The document outlines activities during a set trip of a boiler and turbine system. It provides instructions to close valves, trip coal mills, adjust airflow, and monitor temperatures and pressures to safely cool down the boiler. It also lists steps to open bypass valves, extract steam, and monitor speeds to safely shut down the turbine and generator.
The document outlines activities during a set trip of a boiler and turbine system. It provides instructions to close valves, trip coal mills, adjust airflow, and monitor temperatures and pressures to safely cool down the boiler. It also lists steps to open bypass valves, extract steam, and monitor speeds to safely shut down the turbine and generator.
The document outlines activities during a set trip of a boiler and turbine system. It provides instructions to close valves, trip coal mills, adjust airflow, and monitor temperatures and pressures to safely cool down the boiler. It also lists steps to open bypass valves, extract steam, and monitor speeds to safely shut down the turbine and generator.
1) R/H AND S/H SPRAY VALVES TO BE CLOSED. BLOCK VALVE CLOSED.
2) ONE BFP SCOOP MINIMUM (UNLOAD) AND STOP. BY SECOND BFP MAINTEND DRUM LVLEL UPTO NORMAL. 3) ALL COAL MILL TRIPPED. 4) ESP FIELD MADE OFF. 5) IF SOOT BLOWER IN PROGRESS STOPPED AND ENSURE ALL SOOT BLOWER ARE IN OUT CONDITION. 6) FOR FURNACE COOLING: (a) CHECK TOTAL AIR FLOW. 7) FOR DRUM COOLING (b) CHECK THE DRUM METAL TOP AND BOTTOM TEMP. 8) ECONOMISER RECIRCULATION VALVE E20 OPEN. 9) CHECK :- (a) FURNACE PRESSURE. (b) ID/FD LOADING, ADJUST AIR FLOW. (c) GUNS AVAILABILITY (d) SCANNER FAN 10) IF SET SUDDEN TRIP AND COAL MILL TRIP AT A TIME THEN START COAL MILL FROM LOCAL, OPEN REJECT GATE TO REMOVE COAL POWDER. 11) WHILE COOLING THE BOILER, SECONDARY AIR DAMPER FULL OPEN 12) GUN AVAILABILITY: WATER TO BE REMOVE FROM AIR ATOMISING LINE AND STEAM ATOMISING LINE AND DRAIN OPEN 13) F.O PO; RECIRCULATION TEMP TO BE INCREASED UPTO 1100C. 14) AIR HEATER AIR MOTOR IN SERVICE AND APH ARE ROTATING.
TURBINE AND GENERATOR SIDE ACTIVITIES
1) GENERATOR CIRCUIT BREAKER OPENED. ALL THREE GENERATOR PHASE CURRENT
ARE ZERO. ENSURE SUPPLY CHANGE OVER FROM UAT TO STATION. 2) HP/LP BYPASS OPENED. ENSURE TURBINE SPEED IS IN DROPING AND ON BARRING. CHECK HOOD SPRAY OPEN. 3) HP AND LP HEATER EXTRACTION STEAM VALVE CLOSED LE VEL IS NORMAL. 4) GLAND STEAM COOLER LEVEL IS NORMAL. DEAERATOR LEVEL IS NORMAL. 5) AVAIALABILITY OF PRDS UPTO VACCUM BREAKING. IMMEDIATELY PRDS SPRAY VALVE CLOSED AND MAINTAIN THE PRDS TEMP. 6) ENSURE TURBINE AOP AUTO PICK UP. 7) IF BOILER TO BE HOT BANK THEN HPLP BYPASS TO BE CLOSED 8) AS-306 TO BE CLOSED TO MAINTAIN PRDS PRESSURE/DRUM PRESSURE. 9) GLAND STEAM SUPPLY MANUAL ISOLATING TO BE MADE OPEN TO CHARGE GLAND STEAM AFTER TRIPPING OTHERWISE VACCUM WILL BREAK.