ZXSDR BS8700 Step by Step


Commissioning Guide

GSM Product Support Dept.


Wireless Network Service Center 

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 1/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

LEGAL INFORMATION

By accepting this certain document of ZTE CORPORATION you agree to the following terms. If you
do not agree to the following terms, please notice that you are not allowed to use this document.

Copyright © 2013 ZTE CORPORATION. Any rights not expressly granted herein are reserved. This
document contains proprietary information of ZTE CORPORATION. Any reproduction, transfer,
distribution, use or disclosure of this document or any portion of this document, in any form by any
means, without the prior written consent of ZTE CORPORATION is prohibited.

and are registered trademarks of ZTE CORPORATION. ZTE s company name, logo

and product names referenced herein are either trademarks or registered trademarks of ZTE
CORPORATION. Other product and company names mentioned herein may be trademarks or trade
names of their respective owners. Without the prior written consent of ZTE CORPORATION or the
third party owner thereof, anyone s access to this document should not be construed as granting, by

implication, estopped or otherwise, any license or right to use any marks appearing in the document.

The design of this product complies with requirements of environmental protection and personal
security. This product shall be stored, used or discarded in accordance with product manual,
relevant contract or laws and regulations in relevant country (countries).

This document is provided “ as is and as available . Information contained in this document is


” “ ”

subject to continuous update without further notice due to improvement and update of ZTE
CORPORATION s products and technologies.

ZTE CORPORATION

Address: NO. 55
Hi-tech Road South
ShenZhen

P.R.China
518057
Website: http://support.zte.com.cn
Email: doc@zte.com.cn

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. I

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 2/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

Revision History

Product Version Document Version Serial Number Reason for Revision


R1.0 First published

Author 

Date Document Version Prepared by Reviewed by Approved by


2010-5-7 R1.0 Bai Guowei Cai Kai

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. II

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 3/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

About This Document

 Applicable to: ZXSDR BS8700 BTS

Intended for: Supervisor, commissioning engineer 

This document aims to guide the commissioning task of site engineer after the
completion of BS8700 installation and acceptance test. For detailed information of 
installation procedure and installation check, please refer to the related documents.

Summary
Chapter Description
1  Overview Commissioning flow, manpower projection and skills
required
2  Product Introduction Introduction about BBU and RRU
3  Preparations Before Onsite Prerequisites, tools and documents required for 
Operation commissioning
4  Commissioning Checking hardware, cables, power-on/power-off and
running status of BTS
5  BTS Test CS service test, PS service test, handover test, filling of 
test report
6  Site Cleaning Items to be cleaned on site
Error: Reference source not found 
 Appendix
Error: Reference source not found

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. III

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 4/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

TABLE OF CONTENTS

1 Overview 1
1.1 Introduction...................................................................................................................1
1.2 BTS Commissioning Flowchart..................................................................................... 1
1.3 Manpower Projection....................................................................................................1
1.4 Required Skills.............................................................................................................. 2

2 Product Introduction..................................................................................................... 2
2.1 BBU (B8200) ................................................................................................................ 2
2.2 BBU Boards (B8200) .................................................................................................... 3
2.3
2.4 BBU
RRU External
(R8860) Cable Connection (B8200) .....................................................................4
............................................................................................................... 5

3 Preparations Before Onsite Operation......................................................................... 6


3.1 Checking Onsite Commissioning Conditions ................................................................6
3.2 Preparing Tools............................................................................................................. 6
3.3 Preparing Documents................................................................................................... 7

4 Commissioning..............................................................................................................7
4.1 Checking Hardware....................................................................................................... 7
4.1.1 Checking Configuration and Model of BBU and RRU........................................... 7
4.1.2 Checking SA Jumpers.......................................................................................... 9
4.1.3 Checking Power Supply..................................................................................... 11
4.1.4 Checking BTS Transmission..............................................................................12
4.1.5 Checking Cable Connection...............................................................................14
4.1.6 Checking Power-on/Power-off of BTS................................................................15
4.1.7 Checking BTS Running Status...........................................................................17

5 BTS Test 18
5.1 Commissioning Test....................................................................................................18
5.1.1 CS Service Test................................................................................................. 18
5.1.2 PS Service Test.................................................................................................. 20
5.1.3 Handover Test.................................................................................................... 20
5.2 BTS Commissioning Test Report (Completed on Site)...............................................21

6 Site Cleaning................................................................................................................ 22

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. IV

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 5/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

FIGURES

Figure 1-1 BTS Commissioning Flowchart..................................................................... 1

Figure 2-2 ZXSDR B8200 GU360 Configuration...............................................................2

Figure 2-3 Appearance of R8860..................................................................................... 5

Figure 2-4 RRU interfaces................................................................................................6

Figure 4-5 Board Slot Configuration...............................................................................7

Figure 4-6 Factory Bar Code of CC Board...................................................................... 8

Figure 4-7 Position of the SA Jumper...........................................................................10

Figure 4-8 Cable Connection of BTS............................................................................. 15

TABLES

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. V

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 6/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

Table 1-1 Manpower Projection........................................................................................1

Table 2-2 ZXSDR B8200 Board List................................................................................. 3

Table 2-3 Description of B8200 External Cable Connection.......................................... 4

Table 4-4 Checklist of BBU and RRU Product Configurations and Models.................8

Table 4-5 Setting of X5 Jumper [1, 0] ..............................................................................9

Table 4-6 Setting of X5 Jumper [3, 2].............................................................................. 9

Table 4-7 Setting of X6 jumpers..................................................................................... 11

Table 4-8 Checklist of Input Power Supply................................................................... 12

Table 4-9 BTS Transmission Checklist.........................................................................12

Table 4-10 75Ω E1 Cable Sequence ...............................................................................13

Table 4-11 120Ω E1 Cable and 120Ω T1 Cable Sequences..........................................13

Table 4-12 Cable Connection Checklist........................................................................14

Table 4-13 Description of B8200 Board Status in Normal Working Status................17

Table 5-14 BTS Commissioning Test Report................................................................21

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. VI

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 7/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

1 Overview

1.1 Introduction
This guide focuses on the commissioning of ZXSDR BS8700, including SDR
commissioning flow and procedure.

Please conduct commissioning according to this guide after equipment installation


and check. For equipment installation information, please refer to the following
documents.

 ZXSDR BS8700 (V4.00.30) Hardware Installation Guide (BBU)

 ZXSDR BS8700 (V4.00.30) Hardware Installation Guide (RRU)

 ZXSDR BS8700 (V4.00.30) Hardware Description

1.2 BTS Commissioning Flowchart

Figure 1-1 BTS Commissioning Flowchart

1.3 Manpower Projection

Table 1-1 Manpower Projection

Position Responsibilities
BTS Prepare and check BTS commissioning, and assist the
commissionin iBSC&RNC commissioning engineer in finishing BTS
g engineer  commissioning.

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 1

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 8/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

Position Responsibilities
Supervisor Be responsible for the whole process of commissioning
iBSC&RNC
commissionin Perform data
trace BTS synchronization
related signaling in between BTS
the course and OMCR,
of BTS and
commissioning.
g engineer 

1.4 Required Skills


The person responsible for BS8700 commissioning should know about the following
knowledge:

 ZXSDR BS8700 products (boards, cables and system infrastructure), as well as


installation and checking modes.

 Types, sequences and connection methods of SDR transmission cables.

 Basic (speech and data) commissioning skills of SDR.

2 Product Introduction
ZXSDR BS8700 is of distributed structure, which includes baseband unit (BBU) and
remote radio unit (RRU).

2.1 BBU (B8200)


ZXSDR B8200 GU360 is also named indoor GSM/UMTS dual-mode baseband pool.

Figure 2-2 ZXSDR B8200 GU360 Configuration

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 2

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 9/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

2.2 BBU Boards (B8200)

Table 2-2 ZXSDR B8200 Board List


Abbreviation Full name Description
It provides power to the other boards.
PM0 Power Module One module is configured by default;
“1+1” backup configuration is optional.
This board integrates the functions of 
environment monitoring and E1
interface, providing 6 incoming and 2
SA Site Alarm Module outgoing lines of dry contact monitoring
and 8 lines of E1/T1 interfaces. Besides,
it provides one line of RS232 and one
line of RS485.
Its functions include switching of media
stream and control stream, processing
clocks and managing subracks.
The panel provides GE interface
(optional for optical and electrical) for 
Control and Clock
CC0/CC1 transmission over Iub, and it also
Module
provides antenna interface. Only one
module is configured by default. “1+1”
backup configuration is optional. The
REF interface supports import of BITS
signal source.

This board focuses on IQ signal


switching. Each supports 6 fiber 
Fabric Switch
FS interfaces to connect with the RRU
Module
module. Two FSs at the maximum in
loading sharing mode can be configured.

Baseband
BPC Processing Board Baseband board for WCDMA
Type C

GSM Baseband UBPG is the baseband board of GSM.


UBPG
Processor  One UBPG supports 12 TRXs.

It is on the right side of the subrack,,


FA FAN Module
which is used for heat dissipation.

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 3

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 10/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

2.3 BBU External Cable Connection (B8200)

Table 2-3 Description of B8200 External Cable Connection


B8200 External Cable Connection
Cable Media/ Local end Peer end
No Usage
name type connected to connected to
GPS REF port on
It receives GPS GPS lightning
1 antenna the CC board
signals arrester 
cable of B8200
Blue
Power 
B8200 and
B8200 power  interface on -48V DC power 
2 power  black
cable the PM board supply
cable power 
cables of B8200
DB44 E1 cable stud
It connects E1
connector  out of the DDF
It connects External
DB9
SA panel RS232/RS485 commissioning
3 connector 
cable serial port cable device
It connects
DB25 Parts to be
external alarm
connector  monitored
cable
E1 interface
2M
Iub/Abis on the SA
4 interface coaxial Iub/Abis interface board of  iBSC/RNC
cable
B8200
It connects the
Ethernet
interface
between BBU
Iub/Abis RJ45 and iBSC/RNC. ETH0
interface supper  This interface interface on
and GE categor  provides optical the CC board The IP network
5
electrical y 5/6 interface and of B8200 of iBSC/RNC
port twisted- electrical (electrical
cables pair  interface of the port)
Ethernet on the
panel
(10M/100M/1000
M self-adaptive)
The IP network
Iub/Abis It connects Optical port connecting to
interface optical port on the CC RNC/Abis (not
6 Fiber 
optical between BBU board of  in use because
port and iBSC/RNC B8200 of technical
limitations)

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 4

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 11/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

B8200 External Cable Connection


Cable Media/ Local end Peer end
No Usage
name type connected to connected to

CPRI Single- It connects BBU Optical port


and RRU to on the FS CPRI interface
7 interface mode
transmit IQ board of  on the RRU
cable fiber 
signals B8200
RMB
RRU interfac
It connects RRU Monitor 
commiss e cable
8 for  interface on RMB board
ioning and
commissioning the RRU
cable interfac
e board
 Antenna
RRU 7/8''
9 antenna feeder  Feeder  interface
the RRU on Cell antenna

EXT external
EXT interface
telecommunicatio
on the CC
10 n interface,
board of 
connecting
B8200
external receiver;

2.4 RRU (R8860)


R8860 is an outdoor macro remote radio unit (RRU).

Figure 2-3 Appearance of R8860

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 5

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 12/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

Figure 2-4 RRU interfaces

1. (LC1) Interface between BBU and RRU/RRU cascading interface


2. (LC2) Interface between BBU and RRU/RRU cascading interface
3. (AISG) AISG equipment interface
4. (Mon) Interfaces for external devices (such as monitoring, LMT, etc.)
5. (DCIN) Power interface
6. Interface for Rx diversity RF cable
7. (Interface for RX/TX) Main RF cable
8. (RXout) Frequency extension interface
9. (Rxin) Frequency extension interface
10. (GND) Grounding

3 Preparations Before Onsite Operation

3.1 Checking Onsite Commissioning Conditions

Please refer to the following steps to see if the site is available for commissioning:
 Make sure the equipment has been installed properly on site, and items in
installation acceptance test have been passed;

 Find out the transmission type of the BTS;

 Check whether transmission and power supply are ready for commissioning;

 You need to get the confirmation of the project manager upon the completion of the
above three steps.

3.2 Preparing Tools


  A laptop;

 (Both cross and flathead) screwdrivers, wrenches, multi-meter, and other 


commonly used tools;

 Two testing handsets supporting the services to be tested and related data cables;

 The SIM cards supporting the services to be tested.

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 6

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 13/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

3.3 Preparing Documents


You can find all of the following documents on TSM website (log on to

ecc.zte.com.cn and then click Technical Support), or ask the engineers in the local
office for the documents.

ZXSDR B8200&R8860 Commissioning Test Record 

ZXSDR B8200&B8860 Test Guide

4 Commissioning

4.1 Checking Hardware

4.1.1 Checking Configuration and Model of BBU and RRU

Purpose

 Check the configuration and model of the BTS to be commissioned to ensure it is


consistent with what is planned.

 Record the factory bar code of the PCB on CC board, and send it to iBSC&RNC
commissioning engineer for data synchronization.

Procedure (BBU)

1. Check the following items according to the Figure 4 -5:

1. Check whether the site has been configured with boards as planned;

2. Check whether the boards are all in correct slots;

Figure 4-5 Board Slot Configuration

2. The BTS commissioning engineer records the factory bar code on the PCB of CC1

board as shown in Figure 4 -6, and sends it to the RNC&iBSC commissioning

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 7

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 14/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

engineer for data synchronization.

Figure 4-6 Factory Bar Code of CC Board

Procedure (RRU)

1. Check the nameplate on the left of RRU to see whether it is consistent with what is
planned;

2. Check the nameplate on the left of RRU to see whether its power and frequency
range are consistent with what is planned;

Criteria

Table 4-4 Checklist of BBU and RRU Product Configurations and Models

Item Contents Result Remarks


Whether the site has been
configured with boards as □Yes □No
planned
Check BBU and Whether the boards are in correct
□Yes □No
RRU product slots
configurations Whether RRU product models are
and models □Yes □No
consistent with what is planned
Whether RRU product power and
frequency range are consistent □Yes □No
with what is planned

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 8

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 15/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

4.1.2 Checking SA Jumpers

Purpose

Check transmission type and networking type on site:

 Check transmission mode of Iub/Abis interface circuit (X1, X5)

 Check cabinet No. in the case of BBU cascading (X6)

Procedure

1. Change the settings of X1 and X5 jumpers with jumper cap. Figure 4 -7 shows the
position of jumpers, and Table 4 -5 and Table 4 -6 show their functions. “Short circuit”
means that there is a jumper cap, and “Open circuit” means there is not.

1. Work modes of uplink/downlink links

2. Matching impedance

Table 4-5 Setting of X5 Jumper [1, 0]

X5 jumper position [1, 0] E1/T1 mode


[short circuit, short circuit] Reserved
[short circuit, open circuit] T1, 100Ω

[open circuit, short circuit] E1, 120Ω


close (open
to the circuit,
jumper and
at the the SA
panel, as board
shownisin 
Figure 4 -7
[open circuit, open circuit] E1, 75Ω (default value)

3. E1/T1, and combination of long cable (more than 1000 meters) and short
cable (less than 1000 meters)

Table 4-6 Setting of X5 Jumper [3, 2]

X5 jumper position [3, 2] Mode


[open circuit, open circuit] uplink short, downlink short
[short circuit, short circuit] uplink long, downlink long
[open circuit, short circuit] uplink short, downlink long
[short circuit, open circuit] uplink long, downlink short

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 9

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 16/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

Figure 4-7 Position of the SA Jumper 

Reference

 Uplink represents the transmission from BBU to iBSC/RNC, and downlink


represents the reverse;

 Long/short cable refers to the receiving mode of E1. Use the long cable if E1
transmission distance is longer than 1km, and use the short if otherwise.

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 10

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 17/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

2. Change the setting of X6 jumper with the jumper cap in the case of BBU cascading.
 At most 8 sets of BBU (from 000 to 111, as shown in Table 4 -7) can be cascaded.
The default value is “000”.

Table 4-7 Setting of X6 jumpers

Position of X6 jumper [2,1,0] BBU cabinet No.


[open circuit, open circuit, open circuit] 0
[open circuit, open circuit, short circuit] 1
[open circuit, short circuit, open circuit] 2
[open circuit, short circuit, short circuit] 3
[short circuit, open circuit, open circuit] 4
[short circuit, open circuit, short circuit] 5
[short circuit, short circuit, open circuit] 6
[short circuit, short circuit, short circuit] 7

4.1.3 Checking Power Supply

Purpose

To ensure the power supply of the BTS is normal for subsequent commissioning.

Procedure

1. Wear the anti-statistic wrist;

2. Check the cable tag, and check the polarity of BBU and RRU input power;

3. Measure input voltage of BBU and RRU with the multi-meter:

1. Normal range of DC power supply: -40V DC to -57V DC;

2. Normal range of AC power supply: 200V AC to 240V AC,

Note:

BBU only supports DC power supply, so it is necessary to use PSU module for AC-
DC conversion in the case of AC power supply.

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 11

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 18/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

Criteria

Table 4-8 Checklist of Input Power Supply

Item Content and criteria Result Remarks


Whether the polarities of the BBU’s and
Check □Yes □No
RRU’s power supply are correct
power 
supply Whether input voltage of BBU and RRU is
□Yes □No
normal

4.1.4 Checking BTS Transmission

Purpose

To ensure the BTS transmission is normal for commissioning.

Procedure

E1 cables:

1. Identify each pair of E1 cables by cable sequence and color spectrum shown in
Table 4 -10 and Table 4 -11;

2. Perform self-loop for each pair of E1 cables;

3. Contact BSC engineer to make sure if E1 /T1 transmission is normal.

FE cables:

1. Connect both RJ-45 connectors of the FE cable to the FE cable detector, and
check whether the FE cable is correctly made based on indicators on the FE cable.
If the 8 indicators flash in sequence, it shows the connection is correct.

Criteria

Table 4-9 BTS Transmission Checklist


Item Contents and criteria Result Remarks
Whether connection between E1 cable
BTS □Yes □No
and DDF rack is correct
transmissio
n Whether connection between FE cable
□Yes □No
and switch is correct

Reference

E1 cable description:

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 12

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 19/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

 75Ω E1 cable:

8 pairs of 75Ω E1 are often used in China. One end of it is the DB44 connector, and
the other end is divided into 2 cables (the connectors are made on site). Each of the
two has 8 cores (1-8), which support 4 pairs of E1. The labeled cables are the 1 st-4th
pairs of E1, while the unlabeled ones are the other 4 pairs. The E1 labeled with 1
and 2 are the first pair, those with 3 and 4 are the second pair, and so on. See the
following table for the cable sequence description.

Table 4-10 75Ω E1 Cable Sequence

Signal
RX0– RX0+ TX0– TX0+ RX1– RX1+ TX1– TX1+
definition
Pin at End
22 23 24 25 1 2 3 4
 A
1–1– 1–1– 1–2– 1–2– 1–3– 1–3– 1–4– 1–4–
Cable color 
extern intern extern intern extern intern extern intern
spectrum al al al al al al al al
Signal
RX4– RX4+ TX4– TX4+ RX5– RX5+ TX5– TX5+
definition
Pin at End
13 14 43 44 39 40 41 42
 A
2–1– 2–1– 2–2– 2–2– 2–3– 2–3– 2–4– 2–4–
Cable color 
extern intern extern intern extern intern extern intern
spectrum al al al al al al al al

“1–1–internal”, “1–1–external” represents the internal or external conductor of the


coaxial cable identified with “1”.

 120Ω E1 cable and 100Ω T1 cable

120Ω E1 and 100Ω T1 are divided into 4 pairs of E1/T1 and 8 pairs of E1/T1. One
end of it is the DB44 connector, and each cable has 16 cores (1-16), which supports
4 pairs of E1/T1, the labeled ones are the 1 st-4th pairs of E1, and the unlabeled ones
are the 5th-8th E1/T1. See the following table for cable sequence.

Table 4-11 120Ω E1 Cable and 120Ω T1 Cable Sequences

Signal TX0
RX0– RX0+ TX0+ RX1– RX1+ TX1– TX1+
definition  –
Pin at End A 22 23 24 25 1 2 3 4
Cable color  blue/1 blue/1b pink/ pink/1 green green/ yellow yellow/
spectrum red lack 1red black /1red 1black /1red 1black
Signal TX4
RX4– RX4+ TX4+ RX5– RX5+ TX5– TX5+
definition  –
Pin at End A 13 14 43 44 39 40 41 42
Cable color  yellow yellow/ gray/ gray/2 blue/3 blue/3b pink/3 pink/3bl

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 13

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 20/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

Signal TX0
RX0– RX0+ TX0+ RX1– RX1+ TX1– TX1+
definition  –
spectrum /2red 2black 2red black red lack red ack

“Blue/1 red” means that there is 1 red flag on the blue cable; “pink /2 red” means
there are 2 red flags on the pink cable.

4.1.5 Checking Cable Connection

Items

Table 4-12 Cable Connection Checklist

Item Description Result Remarks


Check
cable Whether the fiber between the FS board
connectio and RRU is correct, or whether the SFP □Yes □No
n of the high speech cable connection is correct.
rack
If the FE cable is used, check whether its
Check connection from the switch to the CC □Yes □No
Iub/Abis board is correct.
interface
connectio If the E1 cable is used, check whether its
n connection from the DDF rack to the SA □Yes □No
cable of BTS is correct.
Check Whether the cables of dry contacts, the
other  Serial Ports 232 and 485 are connected □Yes □No
cables correctly.

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 14

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 21/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

Figure 4-8 Cable Connection of BTS

4.1.6 Checking Power-on/Power-off of BTS

Purpose

To ensure BBU and RRU can work normally.

Procedure (BBU)

1. Power-on Procedure:

1. Plug out all of the boards of B8200 carefully, and keep the PM (power module)
in the slot.

2. After the BTS is powered on, check whether the “RUN” indicator of the PM
module is ON, and the “ALM” indicator is OFF.

3. Check whether the FAN module is running normally (the “PWR” indicator is
ON, and the “ALM” indicator is OFF. If the FAN module is in normal operation,
please insert the CC, BPC, UBPG, FS and SA one by one.

2. Power-off Procedure:

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 15

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 22/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

1. Shut down the power supply system directly.

Reference

 After the PM module or any board is just powered on, the “ALM” indicator flashes,
which shows the board has not been started. If the SA board is not inserted, the
“ALM” indicator on the FA panel will be ON. Hot plug-out/in of the power cables is
forbidden.

The handle bar on the left of a board has three gears, and that on the right is fixed.
Please gear the handle bar to the outmost before plugging out the board, and gear 
the handle bar to the inmost before plugging in the board.

To remove the fan subrack, firstly please push the lock-switch on the panel on the
right before plugging out the fan subrack.

Procedure (RRU)

1. Power-on Procedure:

1. Special power cables have been delivered together with the RRU to connect
with -48VDC power cabinet or AC power cabinet. Please ensure the power 
cables and PGND cables are correctly connected before using the fuse.

2. Power-off Procedure:

1. Shut down the power supply of RRU:

− When the RRU is installed indoors, switch off the RRU air-switch of the
 AC/DC power distribution box;

− When the RRU is installed outdoors, switch off the RRU air-switch of the
indoor/outdoor DC lightning protection box;

Note:

 After all of the above procedure, the BTS commissioning engineer should feed back
the BTS status to the iBSC&RNC commissioning engineer, who will then conduct
version upgrade and data synchronization accordingly. Follow-up operations are not
allowed until the iBSC&RNC commissioning engineer completes the job and sends
a notice.

Ensure that the iBSC&RNC has finished BTS version upgrade and data
synchronization before the subsequent procedures.

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 16

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 23/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

4.1.7 Checking BTS Running Status

Prerequisites

1. SDR version is completely loaded.

2. SDR data synchronization between foreground and background is completed.

3. SDR is reset and restarted normally.

Purpose

1. To make sure BTS hardware work normally.

2. To make sure the current versions in the BTS are correct.

3. To make sure SDR data synchronization between foreground and background is


completed.

Procedure (BBU)

1. After the BTS is reset and restarted, all of the boards can resume working normally
in 5 minutes.

2. Check the status of indicators on the boards according to Table 4 -13.

3. Contact the BSC engineer to check the running status of the current version.

4. Contact the BSC engineer to see whether the running status of BBU boards is
consistent with what the indicators show. Indicator in green means normal status.

Table 4-13 Description of B8200 Board Status in Normal Working Status

Board RUN Indicator (Green) ALM Indicator (Red)


FM Flashing at 1Hz OFF
SA Flashing at 1Hz OFF
CC Flashing at 1Hz OFF
FS Flashing at 1Hz OFF
UBPG Flashing at 1Hz OFF
FA module Flashing at 1Hz OFF

Reference

When the BTS is restarted and reset, “ALM” indicators of PM and the boards may
keep flashing for a while. It is a normal status because the boards have not been
started.

If the board indicators are in abnormal status, please contact the iBSC&RNC

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 17

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 24/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

commissioning engineer for help.

Procedure (RRU)

1. After the BTS is reset and restarted, RRU resumes working normally in 10 minutes;

2. Contact BSC engineer to see whether the RRU boards work normally in OMC.
Indicator in green means normal status.

Warning:

It is forbidden to open the front panel of RRU to see its running status.

5 BTS Test

5.1 Commissioning Test


Prerequisites

Before the test of each item, please notify BSC engineer to make sure the
equipment works normally and the configuration related to the test is completed.

Tools

 Two testing handsets (with frequency lock and forced handover functions);

 Two SIM cards;

 Data cables for testing handsets (to test PS service, optional)

 Test computer (to test PS service, optional)

5.1.1 CS Service Test

5.1.1.1 Dial Test of CS Service

Procedure

1. BSC engineer selects a cell for the test;

2. Lock the frequency of testing handsets at the BCCH frequency of the tested cell.

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 18

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 25/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

Note:

The commissioning engineers should know how to perform frequency lock.


Otherwise please refer to the guide of testing handsets or consult BSC engineer.

3. Local MS user (the calling party) initiates a call. The called party answers. The
calling party hangs up first.

4. Local MS user (the calling party) initiates a call. The called party answers. The
called party hangs up first.

5. The calling party initiates a call. Local MS user (the called party) answers. The
calling party hangs up first.

6. The calling party initiates a call. Local MS user (the called party) answers. The
called party hangs up first.

—End of procedures—

Acceptance Criteria

1. The calling party can hear ring-back tone.

2. The called party answers successfully.

3. Conversation is in good quality.

4. Both the calling party and the called party can hang up normally.

5.1.1.2 Dial Test for the Services in Channels

Procedure

1. Notify BSC engineer before the test.

2. After BSC engineer completes the settings for the test, lock the frequency of the
testing handset at BCCH frequency of the tested cell.

3. Perform dial test.

4. Notify BSC engineer to observe the status of reserved (unblocked) TS.

5. Repeat steps 1-4 to test the other TSs in the BTS.

—End of procedures—

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 19

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 26/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

Acceptance Criteria

 All TCHs of the BTS support CS service.

5.1.2 PS Service Test

Procedure

1. Set the IP address and gateway of the data server according to the parameters
provided by the operator.

Note:

The commissioning engineer should know how to set the IP address and gateway of 
data server. Otherwise please consult BSC engineer.

2. Input WAP address into the testing handset to log on to WAP website.

Note:

The commissioning engineers should have the skill of WAP browsing with testing
handset. Otherwise please consult BSC engineer.

3. Record WAP average login time and WAP login success rate.

4. Refresh WAP webpage on testing handset. Record WAP refresh success rate.

—End of procedures—

Acceptance Criteria

WAP login success rate is above 90%. Webpage can be logged in normally.

5.1.3 Handover Test

Procedure

1. Select a cell of the BTS and lock the frequency of the testing handset at BCCH
frequency of the cell.

2. Establish a call.

3. Observe the parameters of neighbor cells with testing handset to find anther cell in
the same BTS as the target cell. The received level of the target cell should be

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 20

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 27/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

above “ReLevMin”, and near or higher than the level of the frequency in the
conversation.

4. Set handover function of the testing handset to perform forced handover.

—End of procedures—

Acceptance Criteria

The testing handset can be handed over to the target cell while the conversation
remains normal.

5.2 BTS Commissioning Test Report (Completed on


Site)
Table 5-14 BTS Commissioning Test Report

Item Content Result Remark

Number of dial times:


Number of success times:
Number of failure times:
Number of poor-quality call
times:
Local MS user as £Yes
the calling party Service quality: £No
£Normal £Silence
£One-way audio £Cross
talk
£Echo £Background noise
£ Intermittent voice

Number of dial times:


Number of success times:
Number of failure times:
Number of poor-quality call
times:
Local MS user as Service quality: £Yes
the called party £No
£Normal £Silence
£One-way audio £Cross
talk
£Echo £Background noise
£ Intermittent voice
Number of dialed TSs:
£Yes
TS dial test Number of normal TSs:
£No
Number of abnormal TSs:

ZTE Confidential Proprietary © 2013 ZTE CORPORATION. All rights reserved. 21

http://slidepdf.com/reader/full/zxsdr-bs8700-step-by-step-commissioning-guide 28/29
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

ZXSDR BS8700 Step by Step Commissioning Guide

Item Content Result Remark

WAP average login time


WAP login success rate: £Yes
WAP test £No
WAP refresh success rate
Handover times: ______ 
£Yes
Handover test Success times: _______ 
£No
Failure times: ________ 

6 Site Cleaning
Clean the site upon the completion of BTS commissioning.

1. Clean up the useless stuffs in the equipment.

2. Check if the equipment door is closed and locked.