environment, and employees
accessing their place of work. Banksmen will be employed and movements of waste
programmed to reduce risk to the lowest level practicable.
Kier Issue 03 Dated 14.10.2015 Job No. N2038
Flying High Academy, Townroe Drive, Mansfield
13
Danger Demolition signs will be erected in prominent locations around the boundary of the site
to warn of the dangers of access to the working area. In addition Heras type fencing panels
will be mounted to create exclusion zones around hazardous areas (i.e. openings to floors etc.)
and the working areas as work dictates.
CLIENT
Kier Construction Tel:
Marriott House Fax:
Abbeyfield Road e-mail: martin.burton@kier.co.uk
Lenton Lane Ind Est Mobile:
Notts Contact Martin Burton
NG7 2SZ
PRINCIPAL DESIGNER
TBC Tel:
Fax:
e-mail:
Mobile:
Contact
Contact
STRUCTURAL ENGINEER
TBC Tel:
Fax:
e-mail:
Mobile:
Contact
APPOINTED SUB-CONTRACTOR
A ‘Daily Hazards Board’ will be displayed in the site canteen/messroom (or other prominent
position) detailing specific hazards to be noted and morning briefing carried out to remind all
persons working on the site to bring to the attention of the Site Supervisor any matters relating
to health and safety which they think require remedial action.
Operatives are encouraged to raise issues they see or foresee on site. The Site Management
will consider their comments and take appropriate action. They will inform the person who
raised the issue of the action taken or the reason why no action has been taken.
They will inform the person who raised the issue of the action taken or the reason why no
action has been taken.
If the Site Management raises any health issues with Contractor's Supervisors or employees,
they will record an entry in the site diary, outlining the problem and action taken.
An internal weekly progress meeting will be held with all project management personnel.
18 PROJECT RESOURCES
Access Equipment:
Tower/podium Scaffold Unit/s – of varying sizes dependent on space available;
LADDERS OR STEP LADDERS ARE NOT PERMITTED ON KIER SITES – SUPERVISOR CARRY OUT
AN ASSESSMENT FOR EACH AREA REQUIRING ‘WORKING AT HEIGHT’
19. METHOD
METHOD 1.1
SITE SET UP
• Inspect site fencing and ensure sufficient designation of areas for waste skips / storage etc.
• Liaise with any adjacent properties to ensure all are aware of the works.
• Collate all applicable information relating to requirements of adjacent properties regarding
access, movement etc.
• Liase with main office / Local Authority to ensure all applicable licenses etc. are in place for
the specific works area.
• Site all applicable signs (all visitors report to site office / danger demolition / hard hat signs
etc), including main Contract sign, as depicted within tender documentation.
• Erect additional fencing as required.
• Carry out inspection of all fencing etc. to ensure security is maintained and put in
appropriate additional measures where required.
SITE COMPOUND:
First task will to designate and position the following:-
• Fuel storage area;
• Oxy/Propane storage area (vented cage showing empty & full);
• Equipment / Plant storage area.
DOCUMENTS:
Site supervisor / designated person:
• To post F10, H&S Poster, Site Rules, Method Statements, Risk Assessments, First Aid
requirements Section 80 building control etc. within provided site cabin.
METHOD 1.2
• NOTE:
o ALL SERVICES ON THIS PROJECT ARE TO BE DISCONNECTED/ISOLATED BY
ARRANGMENT OF THE CLIENT.
o PERMIT TO DIG TO BE OBTAINED FROM KIER PRIOR TO BREAKING OF
GROUND;
o DUE TO CONTINUATION OF ADJACENT PROPERTIES THROUGHOUT THE WORKS
A CAT SCAN IS TO BE CARRIED OUT & ALL SERVICES NOTED MARKED UP AND
PROTECTED THROUGHOUT THE WORKS – WHERE NECESSARY THIS WILL
INCLUDE ERECTION OF INTERNAL HERAS FENCING TO SEGREGATE THE
SERVICE RUN TO PREVENT ACCESS BY PLANT/MACHINERY ETC.
1.2.1 INVESTIGATION:
Information concerning existing services within the site and surrounding area has been
obtained from the client. Supervisor Note: No certificate – No start
All isolation / diversion / purging of M&E supplies are to be carried out by others therefore
written confirmation will be received from the Client by site supervisor before commencement
of demolition works.
Any retained services will be marked with suitable high visibility materials and road plates
positioned over all cross over points required
A competent external contractor will be engaged to carry out these works where required
(these works will be instructed and be under the control of Kier).
RECORDS
The site supervisor will ensure that all information relating to location of all capped services is
relayed to the CDM Co-Ordinator for inclusion in the File.
EMERGENCY PROCEDURES
First Aid
The requirements for first aid provision are contained in the Health and Safety (First Aid)
Regulations and the Approved Code of Practice to the Regulations.
A first aid box is provided in the [Site Supervisor’s Office]. The contents are as indicated in the
Company Safety Policy.
The Site First Aider will be responsible for ensuring that the contents are replaced as necessary.
A trained First Aider is available on site. The name of that person and the location of the first
aid box is posted in the messroom/canteen.
Medical Assistance
The phone number of the nearest hospital and route is displayed on the site notice board.
A copy of the A-Z map for the area with the route to the nearest hospital accident and
emergency unit clearly highlighted will be pinned to the wall of the site office with the note
`Remove and use in the Case of Emergency`.
The following notice will be pinned within the site welfare facility and where necessary due to
work locations, distributed to all personnel on site.
Emergency services to enter via `Access Point` off Tounroe Drive (or other as instructed -
dependant on position of fire).
EMERGENCY PLAN
The Management of Health and Safety at Work Regulations require every employer to prepare
a plan which sets out the action to be taken in the event of any emergency.
a. Introduction
The aim of this plan is to highlight any situation, which will require the evacuation of all, or part
of the site and to outline the procedure to be followed. This will help to identify quickly whether
any personnel are missing and set in motion the rescue procedures.
Fire in cabins or vehicles, explosion or fire in the site area or compound caused by LPG,
accidents in confined spaces or scaffold collapses.
b. Control
Control over any incident will be exercised by the Site Supervisor who will remain at the main
assembly point throughout.
They will detail one person to act as a guide for the emergency services. The guide should be
positioned at the main entrance to the site.
c. Communication
A representative from the Company will man the site mobile telephone throughout the
emergency and will be responsible for alerting the emergency services.
d. Assembly Point
The assembly point(s) will be at – SITE ACCESS POINT.
e. Action on Fire
All Contractors:
• Isolate any gas appliances.
• Go directly to the assembly point and report to the Site Supervisor.
• The Senior Person from each Contractor must check if anyone is missing. At the assembly
point, Contractors are to report to their supervisors and all other persons are to report to
Site Management.
Site Supervisor:
• On being alerted of an incident, sound the alarm (if appropriate).
• Obtain outline details of the emergency and alert the emergency services.
• Detail a guide to direct the emergency services onto the site.
• Detail a member of the management team to man the telephone.
• Go to the assembly point and assess the situation.
• Check with Contractors if any operatives are missing.
• Standby the Fire Fighting Team (if appropriate).
• Receive and brief the emergency services, giving the location of the emergency water
supplies/hydrants (as appropriate).
h. First Aid
A first aid kit must be taken to the assembly point. The trained First Aider must report to the
Assembly Point.
i. Emergency Services
• The Fire Service should be summoned to all the above incidents (f; g or h). The Ambulance
Service must be summoned to any confined space incident, LPG explosion or drowning
incident. They should be summoned to any fire or other incident if it is thought that there
has been an injury.
• The Site Supervisor at the assembly point will receive and brief the emergency services,
giving details of any missing personnel.
Scope of works:
• Erection of internal fencing to designate internal zones; protect operatives from
hazardous areas (i.e. drop-zones; openings to floors; segregate further contractor/s from
demolition zones).
• Erection of external boundary security fencing to all elevations required (i.e. internal
roadways / car-park etc. to form exclusion zone).
1. Site Supervisor to refer to site layout plan showing exact layout of fencing and access
points;
2. Calculate required number of panels / blocks to each area and designate ‘drop off’ area
for required number of panels at each elevation;
3. Instruct delivery driver to position required amount at each designated point to reduce
manual handling risk;
4. Phase works to ensure unimpeded access for further deliveries (welfare / storage units
etc);
5. Site supervisor to appoint ‘gang’ to erect same ensuring all are issued with correct PPE:
Safety Boots to protect crushing of feet; Rigger gloves to prevent cuts, grazes etc. and
high visibility jacket/vest to ensure visible to all others on site particularly vehicle drivers.
6. Two operatives will be assigned to position bases – these operatives will be instructed in
the correct lifting procedures to prevent manual handling problems – and two further
operatives will follow through with the fencing panels and fixings.
7. On completion the operatives will affix warning notices to all elevations.
8. The site supervisor to assign one operative to inspect boundary fencing at start and end
of shift to ensure all panels / clips in place etc. Any non-conformities to be reported to
supervisor immediately.
I have read this method statement specific to the work tasks which I am to carry out. I have brought to the attention of the
supervisor any areas of the method which I do not understand and have had them explained. I understand it is my duty to
ensure the safety of myself and others around me and will bring to the attention of the supervisor any unsafe work practices or
conditions which come to my attention. I will wear all necessary PPE/RPE.
SOFT STRIP
NOTE #1: - PRIOR TO ANY WORKS COMMENCING SPEAK TO THE SITE SUPERVISOR
TO ENSURE ALL LOCATIONS OF ASBESTOS CONTAINING MATERIAL ARE KNOWN –
DO NOT REMOVE ANY ITEMS WHICH WILL CREATE DISTURBANCE OF THIS
MATERIAL.
NOTE #2:- IF YOU LOCATE ANY SUSPECT MATERIAL STOP WORK AND REPORT IT
IMMEDIATELY TO THE SITE SUPERVISOR & INFORM OTHERS AROUND YOU.
NOTE #6:- ENSURE THAT THERE IS ADEQUATE MEANS OF ESCAPE FROM YOUR
WORKING AREA AND FIRE FIGHTING EQUIPMENT AVAILABLE AT THE WORK-FACE.
ADVISE THE SITE SUPERVISOR OF ANY CHANGES TO ESTABLISHED FIRE EXIT
ROUTES THAT ARE CREATED BY YOUR WORKS.
The works involves the removal (soft strip) of all internal fittings – to include:-
1. Strip out of internal items to include removal of all redundant services, fixtures, fittings,
partitioning, floor coverings etc;
PRIOR TO COMMENCEMENT:-
All operatives will receive on site induction and additional tool box talks to ensure they are
aware of hazardous areas, any drop-zones and exact location of the works, emergency routes
etc. specific to the work zone.
Kier Issue 03 Dated 14.10.2015 Job No. N2038
Flying High Academy, Townroe Drive, Mansfield
24
Ensure appropriate disconnection certificates are available for services feeding the area.
Suitable signage and exclusion zones will be erected to prevent/alert persons of the risk of
entering the working area during soft-strip operations. Where removal of items is carried out at
height no persons will be allowed to enter the area below the working zone.
All access equipment required for the works will be assessed and installed prior to
commencement.
All works will be carried out by the use of hand tools in a controlled manner. Where necessary
barrows/trolleys etc. will be utilised to prevent manual handling problems.
All soft strip materials will be removed from site progressively to prevent a build up of
combustible materials via the insitu rear fire escape. Priority will be given, at all times, to
others within the structure and assistance offered where required.
These items will be removed by hand and removed systematically from the work area to the
designated waste area for loading into skips for removal from the site. This will be carried out
following the generation of a suitable amount of waste materials to prevent a build-up of
combustible materials.
Care will be taken when removing abandoned waste to ensure sharp’s or chemical residues are
not present. Suitable PPE will be worn for all works.
A manual handling assessment will be carried out before lifting larger items and where the risk
cannot be adequately controlled the item will be broken up to aid movement/prevent injury etc.
2 Redundant heating units (overhead & wall mounted) and associated pipework;
Electrical cabling & lighting units;
SAFE WORKING:
All works will be carried out in a methodical manner working back towards the main fire exit
stairwell at all times. Pipework will be cut out using either quick-cut or hot cut methods or
where risk of fire pipe cutters will be employed.
Cables to overhead heater units will be severed using cable cutters and the hanging brackets
unbolted wherever possible or severed using Stihl saws.
Wall mounted heaters/radiators will be prised/dismantled from their fixings and carted from the
work area. Associated pipework/cables will be removed in a methodical manner using cable
cutters / Stihl Saws.
Lighting units will be have their cables severed and the units prised free from their fixings.
Prior to commencement
• the area below will be demarcated as a NO-GO area for all operatives not involved with the
works.
• A safe work platform will be erected in the form of tower scaffold units, the space available
will dictate on the size of the unit. This will be erected by competent operatives in
accordance with manufacturers recommendations. Toe boards will be affixed.
• Operatives to be issued with safety glasses/gloves;
Plasterboard ceiling panels will be prised from their fixings employing hand tools, any nail heads
hammered into the timber frame and timber frame supports removed to provide a neat finish;
A temporary cement bung will be installed to drainage points to seal over to prevent cross
contamination. Associated pipework will be cut back (following confirmation of disconnection of
supply via the Client) employing disc cutting equipment.
These items will be removed by hand and removed systematically from the work area to the
designated waste storage area via either barrow or trolley transfer.
A manual handling assessment will be carried out before lifting larger items and where the risk
cannot be adequately controlled the item will be broken up to aid movement/prevent injury etc.
Suitable PPE will be worn for all works. A temporary cement bung will be installed to drainage
points to seal over to prevent cross contamination. Associated pipework will be cut back
(following confirmation of disconnection of supply via the Client) employing disc cutting
equipment.
6 Removal Of Doors/Skirting/Frames
Doors: Operatives will work in pairs for these works. The doors will be unscrewed from their
fixings and carefully lowered to floor level before being moved to a designated skip.
Skirtings & Door Frames: Skirting will be removed first, followed by frames. All works to be
carried out in a controlled manner - fixings will be carefully removed or prised using small tools.
Two operatives are to be employed per frame to ensure full control is achieved
Employing hand tools the operatives will commence with removing the plasterboard covering
from the uppermost section to expose the MMMF materials behind - See specific method for
removal of MMMF materials. To control dust release localised sprays of water will be
applied as required and a polythene covering will be placed to the floor area to enable easier
clearance of the waste and prevent double handling of the plaster which could lead to excessive
dust within the atmosphere.
One gang of operatives will be appointed to carry out these works. The tiles will be lifted using
suitable hand tools in as whole a section as possible. The lifted tiles will be immediately be
placed within a wheel barrow and transported to the designated waste area to prevent tripping
hazards for the further soft-strip works.
One gang of operatives will be appointed to carry out these works and be issued with high
impact goggles, gloves and instructed to untuck trousers from their boots (to prevent ceramic
shards from entering their boots and causing injury).
The tiles will be removed employing a Kango breaker (under vibration permit system) with
spade head with only one operator working to the area at a time to prevent ejection of shards
causing injury to others. Once works are ceased or completed to the area a clearance
operative will load the tiles/shards into a wheel barrow and transport to the designated waste
area.
Removal of waste
All resultant arisings will be sorted, where necessary, removed from the work area and
positioned either:-
Environmental Monitoring
This will be carried out throughout the duration of the works. When activities of a noisy nature
or with high vibration potential are being carried out, monitoring will be carried out in line with
BS:5228 Part 1 (Code of Practice for Noise and Vibration Control on Construction and Open
Sites), to ensure that this stays within the prescribed parameters. The site supervisor will carry
out continuous monitoring with regard to dust and other disturbances.
ASSOCIATED RISK 03; 05; 06; 10, 13, 14, 17, 22, 27; 32; 40, 53, 70; 105; 110
ASSESSMENT No.’s
ASSOCIATED s.2 of the Health Safety at Work Act 1974
LEGISLATION Working at Height Regs 05;
CDM2015
Manual Handling Regs
Control of Noise at Work 2005
PUWER 98
COSHH 2002
PPE Regs. 92
I have read this method statement specific to the work tasks which I am to carry out. I have brought to the attention of the
supervisor any areas of the method which I do not understand and have had them explained. I understand it is my duty to
ensure the safety of myself and others around me and will bring to the attention of the supervisor any unsafe work practices or
conditions which come to my attention. I will wear all necessary PPE/RPE.
Material located:-
Within partitioning
Above suspended ceilings
Lagging
PREPARATORY WORKS:
All operatives involved with these works are to be instructed on the need to adopt a high
hygiene standard i.e. wash at shift end, no smoking etc.
Due to the risk of inhalation of fibres, all operatives involved will be issued with and instructed
to wear the following RPE/PPE:-
Disposable coveralls;
½ face P3 (high filtration) masks;
gloves;
goggles;
safety footwear.
REMOVAL PROCEDURE
To suppress fibre release the respective materials will be damped down by the use of an airless
spray unit or similar. Once damped the materials will be placed immediately into waste sacks
to prevent double handling and sealed with cloth adhesive tape. Further operatives will then
remove the sealed bags directly to the waste skip provided so as to maintain good
housekeeping standards and prevent damage to the bags etc.
ASSOCIATED RISK 76
ASSESSMENT No.’s
ASSOCIATED s.2 of the Health Safety at Work Act 1974
LEGISLATION PPE Regs 92
Work at Height Regs 2005
CDM2015
COSHH 2002
I have read this method statement specific to the work tasks which I am to carry out. I have brought to the attention of the
supervisor any areas of the method which I do not understand and have had them explained. I understand it is my duty to
ensure the safety of myself and others around me and will bring to the attention of the supervisor any unsafe work practices or
conditions which come to my attention. I will wear all necessary PPE/RPE.
NAME SIGNATURE DATE
HOT WORKS
NOTE: Post fire watcher internal to the structure wherever hot-cutting is required to prevent
risk of ignition
This method has been produced to control hot cutting activities on the project and should be
followed for all works which produce heat/sparks etc.
Prior to commencement:
Site Supervisors Duties:-
1) Carry out Burning & Welding Insurance Conditions Toolbox Talk;
2) Obtain Hot Work Permit – either our internal form 59 or Principal Contractors own
(whichever is applicable);
3) Carry out all preparatory safety inspections/works and position fire fighting equipment as
detailed on Toolbox Talk and Hot Work Permit and sign;
4) Where cutting of pipework/vessels is required ensure former contents are known and
where applicable purging of pipework is carried out by a competent contractor and
certificates issued;
5) Ensure guns, regulators, spark arrestors and pipes are fitted correctly;
6) Issue correct PPE/RPE;
7) Ensure operatives are competent and are aware of their required duties;
8) Erect internal exclusion zones as required.
Safe Working;
Operatives duties:-
9) Carry out full inspection of the work equipment and PPE and report any defects
immediately to the site supervisor;
10) Ensure hoses etc. do not pose a tripping hazard to others within the work area;
11) Check that all preparatory safety works as detailed in Item 2 above have been carried
out;
12) Don PPE/RPE;
13) Carry out the works in a safe and methodical manner;
14) Report any new findings immediately to the site supervisor;
Completion of Works;
Operatives duties:-
15) Dismantle and store equipment correctly;
16) Carry out inspection of the work area – report any findings to Site Supervisor;
ENVIRONMENTAL ISSUES
1 - Abandoned COSHH items throughout structures – Subcontractor to carry out a ‘sweep’ of all
structures as part of site set-up. Any items which are located are to be collected and placed
within a secure area for removal from site via a specialist contractor. Suitable PPE is to be worn
during all collection activities – this will include as a minimum – impervious gloves; safety visor;
overalls. Where manoeuvring onto pallets is required operatives will wear impervious gloves
and coveralls ensuring that, before movement, each drum is inspected and tops secure. Once
placed onto a pallet the drums will be wrapped and banded to make secure. The specialist
contractor will collect and remove to the licensed disposal point under Section 62 Hazardous
waste consignment note. A copy of this note will be provided to the site supervisor, as
producer of the waste, prior to leaving site.
Consignment notes for all waste removal off site are to be provided for evidence as part of the
SWMP;
2 - Spillage Control
Spill kits are to be placed at sensitive zones i.e. adj. bunded fuel tank and drip trays used for
any equipment/plant or COSHH items on site. All spillages are to be controlled following TRD’s
spillage procedure and any use of spill kits reported directly to the site supervisor for logging as
per ISO14001 internal requirements.
Works:
To be adopted where areas have determined the presence of hydro-carbon contamination –
either within the ground invesitgation report or to new areas discovered as floor slabs are
extracted.
Following excavation of highlighted areas contact with the clients representative Ian Price is
required to allow them to inspect the excavation prior to backfill therefore ensure that the
engineer is aware of the works programme to enable him to visit site and inspect.
Once all preparatory works are in place and the machine & lorry are within their designated
locations, works will commence with the careful extraction of contaminated soil from each
highlighted area. Care will be taken not to overfill the bucket attachment due to the risk of
transferral of contaminated matter outside of the working zone. Each bucket load will be lifted
and deposited directly within the lined body of the lorry or onto the impervious liner– this will
be repeated to designated depths as detailed by the client/report.
Once complete each excavation will be barriered off for safety until the Client/ engineer has
inspected and confirmed that it may be backfilled. Clean inert arisings generated from the
demolition works will be used as backfill back to surrounding levels.
4 - Bats
The Bat presence/absence survey has found no evidence of roosting bats, hence no further
survey or licence will be obtained. Measures will be taken to safguard bats as identified in the
Bat Method Statement (UES1386/02)
6– Hypodermic needle
Hypodermic needles and glue cans/bags may be contained within the site. A designated gang
will be assigned to carry out these works prior to commencement of any further activities within
the structure. Following completion of works a final inspection will be carried out by a
competent person.
NOTE #1: BE AWARE THAT IT IS A KNOWN FACT THAT NEEDLES CAN BE TAPED TO
BANISTERS, FURNITURE (WITHIN DRAWS AND TO BACKS) SO THAT WHEN YOU TOUCH/GO
TO MOVE THEM YOU GET STICK INJURIES AND TO TOPS OF DOORS SO THAT THEY FALL
WHEN YOU ENTER. IT HAS ALSO BEEN KNOWN THAT THEY ARE PLACED INTO SOFA
CUSHIONS/MATTRESSES AS WELL AS BEING WITHIN ABANDONED WASTE / BED LINEN ETC.
BE VERY AWARE – DO NOT TOUCH ITEMS WITH YOUR HANDS – USE LONG HANDLED
TOOLS UNTIL YOU ARE SATISFIED THAT THERE IS NO DANGER AND ALWAYS WEAR PPE,
EVEN WHERE YOU ARE SATISFIED THAT THE ITEM IS SAFE TO HANDLE;
NOTE #2: ENSURE THAT CORRECT PPE IS WORN AT ALL TIMES. DO NOT TUCK YOUR
TROUSERS INTO YOUR BOOTS, WEAR THEM OVER TO PREVENT RISK OF ENTRY BY NEEDLES;
Works:
All operatives will be made aware of the above facts during specific on-site induction/toolbox
talk and instructed in the need to maintain vigilance and adopt caution when handling
abandoned waste.
The operatives will then systematically go through each area of the structure (including external
landings/stores/garages etc.) moving abandoned waste/bedding, furniture etc. to inspect same.
All hypodermic needles will be picked up via the ‘litter picking’ equipment – pick up by the blunt
end (or the syringe if still attached) and placed directly into a Sharp Bin as provided to each
operative. All bags/cans etc. will be picked up, again using the ‘litter picking’ equipment as
before.
At the end of shift all contaminated material packaging will be suitably sealed and placed within
a secure area as instructed by the Site supervisor. All full sharp bins will be returned to the
local drug rehabilitation office / local authority or via Wards (as appropriate – liaise with
environmental manager) for disposal by incineration.
1 – If a cut or puncture wound is received encourage free bleeding immediately. This is done
by squeezing the area around the wound to force out a flow of blood;
2- wash the area;
3 – report immediately to your site supervisor who will ensure that you attend the A&E dept of
the local hospital
4 – Any injury of this type MUST be recorded in the site accident book;
5 – the safety officer is to be informed immediately
• First task will be to identify all drain runs on the site – Foul & Surface Water;
• Carry out site survey to identify location/condition of all man-holes;
• Open up each manhole and check the direction of flow – mark on site drawing;
• For those manholes located adjacent to the site boundary/ feeding retained areas –
insert temporary plug at drain outlet;
• Following commencement of demolition works on site each drain run will be severed at
the site of the manhole;
• A permanent cement mortar plug will then be forced within each manhole, consisting of
a 3 to 1 mortar mix.
• Each sealed manhole will be clearly marked on the site plan for inclusion in the site
safety file;
• Operatives gaining access to any manhole shall be trained in the correct entry / rescue
procedures for confined spaces and be supervised at all times – a permit to enter system
will be in operation;
In protection of water course, due attention will be paid to the “Pollution Prevention Guidelines”
published by the Environment Agency. PPG5 (Works near or liable to affect water courses) and
PPG6 Working at Construction and Demolition Sites are especially relevant.
It is considered that the ground materials to be encountered will be sufficiently coherent not to
pose a significant dust generation hazard. In the event of dust becoming a problem, suitable
damping down will be carried out to contain the hazard.
However, adjacent sites are operational and there are public access routes immediately
adjacent all site elevations. Measures will be taken to protect such off site personnel against
hazards associated with the works.
I have read this method statement specific to the work tasks which I am to carry out. I have brought to the attention of the
supervisor any areas of the method which I do not understand and have had them explained. I understand it is my duty to
ensure the safety of myself and others around me and will bring to the attention of the supervisor any unsafe work practices or
conditions which come to my attention. I will wear all necessary PPE/RPE.
NAME SIGNATURE DATE
The following are all items identified as containing asbestos from the survey
NOTE: First task will be to designate the work team and carry out a Tool Box talk detailing the
work task involved and the risk of working with asbestos containing materials. HSE guidance
leaflet ‘Asbestos & You’ will be issued.
All work equipment will be inspected by the user and any defects reported directly to the site
supervisor. The site form relating to work equipment will be completed.
An exclusion zone will be erected around the area – hazard tape and warning notices will be
positioned to all access/egress points to prevent access by unauthorised personnel.
Fire fighting equipment will be positioned as per the site fire plan.
The supervisor will carry out a final inspection of the area with the appointed gang and
highlight hazards and controls via toolbox talk training – a record of this will be kept.
The asbestos areas will be classed as a mandatory respiratory protection zone for the duration
of the work tasks and addressed by the issue of appropriate PPE.
WASTE REMOVAL:
All asbestos waste sacks will be wiped down, swan-neck tied, and double bagged.
All bagged/sealed waste will be transportation to the lockable asbestos skip. Once the skip is
full it will be disposed of at a licensed waste disposal point under a Section 62 consignment
note.
The spillage will be immediately sprayed with water a further bag will be obtained and all
materials placed directly into the bag employing a shovel. The split bag will also be placed into
this replacement bag and the bag swan neck tied to contain.
INDIVIDUAL DECONTAMINATION:-
As per HSE guidance – Asbestos Essentials – Personal Decontamination as found within your
site file.
NOTE:
Asbestos Fibres can cause lung cancer & lung diseases;
You must be trained to work safely with asbestos materials;
You must be trained to use PPE & RPE properly;
Remove your face mask last;
You need to decontaminate yourself properly, otherwise you could take asbestos fibres home
on your clothing and expose your family and friends;
Procedure:
• Clean your boots with a damp rag – soak the rag (cotton but those that do not shed fluff or
impregnated rags (eg ‘Tak’ rags)) in water; fold in half or quarters; wring it out; wipe your
boots; refold the rag to give a clean surface; repeat until you have used all of the clean
surfaces of the rag; put the used rag in the asbestos waste sack; if required use another rag
as before; REMEMBER – do not re-soak the same rag as this will create contaminated water.
Kier Issue 03 Dated 14.10.2015 Job No. N2038
Flying High Academy, Townroe Drive, Mansfield
39
• Where available, clean your overalls with a brush attachment on a Type ‘H’ vacuum and
once complete vacuum off the brush head;
• Otherwise, use damp rags by a ‘patting’ action. Remember rubbing can disturb fibres;
• Always work in pairs – one person decontaminating the other;
• Peel off disposable coveralls making sure they go inside out and place them immediately in
an asbestos waste sack;
• Finally remove your face mask and place immediately in an asbestos waste sack;
Personal decontamination:-
• Can you use the site washing facilities? If so they must be for your use only;
• Keep other people out during personal decontamination and until you have cleaned down
the facilities;
• Wash every time you leave the work area
• Use damp rags to clean down the washing facilities at the end of the task;
• Clean the facilities daily if the work lasts more than one day;
• Inspect the facilities visually once the work has finished;
• Clearance sampling is not normally required for washing facilities;
• All works will be carried out in a methodical manner working in from a designated point.
• All works will be carried out in line with
o HSE ‘Working with Asbestos Cement’ booklet HSG189/2;
o Asbestos Essentials A14 – Removing asbestos cement sheets;
o Asbestos Essentials EM5 – wetting asbestos materials
o Asbestos Essentials EM8 – Personal Decontamination
TBC
EQUIPMENT/MATERIALS
Floor Tile Scrapers
Hand Tools
Hand Held spray unit
Wetting Agent
Asbestos Waste Sacks
Assessment: The work consists of the removal of an asbestos based product known to contain
chrysotile asbestos. The floor tiles are thermoplastic therefore it is anticipated that the control
Kier Issue 03 Dated 14.10.2015 Job No. N2038
Flying High Academy, Townroe Drive, Mansfield
40
limit will not be exceeded. For this reason FFP3 half-face respirators will be used along with
disposable coveralls. In some areas the tiles are non-asbestos but the bitumen adhesive
contains Chrysotile asbestos.
Work Method: Access will be restricted to operatives involved in the work by means of warning
tape and notices. Having donned their correct PPE/RPE the operatives will commence with the
stripping operations.
Utilising the tile scrapers the operatives will carry out lifting of the tiles whilst a further
operative carries out localised spray of wetting agent to the disturbed area to contain any fibre
release. The lifted tiles will, where identified as containing asbestos, then be bagged and swan-
neck tied with cloth adhesive tape before being removed to the designated special waste skip.
Hand tools will be utilised to scrape up the fixing glue residue or specialist environmental
solvent type liquid applied to dissolve the adhesive. This residue will be placed into asbestos
waste sacks for disposal. Each sack will be swan neck tied to seal and double bagged and
sealed once more with cloth adhesive tape before transportation off site under Section 62
hazardous waste consignment note.
TBC
First task will be release the sink from it’s surroundings. Once released the unit will be turned
over for easier access and the base pad sprayed with a PVA solution. Employing a hand-held
scraper the pad will be removed, including any residue to a clean finish and all materials placed
immediately into an asbestos waste sack. The area will be cleaned down finally with a damp
cloth which will also be placed within the asbestos waste sack. Once all works are completed
the sack will be swan neck tied with cloth adhesive tape to seal.
TBC
Care will be taken not to over-wet the sheeting as this will create contaminated waste water.
Care will be taken not to overfill the asbestos waste sack to prevent splitting/spillage etc. Once
suitably filled the sack will be swan-neck tied with cloth adhesive tape and removed from site
under Section 62 consignment notice.
TBC
HAS THE ITEM BEEN TESTED TO PROVE THAT IT IS DEAD!!! IF UNSURE ASK YOUR
SUPERVISOR
Operatives to post warning signs at all approach points to alert others of the works and don
their correct PPE/RPE. A bucket of water and hand held spray will be positioned immediately
adjacent the work area to wash down following the works.
The cable to the fuse box will be severed using a cable cutter. The complete unit will then be
removed from it’s fixing by either unbolting or fixing and placed immediately into an asbestos
waste sack. All asbestos waste sacks will be wiped down, swan-neck tied, and double bagged.
Where the item is noted as loose only the flash-pad will be removed following damping down of
the item to contain fibre release. Again this will be bagged as before.
Following removal all surfaces will be cleaned down with a damp cloth / tac-rag. All PPE/RPE/
cleaning materials will be bagged and classed as contaminated waste also.
TBC
Access: Podium/Tower Scaffold (as appropriate) - work platform/open ends sealed with
1000gauge polythene and cloth adhesive tape
MEWP – Scissor Lift – work platform/open ends sealed with 1000gauge polythene
and cloth adhesive tape
All operatives engaged in these works will be issued with appropriate PPE/RPE – as described
above. A working at height assessment will be carried out and appropriate safe work platform
provided. Inspection of the ground on which the work platform is to be positioned is to be
carried out and any soft-ground either suitably compacted and dressed with hardcore/stone or
covered with suitable road plates (or similar) to provide a safe area.
Following removal of the windows (damping down procedures to be carried out during this
procedure) the cill will be sprayed with a low pressure application of wetting agent to contain
fibre release and carefully prised from it’s fixings using hand tools only. Each cill will be placed
immediately within an asbestos waste sack which, once at ground level, will be cleaned down,
sealed and removed to the contaminated waste skip.
TBC
All operatives engaged in these works will be issued with appropriate PPE/RPE – as described
above. A working at height assessment will be carried out and appropriate safe work platform
provided. Inspection of the ground on which the work platform is to be positioned is to be
carried out and any soft-ground either suitably compacted and dressed with hardcore/stone or
covered with suitable road plates (or similar) to provide a safe area.
Gable infill: Following removal of the roof tiles the exposed ‘gobbo’ will be removed and the
undercloak will be sprayed with a low pressure application of wetting agent to contain fibre
release and carefully prised from it’s fixings using hand tools only. Each strip will be placed
immediately within an asbestos waste sack which, once at ground level, will be cleaned down,
sealed and removed to the contaminated waste skip.
I have read this method statement specific to the work tasks which I am to carry out. I have brought to the attention of the
supervisor any areas of the method which I do not understand and have had them explained. I understand it is my duty to
ensure the safety of myself and others around me and will bring to the attention of the supervisor any unsafe work practices or
conditions which come to my attention. I will wear all necessary PPE/RPE.
NAME SIGNATURE DATE
DEMOLITION
Background info:
PREPARATORY WORKS:-
Careful inspection of each structure will be carried out by the site supervisor and the appointed
machine operator. All sensitive areas will be highlighted to the operatives and Toolbox talk
given to ensure the correct safety measures to be incorporated are known by all persons.
The site supervisor will make contact with all neighbouring representatives who will be affected
by the works to ensure they are aware.
During all works the surrounding area will be classed as an exclusion zone. Works will be
programmed so as not to coincide with peak-times.
Once the designated section of structure is ready for demolition and the site supervisor gives
the instruction, all operatives not involved with the works will position themselves at the
designated safety zone unless appointed as banksman whereby they will position themselves
within their designated view point.
On completion of all preparatory works i.e. hypodermic needle clearance / soft-strip and
asbestos removal operations demolition works will be carried out.
Works:
Mechanical:
The mechanical reduction works will be from top down with the demolition machine with PD19
attachment reaching in to its furthest point at the top level and staggering the cut lower down
Kier Issue 03 Dated 14.10.2015 Job No. N2038
Flying High Academy, Townroe Drive, Mansfield
45
to produce a natural run off of materials, so far as is reasonably practical. In this way
overloading of each floor level shall be reduced to its lowest expectation.
The reduction of the structure shall be progressive working a bay at a time. As each section is
demolished, the debris shall be pulled off to prevent any possibility of a build up of materials.
This reduction process shall be continuous in a progressive and systematic manner. During all
reduction operations, the machine operator, together with his supervisor, shall continuously
asses the integrity of each section of the structure being reduced at that time. Where any
ambiguity exists as to the continued integrity of any adjacent section the works are to
suspended and an action plan formulated to deal with any potential problem.
During all structural reduction operations, the operator of the demolition rig will leave sufficient
bracing to maintain stability allowing him to carefully reduce the building elements in a
piecemeal manner.
Throughout the duration of the works, all operatives shall be aware of and shall carry out any
instructions regarding the safety and integrity of the surrounding environment. Works
considered to have a significant impact on the environment shall not be implemented until such
time as suitable and sufficient control measures have been put into place to reduce such
impacts.
Noise and dust levels are to be kept to the lowest expectancy. Operations shall be carried out
using power fork or grapple where ever possible
All resultant arisings will be sorted and removed from the work area and all deleterious
materials loaded into either rollon/off containers or tipper transport for removal to a licensed
disposal point under Waste Management ‘Duty of Care’ procedures.
Completion Works:
Once at slab level and arisings removed an inspection will be carried out. The excavator will
initially break along predetermined lines employing concrete breaker then, to reduce noise
issues utilise the bucket attachment to lift the slab in sections – an assessment will then take
place to ascertain whether these slab sections can be loaded direct or further size reduction is
required. At no time will works be carried out which may affect the adjacent pavings etc.
Once removed the exposed footings will be grubbed up and once all arisings cleared the ground
will be made good – compacted and graded to existing paving levels with suitable topsoil.
Environmental Monitoring
This will be carried out throughout the duration of the works. When activities of a noisy nature
or with high vibration potential are being carried out, monitoring will be carried out in line with
BS:5228 Part 1 (Code of Practice for Noise and Vibration Control on Construction and Open
Sites), to ensure that this stays within the prescribed parameters. The site supervisor will carry
out continuous monitoring with regard to dust and other disturbances.
ASSOCIATED RISK 07; 11; 13; 14; 22; 33; 53; 70; 75; 80; 84; 85; 102; 105; 107; 110;
ASSESSMENT No.’s
ASSOCIATED Health & Safety at Work Act 1974
LEGISLATION WAH Regs 05
PUWER 98
PPE Regs 92
The Construction (Design & Management) Regs 07
The Control of Noise at Work Regulations 05
BS6187:2011
I have read this method statement specific to the work tasks which I am to carry out. I have brought to the attention of the
supervisor any areas of the method which I do not understand and have had them explained. I understand it is my duty to
ensure the safety of myself and others around me and will bring to the attention of the supervisor any unsafe work practices or
conditions which come to my attention. I will wear all necessary PPE/RPE.
NAME SIGNATURE DATE