Ejercicio Examen DRP
Ejercicio Examen DRP
Warehouse 2
Safety Stock/units 250
Min Order qty/Units
Lead time/days 1
Lot size/units 600 Daily peri
On Hand Inventory/units 125 1 2 3 4
Gross requirements 400 450 420 410
DRP in transit receipts 600
Projected available 325 475 55 245
Net requirements 375 195 605
DRP planned order receipt 600 600
DRP planned order release 600 600 600
Warehouse 3
Safety Stock/units 1300
Min Order qty/Units
Lead time/days 2
Lot size/units 1300 Daily peri
On Hand Inventory/units 2100 1 2 3 4
Gross requirements 800 950 1000 1150
DRP in transit receipts 1000
Projected available 2300 1350 350 500
Net requirements 2100
DRP planned order receipt 1300
DRP planned order release 1300 1300 1300
Daily periods
5 6
220 210
140 230
280 190
300 300
Daily periods
5 6
440 400
405 5
445 245
600
3
1500 Daily periods
6000 1 2 3 4 5 6
900 1300 2200 2200
ansit receipts 1500
d available 5100 5300 3100 2400
irements 100
ned order receipt 1500
ned order release 1500