Monthly Report 2017

Week I April 10-April 14

Week day Activity


Monday - Removal of shear wall 3 formwork
- Erection of girder continues…
Tuesday - Erection of formwork for the first floor slab
Wednesday - Same as Tuesday
Thursday - Fabrication & preparation of rebar for the floor beams
- Formwork erection for the slab continues…
Friday ==========Holiday=============

Week II April 17-April 21

Week day Activity


Monday ==========Holiday=============
Tuesday - Erection of Formwork for stair case & checking the alignment
Wednesday - Placing, arranging & bending rebar of the stair case
Thursday - The columns on axis 5c and 5e are highly damaged hence decided to be
set to do it again.
- Erection of formwork for shear wall 1
Friday - Chiseling continues…
- Fabrication of rebar for the floor beams

1
Monthly Report 2017

Week III April 23-April 27

Week day Activity


Monday - Concrete casting
i) Shear wall
ii) Stair case
Tuesday - Placing of rebar for floor beam including –ve bars
Wednesday - Placing of rebar continues…
- Chiseling continues….
Thursday - Chiseling continues….
- Removing the formwork of shear wall and stair case
Friday - Placing of rebar continues and hanging double stirrup

Week IV May 01-May 5

Week day Activity


Monday =============Holiday=================
Tuesday - Placing HBC on the floor
- Formwork erection for the columns on axis 5c &5e
Wednesday - Placing HCB continues…
- Filling of the columns
Thursday - Formwork erection for the curved solid slab part
- Placing the mesh for the solid slab part
Friday =============Holiday=================

2
Monthly Report 2017

Abstract
This monthly report briefly discusses about the second month of my stay on the internship
program. The contents of this report are much similar to the first report as my schedules are the
same on both site and office.

On the first week of my second month internship program, there was erection of formwork for
the first floor slab and also fabrication and preparation of rebar for the floor beams.

Fig 1 Formwork for the 1st floor slab

On the second week I was able to see the stair case work. i.e. Erection of formwork, placing,
arranging and bending of rebar. And also checking the alignment. On that week the two columns
on axis 5c & 5E were decided to be set to do it again due to the occurrence of high segregation.
And I was able to see the fabrication and preparation of rebar for the floor beams.

3
Monthly Report 2017

Fig 2 chiselling of column Fig 3 shear wall formwork

On the third week there was concrete casting of shear wall and stair case and placing of rebar for
the floor beams including negative bar and hanging double stirrup. Demolishing the columns was
very difficult hence it took them all weekdays on that week.

During the last week there were not many activities due to holidays. The activities were placing
HCB for the ribbed part and the rebar mesh for the solid slab.

Fig 4 placing the HCB

4