Warehouse 1

Safety Stock/units 120


Min Order qty/Units
Lead time/days 2
Lot size/units 300 Daily peri
On Hand Inventory/units 300 1 2 3 4
Gross requirements 180 240 200 220
DRP in transit receipts 300
Projected available 120 180 280 60
Net requirements 140 60
DRP planned order receipt 300
DRP planned order release 300 300 300

Warehouse 2
Safety Stock/units 250
Min Order qty/Units
Lead time/days 1
Lot size/units 600 Daily peri
On Hand Inventory/units 125 1 2 3 4
Gross requirements 400 450 420 410
DRP in transit receipts 600
Projected available 325 475 55 245
Net requirements 375 195 605
DRP planned order receipt 600 600
DRP planned order release 600 600 600

Warehouse 3
Safety Stock/units 1300
Min Order qty/Units
Lead time/days 2
Lot size/units 1300 Daily peri
On Hand Inventory/units 2100 1 2 3 4
Gross requirements 800 950 1000 1150
DRP in transit receipts 1000
Projected available 2300 1350 350 500
Net requirements 2100
DRP planned order receipt 1300
DRP planned order release 1300 1300 1300
Daily periods
5 6
220 210

140 230
280 190
300 300

Daily periods
5 6
440 400

405 5
445 245
600

Daily periods Central DC


5 6 Safety Stock/units
1220 890 Min Order qty/Units
Lead time/days
580 990 Lot size/units
2020 1610 On Hand Inventory/u
1300 1300 Gross requirements
DRP in transit receipts
Projected available
Net requirements
DRP planned order receipt
DRP planned order release
1000

3
1500 Daily periods
6000 1 2 3 4 5 6
900 1300 2200 2200
ansit receipts 1500
d available 5100 5300 3100 2400
irements 100
ned order receipt 1500
ned order release 1500